Kontraktor :
PT. Trane Indonesia MASTER SCHEDULE PT. NUSAPRATAMA DWIKHARISMA PT. TRITUNGGAL LESTARI MAKMUR
Bulan
Nov 2018 Des 2018 Jan 2019 Feb 2019 Mar 2019 Apr 2019 Mei 2019
12-Nov 21-Nov 28-Nov 5-Des 12-Des 19-Des 26-Des 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 01-Mei 8-Mei
No Description Bobot
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
20-Nov 27-Nov 4-Des 11-Des 18-Des 25-Des 1-Jan 8-Jan 15-Jan 22-Jan 29-Jan 5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr 30-Apr 7-Mei 12-Mei
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26
I PRELIMINARIES 2.00% 0.06% 0.06% 0.06% 0.06% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08%
II Unit
Unit CHILLER 25.00% 12.5% 12.5%
- Instalasi Pipa Ruang Cooling Tower 7.00% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.8% 0.8%
- Instalasi Valve 6.00% 0.9% 0.9% 0.9% 0.9% 0.8% 0.8% 0.8%
RENCANA PROGRESS MINGGUAN (%) 100.00% 0.06% 0.06% 0.06% 0.06% 0.08% 0.08% 0.08% 0.08% 0.08% 4.98% 3.88% 8.88% 6.88% 5.78% 5.58% 14.58% 14.38% 15.68% 13.88% 1.38% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58%
RENCANA PROGRESS KOMULATIF (%) 0.06% 0.12% 0.18% 0.24% 0.32% 0.40% 0.48% 0.56% 0.64% 5.62% 9.50% 18.38% 25.26% 31.04% 36.62% 51.20% 65.58% 81.26% 95.14% 96.52% 97.10% 97.68% 98.26% 98.84% 99.42% 100.00%
Bandung, 08 Januari
2019 .............................
Diperiksa & di setujui : Diperiksa & di setujui : Diajukan Oleh :
Managemen Konstruksi Managemen Konstruksi Kontraktor
PT. TRITUNGGAL LESTARI PT. Nusapratama Dwikharisma PT. Trane Indonesia
MAKMUR
Bulan
Nov 2018 Des 2018 Jan 2019 Feb 2019 Mar 2019 Apr 2019 Mei 2019
12-Nov 21-Nov 28-Nov 5-Des 12-Des 19-Des 26-Des 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 01-Mei 8-Mei
No Description Diperiksa & di setujui
Bobot :
s/d s/d s/d s/d s/d s/d s/d s/d Diperiksa
s/d & dis/d
setujui :s/d s/d s/d s/d s/d s/d s/d s/d s/d s/dDiajukan
s/dOleh : s/d s/d s/d s/d s/d
Managemen Konstruksi Managemen Konstruksi 2-Apr Kontraktor
PT. TRITUNGGAL LESTARI 20-Nov 27-Nov 4-Des 11-Des 18-Des 25-Des 1-Jan 8-Jan 15-Jan 22-Jan 29-Jan
PT. Nusapratama Dwikharisma
5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar 19-Mar 26-Mar 9-Apr 16-Apr
PT. Trane Indonesia
23-Apr 30-Apr 7-Mei 12-Mei
MAKMUR W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26
Minggu Je : 11
Material Pipa lantai 2 (cooling tower) 9.4906 0.0000 0.0000 0.0000 0.0000 keterlembatan dalam pengiriman material / baru pipa Black steel Mempercepat kedatangan material 31-01-19 07-02-19
Minggu Je : 11
Bandung, 29 Januari
Ket: 2019 .............................
Bobot A : Pekerjaan tertunda (Shop drawing) Diajukan Oleh :
Kontraktor
Bobot B : Pekerjaan tertunda (Material On site)
PT. Son Duct Sejahtera
Bobot C : SI
Bobot D : Jumlah pekerja
Michael Stefanus
Project manager
KLARIFIKASI KETERLAMBATAN PROGRESS PERIODE
Kontraktor :
Nama Pekerjaan : PEMASANGAN CHILLER PLANT
PT. SON DUCT SEJAHTERA
Konraktor : PT. SON DUCT SEJAHTERA
Minggu Ke : 13
Material Pipa lantai 2 (cooling tower) 10.0000 0.0000 6.0000 -6.0000 -0.1179 -5.8821 Metrial belum di po / mesti berdasarkan gambar approval (belum mekauka proses pembuatan shop 06-02-19 12-02-19
mengajukan gambar) drawing / Mempercepat kedatangan
material
Material Valve Ruang Chiller 6.0000 0.0000 0.0000 0.0000 0.0000 PPM belum mengajukan Mempercepat proses penajan PPM 06-02-19 08-02-19
Material Valve lantai 2 (cooling tower) 3.0000 0.0000 2.0000 -2.0000 -2.0000 PPM belum mengajukan Mempercepat proses penajan PPM 06-02-19 08-02-19
Material PANEL 0.0000 0.0000 0.0000
Material KABEL - 0.0000 0.0000 0.0000 0.0000 PPM belum mengajukan Mempercepat proses penajan PPM 06-02-19 08-02-19
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 1.7038 3.6000 -1.8962 -1.8962 Porses pemindahan material memakan waktu cukup lama Akan mempercepat pekerjaan 06-02-19 s/d selesai
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 2.7000 -2.7000 -2.7000 Metrial belum di po / mesti berdasarkan gambar approval (belum Mempercepat kedatangan material 06-02-19 12-02-19
mengajukan gambar)
Minggu Ke : 13
Bandung, 06 Februari
Ket: 2019 .............................
Bobot A : Pekerjaan tertunda (Shop drawing) Diajukan Oleh :
Bobot B : Pekerjaan tertunda (Material On site) Kontraktor
PT. Son Duct Sejahtera
Bobot C : SI
Bobot D : Jumlah pekerja
Michael Stefanus
Project manager
Manajemen Konstruksi:
Pemilik Proyek:
Kontraktor : PT. NUSAPRATAMA DWIKHARISMA
PT. TRANE INDONESIA MASTER SCHEDULE (R-1) PT. TRITUNGGAL LESTARI MAKMUR
Bulan
Nov 2018 Des 2018 Jan 2019 Feb 2019 Mar 2019 Apr 2019 Mei 2019 Juni 2019
12-Nov 21-Nov 28-Nov 5-Des 12-Des 19-Des 26-Des 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 01-Mei 8-Mei 15-Mei 22-Mei 29-Mei 05-Juni 12-Juni 19-Juni
No Description Bobot
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
20-Nov 27-Nov 4-Des 11-Des 18-Des 25-Des 1-Jan 8-Jan 15-Jan 22-Jan 29-Jan 5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr 30-Apr 7-Mei 14-Mei 21-Mei 28-Mei 04-Juni 11-Juni 18-Juni 30-Juni
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32
I PRELIMINARIES 2.0000 1.0400 0.0000 0.0800 0.1600 0.0800 0.0000 0.0000 0.2400 0.0800 0.0800 0.0343 0.0343 0.0343 0.0343 0.0343 0.0343 0.0342
II Unit
Unit CHILLER 25.0000 12.5000 12.5000
RENCANA PROGRESS MINGGUAN (%) 100.0000 0.0600 0.0600 0.0600 0.0600 0.0800 0.0800 0.0800 0.0800 0.0800 4.9800 3.8800 8.8800 6.8800 5.7800 5.5800 14.5800 14.3800 15.7800 13.9800 1.1800 0.5800 0.5800 0.5800 0.5800 0.5800 0.5800
RENCANA PROGRESS KOMULATIF (%) 0.0600 0.1200 0.1800 0.2400 0.3200 0.4000 0.4800 0.5600 0.6400 5.6200 9.5000 18.3800 25.2600 31.0400 36.6200 51.2000 65.5800 81.3600 95.3400 96.5200 97.1000 97.6800 98.2600 98.8400 99.4200 100.0000
REV 0 AKTUAL PROGRESS MINGGUAN (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 17.3400 0.0000 0.1200 1.9600 7.5900 3.0500 2.7671 2.1900 0.0800
AKTUAL PROGRESS KOMULATIF (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 2.6000 17.2400 17.2400 17.3600 19.4200 27.0100 30.0600 32.8271 35.0171 36.1571
DEVIASI (%) -0.0600 -0.1200 -0.1800 -0.2400 -0.3200 -0.4000 -0.4800 -0.5600 -0.6400 -5.6200 -9.5000 -18.3800 -22.6600 -13.8000 -19.3800 -33.8400 -46.1600 -54.3500 -65.2800 -63.6929 -62.0829 -61.5229
RENCANA PROGRESS MINGGUAN (%) 100.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 17.3400 0.0000 0.1200 1.9600 7.5900 3.0500 2.7671 2.1900 0.0800 0.6400 14.0743 15.4243 2.8243 10.2243 13.7372 0.0000 0.0000 5.9443 2.0342
RENCANA PROGRESS KOMULATIF (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 17.3400 17.3400 17.4600 19.4200 27.0100 30.0600 32.8271 35.0171 35.0971 35.7371 49.8114 65.2357 68.0600 78.2843 92.0215 92.0215 92.0215 97.9658 100.0000
REV 1 AKTUAL PROGRESS MINGGUAN (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 17.3400 0.0000 0.1200 1.9600 7.5900 3.0500 2.7671 2.1900 0.0800 0.0000 0.0000 0.0000 0.0000
AKTUAL PROGRESS KOMULATIF (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 17.3400 17.3400 17.4600 19.4200 27.0100 30.0600 32.8271 35.0171 35.0971 0.0000 0.0000 0.0000 0.0000
DEVIASI (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bulan
Nov 2018 Des 2018 Jan 2019 Feb 2019 Mar 2019 Apr 2019 Mei 2019 Juni 2019
12-Nov 21-Nov 28-Nov 5-Des 12-Des 19-Des 26-Des 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 01-Mei 8-Mei 15-Mei 22-Mei 29-Mei 05-Juni 12-Juni 19-Juni
No Description Bobot
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
20-Nov 27-Nov 4-Des 11-Des 18-Des 25-Des 1-Jan 8-Jan 15-Jan 22-Jan 29-Jan 5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr 30-Apr 7-Mei 14-Mei 21-Mei 28-Mei 04-Juni 11-Juni 18-Juni 30-Juni
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32
I PRELIMINARIES 2.0000 0.0600 0.0600 0.0600 0.0600 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.2800 0.2800 0.5600 0.5600
II Unit
Unit CHILLER 25.0000 12.5000 12.5000 12.5000 12.5000
RENCANA PROGRESS MINGGUAN (%) 100.0000 0.0600 0.0600 0.0600 0.0600 0.0800 0.0800 0.0800 0.0800 0.0800 4.9800 3.8800 8.8800 6.8800 5.7800 5.5800 14.5800 14.3800 15.7800 13.9800 1.1800 0.5800 0.5800 0.5800 0.5800 0.5800 0.5800
RENCANA PROGRESS KOMULATIF (%) 0.0600 0.1200 0.1800 0.2400 0.3200 0.4000 0.4800 0.5600 0.6400 5.6200 9.5000 18.3800 25.2600 31.0400 36.6200 51.2000 65.5800 81.3600 95.3400 96.5200 97.1000 97.6800 98.2600 98.8400 99.4200 100.0000
REV 0 AKTUAL PROGRESS MINGGUAN (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 2.6000 14.6400 0.0000 0.1200 1.9600 7.5900 3.0500 2.7671 2.1900 1.1400
AKTUAL PROGRESS KOMULATIF (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 2.6000 17.2400 17.2400 17.3600 19.4200 27.0100 30.0600 32.8271 35.0171 36.1571
DEVIASI (%) -0.0600 -0.1200 -0.1800 -0.2400 -0.3200 -0.4000 -0.4800 -0.5600 -0.6400 -5.6200 -9.5000 -18.3800 -22.6600 -13.8000 -19.3800 -33.8400 -46.1600 -54.3500 -65.2800 -63.6929 -62.0829 -61.5229
RENCANA PROGRESS MINGGUAN (%) 100.0000 0.0600 0.0600 0.0600 0.0600 0.0800 0.0800 0.0800 0.0800 0.0800 4.7800 3.8800 7.8800 5.8800 4.5800 4.5800 2.5800 0.1800 0.9800 0.0800 0.0800 0.0800 0.0800 0.0800 12.5800 12.5600 1.9800 10.0800 14.7800 - - 9.1600 2.5600
RENCANA PROGRESS KOMULATIF (%) 0.0600 0.1200 0.1800 0.2400 0.3200 0.4000 0.4800 0.5600 0.6400 5.4200 9.3000 17.1800 23.0600 27.6400 32.2200 34.8000 34.9800 35.9600 36.0400 36.1200 36.2000 36.2800 36.3600 48.9400 61.5000 63.4800 73.5600 88.3400 88.3400 88.3400 97.5000 100.0600
REV 1 AKTUAL PROGRESS MINGGUAN (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 5.2000 28.2400 0.0000 0.1600 3.7600 15.1000 6.1000 0.0000 4.1400 2.2000
AKTUAL PROGRESS KOMULATIF (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 5.2000 33.4400 33.4400 33.6000 37.4600 52.5600 58.6600 58.6600 62.8000 65.0000
DEVIASI (%) -0.0600 -0.1200 -0.1800 -0.2400 -0.3200 -0.4000 -0.4800 -0.5600 -0.6400 -5.4200 -9.3000 -17.1800 -17.8600 5.8000 1.2200 -1.2000 2.4800 16.6000 22.6200 22.5400 26.6000 28.7200
Minggu Ke : 22
Material Valve 10.0000 8.0000 10.0000 -2.0000 -2.0000 Menunggu Material On Site
Material PANEL 6.0000 0.0000 6.0000 -6.0000 -6.0000 Menunggu Material On Site
Material KABEL 3.0000 0.0000 3.0000 -3.0000 -3.0000 Menunggu Approval PPM dari TLM
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 7.6000 8.0000 -0.4000 -0.4000 Menunggu Material Chiller & Pompa On Site
- Instalasi Pipa Ruang Cooling Tower 7.0000 6.9771 7.0000 -0.0229 -0.0229 Menunggu Material CT
- Instalasi Valve 6.0000 1.4000 6.0000 -4.6000 -4.6000 Menunggu Material Chiller, Pompa On Site
- Instalasi Kabel 3.0000 0.0000 3.0000 -3.0000 -3.0000 Menunggu Material On Site
Bandung, 16 April
Ket:
2019 .............................
Bobot A : Pekerjaan tertunda (Shop drawing) Diajukan Oleh :
Bobot B : Pekerjaan tertunda (Material On site) Kontraktor
PT. Trane Indonesia
Bobot C : SI
Atim Novianto
Project manager
KLARIFIKASI KETERLAMBATAN PROGRESS PERIODE
Nama Pekerjaan : PENGADAAN CHILLER PLANT
Kontraktor :
PT. TRANE INDONESIA
Konraktor : PT. TRANE INDONESIA
Minggu Ke : 22
Atim Novianto
Project manager
KLARIFIKASI KETERLAMBATAN PROGRESS PERIODE
Nama Pekerjaan : PENGADAAN CHILLER PLANT
Kontraktor :
PT. TRANE INDONESIA
Konraktor : PT. TRANE INDONESIA
Minggu Ke : 18
Material Valve 10.0000 #REF! 10.0000 #REF! #REF! Menunggu Material On Site
Material PANEL 6.0000 #REF! 6.0000 #REF! #REF! Menunggu Material On Site
Material KABEL 3.0000 #REF! 3.0000 #REF! #REF! Menunggu Approval PPM dari TLM
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 #REF! 8.0000 #REF! #REF! Menunggu Material Chiller & Pompa On Site
- Instalasi Pipa Ruang Cooling Tower 7.0000 #REF! 7.0000 #REF! #REF! Pondasi Cooling tower by Other
- Instalasi Valve 6.0000 #REF! 4.5000 #REF! #REF! Menunggu Material Chiller, Pompa On Site
- Instalasi Kabel 3.0000 #REF! 3.0000 #REF! #REF! Menunggu Material On Site
Bandung, 19 Maret
Ket:
2019 .............................
Bobot A : Pekerjaan tertunda (Shop drawing) Diajukan Oleh :
Bobot B : Pekerjaan tertunda (Material On site) Kontraktor
PT. Trane Indonesia
Bobot C : SI
Atim Novianto
Project manager
KLARIFIKASI KETERLAMBATAN PROGRESS PERIODE
Nama Pekerjaan : PENGADAAN CHILLER PLANT
Kontraktor :
PT. TRANE INDONESIA
Konraktor : PT. TRANE INDONESIA
Minggu Ke : 18
Atim Novianto
Project manager
BANDUNG INTERNATIONAL CONVENTION CENTRE
PEKERJAAN PEMASANGAN CHILLER PLANT
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9 Novembetr 2018 Minggu ke : 1
KONSTRUKSI :
12-Nov-2018 12-Nov-2018
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 20-Nov-2018
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 0.0000 0.0000 3.0000 0.0600 3.0000 0.0600
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 2
KONSTRUKSI :
12-Nov-2018 21-Nov-2018
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 27-Nov-2018
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 3.0000 0.0600 3.0000 0.0600 6.0000 0.1200
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 3
KONSTRUKSI :
12-Nov-2018 28-Nov-2018
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 04-Des-2018
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 6.0000 0.1200 14.0000 0.2800 20.0000 0.4000
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 4
KONSTRUKSI :
12-Nov-2018 05-Des-2018
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 11-Des-2018
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 20.0000 0.4000 14.0000 0.2800 34.0000 0.6800
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 5
KONSTRUKSI :
12-Nov-2018 12-Des-2018
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 18-Des-2018
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 34.0000 0.6800 14.0000 0.2800 48.0000 0.9600
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 6
KONSTRUKSI :
12-Nov-2018 19-Des-2018
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 25-Des-2018
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 48.0000 0.9600 14.0000 0.2800 62.0000 1.2400
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 7
KONSTRUKSI :
12-Nov-2018 26-Des-2018
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 26-Des-2018
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 62.0000 1.2400 14.0000 0.2800 76.0000 1.5200
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 8
KONSTRUKSI :
12-Nov-2018 02-Jan-2019
KONTRAKTOR
PELAKSANA :
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
12-Mei-2019 08-Jan-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 76.0000 1.5200 14.0000 0.2800 90.0000 1.8000
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 9
KONSTRUKSI :
12-Nov-2018 09-Jan-2019
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 15-Jan-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 90.0000 1.8000 14.0000 0.2800 104.0000 2.0800
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 10
KONSTRUKSI :
12-Nov-2018 16-Jan-2019
KONTRAKTOR
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
PELAKSANA :
12-Mei-2019 22-Jan-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 104.0000 2.0800 12.9700 0.2594 116.9700 2.3394
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 11
KONSTRUKSI :
12-Nov-2018 23-Jan-2019
KONTRAKTOR
PELAKSANA :
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
12-Mei-2019 29-Jan-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 116.9700 2.3394 13.4800 0.2696 130.4500 2.6090
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 0.0000 0.0000 10.0700 0.8056 10.0700 0.8056
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 107/SPK/TLM-PEMASANGAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 9-Nov-18 Minggu ke : 12
KONSTRUKSI :
12-Nov-2018 30-Jan-2019
KONTRAKTOR
PELAKSANA :
PT. SON DUCT SEJAHTERA MASA PELAKSANAAN : Tanggal
12-Mei-2019 05-Feb-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 130.4500 2.6090 19.4750 0.3895 149.9250 2.9985
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 10.0700 0.8056 11.2275 0.8982 21.2975 1.7038
- Instalasi Pipa Ruang Cooling Tower 7.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Bandung,
Mengetahui, Diperiksa / Disetujui, Dibuat oleh,
PT. TRITUNGGAL LESTARI MAKMUR PT. NUSA PRATAMA DWIKHARISMA PT. SON DUCT SEJAHTERA
Bulan
Nov 2018 Des 2018 Jan 2019 Feb 2019 Mar 2019 Apr 2019 Mei 2019 Juni 2019
12-Nov 21-Nov 28-Nov 5-Des 12-Des 19-Des 26-Des 2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 01-Mei 8-Mei 15-Mei 22-Mei 29-Mei 05-Juni 12-Juni 19-Juni
No Description Bobot
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
20-Nov 27-Nov 4-Des 11-Des 18-Des 25-Des 1-Jan 8-Jan 15-Jan 22-Jan 29-Jan 5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr 30-Apr 7-Mei 14-Mei 21-Mei 28-Mei 04-Juni 11-Juni 18-Juni 30-Juni
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32
RENCANA PROGRESS KOMULATIF (%)
PEKERJAAN INSTALASI AREA CHILLER &
COOLING TOWER
I PRELIMINARIES 2.0000 0.0600 0.0600 0.0600 0.0600 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.0800 0.2800 0.2800 0.5600 0.5600
II Unit
Unit CHILLER 25.0000 12.5000 12.5000 12.5000 12.5000
RENCANA PROGRESS MINGGUAN (%) 100.0000 0.0600 0.0600 0.0600 0.0600 0.0800 0.0800 0.0800 0.0800 0.0800 4.9800 3.8800 8.8800 6.8800 5.7800 5.5800 14.5800 14.3800 15.7800 13.9800 1.1800 0.5800 0.5800 0.5800 0.5800 0.5800 0.5800
RENCANA PROGRESS KOMULATIF (%) 0.0600 0.1200 0.1800 0.2400 0.3200 0.4000 0.4800 0.5600 0.6400 5.6200 9.5000 18.3800 25.2600 31.0400 36.6200 51.2000 65.5800 81.3600 95.3400 96.5200 97.1000 97.6800 98.2600 98.8400 99.4200 100.0000
REV 0 AKTUAL PROGRESS MINGGUAN (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 2.6000 14.6400 0.0000 0.1200 1.9600 7.5900 3.0500 2.7671 2.1900 1.1400
AKTUAL PROGRESS KOMULATIF (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 2.6000 17.2400 17.2400 17.3600 19.4200 27.0100 30.0600 32.8271 35.0171 36.1571
DEVIASI (%) -0.0600 -0.1200 -0.1800 -0.2400 -0.3200 -0.4000 -0.4800 -0.5600 -0.6400 -5.6200 -9.5000 -18.3800 -22.6600 -13.8000 -19.3800 -33.8400 -46.1600 -54.3500 -65.2800 -63.6929 -62.0829 -61.5229
RENCANA PROGRESS MINGGUAN (%) 100.0000 0.0600 0.0600 0.0600 0.0600 0.0800 0.0800 0.0800 0.0800 0.0800 4.7800 3.8800 7.8800 5.8800 4.5800 4.5800 2.5800 0.1800 0.9800 0.0800 0.0800 0.0800 0.0800 0.0800 12.5800 12.5600 1.9800 10.0800 14.7800 - - 9.1600 2.5600
RENCANA PROGRESS KOMULATIF (%) 0.0600 0.1200 0.1800 0.2400 0.3200 0.4000 0.4800 0.5600 0.6400 5.4200 9.3000 17.1800 23.0600 27.6400 32.2200 34.8000 34.9800 35.9600 36.0400 36.1200 36.2000 36.2800 36.3600 48.9400 61.5000 63.4800 73.5600 88.3400 88.3400 88.3400 97.5000 100.0600
REV 1 AKTUAL PROGRESS MINGGUAN (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 5.2000 28.2400 0.0000 0.1600 3.7600 15.1000 6.1000 0.0000 4.1400 2.2000
AKTUAL PROGRESS KOMULATIF (%) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 5.2000 33.4400 33.4400 33.6000 37.4600 52.5600 58.6600 58.6600 62.8000 65.0000
DEVIASI (%) -0.0600 -0.1200 -0.1800 -0.2400 -0.3200 -0.4000 -0.4800 -0.5600 -0.6400 -5.4200 -9.3000 -17.1800 -17.8600 5.8000 1.2200 -1.2000 2.4800 16.6000 22.6200 22.5400 26.6000 28.7200
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 105/SPK/TLM-PENGADAAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 12-Nov-18 Minggu ke : 22
KONSTRUKSI :
12-Nov-2018 10-April-2019
KONTRAKTOR
PELAKSANA :
PT. TRANE INDONESIA MASA PELAKSANAAN : Tanggal
12-Mei-2019 16-April-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 82.6000 1.6000 4.0000 0.0800 86.6000 1.6800
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 93.6313 7.5500 0.0063 0.0500 93.6376 7.6000
- Instalasi Pipa Ruang Cooling Tower 7.0000 76.5977 6.9671 0.0014 0.0100 76.5991 6.9771
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 105/SPK/TLM-PENGADAAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 12-Nov-18 Minggu ke : 20
KONSTRUKSI :
12-Nov-2018 3-April-2019
KONTRAKTOR
PELAKSANA :
PT. TRANE INDONESIA MASA PELAKSANAAN : Tanggal
12-Mei-2019 9-April-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 70.6000 1.3600 12.0000 0.2400 82.6000 1.6000
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 93.6250 7.5000 0.0063 0.0500 93.6313 7.5500
- Instalasi Pipa Ruang Cooling Tower 7.0000 76.5263 6.4671 0.0714 0.5000 76.5977 6.9671
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 105/SPK/TLM-PENGADAAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 12-Nov-18 Minggu ke : 20
KONSTRUKSI :
12-Nov-2018 27-Mar-2019
KONTRAKTOR
PELAKSANA :
PT. TRANE INDONESIA MASA PELAKSANAAN : Tanggal
12-Mei-2019 2-April-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 70.6000 1.3600 0.0000 0.0000 70.6000 1.3600
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 93.1250 7.4500 0.5000 0.0500 93.6250 7.5000
- Instalasi Pipa Ruang Cooling Tower 7.0000 61.0063 4.2500 15.5200 2.2171 76.5263 6.4671
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
PEMILIK PROYEK : TRITUNGGAL LESTARI MAKMUR NO. SPK : 105/SPK/TLM-PENGADAAN CHILLER PLANT/XI/2018
MANAJEMEN
TANGGAL SPK : 12-Nov-18 Minggu ke : 18
KONSTRUKSI :
12-Nov-2018 13-Mar-2019
KONTRAKTOR
PELAKSANA :
PT. TRANE INDONESIA MASA PELAKSANAAN : Tanggal
12-Mei-2019 19-Mar-2019
REKAPITULASI AKHIR
S/D Minggu Lalu Minggu ini S/D Minggu ini Bobot Disetujui
DESKRIPSI Bobot ( % )
Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % ) Progress (%) Bobot ( % )
I PRELIMINARIES 2.0000 66.6000 1.2800 4.0000 0.0800 70.6000 1.3600
II Unit
Unit CHILLER 25.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Unit COOLING TOWER 8.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
III INSTALASI
- Instalasi Pipa Ruang Chiller 8.0000 90.5000 7.2400 2.0000 0.1600 92.5000 7.4000
- Instalasi Pipa Ruang Cooling Tower 7.0000 12.8571 0.9000 12.4349 0.8500 25.2920 1.7500
- Test Tekan Pipa 1.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IV TESTING KESELURUHAN & COMMISSIONING 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
758,744 592,574
152,884 994,207
252,216 382,612
159,343 212,112
458,443 682,414
469,066 471,610
512,117 398,348
180,581 90,411
225,374 174,791
682,871 602,209
1,053,985 1,171,220
2,592,109 771,209
451,458 186,072
1,846,554 811,547
267,007 457,899
447,377 37,355
167,279 339,618
303,119 33,080
296,450 312,739
179,943 113,656
83,264 181,534
184,641 143,059
198,532 84,753
103,673 88,398
418,141 525,029
237,947 341,227
180,391 173,094
80,734 46,813
66,872 35,709
24,365 32,324
24,642 5,468
10,399 1,301
52,615 23,739
196,725 71,941
54.9336324 45.0663676