Beruflich Dokumente
Kultur Dokumente
Table of Contents
Contents Page
Page 2 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 3 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
1.0 SCOPE
This specification gives minimum requirements for the design, material, fabrication, installation and
application of thermal insulation of aboveground surfaces of piping, equipment, instruments, etc.
External acoustic insulation of pipes, valves and flanges shall be executed in accordance with ISO
15665 and this specification.
In case of varying requirements between Licensor’s specification and this specification, the most
stringent requirements shall be applicable.
1.1 DEFINITIONS
For this specification the following definitions are applicable.
2.0 OBLIGATIONS/RESPONSIBILITIES
All insulation shall comply with this specification. All deviations shall be approved by Client or its
delegate.
3.0 GENERAL
3.1 EXCLUSIONS
Excluded from this specification are:
• Insulation of heating ventilation and air-conditioning installations.
• Building insulation.
• Internal lining of furnaces and other equipment.
• Fireproofing of structural steel and piping/equipment supports.
Page 4 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 5 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 6 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 7 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
4.3.4 Insulation codes are used on the engineering documents to indicate which type of insulation shall be
applied (see subsection 3.3).
6.0 MATERIALS
6.1 GENERAL
All materials shall be new, free of damage and in conformity with this specification.
All insulation materials shall be asbestos free, nonflammable and non-corrosive whether dry or wet.
Ceramic fibres shall not be used.
Insulation, fastening and sheeting material shall not contain zinc, when applied on stainless-steel
surfaces. The materials and their packing shall be clearly identified, to prevent interchanging of
insulation materials for stainless application and for carbon/low/medium alloy steel application,
Materials deviating from this specification shall not be used without written prior approval from Client.
Insulation materials shall be supplied completely dry, suitably protected from the weather and stored in
a dry warehouse.
Field stock shall only be allowed in designated areas for a maximum of two (2) working days. No
intermediate storage within the work area is allowed.
Insulation material shall be kept completely dry during application. If insulation work is temporarily
stopped because of bad weather conditions and/or end of normal working hours, insulated equipment
or piping which are not yet finished shall be suitably protected to prevent ingress of water or other
foreign matters into the insulation material.
The chlorine contents of insulation materials for piping and equipment made of austenitic stainless
steel shall be complied with ASTM C795 by conforming to the pre-production test requirements of
ASTM C692 and the confirming quality requirements for chemical analysis of ASTM C871.
6.2.1 Rockwool Preformed Pipe Sections (For pipe sections < 14”)
Reference code ASTM C547.
Page 8 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Preformed rigid foam pipe sections manufactured from resin bonded rockwool.
Pipe sections shall be split and hinged for easy assembly.
Maximum chloride content according to ASTM C871: 10 mg/kg.
The pH value shall be between 6 and 9.
3
Minimum density: 100-125 kg/ m (depending on the thickness).
Thermal conductivity as per table I.
Suitable for a maximum temperature of 600°C.
For acoustic insulation application, the preformed pipe sections shall have a density as specified
above. For additional material requirements refer to section 10.
6.2.2 Cellular Glass Preformed Pipe Sections (Ref. Chapter 8.12 - Hot Oil Systems)
Inorganic cellular glass preformed rigid pipe sections or radiused and bevelled slabs.
Maximum chloride content: 10 mg/kg.
The maximum pH value shall be 10.
3
Minimum density: 115 kg/m .
Thermal conductivity [W/mK]: 0.034 at -20°C; 0.036 at 0°C; 0.040 at +20°C.
Temperature limits: -260°C through 430°C.
The average compressibility: 500 kPa.
Page 9 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 10 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Maximum thermal conductivity [W/mK]: at 20°C freshly blown: 0.020 and after 6 month
ageing 0.023.
Temperature limits: -200°C through +120°C.
Maximum chloride content (ASTM C871: 60 mg/kg).
The pH value shall be between 6 and 9.
Water absorption (ASTM D 2842): Max. 5 vol. %.
3
Minimum density (ASTM D 1622): 40 kg/m .
Compressive strength (ASTM D 1621): Min. 200 kPa and 250 kPa at 10% deformation at
20°C.
Page 11 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 12 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
a. Synthetic and natural rubber (suitable for the applicable operating temperature).
b. Nonflammable felt.
c. Mineral wool as per paragraphs 6.2.1 when operating temperature of the pipe is above the
maximum allowable temperature of the rubber or felt.
Insulation shall be applied in the minimum number of layers as obtainable in commercially available
thickness nearest to the specified thickness. The number of layers for cold insulation shall be as
indicated on table VII.
Insulation thickness applied shall never be less than the thickness specified in the relevant documents.
Insulation applied in two or more layers shall have staggered joints. When insulation support rings and
mineral wool blankets are used, circumferential joints at the support rings cannot be staggered.
Each layer of insulation material shall be secured separately with binding wire, strapping band or
filament tape.
The normal operating temperature is the basis for selection of insulation thickness for heat
conservation and personnel protection. For compressors and exchangers use the higher of the inlet or
of the outlet temperatures.
The spacing of contraction joints for cold insulation shall be applied as indicated in table VIII.
Page 13 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Valves and flanges on insulated steam supply exhaust and condensate lines shall be insulated.
Valves and flanges and equipment nozzles in hot oil piping system shall be insulated. Special attention
shall be paid to the insulation details to prevent leaking product entering the insulation. Drainage
outlets shall be provided to give visible identification of a possible valve/flange leak (refer to subsection
8.12).
Valves and flanges in piping systems with acoustic insulation requirement class B and class C shall be
insulated. Same is applicable for the equipment nozzles if the equipment requires an acoustic
insulation.
• Manholes (including davits) and hand holes, for temperatures less than 275°C.
Notes: Manholes, etc. of equipment with acoustic insulation requirement classes B and classes
C, shall be insulated.
• Channel covers operating below 100°C.
• Untraced branches from traced lines downstream of the first block valve.
• Drain and vent piping on insulated equipment downstream of the first block valve (do not
insulate block valve).
• Pumps and Compressors (unless specifically specified, e.g. for noise insulation).
• Nameplates which indicate design and/or operating data and warnings.
• Flanges and flanged valves for hydrogen service shall never be insulated.
8.2.1 General
8.2.1.1 For the application of insulation blankets, the blankets with galvanized wire mesh shall not
be used on stainless-steel surfaces. For stainless-steel surfaces only blankets with
stainless-steel wire mesh shall be applied.
8.2.1.2 Mineral wool preformed pipe sections shall be used for piping less than 14”. The option for
usage of mineral wool blankets shall be applicable for piping 14” & above.
8.2.1.3 To prevent damage to insulation at flanges, equipment nozzles, valves, instruments, etc., a
distance shall be maintained between the insulation and the flanges, thus allowing free
removal of flange bolts and nuts (see figure 13.3 - distance = bolt length + 30 mm).
Blankets shall be cut to a length equal to the circumference of the pipe plus two (2) times
the insulation thickness.
Blankets shall be wrapped around the pipe with wire mesh on the outside. Blankets shall be
close fitted to the pipe and to each other, all fitted in between support rings (if applied).
For fastening of mineral wool metal mesh blankets, the longitudinal and circumferential
joints shall be tacked with a stainless steel wire (diameter 1 mm) or stainless steel blanket
hooks at a pitch of 50 mm.
Blankets shall not be compressed more than 3 mm by the stainless-steel wires.
For vertical piping with more than one (1) insulation layer, the wire mesh of each blanket
shall be fastened to the upper support ring.
Page 15 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
8.4.1 General
Flanged connections and valves to be insulated (see notes paragraph 8.1) shall be insulated with
enclosures manufactured from aluminum or aluminized steel plate as per subsection 6.5 (see figure
13.9).
Enclosures shall consist of maximum two parts. Parts shall be attached to each other with overlapping
seams such that no water can enter the insulation material. If not possible, seams shall be sealed with
silicon rubber.
The stuffing box gland of all insulated valves shall be kept outside the insulation enclosure.
Page 16 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Top of vertically mounted enclosures shall be executed with a conical cover with edges overlapping the
body of the enclosure. The overlapping edge execution is also applicable for the top of horizontally
mounted valve enclosures.
Both ends of each enclosure shall be mounted over the adjacent piping insulation sheeting.
All sheeting segments of the enclosures shall be attached to each other with overlapping edges and
self-tapping screws as per paragraph 6.4.3.
All seams between metal parts of the enclosure and between the enclosure and the adjacent piping
sheeting shall be sealed with silicon rubber.
Enclosures shall be lined internally with mineral wool blankets or slabs as per paragraphs 6.2.3, 6.2.4.
Blankets shall be cut to the correct size and attached to the inside of the enclosures with clips as
shown in figure 13.12, detail "A". Wire mesh of all blankets shall face the object to be insulated. Clips
shall be screwed to the sheeting of the enclosures.
Total insulation thickness shall be equal to the insulation thickness of the adjacent piping.
Page 17 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Insulation slabs shall be secured with strapping bands as per paragraph 6.4.2 at intervals of 500 mm
and 50 mm from the edge of each slab.
Strapping bands shall be provided with expansion elements where necessary due to equipment
expansion.
Stiffeners, rings, girders, etc. attached to insulated towers, vessels, heat exchangers, etc., shall, unless
otherwise indicated, be insulated with the same insulation materials as for the equipment concerned.
8.6.1 Execution
Insulated surfaces shall be covered with metal sheets as per subsection 6.5. Longitudinal seams shall
be staggered.
For heads and stiffeners, sheeting shall be cut in segments and formed to fit closely to the head or
stiffener.
To prevent ingress of water, sheeting shall be mounted with an overlap of 50 mm minimum at all
seams. Edges of all sheets shall be furrowed. To accommodate the overlap of the adjacent top sheets
the vertical furrow of each sheet shall be flattened over a length of 50 mm.
Sheeting shall be fastened with self-tapping screws as per paragraph 6.4.3 at minimum intervals of 150
mm.
At least one expansion seam per 10 meters or in between two (2) sheeting supports shall be provided.
Expansion seams shall be provided with two (2) furrows and an overlap of at least 100 mm. Sheeting
shall be fastened with a stainless-steel band mounted next to the second furrow (see figure 13.14).
Page 18 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Inside closed vessel skirts, the insulated equipment heads and skirt insulation do not require metal
sheeting (weather proofing). The insulated bottom nozzle shall be provided with metal sheeting up to
the bottom head insulation (see figure 13.11).
Flange boxes (as required) shall be screwed on top of the vessel sheeting with self-tapping screws and
all seams shall be sealed with silicon rubber compound.
8.7 INSULATING CAPS FOR EQUIPMENT HEADS, MANHOLES, HAND HOLES, ETC.
Heads of columns and vessels with a diameter up to 1000 mm, heads of heat exchangers, manholes,
hand holes, etc. shall be insulated as per the relevant details.
Seams shall have an overlap of 50 mm and shall be sealed with silicon rubber compound.
Caps shall be internally lined with mineral wool blankets or slabs as per paragraph 6.2.3, 6.2.4.
Blankets shall be cut to the correct size and pressed against the wall of the cap with wire mesh facing
the object to be insulated. Blankets shall be fastened with clips (see figure 13.12, detail "A") screwed to
the sheeting of the cap. Total insulation thickness shall be equal to the insulation thickness specified for
the equipment.
As applicable (refer to paragraph 8.1.2), caps for manholes, handholes, etc. shall be attached to the
equipment sheeting by means of a 25 mm wide flange rim attached to the open end of the cap (see
figure 13.12).
Where applicable, davits for manholes shall also be insulated by the removable cap.
8.8 INSTRUMENTS
8.8.1 Transmitters
Transmitters, which are to be insulated, shall be provided with standard prefabricated boxes as per the
project instrumentation specification and supplied by the transmitter manufacturer.
8.9 MACHINERY
Where specified, Machinery shall be insulated as per figure 14.25. The "heat insulation" may be read
as acoustic insulation. The insulation thickness shall be in accordance with the recommendations or
specifications of the machinery Seller.
Large machinery surfaces shall be insulated with panels or sectional insulation.
Insulation shall be applied in removable metal-jacketed sections as required for inspection or
maintenance of the equipment. The jacketed sections shall permit removal and replacement with
minimum insulation damage.
8.10.1 Scope
Non-insulated equipment and piping or parts there of whose surface temperature are 65°C or higher
and that are within personnel reach, shall be screened or insulated so that the contact temperature is
lower than 65°C.
At least the following items shall be provided with personnel protection:
• Equipment and pipelines located aboveground or passing through floors or platforms; these
latter shall be shielded or insulated to a height of at least 2 m above the floor or platform.
• Equipment and piping near a staircase, platform, manhole, ladder, etc., if the distance is 600
mm or less.
• Piping connected to manually operated valves, 2 meter on either side.
Flanges, valves, pumps, air coolers header boxes, manholes and hand holes do not require insulation
for personnel protection.
Where the above methods are impractical (e.g. header boxes for air coolers, external
surfaces of heaters, furnaces), warning signs shall be placed with written consent of USER.
Warning signs shall be judiciously located and shall be of sufficient size.
8.11.1 Piping
For insulation with blankets on horizontal piping, clamped support rings shall be attached to the piping
at intervals of 1 m to support the sheeting and to prevent compression of the blanket insulation. For
preformed sections on horizontal piping, no support rings are required.
The weight of the insulation on vertical and inclined (with angle between 45° and 90°) pipelines and
with a total insulated diameter larger than 350 mm, shall be carried by support rings, clamped around
the pipeline with an intermediate distance of 3800 mm for blankets and 5700 mm for sections. A
support ring shall also be mounted above every flange connection.
Support rings shall be as per section 6.3 (see figure 14.2).
Support ring shall be clamped around piping with an asbestos free gasket or glass fabric between the
support ring and the pipe.
8.11.2 Vessels
8.11.2.1 Banding
Expansion springs shall be provided for banding on vessels over 4.5 m in diameter and
operating above 300°C. A minimum of two (2) springs shall be used 180 degrees apart. For
each additional 7.5 m of circumference, one (1) additional spring shall be installed. Springs
shall be equally spaced around banding.
8.11.2.2 Vertical Vessels
For vertical vessels, welded-on support clips will be provided by the vessel Seller (see
standard equipment drawings 04-3230-01-Sheet 052 - 2 sheets).
The weight of the insulation shall be carried by support rings (supplied by Insulation Sub-
Contractor) clamped around the vessel (see section 6.3 and figure 14.2).
8.11.2.3 Horizontal Vessels
For the application of slabs or preformed sections, no insulation supports are required,
unless otherwise specified on the datasheets.
Page 21 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
9.1 GENERAL
Demountable parts shall have lifting lugs, if their mass exceeds 25 kg (e.g. valve and flange boxes or
other parts of insulation which may be removed during maintenance activities).
The execution of insulation and its sheeting shall be self-draining, preventing collection of water on or
inside the insulation.
A primary and secondary vapour barrier shall be applied on the outer layer and the next inner layer of
the insulation.
Page 22 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Note: As an alternative the outer mastic with reinforcement, sealing can be applied by mechanical (or corrosion)
protection tape (Scotchrap™ 52 or equal).
At field installation the joints with the adjacent preformed pipe sections shall be (made) close butted
and full glued with joint adhesive.
Pipe supports and other metal parts welded or clamped to cold insulated pipes or equipment protruding
through the normal insulation shall be cold insulated for a distance of four (4) times the pipe insulation
thickness with a minimum of 100 mm.
Page 24 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
For insulation diameters larger than 3500 mm, stainless steel banding shall be used per
paragraph 4.4.2 at intervals of maximum 300 mm. As a minimum each slab shall be fastened with two
stainless-steel bands.
9.7 INSTRUMENTS
9.7.1 Transmitters
Transmitters, which are to be insulated, shall be insulated with special boxes.
Page 25 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
10.1 GENERAL
The installation requirements for heat insulation as presented in section 6 of this specification also
apply to acoustic insulation with the following additions/exceptions.
For noise insulation the insulation material shall have a density between 65 (50 for class A insulation)
3 4
and 150 kg/m and a flow resistivity of 25000-75000 Ns/m
An essential feature of acoustic insulation is that the sheeting shall not be in direct or indirect metal to
metal contact with the pipe. Any such contact will allow a transmission of vibrations to the cladding,
which will reduce or nullify the noise reduction of the insulation; it may even enhance the noise
radiation, because of the greater surface area of the sheeting.
To prevent metal to metal contact with the pipe support, rings shall contain resilient elements and
contact between sheeting and pipe shall be avoided by anti-vibration seals.
Resilient elements shall not be pre-stressed or pre-tensioned to the extent that their operational range
of deflections is exceeded.
The sheeting shall be completely sealed by design or by application of silicon rubber compound to
prevent flanking noise.
Gaps between the sound absorbing materials along the pipe shall be avoided. The material shall be
fixed properly in vertical systems to avoid collapsing of the blankets due to vibrations or thermal
expansions.
Class A:
Flanges and valves need not be insulated for acoustic insulation in class A, unless acoustic insulation
is combined with thermal insulation for which the requirements of subsections 8.4 and 9.3.7 are
applicable.
Class B:
Distance and support rings shall be avoided if possible. Where used they shall conform to
paragraphs 10.3 and 6.4.6 and figure 13.21.
All flanges and valves shall be insulated to the same class as the pipe. Pipe supports shall be insulated
up to the concrete or steel base (see figure 13.18).
Class C:
Distance and support rings shall be avoided if possible. Where used they shall conform to
paragraphs 10.3 and 6.4.6 and figure 13.21.
All flanges and valves shall be insulated to the same class as the pipe. Pipe supports shall be insulated
up to the concrete or steel base (see figure 13.18). Where a steel structure is used as a base, it shall
also be insulated, if there is no vibration isolation between steel structure and pipe.
Page 26 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Dc dr M
k < ------------ x C (N/m)
n
In which:
2
M = Mass per unit area of the cladding, kg/m .
n = Number of resistant elements in one distance ring (> 3).
dr= Distance between distance rings, m.
Dc = Diameter of cladding, m.
2
C = Deflection factor, 1/s .
The resilient elements shall have a built-in mechanical stop, in the direction normal to the pipe axis, in
order to limit its maximum deflection (see figure 14.21).
Support rings (see figure 14.23) which carry the weight of vertical stretches of acoustic insulation shall
contain resilient elements. The spring stiffness in vertical (= axial) direction k, in N/m of a single
element should be of the order:
Dc dr M
k < ----------- x C (N/m)
2n
Spring stiffness in lateral directions should be in the range as given for support rings in horizontal
piping, where possible.
Resilient elements for support rings in vertical piping have both axial and lateral mechanical stops, to
limit movements of the insulation, (even) when the resilient element fails.
Commercially available anti-vibration mountings should be used wherever possible. Where the
operating temperatures prohibit the use of natural or synthetic rubber as resilient material, other
materials should be used instead; for example, steel springs in the form of a folded band or knitted
metal.
Page 27 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
10.4 SHEETING
The minimum mass per unit area of the sheeting and the related thickness shall be in accordance with
tables II and VI for the class of insulation considered.
Page 28 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 29 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
TABLE I
THERMAL CONDUCTIVITY MINERAL WOOL (W/mK)
PARAGRAPH 6.2.1
PARAGRAPH 6.2.4
PARAGRAPH 6.2.7
PARAGRAPH 6.2.8
PARAGAPH 6.2.5
(COMPRESSION
PIPE SECTIONS
TEMPERATURE
BOILER SLABS
LOOSE WOOL
RESISTANT)
BLANKETS
AVERAGE
SLABS
(°C)
Page 30 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
TABLE II
MINIMUM THICKNESS OF INSULATION SHEETING (mm)
Page 31 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
TABLE III
MINIMUM INSULATION THICKNESS TABLE FOR HOT SERVICE (mm) – (IH)
Based on application of mineral wool
(mm)
PIPE
NORMAL OPERATING TEMPERATURE (°C)
DIAMETER
NPS
(mm) 100 150 200 250 300 350 400 450 500 550 600 650
(inch)
1” 33.4 25 25 25 40 40 50 65 65 75 75 90 115
Note :
(1) Thickness tables calculated using 3E PLUS Insulation Thickness Computer Program Ver 3.0.
(2) Multiple layers shall be provided for thickness above 80 mm.
Page 32 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
TABLE IV
INSULATION THICKNESS TABLE FOR PERSONNEL PROTECTION (PP)
SHIELDING INSULATION
Insulation code P Insulation code PI
NORMAL OPERATING TEMPERATURE °C
Insulation Thickness in mm
< 1½ 50 40 50 65
2 50 40 50 75
3 50 40 65 75
4 50 40 65 75
6 50 50 65 90
8 50 50 65 90
10 100 50 65 100
12 100 50 75 100
14 100 50 75 100
16 100 50 75 100
18 100 50 75 115
20 100 50 75 115
24 100 50 75 115
28 100 50 75 115
30 100 65 90 115
32 120 65 90 115
Notes:
1. The dimensions represent distance between pipe and shielding plate (no insulation material to
be applied).
2. For code P insulation with a minimum thickness in accordance with 251 ≤ t ≤ 350 °C may be
applied in lieu of shielding, if more convenient.
3. Multiple layers shall be provided for thickness above 80 mm.
Page 33 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
TABLE V
Page 34 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
TABLE VI
REQUIREMENTS FOR ACOUSTIC INSULATION CLASSES
A 50-150 50 2
B 65-150 100 5
C 65-150 100 10
Page 35 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
TABLE VII
INSULATION THICKNESS OF INDIVIDUAL LAYERS FOR COLD INSULATION (PIR)
Total thickness (mm) Inner layer (mm) Intermediate Outer layer (mm)
Layer (mm)
25 25 1)
30 30 1)
35 35 1)
40 40 1)
45 45 2)
50 50 2)
55 55 2)
60 3) 35 25
65 3) 35 30
70 3) 40 30
75 3) 45 30
80 3) 50 30
85 3) 55 30
90 3) 50 40
95 3) 55 40
100 3) 60 40
105 3) 65 40
110 3) 70 40
115 3) 75 40
120 3) 40 40 40
Notes:
1 Longitudinal and circumferential butt joints (for preformed pipe sections / segments, tees,
elbows, pipe supports, etc.).
2 Longitudinal ship lap joints and circumferential butt joints.
3 Preformed pipe sections / segments applied in multiple layers all butt joints.
4 The insulation of pipe supports, tees, elbows, etc. shall be applied in one layer with
longitudinal and circumferential ship lap joints (ship lapping in the thickness of the multiple
layer thickness of the preformed pipe sections / segments).
The insulation thickness of equipment shall be applied in one layer. The circumferential joint
between the body insulation and the head insulation shall be ship lap.
Page 36 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
TABLE VIII
CONTRACTION JOINTS FOR COLD INSULATION (PIR)
For the difference in temperature as indicated in the table below the temperature difference between
the outside surface of the insulation system (ambient temperature) and the operating temperature shall
be taken.
Notes:
: α = 16.10 m/(m.K)
-6
1 The coefficient of expansion of stainless steel
: α = 12.10 m/(m.K)
-6
2 The coefficient of expansion of carbon steel
Page 37 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
13.0 FIGURES
Gusset 30 x 3 mm
One per 100 mm
circumference with a
minimum of 4
Bended strip
30 x 3 mm
Wire netting
Spacers 10 mm clearance
See Table III from O.D. pipe
Max. 1000 mm
for length
Rounded corners
to avoid sharp
edges
Page 38 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Insulation thickness
HORIZONTAL
SECTION A-A
Vessel
Note 1)
Note 1) Welded on support clips are provided for vertical vessels only according standard equipment
drawing 04-3230-01-Sheet 052 (Vessel manufacturer scope of supply). Some Reactors or other Cr-Mo
vessels may require a special insulation support cage designed and supplied by insulation sub-
contractor (For vertical vessels where welded-on clips are not allowed).
Welded-on insulation clips are not provided for horizontal vessels and/or heat exchangers.
Page 39 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Allow clearance
30 mm + bolt length
Insulation
Sheeting
HORIZONTAL
Self tapping screws HORIZONTAL
VERTICAL
Sheeting
Sheeting
Bolt length + 30 mm
Up to and including
200 mm sheeting diameter
SECTION ENDPLATE
Page 40 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Tension rod
Pipe
Longitudinal furrows
Expansion furrows
Sheeting
Insulation
Pipe
Furrows for
sheeting diameter
< 120 mm
Page 41 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Horizontal joint
Sheeting diameter <200 mm
Sheeting
diameter < 200 mm
insulation
Pipe
Use folded
end cap fitted
over sheeting
if horizontal
Knurled edge
insulation
Page 42 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Sheeting
Rain cover Slot
Pipe
Insulation
Sheeting
SECTION A - A
Page 43 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Bolt length
= insulation + 30 mm
= Insulation thickness
thickness
plus expansion length
0.8 mm thick
Thickness
Insulation
sheeting over
top half of
Fixed Bellow
point
Drain
Page 44 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 45 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Drain hole
Drain Longitudinal
= Insulation Bolt length Band with quick Seam
thickness + 30 mm release toggles
Page 46 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
40 mm
Page 47 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
EXTEND OF METAL
SHEETING UP TO
HEAD INSULATION
NO METAL
SHEETING
Notes: 1) The height of the inside skirt insulation is the same as for the outside skirt insulation.
2) Vessel skirt shall be provided with a ‘hot box’ (provided by the Seller of the vessel) when
the maximum operating temperature is 340°C or higher. For hot box details see standard
equipment drawing 04-3230-01-Sheet 052 (2 sheets). Minimum height H = 400 mm.
Page 48 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Bend
Cut
Insulation thk’s +
0.8 mm Strip
40 mm
Hole for blind rivets
25 mm 40 mm
DETAIL “A”
Manhole
Self-tapping
Min. 25 mm
screws or blind
rivets
Self-tapping
screws or blind
rivets
Vertical Manhole
Detail “A”
Insulation
thickness
Insulation
Page 49 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Self-tapping
screws
Sheeting
Insulation
Vessel wall
Page 50 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Sheeting
Page 51 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Tape
Insulation material
No self tapping
screws where
sheeting is used
Sheeting
Tape Band
Primary vapour barrier
Pipe
Seam
Secondary vapour barrier
Seams
Insulation material
Seams
Sheeting /
Primary vapour barrier mastic
Vapour barriers Band
Secondary vapour barrier
Sheeting or mastic
Insulation
materials Vapour barrier
Adhesive 50 mm
Pipe
Page 52 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Insulation material
Vapour stop
Vapour barrier
Loose wool
Loose Band
mineral
wool
Vapour stop
Vapour barrier
Band Insulation
Vapour
Extend vapour 25 mm barrier
barrier up to
piping insulation ≥ 50 mm Adhesive
Drain hole Bolt length
+ 30 mm
Page 53 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
100
25
25
25
100
25
100
25
25
25
100
25
Page 54 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
13.18 PIPE SUPPORT FOR ACOUSTIC INSULATION CLASSES “B” AND “C”
Page 55 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 56 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
1. ENDCAP
2. MASTIC SEAL
Page 57 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
1. RESILIENT PAD
2. SPRING + STOP
3. RETAINING BAND
4. SHEETING SUPPORT RING
5. SHEETING
Page 58 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 59 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 60 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
SUPPORT RING
FOR PIPING FLAT STRIP 30 X 3
Page 61 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Bolt length + 30 mm
Bolt length + 30 mm Bolt length + 30 mm
Page 62 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 63 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
APPENDIX 2 SHT 051 – INSUL. SUPPORTS FOR VERTICAL VESSELS COLD SERVICE.
Page 64 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
APPENDIX 3 SHT 052 – INSUL. SUPPORTS FOR VERTICAL VESSELS HOT SERVICE (2 SHEETS).
Page 65 of 66
Sohar Refinery Expansion Project
Document Title: Document No. Rev:
Specification for Insulation of Piping & Equipment L-611 S-000-5390-001 2
Page 66 of 66