ID Task Name Duration Finish 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 Mobilization 1 day Tue 07/05/19
2 Joint Survey (Stake-out) 1 day Tue 07/05/19
3
4 Abutment A 64 days Tue 09/07/19
5 Bridge Excavation (Abutment A) 6 days Sun 12/05/19
6 Bored Pile A1 6 days Sat 18/05/19
7 Rebar Fabrication (Bored Pile) 5 days Fri 17/05/19
8 Setting-out 1 day Fri 17/05/19
9 Boring 1 day Fri 17/05/19
10 Rebar Installation (Bored Pile) 1 day Sat 18/05/19
11 Concrete Pouring (Bored Pile) 1 day Sat 18/05/19
12 Bored Pile A4 7 days Fri 24/05/19
13 Rebar Fabrication (Bored Pile) 5 days Wed 22/05/19
14 Setting-out 1 day Wed 22/05/19
15 Boring 1 day Wed 22/05/19
16 Rebar Installation (Bored Pile) 1 day Thu 23/05/19
17 Concrete Pouring (Bored Pile) 1 day Fri 24/05/19
18 Bored Pile A2 7 days Wed 29/05/19
19 Rebar Fabrication (Bored Pile) 5 days Mon 27/05/19
20 Setting-out 1 day Mon 27/05/19
21 Boring 1 day Mon 27/05/19
22 Rebar Installation (Bored Pile) 1 day Tue 28/05/19
23 Concrete Pouring (Bored Pile) 1 day Wed 29/05/19
24 Bored Pile A5 7 days Mon 03/06/19
25 Rebar Fabrication (Bored Pile) 5 days Sat 01/06/19
26 Setting-out 1 day Sat 01/06/19
27 Boring 1 day Sat 01/06/19
28 Rebar Installation (Bored Pile) 1 day Sun 02/06/19
29 Concrete Pouring (Bored Pile) 1 day Mon 03/06/19
30 Bored Pile A3 7 days Sat 08/06/19
31 Rebar Fabrication (Bored Pile) 5 days Thu 06/06/19
32 Setting-out 1 day Thu 06/06/19
33 Boring 1 day Thu 06/06/19
34 Rebar Installation (Bored Pile) 1 day Fri 07/06/19
35 Concrete Pouring (Bored Pile) 1 day Sat 08/06/19
36 PIT (2sets) 1 day Sun 23/06/19
37 Abutment Seat A 33 days Tue 09/07/19
38 Rebar Fabrication 14 days Thu 20/06/19
39 Chipping of Piles at Cut-off Elevation 8 days Fri 14/06/19
40 Setting-out 2 days Fri 14/06/19
41 Pouring of Lean Concrete 1 day Fri 14/06/19
42 Rebar Installation 14 days Fri 28/06/19
43 Fabrication of Forms 14 days Fri 28/06/19
44 Installation of Forms 14 days Fri 05/07/19
45 Concrete Pouring 2 days Sun 07/07/19
46 Dismantling of Forms 2 days Tue 09/07/19
47
48 Abutment B 64 days Sun 11/08/19
49 Bridge Excavation (Abutment B) 6 days Fri 14/06/19
50 Bored Pile B6 6 days Thu 20/06/19
51 Rebar Fabrication (Bored Pile) 5 days Wed 19/06/19
52 Setting-out 1 day Wed 19/06/19
53 Boring 1 day Wed 19/06/19
54 Rebar Installation (Bored Pile) 1 day Thu 20/06/19
55 Concrete Pouring (Bored Pile) 1 day Thu 20/06/19
56 Bored Pile B9 7 days Wed 26/06/19
57 Rebar Fabrication (Bored Pile) 5 days Mon 24/06/19
58 Setting-out 1 day Mon 24/06/19
59 Boring 1 day Mon 24/06/19
60 Rebar Installation (Bored Pile) 1 day Tue 25/06/19
61 Concrete Pouring (Bored Pile) 1 day Wed 26/06/19
62 Bored Pile B7 7 days Mon 01/07/19
63 Rebar Fabrication (Bored Pile) 5 days Sat 29/06/19
64 Setting-out 1 day Sat 29/06/19
65 Boring 1 day Sat 29/06/19
66 Rebar Installation (Bored Pile) 1 day Sun 30/06/19
67 Concrete Pouring (Bored Pile) 1 day Mon 01/07/19
68 Bored Pile B10 7 days Sat 06/07/19
69 Rebar Fabrication (Bored Pile) 5 days Thu 04/07/19
70 Setting-out 1 day Thu 04/07/19
71 Boring 1 day Thu 04/07/19
72 Rebar Installation (Bored Pile) 1 day Fri 05/07/19
73 Concrete Pouring (Bored Pile) 1 day Sat 06/07/19
74 Bored Pile B8 7 days Thu 11/07/19
75 Rebar Fabrication (Bored Pile) 5 days Tue 09/07/19
76 Setting-out 1 day Tue 09/07/19
77 Boring 1 day Tue 09/07/19
78 Rebar Installation (Bored Pile) 1 day Wed 10/07/19
79 Concrete Pouring (Bored Pile) 1 day Thu 11/07/19
80 PIT (3sets) 1 day Fri 26/07/19
81 PDA (1set) 2 days Fri 26/07/19
82 Abutment Seat B 33 days Sun 11/08/19
83 Rebar Fabrication 14 days Tue 23/07/19
84 Chipping of Piles at Cut-off Elevation 8 days Wed 17/07/19
85 Setting-out 2 days Wed 17/07/19
86 Pouring of Lean Concrete 1 day Wed 17/07/19
87 Rebar Installation 14 days Wed 31/07/19
88 Fabrication of Forms 14 days Wed 31/07/19
89 Installation of Forms 14 days Wed 07/08/19
90 Concrete Pouring 2 days Fri 09/08/19
91 Dismantling of Forms 2 days Sun 11/08/19
92
93 Pre-Stressed Girder (12sets) 49 days Fri 13/09/19
94 Rebar Fabrication (ALL Stirrups) 25 days Tue 20/08/19
95 Preparation of Casting Bed 2 days Tue 13/08/19
96 Pouring of Casting Bed 2 days Wed 14/08/19
97 Rebar Installation and Accessories (Girder 1-4) 4 days Sat 17/08/19
98 Installation of Forms (Girder 1-4) 4 days Mon 19/08/19
99 Concrete Pouring (Girder 1-4) 1 day Tue 20/08/19
100 Removal of Forms (Girder 1-4) 1 day Wed 21/08/19
101 Girder Stressing (Girder 1-4) 1 day Thu 05/09/19
102 Rebar Installation and Accessories (Girder 5-8) 4 days Wed 21/08/19
103 Installation of Forms (Girder 5-8) 4 days Fri 23/08/19
104 Concrete Pouring (Girder 5-8) 1 day Sat 24/08/19
105 Removal of Forms (Girder 5-8) 1 day Sun 25/08/19
106 Girder Stressing (Girder 5-8) 1 day Mon 09/09/19
107 Rebar Installation and Accessories (Girder 9-12) 4 days Sun 25/08/19
108 Installation of Forms (Girder 9-12) 4 days Tue 27/08/19
109 Concrete Pouring (Girder 9-12) 1 day Wed 28/08/19
110 Removal of Forms (Girder 9-12) 1 day Thu 29/08/19
111 Girder Stressing (9-12) 1 day Fri 13/09/19
112
113 Deck Slab 33 days Fri 27/09/19
114 Preparation 10 days Sun 15/09/19
115 Rebar Fabrication 18 days Thu 12/09/19
116 Installation of Rebars 14 days Sat 21/09/19
117 Installation of Forms 4 days Mon 23/09/19
118 Concrete Pouring 2 days Wed 25/09/19
119 Removal of Forms 2 days Fri 27/09/19
120
121 Railings 59 days Mon 23/09/19
122 Preparation 2 days Sun 28/07/19
123 Rebar Fabrication 14 days Sun 11/08/19
124 Installation of Rebars 14 days Sun 18/08/19
125 Installation of Forms 14 days Sun 25/08/19
126 Concrete Pouring 14 days Sun 01/09/19
127 Removal of Forms 14 days Sun 08/09/19
128 Installation of Precast Railings 2 days Mon 23/09/19
129
130 Demobilization 3 days Mon 30/09/19

BRIDGE NO.4 Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline
CONSTRUCTION SCHEDULE