Sie sind auf Seite 1von 1

Daily Modification Report

Date: 2016-03-15 MDR#23


Attendance:
Indict No. Direct No. Equipment No
Construction Manager 1 Foreman 2 Crane 50 ton 2
Project Site Engineer 2 Crane Operator 3 Man-lift 39m 3
QC Engineer 1 Manlift Operator 3 Crawler Crane 200 ton 1
HSE Manager 1 Rigger3 5 Trailers 1
Supervisor 3 Erectors 8 Welding Machines 2
Safety Officer 2 Helpers 8 Bus 1
Surveyor 1 Flag Man 4 Diesel Tanker 1
Timekeeper 1 Welder 2 Pick Up 2
Work Permit Receiver 1 Fabricator 3 Forklift 1
Planning Engineer 1 Driver 1
Document Controller 1 Firewatch 2
Electrician 1
Forklift |Operator 1
Scaffolder 2

SubTotal: 15 45 14
Total Manpower at site: 60
ERECTION OF NEW MEMBERS/ ADDITIONAL SCOPE
Building Name: Process Building E&F
Mark# Qty Unit Weight,kg Total Weight, kg Mark# Qty Unit Weight,kg Total Weight, kg
0
0
Today's Total Erected Weight (Tons) Accumilative erected weight =7.8039Tons
DISMANTLING OF ORIGINAL MEMBERS
Building Name: Process Building E&F
Mark# Qty Unit Weight,kg Total Weight, kg Mark# Qty Unit Weight,kg Total Weight, kg
0

Today's Total Dismantled Weight (Tons) 0 Accumilative erected weight 4.773 Tons
ERECTION OF ORIGINAL STRUCTURE
Building Name: Process Building E/F
Mark# Qty Unit Weight,kg Total Weight, kg Mark# Qty Unit Weight,kg Total Weight, kg

Today's Total Erected Weight (Tons) 0 Accumilative erected weight = 32.7727Tons


Building Name: Process Building G/H
ERRECTION IS STOPPED BECAUSE OF STRONG WIND
Mark# Qty Unit Weight,kg Total Weight, kg Mark# Qty Unit Weight,kg Total Weight, kg
B14-1 1 1218.127 1218.127 B100-1 2 85.485 170.97
B18-1 1 1175.415 1175.415 B99-1 4 110.025 440.1
B83-1 1 65.474 65.474 Q1-1 2 31.241 62.482
B85-1 3 28.765 86.295 Q3-1 2 31.241 62.482
B50-1 1 775.38 775.38 Q8-1 7 11.242 78.694
B51-1 1 775.38 775.38 Q9-1 7 11.242 78.694
B92-1 7 127.254 890.778
Today's Total Erected Weight (Tons) 5.880271 Accumilative erected weight =22.003851 Tons
S.N. Issue detail Date Action by
1 DGC shall handover all Bolts to Zamil DGC
2 DGC release the hold area in the Admin Building DGC
3
Prepared by: Check by: Approved by:
Engr. Jerson M. Hidalgo Eng. Omar Al Hassan. Engr. Jose Antonio Perez Vargas