Structural and All Pipe line Fabrication Erection & Man Power Services
(Fabricator, Fitter, Welder, Helper and Lab Technician’s)
Email: Kenengineers.blr14@gmail.com, Phone: 9731333955, 9986171534
CONTENTS
1. ACTIVTY DESCRIPTION
2. POTENTIAL HAZARDS PRESENT
3. LOCATION
4. PRE ACTIVITY MEETING / CO-ORDINATION
5. WORK PERMIT
6. SAFE WORKING PROCEDURE
7. EMERGENCY PROCEDURE
8. NECESSARY PERSONAL PROTECTIVE EQUIPMENT
9. SPECIALISED TRAINING REQUIREMENT
10. PERIODIC VERIFICATION OF PROCEDURES
Near Bloomers School, Reddy Building, Over Head Tank Ring Road, Kodugodi PO, Channasandra Bangalore - 67
1. ACTIVITY DESCRIPTION
Earthwork of more than one foot is considered as Excavation.
3. LOCATION:
4. PRE-ACTIVITY MEETINGS: -
The contractors and or the Site representative designated to supervise the job will inform the EHS leader/
Facility leaders before starting the work. They will inform about the High Risk Operations. The person
(EHS/Facility) designated to supervise the job, will have the overall responsibility of all the safety measures
being implemented.
The following points will be discussed in the Pre-activity meeting:-
Hazard recognition & Preventive Measures
Training Requirements
Work plan & scheduling
Equipments required
Emergency procedure
5. WORK PERMITS: -
Excavation Work Permit signed by EHS / Facility Personnel be taken after a thorough review of our
safety measures and equipment on site.
Near Bloomers School, Reddy Building, Over Head Tank Ring Road, Kodugodi PO, Channasandra Bangalore - 67
Following check points are ensured where the activity is being done:
The utilities in the area like gas pipeline, electrical cables, sewer, data cables identified
The concerned electrical or other service lines isolated & LOTO applied
The shoring or trenching shield required & provided to prevent soil shift.
Check for any overhead obstruction.
Proper ventilation & lighting available/provided.
The area barricaded & caution board displayed.
Avoid the personnel approach to the edge of the excavating pit.
The electrical equipments earthed & cable protected from damage.
The proper scaffold/ladder provided & tied at the top.
The standby person deputed to provide help in emergency.
The safety belt used & lifeline anchored above the working level.
The required Personal Protective Equipment (Hand gloves, Helmet, Safety glasses, Ear plugs, Safety
Shoes).
The employees working in excavation are trained & training records given to EHS.
7. EMERGENCY PROCEDURE: -
The operators are trained in the process as well as in the High risks involved.
Signature Signature
Prepared by: ( ) Aproved by: ( )
Date: Date:
Near Bloomers School, Reddy Building, Over Head Tank Ring Road, Kodugodi PO, Channasandra Bangalore - 67