MEP Defect List

Owner By:
Project Check by:
Consultant Date: 08-06-19
Location Rev: 00

No. Location Picture Risk Finishing date Status Remark

12-06 14-06 19-06

1 Guard House The wall is absorbed 0% 0% Done

2 Guard House The ceiling is absorbed 0% 0% Done


3 Office The wall not finishing 100%

4 Office The light not install 100%

The glass door have


5 Office some tracer can't 0% 0% 0%
remove
The FF don't have fire
6 All 50% 50% Done
hose reel

7 Toilet Loss window 0% 0% 0%

Loss permanent
8 All 0% 0% Done Only temp cable
electrical system
All most canal system is
9 Factory 0% 0% 0%
not finishing

All most canal system is


10 Factory 20% 60% Done
not finishing

The foundation for tank


11 Tank area 0% 0% 90%
is not finishing
The foundation for tank
12 Tank area 0% 0% 90%
is not finishing

Don't have foundation


13 RO area 80% 100%
for RO sysytem

Not good cable


14 Light system 0% 0% Done
connection
Have some thing on the
15 Wall 0% 0% Done
wall

The cable routing not


16 Wall 0% 0% Done
good

The cable routing not


17 Wall 0% 0% 0%
good
18 Column Need repainting 0% 0% Done

19 Column Sika gound for column 0% 0% Done

Cover for chanel (RO


20 RO area 0% 0% 0%
area)
21 Factory Cover for big chanel 0% 0% 0%

The glass on handrail


22 Office 0% 0% 0%
have sharp

The floor of toilet not


23 Office 0% Done
finishing
The floor is crack (near
24 Factory 0% 0%
big channel)

The floor is crack (near


25 Factory 0% 0%
big channel)

26 Factory The floor is crack 0% 0%


V shape steel on
27 Factory channel must be 0%
Galvanize.

28