Beruflich Dokumente
Kultur Dokumente
This document contains proprietary and confidential information which is the property of Chemetics
Inc. and which is not to be used for any purpose other than for the due execution of Chemetics’ projects
by Chemetics personnel and otherwise in the operation of Chemetics’ business. The contents of this
document are not to be reproduced or provided or made available to third parties, including but not limited
to our clients, whether in part or in full, without the prior consent of the Chemetics Legal Department.
Table of Contents
1. Purpose
This Specification defines Chemetics Inc. requirements for the supply and installation of external
thermal insulating materials for acid plant equipment, ducting and piping.
2. Scope
This Specification applies to gas/gas exchangers, ducting, steaming equipment (waste heat boilers,
super heaters and economisers) and process and utility piping. Other acid plant equipment and
equipment components are covered in the following specifications:
Underside of gas/gas exchangers – 6-SPC-0004: Gas/Gas Exchanger Underside Insulation
Equipment supported on grillages – 6-SPC-0005: Equipment Grillage Insulation
Converter – 6-SPC-7540: Converter Thermal Insulation
3. Definitions
4. References
5. Background
The insulation system described herein has been specifically developed for Chemetics® acid plant
equipment, ducting and piping. Contact section equipment operates at temperatures up to 650C
(1200F). Thermal growth will be very significant under these conditions. The insulation system
described herein will:
Allow the equipment to expand without significant radial movement of the cladding
Prevent damage to the cladding and insulation due to thermal growth of the equipment
Provide a weather tight system
Prevent joints in the insulating materials from opening as the equipment expands (cold spots
on the equipment and hot spots on the cladding are thus avoided)
Achieve superior heat conservation because insulating materials are not excessively
compressed as the equipment expands
6. Scope of Supply
6.1. General
Unless otherwise noted, the Subcontractor will supply all thermal insulation materials required for the
complete insulation of the equipment ducting and piping in accordance with this Specification. In
particular, the supply will include, but not be limited to, the following:
Capacitor discharge weld pins and speed washers
Cladding
All fasteners and latches
Bands, wire and CHIL-SPRINGS®
Insulation materials
Wire mesh for facing and support of insulation
Cladding support rings and expansion spacers (Figures 8 and 10)
Support rings (Figures 5 and 6) and capping rings
Caulking and sealing materials
Documentation for all materials used
Installation drawings showing the arrangement and relevant details of the installation
Bagging, tagging and marking
6.2. Equipment
6.3. Ducting
Ducting to be insulated is identified in 5-LST-0001: Line List. This document shows the insulation
type and thickness.
6.4. Piping
Piping to be insulated is identified in 5-LST-0001: Line List. This document shows the insulation type
and thickness.
7. Materials
7.1. General
The specific materials described below are approved by Chemetics for use in acid plant installations.
Substitutions and alternatives require written approval from Chemetics.
All materials will be flame resistant and non-corrosive in either the wet or dry condition.
All insulating materials will meet the requirements of ASTM C 795 and will have controlled low
chloride content, suitable inhibitor or other effective means to guard against stress corrosion cracking
of stainless steel equipment, ducting and piping.
Materials containing asbestos are not permitted.
All materials will be of new and clean stock.
Mineral wool blankets will be used on ducting, piping greater than DN600 (24” NPS), and all
equipment vertical surfaces. Material will conform to ASTM C 592 Type III and the following
additional requirements:
Bulk density (excluding mesh facing) = 128 kg/m3 (8 lb/ft3) minimum.
Service temperature rating = 650C (1200F) minimum.
Shot content = 15% maximum (by weight).
Sulphur compounds content = 1% maximum (in terms of sulphur).
Cladding will be 304 stainless steel. All insulated surfaces will be clad with Standard Gage (USG)
No. 28 (0.40mm (0.016”)) thick sheet. Ducting, piping and equipment horizontal surfaces will be clad
with smooth sheet. Equipment vertical surfaces will be clad with 67mm (2 5/8”) wide x 16mm (5/8”
deep) corrugated sheet.
Cladding to be coated per subcontractor standard paint. Colour shall be Buff Brown RAL 1011
Ameron No. BR-3 or equivalent.
Expansion spacers will be fabricated from 50mm (2”) wide x 1.5mm (1/16”) thick 304 stainless steel
to the dimensions shown in Figure 8.
Cladding support rings (Figure 8) will be fabricated from 50mm (2”) wide x 3mm (1/8”) thick 304
stainless steel. Rings will be cut to lengths that can be conveniently shipped. Mating pieces will be
spliced together by welding.
Support rings (Figures 5 and 6) will be fabricated from 3mm (1/8”) thick 304 stainless steel. Ring
width will be insulation thickness less 25mm (1”).
Capacitor discharge weld pins will be 304 stainless steel. Pin diameter will be SWG (Standard Wire
Gage) No. 10 (3.2mm (0.125”)).
All banding and wire used to retain the insulation and cladding will be 304 stainless steel.
Tie wire diameter will be SWG No. 18 (1.2mm (0.048”)) minimum. Bands will be:
13mm (1/2”) wide x USG No. 28 (0.40mm (0.016”)) thick for all piping and for ducts up to
900mm (36”) diameter.
19mm (3/4”) wide x USG No. 25 (0.56mm (0.022”)) thick for all equipment and for ducts over
900mm (36”) diameter.
Z clips will be fabricated from 50mm (2”) wide x USG No. 18 (1.27mm (0.050”)) thick sheet.
S clips will be fabricated from 100mm (4”) wide x 150mm (6”) long x USG No. 18 sheet.
All other miscellaneous clips will be fabricated from USG No. 18 series 300 stainless steel sheet.
8. Insulation Thickness
Equipment insulation thickness is shown in 6-LST-0001: Equipment Insulation. Ducting and piping
insulation thickness is shown in 5-LST-0001: Line List.
The total insulation thickness will be achieved by layers of 50mm (2”) and/or 25mm (1”) thick mineral
wool mattresses, semi-rigid boards, or formed hollow cylinders as applicable.
9. Installation
9.1. General
The completed installation will be suitable to properly conserve heat, protect personnel, shed water,
resist the corrosive atmospheric conditions present, and accommodate thermal expansion of the
equipment without disrupting the insulation or cladding.
© Copyright 2017, Chemetics Inc. All rights reserved. Page 7 of 25
SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
The installation methods described herein are approved by Chemetics, but are by no means the only
acceptable methods. Any deviations from the requirements of this Specification must, however, be
noted in the Installer’s proposal and must be approved by Chemetics.
Materials will not be placed or stored directly on the ground.
All precautions recommended by the insulation manufacturers will be followed.
The Installer will ensure that all surfaces to be insulated are dry and clean prior to any welding or
installation of insulation.
The Installer will maintain working areas in a clean and orderly fashion, free of debris and refuse. All
loose, damaged or other unusable materials will be removed to a suitable refuse container on a daily
basis.
The Installer will not cause any equipment, structural steel or buildings to be soiled or damaged.
Large equipment (> 4m (13’) diameter) will have significant thermal growth. Consequently, the
cladding must be supported independently of the insulation by means of cladding support rings and
expansion spacers.
Cladding support rings will be attached to the shell by means of expansion spacers (see Figure 8).
The maximum circumferential distance between expansion spacers will be 600mm (24”). Expansion
spacers will be of sufficient length to allow for thermal expansion of the equipment per the following
table:
Table 1
Equipment Diameter Expansion Allowance
> 4m to 5m (13’ to 16’) 32mm (1 ¼”)
> 5m to 6m (16’ to 20’) 40mm (1 ½”)
> 6m to 7m (20’ to 23’) 45mm (1 ¾”)
> 7m to 8m (23’ to 26’) 50mm (2”)
Cladding support rings will be spaced at 900 to 1200mm (36 to 48”) intervals. The location of support
rings will be selected to minimize circumferential interruptions due to nozzles. When a support ring
intersects a nozzle, continuity of the ring (and hence its load carrying capacity) will be maintained by
installation of an additional ring around the nozzle circumference as shown in Figure 13.
Cladding support rings will be attached to the roof by means of expansion spacers (see Figure 10).
The maximum circumferential spacing between expansion spacers will be 900mm (36”). Radial
spacing between cladding support rings will be the cladding sheet width less 75mm (3”).
All welding will be in accordance with 4-SPC-0060: Equipment Welding Carbon Steel or 4-SPC-0061:
Equipment Welding Austenitic Stainless Steel as applicable.
Capacitor discharge weld pins will be attached to the vessel by capacitor discharge welding. Other
attachment methods require approval by Chemetics.
Pins will be installed on a square pitch. Maximum permissible spacing will be as follows:
© Copyright 2017, Chemetics Inc. All rights reserved. Page 8 of 25
SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
Vertical surfaces 500mm (20”)
Upward facing surfaces 600mm (24”)
Downward facing surfaces 300mm (12”)
The Subcontractor will indicate the actual pin spacing on the installation drawings. Spacing will be
such that each individual insulation blanket or board is impaled by at least four pins. Pins will not be
used for insulation over duct expansion joints (see Figure 2).
When used with semi-rigid board, pins will be 13mm (1/2”) shorter than the insulation thickness and
no speed washers will be used. When used with mineral wool blankets, the pins will be longer than
the insulation thickness and the ends bent back to below the insulation surface after installation of
speed washers (Figure 4).
9.4. Insulation
Insulation will be installed in a staggered pattern. Minimum offset between seams will be 300mm
(12”). Outer layers will overlap seams in the underlying layers.
Mineral wool blankets will be installed with the wire mesh facing outwards. Adjacent edges of
blankets will be loosely wired together. Additionally, the outermost layers will have a minimum of two
bands in contact with each blanket. Each band will have four CHIL-SPRINGS®.
Semi-rigid mineral wool board will be cut to fit the vessel contour. Voids will be filled with loose
mineral wool insulation.
9.5. Cladding
Cladding sheets will be securely installed such that rain water, melting snow or other atmospheric
moisture cannot come in contact with the insulation.
Cladding will be installed in such a manner that the radial and vertical growth of the equipment is
accommodated. Cladding on vertical surfaces may be installed either in horizontal courses or
vertical panels.
Horizontal installation is detailed in Figure 9A. Details are as follows:
Each horizontal (circumferential) cladding course will be attached to the uppermost support
ring only.
Horizontal seams will overlap by 75mm (3”) and vertical seams will overlap by 100mm (4”)
minimum.
Vertical seams in adjacent courses will be offset 300mm (12”) minimum.
Each horizontal cladding course will be held with a minimum of two spring loaded bands.
Bands will be held in place with loops spaced at 1200mm (48”) intervals.
Circumferential overlaps between courses will be maintained with “Z” clips on 600mm (24”)
centers.
Vertical installation is detailed in Figure 9B. Details are as follows:
Each vertical panel will be attached to the uppermost support ring only.
Cladding will be held in place with spring loaded stainless steel bands spaced at 600mm (24”).
Horizontal seams will overlap by 75mm (3”) and vertical seams will overlap by 100mm (4”)
minimum (see Figure 5).
At least one longitudinal seam per cladding course must be designated for expansion (i.e. free
to move as the vessel or duct expands).
Circumferential overlaps between courses will be maintained with “Z” clips on 600mm (24”)
centers.
Vertical seams in adjacent courses will be offset 300mm (12”) minimum.
Horizontal joints between roof and shell cladding will be secured by self-tapping screws as
shown in Figure 6.
Radial seams on equipment roofs will be overlapped using a watertight slip joint as shown in
Figure 7.
Cladding on equipment and vertical duct runs will be supported by angle cleats resting on
support rings (Figures 5 and 6).
9.5.3. Pipe
Cladding will be held in place with spring loaded stainless steel bands spaced at 600mm (24”).
Seams will overlap by 50mm (2”) minimum.
The following details are left to the discretion and experience of the Subcontractor:
Removable insulation covers on manways
Details at junctions between vessel and nozzle insulation
Minor flashing and sealing details
All such details will be defined in the installation drawings and approved by Chemetics prior to
installation. In developing these details, the Subcontractor will ensure that the function and integrity
of the insulation system is not compromised.
FIGURE 1
END CAP AT INSULATION LIMIT ON DUCTS
FIGURE 2
INSULATION AND CLADDING AROUND DUCT EXPANSION JOINTS
FIGURE 3
INSULATION OVER ECONOMISER STIFFENERS
FIGURE 4
MINERAL WOOL BLANKETS
FIGURE 5
CLADDING ON DUCTS AND SMALL EQUIPMENT
(< 4m (13’) DIAMETER)
FIGURE 6
ROOF TO SHELL CLADDING JOINT ON SMALL EQUIPMENT
(< 4m (13’) DIAMETER)
FIGURE 7
SLIP JOINT IN ROOF CLADDING ON SMALL EQUIPMENT
(< 4m (13’) DIAMETER)
FIGURE 8
EXPANSION SPACERS AND CLADDING SUPPORT RINGS
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)
FIGURE 9a
INSTALLATION OF CLADDING (HORIZONTAL COURSES)
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)
FIGURE 9b
INSTALLATION OF CLADDING (VERTICAL PANELS)
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)
FIGURE 10
EXPANSION SPACERS AND CLADDING SUPPORT RINGS FOR VESSEL ROOFS
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)
FIGURE 11
INSTALLATION OF ROOF CLADDING ON LARGE EQUIPMENT
(> 4m (13’) DIAMETER)
FIGURE 12
ROOF TO SHELL CLADDING JOINT ON LARGE EQUIPMENT
(> 4m (13’) DIAMETER)
FIGURE 13
EXPANSION SPACERS AND CLADDING SUPPORT RINGS AT NOZZLE OPENINGS
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)
FIGURE 14
REMOVABLE MANWAY COVER ON LARGE EQUIPMENT
(> 4m (13’) DIAMETER)