92818: PO A 2018 U4 ESP AERATION BLOWER B&C-HEATER

Asset: A13829 ESP HOPPER AERATION AIR BLOWER A Safety Work?: N

Location: 00FAD-F801A ESP HOPPER AERATION AIR BLOWER A

CI:

Sched Start: 06-Aug-2018 Site: KPJB Job Plan:

Sched Finish: 21-Sep-2018 Priority: Supervisor: 1008023

Target Start: 06-Aug-2018 Work Type: OH Lead: BOILERSENIOR

Target Finish: 21-Sep-2018 Status: APPR Vendor:

Actual Start: Parent: 92484 Owner:

Actual Finish: Failure Class: FAN Owner Group:

Report Date: 17-Jul-2018 Problem Code: Service:

Reported By: BOILERPLANNER ( Boiler Planner ) Doc No.: Service Group:

On Behalf Of: GL Account: 00174-????? Classification:

Multi Asset/Location/CI

Asset Description Location Description CI Description Target Description

A13830 ESP HOPPER AERATION AIR BLOWER B 00FAD-F801B ESP HOPPER AERATION AIR BLOWER B

A13831 ESP HOPPER AERATION AIR BLOWER C 00FAD-F801C ESP HOPPER AERATION AIR BLOWER C

A13836 ESP HOPPER AERATION AIR HEATER A 00FAD-H802A ESP HOPPER AERATION AIR HEATER A

A13837 ESP HOPPER AERATION AIR HEATER B 00FAD-H802B ESP HOPPER AERATION AIR HEATER B

Task IDs

Task ID Description Location Location Target Start Target Finish Actual Start Actual Finish
Description
10 Inspect ESP aeration blower, vibration and noise before and 00FAD-F801A ESP HOPPER
after maintenance (reported) AERATION AIR
BLOWER A
20 Replace bearings and parts (oil seals), cleaning strainer, 00FAD-F801A ESP HOPPER
replace oil, replace v-belts AERATION AIR
BLOWER A
30 Alignment V-belt and test run after re-assembly 00FAD-F801A ESP HOPPER
AERATION AIR
BLOWER A
40 Thightening all of bolts connection and cleaning 00FAD-F801A ESP HOPPER
AERATION AIR
BLOWER A
50 Clean outlet pipe, silencer, check valve, isolated valve and 00FAD-F801A ESP HOPPER
pneumatic valve for Fly Ash Silo Blower AERATION AIR
BLOWER A
60 Inspect valve operating condition and repair damage parts 00FAD-F801A ESP HOPPER
AERATION AIR
BLOWER A
70 Repair damaged cover of blower and repainting 00FAD-F801A ESP HOPPER
AERATION AIR
BLOWER A

Planned Labor

Task ID Craft Skill Level Labor Vendor Contract Qty Hours Rate Line Cost

MECH 3 888:00 0 0

Total Planned Labor: 0

Precautions for Hazards

Precaution Description Hazard Description Hazard Type Related Location Related Asset Description

PPE001 Personal Protection Equipment General

PPEEARPG EAR PLUG

PPEGLVCT SAFETY GLOVES COTTON

PPEHELM SAFETY HELMET

PPEHRBDY SAFETY BODY HARNESS

PPEMSKCT MASKER COTTON /CONSUMABLE

PTW001 Permit to Work General

PTW001 Preparation of Maintenance

PTW002 Approval PTW from Shift Leader

PTW003 Check the line isolation