Beruflich Dokumente
Kultur Dokumente
Today, prestressed concrete construction is a very rods were passed through the holes and tightened to pro-
widely used method of both bridge and building con- vide the prestress. Special hollow clay tile units were also
struction. Prestressed construction is a little over fifty developed in which the rods passed through the cores. The
years old, with the first prestressed concrete structure rods had a yield strength of 690 MPa (100 ksi) and were
in the United States being the Walnut Lane Bridge in stressed to between 50 and 70% of the yield strength.
Philadelphia, which was completed in 1951 [Steinman
and Watson (1957)]. However, the Walnut Lane Bridge In the late 1940s and early 1950s, various masonry
was not the first prestressed bridge to be opened to traf- floor systems were being developed and used. At least one
fic. Almost a year earlier, a small three-span prestressed of these was called prestressed masonry, although the stress
bridge was opened to traffic in Madison County, Ten- levels in the reinforcing were probably not high enough
nessee [- 1951a; - 1951b]. This bridge was constructed to maintain a prestressed force after losses. This was the
of prestressed masonry, and was completed in October, Strestcrete system developed in California [Nordberg
1950, nearly a year before the Walnut Lane Bridge. The (1950)]. This system was displayed at the 1949 National
Madison County bridge is still in use today. Prior to the Concrete Masonry Association convention. It utilized spe-
bridge, prestressed masonry was used for the bleachers of cial concrete masonry units that were joined with external
the Fayetteville, TN high school football stadium, which reinforcing bars. The mating surfaces of the units were
could arguably be the first prestressed masonry structure ground to provide for bearing on one another. The rein-
in the United States. Shortly after the bridge was com- forcing bars were stressed to 117 MPa (17 ksi) through the
pleted, the Doric Building was built in Nashville, TN use of a calibrated torque wrench. The system was used in
with a combination of prestressed concrete and masonry many different applications, including roofs, floors, grain
beams. This structure is sometimes credited with being bins walls, and columns for a heavy traveling crane.
the first “truly prestressed” building in the United States
[- 1951c]. The building is still being used today. The first prestressed masonry structures to use high-
strength prestressing wire were the structures described
Despite the early beginnings of prestressed mason- in this paper. Special block units were used, and the pre-
ry, it has not been widely used in the United States. The stressing strands were 14 mm (0.6 in.) 7-wire strands
first US design code for prestressed masonry structures made by John A. Roebling’s Sons Co. The strands were
only appeared in 1999 [MSJC (1999)]. Although cur- tensioned to 116 kN (26 kips), resulting in an initial ten-
rently prestressed masonry is generally used for walls, sile stress of 862 MPa (125 ksi) in the strands.
these early structures were beams. This paper recounts
the history of the first prestressed masonry buildings and EARLY PRESTRESSED MASONRY
bridges in the United States through the examination of DESIGN
three structures, the Fayetteville high school bleachers,
the Madison County bridge, and the Doric Building.
The first prestressed masonry structures were de-
Construction techniques and the use of prestressed ma-
signed by the firm of Bryan and Dozier Consulting En-
sonry are described. A brief history of the designer of
gineers. The first partner, Mr. Ross Bryan, received a BS
these structures, Ross Bryan, is also given.
degree in civil engineering from the University of Kan-
sas in 1933. He was employed by the Kansas Highway
EARLY PRESTRESSED MASONRY Department, and then by the Panama Canal Department.
During World War II he served in the Civil Engineering
Anderegg and Dalzell (1935) describe some of the Corps of the U.S. Navy in the South Pacific. In 1949, he
first tests on prestressed masonry. Beams were construct- formed a partnership with Culver Dozier, a graduate of
ed of prestressed masonry and loaded to failure. Initially The University of Tennessee, and established the firm of
holes were drilled in solid clay bricks and high strength Bryan and Dozier Consulting Engineers. The firm initially
was composed of only the two engineers, and was started
1
TMS Member, Professor, Dept. of Civil and Envi- with $500 of capital. It was at this time that Mr. Bryan
ronmental Engineering, The University of Tennessee started designing prestressed masonry structures. Bryan
Knoxville, TN and Dozier Consulting Engineers was dissolved in 1952
Figure 5—Cross-Section of Madison County Bridge Figure 7—Placing Bridge Beams for Madison County
(1 m = 3.281 ft) Bridge
Figure 8—New Masonry Blocks for Prestressed Masonry Beams (1 mm = 0.03937 in)
ACKNOWLEDGMENTS
Figure 9—Completed Prestressed Masonry Beam A portion of this work was sponsored by the Tennes-
see Department of Transportation. This support is grate-
constructed after the Madison County bridge. Figure 9 fully acknowledged. The author is grateful to Mr. Ed Mc-
shows a typical beam before being shipped to the proj- Dougle, Ross Bryan Engineers, for providing access to
ect. many of the early documents and pictures. The author also
appreciates the information provided by Mr. Ross Bryan
As with the vertical core blocks, special depresser in a telephone conversation shortly before his passing.
(now called positioning units), and end units were made
(Figure 8). Two types of end units were made. One was REFERENCES
for anchoring the strand. At the other end, a unit with a
semicircular groove was used as a dead end anchorage. - (1951a), “Bridge Built of Blocks Strung Like Beads,” En-
The cable terminals were quite expensive and eliminating gineering News Record, 146(3), pp. 39-42, January 18.
the use of terminals at one end provided cost savings. A
prestressing strand was anchored to one end, strung out- - (1951b), “Bridge of Distinction,” Engineering News Re-
side the blocks, around the end block, and then back to cord, 146(3), p. 21, January 18.
the original anchoring block. Thus, only a single strand
was used for each beam, but created the force equivalent - (1951c), “U. S. Progress in Prestressed Concrete,” Ar-
to two strands. Sheet lead strips were placed in the cable chitectural Record, 110(2), pp. 148-155.
slots in the end and spacer blocks to minimize friction.
- (1952a), “Prestressed Block Floors,” Architectural Fo-
The casting of the top slab encased the strands in rum, 97(4), p. 161.
these new block units. This resulted in several advantages.
• The ultimate strength of the beam was increased - (1952b), “Improved Block Beams Cut Erection Costs,”
by about 40%. Engineering News Record, 148, pp. 52-53, March 20.
• The bond on the cable provided better crack con-
trol for the beams. Anderegg, F. O., and Dalzell, C. L., “Pre-Stressed Ceram-
• The encasing of the strands provided better protec- ic Members,” Proceedings, American Society for Testing
tion against corrosion. Materials, 35(11), pp. 447-456, 1935.
Prestressed masonry beams were used in floor and Bennett, R. M., Hufstetler, M. L., and Carver, M., “50
roof construction until about 1958 when the block beams Year Old Prestressed Segmental Concrete Bridges,” Jour-
were replaced by precast pretensioned concrete members nal of Professional Issues in Engineering Education and
[Bryan (1979)]. Two notable structures built with pre- Practice, ASCE, 128(2), pp. 83-87, 2002.
stressed masonry block beams are the Crosley Corpora-
tion manufacturing plant, which had a design live load of Bryan, R.H., “New Designs Cut Prestressed Block-Beam
12,000 N/m2 (250 psf), and the Wilkins Air Force Depot, Cost,” Engineering News Record, 152(16), pp. 32-34,
which has a roof area of 74,000 m2 (800,000 ft2). April 22, 1954.