Sie sind auf Seite 1von 109

HAYWARD TYLER

ENGINEERED PRODUCTS

BHARAT HEAVY ELECTRICALS LTD


(BHEL)
Kahalgaon Power Station

SERIAL NUMBERS
EP/03/10757A,B,C,D,E & F
EP/04/10794A,B & C

3 X 500 MW BOILER CIRCULATING PUMPS


FOREWORD

This instruction manual provides comprehensive Each section contains an itemised Contents List.
installation, operating and maintenance information The major illustrations of the Pump and Motor are
of a Hayward Tyler Glandless, Wet Stator, Motor included at the rear of Section 7. Additional
Pump Unit, referred to in the text as the circulator. illustrations of particular features are incorporated
in the text.
The General Contents list shows that the manual is
divided into eight main sections. Paragraph Note! Where a customer boiler layout drawing is
references are consecutive throughout each section, shown, this is used in good faith. However,
and are preceded by the appropriate section Hayward Tyler can accept no responsibility for any
number. For example 5.1. designates:- errors or consequences that may result.

Section 5, Commissioning. Hayward Tyler Manuals are for guidance only and
5.1. Pre-Start Check List. we reserve the right to update, revise and modify
this manual in accordance with our continuous
Hayward Tyler Engineered Products Ltd. research and development programme.
1 Kimpton Road
Luton Revised manuals will not automatically be issued,
Bedfordshire however, should they be required, Hayward Tyler
ENGLAND may be contacted and arrangements can be made.
LU1 3LD

Telephone: +44 (0) 1582 731144


Email: engineering@haywardtyler.com
Fax: +44 (0) 1582 452198

i
GENERAL CONTENTS

BOILER CIRCULATING PUMP – INSTRUCTION AND MAINTENANCE MANUAL

SECTION 1 TECHNICAL DATA

SECTION 2 STORAGE

SECTION 3 DESCRIPTION

SECTION 4 INSTALLATION

SECTION 5 COMMISSIONING

SECTION 6 OPERATION

SECTION 7 MAINTENANCE

SECTION 8 STUD TENSIONING

ii
SECTION 1
TECHNICAL DATA

CONTENTS

PARAGRAPH PAGE

1.1 GENERAL 1.1

1.2 CHARACTERISTICS 1.1

1.3 MOTOR CHARACTERISTICS 1.2

1.4 CLEARANCES AND SETTINGS 1.2

1.5 HEAT EXCHANGER 1.3

1.6 INSTRUMENTATION 1.3

1.7 TORQUE LOADINGS 1.3

1.8 WEIGHTS (APPROXIMATE) 1.3

ILLUSTRATIONS

FIGURE 1/1 MOTOR ASSEMBLY 1.4

FIGURE 1/2 WINDING RESISTANCE DIAGRAM 1.5

FIGURE 1/3 PUMP PERFORMANCE CURVE 1.6

FIGURE 1/4 MOTOR PERFORMANCE CURVE 1.7

1. 0
SECTION 1
TECHNICAL DATA

1.1 GENERAL

Unit Serial Nos: EP/03/10757 A B C D E F & EP/04/10794 A B


Customer Order No: 0130645 & 0140593
Service: Boiler Water Circulating Pump with
Motor below Pump.
Number Supplied: 9
Electrical: 3300V - 3 Phase - 50Hz

1.2 CHARACTERISTICS

Type: Single Suction - Double Discharge


Size: (2 x 13) x 16 x 19H Volute
Design Pressure: 214 kg/cm2
Design Temperature: 370°C
Hydrostatic Test pressure: 321 kg/cm2
Suction Pressure: 197.4 kg/cm2
Specific Gravity at pump suction 0.542
N.P.S.H. required: 15 m (3% head drop)
Quantity Pumped: 3135 m3/hr
Differential Head: 32.37 m
Pump Efficiency: 83 % Cold 83 % Hot
kW Absorbed: 333.1 Cold 180.5 Hot

1.3 MOTOR CHARACTERISTICS

Type: Wet Stator Squirrel Cage Induction


Output: 360 kW
Service Factor: 1.0
Winding Insulation: XLP
Motor Case Design Pressure 214 kg/cm2
Motor Case Design Temperature 368oC
Speed: 1450 RPM.
Hot Duty Cold Test
Motor Efficiency: 89.5 % 89.5 %
kW Input: 201.7 372.2
Power Factor: 74.0 82.5
Overall Efficiency: 74.3 % 74.3 %
Full Load Current: 85 amps
Motor Starting Current: 410 amps

1. 1
SECTION 1
TECHNICAL DATA

1.4 CLEARANCES & SETTINGS (mm)

Initial Maximum

Impeller Wear Ring Clearance : ∅ 1.46 – 1.58 2.03

Journal Bearing Clearance : ∅ 0.20 - 0.38 0.55

Reverse Thrust Wear Ring Clearance : 0.42 - 0.52 0.76


Rotor End Float: 0.50 - 0.80 1.50

Impeller Setting (Dimension ‘Z’): 572.5 – 571.5 mm


1.5 INSTRUMENTATION:
Temperature Switches: Ashcroft Model T.461-T20-030-69C-XNH:
20-950C with 6096 mm capillary. 15amp. 125 to 250 Volt AC.

Alarm Setting 60°C Trip Setting at 65°C

Thermometer: Ashcroft Model 600A-03-C41-B01-A1-L07-BS-


XNG
0-1200C – CD1
Pressure Gauge: Ashcroft Model 60-1379SSL-04L-XNH-XNG
0-250 Kg/cm2 – CD1.

Flowmeter: KDG Mobrey Series 250 Rotameter


Model 250-50-CX-M12-TO-S6-Z6
Relay Mains supply: 220V 50/60 Hz
Contact Cut Off Capacity: Max 250V/4A/500VA
Thermocouples: Type ‘K’ Dual Element – Ungrounded

1.6 TORQUE LOADINGS:- Refer to Figure 1/1, Schedule of Torque Loadings

1.7 WEIGHTS (Approximate)

Pump Case 3425 kg

Motor Complete 6020 kg

Heat Exchanger 410 kg

1. 2
SECTION 1
TECHNICAL DATA

TOTAL 9855 kg

1. 3
SECTION 1
TECHNICAL DATA

Figure 1/1 Motor Assembly

1. 4
SECTION 1
TECHNICAL DATA

Figure 1/2 Winding Resistance Diagram

1. 5
SECTION 1
TECHNICAL DATA

Figure 1/3 Pump Performance Curve

1. 6
SECTION 1
TECHNICAL DATA

Figure 1/4 Motor Performance Curve

1. 7
SECTION 2
STORAGE

CONTENTS

PARAGRAPH PAGE

2.1 ENVIRONMENT 2.2

2.2 STORAGE - GENERAL 2.2

2.3 INHIBITOR 2.2

2.4 HEAT EXCHANGER 2.2

2.5 EXTERIOR SURFACES 2.2

2.6 STANDARD STORAGE CHECKS FOR STORAGE UP TO 3 YEARS 2.3

2.7 STORAGE PERIODS GREATER THAN 3 YEARS 2.4

2.8 PREPARATION FOR STORAGE AFTER USE 2.4

2.9 INSPECTION RECORD CARDS 2.4

ILLUSTRATIONS

FIGURE 2/1 MOTOR STORAGE / TRANSIT DETAILS 2.1

FIGURE 2/2 PUMP CASE STORAGE DETAILS 2.2

FIGURE 2/3 INHIBITOR FILLING VALVE 2.3

FIGURE 2/4 ROTATING THE ROTOR ASSEMBLY 2.5

FIGURE 2/5 INSPECTION RECORD CARD 2.6

FIGURE 2/6 CHECK LIST 2.7

2.0
SECTION 2
STORAGE

Figure 2/1 Typical Motor Transit/Storage Details

2.1
SECTION 2
STORAGE

2.1 ENVIRONMENT 2) The motor apertures must be blanked off


with flanges secured with studs, bolts and
The storage area must have a hard standing nuts (Fig. 2/1).
floor that will be capable of supporting the
weight of the units. 3) The motor and transit assembly must be
filled to the top of the transit canister with
inhibitor of the appropriate concentration,
2.2 STORAGE – GENERAL through the filling connector located in
2.2.1 Pump Case (Fig. 2/2) the temporary transit flange, sealing off
the motor heat exchanger bottom outlet.
1) The pump case internal cast areas and all
machined faces must be cleaned and a
suitable removable solvent rust 2.3 INHIBITOR
preventative, with a minimum effective Inhibitor is to be produced from a pre-mixed
life of 6 months, applied. Recommended concentration of mono-propylene glycol and
rust preventatives are, Jenolac J400 or distilled water in a 50/50 solution by volume.
Shell Ensis Fluid 264, or their The mono-propylene glycol must contain
equivalents. corrosion inhibitors and meet BS6580 or
2) All pump case openings must be closed equivalent. A tolerance of ±5% on the normal
with covers. These covers to be secured glycol/water mix may be applied.
to the weld preparations with steel The distilled water used must have a
banding and the pump case main flange conductivity of less than 10 reciprocal
with the existing studs and nuts supplied megohms (microsiemens) per centimetre.
on the pump flange.
Check the specific gravity of the inhibitor to
ensure the correct concentration.
The specific gravity of the mixture at 20°C is
as follows:-

Mixture by%Volume Specific Gravity


45% MPG /55% Water 1.036
50% MPG /50% Water 1.038
55% MPG /45% Water 1.040
MPG = Mono-propylene Glycol

2.4 HEAT EXCHANGER


Figure 2/2 Pump Case Storage Details
The heat exchanger should be stored as
instructed by the manufacturers.
2.2.2 Motors (Fig. 2/1)
The heat exchanger interconnecting pipe work
1) The motor and transit assembly must be and the fill and drain assemblies must also be
stored in a vertical position standing on filled with the same inhibitor as the motor,
the motor cover end. blank flanges being used to seal both ends.
NOTE:
When the terminal box protrudes 2.5 EXTERIOR SURFACES
below the motor cover stand, rest the
motor cover on balks of timber of All exterior surfaces of the motor must be
sufficient height to keep the terminal maintained in a good painted condition.
box clear off the ground (Fig. 2/1) Scratched or damaged paintwork must be
repainted.

2.2
SECTION 2
STORAGE

CAUTION:
2.6 STANDARD STORAGE CHECKS FOR To rotate the assembly in a clockwise
STORAGE UP TO 3 YEARS direction may damage the impeller nut
locking screw.
A visual examination and inspection of the
b) If the shaft cannot be rotated or is
motor and transit assembly must be made at
very difficult to turn, the motor must
least every three months as follows:-
be stripped down and inspected as
NOTE: outlined in Section 7.
When stored by the contractor, or by an
8) Check the inhibitor level in the motor and
agency, a record card should be kept of the
transit assembly. The level of inhibitor
intervals between inspections and the results
must not fall below the level of the
of the following inspection checks recorded.
impeller. Top up if necessary.
2.6.1 MOTOR 9) Check the glycol/water concentration by
1) The motor is stored vertically resting on measuring the specific gravity of the
the motor cover - not horizontally. inhibitor. The inhibitor is considered
acceptable if it conforms to the
2) The exterior paintwork is in good concentration and tolerance given in
condition. Repaint where necessary. paragraph 2.3.
3) All flanges and joints are tightly secured 10) Replace the transit inspection cover
and no leakage of the inhibitor has taken when the inspection is satisfied.
place.
2.6.1.2 Topping up/Draining Inhibitor (Fig 2/3)
4)
a) All studs, bolts and nuts are present 1) Remove the access cover plug.
and in sound condition. 2) Attach a hose leading from a pumping
b) The phosphate, or any other plating, device to the hose tube of the inhibitor
applied to these items has not filling valve.
deteriorated. 3) Unscrew the filling valve screw by two
5) Measure and record the ambient turns. This action opens the valve to allow
temperature of the storage area. the pumped liquid to enter the motor.
6) Check and record the insulation resistance 4) When the sufficient inhibitor has been
of the stator windings as follows: pumped in, turn screw to close the valve.
a) Remove the terminal box cover. 5) Remove the hose from the inhibitor
b) Check the insulation resistance at the filling valve.
terminal stems using a l000V megger. NOTE:
Record the result.
If the motor is to be drained, allow the
IMPORTANT: - liquid to flow out of the valve hose tube.
If any insulation resistance value falls below Ensure disposal of inhibitor is carried
200 megohms at 20°C this, and any previous out in accordance with local
readings, with dates, must be reported to regulations.
Hayward Tyler for comment.
c) Fit the terminal box cover.
7)
a) Remove the inspection cover from the
top of the transit canister (Fig.2/1).
Fit impeller wrench onto the impeller
nut and rotate the rotating assembly
seven complete revolutions in an anti-
clockwise direction when viewed from
the pump-end.

Figure 2/3 Inhibitor Filling Valve

2.3
SECTION 2
STORAGE

2.6.1.3 Pump Case and Transit Assemblies


Inspect the pump assembly and check the 2.8 PREPARATION FOR STORAGE
following: - AFTER USE.
1) No extensive corrosion has occurred on 1) Remove the motor from the pump case
the internal pump cast or machined areas. and drain the motor as described in
Section 7.
2) The protective coating is satisfactory.
Re-apply if necessary. 2) Disassemble the motor cover and clean
out any loose material, sediment etc.
3) Visually examine the assembly for
damage. 3) Disassemble the motor as described in
Section 7.
4) Check that the pump case protective
flanges are correctly fitted and secure. 4) Check all fittings and clearances and
general condition (Section 1). Fit spare
2.6.2 Stud Tensioning Equipment parts as necessary.
After use, the stud tensioning components 5) Reassemble the motor as described in
must be thoroughly cleaned, examined for Section 7.
damage and a rust preventative lubricant
applied to all surfaces. 6) Using special wrench provided on the
impeller nut, check that the shaft rotates
The components must be then wrapped in freely, approximately seven revolutions in
suitable waterproofed material and stored in an anti-clockwise direction.
a clean, dry area.
7) Check the insulation resistance of the
winding. This should not be below 200
2.7 STORAGE PERIODS GREATER megohms.
THAN THREE YEARS 8) Fit the transit canister to the main flange
Units that remain in store over three years and stand the motor upright on the motor
require special consideration and Hayward cover.
Tyler Limited should be consulted for 9) Seal off all apertures with appropriate
specialist advice. transit flanges and gaskets.
Motor assemblies that are stripped must be 10) Fill the motor with a pre-mixed
reassembled using new gaskets, the details concentration of inhibitor, in accordance
recorded on the storage record card stating that with paragraph 3, through the filling
it has been stripped and listing any relevant connection in the transit flange, sealing
findings. the motor heat exchanger bottom outlet.
CAUTION: 11) Fit the transit canister inspection cover.
Precautions must be taken prior to use that
the unit is pressure tight. 12) Re-check the insulation resistance of the
motor windings.
13) Check that the storage conforms to Para
2.2.

2.9 INSPECTION RECORD CARD


(Fig. 2/5 and Fig 2/6)
A typical inspection record card and check list
is given on the following pages.

2.4
SECTION 2
STORAGE

Figure 2/4 Rotating the Rotor Assembly

2.5
SECTION 2
STORAGE

Figure 2/5 Inspection Record Card

2.6
SECTION 2
STORAGE

Figure 2/6 Check List

2.7
SECTION 3
DESCRIPTION

CONTENTS

PARAGRAPH PAGE

3.1 GENERAL 3.1

3.2 PUMP 3.1

3.3 MOTOR 3.1

3.4 TERMINAL BOX 3.5

3.5 HEAT EXCHANGER 3.5

3.6 ALARM SYSTEMS 3.5

ILLUSTRATIONS

FIGURE 3/1 AUXILARY COOLING CIRCUIT 3.2

FIGURE 3/2 TERMINAL GLAND 3.4

3.0
SECTION 3
DESCRIPTION

3.1 GENERAL 3.2 PUMP


The Hayward Tyler Glandless Motor The pump comprises a single suction and
Circulator Pump is designed for recirculating double discharge branch casing, welded into
boiler water through the boiler water systems the boiler system pipe work at the suction and
of fossil fuel or liquid cooled nuclear reactor discharge branches with the suction branch
power stations and similar applications. uppermost.
The circulators consist of a single stage Within the pump cavity rotates a key driven,
centrifugal pump and a wet stator induction mixed flow type impeller, mounted on the end
motor, which are mounted within a common of the extended motor shaft. 'Renewable’ wear
pressure vessel. The vessel consists of three rings are fitted to both the impeller and pump
main parts, a pump casing, motor housing and case. The impeller wear ring is the harder
motor cover. component to prevent galling
The motor is suspended beneath the pump
casing and is filled with cold boiler water at 3.3 MOTOR
full system pressure. No seal exists between
the pump and motor, but provision is made to The motor is a squirrel cage, wet stator,
thermally isolate the pump from the motor in induction motor, the stator wound with a
the following respect: - special water tight insulated cable. The phase
joints and lead connections are also moulded in
1) Thermal Conduction. Because the pump an insulated material. The motor is joined to
temperature is so high, usually above 340°C the pump casing by a pressure tight flange joint
and the motor temperature is limited to and a motor cover completes the pressure tight
about 55°C, a simple restriction, in the form shell.
of a 'neck', is provided to minimise heat
conduction. The motor shell contains all the moving parts,
except for the impeller. Below the impeller is
2) Hot Water Diffusion. To minimise situated an integral heat baffle which reduces
diffusion of boiler water, a narrow annulus the heat flow, a combination of convection and
surrounds the rotor shaft, between the hot conduction, down the unit. A baffle wear ring-
and cold regions. A baffle ring restricts cum-sleeve above the baffle forms a labyrinth
solids entering the annulus. with the underside of the impeller to limit
3) Motor Cooling. The motor cavity is sediment penetration into the motor. Should
maintained at a low temperature by a heat foreign matter manage to pass the labyrinth
exchanger in a closed loop water circulation device into the motor enclosure, a filter located
system, thus extracting the heat conducted at the base of the cover end bearing housing
from the pump. strains it out.

In addition, this water circulates through the The motor design is such that for ease of
stator and bearings, extracting the heat maintenance, the stator shell, complete with the
generated in the windings and providing stator pack, the rotor shaft, the journal bearing
bearing lubrication. An internal filter is housings and the thrust assembly, can be
incorporated in the circulating system. withdrawn from the motor case in sequence.
Lifting lugs are supplied to secure hoists when
4) In emergency conditions, if low pressure raising and lowering the motor.
coolant to the heat exchanger fails, or is
inadequate to cope with heat flow from the
pump case, a cold purge can be applied to
the bottom of the motor to limit the
temperature rise.
NOTE:
A high pressure cold purge is to be used
only as an emergency. (para 6.3.8)

3.1
SECTION 3
DESCRIPTION

Figure 3/1 Auxiliary Cooling Circuit

3.2
SECTION 3
DESCRIPTION

3.3.1 Auxiliary Cooling Circuit (Fig. 3/1)


The motor is provided with its own auxiliary 3.3.3 Internal Filter
closed circuit, which besides cooling the motor
A stainless steel woven wire strainer, fitted at the
lubricates the bearings. The water is
base of the reverse thrust seat, filters the liquid in
continuously circulated through the bearings,
the motor before it is circulated through the
motor windings and an external heat exchanger
bearings after passing through the heat exchanger
(cooler), by an auxiliary impeller at the thrust
(cooler).
bearing end of the motor shaft.
The filter should be cleaned at normal
When the motor is stationary, thermosyphon
maintenance periods, removing any accumulation
circulation takes place to remove conducted heat
of foreign matter in the motor cover.
from the pump end of the motor.
3.3.4 Main Flange Joints
3.3.2 Bearings
The pressure joints at the pump and motor cover
The motor rotor shaft is supported by water
flanges employ spiral edge wound gaskets,
lubricated tilting pad type radial and thrust
specially designed for very high pressure and
bearings mounted on the stator shell, thus making
temperature. The main pump/motor flange
the motor internals into a separate construction
gasket is housed in stainless steel overlay,
independent of the motor pressure vessel.
recessed into the joint face.
3.3.2.1 Journal Bearings
The studs and nuts securing the flanges are made
The journal bearings of the circulator are from special high tensile steel and, because
the water lubricated Michell type located at torque tightening these nuts is inadequate, the
the ends of the motor shaft, i.e. pump-end studs are hydraulically stretched and the nuts
and cover-end. Each bearing comprises a tightened down by hand. When the hydraulic
hardened steel sleeve on the shaft running tension in the stud is released, the load is
in six radially located tilting pads whose transferred to the nut giving the required
bearing surfaces are lined with a composite tightness.
material. The bearing surfaces must never
Stud tensioning equipment is supplied with each
be allowed to operate in a dry condition.
circulator order.
3.3.2.2 Thrust Bearing
3.3.5 Terminal Gland
A main thrust bearing is situated below the
The electrical supply to the motor is taken
cover-end journal bearing and takes the full
through special high pressure single lead cable
hydraulic thrust of the pump. This bearing,
terminal glands of the high temperature, safety
also of the Michell water lubricated type, is
type.
formed by a steel thrust disc, with a
composite bearing surface, on the bottom of The seal is effected by a terminal gland
the rotor shaft running on stationary moulding, together with o-rings located between
hardened steel tilting pads. an insulating sleeve and an inner casing, and
between the inner casing and the motor case.
The thrust disc is also designed to operate
The addition of a cone-shaped collar within the
as an auxiliary impeller to circulate the
terminal moulding, plus the design of the inner
internal water content of the motor.
casing, prevents any possibility of a gland
3.3.2.3 Reverse Thrust Bearing blowout at high temperatures. However, if the
motor is subjected to sustained overheating, a
The weight of the rotating assembly, as well
slight leakage may occur into the terminal box.
as the down thrust imposed at start-up and
shut-down, are taken by a reverse thrust
bearing located on a reverse thrust housing
which forms the bottom of the cover
housing cylinder.
The reverse thrust housing also includes a
composites reverse thrust wear ring and is
the mounting for the internal filter.

3.3
SECTION 3
DESCRIPTION

Figure 3/2 Terminal Gland

3.4
SECTION 3
DESCRIPTION

3.4 TERMINAL BOX 3.6.2 Temperature Switches


Robust fabricated steel terminal boxes are Two temperature switches, remotely mounted,
provided on the side of the motor casing for are provided for actuating the alarm. When a
connecting the power supply to the motor. pre-set temperature is reached, the alarm circuit
Each phase supply cable for the motor enters a is energised via one of the switches. Should the
box at its base and should be sealed by a cable motor temperature continue to rise, the second
gland. Each phase notation is identified by a switch is activated to de-energise the motor.
colour coding, Red, Yellow or Blue. 3.6.3 Thermocouples
Bursting discs are fitted to the wall of the A thermocouple is provided for measuring motor
terminal boxes to relieve excessive pressure cavity temperature. Two thermocouples are also
build up within the box should a flash over supplied with weld on pads for measuring the
occur at the terminals. skin temperature of the pump case and suction
Desiccators are fitted to absorb atmospheric manifold. These are to be installed on site by the
moisture that may decrease the electrical user.
resistance to ground. Each assembly is 3.6.4 Instrument Pockets
completely enclosed by a bolted on cover.
Temperature switch, thermometer and
thermocouple pockets are provided where
3.5 HEAT EXCHANGER required.
A heat exchanger (cooler) must be fitted to 3.6.5 Differential Pressure Transmitter with
dissipate the heat generated by the motor and manifold
the heat transferred from the pump casing.
These are to be connected to the process
High pressure outlet and inlet raised facings are connections in the pump case by the user.
situated at the bottom and top of the motor case (Customer supply)
respectively for connection to high pressure
heat exchanger / motor case stub pipes. 3.6.6 Pressure Gauge
Interconnecting pipework must be short and A pressure gauge is remotely mounted to the
direct with the heat exchanger mounted as high motor case.
as possible to promote good thermosyphon 3.6.7 Flow Meter
circulation when the unit is on hot standby.
A flow meter is supplied to be fitted in the low
pressure cooling water return line by the user.
3.6 ALARM SYSTEMS
3.6.8 Ground Detection Relays
3.6.1 Thermometer
The motor windings should be protected by
The thermometer instrument is mounted adjacent ground detection relays, sufficiently sensitive to
to the motor, and gives visual indication of the detect the development of a pinhole or minor
motor temperature. crack in the stator winding insulation.

3.5
SECTION 4
INSTALLATION

CONTENTS

PARAGRAPH PAGE

4.1 GENERAL 4.2

4.2 PUMP CASE INSTALLATION 4.2

4.3 PREPARATION FOR MOTOR INSTALLATION 4.2

4.4 MOTOR INSTALLATION 4.4

4.5 FITTING THE HEAT EXCHANGER 4.5

4.6 FILLING THE CIRCULATOR WITH BOILER COLD 4.6

4.7 HYDROTESTING BOILER WITH CIRCULATOR INSTALLED 4.6

4.8 ELECTRICAL CONNECTIONS 4.8

4.9 MOTOR PROTECTION 4.9

ILLUSTRATIONS

FIGURE 4/1 PUMP CASE INSTALLATION 4.1

FIGURE 4/2 MOTOR INSTALLATION 4.3

FIGURE 4/3 TERMINAL BOX 4.7

FIGURE 4/4 BURSTING DISC ASSEMBLY 4.8

FIGURE 4/5 EARTH LEAKAGE PROTECTION CIRCUIT DIAGRAM 4.10

4.0
SECTION 4
INSTALLATION

Figure 4/1 Pump Case Installation

4.1
SECTION 4
INSTALLATION
3) The cables, leading to the motor, should be
4.1 GENERAL flexible and looped immediately prior to
entering the terminal boxes. The looping
WARNING should be sufficient to accommodate unit
The Hayward Tyler boiler circulating pump is movement caused by expansion and
a precision piece of heavy machinery. contraction of the boiler pipe work.
It should only be installed under the
supervision of a qualified professional engineer
who should ensure that the staff directly 4.2 PUMP CASE INSTALLATION (FIG 4/1)
concerned are adequately trained and have
1) Remove the pump case flange and branch
read and understood this manual.
covers and clean the pump branches.
When installing the circulators the following
2) Attach shackles and slings to the casing
conditions MUST be observed.
eyebolts. A plate on the pump case
1) The system pipe work should be adequately indicates the front of the pump.
supported to accept the weight of the
3) Raise the case to meet the system pipe
circulator.
work, with the suction branch uppermost.
2) When mounted, the pump should
4) Ensure that the main motor/case flange is
accommodate movement in the pipe work
horizontal to within 1°. Tack weld to the
due to thermal expansion without imposing
system pipe work and re-check the
excessive loads on the casing and branches.
horizontal limits.
3) Sufficient clearance should be allowed
5) Complete the weld to the procedure
beneath the motor to permit lowering of the
approved by the boiler manufacturer and test
motor from the pump case for maintenance.
radiographically for flaws.
(See Section 7 Fig. 7/35.). If removable
floors or girders etc. are fitted after the 6) On completion of a satisfactory
motor is installed, ensure that the terminal radiographic test, fit any pressure
boxes or low pressure cooling water supply differential transmitters using the stub pipes
lines will not foul them when the boiler is on on the pump case branches.
load and the circulator moves downwards
7) Fit the blanking off plate until the motor is
due to thermal expansion.
installed.
NOTE:
Two long lift hoists should be used to
raise the pump or motor, each hoist being 4.3 PREPARATION FOR MOTOR
capable of taking the full weight of the INSTALLATION
pump or motor CAUTION:
4) The pump should be positioned so that the The motor should be stored, topped-up with
N.P.S.H. available exceeds the N.P.S.H. inhibitor for as long as possible. If it is
specified in the Technical Data - Section 1). necessary to install the motor before boiler
water is available, install in the inhibited
NOTE: condition to provide additional protection for
When operating at temperature, sub the motor internal components. However,
cooling of the inlet water is normally the inhibitor must then be drained
present and this gives a considerable immediately before mounting the heat
increase in the N.P.S.H. available. The exchanger.
worst condition is normally operating
cold. We do not recommend motor installation on
4.1.2 Installation Notes a Hot Boiler.

The following conditions must be observed 1) Hose down internally, the pump case, the
when installing the circulator: valves and adjacent-piping, to ensure the
removal of all loose debris.
1) Ensure that the main system is free from
solids before mounting the circulators. 2) Fully close the pump suction and discharge
valves.
2) Permanent insulation should be applied
only to the pump case. No insulating
material must be applied to the motor case
or to the main flange studs and nuts, as this
will cause the motor to overheat.

4.2
SECTION 4
INSTALLATION

Figure 4/2 Motor Installation

4.3
SECTION 4
INSTALLATION

10) Ensure that the motor is in correct


4.4 MOTOR INSTALLATION (FIG. 4/2) orientation with the pump case. See Section
7, Fig 7/35.
1) Using a 1000V megger, check that the
insulation resistance to ground of the motor WARNING
leads is above 200 megohms when measured The Hayward Tyler boiler circulating
at the terminal stems with the unit full of pump is a precision piece of heavy
water below approximately 20°C, if machinery.
possible, or at normal ambient temperature. It should only be installed under the
supervision of a qualified professional
2) Stand the motor in a vertical position, on engineer who should ensure that the staff
the motor cover stand, and in the correct directly concerned are adequately trained
orientation to the pump. and have read and understood this
3) Remove the pump case main flange nuts manual.
and cover and ensure there is no debris in 11) Attach shackles and slings to the motor
the pump pipe work system that could enter casing lifting lugs and lift into position,
the pump case. taking care to avoid damage to the terminal
4) Clean and inspect the pump case flange, box.
remove any burrs. 12) Fit the motor to the pump case as follows:-
5) a) Using the chain type hoists, lift the
a) Remove the plug or inspection cover at motor until the impeller is about to enter
the top of the transit canister. the pump case.
b) Loosen the inhibitor filling valve b) Measure the distance between the pump
situated in the motor fill and drain case and the motor flanges at four 90°
transit flange, (Section 2 Fig. 2.1), of degree points on the flange periphery. If
approximately 40-45 litres of inhibitor. necessary, adjust the lay of the motor by
Close the inhibitor filling valve. the chain hoists to make the distances
approximately equal.
6) Remove the transit canister from the motor
case. c) Bring the gap between the flanges equal
all round. This is best achieved by using
7) a spring-loaded 'inside' calliper, set to
a) If the motor is to be operated the gap directly in line with one of the
immediately upon installation, chain hoists. The set calliper is then
completely drain then proceed as (8) moved to the opposite side of the flange
b) If motor operation is not imminent, and the gap adjusted, using the chain
install the motor in the inhibited hoist. Check the gaps at right angles to
condition, proceed as 9), leaving 8) to be the first two and adjust the lay of the
performed when fitting the heat motor to make the gaps equal.
exchanger. d) Check that the studs are centred in the
motor flange holes. Adjust the motor
8) “lay” as required.
a) Connect a clean cold water supply to the e) With the chain hoists working in unison,
motor cover fill and drain connection, slowly raise the motor.
and flush the motor until inhibitor-free
water flows from the top of the motor. CAUTION.
b) Check that the shaft freely rotates, if not, If any increase in effort is required on
strip the motor as described in Section 7 the chain hoists to raise the motor -
to establish the reason and correct the stop raising it immediately as the
fault. impeller may be fouling the pump case
wear ring. In which instance,
9) Clean the overlay that provides the seat for fractionally lower the motor, check the
the gasket in the main flange of the motor. gap and raise the motor again.
Inspect for burrs and surface discontinuity,
dress if necessary with a fine grade stone.
Fit a new gasket. NEVER apply any
compound to the gasket and ensure that it is
dry.

4.4
SECTION 4
INSTALLATION

f) Check the gaps every 10 mm, or less, c) If, after fitting of the heat exchanger,
during the last 100 mm of the motor running the motor is reasonably
raising sequence to ensure that the motor imminent, and sub-freezing
does not 'cock' or rotate as it is raised. temperatures are not envisaged, the
Adjust the gap as necessary. motor and heat exchanger must be filled
with treated boiler water or condensate
g) Continue raising the motor until an
within 3 hours of fitting.
increase in the effort required on the
hoists indicates that the gasket is in
contact with the pump case face. At this 4.5 FITTING THE HEAT EXCHANGER
stage, the gap between the flange faces (CUSTOMER SUPPLY)
should be approximately 2.5mm and
should be equal all round the flange. 1) Remove the blank flanges from the motor
high pressure outlet to cooler and fill and
CAUTION: drain connection.
If the gap is unequal, the gasket may
have come out of its recess. If the gap 2) Ensure that the motor, the heat exchanger
is unequal, lower the motor and the high pressure pipe work and high
sufficiently to check the condition of pressure purge lines, have been flushed free
the gasket. If the gasket is damaged - from all obstructions and foreign matter.
renew. Never use any substance on 3) Flush out the secondary cooling water
the gasket to make it adhere to its system until clear water is discharged.
recess.
4) Mount the heat exchanger onto the motor
h) Coat the stud threads with high
case brackets and proceed.
temperature anti-seize compound or
silicon grease and install the nuts by a) Bring the heat exchanger parallel to the
hand. motor supporting the weight with the
lifting tackle.
NOTE:
b) Clamp the heat exchanger to the motor
Do not coat the exposed extended
by tightening up the securing bolts, nuts
diameter threads of the studs as these
and washers.
threads are for the tensioner
application. c) Ensure the motor / heat exchanger
interconnecting pipe work assembly is
i) Tighten the nuts, using the hydraulic stud
correct for the circulator.
tensioner in accordance with the
instructions in Section 8. Remove the d) Offer up the interconnecting pipe work
lifting tackle and removable lifting lugs. to the heat exchanger and motor flanges
and complete all pipe welds and NDE in
j) Thoroughly flush out the fill and drain
accordance with site approved
system piping, to the motor cover and
procedures.
when satisfied that the piping is clean,
connect to the motor cover. 5) Install gauges and recorders for temperature
k) Install the heat exchanger: see Para. 4.5 and pressure. Connect the low pressure
cooling systems to the heat exchanger.
l) Install the appropriate thermocouples,
the thermometer, pressure guage and 6) Fit temporary strainers to the low pressure
temperature alarm switches. cooling systems, and then check that
m) Connect the power supply cables to the circulation meets the heat exchanger
motor terminals, See 4.8. specification.
n) Install the vibration pick up probes if 7) Close the shut off valve in the high pressure
permanent vibration monitoring is fill and purge line and blow down piping.
required.
The motor and heat exchanger circuit must
13) now be refilled with inhibitor (See 4.4, Para.
a) If, after fitting the heat exchanger, 13 (a) or (b) or with treated boiler water or
running is not reasonably imminent, the condensate.
motor and heat exchanger circuit must
be refilled immediately with inhibitor.
b) If, after fitting the heat exchanger, sub-
freezing temperatures are envisaged the
motor and heat exchanger circuit must
be refilled immediately with inhibitor.

4.5
SECTION 4
INSTALLATION

5) After connecting the supply, open the heat


4.6 FILLING THE CIRCULATOR WITH exchanger vent on the high pressure side, fill
BOILER COLD the motor from the bottom and vent air from
the top, until clean air free water is
Filling the circulator correctly is a prerequisite to discharged from the vents.
ensure satisfactory operation. If air is present in
the motor it could affect bearing lubrication and 6) Close the vent on the high pressure side of
precipitate bearing failure. the heat exchanger.

If air pockets are present in the stator this would 7) Continue to fill the motor and vent any air
affect dissipation of heat generated in the via the vent connections in the boiler system
windings, creating hot spots and consequent pipe work.
degrading of the insulating material, and 8) Isolate the now filled circulator.
ultimately cause winding failure.
9) Ensure that the terminal box is dry and with
Due to the complexity of the passages in the the unit full of water below 20ºC or at
motor through which water must flow to displace normal ambient temperature, using a 1,000
all air, it is necessary to fill the motor very slowly. Volt Megger, check winding resistance to
If air pockets are present in the stator this would ground at the terminals. The resistance
affect dissipation of heat generated in the should exceed 200 megohms.
windings, creating hot spots and consequent
degrading of the insulating material, and IF NOT, CALL HAYWARD TYLER.
ultimately cause winding failure. DO NOT ATTEMPT TO RUN THE
MOTOR.
The maximum filling rate is 2 litres /min.
The motor must NOT be filled via the pump 4.7 HYDROTESTING BOILER WITH
casing, but only through the filling connector
CIRCULATOR INSTALLED
located at the motor cover.
Treated Water or Condensate Available: -
1) Isolate the circulator from the boiler by
closing appropriate discharge valves. Should the customer wish to hydrotest the
circulator, the hydrostatic test pressure must not
2) Supply the low pressure side of the heat
exceed the maximum specified in Section 1.
exchanger as follows: -
a) Open the supply valves in the low Treated Water Not Available: -
pressure cooling water system. If the boiler is to be hydrotested at an early state
b) Flush out the piping for the supply of of construction, the pump casing can be pressure
low pressure treated boiler water, or tested without the motor once the blank off plate
condensate, for filling the motor, until is installed – refer to para.4.2.
clean air free water is discharged.
4.7.1 Post Hydrostatic Test Procedure
NOTE:
The flushing must always be carried out 1) Boiler circulators are not to be drained, but
before introducing any water through the left filled to a level above the suction
lines to the motor and heat exchanger. downcomer.

3) If the low pressure supply contains an 2) Freezing can be avoided by filling with
orifice, check that it is clean and that its flow glycol in the concentration detailed in
rate is correct. Section 2.

4) Adjust the flow rate to approximately 2


litres/min.

4.6
SECTION 4
INSTALLATION

Figure 4/3 Terminal Box

4.7
SECTION 4
INSTALLATION
where it should be maintained at a
temperature of 110oC until the colour
4.8 ELECTRICAL CONNECTIONS reverts to blue. The re-activating time is
4.8.1 Power Supply to Motor between 1 and 2 hours.
c) Screw the desiccators into the terminal
Refer to the terminal box arrangement shown in
box covers taking precautions not to
Fig. 4/3.
damage the desiccators.
WARNING:
7) Fit and secure the terminal box covers using
Disconnect the power supply and the starter
the nuts and washers previously removed.
before commencing any work.
CAUTION:
Ensure that the cable length will
accommodate expansion and removal of the
circulator.
Ensure that the voltage connected to the
circulator is the correct operating voltage as
stamped on the motor nameplate situated on
the bottom of the motor case.
1) Remove the nuts and washers, and then
remove the terminal box cover using lifting
gear, if necessary.
2) Feed the cable through the conduit entry
gland and connect to the terminals in the
phase rotation RED, YELLOW, BLUE (‘U’,
‘V’ or ‘W’). When so connected the unit
will operate in the designed direction, i.e.
clockwise when viewed from above. All
connecting cables and links are marked with
appropriate phase colours.
3) Earth the circulator adequately. Earthing
studs are provided on the motor casing
adjacent to the terminal box.
4) Ensure that all electrical connections
particularly at the terminal box entry gland
are secure.
5) Fit the bursting discs to the terminal box as Figure 4/4 Bursting Disc Assembly
follows: -
NOTE:
The bursting discs are supplied as loose
items and are packed separately to
prevent damage in transit. They are 4.8.2 Recommended Instrumentation
fitted to the terminal box on the
installation of the motor. It is recommended that the following be
provided: -
a) Dismantle the bursting disc assembly
and discard the cardboard sheet fitted in 1) Pump suction and discharge pressure
lieu of the disc. gauges.
b) Reassemble the bursting disc assembly 2) Continuous record of motor voltage.
with the bursting disc in place, as
depicted in Fig. 4/4. 3) Continuous record of motor current.

6) Fit the desiccators, also supplied as loose 4) Ground leakage relay to warn of very low
equipment, as follows:- winding resistance in order to prevent
winding insulation failure.
a) Check that the desiccator crystals are
coloured blue. 5) Indication and record of downcomer
b) If pink, reactivate by placing the temperature and pump case temperature.
desiccator in a well ventilated oven This is required to avoid thermal shocks
when starting a pump on a hot boiler.

4.8
SECTION 4
INSTALLATION

4.8.3 Alarm Circuits (Fig.4/5)


WARNING: 4.9.3 Starting Period Protection
Lethal voltage is present in the alarm system
If the motor fails to start, trip out after a period
when the motor is inoperative. To make the
of approximately 5 seconds. The starting
circulator safe - open the isolator.
current is based on a locked rotor test with an
Suitable alarm and trip devices should be fitted allowance made for saturation of the magnetic
to protect the motor and arranged to provide: - circuit.
1) An alarm - as an indication of motor Motor Starting Current: See Technical Data,
overheat conditions. Section 1.
2) Motor trip (shut down) - if the temperature 4.9.4 Earth Leakage Protection (Fig. 4/5)
rise continues above the alarm setting.
Ground detection relays are recommended,
The normally advised settings for the protection sufficiently sensitive to sound an alarm if a pin-
devices are: 57°C for alarm and 60°C for trip. In hole or minor crack should develop in the stator
practice, the alarm setting should be reduced to winding. This protection is arranged in either of
5°C above normal motor operating temperature. the ways shown in Scheme A, Scheme B or
Scheme C.
4.9 MOTOR PROTECTION If the neutral point of the supply transformer is
grounded, a current transformer (CT) is inserted
The following protective devices must be into the ground lead, and a relay connected
provided for the motor: - across the current transformer secondary, see
4.9.1 Continuous Overload Protection Scheme A.

The overload trip setting should be 10% above Experience indicates that in the event of a fine
the maximum current requirements which could crack in the stator winding, the resistance to
occur with the pump running on cold water at ground drops to between 20,000 and 30,000
some other point than the specified duty, ohms. The relay should not trip the motors but
assuming nominal specified supply voltage. If initiate an alarm.
voltage variation can occur, then the trip setting If the neutral point of the supply transformer is
should be increased to 15% above maximum not grounded, three potential transformers (PT)
current value. are connected to the motor leads, with the
NOTE secondaries connected in an open delta, closed
Overload relays are now typically calibrated by the relay winding, see Scheme B. The relay
in motor full load current (FLC) where the should not trip the motors but initiate an alarm.
relay trips with a current 10% above the Scheme C shows a core balance earth leakage
FLC setting point. Hence the overload relay relay system where a core balance current
of this type should have a setting point of the transformer encloses supply lines L1, L2 & L3
cold duty current. supplying the motor.
Maximum current at nominal voltage: NOTE
See Technical Data, Section 1. It is important that no earth conductor is
allowed to be enclosed by the current
4.9.2 Instantaneous Trip Setting transformer. The earth leakage sensitivity
To allow for transients during the first cycles of and trip time can generally be selected to
the starting period, the instantaneous trip should prevent nuisance tripping. Typical setting
be set at 12 times the motor full load current. points are 300 mA and 1 second. This may
require adjustment depending on supply
Full Load current: See Technical Data, Section conditions.
1.

4.9
SECTION 4
INSTALLATION

Figure 4/5 Earth Leakage Protection Circuit Diagram

4.10
SECTION 5
COMMISSIONING

CONTENTS

PARAGRAP PAGE
H

5.1 PRE-START CHECK LIST 5.1

5.2 INITIAL STARTING-COLD BOILER CONDITION 5.1

5.3 STOPPING 5.3

5. 0
SECTION 5
COMMISSIONING

5.1 PRE-START CHECK When a boiler is started from cold, a minimum


of two circulators must be operated. It is
The following pre-start checks must be normal practice to simultaneously warm the
satisfied before starting the motor. standby circulators to permit immediate staring
1) Ensure that the circulator is completely when required.
vented. CAUTION:
2) Ensure that the low pressure cooling 1. Motors must not be energised if the
water valves are open and the cooling motor cavity temperature is below 2°C.
water flow rate agrees with that specified 2. There should be at least ten-minute
in the heat exchanger manufacturer's intervals between two repetitive starts.
specification. All other valves must be This must never be exceeded;
closed. otherwise the motor winding
NOTE: temperature will rise and could
If the circulator is to be started on hot damage the winding insulation.
standby, the pump delivery by-pass 3. The motor may be damaged if motor
valves must be open. Refer to the hot temperature exceeds 65°C.
standby procedure in Section 6.
1) Ensure that the motor has been vented as
3) Ensure that the high pressure cold water detailed in Section 4, Para. 4.7.
purge at 20°C maximum temperature is
connected but isolated. 2) Ensure that a flow of approximately 2
litres/min., is entering into the motor
4) Using a 1000V megger, check that the through the low pressure fill line.
insulation resistance to ground of the
motor leads conforms to the Winding 3) Ensure that the pre-start checklist, as
Resistance curve shown in Section 1, described in Para. 5.1, has been satisfied.
Fig. 1/2 when measured at the terminal 4)
stems with the unit full of water below
a) Release any air trapped below the
approximately 20°C, if possible, or at
discharge valves by opening valves.
normal local ambient temperature.
b) When air-free water is discharged to
5) Check that the correct voltage is atmosphere, close valves.
connected to the circulator.
5)
6) Check that the electrical supply is
a) Vent the pump by opening vent
available at the point of control selected
valves.
and that the starting equipment is
functioning correctly. b) When air-free water is discharged
from vent valve to atmosphere, close
7) Test the operation of all instrumentation valves.
and alarms.
6) Make sure that the boiler is full and open
8) Ensure that sufficient N.P.S.H. is the discharge valves.
available for the pump to run without
cavitation. NOTE:
The by-pass valve should never be
9) Start parallel operating boiler circulating fully closed. It is normally throttled to
pumps with the stems of the discharge provide a minimal flow between the
valves withdrawn to prevent overheating pump suction and discharge system
of the boiler water in the pump case.
7) Switch on power to the starter.
5.2 INITIAL STARTING-COLD BOILER
8) Press the starter button on the control
CONDITION
console and energise the motor for 5
In systems where the circulators are arranged seconds only.
in parallel, to avoid cavitation, sufficient
circulators must be operated to limit the
capacity per pump to a value where the
N.P.S.H. required is less than the amount of
N.P.S.H. available.

5. 1
SECTION 5
COMMISSIONING

CAUTION:
The motor runs up to full R.P.M. in 12) When the motor temperature has
appropriately one second. If the stabilised: -
motor fails to start after five seconds, a) Adjust the high temperature alarm
press the stop button and do not setting to 10% above this point, or to
attempt to restart the circulator for 20 57°C, whichever is the lower. The
minutes. trip setting must never exceed 60°C.
9) After ten minutes pause, run the b) Make adjustment to other
circulator for a further (2nd) five instrumentation as necessary.
seconds. During this run, check the c) Check all flanges, glands and valves
following:- for leaks.
a) Motor Current (after ammeter has d) As the boiler water temperature
come off initial surge of current) increase, its specific gravity decreases
b) Differential pressure - when the and the amount of N.P.S.H., available
check valves open, the differential increases. The temperature of the
pressure should rise immediately to high pressure water to the heat
approximately 3 bars. exchanger may alter due to lower
losses in the motor, or because of
NOTE:
increased heat flow from the pump.
If the differential pressure does not
NOTE:
rise, stop the motor immediately; it
It is normal procedure to commission
may be an indication that the motor is
circulators separately, but if required,
running in reverse. Reverse rotation
before the last circulator is stopped,
will result in approximately 30% less
the others may be energised and their
head generated and about 10% more
recordings taken after each one is
power absorbed than specified.
brought on-line.
10) After a further (3rd) ten-minute pause,
repeat operation (9).
5.3 STOPPING
1) Press the stop button on the control
11) After another (4th) ten-minute pause,
console. The run-down time is
energise the motor and run for twenty
approximately 2.5 seconds.
minutes. During this running period,
carry out the following checks:- 2) Close the discharge valves.
a) Check the motor for vibration, using 3) Maintain the low pressure cooling water
a vibration detector, several times and supply to the heat exchanger.
record reading for future comparison.
b) Check for rubbing or excess bearing NOTE 1:
noise by holding a listening rod If the circulator is to stand idle for
against the pump and motor case. some considerable time with the boiler
cold, the low pressure cooling water to
c) Check the motor operating the heat exchanger may be turned off,
temperature at regular intervals. especially on systems where the
Initially it should rise several degrees cooling water runs to waste.
then stabilise. If necessary, adjust the
secondary cooling water flow after
checking that the strainers are not NOTE 2:
obstructed. On hot boilers, and whenever the
d) Check, as the motor warms, that the circulator is run, the low pressure
high pressure circulation pipe entering cooling water to the heat exchanger
the heat exchanger from the top of the must always be on.
motor becomes warmer than the high CAUTION:
pressure circulation pipe from the If the circulator is to be idle for an
bottom of the heat exchanger to the extended period, and be subjected to
motor case. This indicates correct freezing temperatures, make sure that
functioning of the heat exchanger. provision is made to protect the
e) Check that motor current and motors from freezing (see Section
differential pressure readings several 2.2.2.)
times and record the readings.

5. 2
SECTION 6
OPERATION

CONTENTS

PARAGRAP PAGE
H

6.1 STARTING THE CIRCULATOR 6.1

6.2 SHUTTING DOWN THE CIRCULATOR 6.2

6.3 ROUTINE CHECKS AND OPERATIONAL CONDITIONS 6.3

6.4 FAULT FINDING 6.5

ILLUSTRATIONS

Figure 6/1 FAULT LIST CHART 6.6

6.0
SECTION 6
OPERATION

Any of the following conditions may exist 6) Ensuring the boiler is still full, energise
when putting a circulator into service. Follow the second duty circulator on line and run
the relevant procedures below and refer to 6.3 up to speed.
for routine checks and operational fault action.
7) Perform the operational checks below.
Refer also to Para. 6.3.
6.1 STARTING THE CIRCULATOR a) Amperage.
6.1.1 Boiler Cold - Circulator Cold and b) Motor cavity temperature on alarm
Filled (Boiler Start-Up). thermometer.
c) Differential pressure.
1) Ensure that the pre-start checklist, 5.1 is
satisfied. d) Low pressure cooling flow and
temperature.
2) Vent the motor as follows: - e) Vibration.
a) Release any air trapped below the f) Drum level.
suction by opening the by-pass valves
and the filling valves. g) Valve and gland leakage.
b) When air-free water is discharged 8) Energising other motors: When the
through the vent valve, close vent boiler differential pressure parameters
valve. require the other circulators to be
energised: -
3) Vent the pump as follows: -
a) Check that the differential
a) Open the vent valve. temperature, between the pump case
b) When air-free water is discharged and boiler water in the downcomers,
from vent valve, close vent valve and is within 28°C.
filling valves. b) Energise the other motors.
c) Open the stems of the discharge c) Close by-pass valves on the newly
valves. energised pump(s).
CAUTION: d) Perform the operation checks on the
The pump must always be re-vented in newly energised pump as detailed in
this manner prior to starting when the para.6.1.1 (7).
drum pressure is below 3.5 kg/cm2.
6.1.2 Boiler Hot - Circulator Hot and
NOTE: Filled (Hot Standby)
The motor starting procedure following
is based on a normal boiler starting NOTE:
procedure where usually two circulators The low-pressure coolant to the heat
are initially operated with the remainder exchanger must be on.
brought-on line as required. 1) Check the differential temperature
4) between the pump case and the boiler
a) On circulators that will not be water in the downcomers.
energised, open the pump discharge CAUTION:
by-pass valves. This ensures that as The differential temperature between the
the boiler heats up, a flow passes pump case and the boiler water in the
from the discharge legs to the pump downcomers must not exceed 28°C. Non-
case and impeller etc. adherence to this may cause thermal
b) Check the motor temperature on the shocks and damage to occur.
alarm thermometer; this should not 2) Energise the motor.
exceed 49°C or be less than 5°C.
3) Close by-pass valves.
5) Energise the first motor. The current will
drop from full starting current after a few 4) Check circulator operation as detailed in
seconds to approximately the value para.6.1.1 (7).
corresponding to the operating point on
the makers test curve.

6.1
SECTION 6
OPERATION

6.1.3 Installation on a Hot Boiler 6) Check the pump case temperature as the
pump case is cooling to ensure that the
NOTE: cooling rate does not exceed 120°C per
Not recommended for safety reasons – but hour. If necessary, correct the cooling rate
not possible on this installation since no as follows:
suction valves are fitted and hence pumps
cannot be isolated. a) Cooling rate too fast: - If the pump
case cooling rate is too fast, slow the
cooling rate by partially opening the
6.2 SHUTTING DOWN THE by-pass valves as necessary.
CIRCULATOR b) Cooling rate too slow: - If the pump
CAUTION case cooling rate is too slow, increase
Low pressure cooling water flow and motor the rate by injecting a high pressure
temperatures must always be within the purge as detailed in Para. 6.3.8.
specified limits, whenever the circulator is 7) When the pump case has cooled to 45°C
on hot standby. de-pressurise the circulator as follows: -
6.2.1 Boiler Hot - Circulator to go on Hot a) Ensure the pump discharge by-pass
Standby valves and shut-off valve are closed.
b) Slowly depressurise the circulator by
1) Press the stop button on the control closing the pump suction by-pass
console. valve and partially opening the pump
2) Ensure that the low-pressure cooling line and suction leg vent valve.
valves are open. c) Open the motor cavity pressure
3) Open by-pass valves to provide gauge shut-off valves and check the
circulation of high temperature boiler pressure on the motor cavity gauge.
water through the pump casing, suction When the pressure has stabilised,
and discharge lines. close the pump suction leg vent valve.
d) Re-check that the pressure does not
6.2.2 Boiler Hot - Circulator to be Isolated increase. Should it increase, check the
for Maintenance following: -
1) Press the stop button of the control i) Make sure that all valves between
console to de-energise the motor. the circulator and high-pressure
system are closed.
2) Close the stems on the discharge valves.
ii) De-pressurise the circulator
3) Close the pump jumper line service again, if necessary.
valves.
8) On completion of depressurising, the
4) Crack open the pump suction bypass motor is ready for removal.
valves to prevent a vacuum forming in the
pump case during the circulator cooling CAUTION
process. The low pressure cooling water must
be maintained until the motor has been
5) Maintain the low pressure cooling
separated from a hot pump case.
system to the heat exchanger, via the low
pressure flowrator valves in the cooling 6.2.3 Boiler Cold
pipes open until the motor has been
1) Press the button on the control console.
separated from the pump.
2) Leave open the low pressure cooling
CAUTION:
water line valves.
Keep a close watch on the motor cavity
temperature, should the temperature 3) Pump discharge valves may be left open.
increase, apply a high-pressure purge as
described in para. 6.3.8.

6.2
SECTION 6
OPERATION

6.3 ROUTINE CHECKS AND 3) If temperature increase continues and


OPERATION CONDITIONS exceeds the 60°C - trip setting - and the
cause cannot be detected or the condition
(Also see fault list chart) corrected, refer to the relevant shutdown
6.3.1 Supply Current procedure in Para. 6.2. If necessary, blow
down the boiler system or apply a high-
1) Check the motor running current each pressure purge to the motor. See 6.3.8.
shift. The current should be constant and a) After cooling and draining, remove
comply with that specified in section 1. and disassemble the motor and
NOTE: examine for worn bearings, blocked
High amperage readings or fluctuating internal strainer, motor passages,
motor currents indicate wear or partial auxiliary impeller and fouled cooling
seizure at the bearing or wear ring surfaces. In addition, leaks in the heat
surfaces. This condition can cause exchanger.
vibration necessitating motor removal 4) Should the alarm sound whilst the
strip and re-installation. circulator is on stand-by, start the
6.3.2 Motor Temperature circulator to accelerate internal high
pressure cooling water flow. Check
1) During normal operation, the motor possible causes for temperature increase
temperature should be checked at weekly as above. The circulator should be tripped
intervals. The thermometer is originally if the temperature exceeds 60°C and the
set to initiate an alarm if the motor cavity shutdown / purge procedure 6.2 carried
temperature reaches 57°C and to de- out.
energise the motor if the temperature
reaches 60°C. If desired, the 6.3.3 High Temperature Alarm and Trip
aforementioned alarm temperature Settings
settings may be lowered, on the
At weekly intervals check that the motor
temperature alarm thermometer, to suit
high temperature alarm setting does not
normal operation but only after the boiler
exceed 57°C or 5°C above normal operating
and circulator has been operated long
Temperature (whichever is the lower) and
enough to stabilise.
that the trip setting does not exceed 60°C.
2) Immediately investigate the following Re-set if necessary.
possible causes for high temperature
alarm sounding: -
6.3.4 Pump Head and Quantity
1) Check the total head generated by each
CAUTION
pump at weekly intervals.
Do not stop the motor.
a) Check the low pressure cooling water 2) Correct possible causes of decrease in
supply for adequate flow, temperature head and quantity as follows: -
vapour locks and leakage in piping a) The gate valve in the circulating
(see 6.3.7.). pump suction line and the check valve
b) Check the circulator for leaks from in the circulating pump discharge
the motor casing, high pressure fill lines are not fully open. Check and
and drain cooling water connections, adjust the setting as necessary.
particularly the motor fill and purge b) Discharge through the pump and
line shut-off valves and the motor suction leg vent or the pump casing
drain valves. and suction leg drain valves. Ensure
c) Check that the cooling water strainers both are closed.
are not obstructed. c) Low N.P.S.H., available due to
d) Check for indication of bearing reduced water level in the steam
damage (noise, vibration). drum, changes in system pipework or
system blockage. Check and adjust
the number of circulators operating to
suit until the fault can be corrected.

6.3
SECTION 6
OPERATION

d) Vent the pipe system to remove f) Electrically induced vibration also a


vapour locks. factor, i.e. Rotor bar breakage etc.
e) Power supply and reverse rotation NOTE:
checks are given in 5.5.1 (5) and 5.2 When (e) is the cause, the motor must be
(9). removed, as detailed in section 7.2,
f) Worn wear rings and a blocked or before repairs can be undertaken.
damaged impeller can be corrected
only after removing the motor 6.3.7 Low Pressure Cooling Water Supply
assembly from the pump case. Failure.
Clearances are specified in section 1. If the cooling water to the heat exchanger is
6.3.5 Insulation Condition lost while the circulator is at operating
temperature, the motor must be de-energised
Before initially energising the motor and within five minutes and the suction and
thereafter at monthly intervals, check the delivery valves closed as soon as possible.
following: -
CAUTION
1) The insulation resistance to ground of the Damage to the windings may occur if:
motor leads. a) the motor remains in operation after 5
a) With the unit filled with water below minutes from the loss of cooling water.
20°C or at normal local ambient Or
temperature, the resistance measured b) if the cooling water is not
at the terminal links, using a 1000V restored before the motor
megger, must exceed 200 megohms. temperature rises above 60°C.
NOTE:
The insulation resistance of the stator CAUTION
winding varies with temperature and Do not attempt to operate the motor by
must always be measured cold 20°C or at overriding the temperature controller trip
normal local ambient temperature. mechanism and restore the low pressure
cooling water as quickly as possible.
2) Ensure that the interior of the terminal Damage to the windings may occur if the
box is dry, especially the insulation cooling water is not restored before the
projecting over the gland stems. motor temperature rises above 60°C.
6.3.6 Vibration NOTE:
Check the circulators for excessive noise or Before re-starting a circulator after an
vibration, which can be either hydraulic or emergency shutdown, low pressure cooling
mechanical in origin. water must be supplied to the pump to
reduce the motor temperature to at least
Vibration should be monitored and recorded 38°C.
daily. If a permanent vibration transducer is
not installed, check at weekly intervals 6.3.8 High Pressure Purge Supply To
using temporary pick-ups. If the reading Motor.
increases, check for the following causes: - On some boiler installations the motor fill
a) Cavitation due to low N.P.S.H., as and drain connection may be connected to a
described in 6.3.4. high pressure cold purge system which can
b) Unequal settings of the discharge be used for emergency motor cooling and to
valves. Check and re-set in the fully protect the motor during boiler cleaning.
open position. During normal operation this purge supply
must be isolated with a double isolation
c) Incorrect directional rotation as
valve fitted to the motor, as any leakage or
described in section 5.2, para. 9.
reverse flow from this point can result in
d) Excessive pipe strain on the pump motor overheating, winding and / or bearing
casing due to expansion or inadequate damage. (Reverse flow totalling no more
support of pipes. Eliminate any strain than 2 – 3 litres is sufficient to cause
by providing adequate support. damage).
e) Damaged or unbalanced rotor or
impeller, worn bearings, excessive
end float or incorrect impeller setting.

6.4
SECTION 6
OPERATION

NOTE:
If the boiler is “laid-up” under a nitrogen
Continuous purging of the motor during
blanket, take necessary precautions to
operation is recommended only during
prevent damage to the motor through
boiling-out and acid cleaning. A purge rate
gaseous water. Any pump start-up, when
of 3.8 litres / min., is normally sufficient to
the boiler is in this condition, must be
prevent the ingress of harmful fluids and
undertaken and initial start and the full fill
solids into the motor.
and vent procedure, as detailed in section
1) Flush down the fill and purge system to 4.7, must be followed.
ensure the line is clean.
6.3.10 Boiler Cleaning
2) Check that the low pressure cooling
water supply valves are open. During any boiling-out or acid cleaning
operation of the boiler, the de-energised
3) Introduce high pressure purge through circulators must be isolated completely prior
the filling valves. Check that the purge to introducing any chemicals to the boiler.
temperature does not exceed 49°C and The circulators must be continuously purged
that the purge pressure is above the boiler with clean cool water at a pressure of
pressure. approximately 7 bar, in excess of the existing
drum pressure to eliminate infiltration of
6.3.9 Extended Shut-Down
contaminated water into the bearing and
When the circulator remains shutdown for motor components.
an extended period: -
CAUTION
1) Check regularly that it remains full of Severe damage can be caused if acid is
water. allowed to enter the motor. If
contamination from acid cleaning is
2) Run the circulator for a minimum of ten
suspected, motor must be purged
minutes every two months.
immediately with clean water and
CAUTION inspected for damage.
If the motor is to be subjected to extreme
low temperature, the motor must be
prevented from freezing, see section 2.2. (5)
6.4 FAULT FINDING
Refer to the fault list chart that follows.

6.5
SECTION 6
OPERATION

Figure 6/1 Fault List Chart

6.6
SECTION 7
MAINTENANCE

CONTENTS

PARAGRAP PAGE
H

7.1 INTERNAL INSPECTION 7.3

7.2 MOTOR REMOVAL 7.3

7.3 DISASSEMBLY 7.4

7.4 INSPECTION OF COMPONENTS 7.16

7.5 ASSEMBLY NOTES 7.27

7.6 ASSEMBLY 7.29

7.7 RE-INSTALLATION OF MOTOR 7.42

PARTS LIST – GENERAL 7.43

ILLUSTRATIONS

FIGURE 7/1 MOTOR REMOVAL 7.2

FIGURE 7/2 MAIN IMPELLER REMOVAL 7.5

FIGURE 7/3 TERMINAL BOX 7.6

FIGURE 7/4 UP - ENDING THE MOTOR 7.7

FIGURE 7/5 TYPICAL WORKING PLATFORM 7.8

FIGURE 7/6 MOTOR COVER AND FILTER REMOVAL 7.9

FIGURE 7/7 THRUST BEARING 7.10

FIGURE 7/8 COVER – END JOURNAL BEARING ASSEMBLY - REMOVAL 7.11

FIGURE 7/9 ROTOR ASSEMBLY - REMOVAL 7.12

FIGURE 7/10 TERMINAL GLAND REMOVAL 7.13

FIGURE 7/11 STATOR ASSEMBLY - REMOVAL 7.14

FIGURE 7/12 JOURNAL BEARING TILTING PADS - REMOVAL 7.15

FIGURE 7/13 JOURNAL BEARING CLEARANCE 7.16

7.0
SECTION 7
MAINTENANCE

FIGURE 7/14 JOURNAL BEARING SLEEVE - REMOVAL 7.17

FIGURE 7/15 THRUST BEARING CLEARANCE 7.18

FIGURE 7/16 IMPELLER AND CASE WEAR RING 7.19

FIGURE 7/17 DETAILS OF TAPING HOOK 7.22

FIGURE 7/18 DETAILS OF TAPING NEEDLE 7.22

FIGURE 7/19 OUTER COIL TAPING 7.23

FIGURE 7/20 INNER COIL TAPING 7.24

FIGURE 7/21 TYPICAL KNOT SEALING 7.26

FIGURE 7/22 ASSEMBLY OF FLANGE STUDS 7.27

FIGURE 7/23 WIRE LOCKING 7.28

FIGURE 7/24 JOURNAL BEARING - ASSEMBLY 7.29

FIGURE 7/25 STATOR ASSEMBLY 7.30

FIGURE 7/26 JOURNAL SLEEVE 7.31

FIGURE 7/27 TERMINAL GLAND ASSEMBLY 7.32

FIGURE 7/28A COVER END BEARING ASSEMBLY 7.33

FIGURE 7/28B COVER END BEARING ASSEMBLY 7.33

FIGURE 7/28C COVER END BEARING ASSEMBLY 7.34

FIGURE 7/29 END FLOAT CHECK 7.35

FIGURE 7/30 MOTOR COVER AND FILTER ASSEMBLY 7.37

FIGURE 7/31 TERMINAL BOX 7.38

FIGURE 7/32 TERMINAL LINK INSULATION 7.39

FIGURE 7/33 BURSTING DISC DETAILS 7.40

FIGURE 7/34 IMPELLER SETTING 7.41

FIGURE 7/35 GENERAL ARRANGEMENT 7.47

FIGURE 7/36 SECTIONAL ARRANGEMENT 7.48

FIGURE 7/37 TERMINAL BOX ARRANGEMENT 7.49

FIGURE 7/38 TOOL KIT LIST 7.50

7.1
SECTION 7
MAINTENANCE

Figure 7/1 Motor Removal

7.2
SECTION 7
MAINTENANCE

b) Immediately secure temporary cooling


NOTE 1:
water hoses to the inlet and outlet
Some of the illustrations shown are typical
connections of the heat exchanger to
only and not necessarily specific to the
maintain a low pressure cooling water
circulator described, i.e. motor proportions
flow within the heat exchanger.
and number of studs etc., but indicate
generally the basis of the unit breakdown. c) Maintain cooling water until the motor is
separated from the pump.
NOTE 2:
For items not annotated on the drawings CAUTION:
within the text refer to the Main Sectional The low pressure cooling water flow, and
Arrangement at the rear of the Section. motor temperature must be maintained
within the specified limits, whenever the
NOTE 3: motor is in contact with the pump case.
A tool kit is supplied with each circulator
contract, containing specialised tools 4) Check the pressure gauges to ensure that the
necessary for the disassembly and assembly of circulator is depressurised.
the motor. 5) Make sure that the discharge valves, the
suction valve, the by-pass valves and the
shut-off valves are closed to isolate the
7.1 INTERNAL INSPECTION
circulator from the boiler and fill system.
Internal inspection of the circulator should be
6) Drain the pump casing.
carried out to the recommendation of the station
maintenance authority. WARNING:
Partial inspection of the internal filter and thrust Never drain the pump casing through the
bearing is possible in-situ after removal of the motor fill & drain line as this could cause
motor cover. contamination of the motor.
7) Fit the removable lifting lugs to the welded
WARNING:
brackets on the motor case.
Inspection must only be carried out with the
circulator isolated from the electrical supply, 8) Set up two chain hoists and rigging, of
depressurised and the motor cover removed sufficient capacity for each to take the full
as in Section 7.3.4. weight of the motor, and connect to the
lifting lugs.
A full inspection requires the motor assembly to
be removed as described below. WARNING:
Normally two hoists are used for removing
the motor and because the load can shift
7.2 MOTOR REMOVAL (FIG. 7/1) from one hoist to the other during the
WARNING: removal, each hoist must be capable of
Before removing the motor, the circulator taking the full weight of the motor.
must be completely isolated from the system, 9) Take the initial strain of the motor.
depressurised and cooled as described below.
CAUTION:
7.2.1 Motor Removal The motor must be removed from the
1) Isolate the electrical supply; disconnect all pump casing without a break in the
instrument cables from the motor identifying sequence (9) and (11).
the connections and leads. 10) Loosen the pump/motor flange stud nuts in
2) Remove the terminal box covers and accordance with the hydraulic stud
disconnect the external power supply cables tensioning instructions - section 8.
from the terminal box as described in 7.3.4, CAUTION
identifying each lead for reassembly. Always double check that the motor and
3) If hoses are not fitted in the low pressure pump case are cooled and depressurized
cooling system, adjacent to the heat before loosening the studs nuts.
exchanger, with sufficient slack to allow the 11) Disconnect the fill and drain line upstream
motor to be separated from the pump case, fit of shut-off valve if there is not sufficient play
temporary hoses as follows:- in the line to permit motor removal.
a) Close the low pressure cooling water
shut-off valves.

7.3
SECTION 7
MAINTENANCE

12) Remove the flange stud nuts and lower the 2) To remove the wear ring, remove the six
motor clear of the pump casing, keeping the screws securing the wear ring inside the
flange faces parallel until the impeller is pump casing. Carefully lower the wear ring
clear of the pump casing. from its location within the casing.
13) When the impeller is clear of the pump case, Lower to ground level, and store in a safe
check the motor cavity temperature. When place for inspection.
the temperature falls below 54oC remove all
instruments and store safely. 7.3.2 Impeller (Fig. 7/2)

14) Lower the motor to the floor. 1) Unlock the punch marks and remove the
impeller cap screw.
15) Drain the motor via the drain valve and
remove the valve and pipework 2) Remove the LEFT-HAND threaded impeller
nut using the special spanner and tommy bar
16) Remove the heat exchanger from the motor, provided in the tool kit.
in accordance with site procedures, as
described in 7.2.1. NOTE:
Do not use any leverage in the water
CAUTION: passages of the impeller to oppose force
To prevent damage never stand or turn exerted on the special spanner; the weight
the motor on either the drain valves or of the rotor will oppose rotation if the
terminal box. tommy-bar is given a few heavy blows
17) Lower the motor to the horizontal position with a lead faced hammer.
to give access to the terminal box, remove If the nut shows any tendency to seize on
the lifting tackle and cover all joint faces and the shaft, do not continue to exert force,
openings with clean rags. but drill and split the nut to remove.

18) If necessary, transport the motor to a 3) Fit the puller, provided in the tool kit, to the
working area where adequate facilities are tapped holes in the top of the impeller boss,
available for disassembly, inspection and using the applicable studs and nuts in the tool
maintenance. kit. Withdraw the impeller from the motor
shaft.
7.2.1 Heat Exchanger Removal
4) Withdraw the impeller washer and remove
NOTE: the impeller key.
As the heat exchanger is welded to the motor
5) Immediately refit a serviceable impeller nut
case via the interconnecting pipework,
to permanently protect the shaft threads.
removal of the heat exchanger is at the
discretion of, and the procedure will be 7.3.3 Baffle Wear Ring
determined by, the senior station engineer.
Examine the baffle wear ring. If damaged,
Check the heat exchanger during the first remove the socket headed cap screws and lock
motor maintenance removal for build up of washers. Remove the wear ring for a fuller
sediment in the shell base; this will provide a inspection or renewal
guide to any future attention that may be
required. 7.3.4 Terminal Boxes (Fig. 7/3)
1) Remove the nuts and washers from the studs
7.3 DISASSEMBLY and remove the terminal box cover.

CAUTION: 2) Remove the nuts and washers from the


terminal studs.
Lifting tackle must not be attached to the
protruding rotor shaft nor must the shaft be 3) Identify the motor supply cable links for
subject to any shock loads. reconnection.
The motor must be adequately supported
before and during any disassembly. 4) Carefully cut the insulation from around the
cable connections and links.
7.3.1 Case Wear Ring
CAUTION:
1) The case wear ring can be left in place, Do not damage the link insulation.
bolted inside the pump case.
5) Remove the washers and the nuts from the
terminal stem as the link is removed.

7.4
SECTION 7
MAINTENANCE

6) Remove the nuts and washers from the NOTE:


terminal box support studs. Using lifting A small metal cover should be fabricated
tackle, lift off the terminal boxes and remove and placed over the terminal stems to
the gaskets. protect them during motor repair.

Figure 7/2 Impeller Removal

7.5
SECTION 7
MAINTENANCE

Figure 7/3 Terminal Box

7.6
SECTION 7
MAINTENANCE

Figure 7/4 Up-Ending the Motor

7.7
SECTION 7
MAINTENANCE

7.3.5 Motor Cover and Filter (Fig. 7/6)


1) Using two cranes and lifting tackle attach one
with shackles to the motor cover and the
other via a sling around the motor flange
neck. Lift and up-end the unit as depicted
Fig. 7/4 until the motor is vertical, with the
motor cover uppermost. Lower the motor
pump flange on to a suitable building stand;
a typical building stand is shown in Fig. 7/5.
Support the rotor shaft beneath the stand
using a screw or hydraulic jack. Care must be
taken to avoid damaging the shaft or flange
faces. If a pit is not available, erect a suitable
working platform, similar to that depicted in
Fig. 7/5.
CAUTION:
Firmly support the impeller end of the
rotor shaft on a suitable wooden block
when placing the motor on the stand and
jack so that when the thrust nut is
removed during a subsequent operation,
the rotor will be adequately supported.
2) Mark the cover relative to the motor case to
ensure correct alignment on reassembly.
3) Using the stud tensioning equipment (Section
8), release the tension of the motor cover nuts
and remove the nuts.
4) Attach the lifting tackle and carefully remove
the motor cover from the motor case.
5) Remove the flexitallic spiral wound gasket
and before discarding, inspect the gasket for
any unusual markings or depressions that
indicate a seat dressing is required.
6) Remove the filter by removing the hexagon-
headed screws and lock washers.

Figure 7/5 Typical Working Platform

7.8
SECTION 7
MAINTENANCE

Figure 7/6 Motor Cover and Filter Removal

7.9
SECTION 7
MAINTENANCE

Figure 7/7 Thrust Bearing

7.3.6 Thrust & Reverse Thrust Bearing (Fig. 3) Remove the split pin and loosen the thrust
7/7) nut using the thrust nut spanner provided in
the tool kit.
CAUTION:
a) Remove the thrust nut - right handed
Ensure that the impeller end of the rotor
thread – and the spacer washer.
shaft is supported firmly. This will prevent
damage to the rotor upon removal of the b) Lower the jack ram, sufficiently to lower
thrust nut. the rotor, leaving the thrust disc sitting on
When cutting removing locking wire, ensure the thrust pads.
that no wire is permitted to fall into the c) Remove the thrust disc, taking care not to
windings. damage the running surfaces on the disc.
1) Remove the reverse thrust housing, complete d) Alternatively, use the thrust disc puller, to
with reverse thrust wear ring as follows: - remove the thrust disc from the shaft.
a) Remove the socket-headed cap screws and 4) Remove the thrust key.
lock washers securing the reverse thrust
5) Remove the thrust seat as follows:-
housing to the bearing housing.
a) Remove the socket-headed cap screws and
b) Lift off the reverse thrust housing
the spring washers securing the seat to the
complete with the composite reverse
bearing housing.
thrust wear ring. Lower the jack.
b) Lift off the thrust seat complete with
2) Remove the thrust disc assembly as follows: thrust pads.
-
a) Set up the jack, with ram extended beneath
the rotor shaft and floor.

7.10
SECTION 7
MAINTENANCE

Figure 7/8 Cover – End Journal Bearing Assembly - Removal

7.3.7 Cover End Journal Bearing 2) Match-mark the cover end bearing housing
Assembly (Fig. 7/8) and the motor case to ensure that they are re-
fitted in their original radial location.
1)
3) Remove the bearing housing securing screws
a) Remove the locking wire and the stator
and lock washers.
lock ring hexagon headed screws.
b) Push down the stator lock ring sufficiently 4) Attach eyebolts and lifting tackle to the cover
to permit split ring to be prised out of its end bearing housing and lift the housing,
groove. complete with the journal bearing assembly,
c) Remove the split ring from its casing to just above the motor casing.
groove, using screwdrivers as levers. 5) Lower the bearing housing and remove and
d) Withdraw the stator lock ring, using discard the `O` ring.
screws as lifters, from the motor case. 6) Place the housing in a clean and safe place
for subsequent disassembly.

7.11
SECTION 7
MAINTENANCE

7.3.8 Motor Shaft (Fig. 7/9)


7.3.9 Terminal Gland Removal (Fig. 7/10)
1) Fit an eyebolt, supplied in the tool kit, and
lifting tackle to the rotor shaft as indicated. 1) To facilitate re-assembly, identify each
With an exact vertical lift, slowly lift the terminal stem body and its respective
rotor out of the stator, taking particular care position.
not to damage the cable ends whilst doing so.
CAUTION
2) Lower the rotor into the horizontal position Make sure that the gland moulding does
and position it carefully on to wooden 'V' not turn with the gland nut by holding the
blocks at floor level. Fit suitable protection, moulding stationary using a clamp
i.e. clean rags, over the journal sleeves. Refit connector and the connecting link.
the thrust nut to protect the threads.
2) Remove the nuts and link from the terminal
block. Unscrew the gland nut and tap the
connector lightly until the gland assembly
can be carefully drawn out of the motor case.
3) Remove the gland nuts from two of the stems
and placed on the third stem.
4) Replace the clamp connector over this stem
and undo the cable gland nut. This action
will draw the gland assembly from the motor
case.
5) Remove the inner casing & the ‘C’ shaped
support ring. The two belleville washers and
back up sleeve remain on the cable.
NOTE:
The terminal gland stems are moulded on
to the stator windings in a continuous
waterproof sheath, which must not be
broken or damaged
CAUTION
Never hammer the end of the stem if the
assembly is tight, as this will damage the
moulding.
6) Remove and discard the 'O'-ring from the
inner casing neck.
7) Feed the remainder of the gland moulding
and the cable assembly through the gland
body into the motor casing.
8) Remove the ‘O’ rings and back up rings from
the inner casing.
9) Suitably tape the terminal stems to prevent
them from damage and lay them over the
case flange.
10) Protect the cables from sharp corners.

Figure 7/9 Rotor Assembly - Removal

7.12
SECTION 7
MAINTENANCE

CAUTION:
Protect the chamfer on the pump side of
the bearing housing from damage, as this
will affect alignment of the rotating
assembly within the motor case.
5) Mark the stator shell and the pump-end
bearing housing, so that the slot in the
housing for the anti-rotation peg and the
stator winding leads can be correctly aligned
upon assembly. (Fig. 7/25).
6) Fit an eyebolt, sling and tackle, to the pump
end bearing housing, and take the weight of
the housing.
7) Remove the socket-headed cap screws and
lock washers. Draw the bearing housing
away from the stator shell.
8) Fit the lifting tackle to the cover-end bearing
housing. Take the weight of the housing;
remove the temporary fitted screws and
carefully ease the housing from the stator
shell.
Further dismantling of the stator assembly is
unnecessary unless the motor is to be
rewound. If rewinding is necessary, contact
Figure 7/10 Terminal Gland Hayward Tyler.
7.3.11 Heat Exchanger
Check the heat exchanger during the first
maintenance removal for build up of sediment
in the shell base; this will provide a guide to
7.3.10 Stator Shell and Bearing Assemblies any future attention that may be required.
(Fig. 7/11) De-scale and inspect the heat exchanger as
1) Place the cable leads within the stator bore. follows:-

2) Using guide rods temporarily re-fit the cover 1) Remove the inlet/outlet and return covers
end bearing housing in position on the stator from the heat exchanger shell. Discard the
shell. Re-fit the housing screws and tighten. gaskets.

3) Attach lifting tackle to the bearing housing 2) Using cleaning rods and a metal brush,
eyebolts. With an exact vertical lift, slowly remove all deposits from inside the tubes of
and carefully withdraw the stator assembly the shell and from each end cover.
out of the motor case. 3) Inspect generally for good order of the heat
4) Lower the stator and support it horizontally exchanger.
on wooden blocks placed at floor level. 4) Clean the mating faces of the shell and return
Ensure that the tapped hole for the eyebolt cover and inlet/outlet cover. Fit new gaskets
(used in lifting the pump end bearing to their respective ends of the shell.
housing) is located at the top centre.
5) Bolt up the end covers with the existing bolts
and nuts.
6) Pressure test the heat exchanger for adequate
sealing.

7.13
SECTION 7
MAINTENANCE

Figure 7/11 Stator Assembly - Removal

7.14
SECTION 7
MAINTENANCE

Figure 7/12 Journal Bearing Tilting Pads - Removal

7.15
SECTION 7
MAINTENANCE

7.4 INSPECTION OF COMPONENTS c) Journal Bearing Clearance


i) Place the tilting pads in their correct
7.4.1 Journal Bearing Tilting Pads (Fig. 7/13) sequence on their corresponding journal
The following procedure applies to both the sleeve and clamp firmly in position,
pump end and the cover end bearing housings. using large hose clips, as shown.
ii) Measure the dimension across the pivots
NOTE:
of each opposing pair of pads to
Pads must be kept in their sets and each set
determine the average dimension.
identified with its original bearing housing
and position in the housing for correct re- NOTE:
assembly Do not use feeler gauges between the
pads and sleeve due to the risk of
1) Remove the securing ring screws and lock damage to the sleeve and the inherent
washers from the applicable bearing housing. inaccuracy of this method.
2) Remove the securing ring, cover end or pump iii) Subtract this dimension from that of the
end. inside dimension of the mating bearing
ring bore. Record the result and
3) Identify the journal tilting pads with their
compare it with the bearing clearance
respective housings and mark the sequence
limits detailed in Section 1. Technical
of removal in a counter clockwise direction,
Data.
1 to 6.
iv) If the clearance is excessive, fit a new
4) Withdraw the tilting pads, noting the location set of tilting pads and a new journal
of the pivot and direction of arrows stamped sleeve.
on the rear side.
v) Remove the clips and tilting pads from
5) Remove the bearing ring. the journal and suitably protect the
journals and pads until required for re-
6) Remove the two anti-rotation stop pegs from assembly.
each bearing ring.
7) Clean and dry all components (except
composite parts).
8) Inspect all components as follows:
a) Tilting Pads
i) Check the surface for scoring or
breakdown of the composite. Slight
scoring is permissible but if the
composite surface is pitted or laminating
renew or return the complete set to
Hayward Tyler for possible reclamation.
NOTE:
Under no circumstances renovate the
pad surfaces with Carborundum Paste
or Emery Cloth.
ii) There should be no evidence of
'brinelling' of the tilting pivot.
iii) Ensure that the edge of the working
face has a 3 mm radius.
b) Bearing Rings
Check the seat surface for brinelling and
renew if grooved on the pad location.

Figure 7/13 Journal Bearing Clearance

7.16
SECTION 7
MAINTENANCE

7.4.2 Journal Bearing Sleeves (Fig. 7/14) 4) Inspect and record findings as follows: -
1) Very slight scoring or scratching of the a) Thrust Pad
journal sleeve is permissible but if excessive i) Slight scoring on the face is acceptable,
or cracked, the sleeve must be removed. but if excessive, the pad must be either
renewed or reground within the limits of
2) If the journal sleeve is to be renewed, screw the end float (see Section 1) to a surface
the journal locking screw into the shaft and finish of 0.15 micrometers.
carefully mill through the sleeve along the
keyway until the sleeve splits. ii) The thickness of the pads must be
uniform and parallel within .01 mm.
3) Remove the sleeve and the journal key. Evidence of brinelling on the pivot is
Protect the sleeve seat until the new sleeve unacceptable. The radius on the edge of
can be fitted as Para 7.6.2. the face should be 1.5mm.
b) Thrust Pad Stop
i) Examine for fretting on the shank and
head. If evident, re-new.
c) Thrust Seat
i) Examine for brinelling under the pivots.
If evident, re-new.
d) Thrust Disc
i) Check by lightly tapping that the
composite facings are correctly bonded
to the metal disc. Renew the disc
assembly if the composite plate is loose
i.e. if a ‘hollow’ sound is heard.
ii) Check the composite face is not badly
worn or scored.
iii) With the thrust disc mounted on a
suitable mandrel, check that the working
faces for both forward and reverse
thrusts are flat to within .025 mm.
e) Auxiliary Impeller (Fig. 7/15)
i) Measure and record the outside diameter
of the auxiliary impeller skirt.
ii) Ensure that the water passages are clear.
NOTE:(1)
The auxiliary impeller is an integral
part of the thrust disc.
NOTE:(2)
Figure 7/14 Journal Bearing Sleeve - Removal All parts containing composite must be
submerged until assembly.
f) Reverse Thrust Wear Ring.
7.4.3 Thrust and Reverse Thrust Bearing (Fig. i) Measure and record the bore of the
composite reverse thrust wear ring.
7/15)
ii) Subtract the outside diameter of the
CAUTION: thrust disc skirt from the bore of the
Thrust bearing pads must be retained in sets wear ring to establish the clearance.
and each pad numbered consecutively in a
iii) Compare the clearance obtained with
clockwise sequence, as viewed from the thrust
that specified in Section 1, Technical
end.
Data.
1) Remove the split cotter pin from the thrust iv) Re-new the reverse thrust wear ring if
pad stops. either the clearance is excessive or if the
2) Carefully remove the thrust pads from the composite has deteriorated.
thrust seat. v) To remove the wear ring, remove the
philidas nuts and the cap screws
3) Clean and dry all components.

7.17
SECTION 7
MAINTENANCE

Figure 7/15 Thrust Bearing Clearance

7.4.4 Impeller and Case Wear Rings (Fig.7/16)


1) Clean the impeller and the case wear rings e) Allow the wear ring to cool and shrink
and check them for damage. onto the impeller.
2) Subtract the impeller wear ring outer f) Drill new grub screw holes using a
diameter from the case wear ring bore, Tungsten Carbide tipped type drill.
allowing for any temperature difference and g) Tap for, and fit, new grub screws. Punch
compare with the clearance specified in lock on the inside of the impeller.
Section 1, Technical Data h) Machine the grub screws flush with wear
3) Check the hardened surface of the impeller ring.
wear ring. i) Check the impeller wear ring for
4) If necessary, renew the impeller wear rings as concentricity. If eccentric, machine the
follows:- wear ring, in situ, a maximum of 0.25mm.
The maximum wear ring clearance
a) Carefully machine away the old ring permitted is 2.03mm.
without damaging the impeller. If
necessary, clean up the wear ring seating. j) Re-balance the impeller. Refer to
Hayward Tyler for the balancing data.
b) Heat the new impeller wear ring until it is
considered sufficiently expanded to slide 5) If the impeller has been damaged or repaired,
on the impeller rim. Heat by playing a always check the dynamic unbalance.
gentle gas flame round the rim. 6) If the pump case wear ring requires renewal,
c) Lift the heated wear ring on to the impeller fit the new ring and secure using the six
rim, using suitable heat resistant tongs. socket head cap screws and lock washers.
d) Tap the wear ring down to its position on Tighten the screws in accordance with the
the impeller. torque figures detailed in Section 1.

7.18
SECTION 7
MAINTENANCE

Figure 7/16 Impeller & Case Wear Ring

7.19
SECTION 7
MAINTENANCE

3) That there is no apparent damage to the


7.4.5 Rotor Assembly windings or cable leads.
1) Clean and inspect for damage all keys, threads, 4) White insulating sleeve, (see detail para.7.6.6)
keyways and sleeve locking screws, located on is below the level of the XLP gland moulding.
the rotor shaft. The difference when new is approximately
2) Fit the impeller washer, impeller key, impeller, 0.65mm. If the nylon and XLP surfaces are
and impeller lock screw on to the pump end of flush, renew the complete tail moulding.
the shaft. 5) Immerse the complete stator in water of a
3) Fit the thrust disc key, thrust disc, spacer temperature below 20ºC ensuring that on the
washer and thrust nut on to the thrust end of lead cables the water reaches no higher than the
the shaft. inner face of the gland moulding.
4) Thoroughly clean the rotor shaft. 6) Check and record the insulation resistance
using a 1000V megger. If the resistance is
5) Check the shaft for run-out, as follows:- below 5 megohms, check carefully for breaks
a) Place the shaft on rollers that locate in the insulation. If a visual check is
between the journal sleeves and the short insufficient to locate a fault, check for the fault
circuit rings. as follows: -
b) Check the run-out along the shaft and a) With the stator still immersed in water, using
laminations; maximum run-out permissible a Flash-Tester, apply a voltage at one third
0.05mm. operating volts and gradually increase until
c) Check the run-out at the impeller wear ring; a visual indication of the fault location
maximum run-out permissible 0.125mm. appears. This should occur before the full
d) Check the run-out at the thrust disc; operational voltage is reached, but if it does
maximum run-out permissible 0.10mm. not, the voltage may be increased to 1.5
times operating voltage for a period not
e) Check the run-out at the journal bearing exceeding one minute. For operating
sleeves: maximum run-out permissible voltage, refer to Section 1 - Technical Data.
0.025mm.
NOTE
6) Check that the laminations, short circuit ring, DC high voltage testing of old windings at
rotor bars and balance rings are undamaged. values higher than 150% rated volts is not
recommended as further damage to aged
NOTE:
windings can occur causing premature
If any components on the rotating assembly
failure.
have been damaged, or renewed, the
complete rotating assembly must be 7.4.7 Motor Case and Cover
dynamically balanced within 5000 gm.mm.
Check the condition of the following: -
7) Take the rotor assembly off the rollers and
remove the impeller and thrust disc along with 1) The weld round the anti-rotation peg.
their connecting components. 2) The motor case and cover flanges.
8) Protect all parts of the rotor until required for 3) The baffle wear ring. With normal usage this
assembly. wear ring should not require renewal
7.4.6 Stator Assembly throughout the life of the unit. However, if it is
damaged, remove the screws and the tab
Unless an electrical fault is suspected, a visual washers and remove the wear ring.
inspection of the windings, followed by an
insulation check, fulfils normal requirements but 4) Faces of all pump case and motor cover nuts for
the following checks should be made: freedom from damage and burrs.

1) No slackness exists in wedges located at the 7.4.8 Terminal Boxes (Fig. 7/37)
bottom of the stator slot behind the cables. Check that the bursting discs are not ruptured and
2) Windings coils are taped together and secured the inside of the terminal box is dry.
to the support brackets. Damaged winding
tapes must be renewed to the procedure given
in para. 7.4.9.

7.20
SECTION 7
MAINTENANCE

7.4.9 General 7.4.9.3 Taping Outer Coils (Fig. 7/19)


Winding tapes must only be renewed with Heat Using one piece of Heat-set Nylon tape 18mm
Set Nylon 66 braided tape 18mm wide x 0.5mm wide x 0.5mm thick approximately 4.5m long,
thick. The taping knots must be secured with an bind and anchor the outer windings coils at the
epoxy resin adhesive, using only those grades stator end as follows: -
specified (see 'knot sealing'). No other grade of
NOTE:
adhesive is permitted.
Take extreme care when retaping not to
It is essential that the tapes are thoroughly dry damage the winding cable insulation
when the adhesive is used in sealing the knots covering.
because if the tapes are damp, the adhesive will
1) Place a smooth wedge of wood between the
not adhere successfully. The adhesive should
stator shell and the outer coil to hold the end
cover the knot completely but must not be
turns away from the shell and to allow the
indiscriminately smeared in the general vicinity
taping hook or needle to be inserted and slid
of the tape.
through.
7.4.9.1 Tools (Figs. 7/17 & 7/18) 2) Insert the taping hook between the stator shell
The following locally made tools should be used and coil towards the end plate. Bend the shank
to assist the tapering operation. of the hook as necessary to be seen or felt
behind the coil.
1) Make one taping hook (Fig. 7/17), from
∅2.4mm x 460mm long gas welding rod as 3) Using the hook tool, hook the tape up from the
follows: bottom and from behind coils, leaving at least
a) Bend the rod about 25mm from the end at a 250mm of tape free at the beginning of the
90 degrees angle. File and emery cloth band for knotting purposes.
smooth. 4) Starting from the centre of the coil, spiral wrap
b) Form the opposite end into a loop handle the tape around the conductors to form a band
giving the tool an approximate length of of two 50% overlaps of tape fully 50mm wide
300 to 350mm to cover the Nitrile rubber insets in the coil.
Sufficient tension should be applied to hold the
2) Make one flexible needle (Fig. 7/18), about conductors together.
255mm long, from ∅0.8mm steel or copper
wire. 5) Continue taping the coil to the anchorage
bracket, welded to the stator end plate, or
3) Bend the wire double leaving a small loop and winding support ring, whichever is fitted, using
solder the ends of the loop together. four spiral half-tape (50%) overlaps. (i.e. eight
a) File and smooth all edges- thickness’) of Nylon tape. The band should
again be made 50mm wide with enough tension
4) Wooden wedges (various sizes) smooth with
to prevent movement of the coils.
no sharp edges.
6)
7.4.9.2 Preparation
a) Tie the ends of the tape into a square (reef)
1) The winding coils are known as first and knot so that the knot is positioned on the
second and windings. The first (Fig. 7/19) outer edge of the coil as far as is practicable
being nearest the shell, the second (7/20) being and so that if pressed into the coil it would
nearer the bore. be between two cables, rather than pressing
2) Remove the existing wrapping tape from the on the top of one.
coils and ensure that the nitrile rubber inserts b) Cut the tape ends protruding from the knot
are in between the layers in the centre of the to 25mm long.
coils. c) Seal the knot with the approved epoxy resin
3) Thoroughly wash out the stator to remove any adhesive to prevent the knot from coming
foreign debris, such as magnetite or rust loose in accordance with para. 7.4.9.6.
deposits, from the windings. 7) Remove the wooden wedge(s), and any taping
4) Dry out the stator windings using a hot air fan tools.
heater positioned nearby; this is to ensure that
the new tape is kept clean and dry for knot
sealing.

7.21
Figure 7/17 Details of Taping Hook

7.22
SECTION 7
MAINTENANCE

Figure 7/18 Details of Taping Needle


SECTION 7
MAINTENANCE

Figure 7/19 Outer coil Taping

7.23
SECTION 7
MAINTENANCE

Figure 7/20 Inner Coil Taping

7.24
SECTION 7
MAINTENANCE

5) Bind and anchor the other two inner coil


7.4.9.4 Taping Inner Coils (Fig. 7/20)
bundles in a similar manner.
Bind the inner winding coils as follows:-
7.4.9.5 Taping the Lead Cables
1) Remove the damaged binding tape from one
Arrange and tape the connections and lead
of the inner coils.
cables in groups of three - two in a clockwise
2) Ensure that the nitrile rubber inserts are in direction and one in an anti-clockwise
position between the layers and the centre of direction, as follows:
the coil.
1) Anchor the cables in position to the windings
3) Bind the second coil bundles, using a length with four spiral half-laps of Heat-Set Nylon
of Heat-Set Nylon 66 braided tape 18mm 66 braided tape 18mm wide x 0.5mm thick.
wide x 0.5mm thick, approximately 2.75m
2) Make the band 50mm wide and tie the ends
long, as follows:-
into a square (reef) knot.
a) Thread one end of the tape on the needle
tool. 3) Cut the tape end to 25mm long and seal the
knot with an epoxy resin adhesive to prevent
b) Leave at least 250mm of tape at the
it becoming loose. the adhesive should
beginning of the band for knotting
completely cover the knot.
purposes.
c) Bind the coil bundle to form a 50mm wide 4) Make the last binding on the lead cable
band of two spiral half overlaps, four 300mm from the respective holes in the
layers thick. bearing housing.
d) Tie of the band with a square (reef) knot on 7.4.9.6 Knot Sealing (Fig 7/21)
the outside of the band , as shown, and so
1) Either of the following adhesives must be
that the final anchorage tape will not press
used to prevent the knots becoming loose.
the knot into the coil bundle.
a) Fast-setting epoxy resin adhesive:
e) Cut the bundle tape end 25mm from the
knot and seal the knot with epoxy resin AV/HV115, as supplied by CIBA-GEIGY
adhesive, as described in para. 7. (UK) LTD.
4) Anchor tape the inner coil bundle to the stator NOTE:
anchor bracket, or winding ring, whichever is A handipack kit comprising two tubes;
fitted, with a length of heat-set Nylon 66 one resin, the other hardener, known as
braided tape 18mm x 0.5mm thick, as 'Rapid Araldite' in the United Kingdom,
follows:- is generally equivalent to the above
specification.
a) Leave at least 250mm of tape at the
beginning of the band for knot tying b) Fast-setting epoxy resin adhesive XD738
purposes. as supplied by CIBA-GEIGY (UK) LTD.,
available in bulk containers.
b) Bind the coil bundle to the winding ring
anchor bracket loop, welded to the stator c) Alternatively use Ren Epoxy RP106/ H953.
with four spiral half-width overlaps, eight 2) Ensure that the tapes are thoroughly dry
layers off tape, with enough tension to hold before applying the adhesive.
the coil bundle in position away from the
stator bore. The complete anchorage 3) Mix and apply the adhesive in accordance
should be 50mm wide. with the manufacturer's instructions. Curing
c) Tie off the band using a square (reef) knot time of the adhesive is 3 to 6 hours.
positioned over the top outer coils of the 4) The adhesive should completely cover the
bundle, as shown. The knot should be knot.
located between two cables rather than
pressing on top of a cable. 5) Check adhesive does not have jagged edges
by smoothing with finger after dipping finger
NOTE: in water.
The knot must be tied on part of the tape
between the coils and the anchorage 6) Check that the adhesive has properly hardened
bracket on all knots before proceeding to further
operations.
d) Cut the tape ends 25mm from the knot and
seal with epoxy resin type adhesive as
described in Para. 7.4.9.6

7.25
SECTION 7
MAINTENANCE

2) Clean up the studs, and using a liquid dye


penetrant and/or magnetic particle
examination, examine for surface cracks,
particularly in the stud threads and thread run
out areas.
NOTE:
If there has been a history of leakage in
service from the joints and/or previous
recorded damage, remove and inspect at
least 10% of each flange stud.
3) Identify any corrosive deposits that may be
present, i.e. pitted areas etc., and if corrosion
is evident, consider its stress corrosion
influences. If any stud condition raises doubts
as to the stud's serviceability, renew all the
studs in the flange.
4) If necessary renew the studs as described in
para. 7.5.2
7.4.10.3 Studs on Extended Circulator Service
Life
If at the end of the circulator nominal service
life, or as otherwise defined, an extension of
circulating pump life is proposed, it is
recommended that all studs should be
renewed. However, should a request be made
for an extension to the life of the existing
Figure 7.21 Knot Sealing studs, then the following points must be
satisfied:-
7.4.10 Main Flange Stud Inspection 1) The general condition and surface integrity of
the studs must be satisfactory.
Stud inspection must be carried out in
accordance with the inspection cycles indicated 2) There should be adequate residual fatigue life
below. in the studs for the extended life proposed;
this can be obtained by suitable fatigue tests
7.4.10.1 Stud Inspection at each Flange carried out on a minimum of three studs
Breakdown selected at random from the pump case/motor
Whenever either the pump case/motor case or case joint.
the motor case/motor cover flange joint is
7.4.11 Repairs to Windings
broken, the exposed portion of all the flange
studs must be thoroughly inspected visually Always consult Hayward 'Tyler if any doubts
for indications of damage or corrosion, exist when repairing windings or making new
mainly in the form of pitting and cracks etc. joints.
Pitted or cracked studs must be renewed -
7.4.11.1 Rewinding the Motor
Para 7.5.2.
Contact Hayward Tyler for assistance should
7.4.10.2 Stud inspection at Pump Overhaul
major faults develop which necessitate a
At each convenient circulator overhaul complete rewind of the motor.
period, approximately 4 - 5 years, a
percentage of the studs must be given a non-
destructive examination, as follows:
1) Remove two random studs from the Pump
Case/Motor joint and any one stud from the
motor-case/motor-cover joint.

7.26
SECTION 7
MAINTENANCE

7.5 ASSEMBLY NOTES 3) Apply high temperature anti-seize compound


or silicone grease to the casing end of the
NOTE: stud.
In the event of new components being required
refer to the 'Parts List' on Sectional 4) Assemble the stud as follows: -
Arrangement Drawing (Page 7.43) and quote a) Screw the stud into the case until
the circulator Serial No.- stamped on the dimension ‘L’ measures 255 mm
motor nameplate - in all correspondence with b) Maintain the ends of the studs on a
Hayward Tyler. common plane to adjacent studs within 2
7.5.1 General mm, this is essential to prevent fouling of
the Hydraulic Stud Tensioner on the studs
1) Ensure that all the parts are free from grease either side of the stud being tensioned.
and oil.
NOTE:
2) Clean all the stud and screw holes. Inspect for When fitting an individual stud to an
and remove any burrs. assembled unit, screw the stud in until its
3) Check for full and free movement of bolts and protruded end is on the same plane as
screws by threading them by hand into their adjacent studs.
respective mating component prior to 5) When initially fitting the nut, prevent the stud
assembly. from turning and ensure the 255 mm
4) Torque wrenches must be calibrated before protrusion dimension is maintained.
use.
5) Tightening must be progressive and in a
diametrically opposed sequence
culminating at the required setting.
CAUTION:
Ensure that the torque is applied about the
axis of the screw by holding the socket and
wrench square to the screw head.
6) Threads inside the motor and pump cases
must only be lubricated with glycol or
glycerine.
7) External threads e.g. pump case and motor
cover studs are to be lubricated with silicone
grease.
8) Socket head cap screws must be punch locked,
unless lock washers or spring washers are
used.
9) Always use new spring / lock washers, as
applicable.
7.5.2 Assembly of Main Flange Studs
Renew damaged or corroded studs, with
reference to Fig. 7/22 and in accordance with
the following instructions.
1) Thoroughly clean the threads in the case with
a suitable solvent and/or by wire brushing.
Remove any very hard encrustation in the
threads by running down a tap but this should
be used only as a last resort.
2) Check the replacement studs for damage to
the threads or protective coating during
transit. Renovate or reject damaged studs as Figure 7/22 Assembly of Flange Studs
necessary.

7.27
SECTION 7
MAINTENANCE

7.5.3 Wire Locking


Hexagon headed bolts and screws must be
wirelocked in groups of three, (Fig. 7/23, details
A, B & C), in accordance with the following
instructions:-
1) Bend a 460mm length of wire into two equal
lengths and insert one leg through the bolt
head hole, as shown in detail A.
2) Using the wire twister tool, twist the wires
together at the rate of between 6 and 12 turns
to 25mm, ensuring that no undue strain
occurs. Bring the twist to within 3mm, of the
next bolt head, and with the wire held taut,
insert one leg of the wire into the head and
pass the other wire around the hexagon, as
shown in detail B. Press the outside leg of the
wire close to the bolt-head and twist the wire
as described.
3) After threading the wire through the third
bolt-head, twist the two legs of the wire
together for a further 25mm. Cut off the
excess and bend the tail around the bolt head,
as shown in detail C.

1. Open the jaws of the pliers by squeezing the


handles together and moving perforated
slider, at the centre of the pliers, forward, to
release the lock hook.
2. Grip both legs of the wire in the pliers’
jaws. Squeeze the plier handles together
and pull the perforated slider rearwards to
lock pliers by the hook lock.
3. Twist the locking wire by pulling the twist
knob and twist rod out of the pliers, letting
the pliers spin free as shown.
4. Return the twist rod by holding the pliers
steady with one hand and pushing the flat of
the other hand against the end of the knob.
5. Repeat twisting cycles as necessary.

Figure 7/23 Wire Locking

7.28
SECTION 7
MAINTENANCE

d) Position the securing rings, on the housings


and tilting pads. Check that the pads are
free to pivot. Secure the ring with the
7.6 ASSEMBLY screws using lock washers as applicable.
Assemble the components to the motor as NOTE:
follows: - The tilting pads are numbered to
identify each set and marked with an
7.6.1 Stator Shell and Journal Bearings
arrow to indicate the rotational
1) Fit the journal bearings (Fig. 7/24) as direction.
follows:- e) Check that the pads are free to tilt slightly
a) Fit the two bearing anti-rotational stop pegs when the trailing edge is depressed. If
in each bearing ring. there is no movement, remove the pads and
b) Fit the bearing rings in the bearing grind the spacers on the side to allow a
housings. tilting action.
c) Assemble the tilting pads in the correct f) Torque tighten the screws.
sequence, against the bearing ring housing.

Figure 7/24 Journal bearing - Assembly

7.29
SECTION 7
MAINTENANCE

3) Prepare the stator shell, complete with pump-


2) Install the pump-end bearing housing to the
end bearing housing, for insertion in the
stator shell, (Fig. 7/25) as follows: -
motor case as follows: -
a) Lay the stator shell horizontally and wedge
firmly. NOTE:
The cover-end bearing housing and the
b) Clean the mating surfaces of the stator
reverse thrust housing are temporarily
shell ends and the bearing housing.
fitted at this stage to provide the means of
c) If previously removed, insert the housing lifting the stator assembly into the motor
lock rings in their respective end of the case.
stator shell observing the matching up
a) Fit an eyebolt to the cover-end bearing
marks for screws.
housing periphery. Sling and lift the
d) Fit the split rings in their grooves in the bearing housing to the stator shell.
stator shell.
b) Ensure that the terminals and cables are
e) Pull the bearing housing lock rings up to stowed in the stator bore and temporarily
the split rings, and secure the lock rings to fit the cover-end bearing housing, securing
the stator shell with socket-headed cap with the socket-headed cap screws. Tighten
screws. the screws.
f) Fit an eyebolt to the periphery of the pump c) Temporarily fit the reverse thrust housing,
end bearing housing. Attach a shackle and securing with the socket-headed cap
sling and lift the bearing housing to the screws. Tighten the screws.
stator end opposite to the end with the
d) Using chalk marks, transfer the radial
cable leads.
location of the anti-rotation peg from the
g) Align the slot in the pump-end bearing pump-end bearing housing along the stator
housing with the anti-rotation peg match shell to the cover-end bearing housing.
marks on the stator shell, and locate the
NOTE:
housing in the shell.
The anti-rotation peg slot should line up
h) Fit the socket-headed cap screws and lock with the centre gland hole in the stator
washers to secure the pump-end bearing shell.
housing to the stator shell and torque
e) Ensure that the motor case is in a true
tighten.
vertical position, with the pump end
downwards, and stable.

Figure 7/25 Stator Assembly

7.30
SECTION 7
MAINTENANCE

4) Install the stator assembly in the motor case


(Fig. 7/11) as follows: -
CAUTION
Do not damage the chamfered register on
the pump end bearing housing when
handling the stator assembly. Before
leaning over the motor ensure that you
remove headgear and any other objects
liable to drop into the motor case.
a) Attach eyebolts and lifting tackle to the
reverse thrust housing.
b) Carefully raise the stator assembly over the
motor case. Align the chalk marks made in
operation 3(c) and lower it vertically into
the motor case.
c) Raise the stator assembly approximately
3mm and try and turn the stator in the
direction the starting torque is applied,
against the anti-rotation stop peg. If the
peg stops the stator from turning, lower the
stator back onto its register.
d) Remove the reverse thrust housing and
cover-end bearing housing from the stator
and withdraw the cable leads from the
stator bore. (The removal of the cover-end
bearing housing is the reversal of its
temporary fitting.).
7.6.2 Journal Sleeves (Fig. 7/26)
1) If a journal sleeve has been removed, fit a new
sleeve as follows: -
a) Clean the journal seat and the bore of the
journal sleeve.
b) Re-fit the sleeve key and ensure that the
journal locking screw is below the shaft Figure 7/26 Journal Sleeves
surface.
c) Heat the new sleeve in water at a
temperature of 80°C for 15 minutes then 7.6.3 Rotor Assembly (Fig 7/9)
quickly slide the sleeve into position on the 1) Attach an eyebolt, shackle and sling, to the
shaft, tapping it home with a soft faced thrust end of rotor assembly.
hammer.
d) To secure and lock the sleeve after it has 2) Ensure that the winding cable leads do not
cooled, unscrew the locking screw. foul the stator bore.
CAUTION: 3) Carefully raise the rotor assembly vertically
Too much force applied to the locking over the stator bore. Lower into the stator,
screw could result in a damaged sleeve. resting the shaft at the impeller end in its
e) Check the bearing clearances as detailed in approximate final position on a wooden block
Para. 7.4.1. supported by a screw or hydraulic jack.
4) Remove the lifting tackle but leave the
eyebolt fitted.

7.31
SECTION 7
MAINTENANCE

7.6.4 Terminal Glands (Fig 7/27) 6) Fit new 'O' rings and back up rings in the
inner casing recesses. Make sure that the 'O'
CAUTION: ring is below the back-up ring, i.e. nearest the
Always fit new ‘O’-rings and back-up rings motor. Sparingly coat the ‘O’ rings and back-
whenever assembling glands. up rings with silicone grease.
1) Observing the colour identification, pass the 7) Carefully slide the complete assembly into the
gland moulding complete with back-up sleeve motor case, until firmly seated on the support
and two belleville washers, through the hole ring, belleville washers and back-up sleeve.
in the motor casing
NOTE:
2) Clean all components, particularly the 'O'-ring If the rings are improperly fitted,
recesses. considerable pressure will be necessary to
3) Apply a light coating of non-conductive force the inner casing into the motor case
silicone grease to the gland moulding and and either the back-up rings or 'O'-rings
white insulating sleeve. will be damaged. Also never hammer the
end of the terminal stem if the assembly is a
4) Fit a new ‘O’ ring in the inner casing neck and tight fit in the inner casing.
slide the inner casing over the insulating
sleeve and gland moulding, until the gland 8) Fit the gland nut and tighten. A torque of
moulding is fully located inside the inner 100Nm should be sufficient.
casing. 9) Ensure that there are no tight bends in the
5) Fit the 'C' shaped support ring on the lead cable and that the cable protective sleeves are
cable beneath the Belleville washers as correctly positioned. Check the lead cable
indicated. binding is in good order and keep the lead
cables well away from the stator bore

Figure 7/27 Terminal Gland - Assembly

7.32
SECTION 7
MAINTENANCE

7.6.5 Cover End Bearing Assembly (Fig. 7/28)


NOTE:
1) Make sure that the screw holes in the stator
a) Fit a new 'O' ring to the periphery of the lock ring do not line up with any of the
cover-end bearing housing. bearing housing screws.
b) Using the lifting eyebolts, hoist the bearing 5) Using the hexagon-headed screws, draw the
housing to just above the motor case and lock ring up to and over the split ring. Torque
protruding rotor shaft. the screws and wire lock in groups of three.
2) Re-fit the cover-end bearing housing using 6) Assemble the thrust bearings, as follows: -
guide rods and observing the correct location
match marks. Make sure that the housing a) With the thrust seat standing edge-wise, fit
seats evenly all round. the thrust pads, in their correct sequence on
the seat with the thrust pad stops and the
3) Re-fit the socket-headed cap screws and lock split pins.
washers and torque tighten.
CAUTION:
4) Position the stator lock ring in the motor case Pads are supplied as sets and must not be
and fit the split ring. mixed.

Figure 7/28B Cover End Bearing Assembly


Figure 7/28A Cover End Bearing Assembly

7.33
SECTION 7
MAINTENANCE

b) Ensure that the thrust pads tilt freely to


form a liquid wedge with the thrust disc,
with the point of the wedge in the direction
of rotation.
c) Centre the thrust seat, Fig.7/28 detail B,
complete with the thrust pads, on the cover
end bearing housing. Assemble with the
socket-headed cap screws and spring
washers. Torque the screws.
NOTE:
If the thrust pads reclaimed by grinding
are fitted, a shim, the thickness of the metal
removed, must be fitted between the thrust
seat and bearing housing. This is to ensure
that the rotor laminations remain
centralised with the stator laminations.
7) Fit the thrust disc key to the rotor shaft.
CAUTION:
Before fitting the thrust disc ensure that the
thrust disc and thrust pad contacting
surfaces are scrupulously clean.
8) Fit the thrust disc as follows: -
a) Extend the jack beneath the rotor assembly
to raise the rotor higher than normal.
b) Lower the thrust disc on to the shaft and
key. Once the disc is located on the shaft,
lower it smartly to ensure that it seats
firmly against the shaft.
c) Fit the thrust disc spacer washer.
d) Fit the thrust nut. Hand tighten the thrust Figure 7/28C Cover End Bearing Assembly
nut until the thrust disc has no movement.
e) Lower the jack until the thrust disc is
seating positively on the thrust pads.
f) Tighten the thrust nut and fit the split pin as 9) Fit the reverse thrust seat housing (Fig 7/28C)
follows:- as follows: -
i) Using the castellated wrench, supplied in a) Ensure that the reverse thrust components
the tool kit, and by un-assisted manual are scrupulously clean.
strength only, tighten the nut as far as b) Fit the composite reverse thrust wear ring
possible. to the reverse thrust housing, the radial
ii) Remove the wrench and radially match grooves outwards, using the six socket-
mark the top of the shaft and nut. headed cap screws and the Philidas nuts.
iii) Re-fit the wrench and ‘slog’ tighten the CAUTION:
nut until one of the castellations (cut- Avoid damaging the composite ring when
outs) in the nut lines up with the split-pin tightening the screws.
hole in the shaft.
c) Fit the assembled reverse thrust housing
iv) Check that the nut has turned at least using the socket-headed cap screws and
3mm from the match marked position. If spring washers.
this tightness is not obtained, re-slog the
d) Torque tighten the screws.
nut up until the next hole lines up
(maximum 12mm further). 10) Check the rotor end float, as detailed in
v) Fit the split pin and splay the legs to 7.6.6., before completing the reverse thrust
wrap around the nut. housing assembly.

7.34
SECTION 7
MAINTENANCE

Figure 7/28 End Float Check (Typical Method)

7.35
SECTION 7
MAINTENANCE

7.6.6 Checking End Float (Fig. 7/29)


7.6.6.3 End float adjustment
There are two methods of checking the rotor
end float, a recommended method using a dial 1) Below limits: If the dimension obtained is
indicator or if such an instrument is not below the specified limit (Section 1) remove
available, an alternative method with a the reverse thrust plate and either:
straightedge and feeler gauges. a) Method 1
7.6.6.1 Recommended method - Dial Indicator Make a steel shim to fit between the reverse
1) Make sure that the thrust disc is seating on the thrust plate and the cover-end bearing
thrust pads. housing, the shim thickness to bring the end-
float within limits.
2) Set up a dial indicator as follows:
Or
a) Set up the dial indicator on the top of the
reverse thrust housing, using a magnetic b) Method 2
block to hold the indicator to the housing. Lightly machine the face of the reverse thrust
b) Set the indicator to record any vertical housing where it makes contact with the
movement of the rotor using a suitable reverse wear ring. The amount machined is
spacer if necessary. determined by the difference between actual
c) Set the indicator dial to zero. measurement and the required end-float.

3) Using the jack beneath the rotor, raise the 2) Above limit: if the end-float exceeds the
rotor, complete with thrust disc, until the specified limit, remove the reverse thrust
thrust disc is positively in contact with the housing and either:-
underside of the reverse thrust plate. a) Method 1
4) Check the dial indicator reading: the reading i) Remove the reverse thrust wear ring from
is the amount of end-float. The end-float the reverse thrust housing.
must conform to that specified in Section 1 - ii) Make a steel shim of a thickness to bring
Technical Data the excess end float within limit, and fit
between the reverse thrust wear ring and
5) Adjust the end float, if necessary, as described the housing.
in operation 3 - End Float Adjustment.
b) Method 2
6) When the end float is satisfactory, fit all the i) Lightly machine the outer face of the
twelve socket-headed cap screws and lock reverse thrust housing where it contacts
washers in the reverse thrust housing. Torque the cover-end bearing housing.
tighten the screws.
ii) Re-fit the reverse thrust wear ring with
7.6.6.2 Alternative method - Feeler Gauges the six socket-headed cap screws and
1) Check that the rotor assembly is supported by Philidas. Torque tighten the screws.
the thrust pads. 3) Fit the reverse thrust housing finally to the
2) Place a straight edge across the reverse thrust bearing housing with the twelve socket
seat housing. Using a suitable spacer resting headed screws and lock washers. Torque
on the rotor and long enough to reach to tighten the screws.
within 10mm. of the underside of the straight 7.6.7 Motor Cover Filter – Assembly (Fig 7/30)
edge, measure with feeler gauges and record
the exact clearance between, and straight 1) Fit the filter assembly as follows:-
edge. Dimension Y. a) Offer the filter assembly to the reverse
thrust housing.
3) Using the jack beneath the rotor, raise the
rotor until the thrust disc is in positive contact b) Secure with the hexagon-head screws and
with the underside of the reverse thrust pads. lock washers and torque tighten.

4) Measure and record the exact clearance 2) Fit the motor cover as follows:-
between spacer and straight edge, dimension a) Ensure that the flange faces are
X. The difference between Dimension X and scrupulously clean.
Y is the end float. See Section 1, Technical b) Position a new flexitallic spiral wound
Data, for limits. gasket in the motor case recess.
NOTE: c) Using lifting tackle, lower the cover into
As a further alternative, a straight edge position on the motor case flange, aligning
and depth gauge can be used. the case/cover match marks.

7.36
SECTION 7
MAINTENANCE

NOTE: 3) Using two cranes and slings, lift the motor


If the cover does not seat correctly, raise it from the building stand and lower the motor
again and check that the gasket has not into a horizontal position, terminal stems
been damaged. uppermost (see Fig.7/5). Chock to prevent
d) Coat the threads of the studs and nuts with movement.
anti-seize compound or silicone grease. Fit 4) Blank-off all the motor case openings until the
and hand tighten the nuts. unit is installed.
e) Tension the studs as detailed in Section 8.

Figure 7/30 Motor Cover and Filter Assembly

7.37
SECTION 7
MAINTENANCE

Figure 7/31 Terminal Box

7.38
SECTION 7
MAINTENANCE

Figure 7/32 Terminal Link Insulation

7.39
SECTION 7
MAINTENANCE

7.6.8 Terminal Boxes (Fig. 7/31, 32, 33)


Fit the terminal boxes as follows: -
1) Ensure that the neoprene gasket is located on
the terminal box support.
2) Using the lifting tackle on the terminal box
eyebolt hoist the terminal box onto the
terminal box support and secure with nuts and
washers.
3) Fit each terminal link as follows: -
a) Connect the terminal link clamp connector
to the terminal gland stem with the socket
headed cap screws and nuts.
4) Insulate the terminal connecting links with
reference to Fig. 7/32 as follows: -
a) Cover the complete length of the
connecting link including the terminal
clamp connector with 3M No. 70 silicone
thermosetting tape to a minimum thickness
of 3mm in three staggered layers.
b) Slide a length of heat shrink tubing over
the insulated section and, as far onto the
clamp connector as possible removing all
wrinkles.
c) Using a hot air gun or propane gas torch
operating at a temperature of 150°C, heat
the tubing and working outwards from the
centre, heat shrink until a tight fit over the
taped area.
5) Re-fit the respective terminal link ends to the
terminal block, and secure with washers and
nuts.
6) Check that the bursting discs are intact. The
details of the bursting disc assembly are
shown as an exploded view in Fig 7/33.
7) Re-new the cover gasket.
8) Fit the terminal box cover and secure with
nuts and washers to protect the terminal stems
until the main supply cables are fitted.
Figure 7/33 Bursting Disc Details
9) Temporarily fit and secure the terminal box
cover until the main supply cables are fitted.

7.40
SECTION 7
MAINTENANCE

Figure 7/34 Impeller Setting

7.41
SECTION 7
MAINTENANCE

7.6.9 Baffle Wear Ring (Fig.7/34)


6) Draw the impeller and rotor assembly
If the baffle wear ring has been removed, re-fit forwards until the thrust disc rests upon the
as follows: - thrust pads.
1) Place the ring on the integral baffle and attach 7) Measure the dimension between the top of the
with the socket-headed cap screws and lock impeller and the pump/motor case flange
washers. (Dimension ‘Z’ shown in Fig. 7/34). Adjust
2) Torque tighten the screws. the thickness of the impeller washer as
necessary, to obtain the dimension given in
7.6.10 Main Impeller (Fig. 7/34) Section 1.4 - Technical Data.
Fit the impeller as follows: - 8) Re-new the locking screw, torque tighten and
1) Remove the protective impeller nut and fit the punch lock.
impeller key. 9) If the unit is to be stored, cover the impeller
2) Fit the impeller washer with the internal with the transit canister and the flanges with
chamfer towards the shaft shoulder. the flange covers. Slowly fill the motor with
inhibitor through the inhibitor filling valve.
3) Coat the threads of the left-hand threaded
impeller screw with silicone grease, then re-fit 7.6.11 Heat Exchanger
the impeller and the impeller nut Ensure that the heat exchanger is serviceable
4) Check that the gap between the key and the before refitting as described Para. 4.3 – Section
top of the impeller hub does not exceed 4
0.25mm.
5) Using the special impeller nut spanner and 7.7 RE-INSTALLATION OF MOTOR
tommy bar, supplied in the tool kit, and a
The re-installation of the motor assembly to the
lead-faced hammer, tighten the impeller nut.
pump case is carried out in accordance with the
NOTE: installation procedure described in Section 4,
The impeller nut has a left-handed thread. para. 4.3
Do not use any leverage in the water
passages of the impeller to oppose force
exerted by the spanner, the weight of the
rotor will oppose rotation if the spanner is
given a few heavy blows with a lead-faced
hammer.

7.42
SECTION 7
MAINTENANCE

PARTS LIST – SECTIONAL ARRANGEMENT

ITEM NO. PART NO. DESCRIPTION QTY.


1 42789/1003 PUMP CASE 1
2 16884M16/50 SKT HEAD CAP SCREW 1
3 42789/1010 CASE WEAR RING 1
4 42789/1202 IMPELLER NUT 1
5 42789/1401 IMPELLER 1
6 42789/1204 IMPELLER KEY 1
7 42789/2030 BAFFLE WEAR RING 1
8 16884M12/35 SKT HEAD CAP SCREW 6
9 42577/212 NORDLOCK WASHER 6 PR
10 42488/433 GASKET - PUMP/MOTOR FLANGE 1
11 42789/1801 PUMP END BEARING HOUSING 1
12 42789/1227 JOURNAL SLEEVE 2
13 42789/1806 JOURNAL TILTING PAD ASSEMBLY 2 SETS
14 42401/111 HEAT EXCHANGER SPOOL PIECE 2
15 16884M12/60 SKT HEAD CAP SCREW 12
16 42577/212 NORDLOCK WASHER 12 PR
17 42789/1704 BEARING RING 2
18 42789/2108 SPLIT RING – STATOR SHELL 3
19 42789/2111 BEARING HOUSING LOCK RING 2
20 16884M10/55 SKT HEAD CAP SCREW 8
21 42577/210 NORDLOCK WASHER 8 PR
22 42789/1805 SECURING RING- PUMP END 1
23 42789/2101 STATOR SHELL 1
24 42789/2110 STATOR KEY 1
25 42789/2104 STATOR LAMINATION 805 MM
26 42789/2105 STATOR END PLATE 2
27 42789/1705 SECURING RING - COVER END 1
28 16801M10/55 HEX HD SCREW 8
29 42577/210 NORDLOCK WASHER 8 PR
30 16884M6/12 SKT HEAD CAP SCREW 6
31 42789/1701 COVER END BEARING HOUSING 1
32 42789/1601 THRUST SEAT 1
33 42789/1605 THRUST PAD STOP 12
34 167WBDGJ62M0 SPLIT PIN 12
35 42789/1603 THRUST PAD 12
36 42789/1501 THRUST DISC 1
37 16884M12/120 SKT HEAD CAP SCREW 12
38 17207M12 SINGLE COIL SPRING WASHER 12
39 42789/003 TERMINAL BOX ASSEMBLY 3
40 42488/431 FLEXITALLIC GASKET – MOTOR COVER 1
41 42789/2028 STUD – MOTOR CASE/MOTOR COVER 16
42 42789/2029 NUT – MOTOR CASE/MOTOR COVER 16
43 16884M6/45 SKT HEAD CAP SCREW 6
44 16526M6 PHILIDAS NUT 6
45 42789/1242 THRUST NUT SPACER 1
46 42789/1243 THRUST NUT 1
47 42789/1205 THRUST DISC KEY 1
48 42789/028 FILTER ASSEMBLY 1
49 167WBCNN10M0 SPLIT PIN 1
50 42789/2502 REVERSE THRUST PLATE 1
51 42789/2501 REVERSE THRUST HOUSING 1
52 42789/1901 MOTOR COVER 1
53 16201M10/45 HEX HEAD SCREW 6
54 42577/210 NORDLOCK WASHER 6 PR
55 42401/112 FILL & DRAIN SPOOL PIECE 1
56 16884M8/25 SKT HEAD CAP SCREW 6

7.43
SECTION 7
MAINTENANCE

57 17207M8 SINGLE COIL SPRING WASHER 6


58 42789/2910 STATOR LOCKING SCREW 18
59 169XYNFB LOCKING WIRE A:R
60 42789/2903 SPLIT RING – STATOR LOCK RING 1
61 42789/2904 STATOR LOCK RING 1
62 16884M12/90 SKT HEAD CAP SCREW 12
63 42577/212 NORDLOCK WASHER 12 PR
64 42789/1711 ‘O’ RING – BEARING HOUSING 1
65 40744/123 WINDING SUPPORT BRACKET 6
66 42789/013 ROTOR ASSEMBLY 1
67 42789/2125 WINDING CABLE 3
68 42789/2001 MOTOR CASE 1
69 42401/112 PRESSURE GAUGE SPOOL PIECE 1
70 16884M6/12 SKT HEAD CAP SCREW 1
71 36810/185 LOCKING PIECE - SPLIT RING 1
72 42789/1208 JOURNAL SLEEVE KEY 2
73 42789/1710 ANTI-ROTATION PIN 4
74 42789/1209 JOURNAL LOCKING SCREW 2
75 42789/2017 ANTI-ROTATION PEG 1
76 42789/2016 THERMOMETER POCKET 1
77 42789/2015 THERMOWELL 2
78 42789/2016 TEMPERATURE SWITCH POCKET 2
79 42789/1018 NUT – PUMP/MOTOR CASE 18
80 42789/1018 STUD – PUMP/MOTOR CASE 18
81 42789/1201 IMPELLER WASHER 1
82 16884M10/55 SKT HEAD CAP SCREW 6
83 42577/210 NORDLOCK WASHER 6 PR
84 38882/102 GRUBSCREW 3
85 42789/1405 IMPELLER WEAR RING 1

PARTS NOT ILLUSTRATED

ITEM NO DESCRIPTION QUANTITY

42554/035 FILLING VALVE ASSEMBLY (TRANSIT ONLY) 1

INSTRUMENTS

ITEM NO DESCRIPTION QUANTITY

42401/156 JUNCTION BOX – TEMPERATURE SWITCH 1


42401/157 JUNCTION BOX – THERMOCOUPLES 1
42401/201 FLOW METER 1
42646/203 THERMOCOUPLE – PUMP SUCTION MANIFOLD 1
42646/203 THERMOCOUPLE – PUMP CASE 1
42401/204 TEMPERATURE SWITCH 2
42401/205 THERMOMETER 1
42401/206 THERMOCOUPLE – MOTOR CAVITY 1
42401/207 PRESSURE GAUGE – MOTOR CAVITY 1
42478/117 DIFFERENTIAL PRESSURE TRANSMITTER WITH MANIFOLD 2

7.44
SECTION 7
MAINTENANCE

PARTS LIST - TERMINAL GLAND

TERMINAL GLAND ASSEMBLY - 3 OFF - EACH COMPRISING:

PART NO. DESCRIPTION QTY.


42789/2320 THREADED BUSH (GLAND NUT) 1
42789/2314 INNER CASING 1
42789/2315 SUPPORT RING 1
42789/2331 ‘O’ RING (CABLE GLAND) 2
42789/2333 ‘O’ RING (STEM) 1
42789/2332 SPIRAL BACK-UP RING 2
42789/2313 BELLEVILLE WASHER 2
42789/2312 BACK UP SLEEVE 1
SP42789/023 GLAND MOULDING AND CABLE ASSEMBLY 1

PARTS LIST - TERMINAL BOX

ITEM No PART NO. DESCRIPTION QTY


.
SP42789/027 TERMINAL BOX ASSEMBLY- EACH COMPRISING 3

1 42789/2705 GASKET-TERMINAL BOX SUPPORT 1


2 16012M10/25 STUD- TERMINAL BOX SUPPORT 12
3 17207M10 SHAKEPROOF WASHER - TERMINAL BOX SUPPORT 12
4 16501M10 NUT- TERMINAL BOX SUPPORT 12
5 SP42789/023 TERMINAL GLAND ASSEMBLY 1
6 16220M12 EYEBOLT 1
7 42789/2701 TERMINAL BOX 1
8 - FLASHPLATE ASSEMBLY 1
9 42789/2708 GASKET - TERMINAL BOX COVER 1
10 16012M10/25 STUD- TERMINAL BOX COVER 26
11 17207M10 WASHER- TERMINAL BOX COVER 26
12 16501M10 NUT- TERMINAL BOX COVER 26
13 42789/2707 TERMINAL BOX COVER 1
14 16220M12 EYEBOLT 1
15 42789/2732 TERMINAL LINK ASSEMBLY 3
16 42715/2721 TUBULAR LUG SOCKET 1
17 16884M6/50 SKT HEAD CAP SCREW – BURSTING DISC HOUSING 8
18 42789/2723 BURSTING DISC 2
19 42789/2713 PANEL DESSICATOR 1
20 42789/2711 GASKET – GLAND PLATE 1
21 16012M10/35 STUD - CABLE ENTRY PLATE 4
22 17207M10 WASHER - CABLE ENTRY PLATE 4
23 16501M10 NUT - CABLE ENTRY PLATE 4
24 42715/2740 CABLE GLAND 1
25 42789/2741 GLAND PLATE 1
26 42789/2720 NUT – TERMINAL SCREW 10
27 42789/2719 WASHER – TERMINAL SCREW 8
28 - EPOXY RESIN -
29 16884M12/55 SKT HEAD CAP SCREW – TERMINAL BLOCK 2
30 42789/2717 TERMINAL BLOCK ASSEMBLY 1

7.45
SECTION 7
MAINTENANCE

SPARES PARTS –COMMISSIONING

PART NO. DESCRIPTION QTY *


42789/2333 SMALL ‘O’ RING - TERMINAL GLAND 3
42789/2331 LARGE ‘O’ RING - TERMINAL GLAND 6
42789/2332 BACK-UP RING - TERMINAL GLAND 6
42488/431 GASKET - MOTOR COVER 1
42488/433 GASKET - PUMP / MOTOR 1
39930/207 GASKET – FILLING VALVE (HP) 1

* QUANTITIES ARE PER UNIT

7.46
SECTION 7
MAINTENANCE

Figure 7/35 General Arrangement

7.47
SECTION 7
MAINTENANCE

Fig. 7/36 Sectional Arrangement

7.48
SECTION 7
MAINTENANCE

Fig. 7/37 Terminal Box Arrangement

7.49
SECTION 7
MAINTENANCE

Fig. 7/38 Tool Kit List

7.50
SECTION 8
STUD TENSIONING EQUIPMENT

CONTENTS

PARAGRAPH PAGE

8.1 INTRODUCTION 8.2

8.2 APPLICATION 8.2

8.3 DESCRIPTION 8.2

8.4 ASSEMBLING THE STUD TENSIONER 8.3

8.5 REPLENISHING THE PUMP TANK 8.6

8.6 INDEXING 8.6

8.7 SAFETY PROCEDURES 8.7

8.8 TIGHTENING THE FLANGE NUTS 8.7

8.9 RELEASING FLANGE NUTS 8.8

PARTS LIST 8.11

ILLUSTRATIONS

FIGURE 8/1 HYDRAULIC STUD TENSIONING EQUIPMENT 8.1

FIGURE 8/2 SINGLE PISTON STUD TENSIONER (EXPLODED VIEW) 8.4

FIGURE 8/3 SINGLE PISTON STUD TENSIONER (GENERAL ARRANGEMENT) 8.5

FIGURE 8/4 QUICK RELEASE COUPLING 8.6

FIGURE 8/5 NUT TIGHTENING SEQUENCE 8.9

NUT TIGHTENING SEQUENCE (CONTINUED) 8.10

8.0
SECTION 8
STUD TENSIONING EQUIPMENT

Figure 8/1 Hydraulic Stud Tensioning Equipment

8.1
SECTION 8
STUD TENSIONING EQUIPMENT

8.1 INTRODUCTION 8.3.2 Hand Pump


All items mentioned herein relate to the M56 Stud The stud tensioner equipment hydraulic
Tensioner Equipment supplied as a comprehensive pump is a hand operated, dual piston, high
kit. This must be used ONLY in conjunction with pressure unit. Initially, both low and high
the circulator manual for the equipment supplied pressure flow is applied at each pump handle
for the specific contract. stroke until the tensioning head starts to take
load, when the high pressure application
continues and the low pressure is diverted
8.2 APPLICATION back to the oil reservoir. Re-setting of the
The physical dimensions of the pump case/motor low and high pressure takes place
case joint and the motor case/cover joint prevent automatically allowing the pump to operate
adequate pressure sealing by hand-tightened nuts. with maximum efficiency at all times.
For these applications, hydraulically operated stud Pressure limiting valves trip when the
tensioner heads are supplied with each contract. pressure exceeds the pump capacity.
The tensioner heads stretch the studs and the nuts The pump body contains the oil reservoir,
are then tightened down by hand. When the incorporating an oil filter plug and oil
tension on the stud is released, the load is pressure return valve for variable pressure
transferred to the nut to give the required tightness. release, the pump handle, gauge and quick
When working on a circulator flange joint, all the release high pressure hoses complete the
heads are employed simultaneously, each being assembly. All the pump components are
diametrically opposed. The heads are positioned easy to dismantle for servicing.
on the studs in a prescribed sequence, and are 8.3.3 Stud Tensioner Heads
pressurised to specified limit in accordance with
each of five consecutive stud tensioning The stud tensioner heads each comprise a
programmes. As the studs are progressively bridge that fits over the stud and stud nut to
tensioned, the mating flanges are drawn together, seat on the flange and is retained by the
so allowing the circulator flange nuts to be bridge retainer. A tensioner body
tightened or released. incorporating a seal, sits on the bridge and is
held in position by the threaded insert,
screwed on the stud. The head is
8.3 DESCRIPTION (FIG. 8/1) hydraulically pressurised via a quick release
The Hydraulic Stud Tensioner Equipment coupling and high pressure hose.
comprises three principal components: - Three of the four heads have two connectors
1) Tensioner head assembly, including the fitted. The fourth head has one connector and
bridge, tensioner body and piston and threaded one blanking plug. The fourth head is
insert (see Fig. 8/3). always the last in line in the system, the other
heads are interconnected.
2) Hand-pump - including oil reservoir.
8.3.4 Operation
3) High Pressure Couplings, hoses and pressure
gauge. When the hydraulic pressure, in accordance
with the stud tensioning program, is applied to
Four metal rods are provided in the kit. One end of the tensioner head, the body reacts against the
the rod is used for tightening the threaded inserts threaded insert which in turn stretches the
when installing the heads. The other end is used stud. While the stud is stretched, the stud nut
for pulling down the flange nuts. is hand tightened, using the bar provided in
Although each Stud Tensioner is operable by one the kit.
engineer, this practice is not recommended due to
weight and environmental criteria.

8.2
SECTION 8
STUD TENSIONING EQUIPMENT

Having hand tightened the stud nut, the hydraulic NOTE:


pressure on the tensioning head piston is gradually The bridge base circumference should
released, via the hand pump oil return valve, and sit flatly against the surface against
the load is transferred to the stud nut to give the which it is being tensioned.
required tightness. The threaded inserts are
5) Attach each threaded insert into the bolt
unscrewed from the studs and the heads are
tensioners by screwing onto the threads
transferred to the next studs in the tightening
protruding above each nut. Screw down
sequence.
the inserts using the tommy bars supplied
with the equipment, until contact with the
8.4 ASSEMBLING THE STUD TENSIONER load cells is achieved.
(FIG. 8/3) CAUTION:
The hand pump and its accessory hoses are Body and piston seals will be damaged
normally provided, in the toolbox, already if the piston protrudes excessively from
assembled needing only to be connected to the the tensioner body, observe the yellow
tensioning heads. However for information maximum extension warning line.
purposes, the assembly of the stud tensioner kit is (Maximum extension 6mm)
as follows: - NOTE:
1) Remove the hand pump, complete with If the seals need replacing, refer to the
pressure gauge, high pressure hoses and hose operator’s manual provided with the
couplings from the hydraulic pump tool box. stud tensioning equipment.
Ensure that all studs are scrupulously clean 6) Connect the end of the high pressure feed
and that their threads are undamaged. hose to the first tensioner head.
Carefully examine that portion of each stud 7) Fit one of the inter-connecting hoses
thread protruding beyond the flange nut after between the first and second heads.
fitting. If the studs have been in service for
some time, inspect as described in the 8) Connect up the second and third heads
Circulator Instruction and Maintenance and finally, using the one remaining hose.
Manual. Connect the fourth head (i.e. with a
blanking plug fitted) to complete the
When tensioning studs of the circulators which circuit.
have been in service, inspect all faces of each
flange nut. Reject any damaged nuts. 9) Check the oil level in the hydraulic hand
(Damaged faces of nuts can be re-ground for pump, fill or top-up if necessary.
subsequent re-use). NOTE.
CAUTION: The quick release female connectors
Never lubricate the stud top threads, or have a knurled security locking ring in
those of the threaded insert. the centre. This must be turned to lock
the spring-loaded end of the coupling
2) Install and hand tighten all flange nuts. Apply to eliminate the possibility of an
silicone grease or high temperature anti-seize accidental disconnection.
compound to the threads and faces of each
flange nut CAUTION:
Do not pressurise an un-connected
3) Connect the high pressure feed hose via the male coupling.
quick release female connector to the gauge
tee on the pump.
4) Assemble the load cell and bridge, over the
first set of bolts (diametrically opposed) to be
tightened. The bridge window should be
positioned so that access to the nut is obtained.
It is normal for the bridge window to face
radially outwards from the centre of the
circular flanged joint.

8.3
SECTION 8
STUD TENSIONING EQUIPMENT

Figure 8/2 Single Piston Stud Tensioner


Exploded View

8.4
SECTION 8
STUD TENSIONING EQUIPMENT

Figure 8/3 Single Piston Stud Tensioner


General arrangement

8.5
SECTION 8
STUD TENSIONING EQUIPMENT

Figure 8/4 Quick Release Coupling

8.6 INDEXING
8.5 REPLENISHING THE PUMP TANK
It is essential that the gasket is uniformly
The pump is supplied already filled with oil compressed and the studs evenly prestressed.
but after repeated use the oil should be To ensure this, diametrically opposed flange
replenished as follows:- nuts are tightened simultaneously in
accordance with a predetermined numbering
1) Unscrew the oil filler plug from the top
sequence.
pump tank.
Using any convenient nut as No. 1 and
2) Replenish the tank from the 5 litre
working in a clockwise direction, sequentially
container of hydraulic fluid to the bottom
mark with chalk on the flange periphery, the
of the level tube.
appropriate nut tightening sequence. Refer to
Fig.8/5 for Nut Tightening Sequences.

8.6
SECTION 8
STUD TENSIONING EQUIPMENT

8.7 SAFETY PROCEDURES 3) Depress the hydraulic piston fully in the


tensioner body by: -
1) Eye protection and gloves should be worn
when working with high pressure a) Opening the oil return valve on the
hydraulics. hydraulic hand pump using the winged
control valve screw.
2) Pressurise slowly, do not exceed the b) Fully tightening the threaded inserts
maximum working pressure (1500 bar). using the rod provided.
Gauge pressure should be constantly
monitored during pump operation. c) Closing the oil return valve on the
hydraulic pump.
3) Do not exceed the maximum piston
extension 6mm. indicated by a yellow 4) The pump, hoses and tensioner heads are
line. pre-filled and system venting should not
be necessary. However, should venting of
4) Do not leave a pressurised system the system be required, loosen the
unattended, release pressure if leaving the blanking plug from the last head in the
working area. circuit and operate the pump until air free
5) Check the equipment fluid emerges from around the plug on
completion of venting.
a) Ensure that the hoses are undamaged.
b) Check that all hose couplings are 5) Using the hydraulic hand pump, obtain a
serviceable and tight on the hose ends true pressure stipulated for the 1st pass of
and tensioning heads. the 5 passes given in the following table.

6) Check equipment is correctly assembled; CAUTION;


The indicated gauge pressures are true
a) Tensioning head components must be operating pressures. Never exceed
seated squarely within each other and maximum working pressure for the
with the motor cover face or motor head when tensioning, or damage to the
pump flange. tensioner or to the studs may occur.
b) The thread engagement between the
stud and the threaded insert must be
48 mm minimum.
c) Before pressurising, ensure hose PASS LBF/IN.2 BAR
connector security by pulling on each
locked connection. 1ST 5000 350
7) Do not attempt to use stud tensioner if
unsure of the correct assembly and 2ND 10000 700
operation of the equipment. 3RD 15000 1050
8) Do not attempt any repairs on the system
4TH 21000 1450
when under pressure.
5TH 21000 1450
8.8 TIGHTENING FLANGE NUTS
1) Fit the four tensioner bodies complete
with threaded inserts onto the studs and
screw down on to each bridge. Attach the TENSIONING PRESSURE PROGRAM
hydraulic link hoses (See Section 4).
2) Ensure that the insert is fully depressed
within the tensioner body.

8.7
SECTION 8
STUD TENSIONING EQUIPMENT

6) The piston stroke and pressure should be 13) When all flange nuts are correctly
continually monitored so that neither go tightened, the gasket is fully compressed
above the corresponding working and the nuts pre-stressed.
pressures. If the maximum piston stroke is
14) Check at several equi-distant points on
reached before working pressure is
the flange periphery that the gap between
achieved go straight to procedure (8).
the faces of the pump case and motor
Close the pump stop valve, then flanges is less than 1.5 mm.
pressurise the system to the required
pressure, when this is reached stop the
pump to hold the pressure. 8.9 RELEASING FLANGE NUTS

7) Check the pressure gauge to ensure the WARNING:


pressure is holding constant. When Ensure that the motor is electrically
satisfied that the pressure is stable, use the isolated, adequately supported and de-
tommy bars to rotate the nuts, through the pressurised, before any nuts are slackened.
access windows, down towards the joint 1) Fit the tensioner heads to the studs and
surface. Fit the appropriate rod (bar) to connect the hoses and hand pump. If one
the flange nuts and fully hand tighten. head is used for this operation it must be
Hand tighten adjacent loose nuts. the head with the blanking plug fitted.
8) Remove the stud tensioner heads by:- 2) Screw down the threaded insert fully, then
a) Screwing in the oil return valve on the release it one half (½) turn. Pressurise the
pump to release the oil pressure system to 1500 bar and unscrew each
(which transfers the load to the nuts). flange nut one half (½) turn using the
b) Tightening, then releasing the threaded appropriate bar. Repeat for every stud on
insert. each pass.
c) Screwing out the oil return valve on 3) Should the nuts fail to move, a slow
the hand pump. gradual increase in pressure should be
d) Removing the threaded insert made until the nut lifts of the flange face.
complete with body. At this stage, a further increase in
pressure is un-necessary and will not
e) Removing the bridge. assist in freeing a tight nut.
f) Disconnect the hydraulic hoses.
CAUTION:
NOTE: Never exceed the maximum system
If the required pressure is not reached, pressure when removing the nuts.
return to step 2.
4) If the nuts are still in contact with the
9) Transfer the stud tensioners to studs flange and cannot be removed with the
numbered 2 in the tightening sequence. system at absolute pressure, consult
Repeat operations 2) to 8). Hayward Tyler for advice.
10) Continue tightening progressively to the 5) Repeat the stud tensioning and nut
numbered sequence until all the nuts are unscrewing sequences diametrically until
tightened to the 1st pass pressure i.e. nuts all flange nuts are released.
2 in turn then nuts 3 followed by nuts 4,
then 5 and so on. 6) After use, thoroughly clean, examine for
damage and lubricate each component of
11) Repeat the tightening sequence round the the stud tensioner equipment. Wrap all
flange of a 2nd, 3rd, 4th or 5th pass, at the components in suitable water-proof
stud tensioning pressure stipulated for the material then store in a clean, dry area in
applicable pass. their respective tool boxes.
12) If, on the 5th pass, the flange nuts can be
tightened further, additional passes at
maximum pressure should be made until
no further tightening is possible.

8.8
SECTION 8
STUD TENSIONING EQUIPMENT

Figure 8/5 Nut Tightening Sequence

8.9
SECTION 8
STUD TENSIONING EQUIPMENT

Figure 8/5 Nut Tightening Sequence (Continued)

8.10
SECTION 8
STUD TENSIONING EQUIPMENT

PARTS LIST

PART NO. DESCRIPTION QUANTITY


42751/080 M56 STUD TENSIONER 1
COMPRISING: -
42751/8000 TENSIONERS 4
COMPRISING; -

ITEM NO PART NO DESCRIPTION QUANTITY


1 42751/8001 BODY 1
2 42751/8002 RAM 1
3 42751/8003 BRIDGE 1
4 42751/8004 INNER SEAL SET 1
5 42751/8005 OUTER SEAL SET 1
6 42751/8006 BONDED SEAL 4
7 42751/8007 ADAPTOR 2
8 42751/8008 SNAP NIPPLE 2
9 42751/8009 SOCKET 1

ALSO INCLUDED: -
HAND PUMP COMPLETE WITH 1600 BAR PRESSURE GAUGE
HYDRAULIC HARNESS MANUFACTURED FROM FLEXIBLE HOSE AND QUICK RELEASE
COUPLINGS TO TENSION 4 TOOLS SIMULTEANEOUSLY.
HARNESS CONSISTING OF 3 METRE LEAD HOSE AND 1.5 METRE INTERCONNECTING HOSES
TOMMY BARS, OIL PACK, SPARE SEALS, STORAGE BOX FOR TENSIONING HEADS, STORAGE
BOX FOR PUMP AND HARNESSES.
MANUALS FOR TENSIONER AND HAND PUMP.

8.11

Das könnte Ihnen auch gefallen