Republic of the Philippines

Region VI
Province of Capiz
Municipality of Maayon
MUNICIPAL ENGINEERING OFFICE
Cycle 3

CERTIFICATION

This is to certify that the following barangay enumerated belowe has a source of gravel which had been
tested and passed the standard requirements for infrastructures project in the Municipality of Maayon.

1. Alasaging
2. Alayunan
3. Bongbongan
4. Canapian
5. Guinbi-alan
6. Jebaca
7. Manayupit
8. Old Guia
9. Palaguian
10. Parallan
11. Poblacion Ilaya
12. Poblacion Tabuc
13. Quevedo
14. Quinabonglan
15. Quinat-uyan
16. Salgan

This certification is being issued for the reference purposes.

Certified by:
Engr. Dely J. Abaygar
Municipal Engineer

Noted by:

Hon. Weldie C. Apolinario


Vice Mayor/Area Coordinator
Republic of the Philippines
Province of Capiz
Municipality of Maayon
Municipal Engineering Office

UNIT COST OF MATERIALS

Description unit Unit Cost


CONTRUCTION MATERIALS AND HARDWARES
Portland Cement bag 280.00
1" Graded Gravel cu.m. 800.00
Washed Sand cu.m. 700.00
Filling Materials cu.m. 400.00
Waterproofing Cement kg 120.00
Red/green Oxide kg 32.00
#80 Nylon String clip 30.00
4" CHB pc 15.00
6" CHB pc 22.00
20mm dia RSB, Grade 40 length 1,105.00
16mm dia RSB, Grade 40 length 365.00
12mm dia RSB, Grade 40 length 204.00
10mm dia RSB, Grade 40 length 155.00
16mm Plain Bar length 370.00
12mm dia Plain Bar length 210.00
10mm dia Plain Bar length 200.00
10mm square bar length 190.00
12mm square bar length 2,000.00
#16 GI Tie wire kgs 85.00
2.0 x 1.2 x 2.4 Checkered Plate sheet 6,500.00
4 x 1/4 Angle Bar (6mm) length 3,000.00
3 x 1/4 Angle Bar (6mm) length 1,900.00
2-1/2 x 1/4 Angle Bar (6mm) length 1,600.00
2-1/2 x 3/16 Angle Bar length 1,100.00
2 x 1/4 Angle Bar (6mm) length 1,000.00
2 x 3/16 Angle Bar length 750.00
1-1/2 x 1/4 Angle Bar (6mm) length 850.00
1-1/2 x 3/16 Angle Bar length 750.00
1-1/2 x 1/8 Angle Bar length 450.00
1-1/4 x 1/4 Angle Bar (6mm) length 650.00
1-1/4 x 3/16 Angle Bar length 30.00
1-1/4 x 1/8 Angle Bar length 342.00
1 x 1/4 Angle Bar length 650.00
1 x 3/16 Angle Bar length 420.00
1 x 1/8 Angle Bar length 250.00
2 x 1/4 Flat Bar length 550.00
2 x 3/16 Flat Bar length 400.00
1-1/2 x 1/4 Flat Bar length 500.00
1-1/2 x 3/16 Flat Bar length 310.00
1-1/4 x 1/4 Flat Bar length 450.00
1-1/4 x 3/16 Flat Bar length 420.00
1 x 1/4 Flat Bar length 400.00
1 x 3/16 Flat Bar length 200.00
1 x 1/8 Flat Bar length 150.00
Ga. 12 x 2"x 4' x 8' Wire Mesh sheet 900.00
0.40mm x 12' GI Corr. Roofing Sheets sheet 570.00
0.40mm x 10' GI Corr. Roofing Sheets sheet 475.00
0.40mm x 8' GI Corr. Roofing Sheets sheet 380.00
0.40mm x 6' GI Corr. Roofing Sheets sheet 285.00
0.40mm x 8' GI Ridge Roll sheet 340.00
0.40mm x 8' GI End Spanish Flashing sheet 340.00
0.40mm x 8' GI Spanish Gutter sheet 340.00
0.40mm GI Fascia Cover/Board sheet 340.00
0.40mm x 3 x 8'GI Plain Sheet sheet 350.00
2x3 C Purlins(.80mm) length 450.00
2x3 C Purlins(1.20mm) length 600.00
Metal Tekscrew 2-1/2 (with neoprene washer) pc 2.50
Roofing Nails kg 90.00
1/8 x 1/2 Blind Rivets pc 1.00
1/2"x12"x 8' Ficem Fascia Board sheet 450.00
1/2 x 8 Bolt w/ plain washer and nut pc 20.00
1/8 Screen Wire m 70.00
Elastomeric Sealant (1 liter) can 450.00
Welding Rod kg 110.00
Mahogany Rough Lumber bd.ft. 35.00
Gemilina Rough Lumber bd.ft. 35.00
Coco Lumber bd.ft. 27.00
Wood Preservative gal 450.00
3/8 Ordinary Plywood sheet 640.00
1/4 Ordinary Plywood sheet 470.00
1/4 Marine Plywood sheet 520.00
1/4 Santa Clara Marine Plywood sheet 900.00
1/2 Ordinary Plywood sheet 700.00
1/2 Marine Plywood sheet 800.00
Common Wire Nails kg 75.00
1" Finishing Nails kg 75.00
3" Concrete Nails kg 120.00
Solignum Clear gal 1,200.00
Lentrex/Leadrex li 1,100.00
1 x 1 x 10 Cove Moulding pc 95.00
1 x 1 x 10 Quarter Round Moulding pc 95.00
1 x 1 x 10 Square Moulding pc 95.00
8 x 8 Floor Tiles pc 25.00
8 x 8 Wall Tiles pc 25.00
6mm Tile Trim pc 50.00
9mm Tile Trim pc 60.00
ABC Tile Grout (2 kg) pack 75.00
ABC Tile Adhesive pack 310.00
Door Knob (kwikset) set 900.00
1.0 x 2.10 Panel Door with 2 x 6 door jamb set 5,000.00
0.90 x 2.10 Panel Door with 2 x 6 door jamb set 4,600.00
0.80 x 2.10 Panel Door with 2 x 6 door jamb set 3,500.00
0.70 x 2.10 PVC Louver Door with PVC Jamb set 1,850.00
0.60 x 2.10 PVC Louver Door with PVC Jamb set 1,700.00
4 x 4 Loose Pin Hinges pair 120.00
3 x 3 Loose Pin Hinges pair 100.00
12 Blader D/C Alum. Jalousie Frame (heavy duty) pair 250.00
13 Blader D/C Alum. Jalousie Frame (heavy duty) pair 260.00
14 Blader D/C Alum. Jalousie Frame (heavy duty) pair 290.00
6 Blader Alum. Jalousie Frame (heavy duty) pair 150.00
1/4 x 22" Smoke Glass Jalousie Blades pc 35.00
1/4 x 22" Clear Glass Jalousie Blades pc 38.00
1/4 x 18" Smoke Glass Jalousie Blades pc 30.00
1/4 x 18" Clear Glass Jalousie Blades pc 33.00
1/4 x 16" Smoke Glass Jalousie Blades pc 25.00
1/4 x 16" Clear Glass Jalousie Blades pc 31.00
1/4 x 14" Smoke Glass Jalousie Blades pc 20.00
1/4 x 14" Clear Glass Jalousie Blades pc 25.00
2" Toks with Screw pc 2.50

4" PVC Pipe (Orange) length 220.00


4" PVC Coupling pc 60.00
4" PVC Elbow pc 45.00
4" PVC Tee pc 65.00
4" PVC Clean Out with Plug pc 65.00
4" PVC Wye pc 65.00
4" x 45 Elbow pc 45.00
4" x 2" PVC Tee pc 65.00
4" x 2" PVC Reducer pc 65.00
2" PVC Pipe (orange) length 85.00
2" PVC Coupling pc 16.00
2" PVC Elbow pc 16.00
2" PVC Tee pc 18.00
2" PVC P-Trap pc 25.00
2" PVC Wye pc 25.00
2" x 45 PVC Elbow pc 16.00
3/4 PVC Pipe (blue) length 80.00
3/4 PVC Coupling pc 13.00
3/4 PVC Elbow pc 14.00
3/4 PVC Elbow Threaded one end pc 14.00
3/4 PVC Tee pc 14.00
3/4 PVC Male Adapter pc 14.00
3/4 PVC Female Adapter pc 14.00
3/4 PVC Plug pc 10.00
3/4 PVC Union pc 85.00
3/4 PVC Faucet pc 85.00
3/4 GI Faucet pc 150.00
3/4 x 1/2 PVC Reducer pc 13.00
3/4 x 1/2 GI Bushing pc 35.00
1/2 PVC Pipe (blue) length 65.00
1/2 PVC Coupling pc 10.00
1/2 PVC Elbow pc 12.00
1/2 PVC Elbow Threaded one end pc 12.00
1/2 PVC Tee pc 12.00
1/2 PVC Male Adapter pc 12.00
1/2 PVC Female Adapter pc 12.00
1/2 PVC Plug pc 10.00
1/2 PVC Union pc 65.00
1/2 PVC Faucet pc 75.00
1/2 GI Faucet pc 120.00
1/2 PVC Gate Valve pc 75.00
Solvent Cement 200ml can 65.00
3/4 Teflon roll 16.00

Lavatory set 1,800.00


Toilet Bowl (pail flush) set 1,800.00
Toilet Bowl with tank set 5,600.00
Urinal set 3,500.00
4" Stainless Floor Drain pc 250.00
1-1/4" S/S Grab Bar set 2,500.00
12" x 12" S/S Kitchen Sink set 1,500.00

Flat Latex White (boysen) gal 550.00


Semi-Gloss Latex White (boysen) gal 700.00
Bagiuo Green Acrylic Roof Paint (boysen) gal 700.00
Laguna White Acrylic Roof Paint li 170.00
Chocolate Brown Latex Paint gal 600.00
Raw Sienna Tinting Color Latex (boysen) li 250.00
Flat Wall Enamel Paint (boysen) gal 700.00
Semi-Gloss Enamel Paint (boysen) gal 700.00
Raw Sienna Tinting Color Enamel (boysen) qt 200.00
Blackboard Slating Green (boysen) gal 650.00
Epoxy Primer (boysen) gal 760.00
Epoxy Enamel (boysen) gal 900.00
Rust Converter gal 450.00
Paint Thinner gal 350.00
Concrete Neutralizer gal 550.00
Metal Primer gal 500.00
Quick Drying Enamel White (boysen) gal 750.00
QDE Mahogany (boysen) gal 650.00
9" Paint Roller pc 120.00
Baby Roller pc 75.00
4" Paint Brush pc 75.00
3" Paint Brush pc 50.00
2" Paint Brush pc 35.00
Description unit Unit Cost
1" Paint Brush pc 30.00
Patching Compound kg 35.00
Body Filler li 250.00
#120 Sand Paper pc 25.00
#100 Sand Paper ft 75.00
#80 Sand Paper ft 75.00

4 Holes Panel Board set 850.00


30 Amp Circuit Breaker set 300.00
20 Amp Circuit Breaker set 300.00
15 Amp Circuit Breaker set 300.00
#8 TW Wire Stranded m 70.00
#10 TW Wire Stranded m 50.00
#12 TW Wire Stranded m 40.00
#14 TW Wire Stranded m 35.00
#12 TW Wire Solid m 30.00
#14 TW Wire Solid m 25.00
#12 THHN Wire Stranded m 35.00
#14 THHN Wire Stranded m 35.00
#12 THHN Wire Solid m 35.00
#14 THHN Wire Solid m 25.00
1 Gang Flush Type Switch set 120.00
2 Gang Flush Type Switch set 170.00
3 Gang Flush Type Switch set 250.00
1 Gang Flush Type Convenience Outlet set 110.00
2 Gang Flush Type Convenience Outlet set 170.00
3 Gang Flush Type Convenience Outlet set 250.00
PVC Receptacle pc 45.00
PVC Junction Box pc 35.00
PVC Utility Box pc 35.00
1" Service Cap pc 45.00
11 Watts Daylight Capsule Bulb pc 125.00
40 Watts Flourescent Lamp set 320.00
1/2" Electrical Pipe m 75.00
1/2 " Electrical Conduit m 25.00
3/4" Electrical Pipe m 95.00
3/4" Electrical Conduit m 25.00
Electrical Tape (big) pc 45.00

2" GI Pipe Sc. 40 m 1,350.00


Welding Machine day 250.00
4"Grinder Stone pc 100.00
Electric Grinder day 150.00
Electric Drill day 150.00
4"Motor Pump inc. Motor with Oil and Fuel day 800.00
6"Fabricated Pulley set 5,200.00
12mm Fab. Non Swivel Eyebolts with nuts & washers set 210.00
Hacksaw Blade pc 82.00
Construction Pail pc 200.00
Concrete Mixer inc. Motor, Oil and Fuel day 800.00
3/4" Turnbuckle pc 450.00
Chain Block (5 tonnage) day 350.00
Oxyacetylene day 750.00
Quick dry enamel black gal 650.00
Tinting color blue pint 120.00
Tinting color yellow pint 120.00
Tinting color red pint 120.00
50mm Sche.40 G.I. Pipe length 700
Concealed Hinges pc 40.00
Drawer Handle pc 45.00
Drawer Roller pair 85.00
Drawer Lock set 40.00
Item-201 cu.m 450.00
Boulders cu.m 600.00
12" x 12" Bronze Plate lot 4,500.00

Certified by:

ENGR. DELY J. ABAYGAR


Municipal Engineer
Republic of the Philippines
Province of Capiz
Municipality of Maayon
MUNICIPAL ENGINEERING OFFICE

LABOR RATES

Item No. Item Description Quantity Unit Unit cost


I Engineer supervision 1 per day 750.00

II Foreman 1 per day 500.00

III Skilled 1 per day 350.00


III.a a. Mason 350.00
III.b b.Carpenter 350.00
III.c c.Steelman 400.00
III.d d. Welder 350.00
III.e e. Electrician 350.00
III.f f. One bagger operator 350.00
III.g g. Leadman 350.00

IV Unskilled 1 per day 250.00

V Bodegero 1 per day 250.00


(also incharge of materials' record)

Certified by:

ENGR. DELY J. ABAYGAR


Municipal Engineer
Republic of the Philippines
Province of Capiz
Municipality of Maayon
Municipal Engineering Office

PRODUCTIVITY OUTPUTS

LABOR
COMMON WORK ACTIVITIES
OUTPUT
NO. ACTIVITIES
RATE UNIT
I CLEARING AND LAY-OUT
1 Light Bush 200.00 sq.m./M-D
2 Medium Dense 100.00 sq.m./M-D
3 Dense 50.00 sq.m./M-D
4 Installation of Batterboard/Lay-out 50.00 sq.m./M-D
II EARTHWORKS
1 Structural Excavation by hand 1.30 cu.m./M-D
2 Pipeline Excavation by hand 2.40 cu.m./M-D
3 Excavation by machine 11.00 cu.m./M-D
4 Back Filling by hand (w/ compaction) 3.00 cu.m./M-D
5 Spreading by hand (w/machine compaction) 2.00 cu.m./M-D
6 Back Filling by machine 11.00 cu.m./M-D
7 Manpower Hauling (on site source) 0.75 cu.m./M-D
III CARPENTRY
1 Formwork 1.80 sq.m./M-D
1.a Footings, gradebeams and columns 3.38 sq.m./M-D
1.b Beams, bond beams and floor slabs 2.86 sq.m./M-D
1.c Roof Beams and bond beams 2.65 sq.m./M-D
1.d Roof Slab 2.13 sq.m./M-D
1.e Edging for roof 4.65 sq.m./M-D
1.f Grade Slab edging (4") 5.31 sq.m./M-D
1.g Retaining Walls 2.66 sq.m./M-D
1.h Stairs and landings 3.23 sq.m./M-D
1.i Form for road 8.00 sq.m./M-D
1.j Form Oil application 124.00 sq.m./M-D
2 Ceiling
2.a Plywood 4.00 sq.m./M-D
2.b Framework 2.00 sq.m./M-D
3 Partition
3.a Plywood 12.00 sq.m./M-D
3.b Framework 2.00 sq.m./M-D
4 Wood Truss 4.63 bd ft/M-D
4.a Fabrication 15.10 bd ft/M-D
4.b Installation 6.67 bd ft/M-D
4.c Purlins, Facia, etc. Installation 20.00 bd ft/M-D
5 Scaffoldings
5.a Fabrication, Installation and Removal 11.88 sq.m./M-D

IV STEEL WORKS
1 Reinforcing Bar 40.00 kg/M-D
1.a Fabrication 114.00 kg/M-D
1.b Installation 100.00 kg/M-D
V CONCRETE WORKS
1 Concreting 0.30 cu.m./M-D
1.a Manual 0.50 cu.m./M-D
1.b Concrete Mixer 0.60 cu.m./M-D
1.c Cocrete pouring w/ Crew 7.22 m3/day
2 4" CHB
2.a Fence 4.67 sq.m./M-D
2.b Building 3.50 sq.m./M-D
3 6" CHB
3.a Fence 3.33 sq.m./M-D
3.b Building 3.20 sq.m./M-D
4 Bricks Installation 1.23 m2/M-D
VI FINISHING WORKS
1 Concrete Finishing 2.70 sq.m./M-D
1.a Plain Cement Finish (walls) 8.00 sq.m./M-D
2.b Plain Cement Finish (corners & overhead) 0.80 sq.m./M-D
3.c Rough Cement Finish 10.00 sq.m./M-D
3.d Colored Cement Finish 4.70 sq.m./M-D
4 Marble Finish 2.00 sq.m./M-D
5 Pebbles Washout Finish 2.60 sq.m./M-D
6 Paintings sq.m./M-D
6.a Paint Roller/wall 7.40 sq.m./M-D
6.b Paint Brush 50.00 sq.m./M-D
6.c Neutralizer 100.00 sq.m./M-D
7 Paint Removal 4.00 sq.m./M-D
8 Acoustic Tile Ceiling 0.30 sq.m./M-D
9 Painting on Hanging Bridge 4.00 sq.m./M-D
VII ROOFING WORKS
1 Roofing (metallic) 3.00 sq.m./M-D
2 Siding (metallic) 0.65 sq.m./M-D
3 Fascia and Gutter Installation 3.00 l.m./M-D
VIII DOORS
1 Door, Installation (inc. door knob)/Ord.Dr. Install 4.00 sq.m./M-D
2 Sliding Door, Installation 1.00 sq.m./M-D
3 Roll-up Door, Installation 0.32 sq.m./M-D
4 Door Jamb Installation 2.50 sq.m./M-D
IX WINDOWS
1 Jalousie Installation 1.25 sq.m./M-D
2 Window Grilles (fab. and installation) 0.75 sq.m./M-D
X REINFORCED PIPE CULVERTS
1 Crushing of stone for aggregates 0.20 cu.m./M-D
2 Casting of Culvert Rings 0.50 ring/M-D
3 Laying of Standard Culverts
3.a 300mm dia RCPC 0.94 pc/M-D
3.b 460mm dia RCPC 0.88 pc/M-D
3.c 610mm dia RCPC 0.75 pc/M-D
3.d 760mm dia RCPC 0.63 pc/M-D
3.e 910mm dia RCPC 0.50 pc/M-D
3.f 1200mm dia RCPC 0.38 pc/M-D
4 Headwalls w/ masonry blocks 0.20 headwall/M-D
XI GROUTED RIPRAP 0.54 cu.m./M-D
XII STONE MASONRY 0.35 cu.m./M-D
5 Stone Masonry 0.35 m3/M-D
6 Grouted Riprap 7.50 m3/day
7 Concrete Lining 4.50 m3/day
XIII JALOUSIE WINDOW 1.25 sq.m./M-D
XIV TILE WORKS
1 200mm x 200mm Tiles, Installation
1.a Floor 2.00 sq.m./M-D
1.b Wall 0.80 sq.m./M-D
XV RAILINGS INSTALLATION 1.00 l.m./day
XVI WELDED STRUCTURAL STEEL
1 Structural Steel Frames 1.25 sq.m./M-D
2 Steel Truss
2.a Fabrication and Installation 0.25 truss/M-D
2.b Purlins Installation 60.00 l.m./M-D
2.c Fascia Frame Installation 6.00 l.m./M-D
XVII STEEL CABLE INSTALLATION 0.75 l.m./day
XVIII PCCP (with concrete mixer) 0.60 cu.m./M-D
XIX REMOVAL OF EXISTING RC PIPE
a. 0.45m dia. 0.8 l.m./M-D
b. 0.60m dia. 0.6 l.m./M-D
XX STEEL ROOF TRUSS 2.13 m2/M-D

Prepared By:

ENGR. DELY J. ABAYGAR


Municipal Engineer
Republic of the Philippines
Province of Capiz
Municipality of Maayon
MUNICIPAL ENGINEERING OFFICE

EQUIPMENT RENTAL
(as per Productivity Output)

Item No. Item Description Quantity Unit

I A. Prime Mover 1 unit per trip

II BULLDOZER 1 unit per day


II.a Clearing ( 500 m2/hr )
II.b Stripping ( 200 m2/hr )
II.c Excavation ( 25 m3/hr )
II.d Quarry ( Stock pilling) ( 50 m3/hr )
II.e Pushing ( 3 m3/hr )

III ROAD GRADER 1 unit per day


III.a Sub grading ( 300 m2/hr )
III.b Spreading ( 42.50 m3/hr )
III.c Clearing ( 950 m2/hr )
III.d Excavation ( 20 m3/hr )

IV ROAD ROLLER (Vibratory) 1 unit per day


IV.a 6 Passes ( 72 m3/hr )

V WATER TRUCK 1 unit per day


V.a Watering ( 1500 gals capacity)

VI BACKHOE 1 unit per day


VI.a Excavation ( Normal condition ) ( 20m3/hr )
VI.b Excavation ( Hard soil / rocky ) ( 15 m3/hr )

Per/day
VII CONCRETE MIXER ( one bagger ) including
1 unit Operator
VII.a Concrete mix ( 0.625 m3/hr )
(up to 0.80 m3/hr for PCCP works)
VII.b CONCRETE VIBRATOR 1 unit per day

Certified by:

ENGR. DELY J. ABAYGAR


Municipal Engineer
Unit cost

16,000.00

13,500.00

9,000.00

9,000.00

5,100.00

9,600.00

1,500.00

1,000.00
Republic of the Philippines
Province of Capiz
Municipality of Maayon
MUNICIPAL ENGINEERING OFFICE

PRODUCTIVITY OUTPUTS
EQUIPMENT AND MACHINERIES

OUTPUT
EQUIPMENT ACTIVITY
RATE UNIT

A. DOZER a. Clearing 500 m2 /hr


Efficiency: b. Stripping 200 m2 /hr
Machine: 100% c. Excavation
Operator: 100% 1.common soil 45 m3/hr
2. slightly hard materials 25 m3/hr
d. Quarry (Stockpiling)
Common Materials 50 m3/hr
Aggregate 40 m3/hr
boulders 15 m3/hr
e. Pushing 3 m3/hr

B. GRADER a. Sub-Grading 300 m2 /hr


Caterpillar and the like b. Spreading (35-50 m3/hr) 50 m3/hr
c. Clearing 950 m2 /hr

C.PAYLOADER a. Loading (30-40 m3/hr) 30 m3/hr


D. CRANE SHOVEL a. Loading 35 m2 /hr

E. SHEEP FOOT ROLER a. Static Rolling (12 passes) 15 cm.lift 15 m3/hr


b. Vibratory Rolling (4 passes) 15 cm.lift 135 m3/hr

F. 3-ROLLER a. Static Rolling (6 passes) 20 cm. Lift (15-20 m3/hr) 24 m3/hr

G. TRACTOR-DRAWN ROLLER a. Vibratory Rolling (6 passes) 20 cm.lift 24 m3/hr

H. TANDEM ROLLER a. Static Rolling (6 passes) 20 cm.lift 24 m3/hr


b. Vibratory Tolling (6 passes) 20 cm.lift 72 m3/hr

I. 5-T DUMPTRUCK a. Hauling Common Borrow 3.5 m3/trip


b. Hauling Selected Barrow/Base Coarse 3 m3/trip
c. Hauling Concrete Batch Class “A” of Aggregates (Gravel Pit) 3 batch/trip
I. 6-T DUMPTRUCK a. Hauling Common Borrow 3.5 m3/trip
b. Hauling Selected Barrow/Base Coarse 5 m3/trip
c. Hauling Concrete Batch Class “A” of Aggregates (Gravel Pit) 2 batch/trip
I. 2 1/2-T DUMPTRUCK a. Hauling Common Borrow 2.5 m3/trip
b. Hauling Selected Barrow/Base Coarse 4 m3/trip
c. Hauling Concrete Batch Class “A” of Aggregates (Gravel Pit) 1 batch/trip
J. BUGGY a. Hauling Concrete Mix 0.17 m3/trip

K. WHEEL BARROW a. Hauling of Aggregates 0.17 m3/trip


b. Hauling of Concrete Mix 0.05 m3/trip
L. WATER TRUCK
(1500 gals. Cap.) a. Watering 1000 m2/trip

M. ASPHALT
(1500 gals. Cap.) a. Spraying Asphalt Prime Coat 300 m2/trip

N. BACKHOE (UH04) a. Excavation (Normal condition) 20 m3/hr


b. Excavation (Hard Soil/Rocky) 15 m3/hr
O. CONCRETE MIXER a. Mixing (for building)
(one bagger) b. Mixing (for PCCP) 0.82 m3/hr

Concrete Vibrator a. vibrating concrete mix 40 m3/hr

Concrete floor finisher a. finishing concrete floor 140 m3/hr

Percussioned drilling a. Drilling hard rock 0.23 m/hr


b. Drilling loose rock 0.30 m/hr
c. Drilling limestone 0.38 m/hr
d. Drilling sticky clay 0.49 m/hr
e. Drilling loose clay 0.70 m/hr

Certified by:

ENGR. DELY J. ABAYGAR


Municipal Engineer