Beruflich Dokumente
Kultur Dokumente
PROJECT MANAGEMENT
Instructions to candidates:
a) Time allowed: Three hours (plus an extra ten minutes’ reading time at the start – do not write anything during this
time)
b) Answer FIVE questions with TWO from Section A and THREE from Section B
c) All questions carry equal marks. Marks for each question are shown in [ ]
d) Non-programmable calculators are permitted in this examination
SECTION A
2. a) Identify and describe the main criteria for project selection models. [12]
b) List FOUR numeric and also FOUR non-numeric types of project selection models. [8]
3. a) Identify the advantages of top-down budgeting AND also the advantages of bottom-up budgeting. [12]
b) Distinguish between direct and indirect costs, giving at least THREE examples of EACH. [8]
4. “Operations and projects differ primarily in that operations are ongoing and repetitive while projects are
temporary and unique.” Discuss this statement, making particular reference to the distinctive characteristics of a
project. [20]
SECTION B
5. A company wishes to install a new networked computer system into its head office. The following table shows the
main activities involved, along with the estimated activity durations:
a) Calculate the expected durations for critical path activities A–E–I. [5]
b) Calculate the scheduled duration for the project. [5]
c) What is the probability of the project being completed in a desired time of 35 days? [5]
d) What is the probability of the project being completed in a desired time of 32 days? [5]
continued overleaf
6. A large manufacturing company is developing a new model of bicycle, and the following table shows some of the
information involved in this project:
Duration
Activity (weeks) Predecessors
A 4 ---
B 3 ---
C 6 ---
D 3 B
E 3 A, D
F 2 B
G 3 E
H 1 A, D
I 5 E
J 3 H, I
K 4 C, F, G
a) Calculate the scheduled completion time and identify the critical path. [4]
b) Calculate the slack (float time) for ALL activities. [6]
c) Construct a Gantt chart for the project. [10]
7. Using the network below and the additional information provided, find:
a) the crash cost per day per activity [8]
b) which activities should be crashed to meet a project deadline of 10 days at minimum cost [8]
c) the new cost [4]
A B
E
1 4 5
C
D
continued overleaf
8. A house building company is considering three potential site locations, A, B and C, for its next development. The
sites at locations A and B will each require an investment of £8m, while the site at location C will require an
investment of £10m. The annual rate of return over the given period is expected to be 5%, and estimates of yearly
sales income, in £m, from each of the three sites are as follows:
Calculate the net present value of EACH of the sites, and advise the company which of the three sites should be
the most profitable. [20]
Relevant Formulae:
Question 5:
Question 7: