contractor was informed in the meeting on 16/06/2019 at RAJUK regarding the final route of
the pipeline. After several reminder finally EPC Contractor submitted request for obtaining
ROW clearance on 24/06/2019. POCL is yet to provide clearance for ROW from Kuril to
Kanchan.
2. Final Route approval from Railway/BBA/FDEE is yet to be obtained from concerned authority.
EPC contractor was requested to update the onsite activities of RAJUK nominated contractor
for their storm water pipeline. EPC Contractor failed to update the PMC & Client to update on
due time, even though RAJUK has changed their design and construction procedure
3. Land for Pitalganj Depot was handed over to EPC contractor on 02//10/2018 and drawing
design for boundary wall and retaining was approved by PMC/POCL on 02/05/19. EPC
Contractor is yet to start the construction work of boundary wall and retaining wall at Pitalganj
Depot area. No Proper schedule to start the work was not obtained from the Project Manager
even after several communication with him in this regard. No feed back on this issue and as
well as other issues was never obtained from the Project Manager of EPC Contractor.
4. EPC contractor was requested to provide estimated cost budget on different proposals for Jetty
design and construction to select the best fit option proposed by the EPC contractor, this was
agreed on last review meeting on 19/06/2019. This is yet to be provided by the EPC which lead
to delay in decision making of Jetty land acquisition and engineering basis finalization.
5. Document approval process on client side is slow and resubmission of the commented
documents by the EPC Contractor are not moving smoothly and taking more time than usual.
6. EPC Contractor is yet to finalize their HDD and CP Contractor even after several reminders
with the reasons behind the requirements from PMC and POCL.
7. EPC contractor is not prepared to carry out the construction works even after getting clearance
from the client. For Pitalganj depot, design drawing for tanks, tank foundation and pilling during
May, 2019 but procurement of tank plates, subcontractor selection and deployment for
8. After several reminders from POCL/PMC, EPC contractor didn't expediate their procurement
process for the major equipment. Whereas, most of the equipmets shall require a delivery lead
time from 4 months to 10 months. It seems EPC is not concerned about the time limitation of
9. However, compatibility and capacity to manage a project in terms of both technical & leadership
of the Project Manager appointed by the EPC contractor was always under a big question mark.
It seems deficiency of leadership, capacity to foresee the upcoming difficulties and technical
capacity of the Project Manager is heading the EPC Contractor towards failure to complete the
project on time. Whenever, he was asked to update any event or any activity, bypassing or
transferring the responsibility to others was always noticed by all the concerning authorities
including POCL, PMC, BPC, NKFTCL. Local partner of the EPC contractor was notified several
times about this dissatisfaction of the ultimate client, lastly Engineering Manager of the EPC
contractor was requested by the Managing Director of POCL to convey his dissatisfaction on
the deployment of the Project Manager by CMECC, the lead partner of the JV. But till now no
visible action in this regard has been taken by the concerning authorities of the EPC Contractor.