Sie sind auf Seite 1von 25

SPCC

AP1 DCDA Conversion Specification


Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
Rev: Date: Status: Prepared By: Checked By: Approved By:
3 05-Apr-18 Approved for Fabrication A.Trikha E. Cori A.Trikha
2 9-Nov-17 Approved for Fabrication E. Li E. Cori T. Wacker
1 18-Aug-17 Approved for Fabrication (MS-R1) A. Marks E. Cori T. Wacker

This document contains proprietary and confidential information which is the property of Chemetics
Inc. and which is not to be used for any purpose other than for the due execution of Chemetics’ projects
by Chemetics personnel and otherwise in the operation of Chemetics’ business. The contents of this
document are not to be reproduced or provided or made available to third parties, including but not limited
to our clients, whether in part or in full, without the prior consent of the Chemetics Legal Department.

NOTES REGARDING VALIDITY OF THIS DOCUMENT:

Paper copies are uncontrolled.


This copy is valid only at the time of printing.
The controlled version of this document is available from the Company Intranet.

© Copyright 2017, Chemetics Inc. All rights reserved. Page 1 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

Table of Contents

1.  Purpose ........................................................................................................................................ 3 


2.  Scope ........................................................................................................................................... 3 
3.  Definitions .................................................................................................................................... 3 
4.  References ................................................................................................................................... 3 
5.  Background ................................................................................................................................. 4 
6.  Scope of Supply .......................................................................................................................... 4 
6.1.  General ......................................................................................................................................... 4 
6.2.  Equipment ..................................................................................................................................... 5 
6.3.  Ducting .......................................................................................................................................... 5 
6.4.  Piping ............................................................................................................................................ 5 
7.  Materials ....................................................................................................................................... 5 
7.1.  General ......................................................................................................................................... 5 
7.2.  Mineral Wool Insulation ................................................................................................................. 5 
7.3.  Cladding ........................................................................................................................................ 7 
7.4.  Fixing Materials ............................................................................................................................. 7 
8.  Insulation Thickness ................................................................................................................... 7 
9.  Installation ................................................................................................................................... 7 
9.1.  General ......................................................................................................................................... 7 
9.2.  Cladding Supports ......................................................................................................................... 8 
9.3.  Insulation Supports ....................................................................................................................... 8 
9.4.  Insulation ....................................................................................................................................... 9 
9.5.  Cladding ........................................................................................................................................ 9 
9.5.1.  Large Equipment (> 4m (13’) diameter) ........................................................................................ 9 
9.5.2.  Small Equipment (< 4m (13’) diameter) and Ducts ..................................................................... 10 
9.5.3.  Pipe ............................................................................................................................................. 10 
10.  Details by Subcontractor .......................................................................................................... 10 

© Copyright 2017, Chemetics Inc. All rights reserved. Page 2 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

1. Purpose

This Specification defines Chemetics Inc. requirements for the supply and installation of external
thermal insulating materials for acid plant equipment, ducting and piping.

2. Scope

This Specification applies to gas/gas exchangers, ducting, steaming equipment (waste heat boilers,
super heaters and economisers) and process and utility piping. Other acid plant equipment and
equipment components are covered in the following specifications:
 Underside of gas/gas exchangers – 6-SPC-0004: Gas/Gas Exchanger Underside Insulation
 Equipment supported on grillages – 6-SPC-0005: Equipment Grillage Insulation
 Converter – 6-SPC-7540: Converter Thermal Insulation

3. Definitions

AWG American Wire Gage


Use in this Specification is defined as the party responsible for
Subcontractor
supply & field installation of the insulation system
SWG Standard Wire Gage
USG US Standard Gage

4. References

Document/Reference Number Title


4-SPC-0060 Equipment Welding Carbon Steel
4-SPC-0061 Equipment Welding Austenitic Stainless Steel
5-LST-0001 Line List
6-DTL-XXXX Equipment Insulation Detail Drawings
6-DTL-XXXXXX Duct Insulation Detail Drawings
6-LST-0001 Equipment Insulation
6-SPC-0004 Gas/Gas Exchanger Underside Insulation
6-SPC-0005 Equipment Grillage Insulation
6-SPC-7540 Converter Thermal Insulation
ASTM C 547 Standard Specification for Mineral Fiber Pipe Insulation
Standard Specification for Mineral Fiber Blanket Insulation and
ASTM C 592 Blanket-Type Pipe Insulation (Metal-Mesh Covered) (Industrial
Type)
© Copyright 2017, Chemetics Inc. All rights reserved. Page 3 of 25
SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
Standard Specification for Mineral Fiber Block and Board Thermal
ASTM C 612
Insulation
Standard Specification for Thermal Insulation for Use in Contact
ASTM C 795
with Austenitic Stainless Steel

5. Background

The insulation system described herein has been specifically developed for Chemetics® acid plant
equipment, ducting and piping. Contact section equipment operates at temperatures up to 650C
(1200F). Thermal growth will be very significant under these conditions. The insulation system
described herein will:
 Allow the equipment to expand without significant radial movement of the cladding
 Prevent damage to the cladding and insulation due to thermal growth of the equipment
 Provide a weather tight system
 Prevent joints in the insulating materials from opening as the equipment expands (cold spots
on the equipment and hot spots on the cladding are thus avoided)
 Achieve superior heat conservation because insulating materials are not excessively
compressed as the equipment expands

6. Scope of Supply

6.1. General

Unless otherwise noted, the Subcontractor will supply all thermal insulation materials required for the
complete insulation of the equipment ducting and piping in accordance with this Specification. In
particular, the supply will include, but not be limited to, the following:
 Capacitor discharge weld pins and speed washers
 Cladding
 All fasteners and latches
 Bands, wire and CHIL-SPRINGS®
 Insulation materials
 Wire mesh for facing and support of insulation
 Cladding support rings and expansion spacers (Figures 8 and 10)
 Support rings (Figures 5 and 6) and capping rings
 Caulking and sealing materials
 Documentation for all materials used
 Installation drawings showing the arrangement and relevant details of the installation
 Bagging, tagging and marking

© Copyright 2017, Chemetics Inc. All rights reserved. Page 4 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
 Packaging and crating
The Subcontractor will ensure that the quantities of material (including allowances for normal
wastage and loss) are sufficient to complete the work.
The following components are excluded from the Subcontractor’s scope of supply:
 Duct insulation capping rings (Figure 1). These will be supplied by the ducting Vendor.

6.2. Equipment

Equipment to be insulated is identified in 6-LST-0001: Equipment Insulation. This document shows


the insulation type and thickness. Where the information shown in 6-LST-0001: Equipment Insulation
is insufficient to define the extent of insulation, Chemetics will produce Equipment Insulation Detail
Drawings (6-DTL-XXXX).

6.3. Ducting

Ducting to be insulated is identified in 5-LST-0001: Line List. This document shows the insulation
type and thickness.

6.4. Piping

Piping to be insulated is identified in 5-LST-0001: Line List. This document shows the insulation type
and thickness.

7. Materials

7.1. General

The specific materials described below are approved by Chemetics for use in acid plant installations.
Substitutions and alternatives require written approval from Chemetics.
All materials will be flame resistant and non-corrosive in either the wet or dry condition.
All insulating materials will meet the requirements of ASTM C 795 and will have controlled low
chloride content, suitable inhibitor or other effective means to guard against stress corrosion cracking
of stainless steel equipment, ducting and piping.
Materials containing asbestos are not permitted.
All materials will be of new and clean stock.

7.2. Mineral Wool Insulation

Mineral wool blankets will be used on ducting, piping greater than DN600 (24” NPS), and all
equipment vertical surfaces. Material will conform to ASTM C 592 Type III and the following
additional requirements:
 Bulk density (excluding mesh facing) = 128 kg/m3 (8 lb/ft3) minimum.
 Service temperature rating = 650C (1200F) minimum.
 Shot content = 15% maximum (by weight).
 Sulphur compounds content = 1% maximum (in terms of sulphur).

© Copyright 2017, Chemetics Inc. All rights reserved. Page 5 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
 Leachable chlorides will not exceed the limits of ASTM C 795.
 Thermal conductivity = 0.063 W/m/K (0.44 BTU*in/ft2/hr/F) maximum @ 204C (400F).
 Insulation blankets will have a mesh facing on one side only. The facing will be 25mm (1”)
hexagonal shaped 300 series stainless steel mesh. Wire diameter will be American Wire
Gage (AWG) No. 20 to 22 (0.82 to 0.64mm (0.032 to 0.025”)).
 Insulation blankets will not be more than 50mm (2”) thick.
 Insulation blankets will be supplied in easy to handle sizes, either 600 x 1200mm (2 x 4 ft) or
600 x 2400mm (2 x 8 ft).
 Binder burn-out will not adversely affect the structural and insulating properties of the mineral
wool.
 Loose material will be of the same specification as above.
Semi-rigid mineral wool boards will be used on all equipment horizontal surfaces (i.e. vessel roofs).
Material will conform to ASTM C 612 Type IVB and the following additional requirements:
 Bulk density (excluding mesh facing) = 192 kg/m3 (12 lb/ft3) minimum.
 Service temperature rating = 650C (1200F) minimum.
 Shot content = 15% maximum (by weight).
 Sulphur compounds content = 1% maximum (in terms of sulphur).
 Leachable chlorides will not exceed the limits of ASTM C 795.
 Thermal conductivity = 0.061 W/m/K (0.42 BTU*in/ft2/hr/F) maximum @ 204C (400F).
 Insulation boards will not be more than 50mm (2”) thick.
 Insulation boards will be supplied in easy to handle sizes, either 600 x 1200mm (2 x 4 ft) or
600 x 2400mm (2 x 8 ft).
 Binder burn-out will not adversely affect the structural and insulating properties of the mineral
wool.
Molded or precision v-grooved mineral wool cylinders will be used on piping DN600 (24” NPS) and
smaller. Material will conform to ASTM C 547 Type II or III and the following additional requirements:
 Bulk density = 128 kg/m3 (8 lb/ft3) minimum.
 Service temperature rating = 650C (1200F) minimum.
 Shot content = 15% maximum (by weight).
 Sulphur compounds content = 1% maximum (in terms of sulphur).
 Leachable chlorides will not exceed the limits of ASTM C 795.
 Thermal conductivity = 0.065 W/m/K (0.45 BTU*in/ft2/hr/F) maximum @ 204C (400F).
 Insulation cylinders will not be more than 25mm (1”) thick.
 Binder burn-out will not adversely affect the structural and insulating properties of the mineral
wool.

© Copyright 2017, Chemetics Inc. All rights reserved. Page 6 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
7.3. Cladding

Cladding will be 304 stainless steel. All insulated surfaces will be clad with Standard Gage (USG)
No. 28 (0.40mm (0.016”)) thick sheet. Ducting, piping and equipment horizontal surfaces will be clad
with smooth sheet. Equipment vertical surfaces will be clad with 67mm (2 5/8”) wide x 16mm (5/8”
deep) corrugated sheet.
Cladding to be coated per subcontractor standard paint. Colour shall be Buff Brown RAL 1011
Ameron No. BR-3 or equivalent.

7.4. Fixing Materials

Expansion spacers will be fabricated from 50mm (2”) wide x 1.5mm (1/16”) thick 304 stainless steel
to the dimensions shown in Figure 8.
Cladding support rings (Figure 8) will be fabricated from 50mm (2”) wide x 3mm (1/8”) thick 304
stainless steel. Rings will be cut to lengths that can be conveniently shipped. Mating pieces will be
spliced together by welding.
Support rings (Figures 5 and 6) will be fabricated from 3mm (1/8”) thick 304 stainless steel. Ring
width will be insulation thickness less 25mm (1”).
Capacitor discharge weld pins will be 304 stainless steel. Pin diameter will be SWG (Standard Wire
Gage) No. 10 (3.2mm (0.125”)).
All banding and wire used to retain the insulation and cladding will be 304 stainless steel.
Tie wire diameter will be SWG No. 18 (1.2mm (0.048”)) minimum. Bands will be:
 13mm (1/2”) wide x USG No. 28 (0.40mm (0.016”)) thick for all piping and for ducts up to
900mm (36”) diameter.
 19mm (3/4”) wide x USG No. 25 (0.56mm (0.022”)) thick for all equipment and for ducts over
900mm (36”) diameter.
Z clips will be fabricated from 50mm (2”) wide x USG No. 18 (1.27mm (0.050”)) thick sheet.
S clips will be fabricated from 100mm (4”) wide x 150mm (6”) long x USG No. 18 sheet.
All other miscellaneous clips will be fabricated from USG No. 18 series 300 stainless steel sheet.

8. Insulation Thickness

Equipment insulation thickness is shown in 6-LST-0001: Equipment Insulation. Ducting and piping
insulation thickness is shown in 5-LST-0001: Line List.
The total insulation thickness will be achieved by layers of 50mm (2”) and/or 25mm (1”) thick mineral
wool mattresses, semi-rigid boards, or formed hollow cylinders as applicable.

9. Installation

9.1. General

The completed installation will be suitable to properly conserve heat, protect personnel, shed water,
resist the corrosive atmospheric conditions present, and accommodate thermal expansion of the
equipment without disrupting the insulation or cladding.
© Copyright 2017, Chemetics Inc. All rights reserved. Page 7 of 25
SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
The installation methods described herein are approved by Chemetics, but are by no means the only
acceptable methods. Any deviations from the requirements of this Specification must, however, be
noted in the Installer’s proposal and must be approved by Chemetics.
Materials will not be placed or stored directly on the ground.
All precautions recommended by the insulation manufacturers will be followed.
The Installer will ensure that all surfaces to be insulated are dry and clean prior to any welding or
installation of insulation.
The Installer will maintain working areas in a clean and orderly fashion, free of debris and refuse. All
loose, damaged or other unusable materials will be removed to a suitable refuse container on a daily
basis.
The Installer will not cause any equipment, structural steel or buildings to be soiled or damaged.

9.2. Cladding Supports

Large equipment (> 4m (13’) diameter) will have significant thermal growth. Consequently, the
cladding must be supported independently of the insulation by means of cladding support rings and
expansion spacers.
Cladding support rings will be attached to the shell by means of expansion spacers (see Figure 8).
The maximum circumferential distance between expansion spacers will be 600mm (24”). Expansion
spacers will be of sufficient length to allow for thermal expansion of the equipment per the following
table:
Table 1
Equipment Diameter Expansion Allowance
> 4m to 5m (13’ to 16’) 32mm (1 ¼”)
> 5m to 6m (16’ to 20’) 40mm (1 ½”)
> 6m to 7m (20’ to 23’) 45mm (1 ¾”)
> 7m to 8m (23’ to 26’) 50mm (2”)

Cladding support rings will be spaced at 900 to 1200mm (36 to 48”) intervals. The location of support
rings will be selected to minimize circumferential interruptions due to nozzles. When a support ring
intersects a nozzle, continuity of the ring (and hence its load carrying capacity) will be maintained by
installation of an additional ring around the nozzle circumference as shown in Figure 13.
Cladding support rings will be attached to the roof by means of expansion spacers (see Figure 10).
The maximum circumferential spacing between expansion spacers will be 900mm (36”). Radial
spacing between cladding support rings will be the cladding sheet width less 75mm (3”).
All welding will be in accordance with 4-SPC-0060: Equipment Welding Carbon Steel or 4-SPC-0061:
Equipment Welding Austenitic Stainless Steel as applicable.

9.3. Insulation Supports

Capacitor discharge weld pins will be attached to the vessel by capacitor discharge welding. Other
attachment methods require approval by Chemetics.
Pins will be installed on a square pitch. Maximum permissible spacing will be as follows:
© Copyright 2017, Chemetics Inc. All rights reserved. Page 8 of 25
SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
 Vertical surfaces 500mm (20”)
 Upward facing surfaces 600mm (24”)
 Downward facing surfaces 300mm (12”)
The Subcontractor will indicate the actual pin spacing on the installation drawings. Spacing will be
such that each individual insulation blanket or board is impaled by at least four pins. Pins will not be
used for insulation over duct expansion joints (see Figure 2).
When used with semi-rigid board, pins will be 13mm (1/2”) shorter than the insulation thickness and
no speed washers will be used. When used with mineral wool blankets, the pins will be longer than
the insulation thickness and the ends bent back to below the insulation surface after installation of
speed washers (Figure 4).

9.4. Insulation

Insulation will be installed in a staggered pattern. Minimum offset between seams will be 300mm
(12”). Outer layers will overlap seams in the underlying layers.
Mineral wool blankets will be installed with the wire mesh facing outwards. Adjacent edges of
blankets will be loosely wired together. Additionally, the outermost layers will have a minimum of two
bands in contact with each blanket. Each band will have four CHIL-SPRINGS®.
Semi-rigid mineral wool board will be cut to fit the vessel contour. Voids will be filled with loose
mineral wool insulation.

9.5. Cladding

Cladding sheets will be securely installed such that rain water, melting snow or other atmospheric
moisture cannot come in contact with the insulation.

9.5.1. Large Equipment (> 4m (13’) diameter)

Cladding will be installed in such a manner that the radial and vertical growth of the equipment is
accommodated. Cladding on vertical surfaces may be installed either in horizontal courses or
vertical panels.
Horizontal installation is detailed in Figure 9A. Details are as follows:
 Each horizontal (circumferential) cladding course will be attached to the uppermost support
ring only.
 Horizontal seams will overlap by 75mm (3”) and vertical seams will overlap by 100mm (4”)
minimum.
 Vertical seams in adjacent courses will be offset 300mm (12”) minimum.
 Each horizontal cladding course will be held with a minimum of two spring loaded bands.
Bands will be held in place with loops spaced at 1200mm (48”) intervals.
 Circumferential overlaps between courses will be maintained with “Z” clips on 600mm (24”)
centers.
Vertical installation is detailed in Figure 9B. Details are as follows:
 Each vertical panel will be attached to the uppermost support ring only.

© Copyright 2017, Chemetics Inc. All rights reserved. Page 9 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2
 Horizontal seams will overlap by 75mm (3”) and vertical seams will overlap by 100mm (4”)
minimum.
 Vertical seams in adjacent courses will be offset 300mm (12”) minimum.
 Spring loaded bands will be installed at each support ring. Bands will be held in place with
loops spaced at 1200mm (48”) intervals.
 Cladding sheets will be secured to the lowermost support ring by means of S clips.
Cladding on equipment roofs will be installed as shown in Figure 11.

9.5.2. Small Equipment (< 4m (13’) diameter) and Ducts

 Cladding will be held in place with spring loaded stainless steel bands spaced at 600mm (24”).
 Horizontal seams will overlap by 75mm (3”) and vertical seams will overlap by 100mm (4”)
minimum (see Figure 5).
 At least one longitudinal seam per cladding course must be designated for expansion (i.e. free
to move as the vessel or duct expands).
 Circumferential overlaps between courses will be maintained with “Z” clips on 600mm (24”)
centers.
 Vertical seams in adjacent courses will be offset 300mm (12”) minimum.
 Horizontal joints between roof and shell cladding will be secured by self-tapping screws as
shown in Figure 6.
 Radial seams on equipment roofs will be overlapped using a watertight slip joint as shown in
Figure 7.
 Cladding on equipment and vertical duct runs will be supported by angle cleats resting on
support rings (Figures 5 and 6).

9.5.3. Pipe

 Cladding will be held in place with spring loaded stainless steel bands spaced at 600mm (24”).
 Seams will overlap by 50mm (2”) minimum.

10. Details by Subcontractor

The following details are left to the discretion and experience of the Subcontractor:
 Removable insulation covers on manways
 Details at junctions between vessel and nozzle insulation
 Minor flashing and sealing details
All such details will be defined in the installation drawings and approved by Chemetics prior to
installation. In developing these details, the Subcontractor will ensure that the function and integrity
of the insulation system is not compromised.

© Copyright 2017, Chemetics Inc. All rights reserved. Page 10 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 1
END CAP AT INSULATION LIMIT ON DUCTS

© Copyright 2017, Chemetics Inc. All rights reserved. Page 11 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 2
INSULATION AND CLADDING AROUND DUCT EXPANSION JOINTS

© Copyright 2017, Chemetics Inc. All rights reserved. Page 12 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 3
INSULATION OVER ECONOMISER STIFFENERS

© Copyright 2017, Chemetics Inc. All rights reserved. Page 13 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 4
MINERAL WOOL BLANKETS

© Copyright 2017, Chemetics Inc. All rights reserved. Page 14 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 5
CLADDING ON DUCTS AND SMALL EQUIPMENT
(< 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 15 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 6
ROOF TO SHELL CLADDING JOINT ON SMALL EQUIPMENT
(< 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 16 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 7
SLIP JOINT IN ROOF CLADDING ON SMALL EQUIPMENT
(< 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 17 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 8
EXPANSION SPACERS AND CLADDING SUPPORT RINGS
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 18 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 9a
INSTALLATION OF CLADDING (HORIZONTAL COURSES)
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 19 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 9b
INSTALLATION OF CLADDING (VERTICAL PANELS)
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 20 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 10
EXPANSION SPACERS AND CLADDING SUPPORT RINGS FOR VESSEL ROOFS
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 21 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 11
INSTALLATION OF ROOF CLADDING ON LARGE EQUIPMENT
(> 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 22 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 12
ROOF TO SHELL CLADDING JOINT ON LARGE EQUIPMENT
(> 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 23 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 13
EXPANSION SPACERS AND CLADDING SUPPORT RINGS AT NOZZLE OPENINGS
ON LARGE EQUIPMENT (> 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 24 of 25


SPCC
AP1 DCDA Conversion Specification
Chemetics Inc.
Ilo Peru
Thermal Insulation for Acid Plant
Equipment, Ducting and Piping CN175700-6-SPC-0002-R2

FIGURE 14
REMOVABLE MANWAY COVER ON LARGE EQUIPMENT
(> 4m (13’) DIAMETER)

© Copyright 2017, Chemetics Inc. All rights reserved. Page 25 of 25

Das könnte Ihnen auch gefallen