Sie sind auf Seite 1von 78

P ROJECT I NTEGRATION

M ANAGEMENT

February 2016 Hisham Haridy, PMP, PMI-RMP


Project Management Processes
The main role of Project Manager is putting all the

pieces of the project together into one cohesive whole

that gets the project done faster, cheaper, and with

fewer resources, while meeting the project objectives.

The reason for the project manager’ existence in an organization and on a project is to

manage integration.

PROJECT INTEGRATION MANAGEMENT February 2016


Project Management Processes

Communications

Stakeholders
Procurement
Resource
Quality

Human
Scope

Time

Cost

Risk
Integration

PROJECT INTEGRATION MANAGEMENT February 2016


Project Management Processes Groups and Knowledge Areas

Processes Group
Monitoring
Initiating Planning Executing and Closing
Controlling
Knowledge Areas

PROJECT INTEGRATION MANAGEMENT February 2016


Project Management Processes Groups and Knowledge Areas
Processes
Monitoring and
Initiating Planning Executing Closing
Knowledge Areas Controlling
1.Develop Project 2. Develop Project Management Plan 2. Direct and Manage 4.Monitor and Control Project 6.Close Project or
Charter Project Work Work Phase
Integration (6) 5.Perform Integrated Change
Control
1.Plan Scope Management 5.Validate Scope
2.Collect Requirements 6.Control Scope
Scope (6) 3.Define Scope
4.Create WBS
1.Plan Project Schedule 7.Control Schedule
2.Define Activities
3.Sequence Activities
Time (7) 4.Estimate Activity Resource
5.Estimate Activity Durations
6.Develop Schedule
1.Plan Cost Management 4.Control Costs
Cost (4) 2.Estimate Costs
3.Determine Budget

Quality (3) 1.Plan Quality Management 2.Perform Quality Assurance 3.Control Quality

1.Plan Human Resource Management 2.Acquire Project Team


Human Resources 3.Develop Project Team
(4) 4.Manage Project Team

Communications (3) 1.Plan Communication Management 2.Manage Communication 3.Control Communication

1.Plan Risk Management 6.Control Risks


2.Identify Risks
Risk (6) 3.Perform Qualitative Risk Analysis
4.Perform Quantitative Risk Analysis
5.Plan Risk Responses
1.Plan Procurement Management 2.Conduct Procurements 3.Control Procurements 4.Close
Procurement (4) Procurements
1.Identify 2.Plan Stakeholder 3.Manage Stakeholder 4.Control Stakeholder
Stakeholder (4) Stakeholders Engagement Engagement

PROJECT INTEGRATION MANAGEMENT February 2016


Project Management Documents
PROJECT DOCUMENTS

Project Management Plan


Project Scope Statement

1-Scope Management Plan

2- Schedule Management Plan 1- Milestone list


Project Charter

3- Cost Management Plan 2-Resource Calendar

4- Quality Management Plan 3-Risk Register

5- HR Management Plan Project Baselines 4- Stakeholder Register

6- Communication Management plan 1- Scope Baseline 5- Stakeholder Management

7- Risk management Plan Strategy


2- Schedule Baseline
8- Procurement Management Plan 6- Issue Log
3- Cost Baseline
9- Stakeholder Management Plan 9- Change Log

10-Process Improvement Plan 10- OTHERS

11-Configuration management plan

12 - Requirements management plan

PROJECT INTEGRATION MANAGEMENT February 2016


Integration Management

“The processes and activities that integrate the various elements of project management”

To coordinate all aspects of the Project Management Plan in order to accomplish the project objectives

Develop Direct and Monitor and Perform


Develop Close
Project Manage Control Integrated
Project Project or
Management Project Project Change
Charter Phase
Plan Execution Work Control
The process of developing The process of The process of The process of The process of The process of
a document that formally documenting the performing the tracking, reviewing all finalizing all
authorizes a actions necessary to work defined in reviewing, and change requests, activities across all
project or a phase and define, prepare, the project regulating the approving of the Project
documenting initial integrate, and management progress to meet changes, and Management
requirements that satisfy coordinate all plan to achieve the performance managing changes Process Groups to
the stakeholder’s needs subsidiary plans. the project’s objectives to the deliverables, formally complete
and expectations. objectives. defined in the organizational the project or
project process assets, phase.
management project
plan. documents, and
the project
management plan.

PROJECT INTEGRATION MANAGEMENT February 2016


Develop Project Charter

“The process of developing a document that formally authorizes a project or a


phase and documenting initial requirements that satisfy the stakeholder’s needs
and expectations”

Tools and
Inputs Outputs
Techniques
1. Project statement of work 1. Expert judgment 1. Project charter
2. Business case 2. Facilitation techniques
3. Agreements
4. Enterprise environmental
factors
5. Organizational process
assets

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
1. Project statement of work
 Business need: An organization’s business need may be based on a market
demand, technological advance, legal requirement, or government regulation.
 Product scope description: This documents the characteristics of the product
that the project will be undertaken to create.
 Strategic plan: The strategic plan documents the organization’s strategic goals.
2. Business case
 The business case is created as a result of one or more of the following:
 Market demand
 Organizational need
 Customer request
 Technological advance
Legal requirement

3. Agreement
 Agreements are used to define initial intentions for a project.

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
4. Enterprise environmental factors
 Appears as an input into most planning processes.
 Can be anything external to your project that affects your project.
 The things that impact your project that are not part of the project itself, such as:
 Company's organizational structure
 Organization's values and work ethic
 Government standards, laws and regulations where the work is being performed
or where the product will be used
 The characteristics of project's stakeholders (their expectations and willingness
to accept risk)
 The overall state of the marketplace for the project
 Business infrastructure systems
 Personnel policies
 PMIS (Project Management Information Systems)

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
5. Organizational process assets

 Project managers have also been dealing with existing processes, procedures, and
historical information.

 These help the project benefit from past company experience. The PMBOK" Guide
calls these organizational process assets. The trick is to think of organizational
process assets as what they really are-processes, procedures, and historical
information.

 The following are some examples of organizational process assets.

 Processes, Procedures, and Policies.

 Corporate Knowledge Base

 Historical Information

 Lessons Learned.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES
1. Expert judgment
 Expert judgment is often used to assess the inputs used to develop the project charter.
 Such judgment and expertise is applied to any technical and management details during this
process.
 Such expertise is provided by any group or individual with specialized knowledge or training,
and is available from many sources, including:
 Other units within the organization,
 Consultants,
 Stakeholders, including customers or sponsors,
 Professional and technical associations,
 Industry groups,
 Subject matter experts, and
 Project management office (PMO).

2. Facilitation Techniques
 Facilitation techniques have broad application within project management processes and
guide the development of the project charter
 Brainstorming, conflict resolution, problem solving, and meeting management.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
1. Project charter

 The project charter is such an important document that project CAN NOT be started
without one.

 A project charter may be created by the project manager but is issued by


sponsor in the initiating process group.

 It is abroad enough so it does not NEED to change as the project progresses.

 It provides the following benefits:


 The project charter formally recognizes (authorizes) the
existence of the project.

 It gives the project manager authority to spend money and commit


corporate resource.

 The project charter provides the high – level requirements for the
project.

 It links the project to the ongoing work of the organization.


PROJECT INTEGRATION MANAGEMENT February 2016
OUTPUTS

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
 The main information in Project Charter:

 Project purpose or justification,

 Measurable project objectives and related success criteria,

 High-level requirements,

 High-level project description,

 High-level risks,

 Summary milestone schedule,

 Summary budget,

 Project approval requirements (what constitutes project success, who decides the
project is successful, and who signs off on the project),

 Assigned project manager, responsibility, and authority level, and

 Name and authority of the sponsor or other person(s) authorizing the project
charter.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
Project Charter

 Project Title and Description (what is the project?) The First Personal Assistant

 Project Manager Assigned and Authority Level (who is given authority to lead the
project, and can he l she determine, manage, and approve changes to budget, schedule,
staffing, etc.?)

 Business Case (Why is the project being done? On what financial or other basis can we
justify doing this project?)

 Resources Pre-assigned (How many or which resources will be provided?)

 Stakeholders (Who will affect or be affected by the project (influence the project), as known
to date?)

 Stakeholder Requirements AS Known (Requirements related to both project and


product scope).

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
Project Charter

 Product Description / Deliverables (What specific product deliverables are wanted


and what will be the end result of the project?)

 Measurable Project Objectives (How does the project tie into the organization’s
strategic goals? What project objectives support those goals? The objectives need to be
measurable and will depend on the defined priority of the project constraints.)

 Project Approval Requirements (What items need to be approved for the project, and
who will have sign-off? What designates success?)

 High-Level Project Risks (Potential threats and opportunities for the project).

Project Sponsor Authorizing This Project:

------------------------------------ -----------------------------------

PROJECT INTEGRATION MANAGEMENT February 2016


Develop Project Management Plan

“The process of documenting the actions necessary to define, prepare, integrate,


and coordinate all subsidiary plans”

Inputs Tools and Techniques Outputs


1. Project charter 1. Expert judgment 1. Project management plan
2. Outputs from planning 2. Facilitation techniques
processes
3. Enterprise environmental
factors
4. Organizational process assets

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
1. Project charter
2. Outputs from planning processes

 Outputs from many of the planning processes are integrated to create the project
management plan. Any baselines and subsidiary management plans that are an
output from other planning processes are inputs to this process.

 In addition, updates to these documents can necessitate updates to the project


management plan.
3. Enterprise environmental factors

 Governmental or industry standards,

 Project management information systems,

 Organizational structure and culture,

 Infrastructure and

 Personnel administration (e.g., hiring and firing guidelines, employee performance


reviews, and training records).
PROJECT INTEGRATION MANAGEMENT February 2016
INPUTS
4. Organizational process assets
 Standardized guidelines, work instructions, proposal evaluation criteria, and
performance measurement criteria,
 Project management plan template that may be updated include,
 Guidelines and criteria for tailoring the organization’s set of standard processes
to satisfy the specific needs of the project, and
 Project closure guidelines or requirements like the product validation and
acceptance criteria,
 Change control procedures including the steps by which official company
standards, policies, plans, and procedures, or any project documents will be
modified and how any changes will be approved and validated,
 Project files from past projects
 Historical information and lessons learned knowledge base.
 Configuration management knowledge base containing the versions and baselines
of all official company standards, policies, procedures, and any project documents.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES
1. Expert judgment

 Tailor the process to meet the project needs,

 Develop technical and management details to be included in the project


management plan,

 Determine resources and skill levels needed to perform project work,

 Define the level of configuration management to apply on the project,

 Determine which project documents will be subject to the formal change control
process.
2. Facilitation Techniques
 Facilitation techniques have broad application within project management
processes and guide the development of the project charter
 Brainstorming, conflict resolution, problem solving, and meeting management.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
1. Project Management Plan
 A project management plan is an integration function-it integrates all the knowledge
area management plans into a cohesive whole.
 The project manager creates the project management plan with inputs of the project
team.
 This plan includes the baselines for the project (Scope, Schedule, Cost) and also it
called performance measurement baselines.
 The project management plan includes:
 The project management processes that will be used on the project.
 Subsidiary plans for scope, schedule, cost, quality, human resources,
communications, risk, procurement, and stakeholders.
 A requirements management plan.
 A change management plan.
 A configuration management plan. Latest version!
 A process improvement plan.
PROJECT INTEGRATION MANAGEMENT February 2016
Direct and Manage Project Execution

“The process of performing the work defined in the project management plan to
achieve the project’s objectives”
Tools and
Inputs Outputs
Techniques
1. Project management plan 1. Expert judgment 1. Deliverables
2. Approved change requests 2. Project management 2. Work performance data
3. Enterprise environmental information system (PMIS) 3. Change requests
factors 3. Meetings 4. Project management plan
4. Organizational process assets updates
5. Project document updates

The key benefit of this process is that it provides overall management


of the project work.
work.
The project manager directs the performance of the planned project
activities..
activities

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
1. Project management plan

 Scope management plan

 Requirements management plan

 Schedule management plan

 Cost management plan

 Stakeholder management plan


2. Approved change requests

 As part of the Perform Integrated Change Control process, a change control status
update will indicate that some changes are approved and some are not.

 Scheduled for implementation by the project team.


 The documented, authorized changes to expand or reduce project scope.

 Can also modify policies, the project management plan, procedures,


costs, or budgets; or revise schedules.

 May require implementation of preventive or corrective actions.

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
3. Enterprise Environmental Factors
 Organizational, company or customer culture and structure.
 Infrastructure.
 Personnel administration
 Stakeholder risk tolerances.
 Project management information systems.

4. Organizational process assets


 Standardized guidelines and work instructions.
 Communication requirements.
 Issue and defect management procedures.
 Process measurement database.
 Project files from prior projects
 Issue and defect management database.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES
1. Expert judgment

 Such judgment and expertise is applied to all technical and management details
during this process.

2. Project management information system (PMIS)

 The system that helps you produce and keep track of the documents and
deliverables..
deliverables

 Example: a PMIS might help your organization produce the project charter by
having you fill in a few fields on a computer screen. It might then generate the
project charter and set up a project billing code with accounting.

 While the PMIS usually consists primarily of software, it will often interface with
manual systems.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES
3. Meetings

 Purpose: Discuss and address pertinent topics of the project when directing and
managing project work.

 Attendees:

1) Project manager,

2) Project team

3) Appropriate stakeholders involved or affected by the topics addressed.

 Types:

1) Information exchange

2) Brainstorming, option evaluation, or design

3) Decision making.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
1. Deliverables
 An approved deliverable is any unique and verifiable product, result, or
capability to perform a service that must be produced to complete a
process, phase, or project.

 Deliverables are produced as outputs from processes


performed to accomplish the project work as planned
and scheduled in the project management plan.

2. Work Performance Data


 The work performance data is collected and appropriately actioned and
communicated.
 Deliverable status,
 Schedule progress, and
 Costs incurred.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
 The work performance data is collected throughout the execution phase of the
project, and then it is sent to various controlling processes to analyze it further;
e.g. Validate Scope, Control Scope, Control Schedule, Control Cost, etc.
 In other words, it is the current (“as of now”) status of various project parameters
such as: how much work is completed, how much time has elapsed, the cost
incurred so far, etc.
 The work performance data is the raw observations and measurements
identified during activities performed to carry out the project work; e.g. actual cost,
actual duration, and percent of work physically completed, the raw data of the
project’s status

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
3. Change Requests
 Change request from customer (may be he needs to change the product features!).
 Corrective action.
 Preventive action.
 Defect repair.
 Updates: Changes to formally controlled documentation, plans, etc., to reflect
modified or additional ideas or content.

Corrective Action Preventive Action Defect Repair

 An intentional activity that  An intentional activity that  An intentional activity to


realigns the performance ensures the future modify a nonconforming
of the project work with the performance of the project product or product
project management plan. work is aligned with the component.

 Quality issue!!! project management plan.  Physical problems!!1


 To avoid problem in the
future!!!

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
4. Project Management Plan Updates
 Requirements management plan,
 Schedule management plan,
 Cost management plan,
 Quality management plan,
 Human resource plan,
 Communications management plan,
 Risk management plan,
 Procurement management plan, and
 Project baselines.
5. Project Document Updates
 Requirements documents,
 Project logs (issue, assumptions, etc.),
 Risk register, and
 Stakeholder register.
PROJECT INTEGRATION MANAGEMENT February 2016
Monitor and Control Project Work

“The process of tracking, reviewing, and regulating the progress to meet the
performance objectives defined in the project management plan”

Tools and
Inputs Outputs
Techniques
1. Project management plan 1. Expert judgment 1. Change requests
2. Schedule forecasts 2. Analytical techniques 2. Work performance reports
3. Cost forecasts 3. Project management 3. Project management plan
4. Validated changes information system (PMIS) updates
5. Work performance information 4. Meetings 4. Project documents updates
6. Enterprise environmental
factors
7. Organizational process assets
The key benefit of this process is that it allows stakeholders to understand the current state of
the project, the steps taken, and budget, schedule, and scope forecasts.

PROJECT INTEGRATION MANAGEMENT February 2016


Monitor and Control

Plan Actual
1. Monitors and controls deliverables/
processes to do with initiating, planning,
+/- Variance
executing and closing by comparing actual
performance against project plan.
Variance
2. Assesses corrective and preventive actions. analysis and
trend evaluation
3. Monitors the effectiveness of implementing
approved changes.
Project
Manager to Recommend and
You should know the variance or follow up the implement Corrective or
Implementation preventive Action
deviations from baselines are often due
to incomplete risk identification
1. Bring deviation under control
and risk management. 2. Decided if and when action is required
3. Make recommendations
4. Issue change request

PROJECT INTEGRATION MANAGEMENT February 2016


Monitor and Control

1. Comparing actual project performance against the project management plan.

2. Assessing performance.

3. Analyzing, tracking, and monitoring project risks.

4. Maintaining an accurate, timely information base concerning the project’s product(s).

5. Providing information to support status reporting, progress measurement, and

forecasting.

6. Providing forecasts to update current cost and current schedule information.

7. Monitoring implementation of approved changes when and as they occur.

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
1. Project Management Plan
 Baselines(Scope, Schedule, and Cost).
 Subsidiary plans within the project management plan form the basis for
controlling the project.
2. Schedule Forecasts
 The schedule forecasts are derived from progress against the schedule baseline
and computed time estimate to complete (ETC).
 This is typically expressed in terms of schedule variance (SV) and schedule
performance index (SPI).
3. Cost Forecasts
 The cost forecasts are derived from progress against the cost baseline and
computed estimates to complete (ETC).
 This is typically expressed in terms of cost variance (CV) and cost performance
index (CPI).

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
4. Validated Change

 Approved changes that result from the Perform Integrated Change Control
process require validation to ensure that the change was appropriately implemented.

 A validated change provides the necessary data to confirm that the change was
appropriately executed.

5. Work Performance Information

 Work performance information is the performance data collected from various


controlling processes, analyzed in context, and integrated based on relationships
across areas.

 Examples of performance information are


status of deliverables, implementation status
for change requests, and forecasted
estimates to complete.

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
6. Enterprise Environmental Factors

 Governmental or industry standards

 Company work authorization system

 Stakeholder risk tolerances

 Project management information systems

7. Organizational Process Assets

 Organization communication requirements

 Financial controls procedures

 Issue and defect management procedures

 Risk control procedures

 Process measurement database

 Lessons learned database.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES
1. Expert Judgment
 Expert judgment is used by the project management team to interpret the
information provided by the monitor and control processes.
 The project manager, in collaboration with the team, determines the actions
required to ensure project performance matches expectations.
2. Analytical Techniques
 Examples of analytical techniques used in projects are:
 Regression analysis,
 Grouping methods,
 Causal analysis,
 Root cause analysis,
 Forecasting methods (e.g., time series, scenario building, simulation, etc.),
 Failure mode and effect analysis (FMEA),
 Fault tree analysis (FTA),
 Reserve analysis,
 Trend analysis,
 Earned value management, and
 Variance analysis.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES
3. Project Management Information System
 The project management information system is part of enterprise environmental
factors.
 Provides access to automated tools, such as scheduling, cost, and resourcing tools,
performance indicators, databases, project records, and financials used during the
Monitor and Control Project Work process.
4. Meetings
 Attendees:
1) Project manager,
2) Project team
3) Appropriate stakeholders involved or affected by the topics addressed.
 Types:
1) User groups
2) Review Meetings.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
1. Change Requests
 Corrective action.
 Preventive action.
 Defect repair.

2. Work Performance Reports


 Work performance reports are the physical or electronic representation of work
performance information compiled in project documents, intended to generate
decisions, actions, or awareness.
 Project information may be communicated verbally
from person to person.
 Communicate project performance and status
information.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS

Work performance DATA, INFORMATION, and REPORT

Work performance data Work performance information


The “as of now” status of the project status,
A comparison between the actual
it provides the current status of the
performance with the planned performance.
project

Example: Cost Variance, Schedule Variance,


Example: The actual cost spent, actual time
Cost Performance Index, and Schedule
elapsed, etc.
Performance Index

Work performance Report


Give stakeholders the information on how the project is progressing in the form of well-
organized and summarized reports, at level of detail that they require

Example: Status reports, memos, justifications, information notes, recommendations, and


updates.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
3. Project Management Plan Updates
 Schedule management plan,
 Cost management plan,
 Quality management plan,
 Scope baseline,
 Schedule baseline, and
 Cost performance baseline.

4. Project Document Updates


 Forecasts,
 Performance reports, and
 Issue log.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS

PROJECT INTEGRATION MANAGEMENT February 2016


Perform Integrated Change Control

“The process of reviewing all change requests, approving changes, and


managing changes to the deliverables, organizational process assets, project
documents, and the project management plan”

Tools and
Inputs Outputs
Techniques
1. Project management plan 1. Expert judgment 1. Approved change requests
2. Work performance reports 2. Meetings 2. Change log
3. Change requests 3. Change control tools 3. Project management plan
4. Enterprise environmental updates
factors 4. Project document updates
5. Organizational process assets

The key benefit of this process is that it allows for documented changes within the project to be
considered in an integrated fashion while reducing project risk, which often arises from
changes made without consideration to the overall project objectives or plans.
PROJECT INTEGRATION MANAGEMENT February 2016
Change Control
Change management Activities
1. Influencing the factors that circumvent integrated change control so that ONLY
approved changes are implemented;
2. Reviewing, analyzing, and approving change requests promptly, which is
essential, as a slow decision may negatively affect time, cost, or the feasibility of
a change;
3. Managing the approved changes;
4. Maintaining the integrity of baselines by releasing only approved changes for
incorporation into the project management plan and project documents;
5. Reviewing, approving, or denying all
recommended corrective and preventive
actions;
6. Coordinating changes across the entire project
(e.g., a proposed schedule change will often
affect cost, risk, quality, and staffing); and
7. Documenting the complete impact of change
requests.
PROJECT INTEGRATION MANAGEMENT February 2016
Change Control

Configuration management activities

 Configuration identification

 Configuration status accounting.

 Configuration verification and audit.

PROJECT INTEGRATION MANAGEMENT February 2016


Change Control
Project Management Information System (PMIS)
 An information system consisting of the tools
and techniques used to gather, integrate, and
disseminate the outputs of project management
processes.
 It is used to support all aspects of the project
from initiating through closing, and can include
both manual and automated systems.
 The system that helps you produce and keep track of the documents and
deliverables.
 Example: a PMIS might help your organization produce the project charter by having
you fill in a few fields on a computer screen. It might then generate the project
charter and set up a project billing code with accounting.
 While the PMIS usually consists primarily of software, it will often interface with
manual systems.

PROJECT INTEGRATION MANAGEMENT February 2016


Change Control
Configuration Management System
 A subsystem of the overall project
management system.
 It is a collection of formal documented
procedures used to apply technical and
administrative direction and surveillance
to: identify and document the functional
and physical characteristics of a product,
result, service, or component; control any
 It includes the documentation,
changes to such characteristics; record
tracking systems, and defined
and report each change and its
approval levels necessary for
implementation status; and support the
authorizing and controlling changes.
audit of the products, results, or
components to verify conformance to
requirements.
PROJECT INTEGRATION MANAGEMENT February 2016
Change Control
Change Control System

 A collection of formal documented procedures

that define how project deliverables and

documentation will be controlled, changed, and

approved.

 In most application areas, the change control

system is a subset of the configuration

management system.

 Change Control system is part of Enterprise

Environmental Factors (internal) on a

project.

PROJECT INTEGRATION MANAGEMENT February 2016


Change Control

Change Management System Configuration Management System


Comprised of several components that
guide the change request through the The evaluates the change request and
process. documents the features and functions of the
When a change request is made that will change on the project scope
affect the project scope.

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
1. Project management plan
 Changes are documented and updated within the project management plan as part
of the change and configuration management processes.
2. Work performance reports
 Work performance reports of particular interest to the Perform Integrated Change
 Control process include resource availability, schedule and cost data, and earned
value management (EVM) reports.
3. Change requests
 All of the monitoring and control processes and many of the executing processes
produce change requests as an output.
 Change requests can include corrective action, preventive action, and defect
repairs. However, corrective and preventive actions do not normally affect the
project baselines, only the performance against the baselines.
4. Enterprise environmental factors
 Project management information system.
PROJECT INTEGRATION MANAGEMENT February 2016
INPUTS
5. Organizational process assets

 Change control procedures, including the steps by which official company

standards, policies, plans, and other project documents will be modified, and how

any changes will be approved, validated, and implemented;

 Procedures for approving and issuing change authorizations;

 Process measurement database used to collect and make available measurement

data on processes and products;

 Project files.

 Configuration management knowledge base containing the versions and baselines

of all official company standards, policies, procedures, and any project documents.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES
1. Expert judgment
 In addition to the project management team’s expert judgment, stakeholders may
be asked to provide their expertise and may be asked to sit on the change control
board.
 Such judgment and expertise is applied to any technical and management details
during this process and may be provided by various sources.
2. Meetings
 A change control board is responsible for meeting and reviewing the change
requests and approving or rejecting those change requests.
 The roles and responsibilities of these boards are
clearly defined and are agreed upon by
appropriate stakeholders.
 All change control board decisions are
documented and communicated to the
stakeholders for information and follow-up actions.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES

3. Change Control Tools


 The roles and responsibilities of these boards are clearly defined and are agreed
upon by appropriate stakeholders.
 In order to facilitate configuration and change management, manual or automated
tools may be used.
 Tool selection should be based on the needs of the project stakeholders including
organizational and environmental considerations and/or constraints.
 Tools are used to manage the change requests and the resulting decisions.
 Additional considerations should be made for communication to assist the CCB
members in their duties as well as distribute the decisions to the
 appropriate stakeholders.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
1. Approved change request
 Change requests are processed according to the change control system by the project
manager or by an assigned team member.
 Approved change requests will be implemented by the Direct and Manage Project
Execution process.
 The status of all changes, approved or not, will be updated in the change request log
as part of the project document updates.
2. Change log
 A change log is used to document changes that occur during a project.
 These changes and their impact to the project in terms of time, cost, and risk, are
communicated to the appropriate stakeholders.
 Rejected change requests are also captured in the change log.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
3. Project management plan updates
 Elements of the project management plan that may be updated include but are not
limited to:
 Any subsidiary management plans, and
 Baselines that are subject to the formal change control process.
 Changes to baselines should only show the changes from the current time forward.
Past performance may not be changed. This protects the integrity of the baselines
and the historical data of past performance.
4. Project document updates
 Project documents that may be updated as a result of the Perform Integrated Change
Control process include the change request log and any documents that are subject to
the formal change control process.

PROJECT INTEGRATION MANAGEMENT February 2016


Close Project or Phase Control

“The process of finalizing all activities across all of the Project Management
Process Groups to formally complete the project or phase”

Tools and
Inputs Outputs
Techniques
1. Project management plan 1. Expert judgment 1. Final product, service, or
2. Accepted deliverables 2. Analytical techniques result transition
3. Organizational process assets 3. Meetings 2. Organizational process
assets updates

PROJECT INTEGRATION MANAGEMENT February 2016


INPUTS
1. Project management plan

 The project management plan becomes the agreement between the project

manager and project sponsor, defining what constitutes project completion.

2. Accepted deliverables

 Accepted deliverables may include approved product specifications, delivery

receipts, and work performance documents.

 Partial or interim deliverables may also be included for phased or cancelled

projects.

3. Organizational process assets

 Project or phase closure guidelines or requirements.

 Historical information and lessons learned knowledge base.

PROJECT INTEGRATION MANAGEMENT February 2016


TOOLS AND TECHNIQUES
1. Expert judgment
 Expert judgment is applied when performing administrative closure activities. These
experts ensure the project or phase closure is performed to the appropriate
standards.
2. Analytical Techniques
 Regression analysis.
 Trend analysis.
3. Meetings
 Meetings may be face-to-face, virtual, formal, or informal. This may include project
team members and other stakeholders, involved in or affected by the project.
 Types of meetings include, lessons learned, closeout, user group, and review
meetings.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
1. Final product, service, or result transition
 Formal acceptance and handover of the final product/service.
 Includes receiving a formal statement that the terms of the contract have been met.

2. Organizational process assets updates


 Project files.
 Documentation resulting from the project’s activities, for example, project
management plan, scope, cost, schedule and project calendars, risk registers,
change management documentation, planned risk response actions, and risk impact.
 Project or phase closure documents.
 Formal documentation that indicates completion of the project or phase and the
transfer of the completed project or phase deliverables to others, such as an
operations group or to the next phase.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
 During project closure the project manager reviews prior phase documentation,
customer acceptance documentation from the Verify Scope process and the
contract, to ensure that all project requirements are complete prior to finalizing the
closure of the project.
 If the project was terminated prior to completion, the formal documentation
indicates why the project was terminated and formalizes the procedures for the
transfer of the finished and unfinished deliverables of the cancelled project to
others.
 Historical information
 Historical information and lessons learned information are transferred to the lessons
learned knowledge base for use by future projects or phases.
 This can include information on issues and risks as well as techniques that worked
well that can be applied to future projects.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
Administrative closure

1. Deliverable Turnover—Verification and Acceptance. In this step, deliverables are reviewed


and tested against previously determined requirements and are accepted by the customer with a formal sign-
off.

2. Post completion Data. In this step, you determine any variances in the schedule, cost (personnel and
expenses), and scope (deliverables and requirements).

3. Follow-Up Maintenance and Warranties. If applicable, hand off any hardware, software, or
other equipment and review the coverage on warranties and the maintenance requirements.

4. Team Member Performance Reporting. The project manager provides information to functional
management on the performance of project team members during the life of the project.

5. Financials. Ensure that all expenses are paid and project budgets are closed. Generate the necessary
financial reports.

6. Releasing Staff. Ensure a smooth transition for all staff to new assignments. Notify functional managers
with sufficient lead time so that meaningful work assignments can be made.

7. Formal Closing Report. Prepare a summary of the information above, including any open issues, and
distribute it to appropriate stakeholders.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
Contractual Closure

1. Turnover of deliverables and all necessary supporting documentation

2. Verification of work and deliverables

3. Formal acceptance of deliverables per previously defined requirements

4. Audit to document performance

5. Final documentation that the contract is complete

6. Final payment

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS

Project
Procurement
Phase is
is complete
complete

Project or
Project is
procurement
complete
Closing is terminated
Conduct Close-Out Meeting Process
Group

Share Lesson Learned Evaluate Success

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS
Close-Out Meeting AGENDA

1. Review project statement of work.

2. Review actual deliverables and show how project met its measurable success
indicators.

3. Summarize what was done well.

4. Identify areas for improvement.

5. Request recommendations for improvement.

6. Determine if any additional tasks are required to complete the project.

7. List additional tasks, responsible persons, and due date.

8. Document lessons learned for the project notebook.

9. Discuss the project notebook availability to appropriate personnel for


future projects.

10. Evaluate subcontractor performance.


PROJECT INTEGRATION MANAGEMENT February 2016
OUTPUTS

Informal Project Team Close-Out Meeting

1. Brainstorm to identify what went right with the project.

2. Brainstorm to identify what went wrong with the project.

3. List ideas for improvements.

4. List ideas for ensuring that what went right happens again.

5. Recognize the accomplishments of individuals.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS

Project Manager’s Role during the project Close-Out

1. Ensure that all project deliverables have been completed and formally accepted

by the customer.

2. Determine if the measurable success indicators were achieved.

3. Conduct project close-out meetings, both internal and external.

4. Write the final project report.

5. Document and share lessons learned.

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS

Sharing LESSON LEARNED

1. Lessons Learned Database

 Categorized electronic project information database

2. Continuous Improvement Recommendations

 Project Management Process

 Forms

 Standards

PROJECT INTEGRATION MANAGEMENT February 2016


OUTPUTS

Evaluation Project SCUCCESS

1. Project purpose

2. Deliverables

3. Measurable success indicators

 Quality

 Schedule

 Cost

PROJECT INTEGRATION MANAGEMENT February 2016


REMEMBER
1. The meaning of control that is important to project managers is the one that concerns
the use of information, comparing actual progress to the plan so that action can be taken
to correct for deviations from plan.

2. The only way a project is really in control is if all team members are in control of
their own work.

3. The effort used to control a project should be worthwhile. You don’t want to spend
$100 to purchase a $3 battery.

4. If you take no action in response to a deviation, you have a monitoring system, not
a control system.

5. Project working times must be recorded daily. If people wait a week to capture what they
have done, they rely on memory and end up writing down estimates of what they did.
Such data are no good for future estimating.

6. Project evaluation is done to determine whether a project should continue or be canceled.


Process reviews also should help the team learn in order to improve performance.

PROJECT INTEGRATION MANAGEMENT February 2016


REMEMBER
1. Change must be controlled and communicated.

2. Understanding and identifying likely sources of change assists you in remaining


proactive.

3. Typical sources of change are scope, schedule, and budget adjustments.

4. It is crucial to keep the baseline plan current.

5. The six common steps you will take in a typical change control process are to enter the
initial change control information into your change control log 1; determine if the change
should be processed 2; submit recommendations to management and/or the customer for
review and approval 3; update the project plan; distribute the updated plan 4; and
monitor the change 5 and track progress against the revised plan 6.

6. The change control form and log are your primary controlling documents.

7. Thresholds should be established when determining your response to project change.

8. Project spin-off usually occurs when the project change is so dramatic that you and your
team determine that an entirely separate project should be initiated.
PROJECT INTEGRATION MANAGEMENT February 2016
REMEMBER
9. Work Authorization System

 A collection of formal documented procedures that defines how project work will be
authorized to ensure the work is done by the identified organization, at the right
time, and in the proper sequence.

 A formal procedure for sanctioning project work.

 When I should start the work I’ve been assigned.

10. Integration is done by project manager.

11. Effective integration requires effective communication.

PROJECT INTEGRATION MANAGEMENT February 2016


Refreshments
Q1: Effective project integration usually requires an emphasis on:

A. The personal careers of the team members.

B. Timely updates to the project management plan.

C. Effective communications at key interface points.

D. Product control.

Q2: The need for ------------ is one of the major driving forces for communication in a project.

A. Optimization

B. Integrity

C. Integration

D. Differentiation

PROJECT INTEGRATION MANAGEMENT February 2016


Refreshments
Q3: All of the following are parts of an effective change management plan EXCEPT:

A. Procedures

B. Standards for reports

C. Meetings

D. Lessons learned

PROJECT INTEGRATION MANAGEMENT February 2016


Refreshments
Q4: A work authorization system can be used to:

A. Manage who does each activity.

B. Manage what time and in what sequence work is done.

C. Manage when each activity is done.

D. Manage who does each activity and when it is done.

PROJECT INTEGRATION MANAGEMENT February 2016


Refreshments
Q5: The project charter for a project was approved for planning and you have just been
assigned as project manager. Realizing that project planning is an ongoing effort throughout
the project, which processes are you MOST likely to combine?

A. Create WBS and Define Activities

B. Estimate Activity Durations and Develop Schedule

C. Develop Human Resource Plan and Estimate Costs

D. Estimate Costs and Determine Budget

PROJECT INTEGRATION MANAGEMENT February 2016


THANK YOU

PROJECT INTEGRATION MANAGEMENT February 2016

Das könnte Ihnen auch gefallen