Sie sind auf Seite 1von 6

GENERAL INTEREST TOPIC

The First United States Prestressed Masonry Structures


Richard M. Bennett1

Today, prestressed concrete construction is a very rods were passed through the holes and tightened to pro-
widely used method of both bridge and building con- vide the prestress. Special hollow clay tile units were also
struction. Prestressed construction is a little over fifty developed in which the rods passed through the cores. The
years old, with the first prestressed concrete structure rods had a yield strength of 690 MPa (100 ksi) and were
in the United States being the Walnut Lane Bridge in stressed to between 50 and 70% of the yield strength.
Philadelphia, which was completed in 1951 [Steinman
and Watson (1957)]. However, the Walnut Lane Bridge In the late 1940s and early 1950s, various masonry
was not the first prestressed bridge to be opened to traf- floor systems were being developed and used. At least one
fic. Almost a year earlier, a small three-span prestressed of these was called prestressed masonry, although the stress
bridge was opened to traffic in Madison County, Ten- levels in the reinforcing were probably not high enough
nessee [- 1951a; - 1951b]. This bridge was constructed to maintain a prestressed force after losses. This was the
of prestressed masonry, and was completed in October, Strestcrete system developed in California [Nordberg
1950, nearly a year before the Walnut Lane Bridge. The (1950)]. This system was displayed at the 1949 National
Madison County bridge is still in use today. Prior to the Concrete Masonry Association convention. It utilized spe-
bridge, prestressed masonry was used for the bleachers of cial concrete masonry units that were joined with external
the Fayetteville, TN high school football stadium, which reinforcing bars. The mating surfaces of the units were
could arguably be the first prestressed masonry structure ground to provide for bearing on one another. The rein-
in the United States. Shortly after the bridge was com- forcing bars were stressed to 117 MPa (17 ksi) through the
pleted, the Doric Building was built in Nashville, TN use of a calibrated torque wrench. The system was used in
with a combination of prestressed concrete and masonry many different applications, including roofs, floors, grain
beams. This structure is sometimes credited with being bins walls, and columns for a heavy traveling crane.
the first “truly prestressed” building in the United States
[- 1951c]. The building is still being used today. The first prestressed masonry structures to use high-
strength prestressing wire were the structures described
Despite the early beginnings of prestressed mason- in this paper. Special block units were used, and the pre-
ry, it has not been widely used in the United States. The stressing strands were 14 mm (0.6 in.) 7-wire strands
first US design code for prestressed masonry structures made by John A. Roebling’s Sons Co. The strands were
only appeared in 1999 [MSJC (1999)]. Although cur- tensioned to 116 kN (26 kips), resulting in an initial ten-
rently prestressed masonry is generally used for walls, sile stress of 862 MPa (125 ksi) in the strands.
these early structures were beams. This paper recounts
the history of the first prestressed masonry buildings and EARLY PRESTRESSED MASONRY
bridges in the United States through the examination of DESIGN
three structures, the Fayetteville high school bleachers,
the Madison County bridge, and the Doric Building.
The first prestressed masonry structures were de-
Construction techniques and the use of prestressed ma-
signed by the firm of Bryan and Dozier Consulting En-
sonry are described. A brief history of the designer of
gineers. The first partner, Mr. Ross Bryan, received a BS
these structures, Ross Bryan, is also given.
degree in civil engineering from the University of Kan-
sas in 1933. He was employed by the Kansas Highway
EARLY PRESTRESSED MASONRY Department, and then by the Panama Canal Department.
During World War II he served in the Civil Engineering
Anderegg and Dalzell (1935) describe some of the Corps of the U.S. Navy in the South Pacific. In 1949, he
first tests on prestressed masonry. Beams were construct- formed a partnership with Culver Dozier, a graduate of
ed of prestressed masonry and loaded to failure. Initially The University of Tennessee, and established the firm of
holes were drilled in solid clay bricks and high strength Bryan and Dozier Consulting Engineers. The firm initially
was composed of only the two engineers, and was started
1
TMS Member, Professor, Dept. of Civil and Envi- with $500 of capital. It was at this time that Mr. Bryan
ronmental Engineering, The University of Tennessee started designing prestressed masonry structures. Bryan
Knoxville, TN and Dozier Consulting Engineers was dissolved in 1952

TMS Journal November 2008 67


when each partner set up their own private practice. Mr. to fit in the cores. A mortar box was placed over the unit,
Bryan was president of Ross H. Bryan Inc., Consulting and it projected above the block by the thickness of the
Engineers, until his retirement in 1977. Mr. Bryan passed mortar joints. A high-strength mortar was placed over the
away in 2003 at the age of 92. unit and struck off to obtain the desired thickness. Spe-
cial end blocks were used to anchor the strands. To enable
Mr. Bryan became aware of prestressed concrete when the prestress strand to be draped, special depresser blocks
he returned from World War II. He had some knowledge were used, and placed at approximately the third points
of precasting, and had applied for a job with a leading pre- of the beam. All block units had a compressive strength
cast fabricator after the war. Although he did not get the of 25.9 MPa (3,750 psi), and the mortar had a compres-
job, he still had an interest in precasting. He read a book sive strength of 13.8 MPa (2,000 psi). Figure  1 shows
by Gustave Magnel on prestressing, and he began to think the blocks being laid for a beam, and Figure 2 shows the
of ways to apply the advantages of prestressing to precast beams being stressed.
systems. Mr. Bryan noted that in a 15 year period from
1936 to 1951, the cost of concrete being placed in bridge THE FIRST UNITED STATES PRESTRESSED
superstructures had increased by 230%, while the cost of MASONRY STRUCTURES
machine made concrete block had increased by only 10%
[Bryan and Dozier (1951)]. Bryan and Dozier thus felt that
there would be economic possibilities of using machine Fayetteville High School Stadium
made concrete units in prestressed construction. The blocks
are also lighter and more flexible than concrete. The first prestressed masonry structure in the United
States was constructed in the summer of 1950, this being
Mr. Bryan began experimenting with concrete blocks the 1,525 seat football stadium bleachers at Fayetteville
in the basement of the consulting engineer’s office build- high school (Figures 3 and 4). Bryan and Dozier obtained
ing. He worked with the Nashville Breeko Block Com- the job because of their bid of about half the price of com-
pany to develop a prestressed system, and test beams were parable reinforced concrete stands, and about the same as
made in the fall of 1949. The initial beams were made prefabricated steel bleachers with wood treads and seats.
with standard three-core concrete blocks. Existing mold The cost was $7.64 per seat, compared to an estimated $15
boxes were used for fabricating the units and changes to $17 for reinforced concrete. The structure was built on
were limited to those which could be made for a minimum site by nine workers in 32 days under the supervision of
of cost. The beams were made by threading the blocks Charles Lindsey, the high school coach (Bryan, 1979).
over the prestressing strands as construction proceeded.
The blocks were 197 mm (7  3/4 in.) long, with a 3.2 mm
(1/8 in.) mortar joint. To make the thin mortar joint, the
blocks were placed on a table which had projecting feet

Figure 2—Prestressing of Concrete Masonry Block


Beams

Figure 1—Blocks Being Mortared Together to Form


a Beam Figure 3—Fayetteville Football Stadium

68 TMS Journal November 2008


Figure 4—Lifting Beams into Place for Football
Stadium
The bleacher span was 9.1 m (30 ft). Beams were
formed with machine-made nominal 200 mm long by
400 mm wide by 300 mm deep (8 in. by 16 in. by 12 in.)
three-core concrete blocks. Two 14 mm (0.6 in.) 7-wire
prestressing strands were used for each beam, these being
in the outer cores. An initial tension of 44 kN (10 kips)
was applied to each strand, resulting in a tensile stress of Figure 6—Original Sketches of Madison County
330 MPa (48 ksi) in the strands, and an average compres- Bridge (1in. = 25.4 mm, 1 ft = 0.3048 m)
sive stress of 1.4 MPa (200 psi) in the concrete blocks. The
next day the strands were tensioned to 116 kN (26 kips), used, except the sides of the blocks were brought in about
resulting in a tensile stress of 862 MPa (125 ksi) in the 40  mm (1.5 in.) to form a keyway for the composite slab
strands. The designers assumed 16% loss, and designed (Figure  5). The bridge had three simple spans, the end
the beam based on a prestress of 724 MPa (105 ksi) in the spans being 6.1 m (20.1 ft), and the center span being 8.8
strands. At mid-span, the prestress after losses resulted in m (28.8 ft). The original design sketch of the prestressed
zero stress at the top fiber of the beams, and a compres- beams is shown in Figure 6. Forty-five prestressed beams
sive stress of 6.5 MPa (940 psi) in the bottom fibers of the were used, with fifteen in each span. The beams were
beams under their own weight. made by the Madison County maintenance crew, and all
forty-five beams were built and prestressed in a little less
The fate of this structure is unknown, but it is be- than three days. As the beams were placed, transverse
lieved that the stands were torn down when a new high prestressing strands were threaded through holes in the
school was opened in 1980. blocks. Figure 7 shows the beams for an end span being
placed by a crane on the center span. A top slab was cast
Madison County Bridge on the beams using 21 MPa (3,000 psi) concrete. After
the slab had sufficiently cured, the transverse strands were
About the time the bleachers were being completed,
the county engineer for Madison County, TN became
aware of the project. He was looking for an economi-
cal bridge construction technique, and approached Ross
Bryan about using similar prestressed beams. The same
concrete blocks as used for the football stadium were

Figure 5—Cross-Section of Madison County Bridge Figure 7—Placing Bridge Beams for Madison County
(1 m = 3.281 ft) Bridge

TMS Journal November 2008 69


tensioned. High-early strength concrete was used for the Lodge. The building has been renovated several times
slab, so the bridge was opened on October 28, 1950, seven since construction, and is still in use today.
days after casting the slab. The cost of the superstructure
was estimated to be about 20% less than for other types of The second floor was constructed of 200 mm (8 in.)
construction. Further details on this bridge and other similar prestressed masonry block beams with a span of 6.1 m (20
prestressed masonry bridges are in Bennett et al. (2002). ft) placed on cast-in-place post-tensioned concrete gird-
ers. The beams were similar to the Madison County bridge
There are eleven existing prestressed masonry bridg- beams, having an extended bottom flange. A 50  mm (2
es in Tennessee, including the original bridge in Madison in.) topping slab was added which was assumed to act
County. All of the bridges were constructed between 1950 compositely with the beams and the girders. The floor was
and 1956. One of the bridges, in Knox County, is adjacent designed for a 4,800 N/m2 (100 psf) live load. The roof
to an urban yard waste mulching facility and receives sig- was constructed of 300 mm (12 in.) deep prestressed ma-
nificant truck traffic. Based on state inspection records, sonry beams with a span 13.7 m (45 ft), or a noteworthy
the superstructures of all the bridges are in good condi- span to depth ratio of 45 [- 1951c].
tion. A common problem with the bridges has been leach-
ing. There has also been some slight spalling and breaking NEW CONCRETE BLOCK
out of the corners of a few blocks in some of the bridges.
Several of the bridges have longitudinal cracks running
Shortly after the construction of the first prestressed
through the bottom of the blocks.
structures, the design of the concrete blocks was changed
to a block with two horizontal cores as shown in Figure 8
Doric Building [- 1952b]. The prestressing strands were placed outside
the block cores to avoid having to thread the blocks over
The first prestressed building floor slab was the Doric the strand. A nominal 300 mm (12 in.) high block is shown
Building in Nashville, TN, which was completed in Janu- in Figure 8, but a nominal 400 mm (16 in.) high block was
ary, 1952. The first floor was used by Kroger, and the sec- also made for longer spans. The blocks were still 197 mm
ond floor was the meeting rooms of the Doric Masonic (7 3/4 in.) long, but a thicker 6 mm (1/4 in.) mortar joint was
used. These new masonry units were used for all bridges

Figure 8—New Masonry Blocks for Prestressed Masonry Beams (1 mm = 0.03937 in)

70 TMS Journal November 2008


sonry structures were found in these early structures, such as
the use of both bonded and unbonded strands.

The durability of prestressed masonry is shown by


the existing condition of the early prestressed bridges. The
superstructures of these bridges remain in good condition
after over fifty years of service, even the first bridges with
a bare cable in an inaccessible location. Prestressed ma-
sonry has withstood the test of time.

ACKNOWLEDGMENTS

Figure 9—Completed Prestressed Masonry Beam A portion of this work was sponsored by the Tennes-
see Department of Transportation. This support is grate-
constructed after the Madison County bridge. Figure  9 fully acknowledged. The author is grateful to Mr. Ed Mc-
shows a typical beam before being shipped to the proj- Dougle, Ross Bryan Engineers, for providing access to
ect. many of the early documents and pictures. The author also
appreciates the information provided by Mr. Ross Bryan
As with the vertical core blocks, special depresser in a telephone conversation shortly before his passing.
(now called positioning units), and end units were made
(Figure 8). Two types of end units were made. One was REFERENCES
for anchoring the strand. At the other end, a unit with a
semicircular groove was used as a dead end anchorage. - (1951a), “Bridge Built of Blocks Strung Like Beads,” En-
The cable terminals were quite expensive and eliminating gineering News Record, 146(3), pp. 39-42, January 18.
the use of terminals at one end provided cost savings. A
prestressing strand was anchored to one end, strung out- - (1951b), “Bridge of Distinction,” Engineering News Re-
side the blocks, around the end block, and then back to cord, 146(3), p. 21, January 18.
the original anchoring block. Thus, only a single strand
was used for each beam, but created the force equivalent - (1951c), “U. S. Progress in Prestressed Concrete,” Ar-
to two strands. Sheet lead strips were placed in the cable chitectural Record, 110(2), pp. 148-155.
slots in the end and spacer blocks to minimize friction.
- (1952a), “Prestressed Block Floors,” Architectural Fo-
The casting of the top slab encased the strands in rum, 97(4), p. 161.
these new block units. This resulted in several advantages.
• The ultimate strength of the beam was increased - (1952b), “Improved Block Beams Cut Erection Costs,”
by about 40%. Engineering News Record, 148, pp. 52-53, March 20.
• The bond on the cable provided better crack con-
trol for the beams. Anderegg, F. O., and Dalzell, C. L., “Pre-Stressed Ceram-
• The encasing of the strands provided better protec- ic Members,” Proceedings, American Society for Testing
tion against corrosion. Materials, 35(11), pp. 447-456, 1935.

Prestressed masonry beams were used in floor and Bennett, R. M., Hufstetler, M. L., and Carver, M., “50
roof construction until about 1958 when the block beams Year Old Prestressed Segmental Concrete Bridges,” Jour-
were replaced by precast pretensioned concrete members nal of Professional Issues in Engineering Education and
[Bryan (1979)]. Two notable structures built with pre- Practice, ASCE, 128(2), pp. 83-87, 2002.
stressed masonry block beams are the Crosley Corpora-
tion manufacturing plant, which had a design live load of Bryan, R.H., “New Designs Cut Prestressed Block-Beam
12,000 N/m2 (250 psf), and the Wilkins Air Force Depot, Cost,” Engineering News Record, 152(16), pp. 32-34,
which has a roof area of 74,000 m2 (800,000 ft2). April 22, 1954.

CONCLUSIONS Bryan, R. H., “Prestressed Concrete Innovations in Ten-


nessee.” PCI Journal, 24(1), pp. 14-31, 1979.
This paper describes the history of the first prestressed
masonry structures in the United States. The early use of pre- Bryan, R. H. and Dozier, C. B., “Prestressed Concrete
stressed masonry was for bridge and building beams, rather Block Bridges,” Proceedings of the First United States
than walls. Many of the features in modern prestressed ma- Conference on Prestressed Concrete, Massachusetts In-
stitute of Technology, pp. 57-60, 1951.

TMS Journal November 2008 71


Masonry Standards Joint Committee (MSJC), “Building Code Nordberg, B., “Prestressed Floor and Roof Slabs of Con-
Requirements for Masonry Structures”, (ACI 530-99/ASCE crete Masonry Units,” Rock Products, Chicago, IL, 53,
5-99/TMS 402-99), American Concrete Institute; Structural pp. 197-201, 1950.
Engineering Institute of the American Society of Civil Engi-
neers; The Masonry Society, Boulder, CO, 1999. Steinman, D. B. and Watson, S. R., “Bridges and Their
Builders,” Dover Publications, New York, New York, 1957.

72 TMS Journal November 2008

Das könnte Ihnen auch gefallen