Beruflich Dokumente
Kultur Dokumente
(Lead)
charges
for trucks (Lead)
(Lead)
(Lead) and charges for
charges for
charges for trucks and tippers for trucks and (Lead)
trucks and tippers per charges for (Lead)
tippers for Cement/ charges for
tippers for cu.meter for trucks and
Rubble/Size Steel/ PCC slabs/ tippers per trucks and
Sl No. Distance Earth /
RCC
Sand /Gravel stones/ Cut Shahabad tippers for
Stones/ poles/ slabs/ CC & cu.meter for Bricks /
/ Murrum/ water/ 1000
Coarse AC & GI 1000 nos
Lime/ Surki/ Laterite litres
aggregate sheets/
per cu.meter blocks/
per cu.meter Packed
Wood/ cum
materials
/tonne
1 2 3 4 5 6 7 8
1 Lead up to 1 km 1 31.50 30.40 19.00 44.70 18.80 50.70
2 Lead up to 2 km 2 44.10 42.60 26.60 62.60 26.30 70.90
3 Lead up to 3 km 3 58.80 58.80 36.70 86.50 35.00 94.60
4 Lead up to 4 km 4 71.40 71.40 44.60 105.00 42.50 114.80
5 Lead up to 5 km 5 84.00 84.00 52.50 123.50 50.00 135.10
6 for Every km beyond 5 km up to 30 km 30 12.60 12.60 7.90 18.50 7.50 20.30
7 for Every km beyond 30 km 10000 10.50 10.50 6.60 15.40 6.30 16.90
Rubble/ size
Earth / stone/ cut
Sand /Gravel stone/ Cement
Steel in Bricks
Sl No. Description of item Murrum/ / Coarse in
Rs/Tonne Rs/1000 Nos.
Surki/ Rs / aggregate, Rs/Tonne
cum Lime in
Rs/cum
1 Loading 18.90 37.80 62.40 74.80 52.00
166 Dismantling
a) Stone masonry in cement mortar 114 TBSC-U.I-01 394.00
Flat stone in roof or floors including
b) 114 TBSC-U.I-03 14.00
lifting :
Pan tiled or Mangalore tiled roof with out
c) 114 TBSC-U.I-04 12.00
roof timbers :
Wrought and framed timber in roofs or
d) 114 TBSC-U.I-06 205.00
floors
e) Old lime mortar plaster 114 TBSC-U.I-07 4.00
f) Old cement mortar plaster 115 TBSC-U.I-08 5.00
Kadapa slabs or shahabad stone slabs on
g) 115 TBSC-U.I-11 7.00
sand bed
Clean removal of lime plaster from walls
and raking out joints 20mm deep or from
h) 115 TBSC-U.I-14 4.00
terraced roof and raking out joints 100 mm
deep
Clean removal of cement plaster from
i) 115 TBSC-U.I-15 5.00
walls and raking out joint 200 mm deep
Buildings Referenc
Material hire Labour
167 Hire charges for Access Scaffolding e to SSR
charges charges
page
A) Brick Masonry / Stone Maasonry
a) 1st floor 117 9.93 67.94
b) 2nd floor 9.93 96.94
c) 3rd floor 9.93 125.95
d) 4th floor 9.93 154.95
e) 5th floor 9.93 183.96
f) 6th floor 9.93 212.96
B) Plastering to walls
a) 1st floor 117 0.99 6.79
b) 2nd floor 0.99 9.69
c) 3rd floor 0.99 12.59
d) 4th floor 0.99 15.50
e) 5th floor 0.99 18.40
f) 6th floor 0.99 21.30
169 HIRE CHARGES FOR CENTERING&SCAFFOLDING-centering using Steel scaffolding pipes , jack props ,
Buildings Referenc Material hire
Lab
e to SoR charges
1st
Floor
a) Footings 116 277.00 532.00
b) Bed blocks, Steps 61.00 274.00
c) Pedestals 315.00 845.00
d) Plinth beams 1335.00 1281.00
170 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M - Steel scaffol
Buildings Referenc Material hire
Lab
e to SoR charges
1st
Floor
a) Lintels 118 1133.00 1360.00
b) Sunshades of any width 224.00 209.00
c) Columns 341.00 1909.00
d) Beams 2002.00 1601.00
e) RCC roof slabs upto 150 mm depth 227.00 182.00
f) RCC slabs upto 150-300 mm depth 233.00 187.00
171 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M - Casurina Ballies , B
Buildings Referenc Material hire Plates etc.,
Lab
e to SoR charges
1st
Floor
a) Lintels 119 760.00 1062.00
b) Sunshades of any width 150.00 163.00
c) Columns 229.00 1491.00
d) Beams 1342.00 1251.00
e) RCC roof slabs upto 150 mm depth 152.00 142.00
f) RCC slabs upto 150-300 mm depth 156.00 146.00
g) Public 8 964.00
Health
RCC walls , water tank walls items
172 Plumbing
PVC Clamps items 160 TBSP-H.II-61 18.00
Part I (I&CAD
LABOUR CHARGES Works)
SKILLED
173 Bar bender 9 I-1 565.00
174 Blacksmith 9 I-2 445.00
175 Blaster (licensed) 9 I-3 515.00
176 Carpenter 9 I-4 480.00
177 Work Inspector(Non technical) 9 I -10 460.00
178 Mason / Brick layer 9 I -11 445.00
179 Operator concrete mixer 9 I -16 445.00
180 Operator Jackhammer / Pneumatic
tamper(skilled) 10 I - 23 445.00
181 Painter 10 I - 35 515.00
182 Plumber(licensed) / Pipe fitter 10 I - 36 515.00
SEMI SKILLED
182 Sprayer(semi skilled) 11 II - 1 400.00
183 Carpenter 11 II - 4 405.00
184 Plumber / Pipe fitter 11 II - 9 405.00
184 Mason / Brick layer 12 II - 35 405.00
185 Painter 12 II - 37 405.00
UN SKILLED
Heavy Mazdoor / Light Mazdoor
186 13 III - 3, 4 350.00
Cost of Materials :
187 Binding wire 17 3 55.00
188 Detonator electric 18 21 10.00
189 Sand (un-screened for concrete items) 18 27 560.00
190 Sand un-screened for filling 18 27 560.00
191 Sand(screened for mortar, plastering
items) 18 28 760.00
192 Impervious Water proof compound 21 80 80.00
193 Roads&
Bridges
Gravel / Quarry spall Works S.No.89/34 103.00
194 Aggregates 6mm nominal size (HBG) S.No.25/33 a 735.00
195 Aggregates 10mm nominal size (HBG) S.No.25/33 b 935.00
196 Aggregates 13.20 / 12.50mm nominal size
(HBG) S.No.25/33 c 1097.50
197 Aggregates 20mm nominal size (HBG) S.No.25/33 d 1215.00
198 Aggregates 40mm nominal size (HBG) S.No.25/33 f 845.00
199 Gelatin 80% M - 104 73.00
200 SoR
Water charges(Urban) 2015-16 M - 189(a) 103.00
201 Water charges(Rural) M - 189(b) 77.00
202 PHE PH Items
PVC pipes 110mm dia.(4.00Kgs/sq.cm) Items Table18 151.00
1000 Nos.
1 No.
1 No.
1 No.
10 Sqm
10 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm 600.00
1 Sqm 550.00
1 Sqm
1 Sqm
1 Sqm
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 sqm
1 Kg
1 sqm
1 No.
1 No.
1 No.
1 No.
1 No.
1 Sqm
1 Sqm
1 Sqm
1 Kg
1 Kg
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 Kg
1 Kg
1 Kg
1 Ltr
1 Ltr
1 Ltr
1 Kg
1 Ltr
1 Ltr
1 Ltr
1 Ltr.
1 Kg
1 Kg
1 Ltr
1 Ltr
1 Ltr
1 Kg
1 Kg
1 Ltr.
1 Ltr.
1 Ltr.
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 RM
1 RM
1 RM
1 RM
1 RM
1 RM
1 RM
1 RM
24x32 Rs. 50 24x25 Rs. 45
1 RM
1 RM
1 RM
1 No.
1 No.
1 No.
1 No.
1 No.
1 Kg.
1 RM
1 Ltr
1 No.
1 RM
1 RM
1 sqm
1 RM
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 Ltr
1 Ltr
1 sqm
1 Kg
1 Kg
1 RM
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 hour
1 hour
1 RM
1 RM
1 RM
1 RM
1 RM
1 Kg
1 Kg
1 Kg
1 sqm
1 sqm
1 sqm
1 cum
1 sqm
1 sqm
1 cum
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
Unit
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
folding pipes , jack props , wallers , Foot plates , brackets , steel centering plates etc.,
eight of 3.66M - Steel scaffolding pipes, jack props, Steel centering Plates etc.
3.66M - Casurina Ballies , Bamboos , Wooden Reapers , Runners , Wood Posts , Wall
lates etc.,
Labour charges Unit
2nd 4th 5th 6th
3rd Floor
Floor Floor Floor Floor
1168.00 1274.00 1381.00 1487.00 1593.00 1 Cum
179.00 196.00 212.00 228.00 245.00 1 Sqm
1640.00 1789.00 1938.00 2087.00 2237.00 1 Cum
1376.00 1501.00 1626.00 1751.00 1877.00 1 Cum
156.00 170.00 185.00 199.00 213.00 1 Sqm
161.00 175.00 190.00 204.00 219.00 1 Sqm
1 Sqm
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Each
1 Kg
1 No.
1 Cum
1 Cum
1 Cum
1 Kg
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Kg
1 KL
1 KL
1 RM
Crew
charges
1 hour 210.90
1 hour 342.50
1 hour 219.70
1 hour 329.60
1 hour 158.20
1 hour 237.90
1 hour 263.60
1 cum
1 cum
1 RM
1 sqm
1 No.
1 No.
1 No.
1 RM
1 RM
1 No.
1 No.
1 No.
1 sqm
1 sqm
1 No.
1 No.
1 No.
1 RM
1 sqm
1 No.
1 No.
Name of the work : Proposed Construction of Centre For Excellence,Institute Of
A
Mental Health,Hyderabad.
D Allowances
1 Add for MA @ 40% 0.40
2 Overheads&Contractors Profit @13.615% 0.13615
Water charges
Type of Habitation 2 1 for Rural
2 for Urban
Name of the work : Proposed Construction of Centre For Excellence,Institute Of Mental Health,Hyderabad.
LEAD CHART (COMMON SoR 2016-2017) (Cement & Steel - November, 2016 rates)
Initial
Reference
S.No./ Cost Convey-
Sl. to SSR Lead in Loading Unloading
Description Source of Materials Item Code Unit excluding ance
No. page KM charges charges
No. seigniorage Charges
number
charges
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11)
Ordinary Portland Cement 43 / 53 grade
1 1 MT 6000.00
(including loading charges) NRB
2 Reinforcement steel Fe- 500 1 MT 37000.00
6 MS flats 1 MT 34500.00
27
7 Sand (un-screened for concrete items) Kunool 18 1 Cum 180.00 560.00 1737.45
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11)
Hyderabad City Out S.No.25/33
14 Aggregates 20mm nominal size (HBG) 0 1 Cum 32.00 1215.00 369.67
Skirts d
Aggregates 13.20 / 12.50mm nominal size Hyderabad City Out S.No.25/33
15 0 1 Cum 32.00 1097.50 369.67
(HBG) Skirts c
Hyderabad City Out S.No.25/33
16 Aggregates 10mm nominal size (HBG) 0 1 Cum 32.00 935.00 369.67
Skirts b
Hyderabad City Out S.No.25/33
17 Aggregates 6mm nominal size (HBG) 0 1 Cum 32.00 735.00 369.67
Skirts a
(Part II)
Hyderabad City Out
18 Rough Stone (OTG) Roads & 1 1 Cum 32.00 160.00 369.67
Skirts
Bridges
(Part II)
Hyderabad City Out
19 Rough Stone (HBG) Roads & 12 1 Cum 32.00 252.00 369.67
Skirts
Bridges
MA
Total
40%
(12) (13)
6000.00
37000.00
30000.00
35000.00
35000.00
34500.00
2297.45
2497.45
800.29
18.31 5852.80
94.43 27401.36
41.97 12511.72
1214.67
MA
Total
40%
(12) (13)
1584.67
1467.17
1304.67
1104.67
529.67
621.67
354.38
1.10 1884.32
1.00 1593.02
2988.00
2540.00
Joinery data 16
JOINERY DATA
COMMON SoR 2016-2017
b) Labour charges for aluminium doors ( S.No.11 of Page No. 396 of SoR 2011-12 )
1st class carpenter 0.099 Nos. 480.00 Each
2nd class carpenter 0.198 Nos. 405.00 Each
Power Saw Cutter -Hand Operated -Operator 0.099 Nos. 480.00 Each
Power Drill -Hand Operated -Operator 0.099 Nos. 480.00 Each
Mazdoor(Unskilled) 0.297 Nos. 350.00 Each
Non-technical work inspector 0.099 Nos. 460.00 Each
Add for MA @ 40% 0.40 372.24
Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.793 Hrs 125.00 1 Hour
Power Drill -Hand Operated -Hire charges 0.793 Hrs 116.00 1 Hour
c) Labour charges for aluminium sliding windows ( S.No.10 of Page No. 395 of SoR 2011-12 )
1st class carpenter 0.096 Nos. 480.00 Each
2nd class carpenter 0.289 Nos. 405.00 Each
Power Saw Cutter -Hand Operated -Operator 0.096 Nos. 480.00 Each
Power Drill -Hand Operated -Operator 0.096 Nos. 480.00 Each
Mazdoor(Unskilled) 0.289 Nos. 350.00 Each
Non-technical work inspector 0.096 Nos. 460.00 Each
Add for MA @ 40% 0.40 400.60
C.Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.771 Hrs 125.00 1 Hour
Power Drill -Hand Operated -Hire charges 0.771 Hrs 116.00 1 Hour
d) Labour charges for aluminium partitions partly glazed ( S.No.8 of Page No. 394 of SoR 2011-12 )
1st class carpenter 0.434 Nos. 480.00 Each
2nd class carpenter 0.434 Nos. 405.00 Each
Power Saw Cutter -Hand Operated -Operator 0.043 Nos. 480.00 Each
Power Drill -Hand Operated -Operator 0.058 Nos. 480.00 Each
Mazdoor(Unskilled) 0.145 Nos. 350.00 Each
Non-technical work inspector 0.072 Nos. 460.00 Each
Add for MA @ 40% 0.40 516.44
C.Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.347 Hrs 125.00 1 Hour
Power Drill -Hand Operated -Hire charges 0.463 Hrs 116.00 1 Hour
e) Labour charges for aluminium casement windows ( S.No.9 of Page No. 394 of SoR 2011-12 )
1st class carpenter 0.100 Nos. 480.00 Each
2nd class carpenter 0.300 Nos. 405.00 Each
Power Saw Cutter -Hand Operated -Operator 0.100 Nos. 480.00 Each
Power Drill -Hand Operated -Operator 0.100 Nos. 480.00 Each
Mazdoor(Unskilled) 0.300 Nos. 350.00 Each
Non-technical work inspector 0.100 Nos. 460.00 Each
Add for MA @ 40% 0.40 416.50
C.Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.800 Hrs 125.00 1 Hour
Power Drill -Hand Operated -Hire charges 0.800 Hrs 116.00 1 Hour
1 Supply and fixing of two shutter main door cum fixed window as per approved drawing with best teak woo
frame of section 150mm x 100 mm with fixed fan light of 500mm at top and fixed panels of 600mm width at side
fixed with 12mm thick Tinted - Bronze/Green glass using 12mm x 12mm teak wood beading and fixing ornamenta
grill made of 25mm x 5mm MS flats as per the approved drawing in fan light portion and fixed panels and 1st clas
teak wood top and middle rails & styles of section 120mm x 35mm, bottom rail of size 150mm x 35mm and 12mm
thick plain float glass for shutter with ornamental etching including cost and
conveyance to site of teak wood frame, shutters, glass including supply and fixing 6 nos MS Zhold fasts of siz
300 mm x 40 mm x 5mm including cost of ISI marked brass fixtures of 8 Nos butt hinges(IS:205) 250mm long ,
No. aldrop (IS:2681) 450mm long, 3 Nos tower bolts- 10mm (IS:204) of 200 mm long , 2 Nos 450 mm long fanc
handles, 2 Nos door stoppers including fixing the fixtures to door with required number of screws, bolt and nut
including labour charges for fixing the frame in position, fixing the shutters to the frame, fixing glass in fan ligh
portion etc., including overheads & contractors profit complete for finished item of work as per APSS 1001 & 100
(The vertical frame of door shall be embedded in flooring for a depth of not less than 40 mm) (3000mmX2600mm)
Cost analysis
Cost of best TW frame 2 m to 3m length 0.2310 Cum 146840.00 1 Cum
Cost of best TW frame up to 2 m length 0.1184 Cum 137941.00 1 Cum
Cost of 12mm thick tinted glass 4.02 Sqm 1546.00 1 Sqm
Cost of 12mm thick plain float glass 3.78 Sqm 1177.00 1 Sqm
Cost of teak wood beading 37.60 RM 26.00 1 RM
Cost of 250mm long brass butt hinges 8 Nos 600.00 Each
Joinery data 18
Say
2 Supply and fixing of ornamental grill made of 25mm x 5mm MS flats for fixing in fan light portion and side fixe
panels for door cum window as per the approved drawing including cutting the flat to required length, welding
painting with red oxide single coat including cost and conveyance of all materials, labour charges etc., complete fo
finished otem of work.
1 Supply and fixing of doors as per approved drawings with best teak wood frame of section 100mm x 65 mm wit
fixed fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beadin
and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of 35mm thick double shutters with bon
wood solid block board type core having cross bands and face veneers, hot pressed bonded with water proo
phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial p
with internal lipping on all sides
including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 nos MS Z
hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked brass fixtures of 6 Nos butt hinges (IS:205
150mm long , 1 No. aldrop (IS:2681) 300mm long, 2 Nos tower bolts- 10mm (IS:204) of 200 mm long at top, 1 No
tower bolt- 10mm bolt (IS:204) 150mm long at bottom, 2 Nos. 150mm long fancy handles (IS:208) , 2 Nos doo
stopper and 2 Nos rubber bushes including fixing the fixtures to door with required number of screws, bolt and nut
including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portio
etc., including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 Th
vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) (2000mm x 2600mm).
(BLD-CSTN-13-16)
Size : 2.00m x 2.60 m 5.20
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 2.00 + 0.50
= 4.50 x 0.10 x 0.065 0.02925
0.06318
Cost analysis
Cost of best TW frame 2 m to 3m length 0.03393 cum 146840.00 1 cum
Cost of best TW frame up to 2 m length 0.02925 cum 137941.00 1 cum
Cost of 4 mm thick pin headed glass 1.00 sqm 331.00 1 sqm
Cost of TW beading 6.00 RM 26.00 1 RM
Cost of 35 mm thick flush shutter 3.895 sqm 2188.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of brass tower bolt 200mm long 2 Nos. 347.00 Each
Cost of brass tower bolt 150mm long 1 No. 260.00 Each
Cost of brass Butt hinges 150mm long 6 Nos. 383.00 Each
Cost of brass aldrop 300mm long 1 No. 1284.00 Each
Cost of brass fancy handle 150mm long 2 Nos. 335.00 Each
Cost of brass door stopper 2 Nos. 198.00 Each
Cost of rubber bush 2 Nos. 25.00 Each
Cost of 10mm MS square bars 3.14 Kgs 35000.00 1000 Kgs
Labour charges for frame work 0.06318 cum 10646.75 1 cum
Add for MA @ 40% 0.40 672.66
Labour charges for fixing flush door shutter to the
frame, fixing the fixtures to the shutter 3.895 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 1480.10
Labour charges for fixing glass 1.00 sqm 284.00 1 sqm
Add for MA @ 40% 0.40 284.00
Add for nails & screws etc.
Rate for 5.20 sqm
Overheads&Contractors Profit @13.615% 0.13615 27362.39
2 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm
with fixed fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Woo
beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of 30mm thick double shutter
with bond wood solid block board type core having cross bands and face veneers, hot pressed bonded with wate
proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercia
ply with internal lipping on all sides
including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 Nos. MS Z
hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinge
(IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts - 10mm (IS:204) of 200 mm long a
top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubber bushes including fixing the
fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame i
position, fixing the shutter to the frame, fixing glass in fan light portion etc., including overheads & contractors prof
complete for finished item of work as per APSS 1001 & 1002 The vertical frame of door shall be embedded i
flooring for a depth of not less than 10 mm) (1800mm x 2600mm)
(BLD-CSTN-13-16)
Size : 1.80m x 2.60m 4.68
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.80 + 0.50
= 4.10 x 0.10 x 0.065 0.02665
0.06058
2 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm
with split type fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Tea
Wood beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of 30mm thick doub
shutters with bond wood solid block board type core having cross bands and face veneers, hot pressed bonde
with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both side
commercial ply with internal lipping on all sides,
including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 Nos. MS
hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinge
(IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia a
top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubber bushes including fixing the
fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame i
position, fixing the shutter to the frame, fixing glass in fan light portion etc., including overheads & contractors prof
complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded i
flooring for a depth of not less than 10 mm) (1500mm x 2600mm)
(BLD-CSTN-13-16)
Size : 1.50m x 2.60m 3.90
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.50 + 0.50
= 3.50 x 0.10 x 0.065 0.02275
0.05668
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.03393 cum 88994.00 1 cum
Cost of medium TW frame up to 2 m length 0.02275 cum 80094.00 1 cum
Cost of 4 mm thick pin headed glass 0.90 sqm 331.00 1 sqm
Cost of TW beading 8.40 RM 26.00 1 rm
Cost of 30 mm thick flush shutter 2.87 sqm 2003.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of Alumimium tower bolt 200mm long 2 Nos. 141.00 Each
Cost of Alumimium butt hinges 150mm long 6 Nos. 165.00 Each
Cost of Alumimium aldrop 300mm long 1 No. 425.00 Each
Cost of Alumimium handle 150mm long 2 Nos. 140.00 Each
Cost of Alumimium door stopper 2 Nos. 63.00 Each
Cost of rubber bush 2 Nos. 25.00 Each
Cost of 10mm MS square bars 2.355 Kgs 35000.00 1000 Kgs
Labour charges for frame work 0.05668 cum 10646.75 1 cum
Add for MA @ 40% 0.40 603.46
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 2.87 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 1090.60
Labour charges for fixing glass 0.90 sqm 284.00 1 sqm
Add for MA @ 40% 0.40 255.60
Add for nails & screws etc.
Rate for 3.90 sqm
Overheads&Contractors Profit @13.615% 0.13615 16230.79
3 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm
with split type fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Tea
Wood beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of 30mm thick doub
shutters with bond wood solid block board type core having cross bands and face veneers, hot pressed bonde
with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both side
commercial ply with internal lipping on all sides,
including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 Nos. MS
hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinge
(IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia a
top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubber bushes including fixing the
fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame i
position, fixing the shutter to the frame, fixing glass in fan light portion etc, including overheads & contractors prof
complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded i
flooring for a depth of not less than 10 mm) (1200mm x 2600mm)
(BLD-CSTN-13-16)
Size : 1.20m x 2.60m 3.12
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.20 + 0.50
= 2.90 x 0.10 x 0.065 0.01885
0.05278
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.03393 cum 88994.00 1 cum
Cost of medium TW frame up to 2 m length 0.01885 cum 80094.00 1 cum
Cost of 4 mm thick pin headed glass 0.72 sqm 331.00 1 sqm
Cost of TW beading 7.20 RM 26.00 1 rm
Cost of 30 mm thick flush shutter 2.255 sqm 2003.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of Alumimium tower bolt 200mm long 2 Nos. 141.00 Each
Cost of Alumimium butt hinges 150mm long 6 Nos. 165.00 Each
Cost of Alumimium aldrop 300mm long 1 No. 425.00 Each
Cost of Alumimium handle 150mm long 2 Nos. 140.00 Each
Cost of Alumimium door stopper 2 Nos. 63.00 Each
Cost of rubber bush 2 Nos. 25.00 Each
Cost of 10mm MS square bars 1.884 Kgs 35000.00 1000 Kgs
Labour charges for frame work 0.0528 cum 10646.75 1 cum
Add for MA @ 40% 0.40 561.94
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 2.255 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 856.90
Labour charges for fixing glass 0.72 sqm 284.00 1 sqm
Add for MA @ 40% 0.40 204.48
Add for nails & screws etc.
Rate for 3.12 sqm
Overheads&Contractors Profit @13.615% 0.13615 14125.36
4 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm
with split type fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Tea
Wood beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of 30mm thick sing
shutter with bond wood solid block board type core having cross bands and face veneers, hot pressed bonded wit
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both side
commercial ply with internal lipping on all sides including cost and conveyance to site of teak wood frame, flus
shutter including supply and fixing
6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 No
butt hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 1
mm dia at top, 2 Nos. 150mm long handles (IS:208), 1 No. door stopper and 1 No. rubber bush including fixing the
fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame i
position, fixing the shutter to the frame, fixing glass in fan light portion etc, including overheads & contractors prof
complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded i
flooring for a depth of not less than 10 mm) (1000mm x 2600mm).
(BLD-CSTN-13-16)
Size : 1.00m x 2.60m 2.60
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 1.00
= 2.00 x 0.10 x 0.065 0.01300
0.04693
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.03393 cum 88994.00 1 cum
Cost of medium TW frame up to 2 m length 0.0130 cum 80094.00 1 cum
Cost of 4 mm thick pin headed glass 0.60 sqm 331.00 1 sqm
Cost of TW beading [ 2x2 (1.00+2x0.30)] 3.20 RM 26.00 1 rm
Cost of 30 mm thick flush shutter 1.845 sqm 2003.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of Alumimium tower bolt 200mm long 1 No. 141.00 Each
Cost of Alumimium butt hinges 150mm long 3 Nos. 165.00 Each
Cost of Alumimium aldrop 300mm long 1 No. 425.00 Each
Cost of Alumimium handle 150mm long 2 Nos. 140.00 Each
Cost of Alumimium door stopper 1 No. 63.00 Each
Cost of rubber bush 1 No. 25.00 Each
Cost of 10mm MS square bars 1.57 Kgs 35000.00 1000 Kgs
Labour charges for frame work 0.0469 cum 10646.75 1 cum
Add for MA @ 40% 0.40 499.65
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 1.845 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 701.10
Labour charges for fixing glass 0.60 sqm 284.00 1 sqm
Add for MA @ 40% 0.40 170.40
Add for nails & screws etc.
Rate for 2.60 sqm
Overheads&Contractors Profit @13.615% 0.13615 11601.90
5 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm
with split type fan light of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Tea
Wood beading and 2 Nos. of 10mm MS Square bars and ISI marked flush door shutter of 30mm thick sing
shutter with bond wood solid block board type core having cross bands and face veneers, hot pressed bonded wit
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both side
commercial ply with internal lipping on all sides including cost and conveyance to site of teak wood frame, flus
shutter including supply and fixing
6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 No
butt hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 1
mm dia at top, 2 Nos. 150mm long handles (IS:208), 1 No. door stopper and 1 No. rubber bush including fixing the
fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame i
position, fixing the shutter to the frame, fixing glass in fan light portion etc, including overheads & contractors prof
complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded i
flooring for a depth of not less than 10 mm) (900mm x 2600mm)
(BLD-CSTN-13-16)
Size : 0.90m x 2.60m 2.34
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393
Outer frame - Horizontal 2 x 0.90
= 1.80 x 0.10 x 0.065 0.01170
0.04563
4 mm thick pin headed glass 2 x 0.90 x 0.30 0.54
Teak wood beading 2 x (0.90+2 x 0.30) 3.00
30 mm thick flush shutter 2 x 0.80 x 2.05 1.64
10 mm MS square bars 2 x 0.90 x 0.785 1.413
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.03393 cum 88994.00 1 cum
Cost of medium TW frame up to 2 m length 0.0117 cum 80094.00 1 cum
Cost of 4 mm thick pin headed glass 0.54 sqm 331.00 1 sqm
Cost of TW beading [ 2x2 (1.00+2x0.30)] 3.00 RM 26.00 1 rm
Cost of 30 mm thick flush shutter 1.640 sqm 2003.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of Alumimium tower bolt 200mm long 1 No. 141.00 Each
Cost of Alumimium butt hinges 150mm long 3 Nos. 165.00 Each
Cost of Alumimium aldrop 300mm long 1 No. 425.00 Each
Cost of Alumimium handle 150mm long 2 Nos. 140.00 Each
Cost of Alumimium door stopper 1 No. 63.00 Each
Cost of rubber bush 1 No. 25.00 Each
Cost of 10mm MS square bars 1.413 Kgs 35000.00 1000 Kgs
Labour charges for frame work 0.0456 cum 10646.75 1 cum
Add for MA @ 40% 0.40 485.81
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 1.640 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 623.20
Labour charges for fixing glass 0.54 sqm 284.00 1 sqm
Add for MA @ 40% 0.40 153.36
Add for nails & screws etc.
Rate for 2.34 sqm
Overheads&Contractors Profit @13.615% 0.13615 10901.76
6 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and IS
marked flush door shutters of 30 mm thick double shutters with bond wood solid block board type Core havin
cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factor
made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cos
and conveyance to site of teak wood frame, flush shutter including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204
of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubbe
bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charge
for fixing the frame in position, fixing the shutter to the frame etc, including overheads & contractors profit complet
for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for
depth of not less than 10 mm) (2000mm x 2100mm)
(BLD-CSTN-13-16)
Size : 2.00m x 2.10m 4.20
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 2.00
= 2.00 x 0.10 x 0.065 0.01300
0.04043
7 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and IS
marked flush door shutters of 30 mm thick double shutters with bond wood solid block board type Core havin
cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factor
made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cos
and conveyance to site of teak wood frame, flush shutter including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205)150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204
of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubbe
bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charge
for fixing the frame in position, fixing the shutter to the frame etc, including overheads & contractors profit complet
for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for
depth of not less than 10 mm) (1800mm x 2100mm)
(BLD-CSTN-13-16)
Size : 1.80m x 2.10m 3.78
Quantity analysis
Joinery data 26
5 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and IS
marked flush door shutters of 30 mm thick double shutters with bond wood solid block board type Core havin
cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factor
made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cos
and conveyance to site of teak wood frame, flush shutter including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204
of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubbe
bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charge
for fixing the frame in position, fixing the shutter to the frame etc., including overheads & contractors profit complet
for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for
depth of not less than 10 mm) (1500mm x 2100mm)
(BLD-CSTN-13-16)
Size : 1.50m x 2.10m 3.15
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.50
= 1.50 x 0.10 x 0.065 0.00975
0.03718
6 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and IS
marked flush door shutters of 30 mm thick double shutters with bond wood solid block board type Core havin
cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factor
made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cos
and conveyance to site of teak wood frame, flush shutter including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204
of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubbe
bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charge
for fixing the frame in position, fixing the shutter to the frame etc., including overheads & contractors profit complet
for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for
depth of not less than 10 mm) (1200mm x 2100mm)
(BLD-CSTN-13-16)
Size : 1.20m x 2.10m 2.52
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.20
= 1.20 x 0.10 x 0.065 0.00780
0.03523
7 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and IS
marked flush door shutters of 30 mm thick single shutter with bond wood solid block board type Core havin
cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factor
made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cos
and conveyance to site of teak wood frame, flush shutter including supply and
fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of
Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm
10 mm dia at top , 2 Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1 No. rubber bush including fixin
the fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame i
position, fixing the shutter to the frame etc., including overheads & contractors profit complete for finished item o
work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not les
than 10 mm) (1000mm x 2100mm)
(BLD-CSTN-13-16)
Size : 1.00m x 2.10m 2.10
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 1.00
= 1.00 x 0.10 x 0.065 0.00650
0.03393
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.02743 cum 88994.00 1 cum
Cost of medium TW frame up to 2 m length 0.00650 cum 80094.00 1 cum
Cost of 30 mm thick flush shutter 1.845 sqm 2003.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of Alumimium tower bolt 200mm long 1 No. 141.00 Each
Cost of Alumimium butt hinges 150mm long 3 Nos. 165.00 Each
Cost of Alumimium aldrop 300mm long 1 No. 425.00 Each
Cost of Alumimium handle 150mm long 2 Nos. 140.00 Each
Cost of Alumimium door stopper 1 No. 63.00 Each
Cost of rubber bush 1 No. 25.00 Each
Labour charges for frame work 0.0339 cum 10646.75 1 cum
Add for MA @ 40% 0.40 361.24
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 1.845 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 701.10
Add for nails & screws etc.
Rate for 2.10 sqm
Overheads&Contractors Profit @13.615% 0.13615 9732.35
8 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and IS
marked flush door shutters of 30 mm thick single shutter with bond wood solid block board type Core havin
cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factor
made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cos
and conveyance to site of teak wood frame, flush shutter including supply and
fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of
Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm
10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1 No. rubber bush including fixin
the fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame i
position, fixing the shutter to the frame etc, including overheads & contractors profit complete for finished item o
work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not les
than 10 mm) (900mm x 2100mm).
(BLD-CSTN-13-16)
Size : 0.90m x 2.10m 1.89
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 0.90
= 0.90 x 0.10 x 0.065 0.00585
0.03328
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.02743 cum 88994.00 1 cum
Cost of medium TW frame up to 2 m length 0.00585 cum 80094.00 1 cum
Cost of 30 mm thick flush shutter 1.64 sqm 2003.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of Alumimium tower bolt 200mm long 1 No. 141.00 Each
Cost of Alumimium butt hinges 150mm long 3 Nos. 165.00 Each
Cost of Alumimium aldrop 300mm long 1 No. 425.00 Each
Cost of Alumimium handle 150mm long 2 Nos. 140.00 Each
Cost of Alumimium door stopper 1 No. 63.00 Each
Cost of rubber bush 1 No. 25.00 Each
Labour charges for frame work 0.03328 cum 10646.75 1 cum
Add for MA @ 40% 0.40 354.32
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 1.64 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 623.20
Add for nails & screws etc.
Rate for 1.89 sqm
Overheads&Contractors Profit @13.615% 0.13615 9149.63
9 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65mm and IS
marked flush door shutter of 30mm thick single shutter with bond wood solid block board type Core having cros
bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory mad
conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cost an
conveyance to site of medium teak wood door frame, flush shutter, including suply and fixing 6 Nos. MS Z hol
fasts of size 300mm x 40mm x 5mm including ISI marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm
long, 1 No. aldrop (IS:2681) 250 mm long,
1 No. tower bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long handles (IS:208),1 No. rubber bush includin
supplying and fixing 1.20mm thick PVC sheet to full height of the shutter inside including labour charges for fixin
the frame in position, fixing the shutter to the frame etc., including overheads & contractors profit complete fo
finished item of work as per APSS 1001 & 1002. (The vertical frame of door shall be embedded in flooring for det
of not less than 10mm) (800mm x 2100mm).
(BLD-CSTN-13-16)
Quantity analysis Size : 0.80m x 2.10m 1.68
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 0.80
= 0.80 x 0.10 x 0.065 0.00520
0.03263
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.02743 cum 88994.00 1 cum
Cost of medium TW frame up to 2 m length 0.00520 cum 80094.00 1 cum
Cost of 30 mm thick flush shutter 1.435 sqm 2003.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of Aluminium tower bolt 150mm long 1 No. 114.00 Each
Cost of Aluminium butt hinges 150mm long 3 Nos. 165.00 Each
Cost of Aluminium aldrop 250mm long 1 No. 391.00 Each
Cost of Aluminium handle 125mm long 1 No. 126.00 Each
Cost of rubber bush 1 No. 25.00 Each
Cost of 1.20mm thick PVC sheet 1.435 sqm 170.00 1 sqm
Cost of Fevicol & labour charges for fixing PVC
sheet 1.435 sqm 80.00 1 sqm
Labour charges for frame work 0.0326 cum 10646.75 1 cum
Add for MA @ 40% 0.40 347.40
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 1.435 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 545.30
Add for nails & screws etc.
Rate for 1.68 sqm
Overheads&Contractors Profit @13.615% 0.13615 8651.90
10 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65mm and IS
marked flush door shutter of 30mm thick single shutter with bond wood solid block board type Core having cros
bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory mad
conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cost an
conveyance to site of medium teak wood door frame, flush shutter, including suply and fixing 6 Nos. MS Z hol
fasts of size 300mm x 40mm x 5mm including ISI marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm
long, 1 No. aldrop (IS:2681) 250 mm long,
Joinery data 32
1 No. tower bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long handles (IS:208),1 No. rubber bush includin
supplying and fixing 1.20mm thick PVC sheet to full height of the shutter inside including labour charges for fixin
the frame in position, fixing the shutter to the frame etc., including overheads & contractors profit complete fo
finished item of work as per APSS 1001 & 1002. (The vertical frame of door shall be embedded in flooring for det
of not less than 10mm) ( 750mm x 2100mm )
(BLD-CSTN-13-16)
Quantity analysis Size : 0.75m x 2.10m 1.575
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743
Outer frame - Horizontal 1 x 0.75
= 0.75 x 0.10 x 0.065 0.00488
0.03231
Cost analysis
Cost of medium TW frame 2 m to 3m length 0.02743 cum 88994.00 1 cum
Cost of medium TW frame up to 2 m length 0.00488 cum 80094.00 1 cum
Cost of 30 mm thick flush shutter 1.333 sqm 2003.00 1 sqm
Cost of MS Z hold fasts 6 Nos. 26.00 Each
Cost of Aluminium tower bolt 150mm long 1 No. 114.00 Each
Cost of Aluminium butt hinges 150mm long 3 Nos. 165.00 Each
Cost of Aluminium aldrop 250mm long 1 No. 391.00 Each
Cost of Aluminium handle 125mm long 1 No. 126.00 Each
Cost of rubber bush 1 No. 25.00 Each
Cost of 1.20mm thick PVC sheet 1.333 sqm 170.00 1 sqm
cost of Fevicol & labour charges for fixing PVC
sheet 1.333 sqm 80.00 1 sqm
Labour charges for frame work 0.03231 cum 10646.75 1 cum
Add for MA @ 40% 0.40 344.00
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 1.333 sqm 380.00 1 sqm
Add for MA @ 40% 0.40 506.54
Add for nails & screws etc.
Rate for 1.68 sqm
Overheads&Contractors Profit @13.615% 0.13615 8335.58
11 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing with fixe
fan light of 500mm height at top door using aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick fo
frame and door shutter made of styles , top and middle rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom ra
of 114.30mm x 44.45 mm , 3.18mm thick,powder coating of alluminium sections 25mm microns thick, 5 mm thic
plain float glass fitted with suitable aluminium glazing clips and rubber beading in fan light portion, double shutter
fitted with 5mm thick frosted / ground glass in the top half and 12mm thick prelaminated particle boar
( One side choice colour and other side balancing white lamnation ) in the bottom half fitted with suitab
aluminium glazing clips and rubber beading,shutters mounted on double action hydraulic floor spring of approve
brand manufacture IS : 6315 marked , Hardwyn make M-3000 for doors including cost of cutting floors as required
embedding in floors
and SS cover plates with brass pivot and sigle piece MS Sheet outer box with slide plate etc.complete (Weigh
Capacity up to 130 Kgs) as approved by Engineer-in-Charge including supply and fixing ISI marked powde
coated aluminium fixtures of 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208
150mm dia and 2 Nos. aldrops (IS:2681) 300mm long including labour charges for manufacturing door , fixing th
door with required No. of screws etc., including overheads & contractors profit complete for finished item of work
(The Aluminium section used shall be standard make confirming to IS 1948 – 1961) and as approved by th
Engineer) (2000mmx2600mm)
Joinery data 33
(BLD-CSTN-13-31)
Quantity analysis Size : 2.00m x 2.60m 5.20
10 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing with fixe
fan light of 500mm height at top door using aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick fo
frame and door shutter made of styles , top and middle rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom ra
of 114.30mm x 44.45 mm , 3.18mm thick,powder coating of alluminium sections 25mm microns thick, 5 mm thic
plain float glass fitted with suitable aluminium glazing clips and rubber beading in fan light portion, double shutter
fitted with 5mm thick frosted / ground glass in the top half and 12mm thick prelaminated particle boar
( One side choice colour and other side balancing white lamnation ) in the bottom half fitted with suitab
aluminium glazing clips and rubber beading,shutters mounted on double action hydraulic floor spring of approve
brand manufacture IS : 6315 marked , Hardwyn make M-3000 for doors including cost of cutting floors as required
embedding in floors
and SS cover plates with brass pivot and sigle piece MS Sheet outer box with slide plate etc.complete( Weigh
Capacity up to 130 Kgs ) as approved by Engineer-in-Charge including supply and fixing ISI marked powde
coated aluminium fixtures of 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208
150mm dia and 2 Nos. aldrops (IS:2681) 300mm long including labour charges for manufacturing door , fixing th
door with required No. of screws etc., including overheads & contractors profit complete for finished item of work
(The Aluminium section used shall be standard make confirming to IS 1948 – 1961) and as approved by th
Engineer) (1800mmx2600mm)
(BLD-CSTN-13-31)
Quantity analysis Size : 1.80m x 2.60m 4.68
Say
11 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing with fixe
fan light of 500mm height at top door using aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick fo
frame and door shutter made of styles , top and middle rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom ra
of 114.30mm x 44.45 mm , 3.18mm thick,powder coating of alluminium sections 25mm microns thick, 5 mm thic
plain float glass fitted with suitable aluminium glazing clips and rubber beading in fan light portion, double shutter
fitted with 5mm thick frosted / ground glass in the top half and 12mm thick prelaminated particle boar
( One side choice colour and other side balancing white lamnation ) in the bottom half fitted with suitab
aluminium glazing clips and rubber beading,shutters mounted on double action hydraulic floor spring of approve
brand manufacture IS : 6315 marked , Hardwyn make M-3000 for doors including cost of cutting floors as required
embedding in floors
and SS cover plates with brass pivot and sigle piece MS Sheet outer box with slide plate etc.complete( Weigh
Capacity up to 130 Kgs ) as approved by Engineer-in-Charge including supply and fixing ISI marked powde
coated aluminium fixtures of 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208
150mm dia and 2 Nos. aldrops (IS:2681) 300mm long including labour charges for manufacturing door , fixing th
door with required No. of screws etc., including overheads & contractors profit complete for finished item of work
(The Aluminium section used shall be standard make confirming to IS 1948 – 1961) and as approved by th
Engineer) (1500mmx2600mm)
(BLD-CSTN-13-31)
Quantity analysis Size : 1.50m x 2.60m 3.90
11 Providing & Fixing of Scientific Doors with metal door frames and door shutters made of galvanize stee
(base steel as per IS 513 of 0.58 mm thick D quality, galvanized as per IS 277 with Zinc of 120 GSM) coated wit
Zinc Phosphate Primer to receive any paint on site or finished with Thermosetting Polyurethane paint of Aliphat
Grade providing high levels of scratch resistance and durability/Epoxy polyester powder for powder coating pain
thickness 50-60 microns (Dry film thickness) outer frame section of 100 x 58 mm x 1.2 mm thick, shutter section o
0.80 mm thick galvanized steel sheet pressed (roll formed) for 46mm thick fully flush, double skin door shell seam
joints at stile edges, in-fill of honeycomb kraft paper used to give the required rigidity and effective acoust
insulation with 6” Tower bolt – 1 No., 6” D handles – 2 Nos., 10” Aldrop – 1 No., Butt Hinges – 3 Nos, Mortise Lock o
approved quality – 1 No, frames fixed to the concrete/masonry wall by means of self expanding screws includin
overheads and contractor profit etc.,complete for finished item of work for Single leaf Door.
12 Providing & Fixing of Scientific Doors with metal door frames and door shutters made of galvanize steel
(base steel as per IS 513 of 0.58 mm thick D quality, galvanized as per IS 277 with Zinc of 120 GSM) coated wit
Zinc Phosphate Primer to receive any paint on site or finished with Thermosetting Polyurethane paint of Aliphat
Grade providing high levels of scratch resistance and durability/Epoxy polyester powder for powder coating pain
thickness 50-60 microns (Dry film thickness) outer frame section of 100 x 58 mm x 1.2 mm thick, shutter section o
0.80 mm thick galvanized steel sheet pressed (roll formed) for 46mm thick fully flush, double skin door shell seam
joints at stile edges, in-fill of honeycomb kraft paper used to give the required rigidity and effective acoust
insulation with 6” Tower bolt – 2 Nos., 6” D handles – 2 Nos., 10” Aldrop – 1 No., Butt Hinges – 6 Nos, Mortise Loc
ofapproved quality – 1 No, frames fixed to the concrete/masonry wall by means of self expanding screws includin
overheads and contractor profit etc., complete for finished item of work for Double leaf Door
13 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) sliding doors three track - two glas
shutters sliding and one mesh shutter sliding- 95 -Series duly manufactured using UPVC reinforced profiles of (10
mm x 45 mm)/(95.50 mm x 60 mm) x 2.0 mm for outer frames, (75 mm x 39 mm)/(66 mm x 42 mm) x 2.0 mm fo
sliding door shutter frames capable of mounting single glazing system, structurally reinforced with hot dip galvanize
up to 50 microns of minimum thickness of 1.2 mm prefabricated & welded through fusion welding the window sas
shall be fitted with 5 mm thick clear float glass of reputed make and mesh shutter shall be made of (48.5 mm x 3
mm))/(50 mm x 26.5 mm) x 2.0 mm UPVC profile section and fitted with nylon/polymer mesh and rollers/pulley du
fixed with TPV Gaskets/ EPDM weathering seal resistant accessories like clipping locking system made o
aluminium 1 No., per set of sashes and the system is to be installed at the site using anchor fasteners, silico
rubber sealant, easy glazing/ deglazing at site etc., including cost and conveyance of all materials, accessories
labour charges for transportation, erection at site with templates for casement sizing, overheads and contractor
profit etc., complete for finished item of work
Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) 3 track sliding doors with mesh shutter
(2-glass shutters and 1-mesh shutter)- 95 - Series duly manufactured using UPVC reinforced profile
(Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3 for ever
100 parts of PVC resin) of (108 mm x 45 mm)/(95.50 mm x 60 mm) x 2.20 mm for outer frames, (75 mm x 39 mm
(66 mm x 42mm) x 2.20 mm for sliding door shutter frames capable of mounting single glazing system, structural
reinforced with hot dip galvanized up to 50 microns of minimum thickness of 1.2 mm prefabricated & welded throug
fusion welding the door sash shall be fitted with 6 mm thick clear float glass of reputed make duly fixed with Gre
colour TPV Gasket for sash & Glazing bead shall be coextruded with Grey colour soft PVC. Mesh shutter shall b
made of (48 mm x 30 mm))/(50 mm x 26.5mm) x 2.0 mm uPVC profile section and fitted with Vinyl Coated Fibe
mesh and rollers/pulley duly fixed with TPV Gaskets weathering seal resistant Door shall be provided with standar
hardware & multi point locking system of Patio/Roto espagulate and the system is to be installed at the site usin
anchor fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost and conveyance of a
materials, accessories, labour charges for transportation, erection at site including overheads and contractors prof
etc.,complete for finished item of work.
14
15 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) openable doors with openable shutter
duly manufactured using UPVC reinforced profiles (Composition of profile shall consists a minimum of 5.5 PHR o
TiO2 and not more than 12PHR of CaCo3 for every 100 parts of PVC resin) of 60mm x 55 mm x 2.40 mm for oute
frames, 74 mm x 60mm x 2.40 mm for mullion sections as per the need and 102 mm x 60 mm x 2.40 mm fo
openable shutter frame capable of mounting single glazing system structurally reinforced with hot dip galvanized u
to 50 microns of minimum thickness of 1.2 mm prefabricated & welded through fusion welding the door sash sha
be fitted with 6 mm thick clear float glass of reputed make duly fixed with Grey colour TPV Gaskets for sash
Glazing bead shall be coextruded with Grey colour soft PVC.System shall be provided with 4 no’s of 3D Hinges fo
each shutter and multipoint locking with keys.with raiser wedges for smooth operation and the system is to b
installed at the site using anchor fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cos
and conveyance of all materials, accessories, labour charges for transportation, erection at site including overhead
and contractors profit etc., complete for finished item of work
13 Providing & Fixing of Open able Windows with Flymesh made of pre-painted steel as per IS 513 of 0.58m
thick galvanized as per IS 277 finish painted with a polyester paint and the section for outer frame of 72 x 55mm
centre mullion of 72 x 50mm, section for fixed glass beading section of 12 x 12 mm and section for shutters of 48
25 mm and outer frame & mullion sections with rebate for glazed shutters, fly mesh and a 20 mm provision for guar
bars/grills and fly mesh shutter section of 20 x 40 mm, stay, handles, latch 2Nos of heavy duty stainless steel pivo
hinges per shutter and panelled with 5mm thick plain float glass and S.S. Mesh for fly mesh shutter (304 grade
fitted using rubber gaskets including fixing the windows in the concrete/masonry wall by means of self expandin
screws, including 10mm Square guard bars with 6” (152.4mm) pitch , complete including overheads and contracto
profit etc., complete for finished item of work.
a Centre fixed both side openable shutter window : 1800mm x1800mm with fixed fan light
of 500mm at top : 3.24
Window portion 2.34 Sqm 6377.00 1 Sqm
Fan light portion 0.90 Sqm 5102.00 1 Sqm
Rate per 3.24 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 Sqm 558.00 1 Sqm
add cost of 4mm thick pin headed glass 1.00 Sqm 331.00 1 Sqm
b Centre fixed both side openable shutter window 1500mm x1800mm with fixed fan light 2.70
of 500mm at top :
Window portion 1.95 Sqm 7288.00 1 Sqm
Fan light portion 0.75 Sqm 5102.00 1 Sqm
Rate per 2.70 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 Sqm 558.00 1 Sqm
add cost of 4mm thick pin headed glass 1.00 Sqm 331.00 1 Sqm
b Double shutter window 1200x1800 with fixed fan light of 500mm at top : 2.04
Window portion 1.44 Sqm 8017.00 1 Sqm
Fan light portion 0.60 Sqm 5102.00 1 Sqm
Rate per 2.16 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 Sqm 558.00 1 Sqm
add cost of 4mm thick pin headed glass 1.00 Sqm 331.00 1 Sqm
d Double shutter window 900x1800 with fixed fan light of 500mm at top : 1.62
Window portion 1.17 Sqm 8017.00 1 Sqm
Fan light portion 0.45 Sqm 5102.00 1 Sqm
Rate per 1.62 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 Sqm 558.00 1 Sqm
add cost of 4mm thick pin headed glass 1.00 Sqm 331.00 1 Sqm
14 Supply and fixing of pre-painted steel casement/openable windows base steel as per IS 513 of - 0.58mm thic
'D quality, galvanized as per IS 277, finish painted with a polyester paint, section for outer frame of 46 x 52 mm
section for shutter of 46 x 46mm section for mullion 46 x 70 mm, and section for beading 18 x 25 mm panelled wit
5 mm thick plain float glass fitted with EPDM gaskets, handle made of high grade aluminium powder coated frame
fixed to the concrete /masonry wall by means of self expanding screws including 10 mm square guard bars @ 15
mm pitch including overheads & contractors profit etc., complete for finished item of work.
A) WINDOWS
a Centre fixed both side openable shutter window 1800x1800 with fixed fan light of 500mm
at top : 3.24
Window portion 2.34 Sqm 5952.00 1 Sqm
Fan light portion 0.90 Sqm 5102.00 1 Sqm
Rate per 3.24 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 Sqm 558.00 1 Sqm
add cost of 4mm thick pin headed glass 1.00 Sqm 331.00 1 Sqm
b Centre fixed both side openable shutter window 1500x1800 with fixed fan light of 500mm
at top : 2.70
Window portion 1.95 Sqm 5952.00 1 Sqm
Fan light portion 0.75 Sqm 5102.00 1 Sqm
Rate per 2.70 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 Sqm 558.00 1 Sqm
add cost of 4mm thick pin headed glass 1.00 Sqm 331.00 1 Sqm
c Double shutter window 1200x1800 with fixed fan light of 500mm at top : 2.16
Window portion 1.56 Sqm 6681.00 1 Sqm
Fan light portion 0.60 Sqm 5102.00 1 Sqm
Rate per 2.16 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 Sqm 558.00 1 Sqm
add cost of 4mm thick pin headed glass 1.00 Sqm 331.00 1 Sqm
d Double shutter window 900x1800 with fixed fan light of 500mm at top : 1.62
Window portion 1.17 Sqm 6681.00 1 Sqm
Fan light portion 0.45 Sqm 5102.00 1 Sqm
Rate per 1.62 sqm
Rate per 1 sqm
deduct cost of 5mm plain glass 1.00 Sqm 558.00 1 Sqm
add cost of 4mm thick pin headed glass 1.00 Sqm 331.00 1 Sqm
Say
15 Supply and fixing of pre-painted steel top hung ventilators made of pre - painted steel as per IS 513 of -0.5
mm thick 'D quality, galvanized as per IS 277, finish painted with a polyester paint & 4 mm pinhead glass fo
ventilators with EPDM Gasket with handle made of high grade aluminium powder coated and nylon receiver, corne
brackets made of CRCA with Zinc Phosphate, Mullion caps made of glass filled nylon, frames fixed to th
concrete /masonry wall by means of self expanding screws including 10 mm square guard bars with 6 pitc
complete for finished item of work including overheads & contractors profit etc., complete for finished item of work
a Top Hung 2 '-0 x 2'-0 (609.6x609.6mm) outer frame section size of 46mm x 52 mm shutter frame section size o
46mm x 46 mm and (ii) Ventilators: Top Hung 4 '-0 x 2'-0 (1219.2x609.6mm) outer frame section size of 46 x 52 m
shutter frame section size of 46 x 46 mm Mullion section size of 46 x 70 mm and (iii) Ventilators: Top Hung 4 '-0 x 3
0 (1219.2x914.4mm) outer frame section size of 46 x 52m m shutter frame section size of 46 x 46 mm Mullio
section size of 46 x 70 mm
a Fixed louvers 2'-0 x 2'-0 (609.6x609.6mm) (Box section) outer frame section size of 33 x 56 mm and (ii) Ventilator
Fixed louvers 4'-0 x 2'-0 (1219.2 x 609.6 mm) (Box section) outer frame section size of 33 x 56 mm Mullion sectio
size of 33 x 56 mm and (iii) Ventilators: Fixed louvers 4'-0 x 3'-0 (1219.2 x 914.4 mm) (Box section) outer fram
section size of 33 x 56 mm Mullion section size of 33 x 56 mm
15 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) 2 Track–2 Panel Sliding windows
duly manufactured using UPVC reinforced profiles (Composition of profile shall consists a minimum of 5.5 PHR o
TiO2 and not more than 12 PHR of CaCo3 for every 100 parts of PVC resin) of (62mm x 60 mm)/(60 mm x 45 mm
x 2.20 mm for outer frames, (66 mm x 38 mm)/(58 mm x 39 mm) x 2.20 mm for sliding shutter frames capable o
mounting single glazing system, structurally reinforced with hot dip galvanized up to 50 microns of minimum
thickness of 1.0/1.2 mm prefabricated & welded through fusion welding. The window sash shall be fitted with 5 mm
thick clear float glass of reputed make duly fixed with Grey colour TPV Gasket for sash & Glazing bead shall be co
extruded with Grey colour soft PVC. System shall have single point locking with Touch Lock and the system is to b
installed at the site using anchor fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cos
and conveyance of all materials, accessories, labour charges for transportation, erection at site including
overheads and contractors profit etc., complete for finished item of work.
16 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) 3 track sliding windows with mesh shutte
– (2-glass shutters and 1-mesh shutter) duly manufactured using UPVC reinforced profiles (Composition of profi
shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3 for every 100 parts of PVC resin
of (94mm x 45 mm)/(80 mm x 52 mm) x 2.20 mm for outer frames, (58 mm x 39 mm)/(54 mm x 38 mm) x 2.20mm
for sliding shutter frames capable of mounting single glazing system structurally reinforced with hot dip galvanize
up to 50 microns of minimum thickness of 1.0/1.2 mm prefabricated & welded through fusion welding. The windo
sash shall be fitted with 5 mm thick clear float glass of reputed make and mesh shutter frame shall be (42 mm
25mm)/(52 mm x 21.5 mm) x 2.0 mm fitted with Vinyl Coated Fiber mesh- on rollers/ pulley duly fixed with Gre
colour TPV Gasket for sash & Glazing bead shall be co-extruded with Grey colour soft PVC. System shall hav
single point locking with Touch Lock and the system is to be installed at the site using anchor fasteners, silico
rubber sealant, easy glazing/deglazing at site etc., including cost and conveyance of all materials, accessories
labour charges for transportation, erection at site including overheads and contractors profit etc., complete fo
finished item of work
17 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) casement windows openable shutters du
manufactured using UPVC reinforced profiles (Composition of profile shall consists aminimum of 5.5 PHR of TiO
and not more than 12PHR of CaCo3 for every 100 parts of PVC resin) of 60mm x 55 mm x 2.40 mm for oute
frames, 74 mm x 60mm x 2.40 mm for mullion sections for two or more openable shutters 75 mm x 60 mm x 2.4
mm for openable shutter frame capable of mounting single glazing system structurally reinforced with hot di
galvanized up to 50 microns of minimum thickness of 1.0/1.2 mm prefabricated & welded through fusio
welding.The window sash shall be fitted with 5 mm thick clear float glass of reputed make duly fixed with Gre
colour TPV Gasket for sash & Glazing bead shall be co-extruded with Grey colour soft PVC and accessories fo
casement window – friction hinges of stainless steel grade 304/430- 2 Nos., per sash, handle with zamak allo
casting 1 No. per sash, multipoint locking system suitably concealed 1 No., per sash provided with raiser wedges fo
smooth operation and the system is to be installed at the site using anchor fasteners, silicon rubber sealant, eas
glazing/ deglazing at site etc., including cost and conveyance of all materials, accessories, labour charges fo
transportation, erection at site including overheads and contractor profit etc., complete for finished item of work
19 Providing, supplying & fixing of Top hung Ventilator with Exhaust Fan provision made out of multi
chambered uPVC sections with TPV Gasket for sash & Glazing bead shall be co-extruded with Grey colour so
PVC and reinforced with Galvanized Iron profiles throughout the window. The outer frame having a overall size o
60mm x 55 mm x 2.40 mm with reinforcement of 1 mm thickness, Mullion with overall size of 74 mm x 60 mm x 2.4
mm with reinforcement of 1 mm thickness and Sash with overall size of 75 mm x 60 mm x 2.40 mm wit
reinforcement of 1.0/1.2 mm thickness. (Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and no
more than 12 PHR of CaCo3 for every 100 parts of PVC resin).Glazing bead for fixing of glass shall be of size 34
20 mm coextruded with soft PVC gasket. Ventilator shall be provided with 4.5 mm Pin Head glass, standar
hardware, single point locking using cockspur handle and friction stays. Wall thickness of frame, mullion and sas
shall be 2.4mm.,including cost and conveyance of all materials,accessories, labour charges for transportation
erection at site including overheads and contractor profit etc., complete for finished item of work
20 Supplying and fixing of 7.5mm thick Aluminium Grill (as approved by the department) 3.58 Kg/Sqm includin
cost and conveyance of all materials, accessories, labour charges for transportation, erection at site, overheads an
contractor profit etc., complete for finished item of work
21 Supplying and fixing of MS Grill to windows / in open court yards using 25mm x 6mm MS flat alround and 10mm
MS square bars horizontally at 125mm centre to centre and vertically at 300mm centre to centre including fixing wit
4 Nos of MS Z holdfasts (2 on each side) duly making cutting brick masonry, fixing and making to original surfac
neatly and painting grill with one coat of red oxide primer including cost all taxes and conveyance of all materia
including cutting, bending, welding including all operational charges and all labour charges etc., complete fo
finished item of work.
16 Providing and Fixing Pre painted Steel Sliding Window 2 Track-2 Panel Sliding Window fabricated from Ro
formed sections made of galvanized Steel colour coated/powder coated (Base Steel as per IS 513 ‘D’ qualit
galvanized as per IS 277 with zinc of 120 GM/Sq.mtr) with total coated thickness of 0.58mm. Primer coat with epox
primer of 5-7microns thick, finish painted with a polyester paint of 12-16 microns thick and back coated wit
Alkydbacker of 5-7 microns or powder coated with purepolyester powder up to 50-60 microns thick. Sectionfo
external frame should be of 59x44mm, Section for shutter should be of 35x50mm. The windows should be panele
with 5mm thick plain float glass. Corner bracket for internal and external frame made of glass filled nylon. Gasket
are to be made of EthylPropylene Diamine Monomer (EPDM).The sections are to be cut to length, joined an
assembled by means of corner bracket. The above frames should be fixed to the concrete/masonry walls by mean
of self expanding brackets & screws including 10mm square guard bars with 6” pitch (152.4mm) includin
overheads & contractors profit etc., complete finished item of work.
17 Supply and fixing powder coated alimunium fully glazed 2 shutter windows with fixed panel in betwee
openable shutters as per approved drawings using anodized aluminium sections of 38.50mm x 33mm , 3mm thic
for outer frame, 59mm(3mm) x 33mm(2.5mm) x 30mm(3mm) for mullions and 38.5mm x 33mm , 3mm thick fo
shutter frame , powder coating of alluminium sections 25mm microns thick and fixing 5 mm thick plain glass fitte
with suitable aluminium galzing clips and rubber beading including supplying and fixing powder coated aluminium
adjustable frictional stay hinges (2 Nos. per shutter), handle with lock (1 No. per shutter) including cost an
conveyance to site of powder coated aluminium sections, glass, rubber beading, fixtures etc., including labou
charges for manufacturing window, fixing in position using wooden blocks and sheet metal screws, etc., complete fo
finished item of work in all floors. (The aluminium sections used shall be standard make confirming to IS 1948-196
and as approved by the Engineer and fixtures shall be of ISI marked) (1800mm x 1300mm).
18 Supply and fixing powder coated alimunium fully glazed top hung ventilators fixed with 5mm thick plain glas
using suitable alluminium glazing clips and rubber beading as per approved drawings using anodized aluminium
sections of 38.50mm x 33mm , 3mm thick for outer frame, 59mm(3mm) x 33mm(2.5mm) x 30mm(3mm) for
mullions shutters z section of 38.50mmx33mm,3mm thick,powder coating of all alluminium sections 25mm micron
thick, including cost and conveyance to site of powder coated aluminium sections, glass, rubber beading, fixture
etc., including labour charges for manufacturing window, fixing in position using wooden blocks and sheet meta
screws, etc., complete for finished item of work. (The aluminium sections used shall be standard make confirmin
to IS 1948-1961 and as approved by the Engineer and fixtures shall be of ISI marked) (900mm x 500mm).
19 Supply and fixing powder coated alimunium sliding window with fixed fan light at top as per approve
drawings with all required accessories such as stoppers,bolts,weather stripping etc. for all sizes and sections
accordance with approved drawings and as per IS 1948-1961 with top section of window of size 62mm x 32mm
1.47mm thick, window side frames of size 61.85mm x 31.75mm,1.50mm thick and bottom frame size 61.85mm
31.75mm,1.50mm thick sloping outwards for drainage and fixed and sliding shutters with bottom,sides and top wit
section of 40mm x 18mm ,1.70mm thick,inter locking section 40mm x 28mm x 18mm,1.60mm thick inter locked fo
weather scaling and mounted on nylon rollers of lift type and fan light top &side sections of siz
63.50mmx38.10mm,1.53mm thick, powder coating of all alluminium sections 25mm microns thick and fixing 5mm
thick plain glass in fan light and for shutters fitted with
alluminium glazing clips and rubber beading including cost and conveyance to site of powder coated aluminium
sections, glass, rubber beading, fixtures etc., including labour charges for manufacturing window, fixing in positio
using wooden blocks and sheet metal screws, overheads & contractors profit etc., complete for finished item o
work. (The aluminium sections used shall be standard make confirming to IS 1948-1961 and as approved by th
Engineer and fixtures shall be of ISI marked) ( 1800mm x 1800mm )
Cost analysis
A.Material :
Cost of powder coated Al. sections 27.038 Kgs. 321.00 1 Kgs.
Cost of 5mm thick plain glass 3.24 sqm. 558.00 1 sqm.
Cost of rubber beading 9.00 RM 2.00 1 RM
B.Labour charges 3.24 sqm 754.11 1 sqm
Add for Screws, Nails, Nuts, Bolts etc., LS
Rate per 3.06 Sqm:
Overheads&Contractors Profit @13.615% 0.13615 12960.20
20 Supply and fixing powder coated alimunium sliding window with fixed fan light at top as per approve
drawings with all required accessories such as stoppers,bolts,weather stripping etc. for all sizes and sections
accordance with approved drawings and as per IS 1948-1961 with top section of window of size 62mm x 32mm
1.47mm thick, window side frames of size 61.85mm x 31.75mm,1.50mm thick and bottom frame size 61.85mm
31.75mm,1.50mm thick sloping outwards for drainage and fixed and sliding shutters with bottom,sides and top wit
section of 40mm x 18mm ,1.70mm thick,inter locking section 40mm x 28mm x 18mm,1.60mm thick inter locked fo
weather scaling and mounted on nylon rollers of lift type and fan light top &side sections of siz
63.50mmx38.10mm,1.53mm thick, powder coating of all alluminium sections 25mm microns thick and fixing 5mm
thick plain glass in fan light and 5mm thick ground glass for shutters fitted with alluminium glazing clips an
rubber beading, powder coating of all alluminium sections 25mm microns thick including cost and conveyance t
site of powder coated aluminium sections, glass,
rubber beading , fixtures etc., including labour charges for manufacturing window, fixing in position using woode
blocks and sheet metal screws, overheads & contractors profit etc., complete for finished item of work. (Th
aluminium sections used shall be standard make confirming to IS 1948-1961 and as approved by the Engineer an
fixtures shall be of ISI marked) (1200mm x 1800mm)
Cost analysis
A.Material :
Cost of powder coated Al. sections 20.17 Kgs. 321.00 1 Kgs.
Cost of 5mm thick plain glass 2.16 sqm. 558.00 1 sqm.
Cost of rubber beading 6.00 RM 2.00 1 RM
B.Labour charges 2.16 sqm 754.11 1 sqm
Joinery data 47
21 Supply and fixing of Cement Bonded Prelaminated Particle Board aluminum glazed partitions using 10m
Cement Bonded Prelaminated Particle Board and 5.00mm thick plain glass to full height. Using with Cemen
Bonded Prelaminated Particle Board to a height of 0.91 meter at bottom panel and remaining height with glass an
aluminum sections anodized to 12 to 15 microns and of sections of size 37mm x 62mm and 1.5mm thickness wit
one meter centre to centre duly fixed with clip beading on both sides including fixing the frame to pillars by M.S
flats, bolts and nuts including cost and conveyance of all materials etc., complete as directed during execution
including overheads & contractors profit etc., complete for finished item of work
17 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) Fixed Glazing - 56 series duly manufactured usin
UPVC reinforced profiles of 60 mm x 56 mm x 2.25 mm for outer frames and the mullion sections are of 60 mm x 7
mm x 2.25 mm frames are structurally reinforced with hot dip galvanized up to 50 microns of minimum thickness o
1.2 mm the sash shall be fitted with 4 mm thick pinheaded glass of reputed make duly fixed with EPDM weatherin
seal resistant including cost and conveyance of all materials, accessories, labour charges for transportation
erection at site with templates for casement sizing scaffolding including overheads and contractor profit etc
complete for finished item of work.
18 Supplying and fixing of two shutter cupboards as per drawing with medium teak wood frames of size 75mm
40mm and MDF Board Interior grade both sides laminated 18mm thick for shutters with 18mm x 12mm teak woo
beading alround and supplying and fixing powder coated MS fixtures 3 Nos. butt hinges of size 100mm long(fo
each shutter), tower bolt 2 Nos. of 100mm x 10mm, 2 Nos of handles 100mm long and standard lockin
arrangements for shutters including cost and conveyance of all materials to site, labour charges, over heads an
contractor profit etc., complete for finished item of work.
JOINERY DATA
OMMON SoR 2016-2017
2548.80
5017.95
3080.00
10646.75
99.13
91.99
712.25
7.12
719.37
96.38
89.44
746.64
7.47
754.11
20.64
27.84
50.75
33.12
206.58
43.38
53.71
820.10
8.20
828.30
Joinery data 50
100.00
92.80
775.90
7.76
783.66
door cum fixed window as per approved drawing with best teak wood
xed fan light of 500mm at top and fixed panels of 600mm width at sides
een glass using 12mm x 12mm teak wood beading and fixing ornamental
r the approved drawing in fan light portion and fixed panels and 1st class
f section 120mm x 35mm, bottom rail of size 150mm x 35mm and 12mm
mental etching including cost and
shutters, glass including supply and fixing 6 nos MS Zhold fasts of size
f ISI marked brass fixtures of 8 Nos butt hinges(IS:205) 250mm long , 1
tower bolts- 10mm (IS:204) of 200 mm long , 2 Nos 450 mm long fancy
fixing the fixtures to door with required number of screws, bolt and nuts
ame in position, fixing the shutters to the frame, fixing glass in fan light
ctors profit complete for finished item of work as per APSS 1001 & 1002
ded in flooring for a depth of not less than 40 mm) (3000mmX2600mm)
sqm
33920.04
16332.21
6214.92
4449.06
977.60
4800.00
Joinery data 51
3270.00
3522.00
1041.00
396.00
156.00
6329.28
3719.97
1487.99
2215.20
886.08
3583.44
1433.38
11.83
94746.00
12146.92
1653.80
13800.73
13801
ade of 25mm x 5mm MS flats for fixing in fan light portion and side fixed
approved drawing including cutting the flat to required length, welding,
ng cost and conveyance of all materials, labour charges etc., complete for
Sqm
Kgs
173.88
131.04
20.16
29.03
12.30
366.41
1574.45
99.40
108.15
198.45
122.64
528.64
Joinery data 52
ved drawings with best teak wood frame of section 100mm x 65 mm with
ith 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading
ISI marked flush door shutter of 35mm thick double shutters with bond
g cross bands and face veneers, hot pressed bonded with water proof
ory made conforming to IS 2202-1991 (Part-I) both sides commercial ply
eak wood frame, flush shutter including supply and fixing 6 nos MS Z
m including cost of ISI marked brass fixtures of 6 Nos butt hinges (IS:205)
mm long, 2 Nos tower bolts- 10mm (IS:204) of 200 mm long at top, 1 No.
ong at bottom, 2 Nos. 150mm long fancy handles (IS:208) , 2 Nos door
g fixing the fixtures to door with required number of screws, bolt and nuts
me in position, fixing the shutter to the frame, fixing glass in fan light portion
rofit complete for finished item of work as per APSS 1001 & 1002 The
n flooring for a depth of not less than 10 mm) (2000mm x 2600mm).
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
4982.28
4034.77
331.00
156.00
8522.26
156.00
694.00
260.00
2298.00
1284.00
670.00
396.00
50.00
109.90
672.66
269.06
1480.10
592.04
284.00
113.60
6.71
27362.39
3725.39
31087.78
5978.42
5978
Joinery data 53
eak wood frame, flush shutter including supply and fixing 6 Nos. MS Z
mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinges
81) 300mm long, 2 Nos. tower bolts - 10mm (IS:204) of 200 mm long at
8), 2 Nos. door stoppers and 2 Nos. rubber bushes including fixing the
screws, bolt and nuts including labour charges for fixing the frame in
ing glass in fan light portion etc., including overheads & contractors profit
r APSS 1001 & 1002 The vertical frame of door shall be embedded in
) (1800mm x 2600mm)
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
3019.57
2134.51
297.90
145.60
6980.46
156.00
282.00
990.00
425.00
280.00
126.00
50.00
98.91
644.98
257.99
1324.30
529.72
255.60
102.24
2.77
18103.54
2464.80
20568.34
4394.94
4395
Joinery data 54
eak wood frame, flush shutter including supply and fixing 6 Nos. MS Z
mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinges
681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at
), 2 Nos. door stoppers and 2 Nos. rubber bushes including fixing the
screws, bolt and nuts including labour charges for fixing the frame in
ing glass in fan light portion etc., including overheads & contractors profit
r APSS 1001 & 1002 (The vertical frame of door shall be embedded in
) (1500mm x 2600mm)
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
3019.57
1822.14
297.90
218.40
5748.61
156.00
282.00
990.00
425.00
280.00
126.00
50.00
82.43
603.46
241.38
1090.60
436.24
255.60
102.24
3.23
16230.79
2209.82
18440.61
4728.36
4728
Joinery data 55
eak wood frame, flush shutter including supply and fixing 6 Nos. MS Z
mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinges
81) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at
8), 2 Nos. door stoppers and 2 Nos. rubber bushes including fixing the
screws, bolt and nuts including labour charges for fixing the frame in
xing glass in fan light portion etc, including overheads & contractors profit
r APSS 1001 & 1002 (The vertical frame of door shall be embedded in
) (1200mm x 2600mm)
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
3019.57
1509.77
238.32
187.20
4516.77
156.00
282.00
990.00
425.00
280.00
126.00
50.00
65.94
561.94
224.77
856.90
342.76
204.48
81.79
6.16
14125.36
1923.17
16048.53
5143.76
5144
Joinery data 56
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
3019.57
1041.22
198.60
83.20
3695.54
156.00
141.00
495.00
425.00
280.00
63.00
25.00
54.95
499.65
199.86
701.10
280.44
170.40
68.16
4.21
11601.90
1579.60
13181.49
5069.81
5070
Joinery data 57
sqm
cum
cum
cum
sqm
RM
sqm
Kgs
3019.57
937.10
178.74
78.00
3284.92
156.00
141.00
495.00
425.00
280.00
63.00
25.00
49.46
485.81
194.32
623.20
249.28
153.36
61.34
1.66
10901.76
1484.27
12386.04
5293.18
5293
Joinery data 58
Sqm
cum
cum
cum
sqm
2441.11
1041.22
7801.69
156.00
282.00
990.00
425.00
280.00
126.00
50.00
1480.10
592.04
2.86
15668.01
3730.48
507.90
4238.38
4238
Sqm
Joinery data 59
cum
cum
cum
sqm
2441.11
937.10
6980.46
156.00
282.00
990.00
425.00
280.00
126.00
50.00
416.61
166.64
1324.30
529.72
2.21
15107.14
3996.60
544.14
4540.73
4541
Joinery data 60
Sqm
cum
cum
cum
sqm
2441.11
780.92
5748.61
156.00
282.00
990.00
425.00
280.00
126.00
50.00
395.85
158.34
1090.60
436.24
3.31
13363.97
4242.53
577.62
4820.15
4820
Joinery data 61
Sqm
cum
cum
cum
sqm
2441.11
624.73
4516.77
156.00
282.00
990.00
425.00
280.00
126.00
50.00
375.09
150.03
856.90
342.76
4.42
11620.80
4611.43
627.85
5239.28
5239
Joinery data 62
sqm
cum
cum
cum
sqm
2441.11
520.61
3695.54
156.00
141.00
495.00
425.00
280.00
63.00
25.00
361.24
144.50
701.10
280.44
2.82
9732.35
1325.06
11057.41
5265.43
5265
Joinery data 63
sqm
cum
cum
cum
sqm
2441.11
468.55
3284.92
156.00
141.00
495.00
425.00
280.00
63.00
25.00
354.32
141.73
623.20
249.28
1.52
9149.63
1245.72
10395.35
5500.19
5500
Joinery data 64
gs with medium teak wood frame of section 100mm x 65mm and ISI
single shutter with bond wood solid block board type Core having cross
nded with water proof phenol formaldehyde synthetic resin factory made
sides commercial ply with internal lipping on all sides including cost and
door frame, flush shutter, including suply and fixing 6 Nos. MS Z hold
ding ISI marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm
mm dia, 2 Nos. 125mm long handles (IS:208),1 No. rubber bush including
heet to full height of the shutter inside including labour charges for fixing
o the frame etc., including overheads & contractors profit complete for
1002. (The vertical frame of door shall be embedded in flooring for deth
m).
sqm
cum
cum
cum
sqm
2441.11
416.49
2874.31
156.00
114.00
495.00
391.00
126.00
25.00
243.95
114.80
347.40
138.96
545.30
218.12
4.47
8651.90
1177.96
9829.86
5851.11
5851
gs with medium teak wood frame of section 100mm x 65mm and ISI
single shutter with bond wood solid block board type Core having cross
nded with water proof phenol formaldehyde synthetic resin factory made
sides commercial ply with internal lipping on all sides including cost and
door frame, flush shutter, including suply and fixing 6 Nos. MS Z hold
ding ISI marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm
Joinery data 65
mm dia, 2 Nos. 125mm long handles (IS:208),1 No. rubber bush including
heet to full height of the shutter inside including labour charges for fixing
o the frame etc., including overheads & contractors profit complete for
1002. (The vertical frame of door shall be embedded in flooring for deth
m)
sqm
cum
cum
cum
sqm
2441.11
390.86
2670.00
156.00
114.00
495.00
391.00
126.00
25.00
226.61
106.64
344.00
137.60
506.54
202.62
2.62
8335.58
1134.89
9470.47
6013.00
6013
inium fully glazed swing door as per the approved drawing with fixed
sing aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick for
p and middle rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom rail
,powder coating of alluminium sections 25mm microns thick, 5 mm thick
um glazing clips and rubber beading in fan light portion, double shutters
glass in the top half and 12mm thick prelaminated particle board
de balancing white lamnation ) in the bottom half fitted with suitable
ng,shutters mounted on double action hydraulic floor spring of approved
rdwyn make M-3000 for doors including cost of cutting floors as required ,
sigle piece MS Sheet outer box with slide plate etc.complete (Weight
y Engineer-in-Charge including supply and fixing ISI marked powder
bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208)
300mm long including labour charges for manufacturing door , fixing the
luding overheads & contractors profit complete for finished item of work.
andard make confirming to IS 1948 – 1961) and as approved by the
Joinery data 66
sqm
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
16611.11
558.00
1792.80
1323.00
29.60
7576.00
792.00
400.00
850.00
3740.73
3.09
33676.33
4585.03
38261.36
7357.95
7358
Joinery data 67
minium fully glazed swing door as per the approved drawing with fixed
sing aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick for
p and middle rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom rail
,powder coating of alluminium sections 25mm microns thick, 5 mm thick
um glazing clips and rubber beading in fan light portion, double shutters
glass in the top half and 12mm thick prelaminated particle board
de balancing white lamnation ) in the bottom half fitted with suitable
ng,shutters mounted on double action hydraulic floor spring of approved
rdwyn make M-3000 for doors including cost of cutting floors as required ,
d sigle piece MS Sheet outer box with slide plate etc.complete( Weight
by Engineer-in-Charge including supply and fixing ISI marked powder
bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208)
300mm long including labour charges for manufacturing door , fixing the
luding overheads & contractors profit complete for finished item of work.
andard make confirming to IS 1948 – 1961) and as approved by the
sqm
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
15861.89
502.20
1613.52
1190.70
28.00
7576.00
792.00
400.00
850.00
3366.66
3.72
32184.69
4381.95
36566.64
7813.38
Joinery data 68
7813
minium fully glazed swing door as per the approved drawing with fixed
sing aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick for
p and middle rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom rail
,powder coating of alluminium sections 25mm microns thick, 5 mm thick
um glazing clips and rubber beading in fan light portion, double shutters
glass in the top half and 12mm thick prelaminated particle board
de balancing white lamnation ) in the bottom half fitted with suitable
ng,shutters mounted on double action hydraulic floor spring of approved
rdwyn make M-3000 for doors including cost of cutting floors as required ,
d sigle piece MS Sheet outer box with slide plate etc.complete( Weight
by Engineer-in-Charge including supply and fixing ISI marked powder
bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208)
300mm long including labour charges for manufacturing door , fixing the
luding overheads & contractors profit complete for finished item of work.
andard make confirming to IS 1948 – 1961) and as approved by the
sqm
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
sqm.
sqm.
sqm.
RM
14738.39
418.50
1344.60
992.25
25.60
7576.00
792.00
400.00
850.00
2805.55
4.35
29947.24
4077.32
Joinery data 69
34024.56
8724.25
8724
with metal door frames and door shutters made of galvanize steel
ck D quality, galvanized as per IS 277 with Zinc of 120 GSM) coated with
int on site or finished with Thermosetting Polyurethane paint of Aliphatic
sistance and durability/Epoxy polyester powder for powder coating paint
ss) outer frame section of 100 x 58 mm x 1.2 mm thick, shutter section of
ssed (roll formed) for 46mm thick fully flush, double skin door shell seam
b kraft paper used to give the required rigidity and effective acoustic
handles – 2 Nos., 10” Aldrop – 1 No., Butt Hinges – 3 Nos, Mortise Lock of
the concrete/masonry wall by means of self expanding screws including
ete for finished item of work for Single leaf Door.
10283.00
1400.03
11683.03
11683
with metal door frames and door shutters made of galvanize steel
ck D quality, galvanized as per IS 277 with Zinc of 120 GSM) coated with
int on site or finished with Thermosetting Polyurethane paint of Aliphatic
sistance and durability/Epoxy polyester powder for powder coating paint
ss) outer frame section of 100 x 58 mm x 1.2 mm thick, shutter section of
ssed (roll formed) for 46mm thick fully flush, double skin door shell seam
b kraft paper used to give the required rigidity and effective acoustic
D handles – 2 Nos., 10” Aldrop – 1 No., Butt Hinges – 6 Nos, Mortise Lock
o the concrete/masonry wall by means of self expanding screws including
lete for finished item of work for Double leaf Door
10968.00
1493.29
12461.29
12461
Poly Vinyl Chloride (UPVC) sliding doors three track - two glass
ing- 95 -Series duly manufactured using UPVC reinforced profiles of (108
mm for outer frames, (75 mm x 39 mm)/(66 mm x 42 mm) x 2.0 mm for
unting single glazing system, structurally reinforced with hot dip galvanized
1.2 mm prefabricated & welded through fusion welding the window sash
glass of reputed make and mesh shutter shall be made of (48.5 mm x 30
C profile section and fitted with nylon/polymer mesh and rollers/pulley duly
ering seal resistant accessories like clipping locking system made of
the system is to be installed at the site using anchor fasteners, silicon
at site etc., including cost and conveyance of all materials, accessories,
n at site with templates for casement sizing, overheads and contractors
rk
7773.00
1058.29
8831.29
8831
Joinery data 70
Poly Vinyl Chloride (UPVC) 3 track sliding doors with mesh shutter –
er)- 95 - Series duly manufactured using UPVC reinforced profiles
nimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3 for every
mm)/(95.50 mm x 60 mm) x 2.20 mm for outer frames, (75 mm x 39 mm)/
or shutter frames capable of mounting single glazing system, structurally
microns of minimum thickness of 1.2 mm prefabricated & welded through
ed with 6 mm thick clear float glass of reputed make duly fixed with Grey
ad shall be coextruded with Grey colour soft PVC. Mesh shutter shall be
.5mm) x 2.0 mm uPVC profile section and fitted with Vinyl Coated Fiber
V Gaskets weathering seal resistant Door shall be provided with standard
Patio/Roto espagulate and the system is to be installed at the site using
easy glazing/ deglazing at site etc., including cost and conveyance of all
transportation, erection at site including overheads and contractors profit
7773.00
1058.29
8831.29
8831
7500.00
1021.13
8521.13
8521
8810.00
1199.48
10009.48
10009
Joinery data 71
sqm
14922.18
4591.80
19513.98
6022.83
-558.00
331.00
5795.83
789.10
6584.94
6585
sqm
14211.60
3826.50
18038.10
6680.78
-558.00
331.00
6453.78
878.68
7332.46
7332
sqm
11544.48
3061.20
14605.68
7159.65
-558.00
331.00
6932.65
943.88
7876.53
7877
sqm
9379.89
2295.90
11675.79
7207.28
-558.00
331.00
6980.28
950.36
7930.64
7931
Joinery data 72
sqm
14922.18
6377.00
-558.00
331.00
6150.00
837.32
6987.32
6987
sqm
14211.60
7288.00
-558.00
331.00
7061.00
961.36
8022.36
8022
sqm
12506.52
8017.00
-558.00
331.00
7790.00
1060.61
8850.61
8851
sqm
9379.89
8017.00
-558.00
331.00
7790.00
1060.61
8850.61
8851
sqm
13927.68
4591.80
18519.48
5715.89
-558.00
331.00
5488.89
747.31
Joinery data 73
6236.20
6236
sqm
11606.40
3826.50
15432.90
5715.89
-558.00
331.00
5488.89
747.31
6236.20
6236
sqm
10422.36
3061.20
13483.56
6242.39
-558.00
331.00
6015.39
819.00
6834.38
6834
sqm
7816.77
2295.90
10112.67
6242.39
-558.00
331.00
6015.39
819.00
6834.38
6834
5952.00
-558.00
331.00
5725.00
779.46
6504.46
6504
5952.00
-558.00
331.00
5725.00
779.46
6504.46
Joinery data 74
6504
6681.00
-558.00
331.00
6454.00
878.71
7332.71
7333
6681.00
-558.00
331.00
6454.00
878.71
7332.71
7333
top hung ventilators made of pre - painted steel as per IS 513 of -0.58
S 277, finish painted with a polyester paint & 4 mm pinhead glass for
made of high grade aluminium powder coated and nylon receiver, corner
sphate, Mullion caps made of glass filled nylon, frames fixed to the
lf expanding screws including 10 mm square guard bars with 6 pitch
g overheads & contractors profit etc., complete for finished item of work
6924.00
942.70
7866.70
4737.00
644.94
5381.94
5382
7030.00
Joinery data 75
957.13
7987.13
7987
oly Vinyl Chloride (UPVC) 3 track sliding windows with mesh shutter
duly manufactured using UPVC reinforced profiles (Composition of profile
O2 and not more than 12 PHR of CaCo3 for every 100 parts of PVC resin)
2.20 mm for outer frames, (58 mm x 39 mm)/(54 mm x 38 mm) x 2.20mm
nting single glazing system structurally reinforced with hot dip galvanized
1.0/1.2 mm prefabricated & welded through fusion welding. The window
float glass of reputed make and mesh shutter frame shall be (42 mm x
ed with Vinyl Coated Fiber mesh- on rollers/ pulley duly fixed with Grey
ead shall be co-extruded with Grey colour soft PVC. System shall have
the system is to be installed at the site using anchor fasteners, silicon
t site etc., including cost and conveyance of all materials, accessories,
n at site including overheads and contractors profit etc., complete for
7341.00
999.48
8340.48
8340
7756.00
1055.98
8811.98
8812
Louvered Ventilator made out of multi chambered uPVC sections with
Grey colour soft PVC. having isolated drainage and reinforced with
indow. The outer frame having an overall size of 60 mm x 55 mm x 2.40
Mullion with overall size of 74 mm x 60 mm x 2.40 mm with reinforcement
shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR
sin). Ventilator shall be provided with 4.5 mm Pin Head glass, standard
llion shall be 2.4 mm., including cost and conveyance of all materials,
rtation, erection at site including overheads and contractor profit etc.,
6606.00
899.41
7505.41
7505
Joinery data 76
9295.00
1265.51
10560.51
10561
1112.00
151.40
1263.40
1263
dows / in open court yards using 25mm x 6mm MS flat alround and 10mm
ntre to centre and vertically at 300mm centre to centre including fixing with
) duly making cutting brick masonry, fixing and making to original surface
red oxide primer including cost all taxes and conveyance of all materials
ding all operational charges and all labour charges etc., complete for
Kgs
Kgs
Kgs
923.16
289.80
904.18
139.10
200.31
2456.55
802.79
109.30
912.09
912
Joinery data 77
6783.00
923.51
7706.51
7707
sqm
5277.24
1305.72
22.80
940.00
150.00
1833.76
3.78
9533.30
1297.96
10831.26
4628.74
4629
Joinery data 78
nium fully glazed top hung ventilators fixed with 5mm thick plain glass
nd rubber beading as per approved drawings using anodized aluminium
ick for outer frame, 59mm(3mm) x 33mm(2.5mm) x 30mm(3mm) for
3mm,3mm thick,powder coating of all alluminium sections 25mm microns
te of powder coated aluminium sections, glass, rubber beading, fixtures
cturing window, fixing in position using wooden blocks and sheet metal
work. (The aluminium sections used shall be standard make confirming
ngineer and fixtures shall be of ISI marked) (900mm x 500mm).
sqm
1627.47
251.10
7.60
352.65
2.75
2241.57
305.19
2546.76
5659.46
5659
munium sliding window with fixed fan light at top as per approved
uch as stoppers,bolts,weather stripping etc. for all sizes and sections in
as per IS 1948-1961 with top section of window of size 62mm x 32mm ,
e 61.85mm x 31.75mm,1.50mm thick and bottom frame size 61.85mm x
for drainage and fixed and sliding shutters with bottom,sides and top with
nter locking section 40mm x 28mm x 18mm,1.60mm thick inter locked for
on rollers of lift type and fan light top &side sections of size
r coating of all alluminium sections 25mm microns thick and fixing 5mm
utters fitted with
sqm
Joinery data 79
8679.20
1807.92
18.00
2443.32
11.76
12960.20
1764.53
14724.73
4544.67
4545
munium sliding window with fixed fan light at top as per approved
uch as stoppers,bolts,weather stripping etc. for all sizes and sections in
as per IS 1948-1961 with top section of window of size 62mm x 32mm ,
e 61.85mm x 31.75mm,1.50mm thick and bottom frame size 61.85mm x
for drainage and fixed and sliding shutters with bottom,sides and top with
nter locking section 40mm x 28mm x 18mm,1.60mm thick inter locked for
on rollers of lift type and fan light top &side sections of size
r coating of all alluminium sections 25mm microns thick and fixing 5mm
thick ground glass for shutters fitted with alluminium glazing clips and
uminium sections 25mm microns thick including cost and conveyance to
glass,
Sqm
6473.61
1205.28
12.00
1628.88
Joinery data 80
6.00
9325.77
1269.70
10595.47
4905.31
4905
3849.00
524.04
4373.04
4373
3872.00
-558.00
331.00
0.00
3645.00
496.27
4141.27
4141
Joinery data 81
pboards as per drawing with medium teak wood frames of size 75mm x
h sides laminated 18mm thick for shutters with 18mm x 12mm teak wood
g powder coated MS fixtures 3 Nos. butt hinges of size 100mm long(for
0mm x 10mm, 2 Nos of handles 100mm long and standard locking
and conveyance of all materials to site, labour charges, over heads and
item of work.
sqm
1441.69
2617.92
138.00
52.00
60.00
230.40
100.00
153.31
1728.00
752.53
2.48
7276.33
990.67
8267.00
3827.32
3827
WS & SA DATA 2014-15 Page-82
2 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having
a minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick
both inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits
up to a depth of 904 mm (3'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8)
150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per
Standard specification and including cost and conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all materials and all incidental and operational, labour
charges like mixing cement mortar, constructing masonry, lift charges, curing , overheads & contractors
profit etc., complete for finished item of work as per Standard specification.
3 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having
a minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick
both inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits
up to a depth of 1524 mm (5'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8)
150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per
Standard specification and including cost and conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all materials and all incidental and operational, labour
charges like mixing cement mortar, constructing masonry, lift charges, curing , overheads & contractors
profit etc., complete for finished item of work as per Standard specification.
5 Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI make confirming to IS 651 & 4127
with C.I grating & constructing cement brick masonry in CM (1:6) prop., intermediate chamber and fitted
with 304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover of standard make as approved including
cost and conveyance of all materials to site, labour charges, overheads & contractors profit etc., complete
for finished item of work.
6 Supplying and fixing of 3" (76.2mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit etc., complete for finished item of work.
7 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit etc., complete for finished item of work.
10 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-Part-
4:1972 of size 550mm x 400mm with 32 mm nominal size C.P. Fitting with parallel pipe thread
conforming to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st quality
Indian make heavy duty complete with standard CI brackets including wooden blocks ,1 No.12.70mm
PVC connection with brass union nuts CP coated , angle stop cock 12.70mm dia. first quality Indian make
heavy duty, 30mm dia. PVC flexible waste pipe 914.4mm length of 1st quality including cost and
conveyance of all materials to site, labour charges , overheads & contractors profit for finished item of
work
11 Supplying and fixing CP finish brass soap dish of approved make ISI quality including cost and
conveyance of all materials, labour charges for fixing , overheads & contractors profit for finished item of
work in all floors
12 Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , plywood back
with NP screws 1st quality including cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work in all floors.
13 Supplying and fixing of 25.4mm dia , 609.6mm long aluminium anodized towel rods with brackets
and aluminium screws including cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work.
14 Supplying and fixing 15 mm brass body CP finish bib tap of not less than 300 grams weight screw
type (full turn) with internal / external threaded connection conforming to IS 8931 as approved by the
Engineer-In-Charge including cost and conveyance of all materials, labour charges , overheads &
contractors profit complete for finished item of work in all floors.
15 Supplying and fixing 15 mm brass body CP finish self closing tap push type conforming to IS 1711
as approved by the Engineer-In-Charge including cost and conveyance of all materials, labour charges,
overheads & contractors profit complete for finished item of work in all floors.
Rate as per SSR 1 No. 271.00 Each 271.00
Add for MA @ 40% 0.40 0.00 0.00
271.00
WS & SA DATA 2014-15 Page-87
16 Supplying and fixing Chromium plated finish brass body quarter turn Bibcock cum Health Faucet
with 1m long tube and wall hook with 7 - 10 years warranty with necessary fittings etc., complete
including cost and conveyance of all materials, labour charges, overheads & contractor profit complete for
finished item of work in all floors.
17 Supplying and fixing of SWR PVC pipes (Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4
Kg/Sq.cm. and fixing all special such as plain bends, off sets, door bends, single junctions, double
junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay
nails including cost and conveyance of all materials to site, labour charges, overheads & contractors profit
complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326)
a) 75mm dia
Data for 6 RM
Cost of 75mm dia pipe 6.00 RM 255.00 3 RM 510.00
Cost of PVC clamps 3 Nos. 15.00 Each 45.00
Labour charges 6.00 RM 71.00 1 RM 426.00
981.00
Rate per 1 RM 163.50
Overheads&Contractors Profit @13.615% 0.13615 163.50 22.26
185.76
say 186
c) 110mm dia
Data for 6 RM
Cost of 110mm dia pipe 6.00 RM 484.00 3 RM 968.00
Cost of PVC clamps 3 Nos. 18.00 Each 54.00
Labour charges 6 RM 71.00 1 RM 426.00
1448.00
Rate per 1 RM 241.33
Overheads&Contractors Profit @13.615% 0.13615 241.33 32.86
274.19
say 274
18 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR
11 to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to 2") for
hot and cold water (IS 15778:2007) including cost and conveyance of all materials to site, labour charges
for fixing, overheads & contractors profit complete for finished item of work at all floor levels.
a) 15.90mm OD pipe
Rate as per SoR 1 No. 156.00 Each 156.00
Overheads&Contractors Profit @13.615% 0.13615 156.00 21.24
Rate per 1 RM 177.24
say 177
b) 22.20mm OD pipe
Rate as per SoR 1 No. 189.00 Each 189.00
WS & SA DATA 2014-15 Page-88
c) 28.60mm OD pipe
Rate as per SoR 1 No. 227.00 Each 227.00
Overheads&Contractors Profit @13.615% 0.13615 227.00 30.91
Rate per 1 RM 257.91
say 258
d) 34.90mm OD pipe
Rate as per SoR 1 No. 310.00 Each 310.00
Overheads&Contractors Profit @13.615% 0.13615 310.00 42.21
Rate per 1 RM 352.21
say 352
e) 41.30mm OD pipe
Rate as per SoR 1 No. 383.00 Each 383.00
Overheads&Contractors Profit @13.615% 0.13615 383.00 52.15
Rate per 1 RM 435.15
say 435
WS & SA DATA 2014-15 Page-89
19 Supplying and fixing 65 mm Nominal Bore GI pipe Medium Grade properties & weight as per IS
1239 in ground or on wall with GI fittings such as elbows tees couplings, nipples, plugs including
excavation for trenches and refilling the trenches ,chiselling masonry walls and making good the walls &
floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance
of all materials and labour charges , overheads & contractors profit complete for finished item of work
except for GI bends union and GI connectors with checkout and socket Tata or Zenith make or
equivalent.
20 Supplying and fixing Bronze Gate/ Globe valve as per IS - 778 Class - I, Indian make heavy type
including cost and conveyance of all materials , labour charges , overheads & contractors profit complete
for finished item of work.
21 Providing and placing on terrace (at all floor levels)polyetheylene water storage tank with double
layer approved brand and manufacture with cover and suitable locking arrangement and making
necessary holes for inlet and outlets and over flow pipes but without fittings and base support for tanks
including cost and conveyance of all materials and labour charges , overheads & contractors profit
complete for finished item of work.
23 Supplying and fixing white glazed flat back half stall urinals of size 590 mm x 375 mm x 390 mm
with integral flushing rim fixed with screws complete Indian make (HSW/Parry/Neycer) conforming to
IS:2556-1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm PVC connection
with brass plumber union nuts CP coated, 12.70mm push cock 1st quality of approved make, 30mm dia
PVC flexible waste pipe of 914.4 mm length of Ist quality including cost and conveyance of all materials to
site, labour charges etc., overheads & contractors profit complete for finished item of work for all floors.
24 Supplying and fixing of 16mm to 20 mm thick polished marble slab partitioins of size 4' 0" x 2' 0"
for urinals including full rounding the edges, fixing in position, polishing, including cost and conveyance
of all materials and labour charges, overheads & contractors profit complete for finished item of work for
all floors.
25 Supplying and fixing of 101.60mm x 609.60mm white glazed porcelain channels 1st quality fixed in
brick masonry to the required slopes, white cement pointing including cost and conveyance of all
materials and labour charges, overheads & contractors profit complete for finished item of work for all
floors.
Rate as per SSR 1 No 495.00 1 Each 495.00
Rate for 1 RM (1/0.6096) 495.00 812.01
Overheads&Contractors Profit @13.615% 0.13615 812.01 110.56
WS & SA DATA 2014-15 Page-92
D A T A (SoR 2016-17)
Name of the work : Proposed Construction of Centre For Excellence,Institute Of Mental Health,Hyderabad.
DATA
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
1 Dismantling, clearing away and carefully stacking useful materials for re-use and disposal of unserviceab
materials with 100m lead as directed by Executive Engineer duly taking actual premeasurements befo
dismantling including all labour charges , overheads & contractor profit etc., complete
a) Brick masonry
(BLD-CSTN-14-9/299)
Mazdoor(unskilled) 0.409 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 143.15
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 200.41
Rate per 1 cum
say
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
l) Clean removal of lime plaster from walls and raking out joints 20mm deep
or from terraced roof and raking out joints 100 mm deep
CIVIL DATA : Page-97
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate as per SSR 10.00 sqm 4.00 10 sqm
Add for MA @ 40% 0.40 4.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 0.56
Rate per 1 sqm
say
m) Clean removal of cement plaster from walls and raking out joint 200 mm deep
Rate as per SSR 10.00 sqm 5.00 10 sqm
Add for MA @ 40% 0.40 5.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 0.70
Rate per 1 sqm
say
2 Dismantling doors , windows and clear storey windows, Ventilators etc., ( wood or steel ) shutters includin
Chowkhats , architraves,hold fasts and other attachments etc., and stacking them within 100m lead includin
labour charge etc., and overheads & contractors profit complete for finished item of work
(BLD-CSTN-14-11)
a) Not exceeding 3 sqm in area :
Details of cost per each :
2nd class mason 0.10 Nos. 405.00 1 No.
Mazdoor(Male) 0.20 Nos. 350.00 1 No.
2nd class Blacksmith 0.05 Nos. 405.00 1 No.
Add for MA @ 40% 0.40 130.75
1 Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wa
in ordinary soils and depositing on bank with an initial lead of 10m and depth up to 3m including a
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads
contractors profit complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APS
308)
(BLD-CSTN-2-1)
Ordinary Soil - Manual Means up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
CIVIL DATA : Page-98
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Mazdoor ( Unskilled) 3.64 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 1274.00
b&c)
Overheads&Contractors Profit @13.615% 0.13615 1783.60
Cost for 10 cum ( a+b+c)
Rate per cum (a+b+c) / 10
Rate per 1 cum Say
2 Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wa
in ordinary soils and depositing on bank with an initial lead of 10m and 1m additional lift charges over th
initial depth up to 3m including all operational,incidental, labour charges such as shoring, sheeting, plankin
strutting etc., and overheads & contractors profit complete for finished item of work excluding dewatering charge
etc., as per SS 20 B(APSS 308)
(BLD-CSTN-2-1& COM-LDLFT-6-66)
Rate with initial lead & lift 1.00 cum 202.64 1 cum
Mazdoor for extra lift ( 1 No. for 60m) 0.02 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 7.00
Overheads&Contractors Profit @13.615% 0.13615 9.80
Rate per 1 cum
Say
2 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and depositin
on bank for all lifts and with an initial lead of 10m and up to 3m depth including all operational, incidenta
labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit comple
for finished item of work excluding dewatering charges etc., as per SS 20 B(APSS 308).
(BLKD-CSTN-2-2)
Ordinary Soil - Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 240.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 2912.00
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2565.50 1 Hour
Crew charges 6.00 hours 237.90 1 Hour
Add MA on crew charges 0.40 1427.40
c&d)
Overheads&Contractors Profit @13.615% 0.13615 21468.16
Cost for 240 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 240
Say
3 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and depositin
on bank for all lifts and with an initial lead of 10m and 3m to 6m depth including all operational,incidenta
labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit comple
for finished item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)
(BLKD-CSTN-2-3)
Ordinary Soil - Mechanical Means up to 3m to 6m depth
Unit : 1 cum
CIVIL DATA : Page-99
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Taking output : 210.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 2912.00
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2565.50 1 Hour
Crew charges 6.00 hours 237.90 1 Hour
Add MA on crew charges 0.40 1427.40
c&d)
Overheads&Contractors Profit @13.615% 0.13615 21468.16
Cost for 210 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 210
Rate per 1 cum Say
4 Earth work excavation for foundations (Manual Means) of buildings in ordinary rock ( not requirin
blasting ) and depositing on bank with an initial lead of 10m and depth up to 3m including a
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads
contractors profit complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APS
308)
(BLD-CSTN-2-4)
Ordinary rock(not requiring blasting) - Manual Means up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Mazdoor ( Unskilled) 5.20 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 1820.00
b&c)
Overheads&Contractors Profit @13.615% 0.13615 2548.00
Cost for 10 cum ( a+b+c)
Rate per 1 cum (a+b+c) / 10
Rate per 1 cum Say
5 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary rock (not requirin
blasting) and depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth including a
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads
contractors profit complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APS
308)
(BLKD-CSTN-2-5)
Ordinary rock(not requiring blasting)- Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 180.00 cum
a) Labour
Mazdoor ( Unskilled) 6.24 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 2184.00
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2565.50 1 Hour
Crew charges 6.00 hours 237.90 1 Hour
Add MA on crew charges 0.40 1427.40
c&d)
Overheads&Contractors Profit @13.615% 0.13615 20448.96
CIVIL DATA : Page-100
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Cost for 180 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 180
Rate per 1 cum Say
6 Earth work excavation for foundations for buildings in hard rock (requiring blasting) and depositing o
bank for all lifts and with an initial lead of 10m and up to 3m depth including all operational,incidental, labo
charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete fo
finished item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)
(BLKD-CSTN-2-6)
Hard rock (requiring blasting)- up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Driller 0.50 Nos. 445.00 1 No.
Blaster 0.25 Nos. 515.00 1 No.
Mazdoor ( Unskilled) 8.35 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 3273.75
b) Machinery
Air compressor 7cmm (diesel) 1.00 hour 963.70 1 Hour
Jack hammer/Pneumatic braker 2.00 hours 19.40 1 Hour
Crew charges
Air compressor 1.00 Hours 210.90 1 Hour
Jack hammer/Pneumatic braker 2.00 Hours 329.60 1 Hour
Add MA on crew charges 0.40 870.10
c)Material
Gelatin 80% 3.50 Kgs 73.00 1 Kg
Detonator electric 14 Nos. 10.00 1 No.
c&d)
Overheads&Contractors Profit @13.615% 0.13615 7199.39
Cost for 10 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 10
Rate per 1 cum Say
7 Earth work excavation for foundations for buildings in hard rock (blasting prohibited) and depositing o
bank for all lifts and with an initial lead of 10m and up to 3m depth including all operational,incidental, labo
charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete fo
finished item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)
(BLKD-CSTN-2-7)
Hard rock (blasting prohibited)- up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Mazdoor ( Unskilled) 5.20 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 1820.00
b) Machinery
Air compressor 6.00 Hours 963.70 1 Hour
Jack hammer/Pneumatic braker 12.00 Hours 19.40 1 Hour
Crew charges
Air compressor 6.00 Hours 210.90 1 Hour
Jack hammer/Pneumatic braker 12.00 Hours 329.60 1 Hour
Add MA on crew charges 0.40 5220.60
CIVIL DATA : Page-101
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
c&d)
Overheads&Contractors Profit @13.615% 0.13615 15871.84
Cost for 10 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 10
Rate per 1 cum Say
3 Conveyance of un-useful excavated earth to a distance of 5 KM for disposal including hire charges of T
P, labour charges etc., and overheads & contractors profit complete for finished item of work.
Rate as per SoR 1 cum 84.00 1 cum
Rate per 1 cum Say
CIVIL DATA : Page-102
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
4 Providing anti termite treatment as per IS 6315 (Part-2) 2001 (pre-constructional chemical treatmen
measures) along the internal & external vertical faces of the columns, plinth beams, basement and top surfac
of the basement filling below flooring bed as per the specified procedure confirming to IS 6315 (Part-2) 2001 an
other relevent approved specification duly using Chlorpyriphos / Lindane emulsifiable concentrate 20% with 1%
concentration @ 7.5 Liters/sqm of the vertical surface & 5.0 Liters/sqm of the horizontal surface of th
substructure to a depth of 500mm around columns & 300mm deep around plinth beams, basements & floor fillin
area including excavation channel along the wall & rodding etc & cost & conveyane of all materials to the sit
cost of labour for spraying, rodding etc complete for finished item of work as per the approval of the Engineer-in
Charge. ( The rate includes overheads & contractors profit )
(BLD-CSTN-16-1)
Unit : 10sqm
A)Materials
Chloropyriphos Lindane Emulsifiable
concentrate of 20% 4.10 Ltrs 228.00 1 Ltr
B)Water charges 1% 0.01 934.80
C)Labour charges
Man Mazdoor 3.00 Nos. 350.00 1 No.
Sprayer 0.22 Nos. 400.00 1 No.
Add for MA @ 40% 0.40 1138.00
D)Hire charges
Sprayer , drilling machine etc., 10% 0.10 2537.35
Sundries and contingencies 3% 0.03 2537.35
Water charges&Electricity 1.50% 0.015 2537.35
5 Filling with carted coarse sand in trenches,sides of foundations and basement with initial lead in layers n
exceeding 15cm thick,watering and ramming including cost and conveyance of water to work site and a
peraitonal,incidental ,labour charges,hire charges of T&P etc., and overheads & contractors profit complete fo
fnished item of work(APSS NO.309&310)
5 Filling with carted gravel in trenches,sides of foundations and basement with initial lead in layers not exceedin
15cm thick,watering and ramming including cost and conveyance of water to work site and a
peraitonal,incidental, labour charges,hire charges of T&P etc., and overheads & contractors profit complete fo
fnished item of work(APSS NO.309&310)
(BLD-CSTN-2-8) & Amendment in SoR 2011-12
Unit : 1 cum
CIVIL DATA : Page-103
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Taking output = 6 cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 108.50
b)Material :
Gravel 6.00 cum 354.38 1 cum
Water 0.72 Kl 103.00 1 Kl
Rate per 6 cum (a+b+c)
Overheads&Contractors Profit @13.615% 0.13615 2352.34
Rate per 6 cum
Rate per 1 cum
Say
CIVIL DATA : Page-104
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
6 Filling with useful available excavated earth (excluding rock) with a lead of 50 m in trenches, sides
foundations and basement with initial lead in layers not exceeding 15cm thick, watering and ramming includin
cost and conveyance of water to work site and all operaitonal, incidental, labour charges, hire charges of T&
etc., and overheads & contractors profit complete for fnished item of work (APSS NO.309&310).
7 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations and und
flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved quar
including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, includin
sales & other taxes on all materials and including all charges for machine mixing, laying concrete in foundation
and under flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc., an
overheads & contractors profit complete for finished item of work. (APSS No. 402)
(BLD-CSTN-3-5)
Unit : 1 cum
A.MATERIALS :
Cement 162.00 Kgs 6000.00 1000 Kgs
Coarse aggregate 40mm 0.90 Cum 1214.67 1 Cum
Fine aggregate ( Sand ) 0.45 Cum 2297.45 1 Cum
Water (including curing) 1.20 kl 103.00 1 kl
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 133.50 1 hour
Crew charges 1.00 hour 219.70 1 hour
Add MA on crew charges 0.40 219.70
C.LABOUR :
1st class mason 0.10 Nos. 445.00 1 Each
Mazdoor (unskilled) 1.39 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 531.00
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
8 Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for foundations and und
flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved quar
including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, sales
other taxes on all materials and including all charges for machine mixing, laying concrete in foundations an
under flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc.,and overhead
& contractors profit complete for finished item of work. (APSS No. 402)
(BLD-CSTN-3-7)
Unit : 1 cum
A.MATERIALS :
Cement 129.60 Kgs 6000.00 1000 Kgs
Coarse aggregate 40mm 0.90 Cum 1214.67 1 Cum
Fine aggregate ( Sand ) 0.45 Cum 2297.45 1 Cum
Water (including curing) 1.20 kl 103.00 1 kl
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 133.50 1 hour
Crew charges 1.00 hour 219.70 1 hour
Add MA on crew charges 0.40 219.70
C.LABOUR :
1st class mason 0.10 Nos. 445.00 1 Each
Mazdoor (unskilled) 1.39 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 531.00
9 Random Rubble stone masonry in CM (1:8) prop: (Cement: Screened sand) using hard other than granit
stones carted from approved quarry including cost and conveyance of all materials like cement, screened san
water, stones etc., from approved quarry, to site, sales & other taxes on all materials including labour for cuttin
stones to required size and shape, mixing, of cement, mortar, construction, curing etc.,and overheads
contractors profit complete for finished item of work in foundation and basement. (APSS No. 601 & 615)
( BLD-CSTN-6-13 )
Unit = 1 cum
A.MATERIALS
Cement 59.40 Kgs 6000.00 1000 Kgs
Rough stone (OTG) 1.10 Cum 529.67 1 Cum
Fine aggregate(sand) 0.33 Cum 2497.45 1 Cum
B) LABOUR
1st class mason 1.20 Nos. 445.00 1 Each
Mazdoor (unskilled) 2.00 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 1234.00
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
10 Random Rubble stone masonry in CM (1:8) prop: (Cement: Screened sand) using hard granite stones
carted from approved quarry including cost and conveyance of all materials like cement, screened sand, wate
stones etc., from approved quarry, to site, sales & other taxes on all materials including labour for cutting stone
to required size and shape, mixing, of cement, mortar, construction, curing etc.,and overheads & contracto
profit complete for finished item of work in foundation and basement. (APSS No. 601 & 615)
( BLD-CSTN-6-13 )
Unit = 1 cum
A.MATERIALS
Cement 59.40 Kgs 6000.00 1000 Kgs
Rough stone (HBG) 1.10 Cum 621.67 1 Cum
Fine aggregate(sand) 0.33 Cum 2497.45 1 Cum
B) LABOUR
1st class mason 1.20 Nos. 445.00 1 Each
Mazdoor (unskilled) 2.00 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 1234.00
9 Vibrated Plain Cement Concrete (1:3:6) nominal mix using 40mm size machine crushed hard granite met
and 20mm graded machine crushed hard granite metal (coarse aggregate) in (2:1) ratio from approved quar
including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water et
to site, sales & other taxes on all materials, all charges for mixing, laying concrete in position, vibrating, curin
centering charges, overheads & contractors profit etc.,for finished item of work for footings and basement.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Overheads&Contractors Profit @13.615% 0.13615 5525.73
Rate per 1 cum
Say
10 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum ceme
content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size graded machin
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) fro
approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coars
aggregate, water etc., to site and sales & other taxes on all materials , centering using Steel scaffolding pipes
jack props , wallers , Foot plates , brackets , steel centering plates etc., including all operational, incidental an
labour charges such as weigh batching, machine mixing, laying concrete, curing etc., and overheads
contractors profit complete but excluding cost of steel and its fabrication charges for finished item of work (APS
No. 402).
(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 380.00 Kgs 6000.00 1000 Kgs
20mm HBG graded metal 0.80 Cum 1477.05 1 Cum
Sand 0.40 Cum 2297.45 1 Cum
B.LABOUR :
1st class Mason 0.133 Nos 445.00 1 Each
2nd class Mason 0.267 Nos 405.00 1 Each
Mazdoor (both men&women) 4.60 Nos 350.00 1 Each
Add for MA @ 40% 0.40 1777.32
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 226.30 1 hour
Crew charges 1.333 hours 342.50 1 hour
Needle vibrator 40mm ( petrol ) 1.333 hours 25.80 1 hour
Crew charges 1.333 hours 158.20 1 hour
Add MA on crew charges 0.40 667.43
Water(including for curing) 1.20 kl 103.00 1 kl
Rate per 1 cum
a Footings
Rate for Design mix M 25 1.00 Cum 8262.92 1 Cum
Hire charges of centering and scaffolding 1.00 Cum 277.00 1 Cum
Labour charges 1.00 Cum 532.00 1 Cum
Add for MA @ 40% 0.40 532.00
b Column pedestals
Rate for Design mix M 25 1.00 Cum 8262.92 1 Cum
Hire charges of centering and scaffolding 1.00 Cum 315.00 1 Cum
Labour charges 1.00 Cum 845.00 1 Cum
Add for MA @ 40% 0.40 845.00
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
c Plinth Beams
Rate for Design mix M 25 1.00 Cum 8262.92 1 Cum
Hire charges of centering and scaffolding 1.00 Cum 1335.00 1 Cum
Labour charges 1.00 Cum 1281.00 1 Cum
Add for MA @ 40% 0.40 1281.00
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
d Base slab 230mm thick for Sump / Septic tank :
Rate for Design mix M 25 0.23 Cum 8262.92 1 Cum
Hire charges of centering and scaffolding 0.23 Cum 277.00 1 Cum
Labour charges 0.23 Cum 532.00 1 Cum
Add for MA @ 40% 0.40 122.36
e) Haunch
Rate for Design mix M 25 1.00 Cum 8262.92 1 Cum
Overheads&Contractors Profit @13.615%
0.13615 8262.92
Rate per 1 cum
Say
11 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum ceme
content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size graded machin
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) fro
approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coars
aggregate, water etc., to site and sales & other taxes on all materials, centering using Casurina Ballie
Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., including all operational, incidental an
labour charges such as weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing
overheads & contractors profit etc., complete but excluding cost of steel and its fabrication charges for finishe
item of work (APSS No. 402)
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 380.00 Kgs 6000.00 1000 Kgs
20mm HBG graded metal 0.80 Cum 1477.05 1 Cum
Sand 0.40 Cum 2297.45 1 Cum
B.LABOUR :
1st class Mason 0.167 Nos 445.00 1 Each
2nd class Mason 0.167 Nos 405.00 1 Each
Mazdoor (both men&women) 5.60 Nos 350.00 1 Each
Add for MA @ 40% 0.40 2101.95
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 226.30 1 hour
Crew charges 1.333 hours 342.50 1 hour
Needle vibrator 40mm ( petrol ) 1.333 hours 25.80 1 hour
Crew charges 1.333 hours 158.20 1 hour
Add MA on crew charges 0.40 667.43
Water(including for curing) 1.20 kl 103.00 1 kl
Rate per 1 cum
a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF
Rate as above 8717.41 8717.41 8717.41
Hire charges of centering and scaffolding 229.00 229.00 229.00
Labour charges 1491.00 1640.00 1789.00
Add for MA @ 40% 596.40 656.00 715.60
Lift charges of materials(Manual) 0.00 210.20 420.39
CIVIL DATA : Page-110
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Add for MA @ 40% 0.00 84.08 168.16
Rate per 1 cum 11033.81 11536.68 12039.56
Overheads&Contractors Profit @13.615% 1502.25 1570.72 1639.19
Rate per 1 cum 12536.06 13107.40 13678.75
Say 12536 13107 13679
CIVIL DATA : Page-111
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
b) LINTELS :
Rate for other Floors FF SF TF
Rate as above 8717.41 8717.41 8717.41
Hire charges of centering and scaffolding 760.00 760.00 760.00
Labour charges 1062.00 1168.00 1274.00
Add for MA @ 40% 424.80 467.20 509.60
Lift charges of materials(Manual) 0.00 210.20 420.39
Add for MA @ 40% 0.00 84.08 168.16
Rate per 1 cum 10964.21 11406.88 11849.56
Overheads&Contractors Profit @13.615% 1492.78 1553.05 1613.32
Rate per 1 cum 12456.99 12959.93 13462.88
Say 12457 12960 13463
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
12 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum ceme
content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size graded machin
crushed hard granite metal(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approve
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, wate
etc., to site and sales & other taxes on all materials , centering using Casurina Ballies , Bamboos , Woode
Reapers , Runners , Wood Posts , Wall Plates etc., including all operational, incidental and labour charges suc
as weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing , overheads
contractors profit etc., complete but excluding cost of steel and its fabrication charges for finished item of wo
(APSS No. 402)
(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 380.00 Kgs 6000.00 1000 Kgs
20mm HBG graded metal 0.80 Cum 1477.05 1 Cum
Sand 0.40 Cum 2297.45 1 Cum
B.LABOUR :
1st class Mason 0.067 Nos 445.00 1 Each
2nd class Mason 0.133 Nos 405.00 1 Each
Mazdoor (both men&women) 3.077 Nos 350.00 1 Each
Add for MA @ 40% 0.40 1160.63
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 226.30 1 hour
Crew charges 0.308 hours 342.50 1 hour
Needle vibrator 40mm ( petrol ) 0.308 hours 25.80 1 hour
Crew charges 0.308 hours 158.20 1 hour
Add MA on crew charges 0.40 154.22
Water(including for curing) 1.20 kl 103.00 1 kl
Rate per 1 cum
A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF
Rate as above 6422.65 6422.65 6422.65
Hire charges of centering and scaffolding 1342.00 1342.00 1342.00
Labour , lift charges for scaffolding 1251.00 1376.00 1501.00
Add for MA @ 40% 500.40 550.40 600.40
Lift charges of materials(Manual) 0.00 116.06 232.13
Add for MA @ 40% 0.00 46.43 92.85
Rate for 1 cum 9516.05 9853.54 10191.03
Overheads&Contractors Profit @13.615% 1295.61 1341.56 1387.51
Rate per 1 cum 10811.66 11195.10 11578.54
Say 10812 11195 11579
B) RCC SLABS :
a) Roof Slabs 115mm thick :
un supported height up to 3.66 m
Rate for Design mix M 25 0.115 Cum 6422.65 1 Cum
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Add for MA @ 40% 0.00 5.34 10.68
Rate per 1 sqm 1089.40 1127.69 1165.98
Overheads&Contractors Profit @13.615% 148.32 153.54 158.75
Rate per 1 sqm 1237.72 1281.23 1324.73
Say 1238 1281 1325
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
c) Roof Slabs 150mm thick :
Rate for Design mix M 25 0.15 Cum 6422.65 1 Cum
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
13 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum ceme
content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size graded machin
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) fro
approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coars
aggregate, water etc., to site and including sales & other taxes on all materials , centering using Casurin
Ballies , Bamboos , Wooden Reapers , Runners , Wood Posts , Wall Plates etc., for 60cm wide sun-shade
7.5cm thick at fixed end and 5cm thick at free end with an average thickness of 6.25cm including a
operational, incidental and labour charges such as weigh batching, machine mixing, lifting of concrete manuall
laying concrete, curing, overheads & contractors profit complete etc., but excluding cost of steel and i
fabrication charges for finished item of work (APSS No. 402, 403 & 903)
(BLD-CSTN-3-16)
A.MATERIALS :
Cement 380.00 Kgs 6000.00 1000 Kgs
20mm HBG graded metal 0.80 Cum 1477.05 1 Cum
Sand 0.40 Cum 2297.45 1 Cum
B.LABOUR :
1st class Mason 0.067 Nos 445.00 1 Each
2nd class Mason 0.133 Nos 405.00 1 Each
Mazdoor (both men&women) 3.077 Nos 350.00 1 Each
Add for MA @ 40% 0.40 1160.63
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 226.30 1 hour
Crew charges 0.308 hours 342.50 1 hour
Add MA on crew charges 0.40 105.49
Water(including for curing) 1.20 kl 103.00 1 kl
Rate per 1 cum
14 Brick masonry for panel walls 340mm thick in superstructure with CM (1:8) prop: (Cement : Screene
sand) using common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or tradition
size 23 x 11 x 7 cms from approved source having minimum crushing strength of 40 Kg/Sqcm. including co
and conveyance of all materials like cement, screened sand, bricks, water etc., to site, including sales & othe
taxes on all materials and such as labour charges, like mixing cement mortar, scaffolding charges, constructin
masonry, lift charges, curing, etc.,and overheads & contractors profit complete for finished item of work. (APS
No. 501 & 504).
(BLD-CSTN-5-5)
Unit : 1cum
A.MATERIALS :
Cement 36.00 Kgs 6000.00 1000 Kgs
Common burnt clay bricks 23x11x7cms 512 Nos 5852.80 1000 Nos
CIVIL DATA : Page-116
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Fine aggregate ( Sand ) 0.20 cu.m. 2497.45 1 cu.m.
B.LABOUR :
1st class mason 0.24 Nos. 445.00 1 Each
2nd class mason 0.56 Nos. 405.00 1 Each
Mazdoor (Unskilled) 1.89 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 995.10
water charges @ 1% 0.01 5105.26
Rate per 1 cum
Hire charges for Access Scaffolding 1.00 Cum 29.21 1.00 sqm
Labour charges for scaffolding 1.00 Cum 199.82 1.00 sqm
Add for MA @ 40% 0.40 199.82
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
15 Brick masonry for panel walls in superstructure with CM (1:8) prop: (Cement : Screened sand) usin
common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size 23 x 11 x
cms from approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance
all materials like cement, screened sand, bricks, water etc., to site, including sales & other taxes on all materia
and such as labour charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift charge
curing, etc.,and overheads & contractors profit complete for finished item of work. (APSS No. 501 & 504).
(BLD-CSTN-5-5)
Unit : 1cum
A.MATERIALS :
Cement 36.00 Kgs 6000.00 1000 Kgs
Common burnt clay bricks 23x11x7cms 512 Nos 5852.80 1000 Nos
Fine aggregate ( Sand ) 0.20 cu.m. 2497.45 1 cu.m.
B.LABOUR :
1st class mason 0.24 Nos. 445.00 1 Each
2nd class mason 0.56 Nos. 405.00 1 Each
Mazdoor (Unskilled) 1.89 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 995.10
water charges @ 1% 0.01 5105.26
Rate per 1 cum
a Up to basement
Rate as worked out above 1.00 Cum 5156.32 1 Cum
Overheads&Contractors Profit @13.615% 0.13615 5156.32
Rate per 1 cum
Say
b) Superstructure :
Rate for other Floors FF SF TF 4F
Rate as worked out above 5156.32 5156.32 5156.32 5156.32
Hire charges for Access Scaffolding 43.17 43.17 43.17 43.17
Labour charges for scaffolding 295.39 421.48 547.61 673.70
Add for MA @ 40% 118.16 168.59 219.04 269.48
Lift charges ( Page 131 of Std. Data ) 0.00 99.51 199.02 298.53
Add for MA @ 40% 0.00 39.80 79.61 119.41
Rate per 1 cum 5613.04 5928.88 6244.77 6560.61
Overheads&Contractors Profit @13.615% 764.21 807.22 850.23 893.23
Rate per 1 cum 6377.25 6736.10 7095.00 7453.84
Say 6377 6736 7095 7454
CIVIL DATA : Page-118
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
16 Reinforced Brick Masonry for partition walls (11.0 cm thick) in CM (1:4) prop. (Cement : Screened san
using common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size 2
x 11 x 7 cms from approved source having minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
6mm M.S plain rods in every third layer with free ends of the reinforcement pegged into mortar joints of ma
brick walls where applicable including cost and conveyance of all materials like cement, steel, sand, bricks, wat
etc., to site, including sales & other taxes on all materials, all operational, incidental charges such as labou
charges for mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing, etc., an
overheads & contractors profit but excluding cost of steel and its fabrication charges complete for finished ite
of work. (APSS No. of 501 & 509).
(BLD-CSTN-5-12)
Unit - 10sqm
A.MATERIALS :
Common burnt clay bricks 23x11x7cms 565 Nos. 5852.80 1000 Nos.
Cement 79.20 Kgs 6000.00 1000 Kgs
Fine aggregate ( Sand ) 0.22 cu.m. 2497.45 1 cu.m.
B.LABOUR :
1st class mason 0.60 Nos. 445.00 1 Each
2nd class mason 0.60 Nos. 405.00 1 Each
Mazdoor (Unskilled) 2.75 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 1472.50
water charges @ 1% 0.01 6392.97
Rate per 10 sqm
Rate per 1 sqm
17 Masonry work in CM(1:6) prop (Cement : Screened sand) in superstructure with fly ash cement / lime sol
blocks of size 290mm x 225mm x 140mm from approved source having minimum crushing strength of 5
Kg/Sqcm. including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, includin
sales & other taxes on all materials and such as labour charges, like mixing cement mortar, scaffolding charge
constructing masonry, lift charges, curing, overheads and contrctor profit etc., complete for finished item of wor
(APSS No. 501 & 504).
(BLD-CSTN-5-17)
Unit = 1 Cum
A.MATERIALS
No of blocks required for
1 Cum of Masonry 110 Nos 27401.36 1000 Nos
Cement 24.00 Kgs 6000.00 1000 Kgs
Fine aggregate ( Sand ) 0.10 cu.m. 2497.45 1 cu.m.
B .LABOUR
Mason 1st class 0.42 Nos. 445.00 1 Each
Mason 2nd class 0.92 Nos. 405.00 1 Each
Man Mazdoor 0.70 Nos. 350.00 1 Each
Woman Mazdoor 2.10 Nos. 350.00 1 Each
CIVIL DATA : Page-119
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Add for MA @ 40% 0.40 1539.50
water charges @ 1% 0.01 5563.19
Rate per 1 cum
b) Superstructure :
Rate for other Floors FF SF TF 4F
Rate as worked out above 5618.83 5618.83 5618.83 5618.83
Hire charges for Access Scaffolding 44.13 44.13 44.13 44.13
Labour charges for scaffolding 301.96 430.84 559.78 688.67
Add for MA @ 40% 120.78 172.34 223.91 275.47
Lift charges ( Page 131 of Std. Data ) 0.00 153.95 307.90 461.85
Add for MA @ 40% 0.00 61.58 123.16 184.74
6085.70 6481.67 6877.71 7273.69
Overheads&Contractors Profit @13.615% 828.57 882.48 936.40 990.31
Rate per 1 cum 6914.27 7364.15 7814.11 8264.00
Say 6914 7364 7814 8264
18 Reinforced Masonry for partition walls (100 mm thick) in CM (1:4) prop. (Cement : Screened sand) using f
ash cement / lime solid blocks of size 290mm x 100mm x 140mm having minimum compressive strength
50 Kg/Sq.cmand placing 2 Nos. of 6mm M.S plain rods in every third layer with free ends of the reinforceme
pegged into mortar joints of main brick walls where applicable including cost and conveyance of all materials lik
cement, steel, sand, bricks, water etc., to site, including sales & other taxes on all materials, all operationa
incidental charges such as labour charges for mixing cement mortar, scaffolding charges, constructing masonr
lift charges, curing, etc., and overheads & contractors profit but excluding cost of steel and its fabricatio
charges complete for finished item of work. (APSS No. of 509)
(BLD-CSTN-5-12)
Unit - 10sqm
A.MATERIALS :
Flyash lime solid blocks 247 Nos. 12511.72 1000 Nos.
Cement 36.00 Kgs 6000.00 1000 Kgs
Fine aggregate ( Sand ) 0.10 cu.m. 2497.45 1 cu.m.
B.LABOUR :
1st class mason 0.60 Nos. 445.00 1 Each
2nd class mason 0.60 Nos. 405.00 1 Each
Mazdoor (Unskilled) 2.75 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 1472.50
water charges @ 1% 0.01 5617.64
Rate per 10 sqm
Rate per 1 sqm
Internal walls :
Rate for other Floors FF SF TF 4F
Rate as worked out above 567.38 567.38 567.38 567.38
Hire charges for Access Scaffolding 9.93 9.93 9.93 9.93
Labour charges for scaffolding 67.94 96.94 125.95 154.95
Add for MA @ 40% 27.18 38.78 50.38 61.98
Lift charges ( Page 131 of Std. Data ) 0.00 14.73 29.45 44.18
Add for MA @ 40% 0.00 5.89 11.78 17.67
CIVIL DATA : Page-120
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate per 1 sqm 672.43 733.65 794.87 856.09
Overheads&Contractors Profit @13.615% 91.55 99.89 108.22 116.56
Rate per 1 sqm 763.98 833.54 903.09 972.65
Say 764 834 903 973
17 Plain Cement Concrete (1:3:6) nominal mix using 20mm size graded machine crushed hard granite met
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost an
conveyance of all materials like cement, fine aggregate(sand), coarse aggregate, water etc. to site, includin
sales & other taxes on all materials and including all charges for mixing, laying concrete in position, curing etc.,
lift charges , and overheads & contractors profit for Bed Blocks & Hold Fasts for finished item of work. (APS
No. 402)
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate for other Floors FF SF TF 4F
Rate as worked out above 4991.28 4991.28 4991.28 4991.28
Hire charges of centering and scaffolding 61.00 61.00 61.00 61.00
Lift charges for scaffolding 274.00 301.40 328.80 356.20
Add for MA @ 40% 109.60 120.56 131.52 142.48
Lift charges ( Page 131 of Std. Data ) 0.00 53.10 106.20 159.30
Add for MA @ 40% 0.00 21.24 42.48 63.72
Rate per 1 cum 5435.88 5548.58 5661.28 5773.98
Overheads&Contractors Profit @13.615% 740.09 755.44 770.78 786.13
Rate per 1 cum 6175.97 6304.02 6432.06 6560.11
say 6176 6304 6432 6560
18 Plain Cement Concrete M 20 nominal mix using WEIGH BATCHER / MIXER, 20mm size hard granite machin
crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approve
quarry, using a minimum quantity of 300 kgs. of cement per 1 cum of concrete including cost and conveyance o
all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including steel centerin
shuttering, machine mixing, lift charges, laying concrete,vibrating, curing, overheads & contrctors profit etc
complete for finished item of work for coping on top of compound wall (APSS No. 402 & 403).
(BLD-CSTN-3-11)
Unit : 1 cum
A.MATERIALS :
Cement 300.00 Kgs 6000.00 1000 Kgs
20mm HBG graded metal 0.90 Cum 1584.67 1 Cum
Fine aggregate ( Sand ) 0.45 Cum 2297.45 1 Cum
Water (including curing) 1.20 kl 103.00 1 kl
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 133.50 1 hour
Crew charges 1.00 hour 219.70 1 hour
Add MA on crew charges 0.40 219.70
C.LABOUR :
1st class mason 0.10 Nos. 445.00 1 Each
Mazdoor (unskilled) 1.39 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 531.00
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
19 Plain Cement Concrete M 20 design mix using WEIGH BATCHER / MIXER, 20mm size hard granite machin
crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approve
quarry, using a minimum quantity of 330 kgs. of cement per 1 cum of concrete including cost and conveyance o
all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including steel centerin
shuttering, machine mixing, lift charges, laying concrete,vibrating, curing, overheads & contrctors profit etc
complete for finished item of work (APSS No. 402 & 403) for steps.
(BLD-CSTN-3-16)
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.80 Cum 1477.05 1 Cum
Sand 0.40 Cum 2297.45 1 Cum
Cement 330.00 Kgs 6000.00 1000 Kgs
Water ( including for curing ) 1.20 Kl 103.00 1 Kl
B.MACHINERY :
Batching plant 0.50 cum 0.308 hour 226.30 1 hour
Crew charges 0.308 hour 342.50 1 hour
Needle vibrator 40mm ( petrol ) 0.308 hours 25.80 1 hour
Crew charges 0.308 hours 158.20 1 hour
Add MA on crew charges 0.40 154.22
C.LABOUR :
1st class mason 0.067 Nos. 445.00 1 Each
2nd class mason 0.067 Nos. 405.00 1 Each
Mazdoor (Unskilled) 3.077 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 1133.90
Rate per 1 cum
20 Reinforced Cement Concrete M 20 design mix using 12mm size hard granite machine crushed graded met
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry, using a minimu
quantity of 350 kgs. of cement per 1 cum of concrete using WEIGH BATCHER / MIXER including cost an
conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site includin
steel centering, shuttering, machine mixing, laying concrete, lift charges, curing etc., and overheads
contractors profit complete for finished item of work (APSS No. 402 & 403) for sill slabs.
(BLD-CSTN-3-13 - A)
A.MATERIALS :
Cement 350.00 Kgs 6000.00 1000 Kgs
12mm HBG graded metal 0.80 Cum 1362.17 1 Cum
Sand 0.40 Cum 2297.45 1 Cum
B.LABOUR :
1st class Mason 0.133 Nos 445.00 1 Each
2nd class Mason 0.267 Nos 405.00 1 Each
Mazdoor (both men&women) 3.60 Nos 350.00 1 Each
CIVIL DATA : Page-123
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Add for MA @ 40% 0.40 1427.32
C.MACHINERY :
Batching plant 0.50 cum 0.308 hour 226.30 1 hour
Crew charges 0.308 hour 342.50 1 hour
Add MA on crew charges 0.40 105.49
Water(including for curing) 1.20 kl 103.00 1 kl
Basic cost per 1 cum
21 Reinforced Cement Concrete M 20 design mix using 12mm size hard granite machine crushed graded met
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry, using a minimu
quantity of 350 kgs. of cement per 1 cum of concrete using WEIGH BATCHER / MIXER including cost an
conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site includin
steel centering, shuttering, labour charges such as weigh batching, machine mixing, laying concrete, l
charges, curing etc., and overheads & contractors profit complete for finished item of work (APSS No. 402
403) for platforms and shelves.
(BLD-CSTN-3-16)
A.MATERIALS :
Cement 350.00 Kgs 6000.00 1000 Kgs
12mm HBG graded metal 0.80 Cum 1362.17 1 Cum
Sand 0.40 Cum 2297.45 1 Cum
B.LABOUR :
1st class Mason 0.067 Nos 445.00 1 Each
2nd class Mason 0.133 Nos 405.00 1 Each
Mazdoor (both men&women) 3.077 Nos 350.00 1 Each
Add for MA @ 40% 0.40 1160.63
C.MACHINERY :
Batching plant 0.50 cum 0.308 hour 226.30 1 hour
Crew charges 0.308 hour 342.50 1 hour
Add MA on crew charges 0.40 105.49
Water(including for curing) 1.20 kl 103.00 1 kl
Basic cost per 1cum
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Add for MA @ 40% 0.00 2.32 4.64 6.96
Rate per 1 sqm 479.13 497.05 514.98 533.60
Overheads&Contractors Profit @13.615% 65.23 67.67 70.11 72.65
Rate per 1 sqm 544.36 564.73 585.09 606.25
Say 544 565 585 606
CIVIL DATA : Page-125
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
b) 25mm thick shelves :
Cost of M 20 design mix 0.025 cum 6074.58 1 cum
Rate per 1sqm
21 Providing High Yield Strength Deformed (HYSD) (Fe 415 grade as per IS 1786-1979) of differen
diameters for RCC works , including labour charges for straightening, cutting, bending to required sizes an
shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing wi
binding wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, includin
cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer ba
including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour charges suc
as cutting, bending, placing in position, tying including sales and other taxes on all materials etc. ,and overhead
& contractors profit complete for finished item of work.( APSS No.126)
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
22 Providing Thermo Mechanically Treated (TMT) (Fe 500 grade as per IS 1786-1979) of different diameter
for RCC works , including labour charges for straightening, cutting, bending to required sizes and shape
placing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wi
of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost an
conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including co
and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cuttin
bending, placing in position, tying including sales and other taxes on all materials etc. ,and overheads
contractors profit complete for finished item of work.( APSS No.126)
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
23 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS 432) of different diameters including labo
charges for straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks
approved materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills f
reinforcement work as per approved designs and drawings, including cost and conveyance of steel bar
including all wastages such as overlaps, couplings, chairs, spacer bars including cost and conveyance of bindin
wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in positio
tying including sales and other taxes on all materials etc. ,and overheads & contractors profit complete fo
finished item of work.( APSS No.126)
24 Ornamental ceiling plastering 12mm thick in two coats using screened sand with base coat of 8mm thick
CM (1:6) and top coat of 4mm thick in CM (1:4) with dubara sponge finishing including cost and conveyance
all materials like cement, sand, water etc., to site, including sales & other taxes on all materials, and a
operational, incidental charges on materials and including cost of all labour charges for mixing mortar, finishin
scaffolding, lift charges, curing, including cutting grooves as directed by Engineer - in - charge etc., an
overheads & contractors profit complete for finished item of work. (SS 901,903 & 904)
(BLD-CSTN-8-3)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.11 Cum 2497.45 1 Cum
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.04 Cum 2497.45 1 Cum
B.LABOUR :
1st Class Mason 0.63 Nos. 445.00 1 Each
2nd Class Mason 1.47 Nos. 405.00 1 Each
Mazdoor (Unskilled) 3.90 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2240.70
water charges @ 1% 0.01 3756.40
Rate per 10 Sqm
CIVIL DATA : Page-128
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate per 1 Sqm
CIVIL DATA : Page-129
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate for other Floors FF SF TF 4F
Rate as worked out above 379.40 379.40 379.40 379.40
Hire charges for Access Scaffolding 2.37 2.37 2.37 2.37
Labour charges for scaffolding 13.70 19.37 25.04 30.71
Add for MA @ 40% 5.48 7.75 10.02 12.28
Lift charges ( Page 131 of Std. Data ) 0.00 22.41 44.81 67.22
Add for MA @ 40% 0.00 8.96 17.92 26.89
Rate per 1 Sqm 400.95 440.26 479.56 518.87
Overheads&Contractors Profit @13.615% 54.59 59.94 65.29 70.64
Rate per 1 Sqm 455.54 500.20 544.85 589.51
Say 456 500 545 590
25 Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM (1:6) and top co
of 4mm thick in CM (1:4) with dubara sponge finishing including cost and conveyance of all materials lik
cement, sand, water etc., to site, including sales & other taxes on all materials, and all operational, incident
charges on materials and including cost of all labour charges for mixing mortar, finishing, scaffolding, lift charge
curing, including cutting grooves as directed by Engineer - in - charge etc., and overheads & contractors pro
complete for finished item of work. (SS 901,903 & 904).
( BLD-CSTN-8-10)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.11 Cum 2497.45 1 Cum
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.04 Cum 2497.45 1 Cum
B.LABOUR :
1st Class Mason 0.63 Nos. 445.00 1 Each
2nd Class Mason 1.47 Nos. 405.00 1 Each
Mazdoor (Unskilled) 3.90 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2240.70
water charges @ 1% 0.01 3756.40
Rate per 10 Sqm
Rate per 1 Sqm
Walls in superstructure :
Rate for other Floors FF SF TF 4F
Rate as worked out above 379.40 379.40 379.40 379.40
Hire charges for Access Scaffolding 0.99 0.99 0.99 0.99
Labour charges for scaffolding 6.79 9.69 12.59 15.50
Add for MA @ 40% 2.72 3.88 5.04 6.20
Lift charges ( Page 131 of Std. Data ) 0.00 22.41 44.81 67.22
Add for MA @ 40% 0.00 8.96 17.92 26.89
Rate per 1 Sqm 389.90 425.33 460.75 496.20
Overheads&Contractors Profit @13.615% 53.08 57.91 62.73 67.56
442.98 483.24 523.48 563.76
Say 443 483 523 564
CIVIL DATA : Page-130
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
26 Plastering 12mm thick single coat in CM(1:5) using screened sand including cost and conveyance of a
materials like cement, sand, water etc., to site, including sales & other taxes on all materials, and all operationa
incidental charges on materials and including cost of all labour charges for mixing mortar, finishing, curing a
directed by Engineer-in-charge etc., and overheads & contractors profit complete for finished item of work.(S
901,903 & 904)
(BLD-CSTN-8-3)
Unit : 10 sqm
A.MATERIALS :
Cement 43.20 Kgs 6000.00 1000 Kgs
Fine aggregate ( Sand ) 0.15 cu.m. 2497.45 1 cu.m.
B.LABOUR :
1st Class Mason 0.60 Nos. 445.00 1 Each
Mazdoor (Unskilled) 0.96 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 603.00
water charges @ 1% 0.01 1478.02
Rate per 10 Sqm
Rate per 1 Sqm
a) for basement :
Rate per 1 Sqm 1.00 sqm 149.28 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 149.28
Rate per 1 Sqm
Say
b) Walls in superstructure :
Rate for other Floors FF SF TF 4F
Rate as worked out above 149.28 149.28 149.28 149.28
Hire charges for Access Scaffolding 0.99 0.99 0.99 0.99
Labour charges for scaffolding 6.79 9.69 12.59 15.50
Add for MA @ 40% 2.72 3.88 5.04 6.20
Lift charges ( Page 131 of Std. Data ) 0.00 6.03 12.06 18.09
Add for MA @ 40% 0.00 2.41 4.82 7.24
159.78 172.28 184.78 197.30
Overheads&Contractors Profit @13.615% 21.75 23.46 25.16 26.86
Rate per 1 Sqm 181.53 195.74 209.94 224.16
Say 182 196 210 224
27 Plastering 20mm thick in two coats using screened sand with base coat of 16mm thick in CM(1:6) and to
coat of 4mm thick in CM(1:4) with dubara sponge finishing including cost and conveyance of all materials lik
cement, sand, water etc., to site, including sales & other taxes on all materials, and all operational, incident
charges on materials and including cost of all labour charges for mixing mortar, finishing, scaffolding, lift charge
curing, including cutting grooves as directed by Engineer-in-charge etc., and overheads & contractors pro
complete for finished item of work .(SS 901,903 & 904)
(BLD-CSTN-8-9)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 16mm thick
Cement 43.20 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.18 Cum 2497.45 1 Cum
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.04 Cum 2497.45 1 Cum
CIVIL DATA : Page-131
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
B.LABOUR :
1st Class Mason 0.63 Nos. 445.00 1 Each
2nd Class Mason 1.47 Nos. 405.00 1 Each
Mazdoor (Unskilled) 3.90 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2240.70
water charges @ 1% 0.01 4032.02
Rate per 10 Sqm
Rate per 1 Sqm
Walls in superstructure :
Rate for other Floors FF SF TF 4F
Rate as worked out above 407.23 407.23 407.23 407.23
Hire charges for Access Scaffolding 0.99 0.99 0.99 0.99
Labour charges for scaffolding 6.79 9.69 12.59 15.50
Add for MA @ 40% 2.72 3.88 5.04 6.20
Lift charges ( Page 131 of Std. Data ) 0.00 22.41 44.81 67.22
Add for MA @ 40% 0.00 8.96 17.92 26.89
417.73 453.16 488.58 524.03
Overheads&Contractors Profit @13.615% 56.87 61.70 66.52 71.35
Rate per 1 Sqm 474.60 514.86 555.10 595.38
Say 475 515 555 595
28 Plastering 20mm thick single coat in CM(1:5) using screened sand including cost and conveyance of a
materials like cement, sand, water etc., to site, including sales & other taxes on all materials, and all operationa
incidental charges on materials and including cost of all labour charges for mixing mortar, finishing, curing a
directed by Engineer-in-charge etc., and overheads & contractors profit complete for finished item of work .(S
901,903 & 904)
(BLD-CSTN-8-8)
Unit : 10 sqm
A.MATERIALS :
Cement 60.48 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.21 Cum 2497.45 1 Cum
B.LABOUR :
2nd Class Mason 0.94 Nos. 405.00 1 Each
Mazdoor (Unskilled) 1.60 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 940.70
water charges @ 1% 0.01 2204.32
Rate per 10 Sqm
Rate per 1 Sqm
a) for basement :
Rate per 1 Sqm 1.00 sqm 222.64 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 222.64
Rate per 1 Sqm
Say Say
b) Walls in superstructure :
Rate for other Floors FF SF TF 4F
Rate as worked out above 222.64 222.64 222.64 222.64
Hire charges for Access Scaffolding 0.99 0.99 0.99 0.99
Labour charges for scaffolding 6.79 9.69 12.59 15.50
Add for MA @ 40% 2.72 3.88 5.04 6.20
Lift charges ( Page 131 of Std. Data ) 0.00 9.41 18.81 28.22
Add for MA @ 40% 0.00 3.76 7.52 11.29
CIVIL DATA : Page-132
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
233.14 250.37 267.59 284.84
Overheads&Contractors Profit @13.615% 31.74 34.09 36.43 38.78
Rate per 1 Sqm 264.88 284.46 304.02 323.62
Say 265 284 304 324
29 Providing impervious coat to exposed RCC roof slab surfaces to required slopes with CM (1:3) prop. usin
screened sand 20mm thick (average) mixed with integral cement water proofing liquid confirming to IS: 264
2003 manufactured by reputed manufacturers as approved by Engineer-in-charge at 1 Kg per one bag
cement, laid over roof slab when it is green, finished smooth with a floating coat of neat cement and thread linin
at regular intervals of 45cmx45cm including cost and conveyance of all materials like cement, sand, wat
proofing compound, water etc., to site, including sales & other taxes on all materials and operational, incidenta
and labour charges for mixing mortar, laying, lift charges, rendering smooth and thread lining, curing includin
rounding off junctions of wall and slab etc., and overheads & contractors profit complete for finished item
work. (APSS No. 901 & 903).
(BLD-CSTN-10-25)
Unit : 10 sqm
A.MATERIALS :
Cement 100.80 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.21 Cum 2497.45 1 Cum
Integral cement waterproofing liquid 0.40 Ltrs 210.00 1.00 Ltrs
B.LABOUR :
1st Class Mason 0.66 Nos. 445.00 1 Each
2nd Class Mason 1.54 Nos. 405.00 1 Each
Mazdoor (Unskilled) 3.70 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2212.40
water charges @ 1% 0.01 4310.62
Rate per 10 Sqm
30 Providing impervious coat to exposed RCC roof slab surfaces of sump , sump side wall,sump botto
slab,in side of septic tank , in sunken slabs etc. to required slopes with CM (1:3) prop. using screened san
12mm thick mixed with integral cement water proofing liquid confirming to IS: 2645-2003 manufactured b
reputed manufacturers as approved by Engineer-in-charge at 1 Kg per one bag of cement, laid over roof sla
when it is green, finished smooth with a floating coat of neat cement and thread lining at regular intervals
45cmx45cm where ever necessary including cost and conveyance of all materials like cement, sand, wat
proofing compound, water etc., to site, including sales & other taxes on all materials and operational, incidenta
and labour charges for mixing mortar, laying, lift charges, rendering smooth and thread lining, curing includin
rounding off junctions of wall and slab etc., and overheads & contractors profit complete for finished item of wor
(APSS No. 901 & 903).
(BLD-CSTN-8-2)
A.MATERIALS :
Cement 72.00 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.15 Cum 2497.45 1 Cum
Integral cement waterproofing liquid 0.29 Ltrs 210.00 1.00 Ltrs
B.LABOUR :
CIVIL DATA : Page-133
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
1st Class Mason 0.60 Nos. 445.00 1 Each
Mazdoor (Unskilled) 0.96 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 603.00
water charges @ 1% 0.01 1711.72
Rate per 10 Sqm
31 RCM facia 50mm thick in CM (1:3) using screened sand for drop walls, fins with rabbit wire mesh & nomia
reinforcement as directred by Engineer - In - Charge with dubara sponge finishing,including cost an
conveyance of all materials to site, sales & othertaxes on all materials,operationals &incidental,cost an
conveyance of cement,wire mesh,water to work site,centering,scaffolding and form work,lift charges etc., an
overheads & contractors profit complete for finished item of work but excluding cost of steel and its fabricatio
charges for finished item of work (APSS NO.403&903).
(BLD-CSTN-8-11)
Unit : 10 sqm
A)MATERIALS
Rabbit wire mesh 13.30 sqm 17.00 1 sqm
Cement for base coat and plastering 240.00 Kgs 6000.00 1000 Kgs
Cement for lumps 50.00 Kgs 6000.00 1000 Kgs
Fine aggregate (Sand) 0.50 cu.m. 2497.45 1 cu.m.
Excluding HYSD steel/mild steel & binding
wire
B) LABOUR CHARGES
1st Class Mason 8.00 Nos. 445.00 1 Each
Operator concrete mixer 1.00 Nos. 445.00 1 Each
Mazdoor (Unskilled) 10.00 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 7505.00
C)Machinery :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 2.00 hours 133.50 1 hours
Crew charges 2.00 hours 219.70 1 hours
Add MA on crew charges 0.40 219.70
water charges @ 1% 0.01 14603.99
Rate per 10 Sqm
Rate per 1 Sqm
CIVIL DATA : Page-134
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate for other Floors FF SF TF 4F
Rate as worked out above 1475.00 1475.00 1475.00 1475.00
Hire charges for Access Scaffolding 0.99 1.98 2.97 3.96
Labour charges for scaffolding 6.79 9.69 12.59 15.50
Add for MA @ 40% 2.72 3.88 5.04 6.20
Lift charges ( Page 131 of Std. Data ) 0.00 75.05 150.10 225.15
Add for MA @ 40% 0.00 30.02 60.04 90.06
1485.50 1595.62 1705.74 1815.87
Overheads&Contractors Profit @13.615% 202.25 217.24 232.24 247.23
Rate per 1 Sqm 1687.75 1812.86 1937.98 2063.10
Say 1688 1813 1938 2063
32 Flooring with polished shahabad / Tandur stone slabs of 15mm to 18mm thick set over a base coat of C
(1:8) , 12mm thick using screened sand over already laid CC bed / RCC roof slab including neat cement slurry
honey like consistency spread @ 3.3 Kgs per Sqm and jointed with neat cement to full depth including cost an
conveyance of all materials like cement, sand, water, flooring stones etc. complete including sales & other taxe
on all materials including all labour charges like dressing of flooring stones to the required size, mixing
cement mortar, laying, lift charges , cost of base coat, water charges etc., and overheads & contractors pro
complete for finished item of work. (APSS No.703 & 701)
(BLD-CSTN-9-1)
Unit = 10 sqm.
A. MATERIALS:
Polished shahabad stone 15 to 18mm thick 11.00 Sqm 1884.32 10 Sqm
Cement for CM (1:8) proportion for base
coat 21.60 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
Cement for pointing 20.00 Kgs 6000.00 1000 Kgs
Sand for CM(1:8) 0.12 Cum 2497.45 1 Cum
B .LABOUR
Mason 1st class 3.10 Nos 445.00 1 Each
Mason 2nd class 1.10 Nos 405.00 1 Each
Mazdoor(un skilled) 0.86 Nos 350.00 1 Each
Add for MA @ 40% 0.40 2126.00
Add water charges 1% 0.01 5796.45
Rate for 10 sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
33 Flooring with Polished black Kadapa slabs 15mm to 18mm thick set over a base coat of CM (1:8) , 12m
thick using screened sand over already laid CC bed / RCC roof slab including neat cement slurry of honey lik
consistency spread @ 3.3 Kgs per Sqm and jointed with neat cement to full depth including cost an
conveyance of all materials like cement, sand, water, flooring stones etc. complete including sales & other taxe
on all materials including all labour charges like dressing of flooring stones to the required size, mixing
cement mortar, laying, lift charges , cost of base coat, water charges etc., and overheads & contractors pro
complete for finished item of work. (APSS No.703 & 701)
(BLD-CSTN-9-1)
Unit = 10 sqm.
A. MATERIALS:
Polished black Kadapa slabs minimum of
15mm thick 11.00 Sqm 1593.02 10 Sqm
Cement for CM (1:8) proportion for base
coat 21.60 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
Cement for pointing 20.00 Kgs 6000.00 1000 Kgs
Sand for CM(1:8) 0.12 Cum 2497.45 1 Cum
B .LABOUR
Mason 1st class 3.10 Nos 445.00 1 Each
Mason 2nd class 1.10 Nos 405.00 1 Each
Mazdoor(un skilled) 0.86 Nos 350.00 1 Each
Add for MA @ 40% 0.40 2126.00
Add water charges 1% 0.01 5476.02
Rate for 10 sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
33 Flooring with non-skid full body ceramic floor tiles of size 300mm x 300mm and thickness between 7
8mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of any colour and finish in all shade
and designs as approved by Engineer-in-charge, set over base coat of cement mortar (1:8), 12mm thick usin
screened sand over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistenc
spread @ 3.3 Kgs per Sqm & jointed neatly with white cement paste to full depth mixed with pigment of matchin
shade, including cost of all materials like cement, screened sand , water and tiles etc., and overheads
contractors profit complete for finished item of work. (APSS No.701 & 707)
(BLD-CSTN-9-6)
Unit = 10 sqm.
A. MATERIALS:
Ceramic tiles 7 to 8mm thick (300mm x
300mm) 10.50 Sqm 450.00 1 Sqm
Cement for CM(1:8) proportion for base
coat 21.60 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White Cement 2.00 Kgs 31.00 1 Kg
Sand for CM(1:8) 0.12 Cum 2497.45 1 Cum
B .LABOUR
Mason 1st class 0.96 Nos 445.00 1 Each
Mason 2nd class 2.24 Nos 405.00 1 Each
Mazdoor(un skilled) 3.30 Nos 350.00 1 Each
Add for MA @ 40% 0.40 2489.40
Add water charges 1% 0.01 8899.45
Rate for 10sqm
34 Flooring with non-skid full body ceramic floor tiles of size 400mm x 400mm and thickness between 7
8mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of any colour and finish in all shade
and designs with borders and design as per the approved flooring pattern as directed by the Engineer-
-Charge, laying tiles using spacers of 2mm thick, set over base coat of cement mortar (1:8), 12mm thick usin
screened sand over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistenc
spread @ 3.3 Kgs per Sqm & jointed neatly with white cement paste to full depth mixed with pigment of matchin
shade, including cost of all materials like cement, screened sand , water and tiles etc., and overheads
contractors profit complete for finished item of work. (APSS No.701 & 707)
(BLD-CSTN-9-6)
Unit = 10 sqm.
A. MATERIALS:
Ceramic tiles 7 to 8mm thick (400mm x
400mm) 10.50 Sqm 530.00 1 Sqm
Cement for CM(1:8)proportion for base
coat 21.60 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White Cement 2.00 Kgs 31.00 1 Kg
Sand for CM(1:8) 0.12 Cum 2497.45 1 Cum
CIVIL DATA : Page-137
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
B .LABOUR
Mason 1st class 0.96 Nos 445.00 1 Each
Mason 2nd class 2.24 Nos 405.00 1 Each
Mazdoor(un skilled) 3.30 Nos 350.00 1 Each
Add for MA @ 40% 0.40 2489.40
Add water charges 1% 0.01 9739.45
Rate for 10 sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
34 Flooring with soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm an
thickness between 8 to 10mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1 to 15) of an
colour and finish in all shades and designs with borders and design as per the approved flooring pattern a
directed by the Engineer-In -Charge, laying tiles using spacers of 2mm thick, set over a base coat of CM (1:8
prop. 12mm thick using screened sand over CC bed already laid or RCC roof slab , including neat cement slur
of honey like consistancy spread @ 3.3 kgs per Sqm. and jointed neately with white cement paste to full dep
mixed with pigment of matching shade including cost and conveyance of all materials like cement, san
water, tiles, white cement etc., to site (excluding cost of C.C. bed) including cost of base coat and all labou
charges for mixing of cement mortar, laying tiles to required slope as directed by the Engineer- in-charg
etc.,and overheads & contractors profit complete for finished item of work. (APSS No.701 & 707).
(BLD-CSTN-9-5)
Unit = 10 sqm.
A. MATERIALS:
Vitrified tiles 8 to 10mm thick of size
600mm x 600mm 10.50 Sqm 550.00 1 Sqm
Cement for CM(1:8)proportion for base
coat 21.60 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White Cement 6.00 Kgs 31.00 1 Kg
Sand for CM(1:8) 0.12 Cum 2497.45 1 Cum
B .LABOUR
Mason 1st class 0.96 Nos 445.00 1 Each
Mason 2nd class 2.24 Nos 405.00 1 Each
Mazdoor(un skilled) 3.30 Nos 350.00 1 Each
Add for MA @ 40% 0.40 2489.40
Add water charges 1% 0.01 10073.45
Rate for 10sqm
Flooring with granite stone tiles 8mm thick (mirror polished of all shades) of 1st quality and of size a
approved by Engineer-in-charge with borders and design as per the approved flooring pattern as directed by th
Engineer-In -Charge, laying tiles using spacers of 2mm thick, set over a base coat of CM (1:8) prop. 12m
thick using screened sand over CC bed already laid or RCC roof slab , including neat cement slurry of hone
like consistancy spread @ 3.3 kgs per Sqm. and jointed neately with white cement paste to full depth mixe
with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, tile
white cement etc., to site (excluding cost of C.C. bed) including cost of base coat and all labour charges fo
mixing of cement mortar, laying tiles to required slope as directed by the Engineer- in-charge etc., an
overheads & contractors profit complete for finished item of work. (APSS No.701 & 707)
(BLD-CSTN-9-9)
Unit = 10 sqm.
A. MATERIALS:
Granite stone tiles 8mm thick (mirror
polished of all shades) 10.50 Sqm 1165.00 1 Sqm
CIVIL DATA : Page-139
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Cement for CM(1:8) for base coat 21.60 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kg
White Cement 6.00 Kgs 31.00 1 Kg
Sand for CM(1:8) 0.12 Cum 2497.45 1 Cum
B .LABOUR
Mason 1st class 0.96 Nos 445.00 1 Each
Mason 2nd class 2.24 Nos 405.00 1 Each
Mazdoor(un skilled) 3.30 Nos 350.00 1 Each
Add for MA @ 40% 0.40 2489.40
Add water charges 1% 0.01 16530.95
Rate for 10 sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
35 Flooring with 16 to 18mm thick high polished granite stone slabs other than black and regular colour
(i.e. of shades like paradiso / bala flower / copper silk / laka red / lavender blue) with borders and design as pe
the pattern approved by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of ceme
mortar (1:8) , 20mm thick using screened sand over CC bed already laid or RCC roof slab including neat gre
cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement pas
mixed with pigment of matching shade to full depth including cost and conveyance of all materials like cement
sand , water , granite slabs etc., to work site and all operational, incidental labour & lift charges, polishin
charges and all other taxes on all materials, cost of base coat and overheads & contractors profit complete fo
finished item of work (S.S.701 & special)
(BLD-CSTN-9-7)
Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs other than
black 16 to 18mm thick 10.50 Sqm 2988.00 1 Sqm
Cement for CM(1:8) for base coat 36.00 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing 6.00 Kgs 31.00 1 Kg
Sand for CM(1:8) 0.20 Cum 2497.45 1 Cum
B .LABOUR
Mason 1st class 3.00 Nos 445.00 1 Each
Mason 2nd class 1.00 Nos 405.00 1 Each
Mazdoor(un skilled) 8.00 Nos 350.00 1 Each
Add for MA @ 40% 0.40 4540.00
Add water charges 1% 0.01 38829.49
Rate for 10sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
36 Flooring with 16 to 18 mm thick high polished granite stone slabs black colour as approved by th
Engineer-in-Charge of length not less than 2.43 mts set over base coat of cement mortar (1:8) , 20mm thic
using screened sand over CC bed already laid or RCC roof slab including neat grey cement slurry of honey lik
consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement paste mixed with pigment
matching shade to full depth including cost and conveyance of all materials like cement , sand , water , grani
slabs etc., to work site and all operational, incidental labour & lift charges, half rounding the edge , polishin
charges and all other taxes on all materials, cost of base coat and overheads & contractors profit complete fo
finished item of work for platforms (S.S.701 & special)
(BLD-CSTN-9-7)
Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs black 16 to
18mm thick 10.50 Sqm 2540.00 1 Sqm
Cement for CM(1:8) for base coat 36.00 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing 6.00 Kgs 31.00 1 Kg
Sand for CM(1:8) 0.20 Cum 2497.45 1 Cum
B .LABOUR
Mason 1st class 3.00 Nos 445.00 1 Each
Mason 2nd class 1.00 Nos 405.00 1 Each
Mazdoor(un skilled) 8.00 Nos 350.00 1 Each
Add for MA @ 40% 0.40 4540.00
Machine cutting charges 16.67 RM 16.00 1 RM
Half rounding the edges 16.67 RM 315.00 1 RM
Add for MA @ 40% 0.40 2207.11
Add water charges 1% 0.01 40526.10
Rate for 10 sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
37 Granolithic Concrete flooring 20 mm thick with (1:1:2), using 6mm to 12 mm size hard granite machin
crushed metal and screened sand laid over CC bed already laid or RCC roof slab, in alternate panels of size n
exceeding 1.50 m x 1.50 m, using glass strips and finishing the top surface to required smoothness and slope
and thread lining including cost of all materials like cement, metal sand and water and overheads & contracto
profit complete for finished item of work. (APSS No.701 & 710)
(BLD-CSTN-9-13)
Unit : 10sqm
A.MATERIALS :
6mm to 12mm HBG Metal 0.17 Cum 1362.17 1 Cum
Cement 120.00 Kgs 6000.00 1000 Kgs
Sand 0.085 Cum 2297.45 1 Cum
B. LABOUR
Mason 1st class 1.25 Nos. 445.00 1 Each
Mason 2nd class 0.06 Nos. 405.00 1 Each
Mazdoor (unskiled) 3.00 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 1630.55
Add water charges 1% 0.01 3429.62
Rate per 10 Sqm
38 Flooring with chequered cement concrete heavy duty tiles confirming to IS:13801 using aggregates, cemen
pigments of size 300mm x 300mm and thickness 25mm of any shade as approved by Engineer - In - Charg
set over base coat of cement mortar (1:6), 12 mm thick using screened sand over CC bed alredy laid or RC
roof slab including neat cement slurry of honey like consistency spread @ 3.3 kgs per sqm and jointed with ne
white cement to full depth mixed with pigment of matching shade including cost and conveyance of all materia
like cement, sand, water and tiles etc.,and overheads & contractors profit complete for finished item of work.
(BLD-CSTN-9-4)
Unit : 10sqm
A.MATERIALS :
Chequred tiles 25mm thick 10.50 sqm 302.00 1 sqm
Cement for CM(1:6) proportion for base
coat 28.80 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing & pointing 2.00 Kgs 31.00 1.00 Kgs
Sand for CM(1:6) proportion 0.12 Cum 2497.45 1 Cum
B. LABOUR
Mason 1st class 0.96 Nos. 445.00 1 Each
Mason 2nd class 2.24 Nos. 405.00 1 Each
Mazdoor (unskiled) 3.30 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2489.40
Add water charges 1% 0.01 7388.65
Rate per 10 Sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate as worked out above 7462.54 7462.54 7462.54 7462.54
Lift charges ( Page 131 of Std. Data ) 0.00 248.94 497.88 746.82
Add for MA @ 40% 0.00 99.58 199.15 298.73
7462.54 7811.06 8159.57 8508.09
Overheads&Contractors Profit @13.615% 1016.02 1063.48 1110.93 1158.38
Rate per 10 Sqm 8478.56 8874.54 9270.50 9666.47
Rate per 1 Sqm 847.86 887.45 927.05 966.65
Say 848 887 927 967
39 Providing polished shahabad / Tandur stone slabs of 15mm to 18mm thick in single piece as specified s
over a base coat of CM (1:5) , 12mm thick using screened sand over already laid CC bed / RCC roof sla
including neat cement slurry of honey like consistency spread @ 3.3 Kgs per Sqm and jointed with neat ceme
to full depth including cost and conveyance of all materials like cement, sand, water, flooring stones et
complete including sales & other taxes on all materials including all labour charges like dressing of floorin
stones to the required size, flat nosing the edges, mixing of cement mortar, laying, lift charges , cost of base coa
water charges etc., and overheads & contractors profit complete for finished item of work for treads and riser
(APSS No.703 & 701)
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
B.LABOUR
Mason 1st class 0.96 Nos. 445.00 1 Each
Mason 2nd class 2.24 Nos. 405.00 1 Each
Mazdoor(unskilled) 3.10 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2419.40
Add water charges 1% 0.01 6164.97
Rate for 10 sqm
40 Providing Polished black Kadapa slabs 15mm to 18mm thick in single piece as specified set over a bas
coat of CM (1:5) , 12mm thick using screened sand over already laid CC bed / RCC roof slab including ne
cement slurry of honey like consistency spread @ 3.3 Kgs per Sqm and jointed with neat cement to full dep
including cost and conveyance of all materials like cement, sand, water, flooring stones etc. complete includin
sales & other taxes on all materials including all labour charges like dressing of flooring stones to the require
size, flat nosing the edges, mixing of cement mortar, laying, lift charges , cost of base coat, water charges etc
and overheads & contractors profit complete for finished item of work for treads and risers. (APSS No.703
701)
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate per 1 Sqm 955.24 989.05 1022.87 1056.68
Say 955 989 1023 1057
39 Providing 16 to 18mm thick high polished granite stone slabs other than black and regular colours (i.e.
shades like paradiso / bala flower / copper silk / laka red / lavender blue) with borders and design as per th
pattern approved by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of ceme
mortar (1:5) , 12mm thick using screened sand over CC bed already laid or RCC roof slab including neat gre
cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement pas
mixed with pigment of matching shade to full depth including cost and conveyance of all materials like cement
sand , water , granite slabs etc., to work site and all operational, incidental labour & lift charges, half rounding th
edges of treads , polishing charges and all other taxes on all materials, cost of base coat and overheads
contractors profit complete for finished item of work for treads and risers (S.S.701 & special)
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Half rounding the edges 33.33 RM 315.00 1 RM
Add for MA @ 40% 0.40 4412.89
Add water charges 1% 0.01 51418.44
Rate for 10sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
b) Risers of 0.15m height :
(BLD-CSTN-9-19)
Unit = 10 sqm
A.MATERIALS :
Cost of high polished granite 10.50 sqm 2988.00 1 sqm
Sand for CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing & pointing 5.00 Kgs 31.00 1 Kg
Machine cutting charges 66.67 RM 16.00 1 RM
Add for MA @ 40% 0.40 426.69
B.LABOUR
Mason 1st class 2.10 Nos. 445.00 1 Each
Man Mazdoor(Beldar) 4.90 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2649.50
Add water charges 1% 0.01 37180.75
Rate for 10 sqm
40 Providing skirting to internal walls to 10.00 cm height with Polished Shahabad/Tandur stone slabs 15m
to 18mm thick, length equal to flooring stones set over base coat of CM(1:5) 12 mm thick using screened san
with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with whi
cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tile
cement, sand and water etc., complete and overheads & contractors profit complete for finished item of wor
(APSS No.701 &707)
(BLD-CSTN-9-23)
Unit = 10 sqm
A.MATERIALS :
Cost of shahabad stone slabs 11.00 sqm 1884.32 10 sqm
Sand for CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
B.LABOUR
Mason 1st class 0.96 Nos. 445.00 1 Each
Mason 2nd class 2.24 Nos. 405.00 1 Each
Mazdoor(unskilled) 3.10 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2419.40
Add water charges 1% 0.01 6164.97
Rate for 10 sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Overheads&Contractors Profit @13.615% 847.75 893.87 939.99 986.10
Rate per 10 Sqm 7074.37 7459.20 7844.04 8228.86
Rate per 1 RM 70.74 74.59 78.44 82.29
Say 71 75 78 82
41 Providing skirting to internal walls to 10.00 cm height with Polished Kadapa stone slabs 15mm to 18m
thick, length equal to flooring stones set over base coat of CM(1:5) 12 mm thick using screened sand wi
cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white ceme
paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, san
and water etc., complete and overheads & contractors profit complete for finished item of work.(APSS No.70
&707)
(BLD-CSTN-9-23)
Unit = 10 sqm
A.MATERIALS :
Cost of Kdapa stone slabs 11.00 sqm 1593.02 10 sqm
Sand for CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
B.LABOUR
Mason 1st class 0.96 Nos. 445.00 1 Each
Mason 2nd class 2.24 Nos. 405.00 1 Each
Mazdoor(unskilled) 3.10 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2419.40
Add water charges 1% 0.01 5844.54
Rate for 10 sqm
42 Providing skirting to internal walls to 10 cm height with non-skid full body ceramic floor tiles of thicknes
between 7 - 8mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of any colour and finis
in all shades and designs as approved by Engineer-in-charge, length equal to flooring tiles, set over base co
of CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate
3.30 kgs per sqm and jointing with white cement paste mixed with pigment of matching shade to full dept
including cost of all materials like tiles, cement, sand and water, overheads & contractors profit complete fo
finished item of work.(APSS No.701 &707)
(BLD-CSTN-9-18)
Unit = 10 sqm
A.MATERIALS :
Cost of Edge cut Rectified ceramic tiles 8
mm thick 10.50 sqm 530.00 1 sqm
Sand for CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing & pointing 6.00 Kgs 31.00 1 Kg
B.LABOUR
Mason 1st class 0.77 Nos. 445.00 1 Each
CIVIL DATA : Page-149
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Mazdoor(unskilled) 0.80 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 622.65
Add water charges 1% 0.01 7327.76
Rate per 10 Sqm
41 Providing skirting to internal walls to 10 cm height with soluble salt porcelain vitrified tiles scree
printed and polished of thickness between 8 to 10mm 1st quality conforming to IS: 13711, IS: 13712, IS
13630(Parts 1 to 15) of any colour and finish in all shades and designs, length equal to flooring tiles, set ove
base coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread
the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with pigment of matching shade to fu
depth, including cost of all materials like tiles, cement, sand and water etc.,and overheads & contractors pro
complete for finished item of work.(APSS No.701 &707)
(BLD-CSTN-9-20)
Unit = 10 sqm
Cost of vitrified tiles 8-10mm thick 10.50 sqm 550.00 1 sqm
Sand for CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing & pointing 2.00 Kgs 31.00 1 Kg
B.LABOUR
Mason 1st class 0.77 Nos. 445.00 1 Each
Mazdoor(unskilled) 0.80 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 622.65
Add water charges 1% 0.01 7413.76
Rate for 10 sqm
42 a) Providing skirting to internal walls to 10 cm height with 8mm thick mirror polished granite tiles leng
equal to flooring tiles, set over base coat of CM(1:5) 12 mm thick using screened sand with cement slurry
honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed wi
pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., an
overheads & contractors profit complete for finished item of work.(APSS No.701 &707)
(BLD-CSTN-9-21)
Unit = 10 sqm
CIVIL DATA : Page-150
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
A.MATERIALS :
Cost of granite tiles 8mm thick 10.50 sqm 1165.00 1 sqm
Sand for CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing & pointing 5.00 Kgs 31.00 1 Kg
B.LABOUR
Mason 1st class 0.77 Nos. 445.00 1 Each
Mazdoor(unskilled) 0.80 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 622.65
Add water charges 1% 0.01 13964.26
Rate for 10 sqm
b) Cladding to internal walls with 8mm thick mirror polished granite tiles length equal to flooring tiles, set ov
base coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread
the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with pigment of matching shade to fu
depth, including cost of all materials like tiles, cement, sand and water etc., and overheads & contractors pro
complete for finished item of work.(APSS No.701 &707)
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
42 a) Providing skirting to internal walls 10cm height with High Polished Granite 16 to 18 mm thick up to 8'-0
(2.43 M) other than black and regular colours, length equal to flooring slabs set over base coat of CM(1:5) 1
mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs pe
sqm and jointing with white cement paste mixed with pigment of matching shade to full depth, including cost of a
materials like tiles, cement, sand and water etc., and overheads & contractors profit complete for finished item
work.
(BLD-CSTN-9-19)
Unit = 10 sqm
A.MATERIALS :
Cost of high polished granite 10.50 sqm 2988.00 1 sqm
Sand for CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing & pointing 5.00 Kgs 31.00 1 Kg
Machine cutting charges 66.67 RM 16.00 1 RM
Add for MA @ 40% 0.40 426.69
B.LABOUR
Mason 1st class 2.10 Nos. 445.00 1 Each
Man Mazdoor(Beldar) 4.90 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 2649.50
Add water charges 1% 0.01 37180.75
Rate for 10 sqm
b) Providing cladding to walls with High Polished Granite 16 to 18 mm thick up to 8'-00 (2.43 M) other tha
black and regular colours, length equal to flooring slabs set over base coat of CM(1:5) 12 mm thick usin
screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointin
with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials lik
tiles, cement, sand and water etc., and overheads & contractors profit complete for finished item of work.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
43 Providing dadooing to walls with glazed full body porcelain wall tiles of size 300 x 600 mm with any typ
of design texture such as marble finish, wooden, bamboo, stone finishes etc., scratch less, stain free an
thickness between 6-8 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colou
and finish in all shades and designs with borders as approved by Engineer-in-Charge set over base coat
CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.3
kgs per sqm and jointing with white cement paste mixed with pigment of matching shade to full depth, includin
cost of all materials like tiles, cement, sand and water etc., complete overheads & contractors profit complete fo
finished item of work.
(BLD-CSTN-9-18)
Unit = 10 sqm
A.MATERIALS :
cost of glazed full body porcelain wall tiles 10.50 sqm 691.00 1 sqm
of sizefor
Sand 300 x 600 mm
CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing & pointing 6.00 Kgs 31.00 1 Kg
B.LABOUR
Mason 1st class 0.77 Nos. 445.00 1 Each
Mazdoor(unskilled) 0.80 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 622.65
Add water charges 1% 0.01 9018.26
Rate for 10 sqm
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
44 Providing dadooing to walls with glazed full body ceramic tiles of any size and thickness between 5 to 7m
1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1 to 15) of any colour and finish in all shades an
designs with borders as approved by Engineer-in-Charge set over base coat of CM(1:5) 12 mm thick usin
screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointin
with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials lik
tiles, cement, sand and water etc., and overheads & contractors profit complete for finished item of work.
(BLD-CSTN-9-18)
Unit = 10 sqm
A.MATERIALS :
Cost of glazed coloured tiles 10.50 sqm 430.00 1 sqm
Sand for CM(1:5) base coat 0.12 cum 2497.45 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 6000.00 1000 Kgs
Cement for slurry 33.00 Kgs 6000.00 1000 Kgs
White cement for jointing & pointing 6.00 Kgs 31.00 1 Kg
B.LABOUR
Mason 1st class 0.77 Nos. 445.00 1 Each
Mazdoor(unskilled) 0.80 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 622.65
Add water charges 1% 0.01 6277.76
Rate for 10 sqm
45 Filling with light weight concrete in Cement Concrete (1:5:10) proportion using brick jelly for low roofs
including cost and conveyance of all materials like cement, sand, brick bats etc., to site including cost of a
labour charges for laying concrete, ramming, curing , overheads & contractors profit etc., complete for finishe
item of work. (APSS. No. 402)
(BLD-CSTN-3-7)
Unit: 1 Cum
A. Materials :-
Cement 129.60 Kgs 6000.00 1000 Kgs
Cost of brick jelly 20mm size(1/3rd rate) 460 Nos. 5852.80 1000 Nos.
Fine aggregate ( Sand ) 0.45 Cum 2297.45 1 Cum
Water (including curing) 1.20 kl 103.00 1 kl
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 133.50 1 hour
Crew Charges 1.00 hour 219.70 1 hour
Add MA on crew charges 0.40 219.70
C.LABOUR :
1st class mason 0.10 Nos. 445.00 1 Each
Mazdoor (unskilled) 1.39 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 531.00
CIVIL DATA : Page-154
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate for other Floors FF SF TF 4F
Rate as above 4016.96 4016.96 4016.96 4016.96
Lift charges ( Page 131 of Std. Data ) 0.00 53.10 106.20 159.30
Add for MA @ 40% 0.00 21.24 42.48 63.72
Rate per 1 cum 4016.96 4091.30 4165.64 4239.98
Overheads&Contractors Profit @13.615% 546.91 557.03 567.15 577.27
Rate per 1 cum 4563.87 4648.33 4732.79 4817.25
Say 4564 4648 4733 4817
46 Reinforced cement concrete (1:5:10) proportion (Cement: fine aggregates: coarse aggregate) using 40m
size (SS5) hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of a
materials like cement, fine aggregate (sand), coarse aggregate, water etc., to site including centering usin
Casurina Ballies , Bamboos , Wooden Reapers , Runners , Wood Posts , Wall Plates etc., shuttering, machin
mixing, laying concrete, lifting concrete manually , curing etc., and overheads & contractors profit complete a
per drawings but excluding cost of steel and it's fabrication charges for finished item of work (APSS NO. 402
403) for Dummy columns.
(BLDS-CSTN-3-13)
Unit: 1 Cum
A.MATERIALS :
Cement 129.60 Kgs 6000.00 1000 Kgs
40mm HBG metal 0.90 Cum 1214.67 1 Cum
Sand 0.45 Cum 2297.45 1 Cum
B.LABOUR :
1st class Mason 0.167 Nos 445.00 1 Each
2nd class Mason 0.167 Nos 405.00 1 Each
Mazdoor (unskilled) 4.70 Nos 350.00 1 Each
Add for MA @ 40% 0.40 1786.95
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 133.50 1 hour
Crew charges 1.00 hour 219.70 1 hour
Needle vibrator 40mm ( petrol ) 1.00 hour 25.80 1 hour
Crew charges 1.00 hour 158.20 1 hour
Add MA on crew charges 0.40 377.90
Water(including for curing) 1.20 kl 103.00 1 kl
Basic cost per 1cum
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
47 Supplying and fixing of stainless steel ( grade 304 ) hand railing as per approved drawing with top rail
50mm dia pipe and 2mm thick medium class and vertical posts of 25mm dia and 1.6mm thick medium class
Nos for each step fixed with base plate of 75mm dia using bonding agent and anchor fastner and welding
drilling of 25mm dia holes with pneumatic compressor for fixing railing, buffing, polishing all members of th
railing thouroughly , lacquer finishing to present seamless finish including cost and conveyance of all material
electrodes, welding charges, cost of all consumables, labour charges , overheads & contractors profit etc
complete for finished item of work.
Rate per 1 RM
Rate per 1 Sqm
Overheads&Contractors Profit @13.615% 0.13615 4554.55
say
48 Providing 110 mm Dia ISI marked PVC down water take pipes with socket , 2.5mm thick 4.0 kg/sq.cm pressu
of ISI marked including cost of necessary PVC Bends, shoes, iron / PVC clamps and all other accessories an
fixing in position including cost and conveyance of all materials, sales & other taxes on materials to sit
operational & incidental charges including all labour charges for fixing at site etc., and overheads & contracto
profit complete for finished item of work. (APSS No. 1328)
49 Supply and fixing pre-cast RCC grills of any design of 50mm thick manufactured with M 30 grade concre
using vibro compaction process using jointless FRP moulds to achieve shuttering finish and adequate
reinforced as per the design approved by the Engineer-in-Charge including cost and conveyance of materials
site and labour charges etc., overheads & contractors profit complete for finished item of work.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Rate for 1 sqm 725.05 765.65 806.26 846.86
Overheads&Contractors Profit @13.615% 98.72 104.24 109.77 115.3
Rate per 1 sqm 823.77 869.89 916.03 962.16
Say 824 870 916 962
50 White washing two coats with white cement to ceiling to give an even shade after thouroughly brushing th
surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charge
and incidental such as scaffolding, lift charges etc., and overheads & contractors profit complete for finished ite
of work in all floors.
(BLD-CSTN-11-5)
Unit : 10 sqm
A.MATERIALS :
White cement 2.00 kgs 31.00 1 kgs
B.LABOUR :
Painter 1st class 0.063 Nos. 515.00 1 Each
Painter 2nd class 0.147 Nos. 405.00 1 Each
Mazdoor(unskilled) 0.32 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 203.98
Sundries including brushes, ladders etc., @
1% 1% 347.57
Rate per 10 sqm
Overheads&Contractors Profit @13.615% 0.13615 347.57
Rate per 10 sqm
Rate per 1 sqm
Say
51 Providing and applying Wall putty of White Cement or Polymer or Cement based of average 1 to 2 m
thickness over plastered surface to prepare the surface even and smooth after thoroughly brushing the surfac
to remove all dirt and remains of loose powdered materials, applying emery paper, Sand the surface, clean
wipe off loose dust, applying knifing paste filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 an
320 No., emery paper for the surface preparation including cost and conveyance of all materials to work site an
all operational, incidental, labour charges, over heads and contractors profit etc., complete for finished item
work in all floors for Internal walls.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
52 Providing and applying Exterior grade Texture ready mixed paint with sand texture added sand particle
Acrylic copolymers and mineral compounds, bactericides and various additives of average 2 to 3 mm thicknes
over plastered surface to prepare the surface even and smooth after thoroughly brushing the surface to remov
all dirt and remains of loose powdered materials, applying emery paper, Sand the surface, clean & wipe off loos
dust, applying putty/ texture paint filler by putty knife / muslin pad, air dry for 2 - 3 hrs for the surfac
preparation including cost and conveyance of all materials to work site and all operational, incidental, labou
charges, scaffolding charges, overheads and contractors profit etc., complete for finished item of work in a
floors for external walls
53 Painting to new walls with 2 coats of Acrylic based Oil bound Washable Distemper having VOC conten
less than 50 grams/litre over promer coat using white cemnt as approved by Engineer-In-Charge, making
coats in all to give an even shade after thourughly brushing the surface to remove all dirt and remains of loos
powdered materials, including cost and conveyance of all materials to work site and all operational, incidenta
labour charges etc., and overheads & contractors profit complete for finished item of work as per APSS 911 f
internal walls in all floors.
(BLD-CSTN-12-1)
Unit = 10 Sqm
Cost of white cement 0.50 Kg 31.00 1 Kg
Painter 1st class 0.08 Nos. 515.00 1 Each
Painter 2nd class 0.19 Nos. 405.00 1 Each
Cost of washable oil bound distemper 1.70 Ltrs 90.00 1 Ltr
Painter 1st class 0.36 Nos. 515.00 1 Each
Painter 2nd class 0.84 Nos. 405.00 1 Each
Add for MA @ 40% 0.40 643.75
Sundries including brushes , ladders etc.,
@ 1% 0.01 1069.75
54 Painting to old walls with 2 coats of Acrylic based Oil bound Washable Distemper having VOC conten
less than 50 grams/litre as approved by Engineer-In-Charge, to give an even shade after thourughly brushin
the old surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of a
materials to work site and all operational, incidental, labour charges etc., and overheads & contractors pro
complete for finished item of work as per APSS 911 for internal walls in all floors.
CIVIL DATA : Page-158
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
(BLD-CSTN-11-10)
Unit = 10 Sqm
Cost of washable oil bound distemper 1.70 Ltrs 90.00 1 Ltr
Painter 1st class 0.36 Nos. 515.00 1 Each
Painter 2nd class 0.84 Nos. 405.00 1 Each
Add for MA @ 40% 0.40 525.60
Sundries including brushes , ladders etc.,
@ 1% 0.01 888.84
55 Painting to new walls with 2 coats of water proof cement paint of shade as approved by the Engineer-I
Charge over a base coat of aproved white cement base coat making 3 coats in all to give an even shade afte
thourughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost an
conveyance of all materials to work site and all operational, incidental, labour charges etc., and overheads
contractors profit complete for finished item of work as per SS 912 in all floors
56 Painting to old walls with 2 coats of water proof cement paint of shade as approved by the Engineer-I
Charge to give an even shade after thourughly brushing the surface to remove all dirt and remains of loos
powdered materials, including cost and conveyance of all materials to work site and all operational, incidenta
labour charges etc., and overheads & contractors profit complete for finished item of work as per SS 912 in a
floors.
(BLD-CSTN-12-4)
Water proof cement paint 2.00 Kgs 55.00 1 Kgs
Painter 1st class 0.15 Nos. 515.00 1 Each
Painter 2nd class 0.35 Nos. 405.00 1 Each
Mazdoor(unskilled) 1.50 Nos. 350.00 1 Each
Add for MA @ 40% 0.40 744.00
Sundries including brushes , ladders etc.,
@ 1% 0.01 1151.60
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
CIVIL DATA : Page-160
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
52 Supply & application of one coat water based cement primer of interior grade I and two coats of acryl
emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for internal wal
including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labou
charges etc., and overheads & contractors profit complete for finished item of work in all floors.
53 Supply & application of one coat water based cement primer of exterior grade II and two coats of acryl
emulsion paint exterior grade with silicon additives having VOC (Volatile Organic Compound) content less tha
50 grams/ liter for exterior walls including cost and conveyance of all materials to site, sales & other taxe
incidental, operational and all labour charges etc., and overheads & contractors profit complete for finished ite
of work in all floors.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
54 Painting to new wood work and flush shutters with lappam finish, over a primary coat and painting tw
coats of synthetic enamel paint Grade-I VOC (Volatile Organic Compound) content less than 50 grams/litre
approved shade including cost and conveyance of all materials to site cost of primer coat and all labour charge
etc. complete including applying sand paper on lappam coats for neat finish including sales & other taxes on co
of all materials etc., and overheads & contractors profit complete in all floors (APSS No.1200, 1207 & 1211).
(BLD-CSTN-12-12-196)
Cost of Synthetic Enamel Paint 1.10 Ltr 276.00 1 Ltr
1st Class Painter 0.36 Nos. 515.00 1 Each
2nd Class Painter 0.84 Nos. 405.00 1 Each
Add for MA @ 40% 0.40 525.60
Sundries including brushes , ladders etc.,
@ 1% 0.01 1039.44
56 Painting primer coat on new wood work using red oxide Iron primer paint grade - 1 of approved bran
including cost and conveyance of all materials to site , all labour charges etc., and overheads & contractors pro
complete in all floors.(APSS No. 1201, 1212 & 1207).
(BLD-CSTN-12-7)
Unit : 10 sqm
A.MATERIALS :
Red oxide primer 0.70 Ltr 142.00 1 Ltr
B.LABOUR :
1st Class Painter 0.21 Nos. 515.00 1 Each
2nd Class Painter 0.49 Nos. 405.00 1 Each
Add for MA @ 40% 0.40 306.60
CIVIL DATA : Page-162
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Sundries including brushes , ladders etc.,
@ 1% 0.01 528.64
57 Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content les
than 50 grams/litre to new iron work including cost and conveyance of all materials to site, sales & oth
taxes, incidental, operational and all labour charges etc., and overheads & contractors profit complete fo
finished item of work in all floors. (SS No. 1201, 1212 & 1207).
(BLD-CSTN-12-12-197)
Unit : 10 sqm
A.MATERIALS :
Cost of Synthetic Enamel Paint 1.10 Ltr 276.00 1 Ltr
B.LABOUR :
1st Class Painter 0.33 Nos. 515.00 1 Each
2nd Class Painter 0.77 Nos. 405.00 1 Each
Add for MA @ 40% 0.40 481.80
Sundries including brushes , ladders etc.,
@ 1% 0.01 978.12
55 Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content les
than 50 grams/litre over primer coat of red oxide to new iron work including cost and conveyance of a
materials to site, sales & other taxes, incidental, operational and all labour charges etc., and overheads
contractors profit complete for finished item of work in all floors. (SS No. 1201, 1212 & 1207).
(BLD-CSTN-12-7 & 12-12-197)
Unit : 10 sqm
A.MATERIALS :
Red oxide primer 0.70 Ltr 142.00 1 Ltr
Cost of Synthetic Enamel Paint 1.10 Ltr 276.00 1 Ltr
B.LABOUR :
for primer coat
1st Class Painter 0.21 Nos. 515.00 1 Each
2nd Class Painter 0.49 Nos. 405.00 1 Each
for enamel painting
1st Class Painter 0.33 Nos. 515.00 1 Each
2nd Class Painter 0.77 Nos. 405.00 1 Each
Add for MA @ 40% 0.40 788.40
Sundries including brushes , ladders etc.,
@ 1% 0.01 1506.76
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
56 Painting two coats with synthetic enamel paint Gr-I having VOC (Volatile Organic Compound) content les
than 50 grams/litre to old iron work including cost and conveyance of all materials to site, sales & other taxe
incidental, operational and all labour charges and overheads & contractors profit etc., complete for finished ite
of work in all floors. (SS No. 1201, 1212 & 1207).
(BLD-CSTN-12-12-198)
Unit : 10 sqm
A.MATERIALS :
Cost of Synthetic Enamel Paint 0.90 Ltr 276.00 1 Ltr
B.LABOUR :
1st Class Painter 0.33 Nos. 515.00 1 Each
2nd Class Painter 0.77 Nos. 405.00 1 Each
Add for MA @ 40% 0.40 481.80
Sundries including brushes , ladders etc.,
@ 1% 0.01 922.92
57 Polishing two coats to teak wood doors using French spirit polish of approved brand for new wood work
teak wood frame and shutters including sand papering to smooth surfaces etc. including cost and conveyance
all materials to site, all labour charges etc., complete for finished item of work in all floors.
(BLD-CSTN-12-15)
A.Materials
French polish 0.228 Ltrs 207.00 1 Ltrs
cost of spirit 1.63 Ltrs 111.00 1 Ltrs
B.Labour
1st Class Painter 0.96 Nos. 515.00 1 Nos.
2nd Class Painter 2.24 Nos. 405.00 1 Nos.
Add for MA @ 40% 0.40 1401.60
Sundries for terpentaine, sand paper, putty,
wood filler, white woolen cloth, linseed oil,
cotton etc., @ 1% 0.01 2190.37
58 Supply & applying Melamine Polish Glossy/ Matt finish to the wood works duly cleaning the surface an
applying emery paper, Sand the wood with 180 No., emery paper and then with 320 No., emery paper, clean
wipe off loose dust, applying suitable knifing paste filler / wood filler by putty knife / muslin pad, air dry for 2 -
hrs, sand with 180 and 320 No., emery paper, apply two component wood sealer, air dry for 24 hrs, Sand wi
320 No emery paper, applying one coat of approved spraying thinner (for spraying)/ applying one coat
approved brushing thinner or general purpose thinner (for brushing) and apply (either with spray or brush) tw
coats of approved brand melamine including cost & labour charges, emery papers, cost of thinner & melamin
polish, over heads and contractors profit etc., complete for finished item of work
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
B.Labour
1st Class Painter 0.24 Nos. 515.00 1 Nos.
2nd Class Painter 0.56 Nos. 405.00 1 Nos.
Helper 0.80 Nos. 350.00 1 Nos.
Add for MA @ 40% 0.40 630.40
Sundries for spraying machine etc., @ 1% 0.01 910.06
59 Supply & applying Poly-Urethane Water Proof Polish Glossy/ Matt finish to the wood works duly cleanin
the surface and applying emery paper, Sand the wood with 180 No., emery paper and then with 320 No., eme
paper, clean & wipe off loose dust, applying suitable knifing paste filler / wood filler by putty knife / muslin pad, a
dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper, applying two component wood sealer, after th
surface preparation applying one coat of approved spraying PU thinner (for spraying) / applying one coat
approved brushing PU thinner or general purpose thinner (for brushing) and apply one coat of PU by brush o
spray, air-dry overnight, Sand again with 180 No. emery paper and removing dust, applying second coat of PU
air drying for 4 - 6 Hrs, Sand with 320 No emery paper, and applying (either with spray or brush) two coats
approved brand PU including cost & labour charges, emery papers, cost of thinner & Poly-Urethane Water Pro
Polish, over heads and contracors profit etc., complete for finished item of work
56 Supply & fixing of Rolling shutter made of 80 x 1.25 mm machine rolled CRCA laths, interlocked togeth
through their entire length and jointed together at the ends by end-locks, mounted on specially designed pip
shaft of 50mm dia nominal bore MS B class pipe with brackets, plates, guide channels, stoppers, bottom lockin
plates and arrangements for inside & outside locking with push-pull operations including cost of hood cover an
springs complete, painted with one coat of approved steel primer, locks, ball bearings, all accessories etc
overheads & contractors profit complete for finished item of work as per special spn: 1108
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Supplying & fixing collapsible steel shutters with vertical, double channel of 20 x10x2 mm of 100 m
centre ,Bracers with flat iron 40x40x6 mm with 38 mm dia steel pulleys, the top, bottom and side vertical frame
of the collapsible gate with 65x65mmx8mm MS Angle and middle guide rail at site height with 65mmx8mm M
flat for the pulleys to guide and fixed with necessary hold fasts, bolts, nuts, rivets, locking arrangement
stoppers, handles, all accessories all fixtures and painted with one coat of approved steel primer etc., overhead
& contractors profit complete for finished item of work as per special spn 1105
57 Providing specialized polysulphide sealant treatment to the expansion joints (Size : 25mm x 12mm) includin
cost and conveyance of all materials to site, all incidental, operational, labour charges etc.overheads
contractors profit complete for finished item of work as per approved drawing for all floors duly a]. Chipping an
removing of existing covering on expansion joints b]. Cleaning of the surface from dirt, dust and othe
contaminations c].Application of one coat of - High performance specially designed SBR latex polymer base
bonding agent d]. Providing and application of Acrylic Polymer modified instatement concrete /mortar to th
damaged edges of joint and making the groove. e]. Providing and fixing of masking tape on top of the joint bo
sides f]. Providing and fixing of Back up support material of Backer rod to leave the depth of 12mm on the joi
g]. Providing and application of one coat of polysulphide primer on inner edges of Joint. h]. Providing an
application of Two part Polysulphide sealant to a width of 25mm and 12mm depth with putty knife and neat finis
i]. Removing of masking tape and providing and application of two coats of Acrylic elastomeric cementitiou
coating.
58 Providing and fixing of Expansion joint filler board for buildings, columns, beams and slabs 25 mm thic
including cost and conveyance of all materials to site, all incidental, operational, labour charges etc.overheads
contractors profit complete for finished item of work as per approved drawing for all floors
Say
CIVIL DATA : Page-166
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
60 Supplying and fixing aluminium composite cladding 4mm thick of approved make with skin material 0.2
mm thick aluminium sheet cover material natural polyethylene aluminium cladding panel fixed with extrude
aluminium basis frame (50x25x1.5mm) angle cleats, weather sealants, rivets, GI brackets all as approved, usin
suitable bolts on structural steel work including necessary accessories complete in all respects including a
scaffolding and labour charges , overheads & contractors profit complete for finished item of work but excludin
cost of structural steel fabrication if any.
61 Supplying and fixing aluminium composite cladding 4mm thick of approved make with skin material 0.5
mm thick aluminium sheet cover material natural polyethylene aluminium cladding panel fixed with extrude
aluminium basis frame (50x25x1.5mm) angle cleats, weather sealants, rivets, GI brackets all as approved, usin
suitable bolts on structural steel work including necessary accessories complete in all respects including a
scaffolding and labour charges , overheads & contractors profit etc., complete for finished item of work b
excluding cost of structural steel fabrication if any.
62 Providing and Fixing Structural Glazing fabricated from Roll formed sections made of Pre-painted Steel
Powder coated (Base steel as per IS 513 of ‘D’ quality, galvanized as per IS 277 with Zinc of 120 Gm/Sqm) wi
total coated thickness of 0.72mm. The glass holding section made of 304 grade stainless steel of 0.6mm thick a
per the design requirement & calculations as given in IS: 875. Primer coat with epoxy primer of 5 – 7 micron
thick, finish painted with a polyester paint of 12-16 microns thick and back coated with Alkyd backer of 5
microns or powder coated with pure polyester powder up to 50-60 microns thick. The vertical section should b
of 50mm x100mm x 0.72mm, 33mm x 58mm x 0.72mm for frame horizontal section, stiffener section should b
48mm x 98mm x 1mm, cover profiles sections should be of 20mm x 58mm x 0.58mm, Glass holding sectio
should be of 37mm x 37mm & 37mm x 18mm. Including 5mm thick Ocean Blue reflective glass. Brackets mad
of CRCA powder coated/Electroplated should be used to connect vertical to horizontal, vertical to slab, to f
verticals at top & bottom as per site requirement.
Gasket made of Ethyl Propylene Diamine Monomer. Natural cure, with Good U.V. Resistance Silicon to be use
Wall fixing of sections to concrete/masonry wall should be with self-expanding cap & screws. The rate is inclusiv
of cost and conveyance of all materials to site, all labour charges, incidental charges, cost of all consumable
etc. and scaffolding charges, form work , overheads & contractors profit etc., complete for finished item of work
all floors.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
63 Providing and Fixing Top Hung shutters in Structural Glazing fabricated from Roll formed sections made
Pre-painted Steel / Powder coated (Base steel as per IS 513 of ‘D’ quality, galvanized as per IS 277 with Zinc
120 Gm/Sqm) with total coated thickness of 0.72mm. The glass holding section made of 304 grade stainles
steel of 0.6mm thick. Galvanized steel sections are to be used as stiffeners inside the colour coate
steel/powder coated sections as per the design requirement. Design calculations are made to suit win
pressures as given in IS 875. Primer coat with epoxy primer of 5-7 microns thick and back coated with Alky
backer of 5-7 microns or powder coated with pure polyester powder up to 50-60 microns thick. The outer fram
should be of 20mm x 58mm x 0.6mm, Shutter section should be of 58mm x 33mm x 0.72 mm, stiffener sectio
should be 56mm x 31mm x 1mm. EARL Bihari Hinges – 2 Nos for each shutter and Aluminium Stays – 2 No
for each shutter, Aluminium Handle – 1 no. for each shutter. The rate is inclusive of cost and conveyance of a
materials to site, all labour charges,
incidental charges, cost of all consumables etc. and scaffolding charges, form work, overheads & contract
profit etc. complete for finished item of work in all floors.
Rate as per SSR 1.00 sqm 5891.00 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 5891.00
Rate per 1 sqm
Say
60 Supply and fixing of curtain Glazing made of pre painted steel (base steel as per IS 513 of 0.6 mm thick D
quality, galvanized as per IS 277 with Zinc of 120 GSM) Primer coated with epoxy primer of 5-7 microns thic
finish painted with a polyester paint of 12- 16 microns thick and back coated with 5-7 microns thick alkyd backe
Section for outer frame should be 46 x 52 mm, section for mullion should be 46 x 70 mm and section for beadin
should be 18 x 25 mm. The Glazing should be paneled with 5 mm thick plain float Glass with Ethyl Propylen
diameine Monomer (EPDM) Gaskets. The sections are to be cut to length, mitre joined with corner bracke
Centre mullions are to be fixed suing mullion cap. Handle made of high grade Aluminium powder coated an
nylon receiver. Gaskets made of Ethyl propylene Diamine Monomer (EPDM) Corner brackets made of CRC
with zinc phosphating. Mullion caps made of Glass filled nylon. The above frames should be fixed to the concre
/ masonry wall be means of self expanding screws,overheads & contractor profit etc., complete for finished ite
in all floors.
a) Fixed Glazing 2'-0" x 2'-0" (609.6x609.6mm) and 2'-0" x 3'-0" (609.6x914.4mm) grid outer frames sectio
size of 46 x 52 mm
Rate as per SSR 1.00 sqm 6013.00 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 6013.00
Rate per 1 sqm
Say
b) Fixed Glazing 3'-0" x 3'-0" (914.4x914.4mm), 3'-0" x 4'-0" (914.4x1219.2mm) grid outer frames sectio
size of 46 x 52 mm
Rate as per SSR 1.00 sqm 5102.00 1 sqm
Overheads&Contractors Profit @13.615% 0.14 5102.00
Rate per 1 sqm
Say
61 Providing and fixing in true horizontal level 12 mm - Mineral Fiber sheet 600 x 600 (Square / Tegular) edg
tiles with a Humidity Resistance of 90% RH,Average NRC 0.50, Light Reflectance >80%, Thermal Conductivi
λ= 0.052 to 0.057 w/mk, Fire Performance Class 0/Class 1 using hot dipped Galvanized Steel section expose
surface with pre-coated capping, main Tee of size 24 x 32 mm at every 1200 mm c/c maximum and rota
stitched cross tee of size 24 x 27 mm at every 600 mm c/c and sub-cross tee of size 24 mm x 25 mm at 120
mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall and the above grid is suspended at eve
1200 mm c/c in both directions using 2.0 mm thick pre-straightened GI Wire including cost and conveyance of a
materials and labour charges such as cutting , fixing of standing of frame work exposing roof making, overhead
& contractor profit etc., complete for finished item of work in all floor in all floors.
CIVIL DATA : Page-168
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
(BLD-CSTN-10-33 & vide Page No. 391 of SoR 2011-12)
Unit 1 Sqm
A) Material requirement
12mm Mineral Fiber sheet 600 x 600 1.00 sqm 456.00 1 sqm
Hotdipped GI Angle - Precoated - Grid -
19mmx19mmX0.7mm 0.40 RM 40.00 1 RM
Polyster painted GI - T section - 1200mm -
24x32mm and 24x25mm (sub-cross Tee)
1.60 RM 47.50 1 RM
Polyster painted GI-T Section - 300mm -
24mm x 27mm 1.60 RM 46.00 1 RM
GI Rod - prestraightened - 2.0mm dia
-Connecting Rod 1.28 RM 10.00 1 RM
6mm Nylon Rawl Plug 1.28 Nos. 2.00 1 No.
B) Labour charges
1st Class Carpenter 0.12 Nos. 480.00 1 No.
2nd Class Carpenter 0.12 Nos. 405.00 1 No.
1st Class Painter 0.024 Nos. 515.00 1 No.
2nd Class Painter 0.024 Nos. 405.00 1 No.
Power Saw cutter - Hand Operated -
Operator 0.012 Nos. 480.00 1 No.
Power Drill - Hand Operated - Operator 0.012 Nos. 480.00 1 No.
Unskilled Mazdoor 0.072 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 165.00
C) Machinery
Power Saw cutter - Hand Operated - Hire
Charges 0.32 Hours 125.00 1 No.
Power Drill - Hand Operated - Hire Charges 0.32 Hours 116.00 1 No.
62 Providing and fixing in true horizontal level 14 mm - Mineral Fiber sheet 595 x 595 (Square / Tegula
Fissura fine model edge tiles with a Humidity Resistance of 90% RH,Average NRC 0.50, Light Reflectanc
>80%, Thermal Conductivity λ= 0.052 to 0.057 w/mk, Fire Performance Class 0/Class 1 using hot dippe
Galvanized Steel section exposed surface with pre-coated capping, main Tee of size 24 x 32 mm at every 120
mm c/c maximum and rotary stitched cross tee of size 24 x 27 mm at every 600 mm c/c and sub-cross tee of siz
24 mm x 25 mm at 1200 mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall and the abov
grid is suspended at every 1200 mm c/c in both directions using 2.0 mm thick pre-straightened GI Wire includin
cost and conveyance of all materials and labour charges such as cutting , fixing of standing of frame wo
exposing roof making, overheads & contractor profit etc., complete for finished item of work in all floor in a
floors.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Polyster painted GI-T Section - 300mm -
24mm x 27mm 1.60 RM 46.00 1 RM
GI Rod - prestraightened - 2.0mm dia
-Connecting Rod 1.28 RM 10.00 1 RM
6mm Nylon Rawl Plug 1.28 Nos. 2.00 1 No.
B) Labour charges
1st Class Carpenter 0.12 Nos. 480.00 1 No.
2nd Class Carpenter 0.12 Nos. 405.00 1 No.
1st Class Painter 0.024 Nos. 515.00 1 No.
2nd Class Painter 0.024 Nos. 405.00 1 No.
Power Saw cutter - Hand Operated -
Operator 0.012 Nos. 480.00 1 No.
Power Drill - Hand Operated - Operator 0.012 Nos. 480.00 1 No.
Unskilled Mazdoor 0.072 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 165.00
C) Machinery
Power Saw cutter - Hand Operated - Hire
Charges 0.32 Hours 125.00 1 No.
Power Drill - Hand Operated - Hire Charges 0.32 Hours 116.00 1 No.
63 Supplying and fixing Gyp Board Suspended regular single layer false ceiling (GS-MFSC-4.1) using 12
mm thick Gyp Board conforming to IS 2095 - 1993 fixing to Gyp steel GI perimeter channels of size 20 mm x 2
mm x 30 mm(web) of 0.55 mm thick along the perimeter of ceiling screw fixed to brick work/ partition at 610 m
c/c and suspending the frame work using Intermediate channels (45 mm x 15mm x 15mm x 0.9 mm) from sof
at 1220 mm c/c with ceiling angle (25 mm x 10 mm x 0.55 mm) fixed with GI Cleat and steel expansion fastene
& connecting clip to the ceiling channels (with knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55 mm) fixed
direction perpendicular to the intermediate channel at 457 mm c/c and fixing the 12.5 mm tapered edg
Gypboard with 25 mm drywall screws at 230 mm c/c & jointing and finishing using joint compound and pape
tape to have a flush look including filling the tapered & square edges with jointing compound, two coats
drywall topcoa including overheads and contractor profit etc., complete for finished item of work
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Jointing Paper tape 1.46 RM 5.00 1 RM
Drywall top coat 0.15 Ltrs 142.00 1 Ltr
B) Labour Charges
1st Class Carpenter 0.12 Nos. 480.00 1 No.
2nd Class Carpenter 0.12 Nos. 405.00 1 No.
1st Class Painter 0.024 Nos. 515.00 1 No.
2nd Class Painter 0.024 Nos. 405.00 1 No.
Power Saw cutter - Hand Operated - 0.012 Nos. 480.00 1 No.
Operator
Power Drill - Hand Operated - Operator 0.024 Nos. 480.00 1 No.
Unskilled Mazdoor 0.072 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 170.76
C) Machinery
Power Saw cutter - Hand Operated - Hire
Charges 0.32 Hours 125.00 1 Hour
Power Drill - Hand Operated - Hire Charges 0.64 Hours 116.00 1 Hour
Say
64 Supplying and fixing Gyp board Fine line Grid false ceiling (GS-FLC-4.6)using 12.5mm thick Gyp Boar
sheet tiles of size 595mm x 595mm conforming to IS 2095 - 1992 fixing to Gyp steel precoated GI wall angle
size 25mm x 25mm x 0.70mm thick along the perimeter of ceiling screw fixed to brick work / partition at 610m
center to center and suspending the frame work using precoated GI Tee section (24mm x 38mm x 0.7mm) fro
soffit at 1220mm center to center fixed with GI Soffit Cleat, rawl plugs and steel expansion fasteners
connecting clip to the GI Tee section with 4mm dia GI rod with galvanised spring steel level clip of PVC unvers
holding clips system at 1200mm center to center and fixing the 12.5mm Gypboard sheet tiles of size 595mm
595mm and finishing two coats of drywall top coat, overheads and contractor profit complete for finished item
work in all floors.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Add for MA @ 40% 0.40 165.00
C) Machinery
Power Saw cutter - Hand Operated - Hire
Charges 0.32 Hours 125.00 1 Hour
Power Drill - Hand Operated - Hire Charges 0.32 Hours 116.00 1 Hour
65 Providing and fixing Thermocole False ceiling in true horizontal level 600mm x 600mm using 12mm thic
Thermocole sheet, anodized Aluminium Tee sections of size 24.50mm x 24.0mm x 2.4mm in grid with cross te
of size 24mm x 24.5mm at every 600mm center to center and anodised aluminium wall angle of size 24mm
24mm fixed to periphery of the wall and the above grid is suspended at every 1200mm center to center in bo
directions using 2.0mm thick GI wire for finished of size 600mm x 600mm including cost and conveyance of a
materials and labour charges such as cutting , fixing of standing of frame work exposing roof complete fo
finished item of work in all floors. (The rate is inclusive of overheads & contractor profit).
66 Supplying and fixing 50mm dia nominal bore Medium Grade properties & weight as per IS 1239 ISI mark M
Tube for fixing of GI Sheet including cost and conveyance of all materials to work site and all operationa
incidental, labour charges , overheads & contractors profit for finished item of work.etc., complete for finishe
item of work in all floors for stair case head room roof.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Overheads&Contractors Profit @13.615% 0.13615 493.48
Say
67 Roofing with corrugated G.I sheets 0.80mm thick fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen & G
limpet washers filled with white lead & including a coat of approved steel primer and two coats of approved pai
on over lapping of sheets complete (up to a pitch of 600) etc., complete, excluding the cost of purlins, rafter
trusses including cost and conveyance of all materials , labour charges , overheads and contractors profit etc
complete for finished item of work in all floors.
Unit : 10 sqm
A. MATERIALS:
G.I corrugated 0.80 mm thick sheets 103.09 Kgs 60.00 1 Kg
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 47.91 Nos. 5.00 1 No.
884
G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 43.90 Nos. 10.00 1 No.
nos = 810
Limpet nos. (for
washers withscam
washers or srews,
& ‘J’ bolts) if
884 + 91.82 Nos. 1.00 1 No.
wooden
810
Bitumen battens
= 1694
washers used. 91.82 Nos. 1.00 1 No.
Zinc cromate yellow paint 0.14 Ltrs 204.00 1 Ltr
Ready mixed paint 0.20 Ltrs 276.00 1 Ltr
B. LABOUR
For roofing
Carpenter II class 0.84 Nos. 405.00 1 No.
Man mazdoor (beldar) 0.91 Nos. 350.00 1 No.
For primer painting one coat
Painter 1st class 0.018 Nos. 515.00 1 No.
Painter 1st class 0.042 Nos. 405.00 1 No.
Mazdoor (coolie) 0.06 Nos. 350.00 1 No.
For two coats of painting to over laps
Painter 1st class 0.042 Nos. 515.00 1 No.
Painter 1st class 0.098 Nos. 405.00 1 No.
Mazdor (coolie) 0.14 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 816.30
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 827.42
Rate per 1 sqm
say
68 Supplying and fixing of Pre-painted Galvalume Trapezoidal Profile Roofing sheets with 0.50m
thickness, Coating: Alu-Zinc coating AZ150 GSM. Tensile Strength: 550 MPA. Paint coating: Regular Modifie
Polyester painting. Painting Thickness (Top): 18 to 20 Microns, (Bottom): 5 to 7 Microns. Sheet Width: 1.02
Length: Maximum 12 Meters with Regular Range Colours fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen
G.I limpet washers filled with white lead & including a coat of approved steel primer and two coats of approve
paint on over lapping of sheets complete (up to a pitch of 600) etc., complete, excluding the cost of purlin
rafters, trusses including cost and conveyance of all materials , labour charges , overheads and contractors pro
etc., complete for finished item of work in all floors.
Unit : 10 sqm
A. MATERIALS:
Galvalume sheet 0.50mm thick 10.50 sqm 456.00 1 sqm
G.I scam bolts & nuts 2 x 27 (laps) x 17 =
884 47.91 Nos. 5.00 1 No.
G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3
nos = 810 nos. with washers or srews, if
wooden battens used.
43.90 Nos. 10.00 1 No.
Limpet washers (for scam & ‘J’ bolts) 91.82 Nos. 1.00 1 No.
CIVIL DATA : Page-173
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Bitumen washers 91.82 Nos. 1.00 1 No.
B. LABOUR
For roofing
Carpenter II class 0.84 Nos. 405.00 1 No.
Man mazdoor (beldar) 0.91 Nos. 350.00 1 No.
Add for MA @ 40% 0.40 658.70
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 657.24
Rate per 1 sqm
say
61 Supply and delivery of encapsulated plastic steps manufactured as per companies standard specificatio
including cost of materials packing as per companiess standards, loading, transportation, unloading and stackin
at site of work , and taxes such as complete sales tax,C.E.D and others etc., as applicable including labou
charges for fixing etc. complete for finished item of work.
Say
62 Supply and fixing ornamental MS Main gate of size 9mts x 3.75 mts ( average height) i.e., varying from 3m
to 4.50 mts at centre as per the approved drawing using MS Angle of 75mm x 75mm x 6mm alround for fram
and 63mm x 6mm MS Flats in 6 rows horizontally, 25mm MS Square bars at 125mm c/c and CI Spikes 9" lon
on top and 6" long CI spikes in the middle in two rows including 6 Nos of Pin clamps fixed in RCC Columns,
Nos of MS aldrops 450 mm Long ( special ) welded at the the centre on each side, 2 Nos of MS tower bol
450mm Long ( special )and providing brass emblem on emboseed cover in the centre of the two leaves an
fixing 2 Nos. of rollers per each leaf including cost and conveyance of all materials,fabrication charges , weldin
charges, incidental charges and all labour charges, over heads and contractor profit etc., complete for finsihe
item of work.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Add cost of rollers 4 Nos. LS
Add for conveyance to work spot
63 Supply and fixing ornamental MS Wicket gate Size 1.50m x 3.00m as per the approved drawing using 75m
x 75mm x 6mm MS angle alround for frame and 63mm x 6mm MS flats in 6 rows horizontally, 25mm MS squa
vertical bars at 125mm c /c and CI spikes 9" long at the top and 6" long spikes in two rows in the middle, 3 No
of Pin clamps fixed in RCC columns, providing 2 Nos.of MS powder coated aldrops 300mm long including co
all taxes and conveyance of all materials,fabrication charges welding charges incidental charges all labo
charges, overheads and contractor profit etc., complete for finsihed item of work.
64 Providing cattle trap including cost of excavation of trap pit and laying 100 mm hick PCC (1:5:10) prop bed
1:50 slope using 40 mm HB Granite metal including constructing 230 mm thick walls alround and middle in PC
M20 Design mix using 20 mm HBG graded metal, 325 mm average height over the bed and duly fixing 7 nos
ISLB 125 x 75 @ 11.9 kg/mt at 470 mm centre to centre and welding 25 mm dia HYSD bars duly inserted in GI
class pipe 50 mm dia (13 nos in all) over ISLB @ 80 mm centre to centre 25 mm dia MS small pieces of 0.15
length for pedestrains (76 nos in all) and including plastering the exposed faces of walls and base in CM 1:5 pro
20 mm thick in single coat duly maintaining 1:50 slope including providing 200mm dia SWG drain pipe to b
connected to the nearest valley to drain off the collected water inside the trap including cost and conveyance
all materials, to site, all labour charges including cutting, welding of bars to (ISLB) RS joists, curing centerin
over heads and contractor profit etc., complete for finished item of work as per the approved drawing.
Sl.
Description Quantity Rate (Rs.) Per Unit
No.
Earth work excavation 5.35 Cum 2026.44 10 Cum
PCC (1:5:10) 1.34 Cum 4212.74 1 Cum
PCC M 20 nominal mix for wall around 0.45
M 1.20 Cum 5568.14 1 Cum
Cost of 25mm dia MS bars 239.66 Kgs 35000.00 1 MT
RS joints 125mm x 75mm @ 11.90 Kgs 154.11 Kgs 34500.00 1 MT
Structural steel 71.00 Kgs 35000.00 1 MT
Labour charges for fabrication 464.77 Kgs 26.00 1 Kg
Labour charges for fixing 464.77 Kgs 4.00 1 Kg
Add for MA @ 40% 0.40 6692.69
20mm thick plastering 12.70 Sqm 222.64 1 Sqm
50mm dia GI pipe 'B' class 47.70 RM 411.30 1 RM
Labour charges for making suitable
arrangement for drainage etc and
transportation to site LS
Rate per 5.423 Sqm
Rate per 1 Sqm
CIVIL DATA : Page-176
D A T A (SoR 2016-17)
CM (1:8)
2622.32
1080.00
70.00
28.00
3800.32
CIVIL DATA : Page-177
DATA
Amount
(Rs.)
efully stacking useful materials for re-use and disposal of unserviceable
ed by Executive Engineer duly taking actual premeasurements before
s , overheads & contractor profit etc., complete
143.15
57.26
200.41
27.29
227.70
228
854.00
341.60
1195.60
162.78
1358.38
1358
1708.00
683.20
2391.20
325.56
2716.76
2717
1512.00
604.80
200.00
175.00
150.00
2641.80
359.68
3001.48
3001
7.00
2.80
9.80
0.98
0.13
1.11
1
CIVIL DATA : Page-178
Amount
(Rs.)
394.00
157.60
551.60
75.10
626.70
627
12.00
4.80
16.80
1.68
0.23
1.91
2
14.00
5.60
19.60
1.96
0.27
2.23
2
205.00
82.00
287.00
39.08
326.08
326
4.00
1.60
5.60
0.56
0.08
0.64
1
5.00
2.00
7.00
0.70
0.10
0.80
1
CIVIL DATA : Page-179
Amount
(Rs.)
4.00
1.60
5.60
0.56
0.08
0.64
1
5.00
2.00
7.00
0.70
0.10
0.80
1
40.50
70.00
20.25
52.30
183.05
24.92
207.97
208
52.65
94.50
28.35
70.20
245.70
33.45
279.15
279
Amount
(Rs.)
1274.00
509.60
1783.60
242.84
2026.44
202.64
203
202.64
7.00
2.80
1.33
213.78
214
2912.00
1164.80
15393.00
1427.40
570.96
21468.16
2922.89
24391.05
101.63
102
Amount
(Rs.)
2912.00
1164.80
15393.00
1427.40
570.96
21468.16
2922.89
24391.05
116.15
116
1820.00
728.00
2548.00
346.91
2894.91
289.49
289
2184.00
873.60
15393.00
1427.40
570.96
20448.96
2784.13
CIVIL DATA : Page-182
Amount
(Rs.)
23233.09
129.07
129
222.50
128.75
2922.50
1309.50
963.70
38.80
210.90
659.20
348.04
255.50
140.00
7199.39
980.20
8179.59
817.96
818
1820.00
728.00
5782.20
232.80
1265.40
3955.20
2088.24
15871.84
CIVIL DATA : Page-183
Amount
(Rs.)
2160.95
18032.79
1803.28
1803
Amount
(Rs.)
s per IS 6315 (Part-2) 2001 (pre-constructional chemical treatment
nal vertical faces of the columns, plinth beams, basement and top surface
bed as per the specified procedure confirming to IS 6315 (Part-2) 2001 and
duly using Chlorpyriphos / Lindane emulsifiable concentrate 20% with 1%
the vertical surface & 5.0 Liters/sqm of the horizontal surface of the
und columns & 300mm deep around plinth beams, basements & floor filling
ong the wall & rodding etc & cost & conveyane of all materials to the site,
c complete for finished item of work as per the approval of the Engineer-in-
s & contractors profit )
934.80
9.35
1050.00
88.00
455.20
2537.35
253.73
76.12
38.06
2905.26
395.55
3300.82
330
108.50
43.40
800.29
10.30
962.49
131.04
1093.53
1094
,sides of foundations and basement with initial lead in layers not exceeding
including cost and conveyance of water to work site and all
hire charges of T&P etc., and overheads & contractors profit complete for
10)
CIVIL DATA : Page-185
Amount
(Rs.)
108.50
43.40
2126.28
74.16
2352.34
320.27
2672.61
445.44
445
CIVIL DATA : Page-186
Amount
(Rs.)
ated earth (excluding rock) with a lead of 50 m in trenches, sides of
lead in layers not exceeding 15cm thick, watering and ramming including
k site and all operaitonal, incidental, labour charges, hire charges of T&P
fit complete for fnished item of work (APSS NO.309&310).
108.50
43.40
151.90
74.16
226.06
30.78
256.84
42.81
43
972.00
1093.20
1033.85
123.60
133.50
219.70
87.88
44.50
486.50
212.40
4407.14
600.03
5007.17
5007
CIVIL DATA : Page-187
Amount
(Rs.)
cement: fine aggregate: Coarse aggregate) for foundations and under
te 40mm size hard , machine crushed granite from approved quarry
materials like cement, sand, coarse aggregate, water etc. to site, sales &
uding all charges for machine mixing, laying concrete in foundations and
layers finishing top surface to the required level curing etc.,and overheads
hed item of work. (APSS No. 402)
777.60
1093.20
1033.85
123.60
133.50
219.70
87.88
44.50
486.50
212.40
4212.74
573.56
4786.30
4786
CM (1:8) prop: (Cement: Screened sand) using hard other than granite
including cost and conveyance of all materials like cement, screened sand,
rry, to site, sales & other taxes on all materials including labour for cutting
mixing, of cement, mortar, construction, curing etc.,and overheads &
d item of work in foundation and basement. (APSS No. 601 & 615)
356.40
582.64
824.16
534.00
700.00
493.60
3490.80
34.91
3525.70
480.02
4005.73
4006
CIVIL DATA : Page-188
Amount
(Rs.)
CM (1:8) prop: (Cement: Screened sand) using hard granite stones
g cost and conveyance of all materials like cement, screened sand, water,
site, sales & other taxes on all materials including labour for cutting stones
of cement, mortar, construction, curing etc.,and overheads & contractors
rk in foundation and basement. (APSS No. 601 & 615)
356.40
683.84
824.16
534.00
700.00
493.60
3592.00
35.92
3627.92
493.94
4121.86
4122
:3:6) nominal mix using 40mm size machine crushed hard granite metal
hard granite metal (coarse aggregate) in (2:1) ratio from approved quarry
materials like cement, fine aggregate (sand), coarse aggregate, water etc.
erials, all charges for mixing, laying concrete in position, vibrating, curing,
actors profit etc.,for finished item of work for footings and basement.
728.80
443.12
1033.85
1320.00
123.60
133.50
219.70
87.88
25.80
158.20
63.28
44.50
486.50
212.40
5081.13
61.00
274.00
109.60
5525.73
CIVIL DATA : Page-189
Amount
(Rs.)
752.33
6278.06
6278
2280.00
1181.64
918.98
59.19
108.14
1610.00
710.93
301.66
456.55
34.39
210.88
266.97
123.60
8262.92
8262.92
277.00
532.00
212.80
9284.72
1264.12
10548.84
10549
8262.92
315.00
845.00
338.00
9760.92
1328.95
11089.87
11090
CIVIL DATA : Page-190
Amount
(Rs.)
8262.92
1335.00
1281.00
512.40
11391.32
1550.93
12942.25
12942
CIVIL DATA : Page-191
Amount
(Rs.)
1900.47
63.71
122.36
48.94
2135.49
290.75
2426.23
2426
8262.92
1125.00
9387.92
9388
2280.00
1181.64
918.98
74.32
67.64
1960.00
840.78
301.66
456.55
34.39
210.88
266.97
123.60
8717.41
CIVIL DATA : Page-192
Amount
(Rs.)
CIVIL DATA : Page-193
Amount
(Rs.)
1307.61
1961.42
CIVIL DATA : Page-194
Amount
(Rs.)
Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
ncrete using WEIGH BATCHER / MIXER with 20mm size graded machine
gregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
of all materials like cement, fine aggregate (sand) coarse aggregate, water
on all materials , centering using Casurina Ballies , Bamboos , Wooden
all Plates etc., including all operational, incidental and labour charges such
g, lifting of concrete manually, laying concrete, curing , overheads &
xcluding cost of steel and its fabrication charges for finished item of work
2280.00
1181.64
918.98
29.82
53.87
1076.95
464.25
69.70
105.49
7.95
48.73
61.69
123.60
6422.65
738.60
CIVIL DATA : Page-195
Amount
(Rs.)
802.83
CIVIL DATA : Page-196
Amount
(Rs.)
963.40
1123.96
1284.53
CIVIL DATA : Page-197
Amount
(Rs.)
Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
ncrete using WEIGH BATCHER / MIXER with 20mm size graded machine
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
conveyance of all materials like cement, fine aggregate (sand) coarse
cluding sales & other taxes on all materials , centering using Casurina
s , Runners , Wood Posts , Wall Plates etc., for 60cm wide sun-shades
thick at free end with an average thickness of 6.25cm including all
rges such as weigh batching, machine mixing, lifting of concrete manually,
& contractors profit complete etc., but excluding cost of steel and its
work (APSS No. 402, 403 & 903)
2280.00
1181.64
918.98
29.82
53.87
1076.95
464.25
69.70
105.49
42.20
123.60
6346.49
237.99
216.00
2996.63
CIVIL DATA : Page-198
Amount
(Rs.)
499.49
106.80
226.80
661.50
398.04
51.05
5156.32
29.21
199.82
79.93
5465.28
744.10
6209.37
6209
CIVIL DATA : Page-199
Amount
(Rs.)
superstructure with CM (1:8) prop: (Cement : Screened sand) using
as per Table- I of IS:1077-1992, Non- Modular or traditional size 23 x 11 x 7
nimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of
nd, bricks, water etc., to site, including sales & other taxes on all materials
ng cement mortar, scaffolding charges, constructing masonry, lift charges,
ors profit complete for finished item of work. (APSS No. 501 & 504).
216.00
2996.63
499.49
106.80
226.80
661.50
398.04
51.05
5156.32
5156.32
702.03
5858.35
5858
CIVIL DATA : Page-200
Amount
(Rs.)
tion walls (11.0 cm thick) in CM (1:4) prop. (Cement : Screened sand)
class as per Table- I of IS:1077-1992, Non- Modular or traditional size 23
having minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos. of
yer with free ends of the reinforcement pegged into mortar joints of main
cost and conveyance of all materials like cement, steel, sand, bricks, water
taxes on all materials, all operational, incidental charges such as labour
scaffolding charges, constructing masonry, lift charges, curing, etc., and
cluding cost of steel and its fabrication charges complete for finished item
3306.83
475.20
549.44
267.00
243.00
962.50
589.00
63.93
6456.90
645.69
ment : Screened sand) in superstructure with fly ash cement / lime solid
140mm from approved source having minimum crushing strength of 50
nce of all materials like cement, sand, bricks, water etc., to site, including
nd such as labour charges, like mixing cement mortar, scaffolding charges,
ing, overheads and contrctor profit etc., complete for finished item of work.
3014.15
144.00
249.75
186.90
372.60
245.00
735.00
CIVIL DATA : Page-201
Amount
(Rs.)
615.80
55.63
5618.83
5618.83
765.00
6383.83
6384
alls (100 mm thick) in CM (1:4) prop. (Cement : Screened sand) using fly
ize 290mm x 100mm x 140mm having minimum compressive strength of
mm M.S plain rods in every third layer with free ends of the reinforcement
k walls where applicable including cost and conveyance of all materials like
c., to site, including sales & other taxes on all materials, all operational,
arges for mixing cement mortar, scaffolding charges, constructing masonry,
ads & contractors profit but excluding cost of steel and its fabrication
work. (APSS No. of 509)
3090.39
216.00
249.75
267.00
243.00
962.50
589.00
56.18
5673.82
567.38
CIVIL DATA : Page-202
Amount
(Rs.)
minal mix using 20mm size graded machine crushed hard granite metal
970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and
ent, fine aggregate(sand), coarse aggregate, water etc. to site, including
d including all charges for mixing, laying concrete in position, curing etc., &
ctors profit for Bed Blocks & Hold Fasts for finished item of work. (APSS
1329.35
1033.85
1320.00
123.60
133.50
219.70
87.88
44.50
486.50
212.40
4991.28
CIVIL DATA : Page-203
Amount
(Rs.)
al mix using WEIGH BATCHER / MIXER, 20mm size hard granite machine
gate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
00 kgs. of cement per 1 cum of concrete including cost and conveyance of
gate (Sand), coarse aggregate, water etc., to site including steel centering,
ges, laying concrete,vibrating, curing, overheads & contrctors profit etc.,
coping on top of compound wall (APSS No. 402 & 403).
1800.00
1426.20
1033.85
123.60
133.50
219.70
87.88
44.50
486.50
212.40
5568.14
758.10
6326.24
6326
CIVIL DATA : Page-204
Amount
(Rs.)
n mix using WEIGH BATCHER / MIXER, 20mm size hard granite machine
gate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
30 kgs. of cement per 1 cum of concrete including cost and conveyance of
gate (Sand), coarse aggregate, water etc., to site including steel centering,
ges, laying concrete,vibrating, curing, overheads & contrctors profit etc.,
PSS No. 402 & 403) for steps.
1181.64
918.98
1980.00
123.60
69.70
105.49
7.95
48.73
61.69
29.82
27.14
1076.95
453.56
6085.23
design mix using 12mm size hard granite machine crushed graded metal
970 and IS 2386 Part 1 to Part 8) from approved quarry, using a minimum
1 cum of concrete using WEIGH BATCHER / MIXER including cost and
ent, fine aggregate (Sand), coarse aggregate, water etc., to site including
mixing, laying concrete, lift charges, curing etc., and overheads &
d item of work (APSS No. 402 & 403) for sill slabs.
2100.00
1089.74
918.98
59.19
108.14
1260.00
CIVIL DATA : Page-205
Amount
(Rs.)
570.93
69.70
105.49
42.20
123.60
6447.95
design mix using 12mm size hard granite machine crushed graded metal
970 and IS 2386 Part 1 to Part 8) from approved quarry, using a minimum
1 cum of concrete using WEIGH BATCHER / MIXER including cost and
ent, fine aggregate (Sand), coarse aggregate, water etc., to site including
charges such as weigh batching, machine mixing, laying concrete, lift
& contractors profit complete for finished item of work (APSS No. 402 &
2100.00
1089.74
918.98
29.82
53.87
1076.95
464.25
69.70
105.49
42.20
123.60
6074.58
303.73
CIVIL DATA : Page-206
Amount
(Rs.)
CIVIL DATA : Page-207
Amount
(Rs.)
151.86
151.86
31500.00
330.00
1695.00
3115.00
3500.00
3324.00
43464.00
CIVIL DATA : Page-208
Amount
(Rs.)
eated (TMT) (Fe 500 grade as per IS 1786-1979) of different diameters
harges for straightening, cutting, bending to required sizes and shapes,
of approved materials and size and tying and lap-splicing with binding wire
cement work as per approved designs and drawings, including cost and
l wastages such as overlaps, couplings, chairs, spacer bars including cost
er blocks and all incidental, operational, labour charges such as cutting,
ncluding sales and other taxes on all materials etc. ,and overheads &
item of work.( APSS No.126)
38850.00
330.00
1695.00
3115.00
3500.00
3324.00
50814.00
CIVIL DATA : Page-209
Amount
(Rs.)
rs (Fe 250 grade as per IS 432) of different diameters including labour
ding to required sizes and shapes, placing in position with cover blocks of
ying and lap-splicing with binding wire of 18 SWG, forming grills for
d designs and drawings, including cost and conveyance of steel bars,
ps, couplings, chairs, spacer bars including cost and conveyance of binding
operational, labour charges such as cutting, bending, placing in position,
s on all materials etc. ,and overheads & contractors profit complete for
36750.00
330.00
1695.00
3115.00
3500.00
3324.00
48714.00
m thick in two coats using screened sand with base coat of 8mm thick in
n CM (1:4) with dubara sponge finishing including cost and conveyance of
er etc., to site, including sales & other taxes on all materials, and all
terials and including cost of all labour charges for mixing mortar, finishing,
uding cutting grooves as directed by Engineer - in - charge etc., and
te for finished item of work. (SS 901,903 & 904)
158.40
274.72
86.40
99.90
280.35
595.35
1365.00
896.28
37.56
3793.96
CIVIL DATA : Page-210
Amount
(Rs.)
379.40
CIVIL DATA : Page-211
Amount
(Rs.)
using screened sand with base coat of 8mm thick in CM (1:6) and top coat
ara sponge finishing including cost and conveyance of all materials like
uding sales & other taxes on all materials, and all operational, incidental
st of all labour charges for mixing mortar, finishing, scaffolding, lift charges,
irected by Engineer - in - charge etc., and overheads & contractors profit
S 901,903 & 904).
158.40
274.72
86.40
99.90
280.35
595.35
1365.00
896.28
37.56
3793.96
379.40
CIVIL DATA : Page-212
Amount
(Rs.)
in CM(1:5) using screened sand including cost and conveyance of all
., to site, including sales & other taxes on all materials, and all operational,
ncluding cost of all labour charges for mixing mortar, finishing, curing as
and overheads & contractors profit complete for finished item of work.(SS
259.20
374.62
267.00
336.00
241.20
14.78
1492.80
149.28
149.28
20.32
169.60
170
s using screened sand with base coat of 16mm thick in CM(1:6) and top
ubara sponge finishing including cost and conveyance of all materials like
uding sales & other taxes on all materials, and all operational, incidental
st of all labour charges for mixing mortar, finishing, scaffolding, lift charges,
directed by Engineer-in-charge etc., and overheads & contractors profit
S 901,903 & 904)
259.20
449.54
86.40
99.90
CIVIL DATA : Page-213
Amount
(Rs.)
280.35
595.35
1365.00
896.28
40.32
4072.34
407.23
362.88
524.46
380.70
560.00
376.28
22.04
2226.37
222.64
222.64
30.31
252.95
253
CIVIL DATA : Page-214
Amount
(Rs.)
sed RCC roof slab surfaces to required slopes with CM (1:3) prop. using
) mixed with integral cement water proofing liquid confirming to IS: 2645-
ufacturers as approved by Engineer-in-charge at 1 Kg per one bag of
green, finished smooth with a floating coat of neat cement and thread lining
ncluding cost and conveyance of all materials like cement, sand, water
, including sales & other taxes on all materials and operational, incidental,
, laying, lift charges, rendering smooth and thread lining, curing including
b etc., and overheads & contractors profit complete for finished item of
604.80
524.46
84.00
293.70
623.70
1295.00
884.96
43.11
4353.73
sed RCC roof slab surfaces of sump , sump side wall,sump bottom
en slabs etc. to required slopes with CM (1:3) prop. using screened sand
ment water proofing liquid confirming to IS: 2645-2003 manufactured by
by Engineer-in-charge at 1 Kg per one bag of cement, laid over roof slab
h a floating coat of neat cement and thread lining at regular intervals of
ncluding cost and conveyance of all materials like cement, sand, water
, including sales & other taxes on all materials and operational, incidental,
, laying, lift charges, rendering smooth and thread lining, curing including
etc., and overheads & contractors profit complete for finished item of work.
432.00
374.62
60.90
CIVIL DATA : Page-215
Amount
(Rs.)
267.00
336.00
241.20
17.12
1728.83
using screened sand for drop walls, fins with rabbit wire mesh & nomianl
gineer - In - Charge with dubara sponge finishing,including cost and
sales & othertaxes on all materials,operationals &incidental,cost and
ter to work site,centering,scaffolding and form work,lift charges etc., and
ete for finished item of work but excluding cost of steel and its fabrication
SS NO.403&903).
226.10
1440.00
300.00
1248.73
3560.00
445.00
3500.00
3002.00
267.00
439.40
175.76
146.04
14750.02
1475.00
CIVIL DATA : Page-216
Amount
(Rs.)
Tandur stone slabs of 15mm to 18mm thick set over a base coat of CM
nd over already laid CC bed / RCC roof slab including neat cement slurry of
Kgs per Sqm and jointed with neat cement to full depth including cost and
nt, sand, water, flooring stones etc. complete including sales & other taxes
charges like dressing of flooring stones to the required size, mixing of
cost of base coat, water charges etc., and overheads & contractors profit
PSS No.703 & 701)
2072.75
129.60
198.00
120.00
299.69
1379.50
445.50
301.00
850.40
57.96
5854.41
CIVIL DATA : Page-217
Amount
(Rs.)
pa slabs 15mm to 18mm thick set over a base coat of CM (1:8) , 12mm
dy laid CC bed / RCC roof slab including neat cement slurry of honey like
r Sqm and jointed with neat cement to full depth including cost and
nt, sand, water, flooring stones etc. complete including sales & other taxes
charges like dressing of flooring stones to the required size, mixing of
cost of base coat, water charges etc., and overheads & contractors profit
PSS No.703 & 701)
1752.32
129.60
198.00
120.00
299.69
1379.50
445.50
301.00
850.40
54.76
5530.78
CIVIL DATA : Page-218
Amount
(Rs.)
eramic floor tiles of size 300mm x 300mm and thickness between 7 -
11, IS: 13712, IS: 13630(Part 1 to 15) of any colour and finish in all shades
er-in-charge, set over base coat of cement mortar (1:8), 12mm thick using
aid or RCC roof slab, including neat cement slurry of honey like consistency
neatly with white cement paste to full depth mixed with pigment of matching
s like cement, screened sand , water and tiles etc., and overheads &
item of work. (APSS No.701 & 707)
4725.00
129.60
198.00
62.00
299.69
427.20
907.20
1155.00
995.76
88.99
8988.45
5565.00
129.60
198.00
62.00
299.69
CIVIL DATA : Page-219
Amount
(Rs.)
427.20
907.20
1155.00
995.76
97.39
9836.85
CIVIL DATA : Page-220
Amount
(Rs.)
n vitrified tiles screen printed and polished of size 600 x 600 mm and
ality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1 to 15) of any
designs with borders and design as per the approved flooring pattern as
aying tiles using spacers of 2mm thick, set over a base coat of CM (1:8)
nd over CC bed already laid or RCC roof slab , including neat cement slurry
3.3 kgs per Sqm. and jointed neately with white cement paste to full depth
de including cost and conveyance of all materials like cement, sand,
(excluding cost of C.C. bed) including cost of base coat and all labour
, laying tiles to required slope as directed by the Engineer- in-charge
t complete for finished item of work. (APSS No.701 & 707).
5775.00
129.60
198.00
186.00
299.69
427.20
907.20
1155.00
995.76
100.73
10174.19
8mm thick (mirror polished of all shades) of 1st quality and of size as
borders and design as per the approved flooring pattern as directed by the
g spacers of 2mm thick, set over a base coat of CM (1:8) prop. 12mm
ed already laid or RCC roof slab , including neat cement slurry of honey
er Sqm. and jointed neately with white cement paste to full depth mixed
ding cost and conveyance of all materials like cement, sand, water, tiles,
cost of C.C. bed) including cost of base coat and all labour charges for
to required slope as directed by the Engineer- in-charge etc., and
te for finished item of work. (APSS No.701 & 707)
12232.50
CIVIL DATA : Page-221
Amount
(Rs.)
129.60
198.00
186.00
299.69
427.20
907.20
1155.00
995.76
165.31
16696.26
CIVIL DATA : Page-222
Amount
(Rs.)
gh polished granite stone slabs other than black and regular colours
wer / copper silk / laka red / lavender blue) with borders and design as per
-in-Charge of length not less than 2.43 mts set over base coat of cement
ened sand over CC bed already laid or RCC roof slab including neat grey
cy spread @ 3.3 Kg per sqm and jointed neatly with white cement paste
e to full depth including cost and conveyance of all materials like cement ,
work site and all operational, incidental labour & lift charges, polishing
aterials, cost of base coat and overheads & contractors profit complete for
al)
31374.00
216.00
198.00
186.00
499.49
1335.00
405.00
2800.00
1816.00
388.29
39217.78
CIVIL DATA : Page-223
Amount
(Rs.)
high polished granite stone slabs black colour as approved by the
s than 2.43 mts set over base coat of cement mortar (1:8) , 20mm thick
eady laid or RCC roof slab including neat grey cement slurry of honey like
qm and jointed neatly with white cement paste mixed with pigment of
g cost and conveyance of all materials like cement , sand , water , granite
tional, incidental labour & lift charges, half rounding the edge , polishing
terials, cost of base coat and overheads & contractors profit complete for
.S.701 & special)
26670.00
216.00
198.00
186.00
499.49
1335.00
405.00
2800.00
1816.00
266.72
5251.05
882.84
405.26
40931.36
CIVIL DATA : Page-224
Amount
(Rs.)
mm thick with (1:1:2), using 6mm to 12 mm size hard granite machine
d over CC bed already laid or RCC roof slab, in alternate panels of size not
ass strips and finishing the top surface to required smoothness and slopes
materials like cement, metal sand and water and overheads & contractors
k. (APSS No.701 & 710)
231.57
720.00
195.28
556.25
24.30
1050.00
652.22
34.30
3463.92
3171.00
172.80
198.00
62.00
299.69
427.20
907.20
1155.00
995.76
73.89
7462.54
CIVIL DATA : Page-225
Amount
(Rs.)
dur stone slabs of 15mm to 18mm thick in single piece as specified set
m thick using screened sand over already laid CC bed / RCC roof slab
like consistency spread @ 3.3 Kgs per Sqm and jointed with neat cement
veyance of all materials like cement, sand, water, flooring stones etc.
es on all materials including all labour charges like dressing of flooring
the edges, mixing of cement mortar, laying, lift charges , cost of base coat,
contractors profit complete for finished item of work for treads and risers.
2072.75
207.36
198.00
120.00
299.69
1379.50
445.50
301.00
850.40
1633.17
261.31
77.69
7846.37
2072.75
299.69
207.36
CIVIL DATA : Page-226
Amount
(Rs.)
198.00
427.20
907.20
1085.00
967.76
61.65
6226.62
slabs 15mm to 18mm thick in single piece as specified set over a base
screened sand over already laid CC bed / RCC roof slab including neat
cy spread @ 3.3 Kgs per Sqm and jointed with neat cement to full depth
materials like cement, sand, water, flooring stones etc. complete including
ncluding all labour charges like dressing of flooring stones to the required
cement mortar, laying, lift charges , cost of base coat, water charges etc.,
omplete for finished item of work for treads and risers. (APSS No.703 &
2628.48
207.36
198.00
120.00
299.69
1379.50
445.50
301.00
850.40
1633.17
261.31
83.24
8407.66
CIVIL DATA : Page-227
Amount
(Rs.)
2628.48
299.69
207.36
198.00
427.20
907.20
1085.00
967.76
67.21
6787.90
lished granite stone slabs other than black and regular colours (i.e. of
opper silk / laka red / lavender blue) with borders and design as per the
-Charge of length not less than 2.43 mts set over base coat of cement
ened sand over CC bed already laid or RCC roof slab including neat grey
cy spread @ 3.3 Kg per sqm and jointed neatly with white cement paste
e to full depth including cost and conveyance of all materials like cement ,
rk site and all operational, incidental labour & lift charges, half rounding the
and all other taxes on all materials, cost of base coat and overheads &
item of work for treads and risers (S.S.701 & special)
31374.00
207.36
198.00
186.00
299.69
1335.00
405.00
2800.00
1816.00
533.28
CIVIL DATA : Page-228
Amount
(Rs.)
10498.95
1765.16
514.18
51932.63
CIVIL DATA : Page-229
Amount
(Rs.)
31374.00
299.69
207.36
198.00
155.00
1066.72
170.68
934.50
1715.00
1059.80
371.81
37552.56
2072.75
299.69
207.36
198.00
427.20
907.20
1085.00
967.76
61.65
6226.62
CIVIL DATA : Page-230
Amount
(Rs.)
1752.32
299.69
207.36
198.00
427.20
907.20
1085.00
967.76
58.45
5902.98
5565.00
299.69
207.36
198.00
186.00
342.65
CIVIL DATA : Page-231
Amount
(Rs.)
280.00
249.06
73.28
7401.04
5775.00
299.69
207.36
198.00
62.00
342.65
280.00
249.06
74.14
7487.90
Amount
(Rs.)
12232.50
299.69
207.36
198.00
155.00
342.65
280.00
249.06
139.64
14103.91
m thick mirror polished granite tiles length equal to flooring tiles, set over
ing screened sand with cement slurry of honey like consistency spread at
ting with white cement paste mixed with pigment of matching shade to full
ike tiles, cement, sand and water etc., and overheads & contractors profit
SS No.701 &707)
CIVIL DATA : Page-233
Amount
(Rs.)
10cm height with High Polished Granite 16 to 18 mm thick up to 8'-00
ar colours, length equal to flooring slabs set over base coat of CM(1:5) 12
ement slurry of honey like consistency spread at the rate of 3.30 kgs per
ste mixed with pigment of matching shade to full depth, including cost of all
water etc., and overheads & contractors profit complete for finished item of
31374.00
299.69
207.36
198.00
155.00
1066.72
170.68
934.50
1715.00
1059.80
371.81
37552.56
Amount
(Rs.)
lazed full body porcelain wall tiles of size 300 x 600 mm with any type
nish, wooden, bamboo, stone finishes etc., scratch less, stain free and
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour
with borders as approved by Engineer-in-Charge set over base coat of
sand with cement slurry of honey like consistency spread at the rate of 3.30
ement paste mixed with pigment of matching shade to full depth, including
sand and water etc., complete overheads & contractors profit complete for
7255.50
299.69
207.36
198.00
186.00
342.65
280.00
249.06
90.18
9108.45
CIVIL DATA : Page-235
Amount
(Rs.)
azed full body ceramic tiles of any size and thickness between 5 to 7mm
: 13712, IS: 13630(Parts 1 to 15) of any colour and finish in all shades and
y Engineer-in-Charge set over base coat of CM(1:5) 12 mm thick using
honey like consistency spread at the rate of 3.30 kgs per sqm and jointing
pigment of matching shade to full depth, including cost of all materials like
d overheads & contractors profit complete for finished item of work.
4515.00
299.69
207.36
198.00
186.00
342.65
280.00
249.06
62.78
6340.54
in Cement Concrete (1:5:10) proportion using brick jelly for low roofs
materials like cement, sand, brick bats etc., to site including cost of all
mming, curing , overheads & contractors profit etc., complete for finished
777.60
897.43
1033.85
123.60
133.50
219.70
87.88
44.50
486.50
212.40
4016.96
CIVIL DATA : Page-236
Amount
(Rs.)
777.60
1093.20
1033.85
74.32
67.64
1645.00
714.78
133.50
219.70
25.80
158.20
151.16
123.60
6218.35
CIVIL DATA : Page-237
Amount
(Rs.)
teel ( grade 304 ) hand railing as per approved drawing with top rail of
m class and vertical posts of 25mm dia and 1.6mm thick medium class 2
ate of 75mm dia using bonding agent and anchor fastner and welding,
matic compressor for fixing railing, buffing, polishing all members of the
to present seamless finish including cost and conveyance of all materials,
all consumables, labour charges , overheads & contractors profit etc.,
12441.62
4136.60
197.60
1300.00
520.00
260.00
18855.82
4099.09
4554.55
620.10
5174.65
5175
VC down water take pipes with socket , 2.5mm thick 4.0 kg/sq.cm pressure
sary PVC Bends, shoes, iron / PVC clamps and all other accessories and
conveyance of all materials, sales & other taxes on materials to site,
ding all labour charges for fixing at site etc., and overheads & contractors
k. (APSS No. 1328)
906.00
54.00
426.00
1386.00
231.00
31.45
262.45
262
620.00
620.00
CIVIL DATA : Page-238
Amount
(Rs.)
62.00
32.45
59.54
112.00
81.59
347.57
47.32
394.89
39.49
39
1035.00
140.60
257.99
318.50
286.83
2038.91
277.60
2316.51
231.65
232
CIVIL DATA : Page-239
Amount
(Rs.)
ade Texture ready mixed paint with sand texture added sand particles
ounds, bactericides and various additives of average 2 to 3 mm thickness
surface even and smooth after thoroughly brushing the surface to remove
d materials, applying emery paper, Sand the surface, clean & wipe off loose
er by putty knife / muslin pad, air dry for 2 - 3 hrs for the surface
yance of all materials to work site and all operational, incidental, labour
ads and contractors profit etc., complete for finished item of work in all
1380.00
140.60
257.99
318.50
286.83
9.90
67.90
27.16
2488.87
338.86
2827.73
282.77
283
15.50
41.20
76.95
153.00
185.40
340.20
257.50
1069.75
145.65
1215.40
121.54
122
Amount
(Rs.)
153.00
185.40
340.20
210.24
888.84
121.02
1009.86
100.99
101
31.00
41.20
76.95
110.00
77.25
141.75
525.00
344.86
1348.01
183.53
1531.54
153.15
153
110.00
77.25
141.75
525.00
297.60
1151.60
156.79
1308.39
130.84
131
CIVIL DATA : Page-241
Amount
(Rs.)
CIVIL DATA : Page-242
Amount
(Rs.)
ater based cement primer of interior grade I and two coats of acrylic
e Organic Compound) content less than 50 grams/litre for internal walls
materials to site, sales & other taxes, incidental, operational and all labour
ctors profit complete for finished item of work in all floors.
165.00
108.15
198.45
171.20
185.40
340.20
332.88
1501.28
204.40
1705.68
170.57
171
ater based cement primer of exterior grade II and two coats of acrylic
ilicon additives having VOC (Volatile Organic Compound) content less than
cluding cost and conveyance of all materials to site, sales & other taxes,
charges etc., and overheads & contractors profit complete for finished item
210.00
108.15
198.45
180.00
108.15
198.45
525.00
455.28
9.90
67.90
27.16
2088.44
284.34
2372.78
237.28
237
CIVIL DATA : Page-243
Amount
(Rs.)
sh shutters with lappam finish, over a primary coat and painting two
ade-I VOC (Volatile Organic Compound) content less than 50 grams/litre of
onveyance of all materials to site cost of primer coat and all labour charges
paper on lappam coats for neat finish including sales & other taxes on cost
contractors profit complete in all floors (APSS No.1200, 1207 & 1211).
158.00
110.60
108.15
198.45
331.20
185.40
340.20
332.88
1764.88
240.29
2005.17
200.52
201
ush shutters with two coats of synthetic enamel paint Grade-II VOC
less than 50 grams/litre of approved brand and shade including cost and
and all labour charges etc. complete, sales & other taxes on cost of all
ctors profit complete in all floors (APSS No.1200, 1207 & 1211) .
303.60
185.40
340.20
210.24
1039.44
141.52
1180.96
118.10
118
work using red oxide Iron primer paint grade - 1 of approved brand
materials to site , all labour charges etc., and overheads & contractors profit
1, 1212 & 1207).
99.40
108.15
198.45
122.64
CIVIL DATA : Page-244
Amount
(Rs.)
528.64
71.97
600.61
60.06
60
303.60
169.95
311.85
192.72
978.12
133.17
1111.29
111.13
111
99.40
303.60
108.15
198.45
169.95
311.85
315.36
1506.76
205.15
1711.91
171.19
171
CIVIL DATA : Page-245
Amount
(Rs.)
enamel paint Gr-I having VOC (Volatile Organic Compound) content less
ncluding cost and conveyance of all materials to site, sales & other taxes,
harges and overheads & contractors profit etc., complete for finished item
12 & 1207).
248.40
169.95
311.85
192.72
922.92
125.66
1048.58
104.86
105
oors using French spirit polish of approved brand for new wood work to
g sand papering to smooth surfaces etc. including cost and conveyance of
etc., complete for finished item of work in all floors.
47.20
180.93
494.40
907.20
560.64
2190.37
298.22
2488.58
248.86
249
h Glossy/ Matt finish to the wood works duly cleaning the surface and
d with 180 No., emery paper and then with 320 No., emery paper, clean &
knifing paste filler / wood filler by putty knife / muslin pad, air dry for 2 - 3
ry paper, apply two component wood sealer, air dry for 24 hrs, Sand with
coat of approved spraying thinner (for spraying)/ applying one coat of
purpose thinner (for brushing) and apply (either with spray or brush) two
cluding cost & labour charges, emery papers, cost of thinner & melamine
ofit etc., complete for finished item of work
22.69
4.82
CIVIL DATA : Page-246
Amount
(Rs.)
123.60
226.80
280.00
252.16
910.06
123.91
1033.97
1034
Water Proof Polish Glossy/ Matt finish to the wood works duly cleaning
r, Sand the wood with 180 No., emery paper and then with 320 No., emery
plying suitable knifing paste filler / wood filler by putty knife / muslin pad, air
d 320 No., emery paper, applying two component wood sealer, after the
at of approved spraying PU thinner (for spraying) / applying one coat of
eral purpose thinner (for brushing) and apply one coat of PU by brush or
with 180 No. emery paper and removing dust, applying second coat of PU,
0 No emery paper, and applying (either with spray or brush) two coats of
abour charges, emery papers, cost of thinner & Poly-Urethane Water Proof
fit etc., complete for finished item of work
46.15
4.82
123.60
226.80
280.00
252.16
933.53
127.10
1060.63
1061
3576.00
486.87
4062.87
4063
CIVIL DATA : Page-247
Amount
(Rs.)
el shutters with vertical, double channel of 20 x10x2 mm of 100 mm
mm with 38 mm dia steel pulleys, the top, bottom and side vertical frames
x8mm MS Angle and middle guide rail at site height with 65mmx8mm MS
ed with necessary hold fasts, bolts, nuts, rivets, locking arrangements,
ixtures and painted with one coat of approved steel primer etc., overheads
ed item of work as per special spn 1105
3129.00
426.01
3555.01
3555
650.00
88.50
738.50
738
oint filler board for buildings, columns, beams and slabs 25 mm thick
materials to site, all incidental, operational, labour charges etc.overheads &
item of work as per approved drawing for all floors
403.00
54.87
457.87
458
302.00
198.00
500.00
76.00
10.35
86.35
86
CIVIL DATA : Page-248
Amount
(Rs.)
mposite cladding 4mm thick of approved make with skin material 0.25
aterial natural polyethylene aluminium cladding panel fixed with extruded
) angle cleats, weather sealants, rivets, GI brackets all as approved, using
k including necessary accessories complete in all respects including all
heads & contractors profit complete for finished item of work but excluding
y.
2820.00
383.94
3203.94
3204
mposite cladding 4mm thick of approved make with skin material 0.50
aterial natural polyethylene aluminium cladding panel fixed with extruded
) angle cleats, weather sealants, rivets, GI brackets all as approved, using
k including necessary accessories complete in all respects including all
erheads & contractors profit etc., complete for finished item of work but
ation if any.
3163.00
430.64
3593.64
3594
mine Monomer. Natural cure, with Good U.V. Resistance Silicon to be used.
sonry wall should be with self-expanding cap & screws. The rate is inclusive
als to site, all labour charges, incidental charges, cost of all consumables
k , overheads & contractors profit etc., complete for finished item of work in
7288.00
992.26
8280.26
8280
CIVIL DATA : Page-249
Amount
(Rs.)
utters in Structural Glazing fabricated from Roll formed sections made of
ase steel as per IS 513 of ‘D’ quality, galvanized as per IS 277 with Zinc of
ness of 0.72mm. The glass holding section made of 304 grade stainless
steel sections are to be used as stiffeners inside the colour coated
r the design requirement. Design calculations are made to suit wind
r coat with epoxy primer of 5-7 microns thick and back coated with Alkyd
ed with pure polyester powder up to 50-60 microns thick. The outer frame
, Shutter section should be of 58mm x 33mm x 0.72 mm, stiffener section
ARL Bihari Hinges – 2 Nos for each shutter and Aluminium Stays – 2 Nos.
1 no. for each shutter. The rate is inclusive of cost and conveyance of all
mables etc. and scaffolding charges, form work, overheads & contractor
work in all floors.
5891.00
802.06
6693.06
6693
g made of pre painted steel (base steel as per IS 513 of 0.6 mm thick D
Zinc of 120 GSM) Primer coated with epoxy primer of 5-7 microns thick,
12- 16 microns thick and back coated with 5-7 microns thick alkyd backer.
x 52 mm, section for mullion should be 46 x 70 mm and section for beading
should be paneled with 5 mm thick plain float Glass with Ethyl Propylene
. The sections are to be cut to length, mitre joined with corner bracket.
g mullion cap. Handle made of high grade Aluminium powder coated and
yl propylene Diamine Monomer (EPDM) Corner brackets made of CRCA
ade of Glass filled nylon. The above frames should be fixed to the concrete
nding screws,overheads & contractor profit etc., complete for finished item
6013.00
818.67
6831.67
6832
5102.00
694.64
5796.64
5797
tal level 12 mm - Mineral Fiber sheet 600 x 600 (Square / Tegular) edge
0% RH,Average NRC 0.50, Light Reflectance >80%, Thermal Conductivity
ance Class 0/Class 1 using hot dipped Galvanized Steel section exposed
in Tee of size 24 x 32 mm at every 1200 mm c/c maximum and rotary
m at every 600 mm c/c and sub-cross tee of size 24 mm x 25 mm at 1200
mm fixed to periphery of the wall and the above grid is suspended at every
2.0 mm thick pre-straightened GI Wire including cost and conveyance of all
cutting , fixing of standing of frame work exposing roof making, overheads
nished item of work in all floor in all floors.
CIVIL DATA : Page-250
Amount
(Rs.)
456.00
16.00
76.00
73.60
12.80
2.56
57.60
48.60
12.36
9.72
5.76
5.76
25.20
66.00
40.00
37.12
945.08
9.45
954.53
129.96
1084.49
1084
590.00
16.00
76.00
CIVIL DATA : Page-251
Amount
(Rs.)
73.60
12.80
2.56
57.60
48.60
12.36
9.72
5.76
5.76
25.20
66.00
40.00
37.12
1079.08
10.79
1089.87
148.39
1238.26
1238
255.44
47.36
71.40
70.56
29.60
3.68
1.28
1.28
36.00
15.95
CIVIL DATA : Page-252
Amount
(Rs.)
7.30
21.30
57.60
48.60
12.36
9.72
5.76
11.52
25.20
68.30
40.00
74.24
914.45
9.14
923.60
125.75
1049.35
1049
ine line Grid false ceiling (GS-FLC-4.6)using 12.5mm thick Gyp Board
onforming to IS 2095 - 1992 fixing to Gyp steel precoated GI wall angle of
long the perimeter of ceiling screw fixed to brick work / partition at 610mm
rame work using precoated GI Tee section (24mm x 38mm x 0.7mm) from
ixed with GI Soffit Cleat, rawl plugs and steel expansion fasteners &
with 4mm dia GI rod with galvanised spring steel level clip of PVC unversal
er to center and fixing the 12.5mm Gypboard sheet tiles of size 595mm x
wall top coat, overheads and contractor profit complete for finished item of
281.00
16.40
172.80
15.36
2.56
2.56
16.08
21.30
57.60
48.60
12.36
9.72
5.76
5.76
25.20
CIVIL DATA : Page-253
Amount
(Rs.)
66.00
40.00
37.12
836.18
8.36
844.54
114.98
959.53
960
False ceiling in true horizontal level 600mm x 600mm using 12mm thick
m Tee sections of size 24.50mm x 24.0mm x 2.4mm in grid with cross tee
0mm center to center and anodised aluminium wall angle of size 24mm x
nd the above grid is suspended at every 1200mm center to center in both
for finished of size 600mm x 600mm including cost and conveyance of all
as cutting , fixing of standing of frame work exposing roof complete for
rate is inclusive of overheads & contractor profit).
26.00
10.40
108.80
12.80
2.56
51.84
43.74
9.60
19.20
70.00
77.75
20.00
37.12
489.81
4.90
494.71
67.35
562.06
562
minal bore Medium Grade properties & weight as per IS 1239 ISI mark MS
g cost and conveyance of all materials to work site and all operational,
s & contractors profit for finished item of work.etc., complete for finished
head room roof.
311.10
132.60
20.40
29.38
493.48
CIVIL DATA : Page-254
Amount
(Rs.)
67.19
560.66
561
0.80mm thick fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen & G.I
including a coat of approved steel primer and two coats of approved paint
up to a pitch of 600) etc., complete, excluding the cost of purlins, rafters,
e of all materials , labour charges , overheads and contractors profit etc.,
ll floors.
6185.40
239.55
439.00
91.82
91.82
28.56
55.20
340.20
318.50
9.27
17.01
21.00
21.63
39.69
49.00
326.52
8274.17
827.42
112.65
940.07
940
4788.00
239.55
439.00
91.82
CIVIL DATA : Page-255
Amount
(Rs.)
91.82
340.20
318.50
263.48
6572.37
657.24
89.48
746.72
747
166.00
24.9
10.05
200.95
27.36
228.31
228
Main gate of size 9mts x 3.75 mts ( average height) i.e., varying from 3mts
oved drawing using MS Angle of 75mm x 75mm x 6mm alround for frame
s horizontally, 25mm MS Square bars at 125mm c/c and CI Spikes 9" long
middle in two rows including 6 Nos of Pin clamps fixed in RCC Columns, 2
pecial ) welded at the the centre on each side, 2 Nos of MS tower bolts
g brass emblem on emboseed cover in the centre of the two leaves and
cluding cost and conveyance of all materials,fabrication charges , welding
bour charges, over heads and contractor profit etc., complete for finsihed
Kgs
Kgs
Kgs
Kgs
Kgs
4165.00
2535.75
22555.31
7600.00
2700.00
1500.00
900.00
1000.00
892.08
1650.58
25712.38
3955.75
5696.28
CIVIL DATA : Page-256
Amount
(Rs.)
2000.00
237.53
83100.66
11314.15
94414.81
2797.48
2797
Wicket gate Size 1.50m x 3.00m as per the approved drawing using 75mm
frame and 63mm x 6mm MS flats in 6 rows horizontally, 25mm MS square
ikes 9" long at the top and 6" long spikes in two rows in the middle, 3 Nos
providing 2 Nos.of MS powder coated aldrops 300mm long including cost
terials,fabrication charges welding charges incidental charges all labour
ofit etc., complete for finsihed item of work.
Kgs
Kgs
Kgs
Kgs
Kgs
Kgs
2142.00
736.92
5671.05
2400.00
362.00
1350.00
118.94
220.08
6359.34
978.36
1408.84
220.11
21967.64
2990.89
24958.53
5546.34
5546
of excavation of trap pit and laying 100 mm hick PCC (1:5:10) prop bed in
metal including constructing 230 mm thick walls alround and middle in PCC
raded metal, 325 mm average height over the bed and duly fixing 7 nos of
m centre to centre and welding 25 mm dia HYSD bars duly inserted in GI B
ver ISLB @ 80 mm centre to centre 25 mm dia MS small pieces of 0.15 m
nd including plastering the exposed faces of walls and base in CM 1:5 prop
ntaining 1:50 slope including providing 200mm dia SWG drain pipe to be
ain off the collected water inside the trap including cost and conveyance of
es including cutting, welding of bars to (ISLB) RS joists, curing centering,
complete for finished item of work as per the approved drawing.
CIVIL DATA : Page-257
Amount
(Rs.)
1084.14
5645.07
6681.76
8388.10
5316.80
2485.00
12084.02
1859.08
2677.08
282.75
19619.01
214.54
66337.35
12232.59
12233
Name of the work : Proposed Construction of Centre For Excellence,Institute Of
Mental Health,Hyderabad.
GENERAL ABSTRACT
Rate
Unit Amount
S.No. Description of Work Quantity Unit
(in words) (Rs.)
In Figures
1 Earth work excavation for foundations 3694.00 Cum 1 One Cum 289.00 1067566
(Manual Means) of buildings in ordinary
rock ( not requiring blasting ) and
depositing on bank with an initial lead of
10m and depth up to 3m including all
operational,incidental, labour charges
such as shoring, sheeting, planking,
strutting etc., and overheads &
contractors profit complete for finished
item of work excluding dewatering
charges etc., as per SS 20 B(APSS 308)
2 Plain Cement Concrete (1:4:8) 123.00 Cum 1 One Cum 5007.00 615861
(cement: fine aggregate: Coarse
aggregate) for foundations and under
flooring bed using coarse aggregate
40mm size hard , machine crushed
granite from approved quarry including
cost and conveyance of all materials like
cement, sand, coarse aggregate, water
etc. to site, including sales & other taxes
on all materials and including all charges
for machine mixing, laying concrete in
foundations and under flooring bed,
ramming in 15 cm layers finishing top
surface to the required level curing etc.,
and overheads & contractors profit
complete for finished item of work.
(APSS No. 402)
4 Filling with useful available excavated 3010.00 Cum 1 One Cum 43.00 129430
earth (excluding rock) with a lead of 50
m in trenches, sides of foundations and
basement with initial lead in layers not
exceeding 15cm thick, watering and
ramming including cost and conveyance
of water to work site and all operaitonal,
incidental, labour charges, hire charges
of T&P etc., and overheads &
contractors profit complete for fnished
item of work (APSS NO.309&310).
b) Lintels
First Floor : 19.00 Cum 1 One Cum 12457.00 236683
b) Roof Slabs
i) Slabs 150 mm thick upto an un-
supported height of 3.66m
First Floor : 4284.00 Sqm 1 One Sqm 1493.00 6396012
10 Random Rubble stone masonry in CM 99.00 Cum 1 One Cum 4122.00 408078
(1:8) prop: (Cement: Screened sand)
using hard granite stones carted from
approved quarry including cost and
conveyance of all materials like cement,
screened sand, water, stones etc., from
approved quarry, to site, sales & other
taxes on all materials including labour for
cutting stones to required size and
shape, mixing, of cement, mortar,
construction, curing etc.,and overheads
& contractors profit complete for finished
item of work in foundation and basement.
(APSS No. 601 & 615)
2 Filling with useful available excavated earth (excluding rock) 20.00 Cum 31.00 620
with a lead of 50 m in trenches, sides of foundations and
basement with initial lead in layers not exceeding 15cm thick,
watering and ramming including cost and conveyance of water
to work site and all operaitonal, incidental, labour charges, hire
charges of T&P etc., and overheads & contractors profit
complete for fnished item of work (APSS NO.309&310)
4 Plain Cement Concrete (1:4:8) (cement: fine aggregate: 9.00 Cum 3819.00 34371
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry including cost and conveyance
of all materials like cement, sand, coarse aggregate, water etc.
to site, including sales & other taxes on all materials and
including all charges for machine mixing, laying concrete in
foundations and under flooring bed, ramming in 15 cm layers
finishing top surface to the required level curing etc., and
overheads & contractors profit complete for finished item of
work. (APSS No. 402)
9 Providing impervious coat to exposed RCC roof slab 45.00 Sqm 367.00 16515
surfaces to required slopes with CM (1:3) prop. using
screened sand 20mm thick (average) mixed with integral
cement water proofing liquid confirming to IS: 2645-2003
manufactured by reputed manufacturers as approved by
Engineer-in-charge at 1 Kg per one bag of cement, laid over
roof slab when it is green, finished smooth with a floating coat
of neat cement and thread lining at regular intervals of
45cmx45cm including cost and conveyance of all materials
like cement, sand, water proofing compound, water etc., to
site, including sales & other taxes on all materials and
operational, incidental, and labour charges for mixing mortar,
laying, lift charges, rendering smooth and thread lining, curing
including rounding off junctions of wall and slab etc., and
overheads & contractors profit complete for finished item of
work. (APSS No. 901 & 903).
10 Providing Thermo Mechanically Treated (TMT) (Fe 500 3.10 MT 53956.00 167264
grade as per IS 1786-1979) of different diameters for RCC
works , including labour charges for straightening, cutting,
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks
and all incidental, operational, labour charges such as cutting,
bending, placing in position, tying including sales and other
taxes on all materials etc. ,and overheads & contractors profit
complete for finished item of work.( APSS No.126)
12 Supply and delivery of encapsulated plastic steps 10.00 Each 228.00 2280
manufactured as per companies standard specification
including cost of materials packing as per companiess
standards, loading, transportation, unloading and stacking at
site of work , and taxes such as complete sales tax,C.E.D and
others etc., as applicable including labour charges for fixing
etc. complete for finished item of work.
601 581352
Column footings
F1 1 24 2.15 2.00 2.00 206.40
F2 1 31 2.30 2.10 2.00 299.46
F3 1 56 2.65 2.50 2.00 742.00
F4 1 14 2.90 2.75 2.00 223.30
F5 1 3 2.85 2.55 2.00 43.61
F6 1 6 2.30 2.30 2.00 63.48
F7 1 51 2.60 2.60 2.00 689.52
F8 1 21 2.85 2.85 2.00 341.15
F9 1 13 3.10 2.90 2.00 233.74
F10 1 3 3.60 3.45 2.00 74.52
F11 1 7 3.05 3.05 2.00 130.24
F12 1 3 3.35 3.35 2.00 67.34
2 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations
and under flooring bed using coarse aggregate 40mm size hard , machine crushed granite
from approved quarry including cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site, including sales & other taxes on all materials and
including all charges for machine mixing, laying concrete in foundations and under flooring
bed, ramming in 15 cm layers finishing top surface to the required level curing etc., and
overheads & contractors profit complete for finished item of work. (APSS No. 402)
Filling with useful available excavated earth (excluding rock) with a lead of 50 m in trenches,
sides of foundations and basement with initial lead in layers not exceeding 15cm thick,
watering and ramming including cost and conveyance of water to work site and all
4
operaitonal, incidental, labour charges, hire charges of T&P etc., and overheads &
contractors profit complete for fnished item of work (APSS NO.309&310).
Deduct
PCC(1:4:8) -122.85
Footings -530.24
Pedestals -30.93
3009.11 Cum
Say 3010.00 Cum
5 Providing anti termite treatment as per IS 6315 (Part-2) 2001 (pre-constructional chemical
treatment measures) along the internal & external vertical faces of the columns, plinth beams,
basement and top surface of the basement filling below flooring bed as per the specified
procedure confirming to IS 6315 (Part-2) 2001 and other relevent approved specification duly
using Chlorpyriphos / Lindane emulsifiable concentrate 20% with 1% concentration @ 7.5
Liters/sqm of the vertical surface & 5.0 Liters/sqm of the horizontal surface of the substructure
to a depth of 500mm around columns & 300mm deep around plinth beams, basements &
floor filling area including excavation channel along the wall & rodding etc & cost & conveyane
of all materials to the site, cost of labour for spraying, rodding etc complete for finished item of
work as per the approval of the Engineer-in-Charge. ( The rate includes overheads &
contractors profit )
a) Footings
F1 1 24 1.55 1.40 0.35 18.23
F2 1 31 1.70 1.50 0.40 31.62
F3 1 56 2.05 1.90 0.50 109.06
F4 1 14 2.30 2.15 0.60 41.54
F5 1 3 2.25 1.95 0.55 7.24
F6 1 6 1.70 1.70 0.40 6.94
F7 1 51 2.00 2.00 0.50 102.00
F8 1 21 2.25 2.25 0.60 63.79
F9 1 13 2.50 2.30 0.60 44.85
F10 1 3 3.00 2.85 0.70 17.96
F11 1 7 2.45 2.45 0.60 25.21
F12 1 3 2.75 2.75 0.60 13.61
482.04 Cum
Add 10% 48.20
530.24
Say 531.00 Cum
b) Column Pedestals
P1 1 203 0.45 0.45 0.60 24.66
P2 1 29 0.60 0.60 0.60 6.26
30.93 Cum
Say 31.00 Cum
c) Plinth beams
External Beams
1 1 431.38 0.23 0.45 44.65
Internal Beams
1 1 1413.47 0.23 0.45 146.29
190.94 Cum
Say 191.00 Cum
7 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with
minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER
with 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS
383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc.,
to site and sales & other taxes on all materials, centering using Casurina Ballies, Bamboos,
Wooden Reapers, Runners, Wood Posts, Wall Plates etc., including all operational, incidental
and labour charges such as weigh batching, machine mixing, lifting of concrete manually,
laying concrete, curing , overheads & contractors profit etc., complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No. 402)
a) Columns
i First floor(F1)
up to plinth beam level
b) Lintels
i First floor(F1)
DD - Double door 1 32 4.05 0.23 0.23 6.86
D1 - Door1 1 20 1.95 0.23 0.23 2.06
W - Windows 1 69 1.65 0.23 0.23 6.02
V - Ventilator 1 36 1.05 0.23 0.23 2.00
8 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with
minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER
with 20mm size graded machine crushed hard granite metal(coarse aggregate - as per IS 383
- 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and conveyance of
all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and sales
& other taxes on all materials , centering using Casurina Ballies , Bamboos , Wooden
Reapers , Runners , Wood Posts , Wall Plates etc., including all operational, incidental and
labour charges such as weigh batching, machine mixing, lifting of concrete manually, laying
concrete, curing , overheads & contractors profit etc., complete but excluding cost of steel and
its fabrication charges for finished item of work (APSS No. 402)
a) Roof beams
i First Floor Beams
B1(230x450) 1 1 1050.50 0.23 0.30 72.48
B2(300x600) 1 1 665.53 0.30 0.45 89.85
B3(450x750) 1 1 113.56 0.45 0.60 30.66
192.99 Cum
Say 193.00 Cum
Staircase-1
Staircase waist slab 1 2 3.45 1.50 10.35
Staircase landing 1 1 3.07 2.45 7.52
Staircase-2
Staircase waist slab 1 2 3.45 1.50 10.35
Staircase landing 1 1 3.07 2.45 7.52
Staircase-4
Staircase waist slab 1 2 3.45 1.50 10.35
Staircase landing 1 1 3.07 2.45 7.52
Staircase-6
Staircase waist slab 1 2 3.45 1.50 10.35
Staircase landing 1 1 3.07 2.45 7.52
4283.23 Sqm
Say 4284.00 Sqm
9 Reinforced Cement Concrete M 20 design mix using 12mm size hard granite machine
crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concrete
using WEIGH BATCHER / MIXER including cost and conveyance of all materials like
cement, fine aggregate (Sand), coarse aggregate, water etc., to site including steel centering,
shuttering, labour charges such as weigh batching, machine mixing, laying concrete, lift
charges, curing etc., and overheads & contractors profit complete for finished item of work
(APSS No. 402 & 403) for platforms and shelves.
10 Random Rubble stone masonry in CM (1:8) prop: (Cement: Screened sand) using hard
granite stones carted from approved quarry including cost and conveyance of all materials
like cement, screened sand, water, stones etc., from approved quarry, to site, sales & other
taxes on all materials including labour for cutting stones to required size and shape, mixing,
of cement, mortar, construction, curing etc.,and overheads & contractors profit complete for
finished item of work in foundation and basement. (APSS No. 601 & 615)
11 Brick masonry for panel walls in superstructure with CM (1:8) prop: (Cement : Screened sand)
using common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or
traditional size 23 x 11 x 7 cms from approved source having minimum crushing strength of
40 Kg/Sqcm. including cost and conveyance of all materials like cement, screened sand,
bricks, water etc., to site, including sales & other taxes on all materials and such as labour
charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift charges,
curing, etc.,and overheads & contractors profit complete for finished item of work. (APSS No.
501 & 504).
i First floor(F1)
External Wall 1 1 431.38 0.23 3.06 303.60
Internal walls
Coffee Shop wall 2 1 26.95 0.23 3.06 37.93
2 1 21.53 0.23 3.06 30.31
Room Walls 2 2 6.86 0.23 3.06 19.31
2 3 11.12 0.23 3.06 46.96
Duct long wall 2 1 18.80 0.23 3.06 26.46
Indoor games long wall 2 1 20.92 0.23 3.06 29.45
Indoor games short wall 2 3 11.30 0.23 3.06 47.72
Staircase wall 2 1 3.07 0.23 3.06 4.32
Kitchen long wall 2 1 15.50 0.23 3.06 21.82
Kitchen short wall 2 3 7.13 0.23 3.06 30.11
Cooridor walls 2 2 3.07 0.23 3.06 8.64
Ward long wall 2 2 28.60 0.23 3.06 80.51
Ward short wall 2 3 8.43 0.23 3.06 35.60
Cooridor wall 2 1 4.91 0.23 3.06 6.91
Duct wall 2 1 24.69 0.23 3.06 34.75
Assistant professor long wall 2 1 22.57 0.23 3.06 31.77
Deductions
DD - Double Door -1 32 1.20 0.23 2.10 -18.55
D1 - Door1 -1 20 0.90 0.23 2.10 -8.69
W1 - Windows -1 69 1.80 0.23 1.35 -38.56
V - Ventilator -1 36 0.60 0.23 0.60 -2.98
Lintels -16.94
Bed blocks and hold fasts -3.84
1461.11 Cum
Add 10% 146.11
1607.22
Say 1608.00 Cum
12 Reinforced Brick Masonry for partition walls (11.0 cm thick) in CM (1:4) prop. (Cement :
Screened sand) using common burnt clay bricks of class as per Table- I of IS:1077-1992,
Non- Modular or traditional size 23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sq.cm and placing 2 Nos. of 6mm M.S plain rods in every third
layer with free ends of the reinforcement pegged into mortar joints of main brick walls where
applicable including cost and conveyance of all materials like cement, steel, sand, bricks,
water etc., to site, including sales & other taxes on all materials, all operational, incidental
charges such as labour charges for mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors profit but excluding cost of
steel and its fabrication charges complete for finished item of work. (APSS No. of 501 & 509).
i First floor(F1)
Utility area wall 1 1 7.80 3.06 23.87
Storage long wall 1 1 7.80 3.06 23.87
Deductions
D1 - Door 1 -1 6 0.90 2.10 -11.34
D2 - Door 2 -1 36 0.75 2.10 -56.70
655.50 Sqm
Add 10% 65.55
721.05
Say 722.00 Sqm
13 Plain Cement Concrete M 20 design mix using WEIGH BATCHER / MIXER, 20mm size hard
granite machine crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386
Part 1 to Part 8) from approved quarry, using a minimum quantity of 330 kgs. of cement per 1
cum of concrete including cost and conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site including steel centering, shuttering, machine
mixing, lift charges, laying concrete,vibrating, curing, overheads & contrctors profit etc.,
complete for finished item of work (APSS No. 402 & 403) for steps.
i First Floor
Staircase 2
Staircase steps 24 0.50 1.50 0.30 0.15 0.81
Staircase 3
Staircase steps 24 0.50 1.50 0.30 0.15 0.81
Staircase 4
Staircase steps 24 0.50 1.50 0.30 0.15 0.81
Staircase 5
Staircase steps 24 0.50 1.50 0.30 0.15 0.81
Staircase 6
Staircase steps 24 0.50 1.50 0.30 0.15 0.81
4.86 Cum
Say 5.00 Cum
14 Plain Cement Concrete (1:3:6) nominal mix using 20mm size graded machine crushed hard
granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all materials like cement, fine
aggregate(sand), coarse aggregate, water etc. to site, including sales & other taxes on all
materials and including all charges for mixing, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for Bed Blocks & Hold Fasts for finished item of
work. (APSS No. 402)
i First floor(F1)
for bed blocks
DD - Double door 32 2 0.23 0.23 0.15 0.51
D1 - Door 20 2 0.23 0.23 0.15 0.32
W - Windows 69 2 0.23 0.23 0.15 1.10
15 Reinforced cement concrete (1:5:10) proportion (Cement: fine aggregates: coarse aggregate)
using 40mm size (SS5) hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand), coarse
aggregate, water etc., to site including centering using Casurina Ballies , Bamboos , Wooden
Reapers , Runners , Wood Posts , Wall Plates etc., shuttering, machine mixing, laying
concrete, lifting concrete manually , curing etc., and overheads & contractors profit complete
as per drawings but excluding cost of steel and it's fabrication charges for finished item of
work (APSS NO. 402 & 403) for Dummy columns.
i Third Floor(F3)
C1 1 124 0.30 0.45 0.90 1.72
C2 1 3 0.30 0.60 0.90 1.72
C3 1 79 0.45 0.45 0.90 1.72
16 Providing Thermo Mechanically Treated (TMT) (Fe 500 grade as per IS 1786-1979) of
different diameters for RCC works , including labour charges for straightening, cutting,
bending to required sizes and shapes, placing in position with cover blocks of approved
materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including
cost and conveyance of binding wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying including sales and other taxes on
all materials etc. ,and overheads & contractors profit complete for finished item of work.
( APSS No.126)
i First floor(F1)
Footings 530.24 cum 80.00 Kgs/cum 42418.95
Pedestals 30.93 cum 100.00 Kgs/cum 3092.85
Plinth beams 190.94 cum 150.00 Kgs/cum 28641.25
Columns 107.63 cum 200.00 Kgs/cum 21526.80
17 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS 432) of different diameters
including labour charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying and lap-splicing
with binding wire of 18 SWG, forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover
blocks and all incidental, operational, labour charges such as cutting, bending, placing in
position, tying including sales and other taxes on all materials etc. ,and overheads &
contractors profit complete for finished item of work.( APSS No.126)
i First floor(F1)
in Reinforced brick masonry 1 655.50 sqm 3.00 kgs/sqm 1966.51 Kgs
for 50mm thick platforms 1 78.68 sqm 4.00 kgs/sqm 314.71 Kgs
for 25mm thick shelves 1 78.68 sqm 2.00 kgs/sqm 157.36 Kgs
2438.58 Kgs
2.50 MT
Say 3.00 MT
ii Second floor(F2)
in Reinforced brick masonry 1 503.71 sqm 3.00 kgs/sqm 1511.12 Kgs
1511.12 Kgs
1.60 MT
Say 2.00 MT
18 Ornamental ceiling plastering 12mm thick in two coats using screened sand with base coat of
8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) with dubara sponge finishing
including cost and conveyance of all materials like cement, sand, water etc., to site, including
sales & other taxes on all materials, and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing, scaffolding, lift charges, curing,
including cutting grooves as directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS 901,903 & 904)
i First floor(F1)
Room 1 1 6.00 4.40 26.40
Preperation area 1 1 5.60 5.00 28.00
Wet storage 1 1 6.10 3.80 23.18
Dry storage 1 1 6.10 3.80 23.18
Storage 1 1 7.70 3.80 29.26
Kitchen 1 1 9.80 7.90 77.42
Utility area 1 1 7.90 4.90 38.71
Hall 1 1 18.72 12.92 241.86
Cofee shop 1 1 27.00 11.20 302.40
Toilet 1 1 3.07 1.50 4.61
Room-1 1 1 4.50 3.70 16.65
Room-2 1 1 4.50 3.70 16.65
Room-3 1 1 4.50 3.70 16.65
Room-4 1 1 4.50 3.70 16.65
Toilet-1 1 1 3.30 1.50 4.95
Toilet-2 1 1 3.30 1.50 4.95
Toilet-3 1 1 3.30 1.50 4.95
Toilet-4 1 1 3.30 1.50 4.95
Corridor 1 1 11.32 1.95 22.07
i First floor(F1)
External Wall 1 1 431.38 3.51 1514.13
Internal walls
Coffee Shop wall 1 1 26.95 3.51 94.59
1 1 21.53 3.51 75.57
Room Walls 1 2 6.86 3.51 48.16
1 3 11.12 3.51 117.09
Duct long wall 1 1 18.80 3.51 65.99
Indoor games long wall 1 1 20.92 3.51 73.43
Indoor games short wall 1 3 11.30 3.51 118.99
Staircase wall 1 1 3.07 3.51 10.78
Kitchen long wall 1 1 15.50 3.51 54.41
Kitchen short wall 1 3 7.13 3.51 75.08
Cooridor walls 1 2 3.07 3.51 21.55
Ward long wall 1 2 28.60 3.51 200.77
Ward short wall 1 3 8.43 3.51 88.77
Cooridor wall 1 1 4.91 3.51 17.23
Duct wall 1 1 24.69 3.51 86.66
Assistant professor long wall 1 1 22.57 3.51 79.22
Assistant professor short wall 1 4 7.13 3.51 100.11
Waiting Space long wall 1 2 18.05 3.51 126.71
Waiting Space short wall 1 3 7.13 3.51 75.08
Toilet long wall 1 1 6.06 3.51 21.27
Toilet short wall 1 1 5.98 3.51 20.99
Professor chamber long wall 1 1 11.30 3.51 39.66
Professor chamber short wall 1 2 4.45 3.51 31.24
Assistant professor long wall 1 1 22.57 3.51 79.22
Assistant professor short wall 1 4 7.13 3.51 100.11
Waiting Space long wall 1 2 18.05 3.51 126.71
Waiting Space short wall 1 3 7.13 3.51 75.08
Toilet long wall 1 1 6.06 3.51 21.27
Toilet short wall 1 1 5.98 3.51 20.99
Professor chamber long wall 1 1 11.30 3.51 39.66
Professor chamber short wall 1 2 4.45 3.51 31.24
Auditorium long wall 1 1 22.34 3.51 78.41
Auditorium short wall 1 2 7.15 3.51 50.19
Kitchen long wall 1 1 15.49 3.51 54.37
Kitchen short wall 1 2 7.15 3.51 50.19
Corridor wall 1 1 3.07 3.51 10.78
Ward long wall 1 2 28.60 3.51 200.77
Ward short wall 1 3 8.43 3.51 88.77
Treatment room 1 1 3.68 3.51 12.92
Corridor wall 1 1 4.91 3.51 17.23
Ward long wall 1 1 21.20 3.51 74.41
Ward short wall 1 2 11.30 3.51 79.33
Wash room wall 1 1 3.07 3.51 10.78
Toilet long wall 1 3 11.12 3.51 117.09
Toilet short wall 1 2 9.01 3.51 63.25
Duct wall 1 1 18.12 3.51 63.60
Deductions
DD - Duble Door -1 32 1.50 2.10 -100.80
D1 - Door 1 -1 26 0.90 2.10 -49.14
D2 - Door 2 -1 36 0.75 2.10 -56.70
W - Windows -1 69 1.50 1.35 -139.73
V - Ventilator -1 36 0.60 0.60 -12.96
5106.12 Sqm
Add 10% 510.61
5616.73
Say 5617.00 Sqm
ii Second floor(F2)
Parapet wall 1 1 414.65 0.90 373.19
1 1 145.02 0.90 130.52
503.71 Sqm
Add 10% 50.37
554.08
Say 555.00 Sqm
i First floor(F1)
External Wall 1 1 431.38 3.66 1578.84
Internal walls
Coffee Shop wall 1 1 26.95 3.66 98.64
1 1 21.53 3.66 78.80
Room Walls 1 2 6.86 3.66 50.22
1 3 11.12 3.66 122.10
Duct long wall 1 1 18.80 3.66 68.81
Indoor games long wall 1 1 20.92 3.66 76.57
Indoor games short wall 1 3 11.30 3.66 124.07
Staircase wall 1 1 3.07 3.66 11.24
Kitchen long wall 1 1 15.50 3.66 56.73
Kitchen short wall 1 3 7.13 3.66 78.29
Cooridor walls 1 2 3.07 3.66 22.47
Ward long wall 1 2 28.60 3.66 209.35
Ward short wall 1 3 8.43 3.66 92.56
Cooridor wall 1 1 4.91 3.66 17.97
Duct wall 1 1 24.69 3.66 90.37
Assistant professor long wall 1 1 22.57 3.66 82.61
Assistant professor short wall 1 4 7.13 3.66 104.38
Waiting Space long wall 1 2 18.05 3.66 132.13
Waiting Space short wall 1 3 7.13 3.66 78.29
Toilet long wall 1 1 6.06 3.66 22.18
Toilet short wall 1 1 5.98 3.66 21.89
Professor chamber long wall 1 1 11.30 3.66 41.36
Professor chamber short wall 1 2 4.45 3.66 32.57
Assistant professor long wall 1 1 22.57 3.66 82.61
Assistant professor short wall 1 4 7.13 3.66 104.38
Waiting Space long wall 1 2 18.05 3.66 132.13
Waiting Space short wall 1 3 7.13 3.66 78.29
Toilet long wall 1 1 6.06 3.66 22.18
Toilet short wall 1 1 5.98 3.66 21.89
Professor chamber long wall 1 1 11.30 3.66 41.36
Professor chamber short wall 1 2 4.45 3.66 32.57
Auditorium long wall 1 1 22.34 3.66 81.76
Auditorium short wall 1 2 7.15 3.66 52.34
Kitchen long wall 1 1 15.49 3.66 56.69
Kitchen short wall 1 2 7.15 3.66 52.34
Corridor wall 1 1 3.07 3.66 11.24
Ward long wall 1 2 28.60 3.66 209.35
Ward short wall 1 3 8.43 3.66 92.56
Treatment room 1 1 3.68 3.66 13.47
Corridor wall 1 1 4.91 3.66 17.97
Ward long wall 1 1 21.20 3.66 77.59
Ward short wall 1 2 11.30 3.66 82.72
Wash room wall 1 1 3.07 3.66 11.24
Toilet long wall 1 3 11.12 3.66 122.10
Toilet short wall 1 2 9.01 3.66 65.95
Duct wall 1 1 18.12 3.66 66.32
Deductions
DD - Duble Door -1 32 1.50 2.10 -100.80
D1 - Door 1 -1 26 0.90 2.10 -49.14
D2 - Door 2 -1 36 0.75 2.10 -56.70
W - Windows -1 69 1.50 1.35 -139.73
V - Ventilator -1 36 0.60 0.60 -12.96
5339.32 Sqm
Add 10% 533.93
5873.25
Say 5874.00 Sqm
ii Second floor(F2)
Parapet wall 1 1 414.65 0.90 373.19
1 1 145.02 0.90 130.52
503.71 Sqm
Add 10% 50.37
554.08
Say 555.00 Sqm
22 Flooring with non-skid full body ceramic floor tiles of size 300mm x 300mm and thickness
between 7 - 8mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of
any colour and finish in all shades and designs as approved by Engineer-in-charge, set over
base coat of cement mortar (1:8), 12mm thick using screened sand over CC bed already laid
or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3 Kgs
per Sqm & jointed neatly with white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement, screened sand , water and tiles
etc., and overheads & contractors profit complete for finished item of work. (APSS No.701 &
707)
i First floor(F1)
Utility area 1 1 7.90 4.90 38.71
Toilet 1 1 3.07 1.50 4.61
Toilet-1 1 1 3.30 1.50 4.95
Toilet-2 1 1 3.30 1.50 4.95
Toilet-3 1 1 3.30 1.50 4.95
Toilet-4 1 1 3.30 1.50 4.95
Toilet 1 1 11.30 4.20 47.46
Wash room 1 1 6.40 3.10 19.84
Wash & Driying area 1 1 7.10 2.90 20.59
F.staff Toilet 1 1 6.00 3.10 18.60
M.staff Toilet 1 1 6.00 2.80 16.80
F.staff Toilet 1 1 6.00 3.10 18.60
M.staff Toilet 1 1 6.00 2.80 16.80
Wash & Driying area 1 1 7.10 2.90 20.59
Washroom 1 1 6.40 3.10 19.84
Toilet 1 1 11.30 4.20 47.46
Toilet-1 1 1 3.30 1.50 4.95
Toilet-2 1 1 3.30 1.50 4.95
Toilet-3 1 1 3.30 1.50 4.95
Toilet-4 1 1 3.30 1.50 4.95
329.50 Sqm
Say 330.00 Sqm
i First floor(F1)
Room 1 1 6.00 4.40 26.40
Preperation area 1 1 5.60 5.00 28.00
Wet storage 1 1 6.10 3.80 23.18
Dry storage 1 1 6.10 3.80 23.18
Storage 1 1 7.70 3.80 29.26
Kitchen 1 1 9.80 7.90 77.42
Hall 1 1 18.72 12.92 241.86
Cofee shop 1 1 27.00 11.20 302.40
Room-1 1 1 4.50 3.70 16.65
Room-2 1 1 4.50 3.70 16.65
Room-3 1 1 4.50 3.70 16.65
Room-4 1 1 4.50 3.70 16.65
Corridor 1 1 11.32 1.95 22.07
Indoor game 1 1 11.30 7.90 89.27
Day care hall 1 1 11.30 8.10 91.53
Kitchen 1 1 7.70 7.10 54.67
Waiting area 1 1 7.10 4.50 31.95
Corridor 1 1 406.94 406.94
Lobby 1 1 4.45 3.00 13.35
Lobby 1 1 10.66 6.32 67.37
Assitant professor hall 1 1 8.50 7.10 60.35
Assitant professor hall 1 1 10.60 7.10 75.26
Cooridor 1 1 33.00 3.00 99.00
Cooridor 1 1 30.00 3.00 90.00
Professor chamber 1 1 4.50 3.70 16.65
Professor chamber 1 1 4.50 3.70 16.65
Professor chamber 1 1 4.50 3.70 16.65
Waiting Space 1 1 11.30 2.50 28.25
Entrence lobby 1 1 18.02 7.59 136.77
Entrence lobby 1 1 10.43 7.59 79.16
Reception 1 1 11.88 7.59 90.17
Reception-1 1 1 7.37 4.29 31.62
Professor chamber 1 1 4.50 3.70 16.65
Professor chamber 1 1 4.50 3.70 16.65
Professor chamber 1 1 4.50 3.70 16.65
Waiting Space 1 1 11.30 2.50 28.25
Auditorium 1 1 18.82 7.13 134.19
Nurses room 1 1 3.70 3.10 11.47
Treatment room 1 1 5.30 3.70 19.61
Ward 1 1 24.20 8.40 203.28
Cooridor 1 1 33.50 3.68 123.28
Cooridor 1 1 17.25 3.07 52.96
Entrence hall 1 1 7.10 4.50 31.95
24 Flooring with 16 to 18 mm thick high polished granite stone slabs black colour as approved
by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of cement
mortar (1:8) , 20mm thick using screened sand over CC bed already laid or RCC roof slab
including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of matching shade to full depth
including cost and conveyance of all materials like cement , sand , water , granite slabs etc.,
to work site and all operational, incidental labour & lift charges, half rounding the edge ,
polishing charges and all other taxes on all materials, cost of base coat and overheads &
contractors profit complete for finished item of work for platforms (S.S.701 & special)
i First floor(F1)
Kitchen 1 1 9.21 0.60 5.53
1 1 9.21 0.60 5.53
1 1 8.58 0.60 5.15
Storage 1 1 7.67 0.60 4.60
1 1 6.50 0.60 3.90
Preperation area 1 1 3.80 0.60 2.28
Wet Storage 1 1 6.13 0.60 3.68
1 1 1.96 0.60 1.18
Dry Storage 1 1 6.13 0.60 3.68
1 1 1.96 0.60 1.18
Pantry 1 1 10.47 0.60 6.28
Toilet 1 1 3.65 0.60 2.19
Washroom 1 1 2.37 0.60 1.42
Kitchen 1 1 6.13 0.60 3.68
1 1 6.13 0.60 3.68
1 1 5.90 0.60 3.54
Female staff Tiolet 1 1 1.25 0.60 0.75
Reception 1 1 4.45 0.60 2.67
1 1 4.20 0.60 2.52
Female staff Tiolet 1 1 1.25 0.60 0.75
Kitchen 1 1 6.13 0.60 3.68
1 1 6.13 0.60 3.68
1 1 5.90 0.60 3.54
Washroom 1 1 2.37 0.60 1.42
Toilet 1 1 3.65 0.60 2.19
78.68 Sqm
Say 79.00 Sqm
Entrance Steps 1
1 1 9.00 0.30 2.70
1 1 9.00 0.30 2.70
1 1 9.00 0.30 2.70
Entrance Steps 2
1 1 9.00 0.30 2.70
1 1 9.00 0.30 2.70
1 1 9.00 0.30 2.70
75.60 Sqm
Say 76.00 Sqm
Entrance Steps 1
1 1 9.00 0.15 1.35
1 1 9.00 0.15 1.35
1 1 9.00 0.15 1.35
1 1 9.00 0.15 1.35
Entrance Steps 1
1 1 9.00 0.15 1.35
1 1 9.00 0.15 1.35
1 1 9.00 0.15 1.35
1 1 9.00 0.15 1.35
43.20 Sqm
Say 44.00 Sqm
i First floor(F1)
Utility area 1 2 7.90 2.10 33.18
1 2 4.90 2.10 20.58
Toilet 1 2 3.07 2.10 12.89
1 2 1.50 2.10 6.30
Toilet-1 1 2 3.30 2.10 13.86
1 2 1.50 2.10 6.30
Toilet-2 1 2 3.30 2.10 13.86
1 2 1.50 2.10 6.30
Toilet-3 1 2 3.30 2.10 13.86
1 2 1.50 2.10 6.30
Toilet-4 1 2 3.30 2.10 13.86
1 2 1.50 2.10 6.30
Toilet 1 2 11.30 2.10 47.46
1 2 4.20 2.10 17.64
Partition walls 1 1 9.39 2.10 19.72
7 2 1.85 2.10 54.39
Wash room 1 2 6.40 2.10 26.88
1 2 3.10 2.10 13.02
Partition walls 1 1 4.03 2.10 8.46
3 2 1.53 2.10 19.28
Wash & Driying area 1 2 7.10 2.10 29.82
1 2 2.90 2.10 12.18
F.staff Toilet 1 2 6.00 2.10 25.20
1 2 3.10 2.10 13.02
Partition walls 1 1 2.68 2.10 5.63
2 2 1.72 2.10 14.45
M.staff Toilet 1 2 6.00 2.10 25.20
1 2 2.80 2.10 11.76
Partition walls 1 1 2.68 2.10 5.63
2 2 1.72 2.10 14.45
F.staff Toilet 1 2 6.00 2.10 25.20
1 2 3.10 2.10 13.02
Partition walls 1 1 2.68 2.10 5.63
2 2 1.72 2.10 14.45
M.staff Toilet 1 2 6.00 2.10 25.20
1 2 2.80 2.10 11.76
Partition walls 1 1 2.68 2.10 5.63
2 2 1.72 2.10 14.45
Wash & Driying area 1 2 7.10 2.10 29.82
1 2 2.90 2.10 12.18
Washroom 1 2 6.40 2.10 26.88
1 2 3.10 2.10 13.02
Toilet 1 2 11.30 2.10 47.46
1 2 4.20 2.10 17.64
Partition walls 1 1 9.39 2.10 19.72
7 2 1.85 2.10 54.39
Toilet-1 1 2 3.30 2.10 13.86
Deductions
D2 - Door 2 -1 36 0.75 2.10 -56.70
878.16 Sqm
Say 879.00 Sqm
27 Providing skirting to internal walls to 10 cm height with soluble salt porcelain vitrified tiles
screen printed and polished of thickness between 8 to 10mm 1st quality conforming to IS:
13711, IS: 13712, IS: 13630(Parts 1 to 15) of any colour and finish in all shades and designs,
length equal to flooring tiles, set over base coat of CM(1:5) 12 mm thick using screened sand
with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and
jointing with white cement paste mixed with pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and water etc.,and overheads & contractors profit
complete for finished item of work.(APSS No.701 &707)
i First floor(F1)
Room 1 1 20.80 20.80
Preperation area 1 1 21.20 21.20
Wet storage 1 1 19.80 19.80
Dry storage 1 1 19.80 19.80
Storage 1 1 23.00 23.00
Kitchen 1 1 35.40 35.40
Hall 1 1 63.28 63.28
Cofee shop 1 1 76.40 76.40
Room-1 1 1 16.40 16.40
Room-2 1 1 16.40 16.40
Room-3 1 1 16.40 16.40
Room-4 1 1 16.40 16.40
Corridor 1 1 26.54 26.54
Indoor game 1 1 38.40 38.40
Day care hall 1 1 38.80 38.80
Kitchen 1 1 29.60 29.60
Waiting area 1 1 23.20 23.20
Corridor 1 1 167.21 167.21
Lobby 1 1 14.90 14.90
Lobby 1 1 33.96 33.96
Assitant professor hall 1 1 31.20 31.20
Assitant professor hall 1 1 35.40 35.40
Cooridor 1 1 72.00 72.00
Cooridor 1 1 66.00 66.00
Professor chamber 1 1 16.40 16.40
Professor chamber 1 1 16.40 16.40
Professor chamber 1 1 16.40 16.40
Waiting Space 1 1 27.60 27.60
Entrence lobby 1 1 51.22 51.22
Entrence lobby 1 1 36.04 36.04
Reception 1 1 38.94 38.94
Reception-1 1 1 23.32 23.32
Professor chamber 1 1 16.40 16.40
Professor chamber 1 1 16.40 16.40
Professor chamber 1 1 16.40 16.40
Waiting Space 1 1 27.60 27.60
Deductions
DD - Double Door -1 32 1.50 -48.00
D1 - Door 1 -1 26 0.90 -23.40
D2 - Door 2 -1 36 0.75 -27.00
1634.29 Rmt
Say 1635.00 Rmt
28 Providing 110 mm Dia ISI marked PVC down water take pipes with socket , 2.5mm thick 4.0
kg/sq.cm pressure of ISI marked including cost of necessary PVC Bends, shoes, iron / PVC
clamps and all other accessories and fixing in position including cost and conveyance of all
materials, sales & other taxes on materials to site, operational & incidental charges including
all labour charges for fixing at site etc., and overheads & contractors profit complete for
finished item of work. (APSS No. 1328)
1 4 3.66 14.64
14.64 Rmt
Say 15.00 Rmt
29 Supplying and fixing of stainless steel ( grade 304 ) hand railing as per approved drawing with
top rail of 50mm dia pipe and 2mm thick medium class and vertical posts of 25mm dia and
1.6mm thick medium class 2 Nos for each step fixed with base plate of 75mm dia using
bonding agent and anchor fastner and welding, drilling of 25mm dia holes with pneumatic
compressor for fixing railing, buffing, polishing all members of the railing thouroughly ,
lacquer finishing to present seamless finish including cost and conveyance of all materials,
electrodes, welding charges, cost of all consumables, labour charges , overheads &
contractors profit etc., complete for finished item of work.
DD(ds)
First floor(F1) 1 32 1.50 2.10 100.80
100.80 Sqm
Say 101.00 Sqm
31 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x
65 mm and ISI marked flush door shutters of 30 mm thick single shutter with bond wood solid
block board type Core having cross bands and face veneers, hot pressed bonded with water
proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I)
both sides commercial ply with internal lipping on all sides including cost and conveyance to
site of teak wood frame, flush shutter including supply and fixing 6 Nos. MS Z hold fasts of
size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of
200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1
No. rubber bush including fixing the fixtures to door with required number of screws, bolt and
nuts including labour charges for fixing the frame in position, fixing the shutter to the frame
etc, including overheads & contractors profit complete for finished item of work as per APSS
1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less
than 10 mm) (900mm x 2100mm).
D1(ss)
First floor(F1) 1 26 0.90 2.10 49.14
49.14 Sqm
Say 50.00 Sqm
32 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x
65mm and ISI marked flush door shutter of 30mm thick single shutter with bond wood solid
block board type Core having cross bands and face veneers, hot pressed bonded with water
proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I)
both sides commercial ply with internal lipping on all sides including cost and conveyance to
site of medium teak wood door frame, flush shutter, including suply and fixing 6 Nos. MS Z
hold fasts of size 300mm x 40mm x 5mm including ISI marked Aluminium fixtures 3 Nos. butt
hinges (IS:205) of 150mm long, 1 No. aldrop (IS:2681) 250 mm long, 1 No. tower bolt (IS:204)
of 150 mm x 10mm dia, 2 Nos. 125mm long handles (IS:208),1 No. rubber bush including
supplying and fixing 1.20mm thick PVC sheet to full height of the shutter inside including
labour charges for fixing the frame in position, fixing the shutter to the frame etc., including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002.
(The vertical frame of door shall be embedded in flooring for deth of not less than 10mm)
( 750mm x 2100mm )
D2(ss)
First floor(F1) 1 36 0.75 2.10 56.70
56.70 Sqm
33 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) 2 Track–2 Panel Sliding
windows duly manufactured using UPVC reinforced profiles (Composition of profile shall
consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3 for every 100
parts of PVC resin) of (62mm x 60 mm)/(60 mm x 45 mm) x 2.20 mm for outer frames, (66
mm x 38 mm)/(58 mm x 39 mm) x 2.20 mm for sliding shutter frames capable of mounting
single glazing system, structurally reinforced with hot dip galvanized up to 50 microns of
minimum thickness of 1.0/1.2 mm prefabricated & welded through fusion welding. The window
sash shall be fitted with 5 mm thick clear float glass of reputed make duly fixed with Grey
colour TPV Gasket for sash & Glazing bead shall be co-extruded with Grey colour soft PVC.
System shall have single point locking with Touch Lock and the system is to be installed at the
site using anchor fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc.,
including cost and conveyance of all materials, accessories, labour charges for transportation,
erection at site including overheads and contractors profit etc., complete for finished item of
work.
First floor(F1)
W - 1500 mm x 1350 mm 1 69 1.50 1.35 139.73
139.73 Sqm
Say 140.00 Sqm
34 Providing, supplying & fixing of Fixed Louvered Ventilator made out of multi chambered uPVC
sections with Glazing bead shall be co-extruded with Grey colour soft PVC. having isolated
drainage and reinforced with Galvanized Iron profiles throughout the window. The outer frame
having an overall size of 60 mm x 55 mm x 2.40 with reinforcement of 1 mm thickness and
Mullion with overall size of 74 mm x 60 mm x 2.40 mm with reinforcement of 1 mm thickness.
(Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and not more than 12
PHR of CaCo3 for every 100 parts of PVC resin). Ventilator shall be provided with 4.5 mm Pin
Head glass, standard hardware. Wall thickness of frame & Mullion shall be 2.4 mm., including
cost and conveyance of all materials, accessories, labour charges for transportation, erection
at site including overheads and contractor profit etc., complete for finished item of work
35 Supplying and fixing of MS Grill to windows / in open court yards using 25mm x 6mm MS flat
alround and 10mm MS square bars horizontally at 125mm centre to centre and vertically at
300mm centre to centre including fixing with 4 Nos of MS Z holdfasts (2 on each side) duly
making cutting brick masonry, fixing and making to original surface neatly and painting grill
with one coat of red oxide primer including cost all taxes and conveyance of all materials
including cutting, bending, welding including all operational charges and all labour charges
etc., complete for finished item of work.
36 White washing two coats with white cement to ceiling to give an even shade after thouroughly
brushing the surface to remove all dirt and remains of loose powdered materials including
cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., and
overheads & contractors profit complete for finished item of work in all floors.
37 Providing and applying Wall putty of White Cement or Polymer or Cement based of average 1
to 2 mm thickness over plastered surface to prepare the surface even and smooth after
thoroughly brushing the surface to remove all dirt and remains of loose powdered materials,
applying emery paper, Sand the surface, clean & wipe off loose dust, applying knifing paste
filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper
for the surface preparation including cost and conveyance of all materials to work site and all
operational, incidental, labour charges, over heads and contractors profit etc., complete for
finished item of work in all floors for Internal walls.
First floor(F1)
External Wall 1 1 431.38 3.51 1514.13
Internal walls
Coffee Shop wall 2 1 26.95 3.51 189.19
2 1 21.53 3.51 151.14
Room Walls 2 2 6.86 3.51 96.31
2 3 11.12 3.51 234.19
Duct long wall 2 1 18.80 3.51 131.98
Indoor games long wall 2 1 20.92 3.51 146.86
Indoor games short wall 2 3 11.30 3.51 237.98
Staircase wall 2 1 3.07 3.51 21.55
Kitchen long wall 2 1 15.50 3.51 108.81
Kitchen short wall 2 3 7.13 3.51 150.16
Cooridor walls 2 2 3.07 3.51 43.10
Ward long wall 2 2 28.60 3.51 401.54
Ward short wall 2 3 8.43 3.51 177.54
Cooridor wall 2 1 4.91 3.51 34.47
Duct wall 2 1 24.69 3.51 173.32
Assistant professor long wall 2 1 22.57 3.51 158.44
Assistant professor short wall 2 4 7.13 3.51 200.21
Waiting Space long wall 2 2 18.05 3.51 253.42
Waiting Space short wall 2 3 7.13 3.51 150.16
Toilet long wall 2 1 6.06 3.51 42.54
Toilet short wall 2 1 5.98 3.51 41.98
Professor chamber long wall 2 1 11.30 3.51 79.33
Professor chamber short wall 2 2 4.45 3.51 62.48
Assistant professor long wall 2 1 22.57 3.51 158.44
Assistant professor short wall 2 4 7.13 3.51 200.21
Waiting Space long wall 2 2 18.05 3.51 253.42
Waiting Space short wall 2 3 7.13 3.51 150.16
Toilet long wall 2 1 6.06 3.51 42.54
Toilet short wall 2 1 5.98 3.51 41.98
Professor chamber long wall 2 1 11.30 3.51 79.33
Professor chamber short wall 2 2 4.45 3.51 62.48
Auditorium long wall 2 1 22.34 3.51 156.83
Auditorium short wall 2 2 7.15 3.51 100.39
Kitchen long wall 2 1 15.49 3.51 108.74
Kitchen short wall 2 2 7.15 3.51 100.39
Corridor wall 2 1 3.07 3.51 21.55
Ward long wall 2 2 28.60 3.51 401.54
Ward short wall 2 3 8.43 3.51 177.54
Treatment room 2 1 3.68 3.51 25.83
Corridor wall 2 1 4.91 3.51 34.47
Ward long wall 2 1 21.20 3.51 148.82
Deductions
DD - Duble Door -1 32 1.50 2.10 -100.80
D1 - Door 1 -1 26 0.90 2.10 -49.14
D2 - Door 2 -1 36 0.75 2.10 -56.70
W - Window -1 69 1.50 1.35 -139.73
V - Ventilator -1 36 0.60 0.60 -12.96
9057.44
Add 10% 905.74
9963.18 Sqm
Say 9964.00 Sqm
Second floor(F2)
Parapet wall 1 1 414.65 0.90 373.19
1 1 145.02 0.90 130.52
503.71
Add 10% 50.37
i First floor(F1)
External Wall 1 1 431.38 3.51 1514.13
Internal walls
Coffee Shop wall 2 1 26.95 3.51 189.19
2 1 21.53 3.51 151.14
Room Walls 2 2 6.86 3.51 96.31
2 3 11.12 3.51 234.19
Duct long wall 2 1 18.80 3.51 131.98
Indoor games long wall 2 1 20.92 3.51 146.86
Indoor games short wall 2 3 11.30 3.51 237.98
Staircase wall 2 1 3.07 3.51 21.55
Kitchen long wall 2 1 15.50 3.51 108.81
Kitchen short wall 2 3 7.13 3.51 150.16
Cooridor walls 2 2 3.07 3.51 43.10
Ward long wall 2 2 28.60 3.51 401.54
Ward short wall 2 3 8.43 3.51 177.54
Cooridor wall 2 1 4.91 3.51 34.47
Duct wall 2 1 24.69 3.51 173.32
Assistant professor long wall 2 1 22.57 3.51 158.44
Assistant professor short wall 2 4 7.13 3.51 200.21
Waiting Space long wall 2 2 18.05 3.51 253.42
Waiting Space short wall 2 3 7.13 3.51 150.16
Toilet long wall 2 1 6.06 3.51 42.54
Toilet short wall 2 1 5.98 3.51 41.98
Professor chamber long wall 2 1 11.30 3.51 79.33
Professor chamber short wall 2 2 4.45 3.51 62.48
Assistant professor long wall 2 1 22.57 3.51 158.44
Assistant professor short wall 2 4 7.13 3.51 200.21
Waiting Space long wall 2 2 18.05 3.51 253.42
Waiting Space short wall 2 3 7.13 3.51 150.16
Toilet long wall 2 1 6.06 3.51 42.54
Toilet short wall 2 1 5.98 3.51 41.98
Professor chamber long wall 2 1 11.30 3.51 79.33
Professor chamber short wall 2 2 4.45 3.51 62.48
Auditorium long wall 2 1 22.34 3.51 156.83
Auditorium short wall 2 2 7.15 3.51 100.39
Kitchen long wall 2 1 15.49 3.51 108.74
Kitchen short wall 2 2 7.15 3.51 100.39
Corridor wall 2 1 3.07 3.51 21.55
Ward long wall 2 2 28.60 3.51 401.54
Ward short wall 2 3 8.43 3.51 177.54
Treatment room 2 1 3.68 3.51 25.83
Corridor wall 2 1 4.91 3.51 34.47
Ward long wall 2 1 21.20 3.51 148.82
Ward short wall 2 2 11.30 3.51 158.65
Wash room wall 2 1 3.07 3.51 21.55
Toilet long wall 2 3 11.12 3.51 234.19
Toilet short wall 2 2 9.01 3.51 126.50
Duct wall 2 1 18.12 3.51 127.20
Deductions
DD - Duble Door -1 32 1.50 2.10 -100.80
D1 - Door 1 -1 26 0.90 2.10 -49.14
D2 - Door 2 -1 36 0.75 2.10 -56.70
W - Window -1 69 1.50 1.35 -139.73
V - Ventilator -1 36 0.60 0.60 -12.96
9057.44 Sqm
Add 10% 905.74
9963.18
Say 9964.00 Sqm
ii Second floor(F2)
Parapet wall 1 1 414.65 0.90 373.19
1 1 145.02 0.90 130.52
503.71 Sqm
Add 10% 50.37
554.08
Say 555.00 Sqm
i First floor(F1)
External wall 1 1 431.38 3.66 1578.84
Deductions
W - Window -1 69 1.50 1.35 -139.73
V - Ventilator -1 36 0.60 0.60 -12.96
1426.15 Sqm
Add 10% 142.62
1568.77
Say 1569.00 Sqm
ii Second floor(F2)
Parapet wall 1 1 414.65 0.90 373.19
1 1 145.02 0.90 130.52
503.71 Sqm
Add 10% 50.37
554.08
Say 555.00 Sqm
40 Painting to new wood work and flush shutters with lappam finish, over a primary coat and
painting two coats of synthetic enamel paint Grade-I VOC (Volatile Organic Compound)
content less than 50 grams/litre of approved shade including cost and conveyance of all
materials to site cost of primer coat and all labour charges etc. complete including applying
sand paper on lappam coats for neat finish including sales & other taxes on cost of all
materials etc., and overheads & contractors profit complete in all floors (APSS No.1200,
1207 & 1211).
First floor(F1)
Double Door DD(ds) 2.25 32 1.50 2.10 226.80
Door1 D1(ss) 2.25 26 0.90 2.10 110.57
Door2 D2(ss) 2.25 36 0.75 2.10 127.58
464.94 Sqm
Say 465.00 Sqm
41 Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic Compound)
content less than 50 grams/litre over primer coat of red oxide to new iron work including cost
and conveyance of all materials to site, sales & other taxes, incidental, operational and all
labour charges etc., and overheads & contractors profit complete for finished item of work in
all floors. (SS No. 1201, 1212 & 1207).
42 Roofing with corrugated G.I sheets 0.80mm thick fixed with G.I ‘J’ bolts & nuts 8 mm dia with
bitumen & G.I limpet washers filled with white lead & including a coat of approved steel primer
and two coats of approved paint on over lapping of sheets complete (up to a pitch of 600)
etc., complete, excluding the cost of purlins, rafters, trusses including cost and conveyance of
all materials , labour charges , overheads and contractors profit etc., complete for finished
item of work in all floors.
44 Providing and fixing of Expansion joint filler board for buildings, columns, beams and slabs 25
mm thick including cost and conveyance of all materials to site, all incidental, operational,
labour charges etc.overheads & contractors profit complete for finished item of work as per
approved drawing for all floors
45 Providing specialized polysulphide sealant treatment to the expansion joints (Size : 25mm x
12mm) including cost and conveyance of all materials to site, all incidental, operational,
labour charges etc.overheads & contractors profit complete for finished item of work as per
approved drawing for all floors duly a]. Chipping and removing of existing covering on
expansion joints b]. Cleaning of the surface from dirt, dust and other contaminations
c].Application of one coat of - High performance specially designed SBR latex polymer based
bonding agent d]. Providing and application of Acrylic Polymer modified instatement
concrete /mortar to the damaged edges of joint and making the groove. e]. Providing and
fixing of masking tape on top of the joint both sides f]. Providing and fixing of Back up support
material of Backer rod to leave the depth of 12mm on the joint g]. Providing and application of
one coat of polysulphide primer on inner edges of Joint. h]. Providing and application of Two
part Polysulphide sealant to a width of 25mm and 12mm depth with putty knife and neat finish
i]. Removing of masking tape and providing and application of two coats of Acrylic elastomeric
cementitious coating.
46 Providing and fixing of 24 gauge alluminium sheet over expansion joint groove of width 15cm
fixed to walls / columns at one edge and resting over the other block walls/columns
concealing expansion joint with slotted holes for free edge of aluminium sheet to facilitate free
movement of aluminium sheet over the finished surface of expansion joint and wall face using
sheet metal screws with nylon receiver complete including cost and conveyance of all
materials to site, all incidental, operational, labour charges , overheads & contractors profit
etc., complete for finished item of work as per approved drawing (for all floors for vertical
joints and bottom of slab)