Beruflich Dokumente
Kultur Dokumente
Region VI
Province of Capiz
Municipality of Maayon
MUNICIPAL ENGINEERING OFFICE
Cycle 3
CERTIFICATION
This is to certify that the following barangay enumerated belowe has a source of gravel which had been
tested and passed the standard requirements for infrastructures project in the Municipality of Maayon.
1. Alasaging
2. Alayunan
3. Bongbongan
4. Canapian
5. Guinbi-alan
6. Jebaca
7. Manayupit
8. Old Guia
9. Palaguian
10. Parallan
11. Poblacion Ilaya
12. Poblacion Tabuc
13. Quevedo
14. Quinabonglan
15. Quinat-uyan
16. Salgan
Certified by:
Engr. Dely J. Abaygar
Municipal Engineer
Noted by:
Certified by:
LABOR RATES
Certified by:
PRODUCTIVITY OUTPUTS
LABOR
COMMON WORK ACTIVITIES
OUTPUT
NO. ACTIVITIES
RATE UNIT
I CLEARING AND LAY-OUT
1 Light Bush 200.00 sq.m./M-D
2 Medium Dense 100.00 sq.m./M-D
3 Dense 50.00 sq.m./M-D
4 Installation of Batterboard/Lay-out 50.00 sq.m./M-D
II EARTHWORKS
1 Structural Excavation by hand 1.30 cu.m./M-D
2 Pipeline Excavation by hand 2.40 cu.m./M-D
3 Excavation by machine 11.00 cu.m./M-D
4 Back Filling by hand (w/ compaction) 3.00 cu.m./M-D
5 Spreading by hand (w/machine compaction) 2.00 cu.m./M-D
6 Back Filling by machine 11.00 cu.m./M-D
7 Manpower Hauling (on site source) 0.75 cu.m./M-D
III CARPENTRY
1 Formwork 1.80 sq.m./M-D
1.a Footings, gradebeams and columns 3.38 sq.m./M-D
1.b Beams, bond beams and floor slabs 2.86 sq.m./M-D
1.c Roof Beams and bond beams 2.65 sq.m./M-D
1.d Roof Slab 2.13 sq.m./M-D
1.e Edging for roof 4.65 sq.m./M-D
1.f Grade Slab edging (4") 5.31 sq.m./M-D
1.g Retaining Walls 2.66 sq.m./M-D
1.h Stairs and landings 3.23 sq.m./M-D
1.i Form for road 8.00 sq.m./M-D
1.j Form Oil application 124.00 sq.m./M-D
2 Ceiling
2.a Plywood 4.00 sq.m./M-D
2.b Framework 2.00 sq.m./M-D
3 Partition
3.a Plywood 12.00 sq.m./M-D
3.b Framework 2.00 sq.m./M-D
4 Wood Truss 4.63 bd ft/M-D
4.a Fabrication 15.10 bd ft/M-D
4.b Installation 6.67 bd ft/M-D
4.c Purlins, Facia, etc. Installation 20.00 bd ft/M-D
5 Scaffoldings
5.a Fabrication, Installation and Removal 11.88 sq.m./M-D
IV STEEL WORKS
1 Reinforcing Bar 40.00 kg/M-D
1.a Fabrication 114.00 kg/M-D
1.b Installation 100.00 kg/M-D
V CONCRETE WORKS
1 Concreting 0.30 cu.m./M-D
1.a Manual 0.50 cu.m./M-D
1.b Concrete Mixer 0.60 cu.m./M-D
1.c Cocrete pouring w/ Crew 7.22 m3/day
2 4" CHB
2.a Fence 4.67 sq.m./M-D
2.b Building 3.50 sq.m./M-D
3 6" CHB
3.a Fence 3.33 sq.m./M-D
3.b Building 3.20 sq.m./M-D
4 Bricks Installation 1.23 m2/M-D
VI FINISHING WORKS
1 Concrete Finishing 2.70 sq.m./M-D
1.a Plain Cement Finish (walls) 8.00 sq.m./M-D
2.b Plain Cement Finish (corners & overhead) 0.80 sq.m./M-D
3.c Rough Cement Finish 10.00 sq.m./M-D
3.d Colored Cement Finish 4.70 sq.m./M-D
4 Marble Finish 2.00 sq.m./M-D
5 Pebbles Washout Finish 2.60 sq.m./M-D
6 Paintings sq.m./M-D
6.a Paint Roller/wall 7.40 sq.m./M-D
6.b Paint Brush 50.00 sq.m./M-D
6.c Neutralizer 100.00 sq.m./M-D
7 Paint Removal 4.00 sq.m./M-D
8 Acoustic Tile Ceiling 0.30 sq.m./M-D
9 Painting on Hanging Bridge 4.00 sq.m./M-D
VII ROOFING WORKS
1 Roofing (metallic) 3.00 sq.m./M-D
2 Siding (metallic) 0.65 sq.m./M-D
3 Fascia and Gutter Installation 3.00 l.m./M-D
VIII DOORS
1 Door, Installation (inc. door knob)/Ord.Dr. Install 4.00 sq.m./M-D
2 Sliding Door, Installation 1.00 sq.m./M-D
3 Roll-up Door, Installation 0.32 sq.m./M-D
4 Door Jamb Installation 2.50 sq.m./M-D
IX WINDOWS
1 Jalousie Installation 1.25 sq.m./M-D
2 Window Grilles (fab. and installation) 0.75 sq.m./M-D
X REINFORCED PIPE CULVERTS
1 Crushing of stone for aggregates 0.20 cu.m./M-D
2 Casting of Culvert Rings 0.50 ring/M-D
3 Laying of Standard Culverts
3.a 300mm dia RCPC 0.94 pc/M-D
3.b 460mm dia RCPC 0.88 pc/M-D
3.c 610mm dia RCPC 0.75 pc/M-D
3.d 760mm dia RCPC 0.63 pc/M-D
3.e 910mm dia RCPC 0.50 pc/M-D
3.f 1200mm dia RCPC 0.38 pc/M-D
4 Headwalls w/ masonry blocks 0.20 headwall/M-D
XI GROUTED RIPRAP 0.54 cu.m./M-D
XII STONE MASONRY 0.35 cu.m./M-D
5 Stone Masonry 0.35 m3/M-D
6 Grouted Riprap 7.50 m3/day
7 Concrete Lining 4.50 m3/day
XIII JALOUSIE WINDOW 1.25 sq.m./M-D
XIV TILE WORKS
1 200mm x 200mm Tiles, Installation
1.a Floor 2.00 sq.m./M-D
1.b Wall 0.80 sq.m./M-D
XV RAILINGS INSTALLATION 1.00 l.m./day
XVI WELDED STRUCTURAL STEEL
1 Structural Steel Frames 1.25 sq.m./M-D
2 Steel Truss
2.a Fabrication and Installation 0.25 truss/M-D
2.b Purlins Installation 60.00 l.m./M-D
2.c Fascia Frame Installation 6.00 l.m./M-D
XVII STEEL CABLE INSTALLATION 0.75 l.m./day
XVIII PCCP (with concrete mixer) 0.60 cu.m./M-D
XIX REMOVAL OF EXISTING RC PIPE
a. 0.45m dia. 0.8 l.m./M-D
b. 0.60m dia. 0.6 l.m./M-D
XX STEEL ROOF TRUSS 2.13 m2/M-D
Prepared By:
EQUIPMENT RENTAL
(as per Productivity Output)
Per/day
VII CONCRETE MIXER ( one bagger ) including
1 unit Operator
VII.a Concrete mix ( 0.625 m3/hr )
(up to 0.80 m3/hr for PCCP works)
VII.b CONCRETE VIBRATOR 1 unit per day
Certified by:
16,000.00
13,500.00
9,000.00
9,000.00
5,100.00
9,600.00
1,500.00
1,000.00
Republic of the Philippines
Province of Capiz
Municipality of Maayon
MUNICIPAL ENGINEERING OFFICE
PRODUCTIVITY OUTPUTS
EQUIPMENT AND MACHINERIES
OUTPUT
EQUIPMENT ACTIVITY
RATE UNIT
M. ASPHALT
(1500 gals. Cap.) a. Spraying Asphalt Prime Coat 300 m2/trip
Certified by: