Table 1: Mobilization Checklist

Option 1: When Standard ISO 20’ Sea Containers are used for all Units

S.N. Activity Number of Days Needed

A Phase 1: Mobilization for Design, Mandatory Inspection and


Production

A.1 Work Force mobilization (Permits, visas 15 days

and security clearance)

A. 2 Site assessment to take actual 5 days

measurement

A. 3 Detailed design (Layout plans & 10 days

structural) development and


approvals

A. 4 Mobilization of production materials 50 days

and sea containers

A. 5 Mobilization of modification 10 days

equipment and tools

B Phase 2: Mobilization for Installation Works

B.1 Equipment mobilization 15 days

B. 2 Material mobilization 90 days

B. 3 Securing Land for Camp Site 10 days

B. 4 Developing Life Support 15 days

Supply and Installation (Turnkey) of Modified Containerized Accommodation and Office Units Page 9 of 37
Option 2: When High cube 20’ Sea Containers are used for Office Units and
Standard Sea Containers for the rest of the Units
S.N. Activity Number of Days Needed
A Phase 1: Mobilization for Design, Mandatory Inspection and
Production
A.1 Work Force mobilization (Permits, visas 15 days

and security clearance)


A. 2 Site assessment to take actual 5 days

measurement
A. 3 Detailed design (Layout plans & 10 days

structural) development and


approvals
A. 4 Mobilization of production materials 50 days

and sea containers


A. 5 Mobilization of modification 10 days

equipment and tools


B Phase 2: Mobilization for Installation Works

B.1 Equipment mobilization 15 days

B. 2 Material mobilization 90 days

B. 3 Securing Land for Camp Site 10 days

B. 4 Developing Life Support 15 days

Currently, UNSOS does not have any land/ site available for contractor’s
permanent camp within MIA in Mogadishu. However, in the other Sectors, UNSOS
may be able to assist. UNSOS shall review the request from the contractor at the
time of issuance of Mobilization Task Order. Bidders must therefore take into
consideration, in their proposals, the requirement to secure land for establishment
of life support camp in Mogadishu by their own means and cost. UNSOS may only
support in facilitating the request of the contractor(s) to the Local Authorities.

NOTE: DOCOL has a fabrication workshop within the MIA and is able to source
additional land nearby for expansion of the workshop and storage. DOCOL also
Supply and Installation (Turnkey) of Modified Containerized Accommodation and Office Units Page 10 of 37
owns a piece of land on the main road which can be used for storage and
fabrication whilst it already has a Man Camp within the MIA.

DOCOL plan is to fabricate the containers and then transport them by Road to other
sectors where the work carried out is fittings like toilets etc. DOCOL being a Local
Somali company, we can procure land for fabrication purposes at very short notice.
For life support services DOCOL intends to hire out an existing hotel or
accommodation facility.

DOCOL already has a fully-fledged setup in Baledogle, with units in Kismayo,


Jowhar and Baidoa which gives an edge on mobilisation

Supply and Installation (Turnkey) of Modified Containerized Accommodation and Office Units Page 11 of 37