Beruflich Dokumente
Kultur Dokumente
ez///ov %, z*//
No. Bl0l247 lQlPolicy(Works Procedur el?37 ID (Works-I)
Government of India,
Ministry of Defence,
Sena Bhavan, New Delhi
Dated 21st June, 2007
Tb
The Chief of Army Staff
The Chief of Naval Staff
The Chief of Air Staff
DEFENCE WORKS PROCEDURE 2OO7
sh,
The Jafa Committee had recommended the revision of Defence
Works Procedure, 1986 to streamline the existing procedure so that
delay in planning and execution of works may be minimized and cost
over runs in Defence Works could be reduced.
2. The recommendations of Jafa Committee were considered in
the Ministry of Defence and accordingly, the Defence Works Procedure,
1986 revised with the approval of the competent authority. The revised
procedure will henceforth be known as Defence Works Procedure, 2(X)7
abbreviated as DWP 2007.
3. A copy of the Defence Works Procedure 2007 is enclosed. This
will supersede the earlier Defence Works Procedure, 1986 issued vide
letter No. 955338OL/CSS/E2 WPC/687 IDO-II/D (W-I) dated 17th June,
1986 and as amended from time to time and will be effective from the
date of issue of this letter.
4. This issues with the concurrence of the Defence Finance Divisicn
vide their U.O. No. 53W/F (W-D dated 2Lst May ?-Cf7.
Yours faithfully,
Rosy Sharma
Director (Works;
Delence Works procedure,
REGISTER OF AMENDMENTS 2OO7
Isl
Amendment Date ol
number amendment
Para referred
to in
Dated initiats
ol person by
INDEX
amendment whom
amendment Sl. No. Contents Page No.
inserted I Obiective 7
1 TI Basic Principles 7
2.
III Classification of Works 8
ry Orisinjrl Works 9
3.
V Repairs 1l
4, VI Scales and Specificatjons 13
5.
VII Annual Works Programme and Budsetinp t4
VIII Processinq of Maior Capital Works l8
6.
X Dem.and for Planning of New Works l8
7. X Acceptance of Necessity 2t
XI Approximate Estimates
8. 22
KII Administrative Approval 24
9, X[I Revised Administrative Approval 25
10. XIV Urgqnt Works 27
XV Special Powers for Engineers 30
11
XVI Procqssing of Low Budgeted Works 3t
12, XVU Revenue and Minor Works 3l
13. XVNI Technical Control over Orieinal Works 32
XIX Technical Control of Repairs and 35
14.
Purchase and Maintenance of'Tools and
Plants
15.
XX Powers of Technical Sanction 35
16.
XXI Appropriation of Fundb 36
17. XXN Tender Action 37
XXIII Acceptance of Contracts 39
18.
XXIV Reduction of Scope of a proiect 40
19. XXV Execution of Works 40
XXVI I\{onitoring and Review 42
Defence Works Procedure, 2007 Dolonce Works Procedure, 2007 l7l
XXVII Procedure for Snecial Proiects 43
XXVIII Comnletion Reoorts 48
DEFENCE WORKS PROCEDURE, 2OO7
XXIX lmnrest and Assisnments 49 I. OBJECTIVE
XXX Dernolition of Buildinps 50 E 'the objective is to ensure thatmaintenance-are
all defence works
XXXI Reappropriation of Buildinss 51 rrrrtl -scrvices - capital, revenue and
XXXII Works Entrusted to Other Asencies 53 t'onrplctcd with the minimum of delay and in a cost-effective
XXXIU General 53 ,,r,,"ire, compatible with the efficient functioning of the
APPENDIX l)cl'cnce Services. This revised Defence works Procedure
cnr.rmerates the mechanisms of and conditions for planning,
'A' Budgetary Svstem for Defence Works 55
'B' Roush Cost Estimate
l)rogramming, budgeting, approval and execution of such
63 works and services.
'c' Format for Ensineer Annreciation 64
II. BASIC PRINCIPLES
'D' Powers of Acceptance of Necessity and 66
Adm Approval The basic principles of undertaking Defence
'E' Approximate Estimate 68
wrlrks are
'F' Time frame for pre-Administrative 70
(a) No new works should be sanctioned without
Approval plannins careful attention to the assets or facilities already
'G' Revised Approximate Estimate 7l available and the time and cost required to
complete the new works.
'H' Composition of Project Management 72
Committee and Terms of Reference (b) As budgetary resources are limited and granted
'I' Completion Report for Orisinal Works 74
on an annual basis, adequate provisions should
tJ'
Powers for Demolition of Buildinss 76
be ensured for works and services already in
progress before new works and services are
undertaken.
Addenda-I Responsibility for Preparation and 79
(c) If an approved work is not commenced within
Scrutinv of Ensineer Documents
one year of the date of Administrative Approval,
Addenda-II Raising Objections in Formation 80
fresh Administrative Approval of the Competent
Headquarters on Works Matters
Financial Authority (CFA) should be taken.
Addenda-III Manasement of Ooerational Works 82
Addenda-IV Powers of Technical Sanction etc. [Table
(d) Since time is of the essence, the completion
125
'B' of RMESI period stipulated in the Adrninistrative Approval
Addenda-V Maintenance and Upkeep will not be exceeded as far as possible.
of 133
Government Buildinss (e) No works services will be executed without
Addenda-VI Relevant Important Orders/Decisions/ L42
administrative approval, formal Ellocation of
Circulars funds and technical sanction having first been
obtained from the Competent Authority in each
t8l Defence Works procedure, 2007 Defence Works Procedure, 2007 I9I
case. However, the procedure to be followed in
case of works initiated for urgent military reasons IV. ORIGINAL WORKS
are laid down in paras 34 lo 36 below. E (a) Original Works comprise works services like
(D No officer will, in the course of the financial construction of buildings, workshops, storage depots, etc.
year, exc€ed the aggregate budget allotment made including their internal fittings and fixtures as well as roads,
to him for any works or under any sub_head of runways, blast pens, marine works, E/M services, water
maintenance. supply, drainage, other utility services, arboriculture, ranges,
(g) No officer wiil exceed any specific budget furniture etc. as well as purchases and additions.
allotment made to him under -any minor or Reconstruction of buildings and roads, widening of roads,
detailed head except in so far as he may within additions and alterations necessitated by administrative/
his powers of transfer of funds, be able io technical reasons, workq necessary to bring into use
excess expenditure on one item by equivalent
-".t buildings and services newly purchased/acquired or those
savings on another. previously abandoned or rendered unusable by
(h) The final cost of any service wilr not exceed the extraordinary causes such as storm, fire or earthquake also
amount of Administrative Approval by more than fall in the category of original works.
L0Vo. An officer will take no action which will (b) Original works of petty nature costing upto 1Rs.
commit Government to expenditure beyond lTVo 10,000/- Doy, at the discretion of the CWE/GE
of Administrative Approval u-o.rni without (Independent) be treated as "Repairs". The CWE/GE
obtaining prior sanction of the Competent (Independent) may delegale all or a portion of his powers
Financial Authority in the form of a Financial under this paragraph to GEs or outstation AGEs by name.
Concurrence (FC), a Corrigendum or a Revised (c) The purchase and installation of static plant and
Administrative Approval. machinery and equipment and the provision of furniture
(D The CFA according Administrative Approval are treated as original works.
- (d) Provision of furniture which does not form part
should be kept informed of the progr"r, bt tn,
works till their completion tlirough regular of any works project will be treated as Original Works.
periodical reports.
E (a) For aclministrative purposes Original Works
C) No project or work services will be split up to are divided into the following categories :
bring it within the powers of a CFA at a lower (i) Major Capital Works i.e., original works costing
level. Rs. 15 lakhs or more.
III. CTASSIFICATION OF WORKS (ii) Low-Budgeted Capital Works i.e., original works
E For purposes of budgeting and control the costing more than Rs. 2 lakhs but less than Rs.
operations of Defence Works are divided into two broad 15 lakhs.
categories, namely :
(a) Original Works (b) Repairs Approval of com@ent authority required.
[10] Defence Works Procedure, 2007 Detence Works Procedure, 2007 [ 11 I
(iii) Revenue Works i.e., original works costing more ,tttttt,tirmcrl us such uruler lhe powers ot' the Competenl Firutnciul
than Rs. 1 lakh and not exceeding Rs. Z lakhs. /uthrrily.
(iv) Minor Works i.e., original works costing not (iii) Superior specifications to those on which approvedl
more than Rs. 1 lakh. ,rttttt'lirmr:rlnintn Arias rates are based will be termed "Special"'
'l'ltrir inrtrytoratktn in worlcs at any stage during planning or
(b) Major Capital Works and Low-Budgeted Capital ctrt'tttien without pri.or approval of the Competent Financial
Works will be budgeted under Capital Heads. ,4utfutity is not Permitted.
(c) Revenue Works and Minor Works as defined above
V. REPAIRS
will be budgeted under Revenue heads.
l-t E (a) Repairs comprise all maintenance and
l6.J New Original Works are further sub-divided as periomal services, renewals and replacements as well as
follows : alterations and improvements necessitated by technical or
(a) Authorised Works : Works Services for which engineering reasons.
scales are authorised in regulations or by separate (b) Works required to make good damages caused to
orders of a general or specific nature issued by existing buildings, roads, installations and services due to
the Government of India are referred to broadly e*traoidittary causes, but which are still usable, are also
as Authorised Works. classified as 'Repairs'. The question whether a building etc.
(b) Special Works : Items of works services not is still "usable" or not will be decided by a Board of
falling within sub-para (a) above are referred Officers convened to investigate the matter.
to as "Special Works". These may be approved (c) A property when taken off from care and
only when exceptional local conditions justifu maintenance ls deemed to be abandoned and will not be
the necessity, or as an important experimental entitled to maintenance funds.
measure. Special Works should not be approved
if the effect would be to introduce a new practice E Repairs are classified into two broad categories :
yotf -due to any reason, irrespective of wf,ether the cost expliffanO bf'As must be held responsible for _their
is within the tolerance limit oi ,rot. deiision. Notwithstanding the procedures laid down in Paras
(e) No change in site is permissible. However, in 22 to 3t above, if for urgent military reasons delay involved
exceptional circumstances, approval of cFA one level in the issue of administrative approval based on approximate
will be obtained.
higher estimates cannot be accepted, the Competent Financial
(t) If upward revision of cost estimates beyond the Authority is empowered to order commencement of w6rk
. on essential items of required work prior to the issue of
tolerance limit is anticipated without any change in scope
administrative approval. In doing so, however, the CFA
of work, then the prepiration and submission of Revised
Approximate Estimates will be initiated. However, should ensure that no accommodation or facility is
constructed in excess of requirements. The "Go-Ahead"
tendering and contract planning may continue; but
sanctions accorded under this para by cFAs lower than
acceptance of tender/conclusion of contract will
be made the Governrnent of India will be subject to the following
only after obtaining Financial concurrence of the cEA.
conditions :
G) It is mandatory to obtain a Revised Administrative (a) The "Go-Ahead" sanction will be ordinarily
Approval from the cEA in the form of a corrig"nou- restricted to items like collection of stores, site
u,
the earliest after the issue of the FC. As such a
co?oig"nou-
Drlonco Worko Procedure, 2007 [2eI
[28] Detence Works Procedure, 2007 ortlcr tor contmettcement tlt wtlrks utlder the
clearance, external services, construction of Prevalent circumstances'
;l.he
essential temporary accommodation for the staff (ili) commander is satisfied that he will be held
and stores, residentiai accommodation for the responsrble for any failure or disaster that may
construction staff and preliminary works if he neglects to order commencement
necessary for the execution of the project. Work "nrut",
of necessary works.
related to piling and reclamation may be also (b)Sh<luldtheconcernedCommanderdecidethatit
covered by the "Go-Ahead" sanction, provicled is necessary to order commencernent of necessary works
it is duly supported by an approximate estimate io .flpurt,,ie frorn the procedures laid down in Paras 2?
for such piiing and reclamation. ttl ti above, he will i"pott the fact in writing to thea
(h) The 'Co-Ahead" sanction will not exceed ZA Vo apprupriute cFA at the ebrliest possibie moment
within
of the rough cost estimate for the entire project il.rf. wittr copies to the CDA concerned and alsotime. inform
made by the Engineer authorities. The t ii i-*"Oiate Superior Commander at the sarne
percentage will not include the cost of acquisition (c)ProvisionunderPara'33belcrwwillbeapplicable
of land required for the project. to works sanctioned under this Fara at the cliscretion of
{c) Provisions under Para 38 below will be applicable the concerned commanrjer. Further, skilled/semi-skilled/
of
to wclrk sanctioned under this Para at the unskilled manpower may b* ernpltlyed r:n daily rates
prcvalent in the station by the
discretion of the Competent Financial Authority. ;il-;; per Nfrric rates
tgl-J (a) Further, notwithstanding the procedures laid bur.iro" Engineer ordering the work not exceeding 15
down in Paras 22 ta 31 above, unexpected circumstances J"y, oo."*ll In terms of time and 1000 man days in effort'
may arise which make it imperative to short-circuit normal with reason and justification. For employing skilled,
procedure. Such circumstances may arise from unforeseen semi-skilled, unskiied manpower beyond these limits
operationai necessity or urgent medical grounds or out of sanction of CFA wiil be obtained'
danger to
natural disasters when reference to the appropriate CFA [5t| (a) Again in the.case of imminent
would entail dangerous delay. In such circurnstances, any buildffi roads Jt." ot of a breakdown of supplywould fro.m an
be
Commander may order the commencement of required E/M or water supply installation, when deiay
work by furnishing an order in writing to the engineer Jii.uuty detrimental to the public service, the local MES
officer concerned. The following principles will guide the or pWb officer will take steps to protect Government
Commander concerned in taking such an action : property or the inhabitants etc. But he rnust at once report
(i) Can the appropriate CFA be referred to and his in"-fu*i, of the case and the reasons for his action to the
approval received without causing dangerous |iup*riot engineer authority, the.L'ocal Military Cornmander
delay in commencement of work ? antj to the CDR concerned indicating the financial liability
(ii) The facts of the case satisff the Commander he iri incurring.
that, if the appropriate CFA could be referred (b)ProvisionsunderPara3Sbelowwillbeapplicable
to in time, the latter would have given the same to wrirts sanctioned under this Para at the discretion of
130 I Ootgncs Works procedure, 2007 Delence Works Procedure, 2007
31 I
th".
.F:ul Engineer or'r'ccr. I,urrher, skilred/semi-rHr"al (viii)Procurement of cement and Steel frorn open
itrTi"i
p:: #Tpi:::i:ll
Para-_35(c) ll:'"i'r;Il.vctr "' J;ir;;;;;;
';fi:# p'v market, if necessary.
lut above) rry it--"rgr"."t, ffil (ix)1 Selective tendering.
exceeding 15 days overall in ferms of time and 1000 man (x)2 Dispensing with adverlisement for tendering and
days in effort.
contracting.
r_ lTl..*. procedures outlined in paras 34
dispense with
to 36above Note : The expenditure to be incurred fttr items cited in
sub-Paras (iii) to (vii) above will be met out b7 conttngencies
9o. lol the necessity for the issue of of
Administrative Approv{by the p_roject. The cost of consurtancy wilr be" arso m"et i"t ,iy
ttre Cne.Uased on subsequently
prepared Approximate Esiimate Contingencies if not separately providbd
at the .urri"ri ofp-J.iunity fcr.
not exceeding six months after commencement XVI. PROCESSING OF LOW BUDGETED WORKS
Further of works.
such works can t. rtuii.o *ith;;;-;iii"g
. ld|
ro. In case of Low Budgeted Works, i.e., original
specific allotment of funds for the project capital works costing more than Rs. 2 Lakh,.nut iess Ilan
rru;"li- t3 tne
condition that necessary allotm"rrt of funO,
is applied for and obtiined u, ,h" ,urliest
f;;;i,;;uipo* Rs. 15 Lakh, these works will be sanctioned by the cEAs
opportunity as after the Annual Low Budgeted works programme has
per provisions in para 45 below. been approved as per para 19 above and bulf ailotments
XV. SPECIAL POWERS FOR ENGINEERS of funds for this purpose in the relevant financial year have
When an urgent w,ork (under paras been made to the respective cEAs. Board proceedings can
-, -F is entrusted to th-e engineu",
34-36) 3l(d), be dispensed with in case of Low Budgeted works c"osting
io" .o-prutio' oi trru upto Rs. 10 Lakh, if so decided by tne ene. Administrativl
works in a compressed time frame, the
Ctrief errgirr.u" Approval in such cases will be based on consideration and
can exercise the fouowing speciar powers
in
with planning and executi"on of such works connection approval of a Statement of case as per para 22 above by
:
(i) Detailing officers anywhere in the country. the cEA and Approximate Estimates as per para 30 above.
(1i) Resorting ro consultancy for any irem of work. lhl| In case of Low Budgeted Works carried out for
(iii) Purchasing of stationery, reprographic urgent reasons as cited in paras 34 to 36 above, the
equipments, typewriters or any other procedures laid down therein can be adopted.
office XVII. REVENUE AND MINOR WORKS
equipment required.
(iv) Installation of Telex, Fix, Internet |Zil| (a) In case of Revenue Works and Minor Works
.
communication
or other
equipmenr in CBICWE/CE as defined in para 5 (a) (iii) & (iv) above, these works
office.
(r) Payment of charges for telephone connections The dispensation.mentioned in para OB (ix) & (x) woutd
clearly sp9t- out in the administrative ipirrbvat b6coroei be
including STD fa-itity on priority Uuri" ----"'' Ei
(vi) Hiring of civil transport for project work.
ths coWCFA not betow the tevel ot cod_in_b;"d ili;;i
The_re_a_cons tor dispensing wirh compirition *au
on record ln writing. il;illi;
(vii)
fliring of office and temporary accommodation Chief .Englneer coud exercise these po{rers ln
connection
-
for construction staff. wlth the urgent work, after taklng ne lppronf of-iFA.---
t32 l Defence Works Procedure, 2007 [33 I
Dtbncc Works Procedure' 2007
will be sanctioned by the CFA after consideration of a Action is
tha ArJnrinistrative Approval bef<lre Contract
Statement of Case as per Yara 22 above and Approximate
tukcn.
Estimates as per Para 30 above against bulk allotrnents fnr
(c) Schedules of works will be pre.pared l-olg-,:itn
this purpose rnacle in the relevant financial year. No Board and technically
Froceedings will tre necessary in these cases. In case of rcquiiii. designs arut drawings' cosiedauthority before
sanctioned by the cornpetent engneer
Minor works eosting less than Rs. 50000i-, no Approximate technical sanction will
Estirnates will be necessary. tcntler document, ut. iisued. ThJ based on
(b) In case of Barrack Darnages, subject to the i;;lt.tt the anticipated contraitor's ofpercentage
market trends'
l'f',, B"gi"eer Offiier's appreciation
condition that barracl< damages have been recovered frcrn
the individual/ unit concerned at the rates comrnensurate
(d) Costed sctreOutl of works will be in strict
so. far as-scoFe
with the cost of repair or replacement as(per) Paras 634 uraoJun.e with the administrative approvalengineer officer
ii;grk uto t.ui", -" to"t"rned' The
and 635 of MES Regulafions, the engineer officer concerned s'anction to a project may'
may carry out repairs without waiting for any specific competent to accord technical shown in
wherever ,r.."rruil, deviate from specifications
sanction of the CFA. "lhe expenditure incurred for this
purpose will be charged to allotments fclr rnaintenance. ittt upptoximate estimate provided that :
(ri the deviations ate necessitated by engineer/ to alter
K/III. TECI-INICAA. CONTHOL OVER ORIGINAL WONKS aesthetic ieasons and are not such as
WJ (a) Technical sanction, which is issued b,v the the scoPe of the work;
from authorised
competent engineer authority, amounts to no ffiore than a
guarantee that the works proposals are structurally sound
\ / there i, ,,o serious departure
(ii)
general sPecifications; and
and that the estinnates are accurately calculated and based (iii) the total cost of the P.roiegt tt id1t:tt:rativelv
approved iS not exceeded beyond the
on adequate data. Ordinarily such technical sanctions are tolerance
accorded only after ,Administrative Approval. But in case limit.
of atrthorizeci iterns of work based on approved scales of (e) In case of works carried out by specialist .fltTt
accommodation and specificaticlns, necessary documents
inciuding designs and drawings aan be prepared in advance basedontheirowndesigns,technicalsanctionswillbe
design on receipt
accorded on the basis of the accepted
so that the stages of Technical Sanction and Tender Action the contract.
can be covered expeditiously after Administrative Approval
oi it, tender but before the acceptance of
(f) Schedules of works may be sanctioned projectsfor the
is accorded.
(b) The Government may also issue special instructiclns proieli ui u *ttoi" or part- of sucir projects' Large
and. execution' be
may, for .o.ru.niJrr." ir planning, iititig
specifying the categories of works cases r,vhere technicai is to
be
sanctions can be issued to facilitate lbnder Action even broken into sub-projects' The teim 'sub-projects"project if
unit of the
before Adroinistrative Approval. In such cases, if necessary, il,* to a disiinci setf_contained kept distinct
revision of Technical sanction will be made on the basis
lfiirrroit is sufficienity tutg" or important to be
Further' any
iot p"tpotes of plantti"g,-'iting. and execution'
of finalized scope of work, scale and specifications as per
self-contained !*t"tttui' t"tulc" may be treated as a
sub-project.
135 I
[34 I Delence Workg Procedure, 2007 Dllrncr Workr Ptoc{utc:-2od
Regulations'
(g) In order to ensure that sub-projects are kept within llvinq does not exceed the power under MES
the scope of the whole project as defined in the iffii:i ,ii;. n""rr-i"", or puiu 44 belorP also refer. AND
Administrative Approval, Technical Sanction to all irx. TEcHNtcAL coNTRoL -oF REPAIRS
sub-projects of a project must be accorded within as short PURCHASE AN; MITTIiETTANCE
OF TOOLS AND
a time as possible after issue of administrative approval. PLANT
(h) The competent engineer authority befr,rre according rfuJ (a) Estimates
tl".ttni.ut or requisitions will be prepared,
technical sanction to a sub-project must be satisfied that sanction by th9 competent
.or,rb=uttd -accorded
the amount of technical sanction for the whole project is ;li;;-;"irtoiitv before work is commenced'
before
not likely to exceed the amount of administrative approval (b) The competeni englneer authority'that the
...orJing iu.t rri.ut sanction, must be
including the tolerance limit of 10 per cent. satisfied
(i) In case the technical sanction amount for the whole iii""ri fu technical sanction-tqr the repair-estimate is not
project is likely to exceed the amount available in the lfi;tl"-rxceed itl-ro;6, placed at liis disposal for the
Administrative Approval amount including the tolerance Purpose.
limit of L0 percent, but without any change of scope of executives are responsible for the
(c) The engineer-uttututy
the project, then the Technical sanction can be issued to construction tit""tt, and economy for repair
enable taking Tender action, subject to the stipulation, to estimates and requisitions'
be recorded in rwiting, that revised administrative approval
is being obtained and that no financial commitrnent will
il;":wens oi rEcHNlcAL sANcrloN
be made until the revised administrative approval or E4l (a) Powers of technical sanction are laid down
financial concurrence is received. in VtFn'egulations, Table 'B"
0) In the case of purchase of buildings, the valuation (b) The engineer officer- competent to" :1ltli:n the
projeJ'us. *nor? iiiechnically responsible for a
the project
statement will be taken as technical sanction. The valuation
the project.as 'whole
statement will be prepared/approved by the competent and for ensuring that the amount oi
and subject to
engineer authority as in the case of technical sanction for ir'noi.*eedeo-except in the circumstances may delegate
construction work. In cases where there is a time lag of iil .""Jitio"t r"io ou:*n in para 42 above' He officers to
one year or more between the preparation of valuation ililfit" "i rrt orscretior to local engineer. in para
os defined
statement and final purchase, a certificate that the property ;;;;;-i;.n*cat ,unctiol to sub-proiects,
has not deteriorated/ depreciated during the interval will ;;-;til; ttre-qjf plan locallv within the
*nirrt ttj otottt
riirirr-ni'rt.i, po*.ii,rrrout MES Regutations Table 'B'.
be taken by the Engineers before the purchase is made. down in each
A fresh valuation statement will be prepared in case of Wh;; a-"r;g",rtie t*n *tt'oti'y.he will lav
sanction will be
deterioration. A copy of the valuation statement will be case .the total ,i*-"pto which technical
without the
endorsed to the CDA concerned. ai."ra?,t;Ji,iti; ,u,'r"'*itt not be exceeded Copies of
(k) The Competent Engineer Authorily must also
prior .on*rr"rr.J oi-lttt delegating authority'in all cases
satisfy himself that the amount of Technical Sanction he is Iu.ti'O"rtgation of powers witl be lorwarded
to the CDA concerned'
[3el Defence Works Procedure, 2007 Ddrnor Workl Proccdure' 2oo7
[37 I
(c) Chief Engineers are authorized in exceptional b*n ,on.tionecl and ordered to be commenced against
circumstances to increase the powers of any officer ililil; u"rr, uloi-ent of f:{: f,'1:^l: J.n?i':n i;:
subordinate to them by name to the extent they consider ;il"il;";;'j;li'; ';levant financial vear' It will' be the
such allotment
necessary within their own limits for technical sanction of ljlp,i"iiirility by every cFA to ascertain that
adequately for' these
designs and acceptance of contracts. It will be ensured that ,,f-'run<.rt ni. i"O".i been made year before
while delegating such powers the following requirements of *orr., ouring the relevant financial
iiitrg"r];,
are complied with : ;t";; of the certificate will be
Nch u certificate 4 foi
:opy
watching the adequacy of
(i) Enhanced powers are granted in exceptional lont to the CDA coice'n"d
circumstances and in respect of individual iddt against sanction of works of these categories'
projects. (c) Notwithstanding sub-para (a) and (b) above' in
(ii) Sanctions are given by name to officers. writing' the C-FA may
ca$cs of urgency to Ut iecordid.in
(iii) The period for which the delegated power is to order .o**"rr."'it"* of preliminary.^y9tkt lik-e site
itc' in specified cases t"l]t,tl
be exercised is specified. clcarance,
services' etc' tn
i, "*t"rrrui-tervices
ittt conclition that the said new worksthat
(d) In the case of works carried out by agencies other the said new
than the MES, the normal procedure in force in the agency rpecified cases subject to the condition
concerned for according technical sanction will be followed. works services n*i u..n accorded Go-Ahead sanction and
Works/Ldw Budgeted
In the case of projects costing more than Rs. 50 Lakh, also in the approv-eJ fufu:ot Capital
financial year
however, it should be ensured that detailed plans and 6upituf Wort s p-gtut-e oJ ihe relevant works does
specifications conform to the scales and specifications un,iitt"t ttre estimaied to't of such preliminary
approved by Ministry of Defence, before technical sanction not exceed 5 p";';"; oi ttt" total cost approved in each
a demand for a special
is accorded. case. Simuttun"orrrij he will forward
ullotment of funds to the appropriate higher authority
)O(I. APPROPRIATION OF FUNDS
explaining the urgencY'
Eil (a) Appropriation of funds means the allotment
}O(II. TENDER ACTION
of a particular sum of money to meet expenditure on a
@| (a)ias After the schedule of work for a project or
specified work through the annual allocation of funds under
the budgetary heads indicated at Appendix A immediately suU-ffict' U."n technically sanctioned by the
authority, tendttt will be invited for
after passing of the Defence Service Estimates by competent
of contracting
the execution of tt* *ott' Normal method
"rrgrn""'-
Parliament. No new Major Capital Work will commence
i.e., no Contract Action as per para 48 below will be taken *itt U" based on competitive tendering'
in respect of that work, unless and until such specified (b) Special tenders, such as. those of single cost-plus
guidelines
aliotment of fund is made for that work or project. ,yp, i"q,rire the "ppt"yl of E^-in-C' Separate with the
(b) In case of Low Budgeted,Works, Revenue Works will be issued Uy-itt. E-in-C for such projects
and Minor .Works, a certificate will be given by the approval of Defence Finance'
concerned CEA in case of each of these works that it has (c) In case of the following categories.of works' the
Tiade
practi;; of advertisement in news papers and Indian
Procedure' 2oo7 l3eI
'
[38 I Delence Works Procedure, 2007 ----,----Workr
Drhnco
tl"^t:i::*::ti:
Journal, giving notices inviting applications for issue of
(l) ln .o,*
tl, ln u'lru offi
vrrrJ resultant single,
accepted after pe1m.l-sslon
tenders, will be dispensed with and tenders will be rctslvetl, the same ca" ottly be and a report to the
distributed to selected eligible contractors who are already of nrxt higher engi;"i Authority concerned CDA/PCDA'
on the approved list of MES and have got the capacity rnnrt wlll be furnis"hed to the
: In case of works to 'be
and experience to undertake the proposed work. [d| Mobilization Advancelocation and/or requlnng
(i) All works costing upto Rs. 5 Lakh. cnrrlcd out ln remote/difficult
tools or plants, or works
(ii) All works approved under Paras 34, 35 rrr,hirizatio' ot rpe.iut equipment,
and 36 above. trt bc completed ;;ffi;"'; uod.to*ptesse,! -ti11";lt:t"'
"i"titde. in the tender notice the
(d) However, the notice shall be got displayed on the tlro Chief Errgi""t; t""V
the prospective contractors
notice boards of the following offices : ;;il.t ,,f ;offl"uti* advance todelay'in iommencement of
(i) SE/EE of CPWD & State PWD in station. to us to prevent-.uuolOuUte E-in-C's Branch will
works after acceptance of contract' approv{ of' Defence
(ii) l,ocal Municipalities and Cantonment lrsue necer.u.y g"i;"li"tt *itf'.
the
amount ot mobilization
boards. rlnsnce from timJ';; 1il" on the
(iii) State Bank of India, l,ocal &. nearest ndvance subject ;; ;;;t-"-
of L}vo of the value of the
interest to be charged
branches to places of work. contract that can-b"-!iu"1"O' the and/or adjustment
(iv) Railway and post offices nearest to places recovery
rund the method u"Jitfi"O"le of
of work. trl.suchadvanceindifferentcategoriesofcases.
(") MES formations in station. XXIII. ACCEPTANCE OF CONTRACTS
(vi) Head offices of Builders Association of -f;ffi gt
India. .,,* H'gL ,ij":'fii[1F ?:.TTitr1;::
(vii) Internet Publication of tenders should be und 440 ibid. to
on the website of concerned Deptt/MoD. (b) It is emphasized that no officer is empowered
over the
(e) Scrutiny of tender documents by Audit prior to uccept a contract *t'itt' is likely
to cause excess
into account
acceptance of tender is not necessary. Chief Engineers are ffi ffi ;;ilt"ili;uri"" approvalafter
pt"
taking
above' tn the
empowered to alter standard contract documents at the toleran." uno*J'"iOJ -2(h) 111e-
pre-tender stage to suit urgent requirements particularly contract i, .ou",i"g
p"tt of tire work covered in the
"tfy-" procedure indicated in para
with reference to security deposits, percentage paynlents, administratiue app?wai ttte
speed of payments, issue of stores, deviation limits and 32 above wilt be followed'
similar matters. They will, however, consult the CDA/IFA over the tolerance limit of
107a
@ When -nppt"""i'
an excess
concerned wherever possible. Where the decision of Chief
over Admlrrirtrutiit which cannot be met by
Engineer on such alterations involves a major departure t:,
from the existing procedure, he shall send a copy thereof
-r"itgt on other items, occurs or appeartwill l1f"'ly -.ottut
be at
on account of technical reason" u
t"pott 11de
to the E-in-C/DGW and CDA/IFA for information. authority who granted the
once to tfre comietent engineer
[40] Defence Works procedure, 200?
Defence Works Procedure, 2007
technical sanction for the work. If there [41 I
curtail the work or-modiff it, the orders
is stilltimil or materials can be introduced if technical or aesthetic
be taken, If no modification is ordeled,
of the cEA will rja.sonl so justiff, with the prior approval of the Zonal
a revised estimatJ chief Engineer concerned, subject to the condition that
will, be prepared and revised adminiitruiiu"
uppiouui oi rr," this must be within the existing tolerance limit as applicable
CFA obtained as per para 32 abovi.
and not exceeding 5vo of the original Admiiistrative
In the.case of projects estimated to cost Rs.
,^,_. @ 3 Approval amount.
raKn or more, when the amount of accepted contracts
reduces rhe cost of the project below
ttt. ui-inistlatively lE| The technical sanctions accorded to costed
approved amount by more than 15 p.r.rni,-ih"'upprou.o schedule as per para 42 above will be revised only for the
amount for thar project will be reduced following reasons :
Uy if,"'ulount
exceeding 15 percent by the CE/CWE/GE
within whose
(a) Engineering/technical reasons such as changes in
powers of technical sanction the work designs, specifications, drawings etc. Revision will
falls. The oetam or
reduction will be sent to the cDA and
all others concerned. not, however, be necessary if such variations are
The amount of sayng_up to 5 percent (of sanctioned by the authority competent to revise
the oriliid
amount) thus retained wil be used to cove*u"i?tiin,.q/A the technical sanction, before deviation orders
cost for technical reasons. i, or amendments to contracts are issued under
)O(IV. REDUCTION OF SCOPE OF provisions of the contract. However, such
A PROJECT competent authority Doy, on his own
E! .When the
" administrative
for
scope of a work service is reducecl
or other reasons, the Administrative
responsibility, delegate the powers of revision of
technical sanction to the authority issuing
Approval need not be revised; but the upprou"J-un,tun,, deviation orders for the specific purpose.
for the abandoned or recJuced it"n,u of the
service
total approval amount w'r be reduced accordingrvand the
(b) On account of revision of administrative approval,
concerned engineer authority within whose uv trr" if the variations are not already coverecl by
technical sanction the work falis. Details i"'*";, of sanction to deviation order or amendments to
of ,u.rr'r"ou.tion, the contract vide clause (a) above. Revision will
of scope will be sent to the cEA, the cDA
uno urr *r,"r, not, however, be necessary where the variation
concerned.
is due to non-technical reasons, such as difference
)Ory. EXECUTION OF WORKS in cost of stores or where the percentage in the
@ and ($ After acceptance of contract, the execution accepted contract differs from the anticipated
of" works their rrpr*irion wilr be carried out by the percentage provided in the costed schedules.
;ngineers-in-charge as per MES negutations r""o *rtr,'Lags
(c) The original technical sanction is found to have
standing orders. Deviations on" and amendments of been based on inaccurate estimates initially. In
contracts, if necessary, will be carried cases, however, where scope of work is changed
ou, ur-p.r'VfeS
Regulations and Standing Orders. due to administrative reasons, the technical
(b) while constructing a building, new sanction will be revised and issued before such
specifications
items of work are actually executed.
Delence Works Procedure, 2007 Dolence Works Procodure' 2007 [43]
I 421
)OffI. MONITORING AND REVIEW XXVII. PROCEDURE FOR SPECIAL PROJECTS
monitoring 1nq timely @| Notwithstanding the provisions made above, in
It] (a) To enable effective .u*. [Iiorks projects requiring the acceptance of necessity
.orrrrForrection of works in progress, Quarterly Progress
indicating physical und finuttcial progress of
all rund administrativi approval at ahe level of MoD, the special
ir"p.itt pr'cedures outlinedln Paras 56 to 60 below may be adopted
*ujor capital *oiti will be prepared and submitted to
,"ii,*,f"6 CFAs for information ind direction.whiclt Avoidable il' such works are of the following categories :
delays or stoppages in progrest 9{ *9ik1 lq* (a) Strategic imPortance
for (b)
occurred or are ior.r*"r1. witt be identified' reasons High Tech ComPlexitY
taken
shortfalls examined and necessary remedial steps (c) Urgent necessitY
promptty through onJine communications systems to -and close interaction
Note : Such worl<s may be requiring with
prevent cost and tiPe-overruns' usar, specialist design consultants vendors of plant and
(b) Works Review Committees will be set up for each equipments and transfer of technologt-
Servics by the Ministry of Defence at the level of
Joint
@] PreparatorJ f'age
S".r.ruty'includingDefence(Finance)representativefor
rplanning and (a) For initiating ttE demand for new works services
,uttyi"g' o"t Qulrterly Review of the lbr a ipecial project, ihe Uret establishment/formation will
i-pi"tti""tation of works projects costing mole than Rs' 15
lines indicated in Para
."o".. The review procedut" -ay be revised as and when 1rr.pur" a Statement of Case on the
22 above.
t"q"it"O so that ih" Minittry's.attention is focused on
level' (b) The Statement of Case will be then examined by
Cuiriruf works projects sanctioned at Government
(c) In case of all projects/works costing more^than Rs' the iommand Hqrs/Service Hqrs for setting up a Board
of Officers who *ill e*a-ine the detailed features of the
1 crore, a representative bt ttt" User will be nominated
as
project' officer to coordinate functional aspects of the works proposal with a view to :
User's requirement with the engineers -from the (i) Defining clearly the scope' scales. and
specifications of the works proposed'
commencement to the completion of such works'
'(d) In addition, depending on the relative importance (ii) Programming the various implementation
phaies of the project and the time schedule
and vaiue of various wbrks projects, project management
auihorities may be set up at the level of Ministry of
Defence' for each Phase.
Service HQrs, Command HQrs and other formations
and (iii) Indicating the time and efforts required
entrusted with suitable responsibilities and powers to review for acquisition and development of land
itr" ptogt"ss of works, ,"roiu" bottlenecks and take suitable and for environmental clearance, if any'
decisions to ensure timely and cost-effective completion
of (iu)
suchworks.Theljsers'representative,theZonalChief :;:ff#'Jff_:,.H: "*::,1i"":x["Ji
n"lin."t and Defence (Finance)/IFA representative will
-associated
utilities of preparatory nature required.
be with such project management authorities. (u) Nature of consultanry required at any stage
Oalanco Worka Procedure, 2007 I45 l
[44] Defence Works Procedure, 2007
of the works project, viz., preparation of 24 atrove based on Estimates produced
feasibility/project reports, programming lry Engineer Auth<lrities.
schedules of works, external services and (lr) It is reiterated that the CEA in such cases is
utilities, structural/architectural drawings/ rlwuys MoD. A prop<lsal will be submitted after acceptance
designs, cost estimates, preparation of bills ul' l)ctailed Project Report (DPR) to the CFA for granting
of quantities and/or tender packages, g "(jo-Ahead Sanction" amounting to 5 per cent of the
appraisal of tender documents, project/ ruugh cost estimate for approving :
construction management etc. for the (i) The broad scope and features of the wuri;r
whole or for part(s) of the project. proposed.
(vi) Details of rough cost estimates. (ii) Site surveys and development of land and
(vii) Phasing of fund requirements. enabling works including preparatory
Note : It would be the primary responsibility of the User external services and utilities.
establishment and the Command HqrslService Hqrs trt complete (iii) The engagement of outside consultancy,
this preparatory stage systematically and expeditiously. designing or estimating work and the cost
thereof, subject to the stipulations made
m Steps upto Go-Ahead Sanction
in Para 24 above.
(a) After examination of the recommendations of the
Board of Officers, the Command HQrs will take the
(iv) Delegation of special powers under Para
38 above to the Zonal Chief Engineer/
following steps through the Service Hqrs :
Project Chief Engineer.
(i) Propose inclusion of the works proposal (u) Appointment of a Project Management
in the Annual Works Programme, if not Authority for steering the project through
already done.
all other phases such as detailed planning
(ii) Propose specific phasing and allocation of and estimation, administrative approval,
funds to ensure adequate fund availability finalization of
designs and drawings,
for the entire duration of the project. control action, execution and monitoring
(iii) Initiate preparation of Detailed Project of the physical and financial progress of
Report (DPR) for works projects of high the works. The composition of and powers
value requiring MoD/ Cabinet approval which can be entrusted to such a Project
under departmental or outside consultancy Management Authority is illustrated in
arrangements. Appendix 'H'.
(iu) Approval of CFA will have to be obtained (c) On receipt of the "Go-Ahead" sanction, the
from the MoD for aPPointment of prcparatory activities mentioned at sub-para (b) above will
Consultants for any purpose related to the lrc started.
project, including preparation of the DPR, Note : It will be the responsibility of the Seruice HQrs to
subject to the stipulations made in Para ctnqtlete this stage uptct "Go-AheQd" sanction expetlitiously.
Defence Works Procedure, 2007 Drlonce Workl Procedure, 2007 147 I
[46 I
sanctionecl, the date by which the works will be
@| Steps upto Administrative Approval
completed and the budgetary sources from which
(a) After the "Go-Ahead" sanction the engineer will be allotted. The Administrative
fun<ls
authorities will start preparation of basic designs Approval will also indicate the scope of
and Approximate Estimates. However, in cases consultancy required for the implementation of
where a Detailed Project Report has to be the project.
prepared as per Para 57 (a) (iii) above, the
preparation of the Approximate Estimates may |d| Steps upto Contract Action
be undertaken on the basis of the approved (a) On receipt of tenders, the Engineers will evaluate
DPR. thc tenders and prepare a tender appraisal report
(b) The AEs for works which are to be completed comprising :
in two years shall be so framed that it caters (i) Comparative evaluation of tendered rates'
for escalation for two years. However, the contract (ii) Finalized Approximate Estimates based on
shall not include any escalation clause except approved scope of work, technical sanction
statutory increases. and lowest accePtable tender.
(c) On the basis of the Approximate Estimates, the (b) The competent engineer authority will ensure
Technical sanction for the works will be given completion of detailed designs and drawings as well as
by the competent engineer authorities to enable cost;d schedules and, if considered necessary, issue revised
taking of Tender Action. In case of works of technical sanction without delay after receipt of
high technical complexity tendering for Item Rate Administrative APProval.
Contracts may be resorted to. (c) On receipt of
Administrative Approval and
(d) (i) In case of selective tendering, when technical sanction, the contract will be concluded.
approved by the CFA the time to submit Note. It will be the responsibility of the competent Engineer
tenders will be normally restricted to 4 Authoity (CEA) to ensurelhat necessary documents are handed
weeks from the date of issue of tender over to'the contractor and the latter Storts the worl<s on the site
notice. within a pre-determined time stipulated in the contract.
(ii) The Offer of Mobilization Advance as @| Execution and Monitoring of Works
indicated in Para 47 above will be made (a) With a view to completing the works strictly as
to ensure prompt mobilization of resources
per approved scope of works and time-schedule, the Project
and commencement of works.
Manig"-"ttt Group will be institutionalized by the
(e) Simuitaneously with the issue of tenders, the compJtettt Administrative Authority who, in tytg, will
Engineer authorities will submit the Approximate reguiarly monitor the progress of the- works, help the
Estimates to the CFA for issue of Administrative enlineeis in mobilizing physical and financial resources
' approval' will
Approval. The Administrative,'of anl remouing procedurpl bottlenecks. The review by the
indicate thc detailed scope' the works Project Management Group will be carried out periodically
[48 I Defence Works Procedure, 2007
Drllnce Works Procedure, 2007 [4e]
every six months. Such PMGs will invariably be constituted
I
for Projects costing Rs. Crore and above' wlll [c rcnclered in accorclance with the following procedure
(b) user establishment will nominate a representative Itt thc filrm set out in Appendix 'I'.
to ttre Project N{anagement croup to coordinate the (b) Part A of the form will be completed as soon as
functilnal rlquirements of the users with the Engineers. lhe proJect is physically completed, and will be forwarded
(c) The Zonal Chief Engineer/Project Chief Engineer thrgugh engineer channels to the Engineer Adviser of the
('l'A. After being noted, they will be returned direct to
cclncerned may approve cleviations/amendments to the
Contracts Lrpt; l0% of the Contracted Amount (CA)' tlro CE concerned for completion of Part 'B' and
Deviation beyond this limit but gpto 20Vo of CA value will r€1tl)mission of the form in accordance with the existing
proccdure in para 379 MES Regulations.
be referrecl to the Project Management Authority, so long
as Overall cost remains within 10%o of Administrative (c) For the purpose of rendition of Part A of the
Approval amount. egmptetion report, each administrative approval, whether
(d) During the execution of the works, as far as It r.lot"t to a phase of a project or to an item of
possible, utty for change in scope of wo.rk or rupplementary work, will be treated separately. These
'ofdemand
designs an{/or specifications. ,will be rcji,tts will be replaced by a consolidated completion report
ietr,rfitting
discouragJd as it leads to interference with works 'A ut the final stage.
progru-L.t and delay in completion of the projects' (d) However, the various phases and the supplementary
iln*.u.t, if considerecJ necessary, the Project Management works, if any, will be treated as one project for purpose
Group may engage Engineers/Architects and other of savings and excesses.
speciilists to review any part of the works project including (e) Once Part A of the final completion report has
designs in order to expedite/improve the implementation hcen completed, the work will be regarded as completed
and/-or quatity of the works in progress or to detail other for all purposes of the MES Regulations although the
technicai req-uirements of the total project of which the tccounts may not have been settled. No further
works may be a part, subject to the condition that the cost nupplementary estimates may be accepted.
of such consultanry and resultant additional works do not (t) The financial closure of the project i.e., patl 'B'
lead to exceed the tolerance limit. wlll be rendered as soon as possible but not later than l'2
Note : The Project Management Group will obtain regular months from the date of physical completion of the project.
reports from the Chief Engineer on the phy,sical and financial aspects n(lx. IMPREST AND ASSIGNMENTS
"constructions-in
of the piogress and report the same to the CFA at
rlgular intervals and alio eisure that rivised administralive approval for making payments to
@ (a) The procedures prescribed
oi tne CFA is taken for expenditure beyond tolerance limit well in contriErs, labour etc. are in the MES
time. Regulations. Cash assignments will be placed by CsDA at
)OryIII. COMPLETION REPORTS thJdisposal of CsWE, GEs and the AGE (if an AEE/AE).
ln the case of each CWE or GE the amount of the
@| (a) On completion of a work, completion reports ussignment will be fixed by the Chief Engineer in
conJultation with the CDA. Within the amount so fixed
[50] Delence Works Procedure, 2007 Oelonce Workr Procedurs, 2007 lsl I
the assignment will be recouped on application to the CDA (b) ln ordcr to dctcrmine the authorities competent
us tteed arises. Generally each CWE, GH and AGE (if an Io sirncti<lrr deltt<lliti<ln under the powers at Appendix 'J',
AEEiAE) will be placed in account with one Tieasury or tlrc lrook value of each building (including ancillary
authoi'ized bank; but, where necessary, the assignment may lrrriltlings) will be taken separately and not the total book
be apportioned between two or more treasuries or vuluc of all the buildings in a demolition statement.
authorized banks. (c) An assessment will be made whether it would be
(b) However, to enable petty payments being made, rrrorc advantageous to undertake the demolition through
CsWE, GEs and AEEs/AEs holding cash assignments may rlcplrtmental labour and the salvaged material used for
be also allowed an imprest upto a limit of Rs. 10,000' In othcr works. Thereafter, the decision to undertake
case of works carried out in remote locations or under rlcmolition as per MES Regulations will be taken.
Para 55 above, this limit of imprest amount to be provided (d) The cost of demolition will be dealt with as a
with a CWE/GE may be further enhanced. The imprest work and any proceeds from the sale or demolition being
will be authorised in consultation with the CsDA concerned dcalt with as laid down in para 828 MES Regulations.
by CsWE in the case of GEs and Rpp5/AEs and by CEs (e) A demolition certificate on IAFW 2201 will be
in respect of cswE. The amount of imprest will be drawn submitted in support of bills in which charges for demolition
from iash assignment and accounted for initially under the 0ppear.
Suspense Head "Departmental Account Military Cash (f) In an estimate or reconstrqction, administrative
Balince,'which should be cleared at the end of the financial upproval to the execution of the service is authority for
year, the balance being deposited into the Tieasury or uny demolition involved irrespective of the value of the
authorized bank as the case may be. The amounts drawn huildings to be demolished.
from the imprest for payment will, however, be recouped XXXI. REAPPROPRIATION OF BUILDINGS
as and when necessary and charged to the Service Head
till the end of the financial Year. @| Reappropriation means the useforof a group of
(c) Outstation Junior Engineer B/R or E/M will be buildings, a building or a portion thereof, any purpose
allowed imprest by cswE/GEs/AGEs (if AEEs/AEs) vrithin other than for which it was constructed. Reappropriation
the limits specified in para 537 of the MES Regulations may be temporary or permanent and may be intended
upto a limif of Rs. 1500/-. These imprests will be_advanced either for an authorized or for a special purpose. They will
und t.tonped by CsWEiGEs/AGEs (if an AEE/AE), as be dealt with as under :
the case maY be. (a) A re-appropriation entailing no alteration and
)OO(. DEMOLITION OF BUILDINGS no cost. This can never be permanent re-
appropriation as the room or building must of
@ (a) The demolition oronsale of any building etc', necessity be available for its original purpose.
for dernolition may be approved a demolition statement
This is initiated by the unit and sent to the local
(IAFW 1819) by the authorities indicated in Appendix 'J', Commander. Such appropriations may be
provided the book value of the building does not exceed approved in writing by any of the authorities
ih. ti-it shown against each of the authorities cited therein.
Drhnce Workr Procedure' 2oo7 [63 I
pcrmitted by the authority competent to sanctlon
[52] Delence Workg Procedure, 2007 Lxpencliture- for re-appropriation'^ Any
mentioned in Appendix 'D' irrespective of the re-appropriation involving change of scales
Capital value of the building involved. Atl UeyonO 5 percent or introducing a new p-ractice
sanctions accorded by an authority lower than wiil requiri the sanction of Government of India'
the Commander of an Area/Corps will be (d)Re-appropriationincludedinanadministrative
reported to him. Each sanction will specif, the approval will not be approved separately on
period for which the approval will remain in fnfW 1831. The particulars including expe.nditure
force and will be communicated to the Controller will, however, bL recorded in the Register of
of Defence Accounts and Garrison Engineer Buildings.
concerned. It will be renewed as required. No XUII. WORKS ENTRUSTED TO OTHER AGENCIES
IAFW 1831 is necessary, nor will the particulars
be recorded in the Register of Buildings. @| The procedures for various works services
outlii6-cfabove are designed principally for use in MES'
(b) A re-appropriation entailing alterations and but it is intended thit they should apply upto- out the
expense : This will be initiated by the unit carried
Aclministrative Approval stage also to works
concerned on IAFW 1831, who may obtain the on behalf of the Mi.rirtry of Defence by outside agencies
assistance of the local MES authorities to advise like State Governments, Central PWD, P&T Railways'
on the best method of adaptation, and sent to state PWD, Port Tiust and such other Departments as may
the local Commander who, if he accepts the tre notified from time to time. In the case of works
projects
proposal in principle, will ask the local MES ..rrtittg Rs. 5 lakh and above, however, detailed plans and
authorities for the approximate cost. The powers ipecifi".ations will be shown to the Users with a view to
of sanction in respect of re-appropriation ensuring compliance with the scales and specifications as
involving expenditure will be the same as laid ,ppr""Jo by tvtinistry of Defence, before technical sanction
down in Appendix D, but no expenditure will is accorded.
be incurred unless funds are available. All
)OO(III. GENERAL
sanctions accorded by an authority lower than
direct
the Commander of an Area/Corps will be [G6l| The MES formations may resort -1o
reported to him, Each sanction will state whether pur.fidof stationery and office equipment for. all engineer
post
the re-appropriation is permanent or temporary activities such as pre-Administrative approval planning,
and the period for which it remains in force and administrative approval planning and maintenance services'
will be communicated to the CDA and Garrison ihe office equipment includes typewriters, intercom equip-
Engineer concerned. It must be renewed as ment, calculitors, electronic stencil cutters, dictaphones,
required and the particulars including expenditure tape'recorders, photocopiers, copying machines' franking
and
will be recorded in the Register of Buildings. machines, addreisographs, filing ind indexing systems
(c) Re-appropriation involving minor increases in lor.rpur"i, includin! peripherals/software. The list of items
scales upto 5 percent of the authorized area
necessitated by constructional reasons can be
[54 I Delence Works Procedure, 2007 Dllrncs Works Procedure' 2007 [55 I
new major work so long as the latter has (i) Authorized percentages for maintenance etc"
been administratively approved and where laid down are in no case exceeded'
Engineers
released for execution by CFA. (ii) All Transfer of Funds made UV C!11t concerned
anO CrWi are reported to Service
HQ
(iii) Between a major work in progress and a
No Transfer of
new major work provided the latter is before tJ Mutttt at the latest' t-his
Funds will be permissible after date'
administratively approved and its cost does
not exceed Rs. 15,00,000. (c) No other transfer/re-appropriation will be allowed'
4-2 5. General
is., spread
Sub-para (ii) and (iii) above are subject to the condition It is of great importance that expenditure possible and
that the new work is included in the annual works .u.r,ly over tf,e ;;titA-t during which work is
programme and is administratively approved. every effort must be made to avoid a
rush of expenditure
at the end of the Year'
162 I Defence Works procedure, 2007 Delence Works Procedure, 2007 [63]
6. Acquisition ol Land
APPENDIX 'B' (Para 22 Refers)
(a) Funds on this account will be provided for
by ROUGH COST ESTIMATE
respective Service HQ Major ge'aO 4076_Capitat
.unde1
outlay on Defence Services, Sub Major Head ,0i, Ar*y, STATION
Minor Head 050-Land,- Sub iVlajor Head 02_ Navy, NAME OF PROJECT
Mino,
Head 050-Land and Sub Major Head 03-Air eoi.!,
Minor
Head 050-Land. s. liem of Work Basls ol Cosl Remarks
(b),Budgeting and accounting of funds No, Calculation {Rs.l
... . under this Head
will be d_o-ne by DGDE as per insiructions of the concerned (a) (b) (c) (d) (e)
GOC-in-C 25
[68 I Defence Works Procedure, 2007 Oelence Works Procedure' 2007 [6e]
N.B. : The items of work in this form are appropriate
APPENDIX 'E' (Parp 29 Refersl lor a building Project. The items may bevaried as necessary
APPROXIMATE ESTIMATE lor other projects.
PART-I : Abstract of Cost
Basis of Cost of
STATION.
lternFln-Ihe Abstract o1 999!
N.B. : (a) lnstructions for preparing this Memorandum
NAME OF PROJECT. will be issued by Engineer-in-Chief.
BRIEF PARTICULARS OF WORK TO BE DONE (b) ln Part I of the approximate estimate a ;;ote
Iteme of Work Cosl Remarkr
*1ll bb given against the provision for each item of work
lndicating the percentage added in part ll for variation
Srl.
Na-
1. Cost of Land of rates.
2. (a) Surveys and Soil lnvestigation
Note : For AEs for MoD Establishment worlcs, establishment
(b) Site Clearance and Development
cost will not be inciucled, howeve4 for deposit worlcs
it will be
3, (a) Buildings (including internal water supply and
electrical work) included.
(b) lnternal Sanltation
(c) Air-conditioning & Retrigeration
4. Furniture
5. Special items ol work
{to be detailed in Part ll)
6. External Services
(a) Roads
(i) lnternal
(ii) Access
(b) Water Supply
(c) Electric Supply
(d) Sewage disposal
(e) Area Drainage
7. Arboriculture, if any
8. Gonsultancy, il any
9, Contingencies (3% on item.s 1 to 7 above)
10. Establishment Charges
(limited lo 2'/" on items 1 to 7 above)
11. Railway Works
Grand Total
(a) Time required for physical completion ot works
under normal circumstances from date of
administrativa approval.
(b) Time required lor physical completion of works
ll carried out as o€r Para 55 of DWP.
[70 I Defence Works Procedure, 2007 Dclence Works Procedure, 2007 [71 I
N.B.:Theitemsofworkinthisformareappropriatelor
abuilding Project. The items may bevaried as necessaryforother
projects.
DeJence Works procedure, 200? I{ :f"i
,v tr
Defence Works Procedure' 2007 J
Part B
COMPLETION REPORT FOR ORIGINAL WORKS 8. Completion cost Rs""""""'
approval""'
Head of Account. 9. Percentage of excess over administrative
Name of Area....... 10. AuthoritY Passing the excess
Division 11. Certifiedthatthefollowinghavebeencompleted
in resPect of this Project :
(a) Record Drawings of buildings'
Part A (b) Periodical Sewices Measurements'
i.j rut"tution of Cbntt' Plan where
necessary'
1.. Name of work....
(d) Completion cost recorded in the Register
of
2. Authority according administrative approval and Buildings.
amount.....
3. Total amount of Technical Sanction
4. Date physically completed Date.......-....'..AGE
5. Recorded expenditure upto (4)............. Date...............GE
6. Estimated amount of liabilities outstanding on Date...............UA
(4) ...... Date...............CWE
7. Certified that the necessary entries have been
made in the Register of Buitdings/plant Record
Bogk (in the case of furniture, certified that the
articles have been brought on ledger).
Station
No............. ..............Dare............... .. AGE
Forwarded to CWE through U.A GE
Forwardefl to CE CWE
Fonvarded to E-in-C CE
Noted and returned to GE E_in_C
CE
CWE
[76] Defence Works procedu re,
ZOOT
Government of lndia
coAs/qNs/CAS
&.{Au
F dd""d"i
AND SCRUTINY OF ENGINEER DOCUMENTS1
RESPONSIBILITY FOR PREPARATION (RuPees in takhs)
GE AGE GE GE
AGE
ryh
l88 l
t8eI
aDorox' 12 of 15 lakhs
tenance works to the extent.of
(b) No operational work will be sanctioned by.a formation involving phvsical
in a year. Tifi;;;Jn"fuO"t
tdsi<s
commander bdlow the level of a division commander. thos'e jobs
execution cli"t"tt-' 6ti does
not include
(c) The above restrictions will not be operative during which in rirre -and
of stores and equipment
actuai hostilities or when hostilities are imminent, when full "ofi'putrttase
such as generatois pumping sets'
' "' \ animal
-:
powers may be exercised by all commanders vested with powers (d) ,*re a,,aiuffi'lft"ut"i (troopi and civilian)'
io sanction operational woiks. On termination of hostilities, the and mechanical transport, stords
and equipment must
procedure laii down in Section 7 of Works Manual (War) India itself'
be plannef- ui-tt'" pfanning stase
iggs *ilt be adopted lAuthority : Army Headq,uarters No' (e) The hirini o'' u"qui'ition--of iand should also be
A100965/Q3W (Policy) dated 09 June 1977 and Army_Headquarters tutu*t"t General staff before
ur""r,u,n"'5 uj tn" Er"ii"i
Ietter N;A100955/Q3W (Policy) dated 15 Jan 19751.
the operaiioial works are sanctioned'
Purchase of StationerY. Schedule of Demand
28. There is no provision under the operational works
procedure for purchase 9{ s14i-qnery - lAuth ority ^: . Army -!ead' Operational Works the demand for new
quorttrt lener No. B\S7SS1\QEW (Policy) dated 04 lan 19771 32. The formations should"a;;dlproject
stan loperations)^ l:lntn'
Time for ComPletion. ooerational works ilIil" each veir as per Appendix
ofs"p'"Tp".t
"ti"irtt- *fltuld be tisttio in tieir oider of
corps headquarters ":y
29. No operational works should extend peyond two working
seasons. If a major or immediate delay' is envisaged, corps 'A' attached. The
headquarters should be informeg eivi^ng the reasols .for the nrioritv.
t"'"^*r3. will scrutinise
The General Staff (operatiot ns) branchwith the chief
delayindicating revised pro_posed^ qlrte of comple-lio.. lAuthority : in coni,lltation
Army Headquirten letteV No. Al109syQ3w (Policy) dated 15 Jan the demands of th;-ib;;;ridnJ th" Cotpt commander for
1e7sl. Engineer ana win''pJi';ffifip;;
uppto;;] branch will 'forward
The General Staff (operations)
SECTION-4 : PIANNING OF OPERATIONAL WORKS
the final list of n,r-*u", of oleiationut
iuort approved by the
Corps CommandeJio Ciuu't"r^
Masterbeneral Bianch (Works)
Staff (operations) and
Planning PersPective wrro wlr forward ,il; ;#'i;.G11;t"i
30. A three year plan for operational works should be Quarter Master G;;;tj'B-'"*tt
Ol^tworks)' bommand Head-
drawn up for the corps sector on a roll-on concept. This plan quarters by 10 o;;;;^;"J't"ttl Cbpies of demand will also
^the corps headquarters
be forwarded to ;;g;;*r ;t;;;h
at
should de made at iorps headquarters by the General .Staff
lOoerations) Branch in ionsultatinn with headquarters divisions and to Divisions'
)nd tt Chief Engineer and should be approved by.the Corps 35.Forworkstobeexecuted..byagenciesotherthan
ctriet' engineer.will'con"sult them
" regarding
Commander. Thisllan should be reviewed periodically to cater formation by them for
for changes due to financial constraints. "rgin""ii
the approximate ;"';;^;ii *. t*" required
f f. iVtrite planning operational works, the following will siarr (bperations) branch
compfelion, b"foi""'th; G";";;r. headquarters'
be kept in view :
(a) Type of work should be restricted to those mentioned
ffilj5ffi# G;""d
Grant
to Command
Maintenance
in ParagraPh 3, Section 1'' 36. Chief n"gin""' Cgrps will fonvard the demand for
-cointnuno
(b) headquarters through
\ / Only thise works to be-planned and executed under maintenance df;'; in the first'week of October
opeiational works procedure-which cannot be executed Quarter Master Etn"ti $;ii;
under the Defence Works Procedure' each Year.
(c)
\/ The quantum of operational works sanctioned and
planned to be execuied should be within the- capability
bf tne engineer troops. As a rough yardstick one
engineer rEgiment can execute operational and main-
te0 l lell
rcquirccl 'by thc:
40. Publisb aPProved ratcs fclr civil iabtlur
SECTION-S : EXECUTION oF OPERATIONAL WoRKS cnuinccrs.
'"""';;:"ioonitor the progress and ensure proper utilisation o['
Pollce Enquiry Central Bureau of lnvestigations Etc. taken over to include the following :
81. All such cases will be deait with try the fbrmation (i) Administrative aPProval'
headquarters concerned and progressed through Adjutant (ii) Technical sanction.
General Staff channels. (iii; nuOg"t allocation, yearwise' , r - t\,^^-
82, At the time of turnover of engineer regiments, fuli ii"j bltiits of expendiiure incurred to date' (Year-wise'
details of all pending cases will be obtained by the Adjutant m case *;t[I;;pread over more than one financial
General Staff branch of the division headquarters" Division year), booking U,y itre. Controller.of Defence Accounts'
headquarters will instruct the relieving engineer regiment to iiuuiiiti"t witfi their latest position'
deal with certain cases after handing and taking over and instruct (v)
\'/ Details of storesovcr procured, incorporated and.balance
the relieved engineer regiment to hand over records/elocuments *tor"u handed with cost' Condition of stores'
plant anJ- machineql handed over will b: i"
pertaining to such cases. :?jl::t"d
giving their
83. In case of doubt, divisi<ln headquarters will ref'er the tn" r,unoint-;a tdring over documents
case to the Adjutant General Branch of Corps Headquarters locations.
and obtain a ruling on the subject, well before the turnover of (vi) Or.rtstanding demand details'
relevarit correspondence connected with opera-
engineer regiment.
84. Adjutant General Branch of Corps Headquarters inay
' ' eu
iuiit
tional works in their area of interest'
seek the advice of the Engineers branch or Quarter Master (b) Maintenance Stores. These will be handed and taken
General (Works) branch as deemed fit. ou"t bti the basis of survey board proceedings'
85. Reports and returns and replies to querries on the (c) Operational Works Physicatly Completed But Flnan-
strbject will be submitted by the Adjutant General Staff, at all cially Not Closed.
" (i)
levels- \"' Conv u"* o[ board prclceedings based on which the asscls
tt^r? i.t"'n over b/ the user units and entered
in numerical records'
t1041 trOsl
(ii) List of liabilities on account of which the costruction
CentrallY Procured Stores
account has not been closed by the Controller of -Ctti.f
90. Engineer of the Cgrps will be responsible t()
Defence Accounts with their latest position.
(iii) Expenditure incurred and booked by Controller of' take provisioning a-ction for the following storc"s-
Defence Accounts till date (duly reconciled). (u) Cement
(iv) Surplus_ sto-res, plant and machinery held, if any, on (b) Steel
the order from Chief Engineer, C6rps or Commancl i"i Corrugated or plain galvanise<l iron (CGI or PGI)
sheets.
should be disposed off by the relieved engineer regi- surface (FBS) rolls'
ment and not handed over to relieving engineer re[i- (d) Frefabricated bitumenised
ment. (e) Bitumen'
(d). Surplus Stores, Plant and Machinery. All surplus (0 lixPlosives
stores, plant and machinery will be listed job-wise (this does tgl Generators or any other Plant'
not include those stores mentioned in Paiagraph (b) to (c) (h) Paints
above, which will be listed separately for each job).-Thci foilowiirg 0) Alkathene PtPes
details pertaining to all surplus stores will be furnished to the Procurement
relieving unit : qf. (a) Cement : The engineer regiments ih?l1d-f:Ii:1
(i) Operational task number against which they were ttt"it qrrutioly forecast demand of cemcnt to reach thc b'ngrneer
procured or released. 01 April' 0i.Julv and
(ii) #;.t;;pt'tt""oq""it*t uv-pl {Tuury' wiii forwarci
Source and date of release/receipt order number an<J oi-d;i.b"i each yA; iht'cni"l !1gine5r -cu1pL Cement wilX
consolidateO OemariJ io-G ,onat Chief
date. Engineer.
(iii) Cost. ;;';;l;;JJ uy tt" lo"ui chief Engineer.s fiilrn rtre stocks
available with engiir""i furU. Corps i;i'rl.t
(iv) Survey board proceedings giving condition of stores, Engi'ccr.will srrb
plant and machinery. regiiircnls based ort
allot the cement t"'-lfr. &visi.nal engineer
87. A copy of the survey board proceedines will be -"-.. forecast demands' pGI
their
lqld by the staff at the division heldquarterf and thc steer ccr anJ Sheets : cn i.irc i:asis uf .perational
-ftoi""t"C
abt t:'],'':i:l:"assess
Chief Engineer Corps. *otrc tt iommunO, Chief Erreirillr atiLl t'orward the
88. Any shortcoming or irregularity noticed by the division the approxi*ut" ,"quii"*"nt'o[ these sti.;ru5
[o lltc comrnanttr
headqnallsrs at the time of handing and taking over, will be demand in the ro"in= oi No""mber or Deccntl-ic.:l
i'1;i'c'liirl'uly' .n
regularised under orders of the Division commander. One full A;ffi'ilfiLo f* tuting provisioninu :tctic'ti.
project
set of handing and taking over documents will be forwarded sanction of operational rioiks, engine'er rc:ginrc::'-s.will
on D-ER (F) Forrn l"Jurnber 1 to
by the division headquarters with the remarks of the General ;;;rrd 6f tn"*" stores
i'nti ftrrwarrl the
Officer Commanding if necessary to Corps Headquarters General Chiet Engineer t"6; ;L;-;ill scrutinise ihcm
Staff (Operations) ind held with the Otri"f Engineer. demands to E-3 section' with cr:py. to. eonal Chief
"o**ind,
i;i";;r. O"p"nOing-upon the avaiiability wiihin tlte ccrnntand,
hranch comrnand head-
SECTION-11 : PROVISIONING OF STORES, il:;';;;,[ r,iiir u"'i*"'"6 by Engine.ers avallable i:l stock. 'Nct
PIANT AND MACHINERY ouarters. ln case stores are not ieadily
H#i;tl;'"?ffii wil "
be issuect ro rire cngineer
""iriii"ut"r
J.h;;;;t, Ctti"r Engineer.corps i'vill undertake
Categories of Stores Ail;;;t. i; enquiri"*. nft"t the fiialisation irf the quotations,
89" The stores required for operational works mainly fall to float trade
name of ttre approveJ firm will be intimated to the Engineer
under the following two categories :
irJii*"",--"r..1
'b;;;ry conrroller of Dct'ence Accounts. The
(a) Centrally controlled stores.
engineer ..g,."ni,"iuiil itt"n place the
supply orders on that
(b) Stores to be procured locally by engineer regiments.
firm.
11061 tr07l
(c) Bitumen and Explosives : The engineer regiments .A t.g a
should intimate the approximate requirement of bitumen anci o p-6
o o:o.
explosives for the following year based on projected works and G, 5b
the boards convened for maintenance grant. This requiremenl N aP
*o6
should be forwarded to the Engineers branch (corps) by 10
cl) g6p
5= O
.!
January each year. Chief Engineer will scrutinise the demands l!
and forward the consolidated requiremcnt to command to take o.
provisioning action. Stores will actually be procured or released
by the zonal Chief Engineer on order of Chief Engineer :l
.! :l
command. E ol
o NI
(d) Generating sets, Pumping Sets, PBS Rolls : These tt
stores fall under the category of controlled stores and are T' I
f--rCHir.
O iD v 6
I I or: ;5<Er0H
€=.-Fe,SE *L-o'_ ^.)O
f$t +: #;ST *HFH:' :
;;6 6- o gH
ttoo
E3g[r[i$;$;}FFiE *s
o
fe;s+s1Hg
-;5 za
-rE7 >x
09
;;:r;l;gqE; r,:s
zfx9
I=
iEaas = ga
i .=$; F
g
o =6
gF
rlEFH
ao
F F
33FH s ti
fg Fi$Fff5#iiii$F
3; $sH +Fx;sF:'r[55 iFS-3 EF
I o {= r io'o
99-Al O
F
g
'd3
I I€
I ;is
:=33?AoxDF
rE;
lF5g
D
o
o
o
o
E i:r;
X=id.=
X Ai o.r
+s. '6' "edo
I
8.5 N€ A
Sl. No. Job Number Brief des- Amount Work Specific Progress Amount Tasks plan- Remarks
cription of allotled Commenced conslruclion since work expended ned lor lhe
work and lrom carried out starled ensuing
probable during lhe month
dale of com- month under
olelftrn {PDCI review
arl tbt (c) (d) {e} {o (q) ft) fi) &t
(a) Any problem of stores supply?
(b) Any problem of unskilled hands?
(c) Any other bottleneck?
o
\e
Appendix ..D" to Addenda lll (para 64 Refers)
MONTHLY EXPENDITURE RETURN FOR THE MONTH
OF...
Expenditure on Total
purchase of stores expe n-
against book debit dilure
New Operational
(Para 76 Rerers)
rlArNrENANcE PLAN oF AssEr:.-c.ryEA#3"3#
wonKs pART r FoR THE ;' ;?#i;,T^:^rrr
veanzo 20 .....
Formation :
Allotment ;
NOTES:
1. Total cosl of repairs n Part I should
not exceed ZS% of the allotment during the
2. Format for Part ll is irnilar io that of part l. current year
3. Abbreviations used (a; BrR-Building and
:
Roads.
{{) ilM-Electricat and lVlechanical.
The powers of Engtneer authorities for according Technical Sanctiog entering into contracts, purchase of stores
etc.'
are given in table below :
E-in-C C.E. c.w.E. G.E. AEE Vc s.D.o. Remarks Reference
Item Ilescription of Work
No. etc. Inde sub AE/AEE to Paras
div.
1 2 3 4 5 6 7 t 9 10
1 Technical sanction ln mt
resnect of:-
*(a) Major works (including F.P. F.P. 50 lakhs 15 lakhs 2'5 lakhs Rs 50,0fi)
Sub-projects and Minor
Works\ N
i5 2'5 lakhs Rs 50,000 ('l
(b) Maintenance of build- F.P. F.P. F.P. lakbs
ings communications,
etc., and maintenance
and operation of in-
sfrllqfinn<
(c) Purchase, manufacture F.P. 7'5 lakhs 2 lakhs 0'75 lakh 40,000 Rs 7,5fi)
and repair of tools and
nlenr excent (d) below
'(d) of 2 lakhs 40,000 7,500 4,000 Rs 2,000
Purchase camp F.P.
equipment or furniture
and equipment for MES
offices and Inspection
Houses.
tpo*,ers (woRKS-n) MoD (F) Uo No' 28&WII of 199'
enhanced vide case No 95533/PoL.tE2w (PPC)ll39fD
(e) Manufacturing F.P. F.P. F.P. These apply to 886
iopcratlons manufacturing
operations carried
out under the rules
for *'orkshops. (see
nlsn Annx K\
2 Enteriqg iilo F
ffies, indrrtqg
ortracsfabcalmatshe
ad oettv $m[€s-
'(a) Through compgtitive F.P. F.P. 50 lakhs 15 lakhs 2.5 Rs 4?3,746
tenders lqLhc v)(m 934
6:0 0-25 432 N
'(b) fhrough single tender 60,1125' 251t25* ot
lakhs lakhs lakhs lakh
'For oroorietarv items only.
4. Elccttion on the basis F.P. 3 lakhs 75,000 30,000 9v
of' trade quotations, of 955
retreadi4g of tyres zas L and of such repairs to plant and machinery (including vehicles) of MES repair
are beyond the capacity responsibility
of local MES facilities
or are urgently required
dd $/herc dday is
detirctalopltbser-vftr
lro*.rs enhanced vide case No 95533/POIJEZW (PPC)/139/D (WORKS-II) MOD (F) UO No. 288AMII of 199.
zPowers for items 3, 4(a) (D (ii) & (b), 5 (a) (i) (iD
G) & (c) and 6 (a) & (b) enhanced vide MOD No. 4/03108/
ESP-1 (P & C\t?S7tDO IVD (w-D dateA n43-99.
requirements
'Po*"r. for items at 4(a) (r) (ii), (b), 5 (a) (r) (ii), O) & (c) enhanced vidE GOI' MOD ,n17f,tftt16/EsP-1 (P & Cy
zrltDc.-ll D(wJ) dilea n43-9-
(ii) i" emergent cases F.P. 3,00,000 2,25rffi L,00,000 60,000 7N
when delay is
detrimental to Public
Qcroice
(b) Storesfor which DGS 20,000 20,000 z),000 12,5ffi Not exceding 743
& D rate or running Rs.1,fi),000/- in
contracts exist when aggregate in a year.
these are urgentlY
required or can be
more convenientlY
obtained locally or from
neiuer station.
(c) 4,000 2.000 5'%.747
Cash Purchase Powers
6. Disnosals of- N
(a) Surplus buildings sanc- F.P. 30 lakhs L5 lakhs 6 lakhs Amount represent the 160, 163, o
tioned for demolition total book value of tffi
assets in any one
camp, sot of lines or
installation put up for
disnrxel
\uLhoriti
Nots-
ne>d.higher grade by
1. The powers of the holder of an appointment may be incrgasgd by name upto that 9f. the-
the cwE in the u GE and an sDO, by ine cE in the case of a ewe and by the E-in-c in the case
of a CE. "u."-oi
in such cases a report
1 The normal powers of an officer may be r-estricted- by his i{Tediate {ES superiol but
o'uit U" made to the CE io ttre case of GE's, and tb the- E-in-C in the case of Cs. W'E'
.3. An officer officiating i" - *ill ei'erclqe th9 q! powers of the appointment 'as
given in this table'
4.
"pp"i"t-"nt
ll-Ce -"y-afi;d;f hir Jliretion powers in full to DCEs-wothg
l_od:,1
his jurisdiction'
The E-in-t may"delegate his powers in full to the officers codcerned on 5's stafi by
name.
5.
powers under cotum""i;J;;;;fuii."bl" ulro to military officers of eq}ivalent.rank holding the appoinrments.
6.
are carried out
7. il-oi["|. uutLorir"a "d"; ;; upiri"uui" in all cases on whosoever behalf the works, etc.,
by the MES. E'-
8. The E-in-C and CEs have full powers in respect of purchase of books, newspa-pers al-d -periodicals; -C-1'^$'
and GEs may purchase books,' n"*r_pup"rr-'"1 pe.iodicals to the extent of tRs. :O0O].,.. and [Rs 1500']" per
-
India will 6s armn8ed by the I
annum respectively. i;y-;;i for publicitio".-out.il"a direct from firms outsidl purchased-
cDA. This rule does?;;illy 6;;h'ii;;r ui et"u, Sub-Area or Station orders which may be
as required.
orrt""1r c"--anding ESDs u'ill exercise the following powers under this Table: -
Item 1 (a) 1-5 lakhs 5 lakhs Powers under irem 1(a) will be delesated bv T
the authority competeii'to t""[oi*ffy"r-aioi
the project as a whole.
$
Item 1 (b) F.P. 5 lakhs
Irem 2 (a) 15 lakhs 5 lakhs
12. The p_ower for emelgent cas-es_ for the direct purchpe
9f stores vide item 5(a) (ii) will be exercised only when
immediate non-acquisition of the stores concerned is likely to hold up a work or when delay is detrimental to
the public services. These powers will not be exercised to replenish stocks of items of Divisional stock.
Direct Purchase also includes job works like "Repair work Orders/Fabrication Work Orders" but excludes B/R
and E/IVI works which are required to be got executed as Minor Work through the Term Contracts.
Powers.enhanced vide case No 95533/POL1F,ZW (PPC)ll34glD (WORKS-II) MOD (F) UO No. 288/IWI of 1999.
o
o
o
o
z
9
TD
G)
N
@
5
$
o
(r'
€
t
9.
o F
t(,
o.
D
o
CL
o
(-
o,
5
@
ct)
t1341 tl3sl
in each station. Preferably, a Board of Officers should c:roabilities. limitations and constraints of the MES' Quite o[tcn
be convened for the purposc" A conferencc should ;;[;r"'i;;'i" n,"t" calls beyond the resources of MES and
then be held by the Station Commander with the GE rh;;;"i; decry the tvtgs rlvtren these are not met' In an
or AGE, the unit Commanders and their QMs to cnuironment where mutual confidence between the users and
discuss and finalise maintenance programme for the tft" riuti"n authorities on one hand and the MES on the other
il l;kt*; neither can the MES personnel give. of their best
station as a whole on the form attached. Priorities -
will be allccated based on consideration given in the nor thos1 among them who are negligent, rude ,or . insofell
subsequent sub paras. brought to book-simply because there are glaring shortcomtngs
(b) Priority - 1. Works required for ensuring structural on the part of users also.
scundness, enhanced life and utility of Government pf ft is perhaps not.known to a large. number of ,users
assets as well as safety of these assets against damage that maintenance wbrks bills are not passed Uy llt auditors with
due to natural or unnatural causes. tunless these are accompanied by the users certificates
(c) Priority - 2. Maintenance and repairs necessitated for rcgard to lhe completion of the work'
ensuring a high standard of hygiene, sanitation as also (c) Most users are neither conscious of their own
providing hazard-free and secure occupancy to users. ,"rpoittibilities towards maintenance and up keep of Government
(d) Priority - 3. Periodical services. ,,rritt no. have any qualms about misusing/ne.glecting government
(e) Priority - 4. Items which might have been left from niit"ttu. To bring' about awareness in ttiig regard,*E-in-Cs Domestic
the previous years maintenance programmes. il;il' i"*pt f"i N".. 14-Hints on Care and _Upkeep. letter No-
(f) Priority - 5. Other general repairs and maintenance. Accominodation was issued vide E-in-Cs Branch
llj++/Oom AccnlE2-A dated 17-9-73. The following are some
6. Similar action will be taken for the formulation of
maintenance and repair programme in respect of furniture. lvpi"ui examples of disregard towards upkeep of Government
7. In preparing -maintenance programme and alloting '- by the users : to sanitary fittings gl *utf. hand basins
twsets
priorities in a station, adequate attention will be paid to the \ / Undue damage
1i)'
genuine equitable needs of all units. and WCs duE to rough use or mishandling'
8. The programme should clearly, lay down the priorities
(ii) of stop cocks,- man-hole covers, float- valves
\", Theftrro*
of work, the allotment of funds, the time by which the buildings wittrin unit premises. This besides reflection
"rln
onlackofsecurityconsciousnessintheunit,results
or furniture will be handed over to the MES, and the time of
commencement and completion of works. It would be apt to in waier, careless accumulation of water
wast^age of.
earmark some funds and MES effort as reserve to cater for on roofs*causing seepage *thein walls and dampness'
any unforeseen requirements. (iii) Forcins sarbage" down kitchen and toilet drains
'---' o, theieiageiystem resulting in choking of the same'
9. The maintenance programme for the entire station,
unitrvise for the ensuing year, will be drawn up and published (iv) Indiscrimina"te driving of naiis in walls thus spoiling
in station orders by end of January. Based on this MES will the Plaster and colour wash'
prepare a work programme specifuing for each work, the agency (v) Chopping wood or hammering things directly on floors
and resources including time allotted. Maintenance programme therebY breaking the same-
once issued will be adhered to strictly unless there are compelling (vi) Non-cieaning of-roofs or terraces before start of rainy
reasons for change. seasonordu*ringtherainyseasontokeepwater.spouts
10. Inspecting officers should also check the maintenance and drain dowi pipes ciear of refuse and diit'
programme, their execution and record their findings in their t ' Unauthorised to
(vii) electiic.connection thus causing exten-
reports or tour notes. sive damage wires, switches and plugs and very
11. As regards the role of the users, the following points often, resulting in fires.
need emphasis : (viii)Misuseoffur"nitureforpurposesotherthanwhatit
(a) The users are generally not fully aware of the is meant.
g RqP*et 5q{g-izP
;utat3tg,*aF5FE;,
i # ?;cs Ft+fE:E s$ ri f
gAlas is
; *;rgscg og-Y:$AT
*;3r'>313
: P E = s eE T tsrA$B E
EHFEH6;: s*hF$os
i.iflEiE [i il:ili 5
iH E$lrE 3 slii;;r
zo*#,f;
f,*EIiaf
a r1;s*b eEse$i;
;5 +gig$f
.-l+lEaEI
a{iniIt
c =c-= =','
aE3-3€FH
=-4<. c-- :-c
Note_l.lnthefinalrevisedmaintenaceprogrammeGEshouldindicatethefollowingunderB&R,E&Mand'Uniture:-
(a) Funds demanded
ioi Punas received
(ci Funos allocated
(d) Balance should always be indicated rather than
specific building Nos where rewiring is planned
2. Aoainst E & M maintenance programme the
not reft vasue'
..'*f.t$fl"il il"f;", or charpovs ror-lTtljlgj:g fl1,."X'lL9#T'[i"'Jft'trf,'f9ru1"?;li
4. Number of charpopchairs/any n"rn oI t"ni*iE ti'l"'ilfu'
1138 1
Il]el
work' etc' not
Two coats on all wood work, iron portions
Every
Normal Periodical Services [Table 'G' of RMESI I three Years for all buildings/ except
"iit""*i""--tt"ut"J
lnternal and External Lime washing (white or tinted) lnternal inting and oili
Haltyearly Pantries, cookhouses and other buildings or rooms iron work' wall sur{aces'
Every two Onb coat on all wood work, treated
where food is dealt with, bakeries, grain stores, foul- years ;;iru;;"* otrre*ise for followins in
linen stores, mortuaries, latrines and urinals. hospitals :- ^ot
W?fi'., Op"ration theatres, Specialist consulting rooms'
Yearly All other buildings except store houses in general bu l\il ;;iti"6-rooms, Admn offrs rooms' Labour rooms'
including Medical and QM stores of hospitals.
etc not otherwise
Every two Store houses excluding Medical and QM stores of Every two One coat on allwood work, iron work :-
vears hospitals. tieateO for following
-.""it'arv, in hospitals
Fiiiiiit, i'c,ui-rinen' stores, . cook,houses and
Distempering (including whitenlng of ceilings)
Liii"i'l, o g./'ijo' J *hele lgggjg i eglt lrylh'
ir i
"
Yearly One coat of oil bound distemper for hospital wards,
One coat on all wood work, iron.work etc not
otherwise
operation theatres, Specialist consulting rooms, Ml tieateO for following in hospitals^:-- L-!L
waiting rooms, Admn officers rooms in hospitals, Labour
Affi;- Buildings eicJpt Ad'mn -officers rooms' bath
rooms, Dental Surgery and X-Ray rooms. ;;;;, oi.pd""tiw, uboratory, Mortuary' Medical and
Every two One coat of size distemper for Offices, Schools etc
years or Wvo coats of distemper where one coat ls authorised on allwood work, iron work etc not otherwise
One coat'toi -irt
every year. iij"t6o nuiroings/portions except
those
Every four Two coats of distemper where one coat is authorised
years every two years.
Tarring and treating with wood preservative
Unit cookhouses.
Yearly Dadoes of stable (to be tarred)
VARIATIONS
Variations of the intervals laid down above may
Every four Huts, fencing and other external work (to be tarred be
years or treated with wood preservative as the case may
made as follows : -
may be distemperecl half-yearly if
be).
(a)
\-, Hospitals wards
Yearly One coat on all wood work, iron work, etc hot t-quitition"d by the OC hospital'
otherwise treated for following in the hospitals :- have
Wards, Operation theatres, Specialist consulting roorns,
(b) Rooms in trospitats in which inlectious diseases
thc Medical
Ml Waiting room$, Admn officers rooms, Labour rooms, occurred rn"li-i"ft"i disinfection .by
authoritiesj bL iedistempercd' repainted .etc
on the
Dental Surgery, X-Ray room, Pantry, Sanitary, foullinen work
stores, cook houses, and other bldgs/rooms where certiticates- .i t- offi""t lhat the is
1995
I Para 121 , Ein-C Standing Orders'
[142] t r43 li , 3qq;
. , .,
,.r\ \
Addenda VI will then be carried out in accordance.,with.ttre normal pro.-c€dulc
obtaining in the CPWD/State PWD:iThe expenditure will'.be
RELEVANT IMPORTANT ORDERS/ DECISIONS/CIR. incurredl by these agencies and audito4,;.bJ ltheir, -ig$pective
CULARS Accountanis General who will act as Sub4.udit.'Officers of
1. construction of roads with specification of class 9 and GDA concerned. No payments will be made in cash by the
above- is not permissible under operitional works p.o""au.*. Defence Officers in such cases.
. .^^^/$fqg4F_: po1,1, oI India,- Ministry of Defence tetter No. /Authority : Govt. of India. Ministry of Defence No-
At009ss/Q3w (poticy)lg4[Stso_rilD 1W_j cit, zi.z:.aa.1 Al00g55lQ3I4t (Policy)lLg72lslD (Worl<s-I) dt. 4.1.61 olq 4HQ,
2 The term 'road' includes tracks of all descriptions. QMG's Branch letter Na A/009551Q3W (Policy) dated 7.2.621.
6. Powers to sanction works
. ^/4"-t^tgrity : AHe E-in-C Branch No. S95It/il/Q2Wl Esu
dt. 21.7.60.1 The powers of sanction of Operational Works as defined
Commanders are unlimited at qry199t.
3. shelters have beeh defined to be constructions whose - 3 above by
in para
:
design should be on the lines of local village practiie using lAuthority AHQ, QMG's Branch No Al00955lQ3W
materials procurable locally. They should pioviie reasonablc (Policy) dated 7.2.62.1
protection against the elements fdr atleast d hot whether or a 7. Maintenance of Accounts.
monsoon. The Works and Field Units operating Supplies and Services
The actual floor area per person to be accommodated in Imprest will maintain a simple imprest account (IAFA-821) in
shelters should be decided by. tli.e Goc concerned. The target which will be posted cash receipts and payments. The imprest
is the least possible accommodation compatible with ieasonable account (IAFA 821) will be closed on the last day of each
comfort and protection from the elemeirts. In no case should month. The imprest account duly supported by original vouchers
the accommodation provided exceed the scales laid dtwn for will be forwaided to the CDA by the 10th of the month
hutted accommodation. following that to which it relates for audit and adjustment. The
vouchers will be allocated by endorsing thereon the job Nos.
. lAuthor.ity : _!_haptel II Scales General page l0 Scales of
Accommodation (War) 1944.1 and will show the authority for expenditure i.e. number and
4. The term "operational and rechnical" accommodation date of the order of the competent authority sanctioning the
cov.erl any construction o{ qoye, for carrying out repairs to work. All vouchers will be embossed with the field operational
technical for the ronhuJt of op6iations. works on the top right hand corner. Each entry of the receipts
.equipments required
-
and payments in th-e cash book will be serially- numbered for
Such works include :
(i) Constructions of bunker. each- month pertaining to each cash book, the same serial
(ii)Construction of Command posts. numbers being assigned to the vouchers etc. duly marked with
(iii) Construction of Communicdtion centres. the Imprest Account Number.
(iv) Construction of advance main dressing- stations. The specimen signature of the Imprest Holder will be
(u) Construction of shelters for ammunitiots, ,"ppii., forwarded in triplicate to the CDA and the TreasurylBank
and stores. concerned for reference and record.
/Authority : He, EC No: 2562971e3W1(poticy) dt.27_t_621. The procedure for the maintenance of imprest accounts
5. works ordered on other- agencies viz, will be analogous.to that laid down for Field Imprest Accounts
^___ _Operational in the Pamphlet 'lField Imprest Payments Instructions']
. CP\4/D/State PWD.
places. y!9t" no MES organization exists, the execution /Authority : Para 2A(ii) of AHQ. E. in C's Branch No-
, of operational Military works bE aho may entrusted to other 38935182A dated 1-10-51 l.
a'gencies i.e., central plutic works Department, the State public 8. Construction Accounts (By MES)
Works Department. ' When operational works are ordered for execution by
These^agencies will undertake works where orOer.d by normal GEs of MES who have Unit Accountants attached to
t'brmation commanders in operational works areas. The worki I Since incorporated in FR Part ll as Appendix 26.
tL44l tl4sl
them the normal procedure will be followed but separate. con-
struction accounts folios for each operational work will be reouisitionins of lands and buildings will be carried out under
maintained and a Monthly Expenditure Return (M.E.R.) showing ihci no.mal lrocedure laid down for that purpgry'-
lAuthoiity : A.H.Q.Q.M'G. Br. No' 056331Q3(W'iii)
dt"
- Statisticsincurred
expenditure on each work will be rendered by_the GE.
in regard to expenditure and receipts (Cash and 9-2-s21.
St<lres) should be k-ept in the monthly abstract of receipts and 13. Audit ObJections on Special Works'
-Theseparately in the Division.
charges (a)Incases*heretheconstructionalcommitmentshave
normal procedure as regards tenders, contracts, employ- not been made or where financial commitments such
ment of D.E.L. stores and Cash Accounts will be followed by as collection of stores etc. have been made but which
G.E. Operational Works will only be put in hand by the normal do not involve payment of any com,pensation' the
G.E. on receipt of orders of the Commanders in Operational workwillbesuspendeduntilthesanctionofGovern-
-cash relating to the operational
Works areas. All payments works ment of India is obtained.
will be made out of assignment placed at the disposal of (b) In cases where contract has been concluded and the
G.E. of a I)ivision of M.E.S. workhasbeenstartedbutitisnotlikelytoentail
Stores for works will be accounted for in the normal uny tbr compensation the work will be suspended
manner and such accounts for operational works will be kept "f"it
as in (a) above.
by the MES Officers. The construction accounts for operational (") In casis where postponement of work will result in
works will also be maintained by the G.E. in the normal manner. payment of compensation to the contractor or damage
All vouchers to be endorsed with the words "Operational io"the incompldte work the work will continue but
Works". the details of^the sase and the repercussion of stop-
9. Construction Accounts to be maintained in E Section ping/ abandoning the work be immediately reported
of Main Office when the work is undertaken by Field Units. to A.H.Qrs- for instructions'
/Authority : C.E.E.C. (now C.C.) Lucknow No. 519200041 (d) audit objections,..if upheld,.and
\-/ Action to settleanytheinfructuous
llSlE2l(W) daied 11-3-60 as amended vide his No- 51920004 to regularize expenditurc will be
l1 l238lE2(w) dated 21-12-601. taken bY the CFA.
10. The construction of Principal Roads and Bridges will /Authority i aaQ No. 586421Q3W (Policy) Maintenance
dt'-30-9-581
not be undertaken under Operational Works. ic. p*""drrre for Taking over/Accounting and
lAuthority : Min of Def. No. Al00955lQ3W (Policy)l4g4lslD of Tangible Assets created under c)perational works Procedure.
(w-r) dt. 7-12-591. dovt. of India Ministry of Defence No. 66449/EZNl69lSl
11. The preparation of Estimates, according administrative SO- fiI/D(w-I) dt. 16th April tg-69 .T amended vide Ministry
^No.
approval, Technical sanction, allotment of funds will not be ;i D;6; C'orrigendum 6644elE2N7e2lqo--I]l/D(y-U
n-eiessary in the case of operational works in an operational Uut".r Zj-+-68 and No. 66449 ;EZN36751SO-III/D(W-1)^ dated
i_g_os and cGDA's No. 18009/AT_S dt. 28th. Aprit 1966
works aiea. Orders of Commanders in operational works areas on
for execution of works will serve the purpose to cover all the it uUou" subject are reproduced -below for inftrrmation and,
stages mentioned above. "
!"i0"""" of ad concerned. Cases of construction of other than
[Authority : A.H.Q.Q.M.G's Branch No. 599431Q3(W'iii) l"*porury structures under.operational wor-ks. prglelY: should
dated 23124-5-521. pf"dt" be placed under objection as stated in CGDA's memo
12. Hiring and Requisitioning of Lands and Buildings (in- dt.28-4-66.
cluding furniture) required for operational purposes- in opera- 1.
,,I am directed to refer to the Procedure for operational
tional works areas will be treated as operational works and the works laid rlown in Govt. of India. Ministry of Defenc_e letters
Operational Works Procedure will be followed. ,_Expenditure No. 05633/Q3(W.iii)/204lQ,/D-V48 datcd 23 January 1948, No-
incurred on such hiring/ requisitionMaintenance will be treated
-expenditure. ddqqgf1ziiiofr.tiWorks-l) daled 10 Dec., 1'962 as amendcci
as operational works In other cases hiring and vide No. 66449182N3256 (D I rlated 27th .lune 1963 and No'
!' OoaqgYzNnal SO-fiI./D,',v'l) ciattti ?.2nd January t9s6' The
r&
11461 It47l
President is pleased to sanction the following procedure for
taking over, accounting and maintenance of assets created under (b) In respect of assets taken over under para 3 separate
the Operational Works Procedure. orders will issue.
2. Taking over of assets ln areas where MES is inducted. 5. This letter issues with the concurrence of Ministry of
(a) On orders of the GOC-in-C, AOC-in-C, Chief En- Finance (Defence) vide their u. o. No. SW1 of 1966.
gineer Command will take over on the attached form APPENDIX 'A'TO GOW. OF INDIA LEfiER NO.
at Appendix 'A' to this letter assets which are tech- 6644e1E2N1 6sis/so-lll/D/(w-l) DATED 1 6-4-66
nically suitable for maintenance and have a reasonablc PROFORMA
life expectation. Based on the available data/informa- Register of Military Buildings/Assets
tion, Chief Engineer will assess the cost of construction
as no complete Construction Accounts were main- s. No. of Descrlp- Specifi- Water (W) Electrif- Assessed
cost
Rem-
arks
tained for individual assets constructed under the No Bldgs/ tion of cation Sewage ication
AesEts Assgts (s) (E)
operational works procedure. The cost will be approved
by the Chief Engineer Command and entered in the
appropriate column in the form. The cost of any
subsequent addition alteration/special repairs be 15. Clarification
entered in the form as in the case of normal work. With reference to para 2 (b) of the above letter, it is not
(b) Since works of temporary nature can alone be con- known whether, in actual practice works of temporary nature
structed under the Operational Works Procedure, alone have been/are beinf constructed under the operational
maintenance, allotment as for temporary buildings will works procedure. For instfnce it would ?Pp.eal from para.4 of
be admissible based on the assessed value of the oase 23 of Scales of Accommodation (War) that it would not
assets. MES will carry out the maintenance under bc-appropriate to view prefabricated sheds as temporary..struc-
normal rules. turei *h6n they are raiied on dwarf walls or given additional
3. Taking over of assets in areas where MES is not ventilation, lighiing, special floor or other alterations and addi-
inducted. tions. In view of this case of construction of works of other
(a) In such areas only numerical account of assets will than temporary nature if any executed under- the.operational
be kept. The accounting will show the brief descrip- worls procedure coming to your notice may be placed under
tion of the structure and the location where it is objection and regularistion watched-
' f,Authority z C. C. D. A. No- 18009 AT-S dated 2S-4-661
constructed. The record by numbers will be main-
tained by the Engineer Tr6ops, under the direction
. of Chief Engineer Corps, who will be responsible to 16 Onrnsonrl Works-Suppty & Senices Imprest'
the local audit for proper accountC. A copy of the Advarie against Sup.ply and Senrices imprest provided to
record will also be maintained by the Chief Engineer rorks and fielil units Uy ttre Chief Engineers- from which
disbunements are made aie monthly drawn from the Controller
in C-ommand.
Of Defence Accounts concerned. This is however, not practicable
(b) Malntenance : An ad hoc yearly grairt for the main-
in case of units deployed in remote areas where no banking
tenance of these structures will be given to the Chief
facilities exist. In such cases, the President is pleased to sanction
Engineer Corps who will be resporisible to carry out
that the Chief Engineers in Consultation with CDA concerned
the necessary rnaintenance through troops at his dis- may authorise drawal of advances from the Field Cashier con-
posal.
cerned.
4. Disposal. 2. Past cases will be regularised accordingly.
(a) Assets taken over under para 2 ivill be dispose-d 3. This issues with the concurrence of Ministry of Finance
of under normal rules, (Defence) vide their u.o. No. 121lSW1 of 1966.
'
/Auihority : Govemment of lfrdig, Mi1t, of D-ef.,le-tter No.
3S%5-EU\348/S-D (lV'orlcs-Il) dated 26th March 19661
tr48l
tl4el
17. Review and modification of procedure for recoyery
of Departmental charges from Navy and Air Force for MES recovered from these two services for works and
works and services. services rendered by MES be restricted to |Vo'
_ !la:r existing provisions in paras 214 read with paras 310
of^ MES Regulations all works and services carried out for the (u) As regards tools and plants charging of LrVo of the
\avy and Air Force are subject to the levy of departmental
-Table ,H' value of works as T & P Charges will continue' The
ghargeJ in accordance with the rates prescribed in amount so collected will be credited in a centralised
ibid. These charges are adjusted cenirally as per procedure manner under the existing deduct Head (Code No'
prescribed in para 559 ibid. -'E' of Minor Head 111-
495106) under Sub Head
2. Consequent on the reorganisation of MES and the Works' under Major Head 2076 (Army):- For this
setting up of dedicated Zonal Chief Engineer formations for category prefixes 08 and 09 will be used
purpose,
Navy and Air Force for works and ServiCes rendered by MES
has been reviewed. It has been decided that with effeit from
i"ftii" op"tatirig ihd concerned Codg llead (495/06)
the finan-cial year commencing on Ist April 1993, the existing to ident'ifu the-T & P chargqs booked to Navy and
system of recovery of departmental charges on MES works ancl
Air force resPectivelY.
(vi) incu.red by- dedicated MES formation of
services should be modified as follows : ' -' Expenditure
Nuly and Air Force on-Miscellaneous expenses' print-
(i) lay and Allowances of Army Officers and personnel ing lnd stationery, Telephone-and payment to other
deployed in dedicated MES formations of Navy and Departments for work done for Defence which are
Air force will be booked against minor Head 102 of now booked under Minor Head 800- other expen-
the two seryices Navy (Major Head 2077) Code Head diture of Major Head 2A76 (Army) will be.debited
11600102 and Code Head 1/601/01 and Air force (Major
to respective"Minor Head 800-Other-Expenditure of
Head 2078) Code Head |fiAU\Z and Code Heiad Major^Head 2077 (Nu"y) and Major Head 2078 (Air
1,1708.l0l through contra-debit/contra-credit after initial
for6e) respectively. For this purpose separate budgetary
disbursemelt from Atmy Budger through CDA(O) heads/cod-e heads will be oPened.
(vii) The recovery of pensionary.ctrgges at l/2lo as,Part
and CDA(ORs).
(iD Pay and Allowances of civilian officers and personnel ' ' of departmehtal iharges leviable at -present on Navy
of dedicated MES formations of Navy and Air Force and liir Force will be dispensed with, as expenditure
will be provided for and booked against Minor Head on pensions do not form plrt of Army Demand No- 18'
104 of the respective services. Nary (Major Head
2077) and Arr force (Major Head Z07g). For rhis 3. Action is being taken separately for opening new
purpose suitable budgetary heads/Code Heads will be budgetary/code heads foi implementing the above measures.
" 4. Action is being also taken separately for amendment
opened.
(iii) For TA and outstation allowances and all other con-
of relevant provisions of MES Regulations'
veyance charges of MES civilian officers arrd personnel
5. The^ revised procedure as explained above comes into
of such dedicated MES formations in Navy force with effect from Ist April, t99i i.e. with effect from the
ancl Air beginning of the financial yeat 7993-94-
force, suitable and separate budgetary Hbads/Code " O. it is clarified that notwithstanding the direct booking
Heads will be opened under Minor Head 105 of the
two sen'ices. The same expenses in respect oi Arnry of expenditure of dedicated MES formations of Navy and Air
personnel can be adjusted through contra-debiticrc.lit For""' as indicated above, the periodical reviews of norms and
under separate code heads. itiengttr of establishment of such dedicated MES formations
(iv) In view of the direct booking of various elements ol' wil Jontinue to be carried out in an integrated manner along
expenditure incurred on establishment of cleclicatecl
with reviews of norms of MES establishment as whole. conse-
ouentlv the deplovment of the overall sanctioned establishment
MES formations of Navy and Air Force as indicatecl
above, the percentages of departmental charges to be:
6i MdS will be'alio considered in an integrated manner keeping
Ar
llsol tlsrl
in view the nature and quantum of rvorkload of individual Aor€ements involving annual payment not
units/formations of various categories. (iv) CE Command
eiceeding Rs. 500 lakhs in eTX-case:--
7. This issues with the concurrence of Ministry of Defencc
(v) E-in-C/DGW Full Powers
(Fin/IVorks) vide their De,No. 7748lAddl FA(c)/g: dt. Z:.S.9:.
/ Authority t C*t of India , Ministry
Lettcr
, _ _ lAuthority ; Govt. of India, Ministry of Defence No. ^o[ ^2*:",u
12(1)/931D(Works-II) Dt. 23rd Aug 19931 N,,. qqASOln2ePql24g2lDlWorks-ll duted 20-10-2009 I
18. Construction of Civil Works for Ordnance Factories 20. Norms of Expenditure for Malntenance
of Military
through Agencies other than MES - :-1.
Itouds
I am directed to refer to FB proposal NO. 6891P&MM/datecl The existing norms lbr maintc,lance clt roads werc laid
19-19-1986 forwarded vide their UO No. SPL/COM/BS, rhat tlown unde. C,ru"r-nt"nt ol India, Ministry of Defe nce- -lcttcr
i'.i,,.'sze-66ru82 (wPa)t;t-ivls+:ipo-lvD" ( w-I) da t ed
Government have approved that the Civil Works o[ orclnancc 23 J ulv
where necessary. Subject to rates of construction bcing com- t986.
parable the overhead charges also being reasonable in comparison 2.The roacls maintenance norms as approved earlicr under
-quoted
to what in which the works are required to be got completecl. i,boue letter are for three categories namcll plains'
2. As and when required, the Ministry will get the quality ;;;ti Jnd hilly ur"ut. The norms have bccome much bekrw
of the works checked by an agency other than the consultani ;;-;;q;i;;o i""*r onJ ne",t rationalisation bv *",!iig in
,t-!.:* by
or the contractor of the OFB for the Civil Works. iin" *i|n the road classification ancl the noims laid d.wn
3. This issues with the concurrence of lntegrated Financc ' - --
Ministry of Surface Transport in March 1993'
Branch vide their Uo No. 785-SAF (DP-Iy87 dated 29th Sep- i-'Accordingly, I am directed to convey the sanction ot'
tember, 1987. the piesident to ihe u,fopiion of the undermintioned ntlrms 'l
19. Delegation of Powers to officers of MES for executlon *uirrt"non"e for military roads in ancl ex-cantonmcnt by the
of electricity and water supply agreement and agreement firr MES in plains :
disposal of sewage.
(a) Agreemenl or memoranda of terms for laklng a bulk supply ol electrlc
enorgy or walor fiom an oulslde aource lor milltary bulldings.
(i) Garrison Engineer Agreemsnts involving annual payment nol
exceeding Rs. 30,00,000/- in each case.
(ii) Commandar Works Engineer Agreements involving annual paymont nol 4For hilly areas, heavy rainfbll areas above 3000 mm pcr
exceeding Rs. 100 lakhs in each case. .nnum ancl foi deseit areis&lack cotton soil, the following
(iii) CE Zone Agreements involving annual payment not pi"tittlincrease over the scales at para 3 above shall bc
exceding Rs. 300 lakhs in each case. annlicable
II :
(a) Hilly areas and heavy rainfall areas above 34% of normal rePairs
(v) CE Command Agro6m6nts involving annual payment not 3000 mm Por annum
exceding Rs. 500 lakhs in each case. (b) Desert areas/Black cotton soil areas 11To ol normal rePairs
Full Powers
5. These norms will be effective tiom 01-04-99 and thc
(v) E-in-C/DGW
(b) Agreement or memoranda of lerms tor glvlng e bulk supply of electric maintenance grant based on the above norms will comc into
onergy or waler to non-military consumer and for glvlng sewage tor lrealmeni "financial year 1999-2000 and onwards. Howcver,
and dleposal to outsldc bodles. ii,rc,e for the
(i) Garrison Engineer
Itrt actual maintenancd wiil be restricted within thc allotted
Agreoments irrvolving annual payment not
exceeding Rs. 30 lakhs in each case. I'unds"
6. This issues rvith the concurrence of tho Ministry rlf
Commander Works Engineer Agreements involving annual payment not
l)ct'ence Finance vicle their UO No' 2061W-Ill99 of 1999'
(ii)
exceeding Rs. 100 lakhs in each cas6.
Notes_l. The road classification is based on instructiot]s
vE
irru"i'Uy-E-in-C'. Branch vicle letter Nos. 84008/Pol/CP datcd
(iii) LOF.A Agreements involving annual payment not
exceeding Rs. 300 lakhs in each case.
22 Nov. 91 and 05 Mar 92 :
Itsz1 tls3l
'Ilpe of Roads Carrlage way 0i) Oflice accn (Adm block 45 .48 30.00 13'23 20.95 29.53
RD1 Double carriage way each 7.5 m widc onty) ot Fmn HQrs down
to Sub Area and equivalent
RD2 Two large carriage way 10.5 m wide in other services trg accn
RD3 Two lane carriage way 7 m wide ot cat 'A' Est of Army and
conesponding institutions ol
RD4 Single lane carriage way 3.5 m wide Navy/AF/R&D and Tech
accn of R & D laboratories.
No. 8z96611tE2W (ppc) vot_rv (iii) Ml Rooms and 83.30 54.66 32.19 s3.60 74.95
^_^.J4r!ltority-M.O.D.
278/DO-rr/D (w-r) Dt. 15_03_99J Hosoitals.
ilfo o"'
Rs
31.'].0
o.'
GOC (Div Area, Corps and
Command) & Eqriivatent
otfrs of services. PART II
(b) Non R€ldenrtd Bldge PLINTH AREA RATES FOR ELECTRICAL ENGINEERING
(i) Otfice Bldgs (any type 33.32 MAINTENANCE
2't'8'l 20.9s 34.71 48.61
except in sub para (ii) 8.No. Catogory ol bullding Ratos in Rs per Sqm for
below) storage a6cn (Airy day to day services,
type) wksps/garages and Repairs and maint
tsch accn excopt in sub
para (ii) below etc. Concentra Scattered
ted GrouD Group
I 2 3 4
RESIDENTIAL BUILDINGS
ryq
lL74l lr75l
(*) There was casting error in the total draft corrigendum
ADDITIONAL CHECK LIST FOR AEs/RAEs
resulting in gross difference of Rs. 95,3781- (including
3Vo contingency charges). This was brought to the
1. Title of the project is as per that provided in the approved
notice of Dir (Planning) of CE who in turn corrected
list of the MWP.
the same.
(xi) While processing a proposal it
was found that 2. AE Part II contains details of the work required for
following items of work (as applicable) separately in consonance
establishment charges @ 2Vo was included in the AE
with the details indicated in BPs.
Pt II where as in other similar cases, Estt. charges
were not included. As such the matter was discussed (a) Site clearance (demolition of old buildings)
with Dir (Planning) of CE who stated that as per policy (b) Building work-(construction of new building)
in vogue Estt. Charges are not being claimed and (c) External electrification
accordingly AE Pt II was corrected by them, (d) External water supply
(xiD Nomenclature as mentioned in MWP was Sewage (e) Sewage disposal and drainage
treatment plant for "Allahabad Fort Area" where as (f) Roads, culverts and retaining walls
the SOC stated that the work is for 508 ABW Area. (g) Fencing and gate
The Executive Authority have been asked to confirm (h) Air conditioning
that entire Fort Area has been included in the (i) Gen sets
proposal.
(j) Garage and servant quarters
(xiii) The Board Proceedings are incomplete where no
3. Scales
recommendation/financial effect has been brought out
therein. The recommendalion should include apart
(i) the scale of accommodation applied is as authorized,
correct and latest as per the scale of accommodation
from other points, provision of generating set,
as amended from time to time.
transformer, street light fittings, hard standing and UG
Cables etc. if required in the project otherwise AEs (ii) Correct conversion factor for plinth area has been
to be modified accordingly. applied.
(xiv) Quantity of CI/GI pipes required to be replaced and 4. Rates
new pipe required to be laid, has neither been Rates applied are based on (as applicable)
mentioned in BP nor in SOC. (D Standard Schedule of Rates 1996 (SSR %).
(*) Building No. & nirmber of doorsApindows where (ii) Plinth area rates at par with SSR !)6 published by the
mosquito proofing is to be provided has not been E-in-Cs Branch.
brought out in the B.P. Further replacement of 20 (iii) Nedold sanctioned work by the Government, if
Nos. of chowkhats and 100 Nos., of windows have required.
been included in AE Pt II which were not (iu) Recently concluded contracts, if required.
recommended in B.P.
I Ar etipulated vide Annorurc to Instruction Order No. 6-200&
tL761
(") Market/Assessed rates.
(ui) ED rat "s published by the E-in-C's Branch for E/IvI
items.
(vii) MV/DCS applied are as per latest returns.
(viii) MV/DCS not applied on market/assessed/contract
rates and furniture rates.
(ir) Correct allowances for the following have been
catered for (as applicable)
(a) Seismic element zone wise.
(b) Anti-termite treatment.
(c) Framed structure.
(d) Multi storied construction.
(e) Extra foundation.
(Q Mosquito proofing.
(g) Additional height.
(*) Items of furniture are provided as per latest scale and
rates based on latest furniture rate list.
(xi) The necessity of the proposed work is accepted in
principle at appropriate level.
_. - _. . f.,:,.t1ll:Ir\..,^
,..'';\..
" ,,,. ,,,,,
,.
\ '\
: \\it
\.
34q6 '*$ . i
\ ., ,J
. \' - ? jr'
r"
,\-
"L*.. l,: .r;'.
-.