Instructions related with PreNI & NI of kanpur

SL Work/Activity Supervisor McML/Seimens Officer Incharge


Incharge. Staff.

1 During NI Block working between CNB to GMC, Sh. V.K. Verma One wireman. DSTE/SW/CNB
CPBI, CPB will remain working from Old RRI panel for and Sh. Ajay
this separate Supply arrangement should be made in Sharma.
Old RRI for signal No. 10, 22 and 33 using a separate
transformer. This supply should be taken from AT
supply.

2 Free signal will be provided for all PF starters and Sh. V.K. Verma One wireman. DSTE/SW/CNB
home signal No.1, 11, 25, 48 & 58 for this also supply and Sh. Ajay
should be taken from AT supply using a separate Sharma. On duty
transformer with one Tx Standby. Cable already laid SI at Old RRI
from free signal board to MDF needs to be bell tested
and inserted on respective terminals in advance. As
soon as NI starts links of free signal are to be made
through.

3 For providing free signals on 8 Old signals (Sig. No1, Sh. P.S. Patil and One Fitter and SSTE/IRPMU/CNB.
20, 23, 48, 15, 51, 40, 49, 42) which are being Sh. J.N. Gupta. Two Wireman.
retained additional 2 aspect unit is to be provided on On duty SI at Old
elbow. Four conductors are to be tested from Old RRI RRI.
to these signals and same to be terminated on both
additional 2 asepct unit and MDF of Old RRI for these
signals free signal board case to be kept jointed with
signal cables so that when Tx is powered these
signals are lit immediately. 100% Testing should be
done for free signals in advance.

4 110VDC outdoor point supply to be disconnected from On duty SI at Old DSTE/SW/CNB


Old RRI as soon as NI starts by taking out fuses of RRI.
rectifier. This rectifier to be marked in advance. Two
hours before NI battery of 110VDC to be disconnected
so that point is working on rectifier only. .

5 All Patch cables to be removed from MDF of new RRI Sh. V.K. Mishra, SSTE/IRPMU/CNB.
as soon as NI starts excep cable for TPRs required to Sh. Bishram
keep Block working between CNB to GMC/CPBI/CPB Yadav, MDDF
working. Patch cable of L-xing No. 82, 83 also not to supervisors.
be removed. Terminal Numbers of all these TPRs to
be noted down and special tags to be provided on
patch cable at new RRI & old RRI.

6 During NI 60V internal supply and 60 V external On duty SI. DSTE/SW/CNB


supply are to be kept alive in Old RRI.
7 Details instruction sheet showing terminal numbers of Sh. Ram Saran DSTE/SW/CNB
NI working gears on MDF in Old RRI not to be
disturbed.
8 Cross marks to be provided on all new signals and all Sh. Prahlad and SSTE/IRPMU/CNB.
released signals during NI. For this McML should keep
30 Cross marks ready in advance.
9 All patch cables except these which are necessary to Sh. Bishram One wireman ASTE/IRPMU/CNB,
be removed from MDF panel in new RRI and links to Yadav & Sh. Gani each per zone. SSTE/IRPMU/CNB,
be connected as soon as NI starts. For this MDF panel Sh. Gauri
to be divided in 5 zones. Shankar.
10 110 V fuse of all point groups tobe kept disconnected MDF team. Seimens staff ASTE/IRPMU/CNB,
in advance in new RRI before NI. The fuse to be
inserted before testing of concerned points enroute to
be tested and same to be removed after testing.
Details of each point group and fuse numbers are to
be kept ready.
11 All cables of points being laid during Pre-Ni to be Sh. P.S. Patil and 2 wireman,2 DSTE/SW/CNB
tested before block and detailed planning to be made Sh. J.N. Gupta. helper
to complete the point work in assigned block
12 Testing of all gears on 3rd 4th & 5th line to be done Sh. V.K. Verma, ASTE/IRPMU/CNB,
from new RRI panel on 6 to 8th Septenmber during Sh. Ajay Sharma, ASTE/IRPMU/JHS,
surrendering of 3rd, 4th & 5th line. & outdoor SSTE/IRPMU/CNB,
supervisors. DSTE/SW/CNB.

13 Simulation panel at new RRI to be disconnected on Sh. V.K. Verma Siemens. ASTE/IRPMU/CNB
5/9/09. All indoor testing tobe completed before and Sh. Ajay
disconenction of simulation panel. Sharma.
14 Checking of lamps and glasses of all aspects of new Sh. Prahlad & DSTE/SW/CNB,
signals to be done in advance. Arrangement as Sh V.K. Jha ASTE/IRPMU/JHS.
discussed should be made to keep all aspects of new
signals closed during testing. For this necessary
material to be purchased from local market.

15 Testing of block working cable and block working Sh. Prahlad, 2 wireman SSTE/IRPMU/CNB.
circuit between CNB and 'C' panel on 3rd, 4th & 5th Sh. V.K. Verma,
line to be tested before 28/8/09. Sh. Rajesh Singh

16 Installation and testing of Earth leakage detector to be Sh. U.K. Awasthi Seimens to ASTE/IRPMU/CNB
completed before by 31/8/09. Liason
17 Installation wiring and testing of inverters in new RRI Sh. U.K. Awasthi Seimens to ASTE/IRPMU/CNB
to be compelted before 28/8/09. Liason
18 All power equipments including battery sets to be kept Sh. U.K. Awasthi ASTE/IRPMU/CNB
ready in all respect during NI.
19 Repairing of DG set in new RRI to be done before NI. Sh. V.K. Mishra ASTE/IRPMU/CNB

20 Wiring for power supply monitoring of East Cabin in Sh. Jaiswal, 1 carpenter & 1 SSTE/IRPMU/CNB
DATA logger of new RRI tobe completed by 26/8/09. wireman

21 Details of alteration to be made in outdoor TPRs for Sh. Prahlad DSTE/SW/CNB,


suiting Old RRI with insertion / dismantling of points in Sh. V.K. Mishra, ASTE/IRPMU/JHS
yard during Pre-NI to be prepared and same tobe Sh. V.K. Jha
mentioned in instructiion sheet of concerned zone in
during NI.
22 DATA logger software upgradation and charger Sh. Jaiswal, Seimens to ASTE/IRPMU/CNB
repairing to be completed by 31/8/09. Liason with
Efftronics
23 Providing AT supply for building lighting in new RRI Sh. U.K. Awasthi DSTE/SW/CNB.
building to be completed before NI. For this laisoning
with SEE/C to be done.

24 Date of all pending signal foundation to be finalised Sh. Prahlad 1 maison with 2 SSTE/IRPMU/CNB.
and arrangement like fast drying cement to be made helper, Sh.
well in advance so that targets can be met. Ranga Rao

25 All pending items in outdoor like Stop board, calling on Sh. Prahlad 2 fitter, Sh. SSTE/IRPMU/CNB
signal and route indicator etc. to be provided before Ranga Rao.
31/8/09.
26 Shifting of location boxes & signals which are coming Sh. Prahlad and SSTE/IRPMU/CNB.
under infringement to be planned and done in Sh. Rangarao
advance.
27 New tail cable connection for sig. 49& 51 and fixing of Sh. Prahlad and SSTE/IRPMU/CNB.
route on signal 15 and sig 26 to be completed by Sh. Rangarao
31/8/09
28 Writing , numbering of new signals as well as Location Sh. Prahlad 2 painter Sh. SSTE/IRPMU/CNB.
Box to be completed by 31/8/09. Ranga Rao.
29 Testing of TPRs for boundary change track circuits Sh. V.K. Jha and 2 wireman, Sh. SSTE/IRPMU/CNB.
and new track circuits to be compelted by 31/8/09.this Sh. Bishram Ranga Rao
includes providing new TLJBs where ever TLJB is Yadav.
damaged.
30 Super imposed wiring of point machines Sh. P.S. Patil and DSTE/SW/CNB
133a,151b,152a,b,121a,b,122a,b during pre NI. Sh. J.N. Gupta.

31 At the time of closure of NI all cross marks to be All Outdoor McML to ensure All Outdoor Officers.
removed from new signals and put on old signals. supervisors sufficent staff.
Sufficient man power to be deployed to reduce delay.

32 Shed Notice to be prepared with new OHE mast Sh. Ram Saran ASTE/IRPMU/CNB
numbers in advance.
33 All trains to be kept outside yard before clossure of NI Panel Siemens. Panel Officers.
and first train from each direction to be received only Supervisors.
after checking point correspondance from outdoor by
operating 2 times from the panel.

34 In Joint inspection of Goomtee, it is to insure that Sh. V.K. Mishra & DSTE/SW/CNB
230V supply and socket to be provided by Electric Sh. R K Shukla
Department for charging of Mobile phones. For this
additional chargers may be purchased. Two sockets
for VHF set charging also need to be provided.

35 Work on all boundry change track circuit to be All zone All zone Officers.
completed during First hours of NI. supervisors.
36 Joint signal sighting inspection to be done by SI, LI, TI Sh. V.K Mishra, SSTE/IRPMU/CNB.
before commissioning by going in the yard. Sh. Prahlad.
37 Keep Safety certificate signed in advance by XEN & ASTE/IRPMU/CNB.
SEE/CN/CNB. .
38 One gang of OHE, S&T and Engg. Each should be ASTE/IRPMU/CNB.
round the clock available at new RRI kanpur after
commissioning. This should be advised to Dy. CE/C
and Dy.CEE/C/ALD.
39 Magneto phone and PA system to be installed and Sh. R K Shukla, SSTE/IRPMU/CNB.
tested well in advance. DSTE/SW/CNB.
40 Attendance of staff during NI to be kept at new RRI. Sh Ramsharan
Staff should be given instruction to report Half an hour
in advance.
41 Sr. DEE/G to be advised to keep laison with for KESCO DSTE/SW/CNB.
commercial supply so that no power failure of local
supply happens during NI.
42 Changing height of Sig. 44. & testing it. This signal Sh. Prahlad DSTE/SW/CNB.
will be having 2 asepect only.
43 Keep sufficent amount of signal material like track Sh. P.S. Patil, SSTE/IRPMU/CNB.
feed charger,battery,resistance,lamps,TLJBs in spare Sh. Prahlad and
during NI. Sh. J.N. Gupta.
44 ASC/RPF Should be advised for Petroling on Ganga
Ghat site and visit Yard.

Any other activity leftover should be conveyed in advance by supervisors and officers in advance.

(NIRAJ YADAV )
DY.CSTE/Proj/IRPMU/CNB.

Copy to:-
1 All officer incharge for information & necessary action.
2 CSTE/IRPMU for kind informatioin please.
3 CAO/IRPMU for kind information pelase.
4 CSTE/NCR for kind inforamtion please.