Completion & Workover – DURI07261 – 5M54C

CHEVRON PACIFIC INDONESIA - SUMATERA OPERATION


COMPLETION & WORKOVER PROGRAM – DURI – DURI07261 – 5M54C

7/11/2019

PREPARED BY: ROHUL RAMADHAN X ROHU


COMPLETION ENGINEER Rohul Ramadhan
Completion Engineer
Signed by: Rohul Ramadhan
7/15/2019

REVIEWED BY: GREGORY LUKE X


COMPLETION ENGINEERING ADVISO Gregory Luke
Completion Engineering Advisor
Signed by: Nasir Hoviari
7/15/2019

SANTOSO BUDI UTOMO X


APPROVED BY: sanbudi
DC ENGINEERING TEAM LEAD Santoso Budi Utomo
D&C Engineering Team Lead
Signed by: Santoso Budi Utomo
7/17/2019

NURMANTHIAS SETIAWAN X NSA


DC OPERATION TEAM LEAD Nurmanthias
D&C Operation Team Lead
Signed by: Nurmanthias Setiawan
7/17/2019

HENDRI JUNAIDI X Hendri Junaidi


DC OPERATION SUPERINTENDENT Hendri Junaidi
D&C Operation Superintendent
Signed by: Hendri Junaidi

RIG : APS 3517


AFE NUMBER : 2500CP7500
AFE AMOUNT : $44,925
PROGRAM NUMBER : DURI0726120190423PRF01
EST. TIME : 4 DAYS
Completion & Workover – DURI07261 – 5M54C

WELL COMPLETION & WORKOVER PROGRAM


5M54C (DURI07261)

Table of Content
A. OBJECTIVES .................................................................................................................................................... 2

B. INFORMATION AND DETAILS ........................................................................................................................... 2

1. BASIC WELL DATA ......................................................................................................................................................2


A. BEFORE AND AFTER DIAGRAM - WELL SCHEMATIC ............................................................................................................ 3
B. CURRENT - WELL SCHEMATIC........................................................................................................................................ 3
2. AS BUILT DATA – CASING/LINER DATA............................................................................................................................3
3. COMPLETION INTERVAL – GEOLOGICAL DATA, WELL PRESSURE, WELL TEMPERATURE, AND CALCULATED MASP ..........................3
4. WORKOVER HISTORY ...................................................................................................................................................4
5. GENERAL DATA ..........................................................................................................................................................5
6. WELL CONTROL RISKS..................................................................................................................................................5
7. COMPLETIONS FLUID MANAGEMENT PLAN ......................................................................................................................6
8. CASING/TUBING TEST PRESSURES ..................................................................................................................................7
CASING TEST IS REQUIRED / NOT REQUIRED IN THIS PROGRAM .................................................................................................7
9. BARRIER....................................................................................................................................................................7
10. DISPLACEMENT PROCEDURE........................................................................................................................................8
11. RIG - BOP CONFIGURATION......................................................................................................................................11
12. CHOKE MANIFOLD CONFIGURATION ...........................................................................................................................13
13. SHEAR TABLE .........................................................................................................................................................14
14. BOP TEST PRESSURES AND FREQUENCY ......................................................................................................................14

C. JOB PROCEDURE – BASE PLAN ....................................................................................................................... 16

1
Completion & Workover – DURI07261 – 5M54C

A. Objectives
The program objectives are:
• Maintain Well Control at All Times
• Provide safe and reliable operations
• POH TP
• Perforate interval in Rindu sand
• RIH new TP

B. Information and Details


1. Basic Well Data
Well Name 5M-54C
Well Grid DURI07261
1° 19' 50.142'' N
Well Coordinate
101° 14' .527 '' E
Well Type Oil Producer / Vertical
Spud Date 12-Apr-07
RTE (feet) 66
GLE (feet) 47
MD/TVD (feet) 766 / 766
PBTD (feet) 727
Wellhead Picture: Note:
1. Wellhead type:
▪ Tubing Head: 10-3/4” SOW x 11” 2M
▪ Tubing Hanger: 11” Nom x 3-1/2” NUE
▪ Cover Plate: 11” 2M x 3-1/2” Nom
2. Well status is ON
3. Good well pad condition and access road

2
Completion & Workover – DURI07261 – 5M54C

a. Before and After Diagram - Well Schematic

3
Completion & Workover – DURI07261 – 5M54C

Well Schematic

4
Completion & Workover – DURI07261 – 5M54C

2. As Built Data – Casing/Liner Data


Type Surface
Size (Inch) 18 5/8 Burst Rating (psi) 1694
OD (Inch) 18 5/8 Collapse Rating (psi) 546
ID (Inch) 17.75 Tension Rating (klbs) 865
Weight (lb/ft) 87.5 Setting Depth (MD) 135
Grade K-55 Setting Depth (TVD) 135
Pressure Test No, based on Historical Data.
Type Intermediate Casing
Size (Inch) 13 3/8 Burst Rating (psi) 1911
OD (Inch) 13 3/8 Collapse Rating (psi) 791
ID (Inch) 12.61 Tension Rating (klbs) 853
Weight (lb/ft) 54.5 Setting Depth (MD) 230
Grade K-55 Setting Depth (TVD) 230
Pressure Test No, based on Historical Data.
Type Production Casing
Size (Inch) 10-3/4” Burst Rating (psi) 2191
OD (Inch) 10 3/4 Collapse Rating (psi) 1106
ID (Inch) 10.05 Tension Rating (klbs) 629
Weight (lb/ft) 40.5 Setting Depth (MD) 469
Grade K-55 Setting Depth (TVD) 469
Pressure Test No, based on Historical Data
Type Tubing
Size (Inch) 3.5 Burst Rating (psi) 4060 (70%)
OD (Inch) 3.5 Collapse Rating (psi) 4004 (70%)
ID (Inch) 2.99 Tension Rating (klbs) 109.37
Weight (lb/ft) 9.3 Setting Depth (MD) 697
Grade J-55 Setting Depth (TVD) 697
Pressure Test No, based on Historical Data.
As Built Data – Fluid Inside Casing
Fluid Type Water
Fluid Weight (ppg) 8.33 PPG

5
Completion & Workover – DURI07261 – 5M54C

3. Completion Interval – Geological Data

Completion Interval – Geological Data, Well Pressure, Well Temperature, and Calculated MASP
Pressure and temperature Pressure refers to Rindu ‘sd
refer to Temperature refers to Pertama ‘sd
Max. Zone Pore Pressure 5.55 ppg
(PPG)
Min Zone Frac Gradient 9.29 ppg
(PPG)
Max. Zone Temperature 273 degF
(deg F)
MASP Calculation:

Note:
MASP during bullheading to be limited to 300 psi
Maximum allowable steam injection in DSF (surround well) is 0.6 psi/ft

4. Workover History
Date Comments
12-Jul-2016 STM04 - Acidizing Using Simple Acid – No Well Control Issue
MIRU 100%,N/D HH,CD,TOH PLGR,N/D WHA,N/U BOPE,CHECKED
TOS,TAG@728 (HOLE CLEAN),TOH 2-3/4" TP (SN:10-62367),R/T 6-5/8"
LINER SCRAPER,TAG@,,,,TIH w/ 3-1/2" OE TBG,HANG OE@,,,,N/D
BOPE,N/U 3" MASTER VALVE,N/D CIRCULATING LINES. (JOB SUSPEND DUE
TO ACIDIZING THREATMENT BY HLS TEAM).

05-Feb-2014 PMP05 - Rod Pump Not Pumping Normal – No Well Control Issue
MIRU 100% AT 5M-54C, TOS@715 FT (13 FT SAND FILL), TOH 2-3/4 TP (10-
61518), FOS F/715 FT TO 728 FT (PBTD), R/D FOAM COST $ 1,482.50, TIH 2-3/4

6
Completion & Workover – DURI07261 – 5M54C

TP (10-62367) + PLRG, PUMP SET @ 695 FT, TEST PUMPING 300 PSI, JOB COMP
AT 21:00 HRS. WELL POP AT 22:00 HRS. REPORTED TO BUSER CENTRAL

5. General Data
Mechanical Status in • Last Tag at 728 ft
Wellbore • Mechanical Problem: None based on report
Installed Wellhead ▪ Tubing Head: 10-3/4” SOW x 11” 2M
▪ Tubing Hanger: 11” Nom x 3-1/2” NUE
▪ Cover Plate: 11” 2M x 3-1/2” Nom

Bit History
13-Apr-2007 22 inch bit to 135 ft
14-Apr-2007 17.5 inch bit to 230 ft
18-Apr-2007 14 inch bit to 728 ft
16-Apr-2007 12.25 inch bit to 469 ft
17-Apr-2007 9.87 inch bit to 766 ft

6. Well Control Risks


• There is no historical Killing problem well kick due to insufficient
Hydrostatic Pressure.
• MASP is 18 psi from upcoming exposed zone Rindu ‘sd (add
Reservoir Pressure
perforation)
• Maximum pressure is 5.55 ppg from Rindu ‘sd (add perforation)
• Pressure may be higher than anticipated due to Steam
• Uncontrolled flow of hydrocarbon or steam to surface
• Higher GOR causing high shut-in pressure and flammability
Reservoir Fluid
• Presence of H2S causing personnel injury
• Hot water or crude oil causing personnel injury.
• Well is produced from Rindu, Pertama and Kedua ‘sd
Fluid Losses • In case need LCM, there's risk for shortage of LCM. However, Service
provider can deliver to location within 30 km
Mechanical • Plunger and rods left in hole unable to recover
• Tubing stuck, unable to pull with maximum capacity
Condition of Well
• Tubing broken/ collapsed after pulling
Bore
• Sand/ clay fill up wellbore, blockage the annulus
For Workover, criteria for shut In based on Chevron Pacific Indonesia
Offset Injector IBU_CPI_DR-SOP_33 Shutting in Steam Injectors prior to Drilling or
Wells Management Workover Activities (DSF) Section 5.1
Plan

7
Completion & Workover – DURI07261 – 5M54C

Duri 5M84C is located in Area 08 SW . Based on Chevron Pacific


Indonesia IBU_CPI_DR-SOP_33 Shutting in Steam Injectors prior to
Drilling or Workover Activities (DSF) Section 5.2 Criteria for
Monitoring – Table 2.

Request to shut in following injector well prior to rig to commence at


5M84C for injectors well in range up to 250 meters (821 ft).
N/A

List of surrounding injector wells that may potentially impact to the


wellbore are:

No need to shut-in those injectors due to no well control issue in


history. But D&C will request to Asset Team if there is killing problem
encounter during execution.
Other No other significant risks were evaluated.

7. Completions Fluid Management Plan


• Initial Killing use Fresh or Formation water (8.33ppg). Fill up well to cool
down or/and maintain over balance.
• If water density is not enough to kill the well then completion fluid density
can be determined as following formula (ensure well’s annulus or string has
been filled up with fresh or formation water) :
KF ppg = 8.33 ppg + {(Shut-in Pressure*)/(0.052 x TVD)} + 0.5 ppg (SF)
Minimum * If bullheading through tubing use SITP
If bullheading through annulus use SICP
Overbalance
• Completion Fluid Brine i.e. KCL, NaCl and combination of Sodium Formate
and Sodium Nitrate are commonly used for killing fluid within the area
operation which will be provided by a third-party Contractor
• Based on history, this well doesn’t have killing problem history. This well
could be killed using water from 60-120 bbls and bleed to 0 psi.
• In case found pressure, we will use safety factor 0.5 ppg
• Maximum pore pressure is 5.55 ppg, for initial killing will use water.

8
Completion & Workover – DURI07261 – 5M54C

Expect high fluid losses from Pertama sand


Mitigation for Fluid Loss:
- Refer to IBU SMO Loss circulation SOP section 2.2
- There are 2 tanks available in rig site with both have maximum 200 bbls
capacity or total for 2 tanks are 400 bbls. With average pump rate 2-5 bpm, 2
tanks could supply water for 80 – 200 minutes depends on the fluid loss and
supply water from killing line.
- Each of area has dedicated stand pipe or central gathering station (either
treated formation water or fresh water): Stand pipe 5U and 6L Brine and Mud
Fluid loss are provided by third party contractor (PT. Matra Unikatama).
control plan - With 1 load of vacuum or tanker capacity is 60 bbl., we need 7 load to full the
tank. We need the vacuum to re-fill up rig tank every 12 – 30 minutes to get
continues pumping (assuming no fluid in the tank).
- Based on assessment, the access road to location is good enough for vacuum
truck to reach the location. The availability of vacuum truck to be discussed
with operation team in Pre-Operation Meeting.
- If polymer is needed. Chemical for mixing polymer will be provided by service
company (Matra Unikatama) which base is located within 30 KM from the
field.

TCT/PCT N/A
Hydrates
N/A
Suppression

8. Casing/Tubing Test Pressures


Casing test is not required in this program
Casing test value is defined as per DCM-BST-102002-A-IBU-SMO 500psi + MASP/MAWP. Casing
test variance is 5% and 15 minutes stabilized as per Well Barrier Design SOP revised as per MOC
Barrier Test or Well Barrier Design SOP Black language.
Tubing test is not required in this program
Tubing test value is minimum 10% above operating pressure when the well is in operation or
500psi above MASP whichever is higher. Tubing test variance is 5% and 15 minutes stabilized as
per Well Barrier Design SOP revised as per MOC Barrier Test or Well Barrier Design SOP Black
language.

9. Barrier
No Operation Procedure Internal Barrier External Barrier
1. Non-Routine N/D or N/U Tree Kill Weight Fluid inside 1) Kill Weight Fluid
wellbore 2) Tubing Hanger
2. Routine N/U or N/D BOPE 1) Kill Weight Fluid 1) Kill Weight Fluid
2) Stab-in FOSV/IBOP 2) Tubing hanger with
seal mechanism
3. Routine Tripping with OE, 1) Kill Weight Fluid 1) Kill Weight Fluid
Casing Scrapper, 2) Stab-in FOSV/IBOP 2) BOP

9
Completion & Workover – DURI07261 – 5M54C

Packer, or other DHT


with definite diameter
4. Routine Release / install packer 1) Kill Weight Fluid 1) Kill Weight Fluid
with Workstring 2) Stab-in FOSV/IBOP 2) BOP
5. Routine - HO Foaming 1) Kill Weight Fluid 1) Kill Weight Fluid
2) Stab-in FOSV/IBOP 2) BOP
6. Routine Fishing operation with 1) Kill Weight Fluid 1) Kill Weight Fluid
DP (jar up/down) 2) Stab-in FOSV/IBOP 2) BOP
(Ready at rig
floor/wellhead)
3) Check valve pump
7. Non-Routine Wells Unable to Hold a Continue operations Continue operations
Column of Fluid. while pumping fluid while pumping fluid
into the well regularly. into the well regularly.
If there is no bleeve If there is no bleeve
history & free gas, history & free gas,
wellbore will have static wellbore will have
fluid level at some static fluid level at
point, monitor and fill some point, monitor
up wellbore as needed. and fill up wellbore as
needed.

10. Displacement Procedure


There is foaming job on this well.
Foaming job:
Internal barrier are hydrostatic, kelly cock/FOSV and IBOP. Meanwhile external barrier are
hydrostatic and BOP. BOP will be in open position during the displacement. Kelly Cock/FOSV and
IBOP will be installed at work string during execution to secure work string in case well control
incident happens. Detail procedure for Aerated/foaming job is available procedure.

10
Completion & Workover – DURI07261 – 5M54C

11. Rig - BOP Configuration


RIG: APS 3517
BOP Specification & Configuration - The following information for the Blow Out Preventer (BOP) stack shall
be specified for the well or well program/grouping.
No Acceptance Criteria Data
1. Quantity, Bore ID & Pressure Rating of Annular Preventer(s) 1 Unit/Ready/11 Inch x 3000 Psi
1 Unit, 11 Inch, 3000 Psi, Shear Blind
2. Quantity, Bore ID and Pressure Rating of the Ram Preventers
Ram
Configuration of Ram Preventers to include position within
the stack and Ram Type (i.e. Fixed Pipe, Variable Bore,
3. See picture BOP configuration below
Casing, Blind Rams, Blind Shear Rams, Shear Rams, Casing
Shear Rams, etc.)
Available Single Ram, size 11in x 3000
For each Pipe Ram type preventer provide pipe size or size
4. Psi c/w Blind Shear Ram, See picture
range and hang off capacity
BOP configuration below
Location, bore ID and Pressure Rating of the Choke & Kill 3-1/8 Inch x 3000 Psi (Choke), 3 Inch x
5.
Valves & Lines 3000 Psi (pipe Line)
Reference point and distance from reference for each See BOP space out diagram section
6.
component in the stack below
Elastomer type is Nitrile (NBR) with
Temperature rating and fluid compatibility of BOP temperature range -20 to 190 deg. F.
7.
rubbers/elastomers Oil and water-based muds. Poor
Resistance to H2S

11
Completion & Workover – DURI07261 – 5M54C

BOP Class 2
Component Dimension
Ram to WPF (A) 7.5 Ft.
Annular to WPF (B) 4.7 Ft.
Space to WPF (C) 0.7 Ft.
Drip Pan (D) 2.5 Ft.
Annular (E) 3.08 Ft.
Shear Blind Ram (F) 2.33 Ft.
Drilling Spool (G) 1.58 Ft.
Total BOP Stack (H) 13 Ft.

12
Completion & Workover – DURI07261 – 5M54C

12. Choke Manifold Configuration

13. Shear Table

14. BOP Test Pressures and Frequency


Allowable Pressure
Equipment Tested Pressure Test Requirement
Rating (psi)
BOP Class 2 – HO Operation
Low: 250 – 350 psi
Annular 2,100 (70%)
High: 1200 psi 5 minutes hold, with no
Low: 250 – 350 psi visible leakage
Shear Blind Ram 3,000
High: 1200 psi
Note:
• Ensure not to exceed 70% Casing Burst Pressure or 100% Wellhead RWP or 70% Annular RWP
or 100% Packer RWP
• All pressure tests must be recorded on a pressure recording chart (use Barton chart) and
BOP test form. The Chevron site representative shall witness and sign off on all BOP &
Choke manifold pressure tests.
The Frequency of the BOP tests

13
Completion & Workover – DURI07261 – 5M54C

Annular, Ram BOP, Choke Manifold, IBOP (Ready at rig floor/wellhead) and FOSV must be pressure
tested as follows:
a. Not exceed interval of 21 day
b. Before the equipment is put into operational service on wellhead
c. In accordance with the equipment owners PM program
d. Following the disconnection or repair of any wellbore pressure seal in the BOP stack
assembly or choke manifold (limited to the affected components only)
Chamber pressure test shall be performed and charted as follow:
a. At least once yearly
b. When equipment is repaired or manufactured
c. In accordance with the equipment owners PM program

14
Completion & Workover – DURI07261 – 5M54C

C. Job Procedure – Base Plan

HO Completion Engineering Team - Recommendation


DC Eng SMO Rumbai - 2019.

GENERAL PROCEDURE FOR WORKOVER HOOU - IBU SMO COMPLETION


WELL NAME / ID 5M54C-01

JOB TYPE PRF01 - Regular Perforation

CURRENT WELL STATUS ON

PROGRAM NUMBER DURI0726120190423PRF01

WELL PROFILE VERT

PROD CASING SHOE 469 ft

CURRENT TBA 376 ft

CURRENT/ PROPOSED 697 ft / 700 ft


PS
CURRENT PBTD 727 ft

DEVELOPED BY Fadhlan/Riko (07-May-2019)

Last Job History:


- This well was drilled on 19-Apr-2007 with OHGP completion and vertical well profile. Original target sand is PK sand.
- Last Rig job was STM04 (Acid CTU) on 12-Jul-2016 by CPI-79 & CTU-D1 . No well control issue.
Tag TOS @ 727 ft (Hole clean). R/T w/ Lnr Scrapper Tag @ 727 ft. CT TREATMENT ZONE : 514-524, 538-548, 568-578, 598-608-649-664, 691-
706 ft.
- PMP05 (NPN) job on 05-Feb-14 by CPI-74. TOS @ 715 ft (13 ft sand fill) - FOS to 728 ft (PBTD). No well control issue.
- No workover job performed yet on this well since drilled.
- Now asset propose to POH TP, wellbore clean up, raise up PBTD to 720 ft MD, add perforation (new zone - 4 SPF / regular) Rindu-1: 340-360 ft

15
Completion & Workover – DURI07261 – 5M54C

MD, then RIH TP.

Head Up List before moving into the well:


- Ensure to req to FOD (PMT) to shut off electric source and LOTO prior rig enter the location

Time
No PROCEDURE
(hrs)

1 MIRU RIG.
12
2 N/D PRODUCTION LINE. 2
3 CHECK SICP AND SITP, RECORD IN THE MORNING REPORT.
LINE UP LINES FROM CASING AND TUBING TO TANK. BLEED OF CASING AND TUBING PRESSURE TO 0 PSI (OR AS LOWEST
AS POSSIBLE) THEN CONTINUE TO KILL THE WELL. FLOW CHART KILLING WELL DSF CAN BE FOUND ON LAST PAGE AS
KILLING GUIDANCE.

Make sure to kill the well properly before commencing workover operation and also maintain primary well Control at all
time (WSEA 3A and 3B)

Last Successful Killing: water 8.33 ppg with volume max 120 bbls
24
Note: for well with killing problem history (RLN12) we may follow last successfull killing recipe above or may use other
alternative based on actual condition. Please discuss with fluid engineer and team leader operation for more detail
information.

Fresh or Formation water (8.33ppg) is used to fill up wells in most location in HO due to depleted formation. Filling up well
with water is normally performed to maintain fluid return to surface and maintain over balance. If the well unable to
maintain fluid column, operation can be continued while pumping fluid in to the well regularly

If water density is not enough to kill the well then completion fluid density can be determined as following formula (ensure

16
Completion & Workover – DURI07261 – 5M54C

well’s annulus or string has been filled up with fresh or formation water) :
KF (ppg) = 8.33 (ppg) + 0.5 ppg (SF) + (Shut-in Pressure (psi)*)/(0.052 x TVD top of perforation (ft))
*If bullheading through tubing use SITP
If bullheading through annulus use SICP

Completion Fluid Brine i.e. KCL, NaCl and combination of Sodium Formate and Sodium Nitrate are commonly used for killing
fluid within the area operation which will be provided by a third party Contractor

4 DISCONNECT STUFFING BOX, RELEASE POLISH ROD, POH PLUNGER AND SUCKER ROD STRING

History: TIH w/ 2-3/4" PLGR ON 26 JTS 7/8" S.ROD (USED 7/8" S COUPLING) + 1 JT 7/8" PONY ROD (4 FT) + 1-1/4" POLISH
ROD,PLGR SET@ 695.65

Fishing Tree Plan if found plunger stuck, 2


--> Option #1 : Apply over pull and reciprocate plunger or break shear coupling.
--> Option #2 : Blind backoff sucker rod.
--> Option #3 : Cut sucker rod using rod cutter.
--> Option #4 : Pull with tubing pump to recover the succer rod (stripping job)
Other options will be dictated based on the fish condition. Discuss with fisherman and TL Operation.

5 N/D X-MAS TREE, INSTALL FOSV, AND N/U BOP (ENSURE WELL SECURE). PERFORM FUNCTION TEST AND PRESSURE TEST
BOP.

Low pressure test BOP'S to 250 psi and high pressure test to 650 PSI or 500 + MASP hold 5 minutes each. Record on
6
Borton chart (WSEA 9B)

MASP = 18 psi
Inspect wellhead connection, valves, seals. replace if necessary.

17
Completion & Workover – DURI07261 – 5M54C

6 POH EXISTING TUBING STRING

History: TIH w/ 2-3/4" TP (SN:10-61628) ON 20 JTS 3-1/2" NUE TBG + 3 JTS 3-1/2" NUE PUP (20 FT). SET 10-3/4" TBG
HANGER, PUMP SET AT 696.64 FT.

Fishing Options for WPF Rig,


1. Please reciprocate and overpull stuck TP.
For 2-3/8" NUE tubing max overpull to 40 klbs, for 2-7/8" NUE tubing max overpull to 60 klbs and for 3-1/2" and 4-1/2" NUE
tubing overpull to 80 klbs. 12
2. R/U Wireline and RIH Jet Cutter. RIH FPI as necessary to determine stuck point - as deep as possible. If Stuck Point 200 ft
above TBA, cut tubing at 2 spots (1st in the middle of stucked fish, and 2nd above stuck point).
3. Continue with wash over using rotary shoe and circulate out (if loss use foam unit). For size of rotary shoe please find in
reference.
4. Fish out remaining fish (if thread in good condition, screw in tubing to TOF or use die collar or tapper tap, if thread is not
good RIH skirt mill and then use Overshot or Spear). For size of overshot and spear please find in reference
5. Repeat step no 2, 3, and 4 as necessary
Please confirm to CE prior performing step no 2, 3, 4 and 5.

18
Completion & Workover – DURI07261 – 5M54C

Fishing Options for RT Rig,


To free the existing completion string:
--> Option #1 : Back off with Rotary Slip
--> Option #2 : Jarring Job with Surface Jar - If Doughnut Stuck
Follow SOP for Jarring Job then continue with Option#1. Back off as deep as possible, recommended to backoff until below
TBA to continue process with wash over job.
--> Option #3 : R/U Wireline and RIH Jet Cutter or Prima Cord (String Shot) - follow SOP for Back off with wireline. RIH FPI as
necessary to determine stuck point - as deep as possible. If Stuck Point 200 ft above TBA, cut tubing at 2 spots (1st in the
middle of stucked fish, and 2nd above stuck point ).

Continue with fishing job as below,


1. Wash over using rotary shoe and circulate out (if loss use foam unit).
2. Fish out remaining fish (if thread in good condition, screw in tubing to TOF or use die collar or tapper tap, if thread is not
good RIH skirt mill and then use Overshot or Spear).

Note,
1. If TOF is not clear please Run IB, next job will be decided based on IB result.
2. Do not conduct back off tubing for WPF Rig (if need to back off tubing, please suspend job and move out rig)
3. Please do inspect pulled tubing string condition (every tubing, nozzles, mandrel and cup packer). Report for any anomaly
4. Notes in the tour report if there is any anomaly such as fluid cut, sand fill, scale, etc
5. Please discuss with Fisherman and TL Operation if any deviation.
In case Rig did not successful to pull out stuck tubing pump and have to pending well, make sure to TIH tubing pump
(instead of OE tubing) so Rig still able to perform pressure test Xmas tree (all tree, connections, stuffing box, or sample
cock whichever applicable) to 500 psi + MASP as per stated in WSEA 10-L

Reference,
Fishing in Casing
Fishing in Liner
Fishing tool per hole size

19
Completion & Workover – DURI07261 – 5M54C

7 SPOT CEMENT WITH TOC AS TARGETTED ON RECOMMENDATION

TOC is expected at 720 ft as the new PBTD


Cement slurry calculation: 0.85 sacks cement + 0.32 Sacks Silica + 21 L Water
WOC est 3-4 hrs
4
TIH with 3-1/2" or 4-1/2" OE tubing and set 20 - 30 ft above target TOC
Displace tubing with at least 1 volume tubing after spot cement
Raise up OE tubing and WOC
Tag actual top of cement and update wellview report

8 ROUND TRIP WITH CASING SCRAPPER TO TBA AND LINER SCRAPPER TO NEW PBTD

Run with 6-5/8" liner scrapper and 10-3/4" casing scrapper


TBA : 376 ft
PBTD : 720 ft
4

Do Not Rotate the String while running or scrapping the casing


If there is indication casing damage, please execute "Contingency Plan for Casing Leaking/ Clay Problem" - Please call TL
Operation and CE before conducting this plan

20
Completion & Workover – DURI07261 – 5M54C

9 PERFORATING JOB BY SERVICE COMPANY


Prior perforation job please make sure to perform pressure test to lubricator and its connection (WSEA 10A, B, and C)
Gun size: 4.5"
Perforation interval,

Well Interval (ft) Length (ft) Density Sand Gun Type


5M-54C 340-360 20 4 spf R1 Reguler

Required Fluid Level

For New Perforation Zone (NZBP/PRF01):


- Check fluid level before perforation, if wellbore is full of fluid then continue with perforation job. If not, follow next
procedure.
- Isolate existing perforation zone with sand and cement cap to at least 10 ft above TBA or 10 ft above existing top opened
sand. If static level achieves as per require fluid level, then continue with perforation job
- If require static fluid level can't achieve, please check wellbore integrity and overcome the problem. Seek advice to TL
Operation and CE.
- After each perforation run, observe well for 15 minutes and cooling the well as needed. For steam zone that steam exist
based on G&G data, please cooling down with 1500 bbls water.
- For opening isolated perforation zone, please ensure:
▪ Continue pumping water during DOC/clean out sand
▪ Ensure sufficient water supply for the job

21
Completion & Workover – DURI07261 – 5M54C

▪ Use 1 bpm over initial killing rate. After assessment, if the pumping rate and water supply isn’t possible, then do not
procced to open the isolation zone, propose production only from new perforation zone. Please contact TL Operation
and CE.
Note:
- Please follow SOP for perforation Job by service company
- Please ensure all the charges has fired and report it in Wellview
- Please avoid casing collar

Reference,
Marked Log or CBL Folder
10 CLEAN OUT SAND TO PBTD
RIH with mule shoe and clean out sand to PBTD.
Ensure water supply is enough during clean out

Option for clean out sand on a loss circulation condition,


1. Pump fluid into wellbore with max rigs pump rate
2. Pump using 40 smf polymer. If well is still experiencing loss circulation, increased completion viscosity by 10 smf until 6
max of 80 smf.
3. Aerated polymer
4. Use Foam whenever required if there is experience loss circulation
Reference,
Loss Circulation SOP page 11-12
11 RIH WITH TUBING PUMP AS PER PROGRAM REQUIREMENT.
Install tubing hanger and pressure test to 650 psi or 500 psi + MASP hold 5 mnts as per WSEA 10 H.
RIH TP 2.75 inch tubing pump with 3.5 PMS (250 micron) with bottom pump at 700 ft MD. 2

Please inform CE if get indication new sand fill in the wellbore


12 INSTALL FOSV, N/D BOP, NU X-MAS TREE 4

22
Completion & Workover – DURI07261 – 5M54C

13 RIH PLUNGER, SUCKER ROD AND POLISH ROD. SET PLUNGER AS PER PUMP SET.
Perform pressure test Xmas tree (all tree, connections, stuffing box, or sample cock whichever applicable) to 500 psi +
MASP as per stated in WSEA 10-L.
1
Conduct test pumping 300 psi - 10 minutes to make sure pump can be normally operated
If it is OK- Continue R/D Rig,
If leaking - Re POH Tubing Pump & check, change TP if needed
14 N/U PRODUCTION LINE. 1
15 RDMO
Ensure to do Proper Handover with PMT.
2
Note: Ensure to write down handover information in the tour report.
Contingency Plan for Casing Leaking/ Clay

CONDUCT PRESSURE TEST CASING


Problem - Please call CE before

Before performing Pressure test please isolate lower zone by setting packer (serco/DCS) or dump sand and cement cap if
necessary. Pressure Test casing with 300 PSI and hold for 5 mnts.
conducting this plan.

IF test casing is OK - continue with the next original program.


IF there is any indication of casing leak, perform the following step:
3
1. Locate casing leak by adjusting packer depth setting or by using pressure washer
2. Perform injectivity test with low rate and record as a base line for Squeeze Cementing Design
3. Prepare next step to do Squeeze Job.

Other options or detail information please discuss with TL Operation

23
Completion & Workover – DURI07261 – 5M54C

ISOLATE OPEN ZONE WITH ONE OF BELOW METHOD DEPEND ON WELL CONDITION.

1. Using packer-- Retrievable Packer + Dump 5 ft sand on top


a. RIH with Retrievable Packer
follow SOP for Running and Setting Packer complete with Setting/Releasing Tools.
b. RIH with Mule Shoe and dump sand at least 20 ft above packer. 4
2. Dump sand above TBA and Cement cap 5 ft
a. RIH with Mole Shoe and dump sand above TBA/open interval or depend on program.
b. Dump 5 - 10 ft Cement Cap with Class "G" Cement on top of the sand

Discuss with TL Operation if other isolation alternative need to be proposed.


PREPARE CEMENTING UNIT AND PERFORM SQUEEZE CASING LEAK JOB

Discuss with TL Operation, Completion Engineer, and or Cementing Engineer to determine detail squeeze method (basic 12
method is bullhead)
WOC
WOC as per design and monitor cement surface sample 6

DOC TO ORIGINAL TOP OF CEMENT. RETEST SQUEEZE CASING LEAK RESULT.


Pressure test casing and increase pressure gradually (per 100 psi) to get 300 psi - 5 mnts hold.
4
If still leaking, discuss with TL Operation and Completion Engineer if required additional squeeze or other alternative will be
taken.

TOTAL TIME : P10


66 3.0 Days
Assumption: No Test Casing, No Casing Leak, No Killing Problem, No Fishing Problem
TOTAL TIME : P50
84 4.0 Days
Assumption: No Test Casing, No Casing Leak, with Fishing Problem
TOTAL TIME : P90
109 5.0 Days
Assumption: Test Casing,Casing Leak, with Fishing Problem & Killing Problem

24
Completion & Workover – DURI07261 – 5M54C

25