Sie sind auf Seite 1von 8

FireSafe
CASE STUDIES IN
STRUCTURAL STEEL

Fire safety engineering by design Issue 3, March 2006

Alternative solutions in

Fire Safety Engineering


Bare Steel Construction
• Un-compromised Safety
• Architectural flexibility
• Reduced construction costs

Adelaide Airport

www.onesteel.com
Welcome to FireSafe™ Solutions Issue 3, showcasing steel framed retail projects that
benefited from the application of performance based Fire Safety Engineering assessments,
to provide alternative solutions using bare steel construction that can offer benefits such as:

Increased Safety Levels Reduced Building Costs


Architectural Flexibility Faster Construction

Focus on Shopping
and Retail Centres
Would you like to Modern shopping centres are paper by Bennetts and Thomas [3]. The building. Although it can be argued that
find out more? complex buildings for which it is advocated design and management such a philosophy could be applied
TALK IN CONFIDENCE TO
sometimes difficult to satisfy the approach only applies to low-rise to every building it is particularly
YOUR ONESTEEL STATE
Building Code of Australia’s (BCA) (typically 4 storeys or less), sprinklered critical with such buildings because
MARKET ENGINEER
prescriptive deemed-to-satisfy shopping centres. of their size and interconnectedness.
provisions and achieve the desired It is important to note that shopping Current deemed-to-satisfy regulations
NSW/ACT David Bell functionality. Access between levels are confused on this matter as they
centre buildings are examples of
Phone: (02) 9792 9075 is important and this, combined frequently allow smoke exhaust
buildings for which there are strong
Fax: (02) 9792 9093 with the desire to have buildings systems to be designed for relatively
economic motives to avoid a significant
Mobile: 0407 357 120 that are more open and connected, small fires but the structure (which
fire, and management practices within
belld@onesteel.com means that substantial openings are is only affected locally) is required to
these buildings are often conducive to
QLD Nick van der Kreek provided between levels. Traditional achieving this outcome. Examples of have very high levels of fire resistance,
Phone: (07)3845 5603 “compartmentation” therefore has little these practices are: suggesting a much more severe fire.
Fax: (07) 3845 5609 meaning and is unlikely to offer much The reality is that it will be impossible
Avoiding fire starts
Mobile: 0417 145 199 assistance in containing the effects to design a smoke exhaust system
• house-keeping audits
vanderkreekn@onesteel.com of a major fire. This, combined with for a major unsprinklered fire - yet
• audits of electrical cabinets
VIC/TAS Gary Oldfield the fact that these buildings contain testing undertaken as part of the above
(e.g. infrared evaluation)
Phone: (03) 8312 2639 massive quantities of combustibles, research has illustrated the fact that
• residual current protection
Fax: (03) 8312 2650 means that extremely severe fires such fires are quite possible.
• regular replacement of old
oldfieldg@onesteel.com could develop within these buildings. The achievement of high levels of
electrical (light) installations
WA/SA/NT Spiros Dallas Such fires could have disastrous safety in these buildings is actually
• maintenance of electrical
Phone: (03) 8312 2633 effects due to the associated smoke a risk management exercise where
equipment
Fax: (03) 8312 2650 and heat. the objective could be taken as
A significant amount of research Minimising fire size eliminating the occurrence of a
Mobile: 0419 587 951
has been undertaken over the last • camera surveillance within centre major unsprinklered fire. This will be
dallass@onesteel.com
eight years and supported by funding (security) achieved through appropriate design
from OneSteel (and previously BHP • fire awareness and fire-fighting and through proper management of
REFERENCES
Steel) and the Building Commission training for all staff the fire-safety systems. Therefore
1. Fire Code Reform Centre,
of Victoria. The original work was • sprinkler management policies fire-safety practitioners must have a
“Fire Safety in Shopping
Centres”, Final Research undertaken under the guidance of None of the above factors are significant input into developing and
Report, Project 6 the Fire Code Reform Centre (FCRC) considered in building codes or maintaining appropriate management
and the results were published in a regulations, yet it is possible that practices and procedures. Under these
2. OneSteel/BHP Special summary report prepared for that circumstances it can be argued that
these may have a bigger impact on
Publication, “Design of organisation [1]. This report and other the design fires appropriate to all fire-
fire safety than the specific matters
Sprinklered Shopping detailed reports prepared for the safety systems (including the building
addressed by the regulations. In
Centres for Fire FCRC dealing with aspects of the structure) should be sprinklered fires.
reality, the fire safety of these
Safety”, 2001 fire safety of shopping centres are buildings is a complex function of The buildings described in this
3. Bennetts, I. D. available directly from the website of building management, the reliability of booklet have been mostly based on
and Thomas, I. R., Design of the Australian Building Codes Board systems, occupant behaviour, smoke the recommendations of the above
Sprinklered Shopping Centre (ABCB). This work was extended management, building layout, fire- publications. These buildings include
Buildings, Journal of Fire following further testing and slightly fighting facilities and personnel, and two shopping centre complexes
Protection Engineering, Vol revised but more complete design the behaviour of the building structure. in Adelaide – West Lakes Mall
12 No. 4, 2002, Society of and management recommendations It has been found that the redevelopment and Norwood shopping
Fire Protection Engineers were given in the OneSteel publication achievement of high levels of fire plaza, Adelaide airport redevelopment
“Design of Sprinklered Shopping safety will be almost totally dependent since this building contains significant
Centres for Fire Safety”, 2001 [2]. on limiting the fire size and providing retail and Rhodes Shopping Centre
The essential content of the approach alternative paths for occupants to in NSW.
has been described in the technical move to safer places within the

FireSafe™ : Fire Safety Engineering by Design | Page 2


Norwood Plaza
THE STEEL-FRAMED SOLUTION PROVIDES THE SPEED
REQUIRED TO MEET THE CHRISTMAS RUSH.

THE SPEED OF CONSTRUCTION


PROVIDED BY THE STEEL-FRAMED
SOLUTION OFFERED THE
TENANTS THE POSSIBILITY
OF PRE-CHRISTMAS TRADING.
THE $24.5MILLION PROJECT
WAS COMPLETED IN JUST
12 MONTHS FROM START
OF DEMOLITION TO THE
FIRST RETAIL SALE.

Norwood plaza consists of varying With the exception of transfer surface area-to-mass ratio to achieve OWNER/DEVELOPERS
Parkade Pty Ltd
numbers of levels throughout. beams, no beams within the project the required performance without
A basement carpark is provided were fire protected and this lead to additional fire-protective coating. ARCHITECTS
throughout the building with the significant economies in construction. Hardy - Millazzo
The fire safety engineering report
number of storeys above this varying Intumescent coatings were used to relating to the structural steelwork STRUCTURAL AND
BUILDING SERVICES
from one to three floors at the eastern achieve enhanced fire-resistance for produced by OneSteel’s fire engineers ENGINEER
edge of the building. Ground floor is the columns and transfer members Ceasre VU, emphasised the need for Kellogg Brown Root
retail and includes a major store. although the report concluded that a (KBR)
development and implementation of
The other levels incorporate carparking, lesser fire resistance was required, and fire-safety management plans within BUILDER/PROJECT
MANAGER
commercial and plant areas. that in some cases, the columns and this shopping centre. Hansen Yuncken
The building has an escalator link beams had a sufficiently low exposed
BUILDING CERTIFIER
between the basement carpark and Katnich Dodd
the ground floor retail.
PHOTOGRAPHER
A structural steel framing solution Kevin O’Daly
was utilised for this building and a
fire-safety engineering evaluation was
undertaken to determine the extent NORWOOD PLAZA – FIRE RESISTANCE REQUIREMENTS SUMMARY
of fire protection required for the
BUILDING ELEMENT ELEMENT REQUIREMENT
structural steelwork and this was done
in accordance with the references
DTS Alternative Solution
discussed in the introduction.
beams in carpark ksm* ≤ 30m2/tonne
The structural steel framework
incorporated a variety of OneSteel columns in 60/-/- 60/-/- but report considered
carpark that ksm sufficiently low and
300PLUS® Sections including welded no protection required
columns and tubular columns and columns in retail 180-/- 60/-/- but report
transfer, primary and secondary beams recommended 30/-/-#
ranging in size from welded beams (for transfer beams 180-/- 60/-/- but report considered
transfer beams) to 310UB40 sections that ksm sufficiently low and
no protection required
(for secondary beams).
beams in retail 180/-/- ksm = 30m2/tonne
sprinklers YES YES
k sm is the exposed surface area-to-mass ratio
*# also applies to connections between primary beams and columns

FireSafe™ : Fire Safety Engineering by Design | Page 3


Adelaide Airport Terminal
A SHOPPING CENTRE IN FIRE ENGINEERING TERMS.

THE $260 MILLION REDEVELOPMENT


OF ADELAIDE AIRPORT IN FIRE SAFETY
ENGINEERING DESIGN TERMS IS VERY SIMILAR
TO A SHOPPING CENTRE – LARGE IN PLAN
RELATIVE TO ITS 3 STOREY HEIGHT WITH MANY
PEOPLE COMING AND GOING THROUGH ITS
OPEN MALL TYPE AREAS AND RETAIL STORES.

FireSafe™ : Fire Safety Engineering by Design | Page 4


This building consists of three to ensure that during such isolations, On the basis of extensive sprinkler
levels and includes retail outlets; a particular fire-safety measures testing it was established that
departure lounge, an arrival lounge, are put into place to minimise the sprinklered fires would not result in
baggage handling, and baggage likelihood of a significant fire. a significant increase in temperature
reclaim areas. There are also It was recognised that airport of exposed structural steel members.
administration areas and gate terminal buildings are highly In several areas it was noted that
lounges. According to the BCA, the supervised buildings where occupants columns pass through parts of the
building is a mixture of Class 9 and are likely to detect fires relatively building with high ceilings where
Class 6 and would be required to be rapidly. Most fires will be extinguished activation of sprinklers on the ceilings
constructed as Type A construction. before the sprinklers are activated would be likely to be delayed. Parts
A section through the building is and will be assisted by the availability of the building where such situations
shown below. of portable extinguishers and may occur include areas such as the
Steel-framed construction was appropriate training of airport staff. departure and arrival areas. It was
chosen to allow ease of construction The airport fire brigade was also noted that the fire load in these areas
and to deliver the desired architectural noted as being close at hand. The was localised and given the exposed
features. isolation management procedure is surface area-to-mass ratio of the
to be aimed at managing sprinkler 300PLUS® columns passing through
OneSteel’s fire engineers Cesare these areas would not result in
VU assessed the fire safety aspects of isolations so as to minimise the likelihood
of a serious non-sprinklered fire. column failure if subject to a localised
this building relating to the structural fire before sprinkler activation.
steel. Their report indicated that
the building should be designed in
accordance with reference [2] (see
Introduction). It was agreed by the
stakeholders in the fire engineering
process that the building need only
be generally designed to resist
the range of possible sprinklered OWNER/DEVELOPER
fires. This design assumption was Adelaide Airport
considered to be satisfactory on the Limited

basis that sprinkler management PROJECT MANAGER


and maintenance procedures were Barry Phillis &
Associates
developed and implemented to
minimise the frequency, extent and ARCHITECT
duration of sprinkler isolations and Hassell

ADELAIDE AIRPORT TERMINAL – FIRE RESISTANCE REQUIREMENTS SUMMARY STRUCTURAL ENGINEER


Wallbridge & Gilbert
BUILDING ELEMENT ELEMENT REQUIREMENT
D & C CONTRACTOR
Hansen Yuncken
DTS Alternative Solution
BUILDING SERVICES
columns FRL 180/-/- (retail) generally no requirement; in ENGINEER
FRL 120/-/- (other areas) high roof areas sufficiently low Bestec
k sm* to survive localised fire
BUILDING CERTIFIER
beams FRL 180/-/- (retail) no requirement Airport Building
FRL 120/-/- (other areas) Controller

floors 180/180/180 (retail) 60/60/60


120/120/120 (other areas)
sprinklers YES YES

k sm is the exposed surface area-to-mass ratio


*
FireSafe™ : Fire Safety Engineering by Design | Page 5
Rhodes Waterside
Shopping Centre
135,000 SQUARE METRES OF SHOPPING AREA
ENCLOSED BY A STEEL-FRAMED STRUCTURE.

BUILT AT A REPORTED COST OF $150


MILLION DOLLARS IS A SHOPPING CENTRE
THAT INTERACTS WITH THE RESIDENTIAL
BUILDINGS AROUND IT, PROVIDING NOT
JUST SHOPPING BUT MEDICAL SERVICES,
BUSINESS OFFICES RESTAURANTS, AN EIGHT-
SCREEN CINEMA COMPLEX AND A BULKY
GOODS RETAIL STORE AND WAREHOUSE.
This was necessary since speciality steel members, it was successfully
stores are far more subject to change argued that these members had
and modification than major stores sufficient inherent fire resistance
and therefore it is more likely that associated with their surface area-to-
sprinklers would be isolated in the mass ratios to allow evacuation
speciality shops to allow tenancy of the particular areas. In addition, it
upgrade works. In addition, particular was recognised that as this building
This is a 135,000 m2 project sprinkler management protocols were is a highly redundant building, the
incorporating below ground required for the shopping centre in effects of an unsprinklered fire will
carparking over the entire site with a order to minimise extended sprinkler be localised. Accordingly, there is little
retail complex including two levels of isolation. Also, end of line taps are protection of structural steel members
specialist shopping malls, mini-major provided for each sprinkler zone to within this building other than that
retail tenancies (Coles® & Bi-lo®), allow the checking of water flow both associated with ceilings
bulky goods retail (IKEA®), food courts, during commissioning and annually. and architectural cladding, where
cinemas and 4 levels of commercial The fire-resistance levels within such is provided.
tenancy above the cinemas. A full the building have been generally The following diagram gives
height carpark structure adjacent specified as 60 minutes. However, a schematic section through the
to the retail tenancies provides in the case of 300PLUS® structural commercial part of the building:
carparking over 9 levels including
the basement. Carparking is also
OWNER/DEVELOPER available over the top of IKEA®, as
Walker Corporation
part of the 2,000 overall car spaces
ARCHITECT provided in the shopping centre.
The Buchan Group
The fire-safety engineering design
STRUCTURAL for this complex considered each
ENGINEER RHODES WATERSIDE – FIRE RESISTANCE REQUIREMENTS SUMMARY
Van der Meer of the individual areas within the
Consulting complex and incorporated specific BUILDING ELEMENT ELEMENT REQUIREMENT
measures to minimise the likelihood
BUILDER/PROJECT
MANAGER of a severe fire. Sprinkler zoning was DTS Alternative Solution
Walker Group selected such that separate zones fire-resistant walls 180/180/180 60/60/60
Constructions
were provided for the mini-major floor slabs 180/180/180 60/60/60
FIRE ENGINEERING stores and bulky-good areas and beams 180/-/- ksm ≤ 30m2/tonne if steel
Lincolne Scott other key areas in order to maximise or 60 /-/-

BUILDING CERTIFIER the reliability of the sprinkler systems. columns 180/-/- ksm ≤ 26m2/tonne if steel
or 60 /-/-
McKenzie Group
sprinklers YES YES

FireSafe™ : Fire Safety Engineering by Design | Page 6


West Lakes Re-Development
STEEL’S VERSATILITY ALLOWS ECONOMICAL
RE-DEVELOPMENT TODAY AND THE FLEXIBILITY
TO MAKE FURTHER CHANGES TOMORROW.

THE DESIGNERS
USED THE
VERSATILITY OFFERED
BY THE SUPERIOR
STRENGTH TO
WEIGHT RATIO OF
OWNER/DEVELOPER
STEEL FRAMING TO Deutsche Bank
Real Estate
MAKE SUBSTANTIAL
PROJECT MANAGER
CHANGES TO Clifton Coney Group

THE EXISTING ARCHITECT


Hames Sharley
SHOPPING MALL.
STRUCTURAL
ENGINEER
They did so with the knowledge Wallbridge & Gilbert

that any future changes are relatively BUILDER/PROJECT


easy to make as a steel frame MANAGER
Baulderstone
can be readily strengthened, and Hornibrook
modified by welding or bolting new
FIRE ENGINEERING
members to it. Warrington Fire
The redevelopment of the West the building, principally some of the of a significant unsprinklered fire.
BUILDING CERTIFIER
Lakes shopping mall involved the primary beams and columns within However, it is very unlikely that Katnich Dodd
addition of a ground level carpark the promenade area adjacent to such a fire would develop given the
below a cinema complex and adjacent and providing direct support to the presence of sprinklers.
mall and food court areas. The entire cinemas. A cross-section showing the Even a shielded sprinklered fire
building extension was framed in promenade in relation to the seating would not generate sufficient heat to
structural steel including the cinemas tiers is shown above. detrimentally effect the supporting
with columns being placed within the Egress from the upper seating structural steel members.
walls between cinemas and trusses tiers is via two alternative exits and
supporting the roof spanning the full the cinemas can be evacuated in WESTLAKES RE-DEVELOPMENT – FIRE RESISTANCE REQUIREMENTS SUMMARY
width of each cinema. It is important several minutes. The space below
to note that the acoustic requirements BUILDING ELEMENT ELEMENT REQUIREMENT
the seating tiers is used primarily for
for the cinema walls were achieved storage. These areas as well as all
by multiple layers of plasterboard DTS Alternative Solution
other areas within the construction
and this, by default, provided very type of construction type B
are sprinklered.
substantial thermal protection for the columns - carpark ksm < 26m2/tonne
As far as the cinemas were beams - carpark ksm < 30m2/tonne
300PLUS® steel columns located
concerned, evacuation of an upper columns - cinemas 120/-/- 60/-/- for some columns
within the walls.
tier was found to be able to be in promenade; remainder
The floor construction consisted ksm ≤ 26m2/tonne
achieved within a few minutes, as
of composite slabs supported by beams - cinemas - /-/-* certain beams in
was evacuation of the lower tiers. promenade 60/-/-;
300PLUS® steel beams. It was Evacuation can occur well before remainder ksm ≤ 30m2/
found that it was only necessary to any supporting structural steelwork
tonne
fire protect certain elements within sprinklers YES YES
would feel the temperature effects
* support of another part may require 120/-/-

FireSafe™ : Fire Safety Engineering by Design | Page 7


OneSteel FireSafe™
Guides

ONESTEEL’S FIRESAFE™ DESIGN GUIDES ARE AVAILABLE


TO VIEW OR DOWNLOAD FROM THE ONESTEEL WEBSITE
www.onesteel.com/publications.asp
ALTERNATIVELY, THE FIRESAFE™ DESIGN GUIDES ARE
ALSO AVAILABLE ON CD AS PART OF THE ONESTEEL
DESIGN COMPENDIUM. TO ORDER SIMPLY
PHOTOCOPY THIS PAGE AND FAX OR MAIL TO:

ONESTEEL DIRECT
FAX: 1800 626 919
MAIL: LOCKED BAG 8825 WOLLONGONG DC
NSW 2500 AUSTRALIA

YES, please send me the OneSteel Design Compendium

Customer ID (please refer to fly sheet)

Given Name*(s) Dr/Mr/Mrs/Ms

Surname*

Occupation*

Company*

Company Address*

Suburb* State* Postcode*

Email Address

Telephone ( ) Fax ( )

Please add me to your mailing list

*Required Fields

9 320075 045630

This publication has been prepared by OneSteel Market Mills an operating business group of which OneSteel Manufacturing Pty Limited ABN 42 004 651 325, OneSteel NSW Pty Limited ABN 59 003 312 892,
OneSteel Wire Pty Limited ABN 59 000 010 873, OneSteel Trading Pty Limited ABN 50 007 519 646, OneSteel MBS Pty Limited ABN 76 096 273 979 are a part. Please note that any specifications or technical
data referred to in this publication are subject to change and/or variation or improvement without notice and no warranty as to their suitability for any use is made. Users of this publication - to ensure accuracy
and adequacy for their purposes - are requested to check the information provided in this publication to satisfy themselves as to its appropriateness and not to rely on the information without first doing so.
�����

Unless required by law, the company cannot accept any responsibility for any loss, damage or consequence resulting from the use of this publication. Photographs shown are representative only of typical applications,
current at March 2006. This publication is not an offer to trade and shall not form any part of the trading terms in any transaction. © Copyright 2002-2006. OneSteel Market Mills. Registered Trademarks of
OneSteel Market Mills: 300PLUS®. IKEA® is a registered trademark of IKEA® International Pty Ltd. Coles® and Bi-Lo® are registered trademarks of Coles Myer Ltd. Issue 3. Printed February 2006.

©Copyright 2002-2006. OneSteel Manufacturing Pty Limited ABN 42 004 651 325. e13400 www.onesteel.com

Das könnte Ihnen auch gefallen