Work Plan for the Excavation for the Reservoir/Dam 12th September 2018

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8


Item Description No of Days
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6

1 Excavation Second Core 6

2 Cutting First Slope 6

3 Cutting Second Slope 4

4 Excavationg the Exit Area 5

5 Compaction of Embankments 4

6 Cutting of Spilway 2

7 Laying of Boulders at Spillway 2

8 Excavation for Channeling Storm water and 6

9 Construction of filtration Columns 2

10 Trench around the Reservoir 6

11 Grading And Compaction Around the Reservoir 4

12 Installation of Spout water Feature 6

13 Fencing 4