Beruflich Dokumente
Kultur Dokumente
This paper was prepared for presentation at the SPE Annual Technical Conference and Exhibition held in Amsterdam, The Netherlands, 27–29 October 2014.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents
of the paper have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written
consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may
not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
Abstract
The operator’s drilling efficiency program has been expanded to a Limiter Redesign Process that seeks to
optimize all rig time, including flat time. As drilling efficiency gains have been achieved, flat time now
accounts for roughly 80% of the total rig time and approximately 70% of the total cost of drilling and
completions operations; leaving 20% of rig time for drilling. This fact led to the generation of a
comprehensive Flat Time Reduction (FTR) program.
The Fast Drill Process has become a well-known workflow to identify hole-making limiters and
mitigate them through “relentless redesign to the economic limit of performance”. Efforts to increase
drilling efficiency continue, and this process has yielded a continuous increase in the overall footage per
day and a reduction in flat time within individual hole sections.
To address operations that do not include drilling of rock, the operator has launched a similar effort and
workflow process which focuses on “flat time” portions of the well construction process. This has become
a key focal point in the organizations approach to maximize capital efficiency. The Flat Time Reduction
process provides an environment in which operations are optimized while further enhancing a workplace
where “Nobody Gets Hurt.”
This process is yielding significant savings globally and has been accomplished through planning,
“real-time” recognition and response, collaboration with service providers, and a focus on Non-Productive
Time (NPT) reduction while continuously improving safety performance. Field applications of limiter
redesign are discussed in this paper. The purpose of this paper is to present the current status and specific
approaches being used to reduce flat time and share the workflow process.
dramatically and typically becomes very erratic. The results of the pilot program confirmed that
significant ROP performance gains could be obtained simply by monitoring MSE trends and adjusting the
drilling parameters (WOB & RPM) at the rig site to minimize MSE. This process was deployed by the
operator in 2005 and is known in the industry as the Fast Drill Process (FDP)4.
The operator implemented and refined this workflow to improve drill rate performance throughout the
operator’s worldwide drilling operations5, 6. This workflow follows a plan-do-analyze-improve cycle to
identify and overcome limiters in the drilling operation as outlined in Fig. 1. The Key elements of the
Limiter Redesign Process™ are:
● Identify the current limiter
● Plan to extend the limiter
● Identify risks with change
● Plan to mitigate risks
● Run trial and take data
● Adjust trial based on real time events
● Capture learnings
● Repeat the cycle to the economic limit
MSE surveillance plays an important role in the process as it helps identify drilling dysfunctions. Most
of the early limiters were related to bit design and drilling mechanics issues such as: vibrations,
bottom-hole balling, and bit balling. Worldwide drilling performance increased by approximately 43% in
footage per day in the first two years. However, by 2007 performance gains had started to plateau, as
shown in Fig. 2. Maximum downhole motor differential rating, improving hole quality, and maximum
available bit weight became limiters.
Continued performance improvement needed to address limiters that were not just a function of
adjusting WOB and RPM. An internal study revealed that major non-productive time (NPT) events were
usually preceded by near misses such as pack-offs, tight hole, and/or cavings. In addition, this study
showed that the flattening trend was associated with non-bit limiters, primarily borehole quality and
self-induced hole cleaning ROP limits in high angle soft rock formations7-11. Identification of these
non-bit limiters, near misses, and their root causes lead to the expansion of the Fast Drill Process to
include Borehole Management limiters. Internally the Limiter Redesign Process was renamed Fast Drill
SPE-170751-MS 3
Borehole Management (FDBM). The new expanded objective was to improve borehole quality and
address near misses in both the upfront drilling design process and in real time drilling operations.
The FDBM initiative was the continued evolution of the Fast Drill Process. Research and field trials
confirmed that poor borehole quality12-18 (enlargement, borehole patterns, hole out of round, ledges, etc.)
contributed significantly to drilling dysfunction and inadequate hole cleaning. A major factor was
wellbore instability induced hole enlargement19. To mitigate this required adopting a “maximum mud
weight philosophy” with a focus on finding and fixing the limiters/risks that come with the new mud
weight approach20.
The FDBM initiative also required a “rethinking” of operational procedures related to connection
practices and the definition of effective hole cleaning while drilling. Changing the connection practices
occurred fairly quickly. Many of these changes (reducing rotary speed prior to coming off-bottom,
minimal-to-no backreaming, minimal circulation, reduced Torque & Drag data gathering frequency, etc.)
were initiated by drill teams in field trials that challenged the normal accepted practice.
Changing the hole cleaning philosophy from: “a clean hole is the #1 priority” to, “drill at ROPs that
create a maximum sustainable cuttings bed height”, was more of an organizational challenge. The
philosophy behind “maximum sustainable ROP” is to drill at the fastest ROP that still provides for a stable
cuttings bed height (i.e. no pack-offs) and where the drilling ECD does not exceed the fracture gradient.
To achieve the maximum sustainable ROP requires a quality borehole with minimal oversize. This was
especially important in high angle soft rock formations where wellbore instability routinely limits the
drilling performance.
Adoption of the new connection practices, new hole cleaning philosophy, maximum mud weight and
mitigating vibrations broke the flattening footage per day trend. Over the next four years footage per day
increased another 40⫹%.
By 2011, seven years since the initial FDP trial process, the footage per day performance had improved
90% worldwide, Fig. 2. By this time “drilling” typically accounted for approximately 20% of the total rig
time. The remaining ~80% was used for performing “flat time operations” (i.e. testing BOPs, logging,
running casing, running riser, completing, etc.). Rethinking of all the tasks that are required of a drill rig
led the operator to focus on Flat Time.
To address this, a “Flat Time Reduction” initiative was rolled out in 2011 to focus on non-drilling
events. The Limiter Redesign Process was well established in the organization, contractors and service
personnel, and its success made it a prime methodology to help reduce flat time operations. The original
4 SPE-170751-MS
Fast Drill Process continues to expand and evolve, and now Flat Time Reduction and Fast Drill Borehole
Management share the same “relentless redesign” workflow and reside together under the Limiter
Redesign Process umbrella, Fig. 3.
When focusing on Fast Drill, the question asked is “What limits us from increasing footage per day?”
When focusing on Flat Time the question is “What limits decreasing the overall days per well?” Within
Flat Time Reduction, focus areas include but are not limited to: critical analysis of current procedures,
examining critical path operations, rig capability analysis, performing field trials of new technologies,
performance stewardship, and recognition and rewards programs.
Since flat time operations do not produce footage drilled, the global metric for measuring the effect of
the process needed to change. The common metric for all rig operations is reduction in drilling cost. The
cost savings trends which have been realized since the start of the Fast Drill Process is shown in Fig. 4.
The next section of this paper will discuss the organization that achieved these results.
Limiter Redesign Process Network
In 2005, a network of “Champions” from the global drill teams was established to promote sharing of Fast
Drill initiatives across the organization. Since the focus has expanded to include all rig operations, the
Champions now focus on all limiters (Fast Drill, Borehole Management and Flat Time) and are supported
by senior technical professionals and subject matter experts. Each Champion is responsible for staying
abreast of global initiatives, driving change within the teams, mentor on the workflow and share initiatives
with the other Champions. They are a conduit of knowledge relaying information from the network to
SPE-170751-MS 5
their drill team and from their drill team to the network. While there are designated individuals assigned
to the Limiter Redesign Process Network, everyone on a drill team is encouraged to share their ideas and
question the base assumption of the drill well design. Proactively, the senior technical professionals and
subject matter experts are involved in the network to facilitate cross collaboration, provide training, and
promote the Limiter Redesign workflow.
The strength of the network is built on the participation of individuals on drill teams and the
information shared. There are several tools/avenues used to promote a culture of open knowledge sharing,
to transfer knowledge across the organization and to serve as a platform to spread knowledge more
efficiently. Some of the tools include a central database of Flat Time Reduction initiatives, a quarterly
Drilling Limiter Redesign Process Newsletter, monthly global teleconferences and an annual Limiter
Redesign Conference. The Limiter Redesign Process is engrained in the organization and has become the
way work is performed, both while drilling and in flat time operations. The Limiter Redesign Process
Network is supported by all levels of management through the proven ability to help 1) maximize the
value of every dollar spent, 2) to assist in identifying the value of the risk versus the benefit and 3) to
promote safety and efficiency. This is done by promoting new technology and eliminating risk exposure
to rig personnel by “Engineering out the Hurt.”
Definition of Flat Time Reduction
To fully appreciate the opportunity for improvement in flat time operations, it is important to understand
the operator’s definition of Flat Time. Flat time can best be described on a Days vs. Depth curve as all
Drilling stewarded time outside the Fast Drill Metric. In Fig. 5, the Flat Time is represented by the red
lines where there is a plateau in progress (depth). The Fast Drill Metric starts after a successful integrity
test and ends upon reaching section TD as depicted by the blue lines in Fig. 5. Although there may be
plateau times or periods where no progress (depth) was made within the Fast Drill time, these are not
considered part of the Flat Time metric. Any plateau time which occurs between an integrity test and
section TD is considered part of the Fast Drill metric. The operator has chosen to define the metrics as
described above because the plateau times within the Fast Drill Metric are directly related to drilling
performance and doing so simplifies the data extraction from the daily drilling reports, reducing the
chance for error.
When analyzing the data, the objective is to reduce the overall days per well. Categorization of Fast
Drill vs. Flat Time is a convenient way to help sort out priorities, but the objective is not to reach a
specified flat time percentage; reduce rig time and let the percentages fall where they may. It is important
to note that Flat Time should not be confused with NPT; there are essential flat time operations which
6 SPE-170751-MS
must be performed in the well construction process. The goal of Flat Time Reduction is to minimize the
time spent during flat time portions of the well construction process.
The Flat Time Reduction motto is to “Plan Smart, Work Safely”. The objective is to plan and engineer
work smarter, allowing work to be conducted in a safe and more efficient manner. With a focus on
“Engineering out the Hurt”, Drill Teams are empowered to simplify rig operations and implement new
tools or processes which will remove or reduce human intervention. History has shown that safer
operations are often faster. A thoroughly planned operation can eliminate risk, simplify the design and will
not only result in efficiency gains but will likely improve safety. For example, eliminating a casing string
will simplify the well design, require less time to run the string of casing and eliminate all human
intervention required to run that string of casing. Working at a quick pace is not the objective of Flat Time
Reduction; core safety values will not be compromised for speed. Simply performing a single operation
(i.e. making a connection) as quickly as possible will yield small incremental savings and may negatively
impact safety. Instead, the operator has looked for ways to work smarter and more efficiently. A positive
by-product of this initiative has been improved safety awareness as well as performance.
Opportunities for Improvement
Time based data obtained from daily drilling reports are used to identify the greatest opportunities for
improvement and to benchmark against similar operations. Fig. 6 shows a global break down of several
of the major phases required in the well construction process. Note that in 2013 only 23% of the total time
is spent within the Fast Drill Metric. The other 77% of the rig time is spent in flat time. Of the 77% flat
time, 6% is spent performing BOP/Riser and Wellhead operations, 6% is spent on abandonments and slot
reclamation, 11% is spent on mobilizing and demobilizing the rig, 15% of the total time is spent on
completions operations and an additional 17% of the total time is spent running casing and cementing. By
analyzing operations at various levels of granularity, teams are able to identify the areas for improvement.
The objective is to minimize the overall days per well regardless if that time is associated with Fast Drill
or Flat Time. Both reside under the Limiter Redesign Process and contribute to the time reduction of the
overall days per well. Four methods have been developed to date to work on these issues; see Fig. 7.
Four Methods to Maximize Capital Efficiency
The Limiter Redesign Process has produced significant savings globally through four basic methods:
planning, “real-time” recognition and response, collaboration with service providers, and a focus on NPT
reduction, all while continuously improving safety performance and reducing the environmental footprint.
SPE-170751-MS 7
frac-pack as shown in Fig. 10. The evaluation of the open hole log yielded relatively poorer reservoir
quality in one of the two zones for two of the development wells which did not support the additional
completion costs of a stacked frac-pack. Furthermore, pressure surveys from an offset development well
indicated the potential for balanced depletion of both zones through other offset wells in the development.
By recognizing these facts, the team was able to respond to and simplify the completion design. The
elimination of the second zone allowed for a reduction in manual intervention required to run the
additional completion equipment which improved the safety of the execution and reduced the possibility
for non-productive time by simplifying the completion design. The completion optimization based on
actual results provided capital efficiency savings, maintained initial well deliverability targets and reduced
the development schedule with no impact on reserves capture,. Had the stacked frac pack been installed
as originally planned on the two wells, the flow from the lower zone would have been limited by the
completion system. The key highlight of this optimization was the recognition of the improvement
opportunity and the joint effort between the different functions that enabled the capital savings.
Abandonment of Long Intervals in a Deepwater Well with a Sacrificial Tubing String (Planning)
A deepwater Gulf of Mexico (GOM) well was drilled in 2012 with a planned original hole for appraisal
and then a sidetrack updip for future production. The original hole was drilled with a build and hold
directional profile to a maximum inclination of 52 degrees. Intermediate casing was set at approximately
14, 550 ft. measured depth (MD) and an open hole section of 7, 000 ft. was drilled to a total depth of 21,
550 ft. MD as shown in Fig. 11. The original hole penetrated six hydrocarbon intervals that were not in
pressure communication. The objectives of the original hole abandonment were to safely isolate all
hydrocarbon zones and enable an open hole sidetrack to an updip location.
There are numerous regulations that address abandonment guidelines to ensure proper isolation of
hydrocarbon zones, protection of fresh water areas, and pressure isolation of the wellbore21. Common
practice to install an open hole barrier is to pump a cement plug of sufficient volume to provide isolation
above and below any zones of interest. The plug is balanced by pumping appropriate volumes of spacer
ahead and behind to achieve the equivalent hydrostatic pressure inside and outside of the pipe. Cement
SPE-170751-MS 11
Figure 12—The sacrificial tubing string is run in hole on drill pipe and cemented in place. The tubing is released by pressuring up against the wiper
dart (Rogers 2006).
detail in SPE papers 139426(25) and 163503(26). Fig. 14 illustrates the BHA configurations used in each
of these wells. Note that the stabilization contact points are different in these designs, and the results of
the modeling program are provided on the right hand side. The BHA Strain Energy is a vibration index
that characterizes the amount of bending energy in the BHA resulting from a certain amount of lateral
excitation that is common to all of the designs.
SPE-170751-MS 13
The vibrations model helped explain the severe component wear seen in Well-1, and Well-2 achieved
the objective of a significant reduction in lateral vibrations. BHA-2 was confirmed to have lower
vibrations at about 90 and 140 RPM than at 120 RPM, but in the hard formation there was significant
stick-slip at the lower speed and there was too much torque at the higher speed. Reducing bit aggres-
siveness and BHA mass were identified upgrades for subsequent runs.
Wells 3 and 4 were drilled at about the same time and both had improved but slightly different results.
Both were shorter BHA designs with lower vibration indices in the 100-140 RPM range than the BHA for
Well-2. BHA-3 had logging while drilling (LWD) tool constraints that generated higher index values at
120 RPM and was therefore run at lower RPM and WOB. BHA-4 included a torsional shock sub that
required higher rotary speeds to be effective. Both of these runs completed the interval in a single trip. The
run in Well-3 actually reached section TD, which included drilling more than 1500 ft. of salt below the
hard interval, with a resulting bit dull grade of 4-4. The run in Well-4 required a bit change after drilling
the hard interval.
The performance of BHA-3 was considered to be better than BHA-4, so it was used as the starting point
for Well-5. A change in the LWD tool suite enabled the contacts to be repositioned to facilitate tuning
BHA-5 for the lowest possible indices at 120 RPM. Fig. 15 illustrates the change in the sweet spot rotary
speed for this BHA design. The BHA Strain Energy vibration index value of less than 0.3 at the sweet spot
rotary speed is considered to be exceptional. A value of 10 is considered to be good, and many prior art
BHA designs exceed 100.
To combat stick slip, Well-5 was the first well to use a full string of 6-5/8-inch drill pipe in this interval.
Well-1 used 5-1/2-inch pipe, Wells 2 and 4 both used a tapered string of 6-5/8 and 5-7/8-inch pipe, and
Well-3 used a full string of 5-7/8-inch pipe. The larger pipe provided up to twice the torsional stiffness
to resist stick-slip torsional vibrations and is credited with a substantial reduction in stick-slip.
14 SPE-170751-MS
Field Trials of a Drilling Advisory System (Real Time Recognition and Response)
The Drilling Advisory System (DAS) comprises a computer that reads standard Wellsite Information
Transfer Standard (WITS) data at the rig and calculates MSE and other diagnostics to provide a better
understanding of the MSE values corresponding to different drilling parameter values, in real-time. It also
estimates stick-slip at the bit using a method described in SPE 163420(34). Despite what was in hindsight
a primitive optimization algorithm, this DAS trial provided benefit in Wells 3 and 4 to help guide the use
of better drilling parameters and increase bit life.
The DAS system was significantly upgraded for Well-5, with a second-generation algorithm that
included WITS output of recommended WOB and RPM on the mudlogger display in front of the driller.
The upgraded system was used in the first portion of the interval in Well-5 (“DAS On” in Fig. 16). In the
second interval, a conscious decision was made to not actively use the recommendations (“DAS Off” in
Fig. 16). There was a step-change reduction of 27% in the ROP in the second interval that began at the
time of the parameter change.
In the second interval, the WOB was increased, and the RPM was also increased to reduce the
occurrence of stall events. MSE and the lateral vibrations increased in Interval #2 as seen in Fig. 17. This
case study is considered in more detail in IPTC 17216(35).
SPE-170751-MS 15
Figure 17—MSE increased at the higher WOB levels seen in Interval #2.
Conclusions
This paper has described how a Limiter Redesign workflow has expanded from a purely bit-on-bottom
drilling improvement process to now include all phases of rig operations. In review, specific limiters to
improved performance are identified and the physics of the systems impacting the limiter are probed until
fully understood. Solutions to remove or extend the limiter are then developed, risk identified and
mitigated, then implemented. The process then repeats itself with the identification and elimination of
subsequent performance limiters.
Conclusions that can be drawn from this ongoing workflow process are summarized below:
● The safety, health and environmental aspects of the drilling operations are improved as critical-
path operations are simplified, made more efficient or removed altogether. The emphasis is on
working smarter, not faster.
● Significant efficiency gains have been realized across all phases of drilling operations from the
application of the Limiter Redesign Process. This is truly an extension of the Fast Drill Process as
those initiatives continue to be progressed within the drill teams.
● To be effectively utilized, the process must have the support of drilling management, operations,
engineering and service providers.
● This effort requires an organizational structure that fosters open communication, the global sharing
of learnings and empowers individuals to relentlessly seek to improve the performance of their
operations.
● It is an ongoing and evergreen workflow process. As limiters are eliminated, subsequent limiters
are identified and the process continues until further improvement is not economically justified
(reached the economic limit).
● The Limiter Redesign Process has been firmly engrained in the operator’s culture for a decade and
has readily expanded to include all aspects of rig operations as well as to other parts of the
operator’s upstream organization.
Now that ~80% of rig time is Flat Time due to the success of Fast Drill, significant efficiency
opportunities still remain to be captured. Within Flat Time, there is a great diversity of tasks with
corresponding limits and potential solutions. This diversity will require a multi-year effort to realize many
of the potential opportunities in Flat Time operations.
Acknowledgements
The authors would like to thank ExxonMobil Development Company management for their support of the
Limiter Redesign Process and permission to publish this work, the drill teams who do this work every day,
16 SPE-170751-MS
and the participants of the Limiter Redesign Network for sharing their learning and allowing the authors
to present this paper.
References
1. Dupriest, Fred E. and Keoderitz, William L., “Maximizing Drill Rates with Real-Time Surveil-
lance of Mechanical Specific Energy”, SPE/IADC paper no. 92194 presented at annual Drilling
Conference, Amsterdam, The Netherlands, 23 – 25 February 2005.
2. Pessier, R.C., Hughes Tool Co.,; Fear, M.J., BP Exploration, “Quantifying Common Drilling
Problems With Mechanical Specific Energy and a Bit-Specific Coefficient of Sliding Friction”,
SPE 24584-MS 1992
3. Teale, R., “The Concept of Specific Energy in Rock Drilling, ” Intl. J. Rock Mech. Mining Sci.
1965
4. Dupriest, F. E., “Comprehensive Drill-Rate Management Process to Maximize Rate of Penetra-
tion”, SPE paper no. 102210 presented at annual Technical Conference, San Antonio, Texas, 24
– 27 September 2006.
5. Dupriest, F.E., Witt, J.W., and Remmert, S.M., “Maximizing ROP with Real Time Analysis of
Digital Data and MSE, ” Paper IPTC 10706 presented at the International Petroleum Technology
Conference, Doha, Qatar, 21-23 November, 2005
6. Remmert, S.M., Witt, J.W., and Dupriest F.E., “Implementation of ROP Management Process in
Qatar North Field, ” Paper SPE 105521 presented at SPE/IADC Drilling Conference, Amsterdam,
The Netherlands, 20-22 February 2007
7. Richard W. James, SPE, Paul Pastusek, SPE, Gary R. Kuhn, Anton Andreev, Jeffrey R. Bailey,
SPE, Lei Wang, SPE, “Successful Optimization Strategies Combine to Deliver Significant
Performance Boost at the Edge of the ERD Envelope, Sakhalin Island, Russia”, IADC/SPE
150959 presented at the 2012 IADC/SPE Drilling Conference, San Diego, California, USA, 6 – 8
March 2012.
8. Michael W. Walker, SPE, “Pushing the Extended Reach Envelope at Sakhalin: An Operator’s
Experience Drilling a Record Reach Well”, SPE151046, SPE / IADC Conference, San Diego,
2012
9. Gregory F. Smyth, SPE, Andrew M. Evans, Jonathan Babb, Neil Bolivar, “Extension of Gauge
Length to Reduce Vibrations and Improve Drilling Performance”, SPE 140317 presented at the
SPE/IADC Drilling Conference, Amsterdam, The Netherlands, 1-3 March 2011
10. Michael W. Walker, Andrew J. Veselka, Shane A Harris, SPE, “Increasing Sakhalin Extended
Reach Drilling and Completion Capability”, SPE 119373, SPE / IADC Conference, Amsterdam,
2009
11. Michael W Walker, SPE, “Extended-Reach Drilling Offshore California: An Operator’s Experi-
ence with Drilling a Record Extended Reach Well”, SPE 112536, SPE / IADC Conference,
Orlando, 2008
12. Dupriest F.E., Elks, Jr W.C., Ottesen S., Pastusek P.E., Zook J.R., ExxonMobil, Aphale C.R.,
ExxonMobil Upstream Research Company, “Borehole Quality Design and Practices to Maximize
Drill Rate Performance”, SPE 134580 presented at the SPE Annual Technical Conference and
Exhibition, Florence, Italy, 19 –22 September 2010
13. Gaynor, T., Chen, D.C-K., Stewart, D., and Comeaux, B., “Tortuosity versus Micro-Tortuosity —
Why Little Things Mean a Lot”, SPE 67818 presented at the SPE/IADC Drilling Conference,
Amsterdam, The Netherlands, 27 February - 1 March, 2001
14. Pastusek, P., Bracken V., “A Model for Borehole Oscillations, ” Paper SPE 84448 presented at
the SPE Annual Technical Conference and Exhibition, Denver, Colorado, 5-8 October 2003
SPE-170751-MS 17
15. Bouallug, R., Sellami, H., Menand, S., and Simon, C., “Effects of Formations Anisotropy on
Directional Tendencies of Drilling Systems, ” Paper SPE 98865 presented at SPE/IADC Drilling
Conference, Miami, Florida, USA, 21-23 February 2006
16. Dupriest, F.E. and Sowers, S.F., “Maintaining Steerability While Extending Gauge Length to
Manage Whirl, ” Paper SPE 119625 presented at the SPE/IADC Drilling Conference, Amsterdam,
The Netherlands, 17-19 March 2009
17. P. Pastusek, V. Brackin, and P. Lutes, “A Fundamental Model for Prediction of Hole Curvature
and Build Rates With Steerable Bottomhole Assemblies”, SPE 95546 presented at SPE Annual
Technical Conference and Exhibition, Dallas, Texas, 9-12 October 2005
18. S. Menand, H. Sellami, C. Simon, A. Besson, N. Da Silva, “How Bit Profile and Gauges Affect
Well Trajectory”, SPE 82412 Presented at the SPE/IADC Drilling Conference 2003
19. Ottesen S., ExxonMobil, “Wellbore Stability in Fractured Rock”, SPE 128728 presented at the
SPE/IADC Drilling Conference, New Orleans, Louisiana, USA 2-4 February 2010
20. Dupriest F.E., Elks, Jr. W.C., Ottesen S., ExxonMobil, “Design Methodology and Operational
Practices Eliminate Differential Sticking”, SPE 128129 presented at SPE/IADC Drilling Confer-
ence, New Orleans, Louisiana, 2-4 February, 2010
21. “Oil and Gas and Sulphur Operations in the Outer Continental Shelf, ” Title 30 Code of Federal
Regulations, Pt. 250. 2014 ed.
22. Bogaerts, M. et alet al. 2012. Challenges in Setting Cement Plugs in Deep-water Operations.
Paper SPE 155736 presented at the SPE Deepwater Drilling and Completions Conference,
Galveston, 20-21 June
23. Gupta, N. et alet al. 2014. Case Study: Long Cement Plugs in Ultradeepwater Environment in
French Guiana – Challenges and Solutions. Paper OTC 24338 presented at the Offshore Tech-
nology Conference Brazil, Rio de Janeiro, 29-31 October.
24. Rogers, H. et alet al. 2006. Drillable Tailpipe Disconnect: Used Successfully in More than 120
Wells Worldwide. Paper SPE 102534 presented at the SPE Annual Technical Conference and
Exhibition, San Antonio, 24-27 September
25. Bailey, J. R. and S. M. Remmert. 2010. “Managing Drilling Vibrations Through BHA Design
Optimization”, SPE Drilling & Completion Journal. SPE 139426.
26. Bailey, J. R. C. C. Elsborg, R. W. James, P. E. Pastusek, M. T. Prim, and W. W. Watson, 2013.
“Design Evolution of Drilling Tools to Mitigate Vibrations”, SPE Drilling & Completion Journal.
SPE 163503.
27. Bailey, J.R., and Wang, L., ExxonMobil Upstream Research Company, and Tenny, M.J.,
Armstrong, N., Zook, J.R., and Elks, Jr., W.C., ExxonMobil Development Company, “Design
Tools and Workflows To Mitigate Drilling Vibrations”, SPE 135439-MS presented at the SPE
Annual Technical Conference and Exhibition, Florence, Italy, 19-22 September 2010
28. Sowers, S.F. and Dupriest, F.E., “Roller Reamers Improve Drilling Performance in Wells Limited
by Bit and Bottomhole Assembly Vibrations, ” Paper SPE 119375 presented at the SPE/IADC
Drilling Conference, Amsterdam, The Netherlands, 17-19 March 2009
29. L.A. Sinor, et alet al., Drill Bits With Controlled Cutter Loading and Depth of Cut”, US Patent
6, 298, 930, October 9, 2001
30. M.W. Dykstra, et alet al, “Drill Bits with Reduced Exposure”, US Patent 6, 460, 631, October 8,
2002
31. Norris, J.A., Dykstra, M.W., Beuershausen, C.C., Fincher, R.W., Ohanian, M.P., “Development
and Successful Application of Unique Steerable PDC Bits”, SPE 39308 presented at the 1998
lADC/SPE Drilling Conference, Dallas Texas 3-6 March 1998
18 SPE-170751-MS
32. S. Barton, A. Garcia, and P. Pogliano, A. Silva, and M. Pelligra, “Drilling Cost Reduction
Through Use of Torque Controlling Features on Steerable Drill Bits Within Latin America”, SPE
121853 presented at the Latin American and Caribbean Petroleum Conference in Cartagena,
Colombia, 31 May – 3 June 2009
33. Joshua E. Davis, SPE, Gregory F. Smyth, SPE, Neil Bolivar,; Paul E. Pastusek, “Eliminating
Stick-Slip by Managing Bit Depth of Cut and Minimizing Variable Torque in the Drillstring”,
IADC/SPE 15113 presented at the SPE/IADC Drilling Conference, San Diego, California, 6 – 8
March 2012
34. Ertas, M. D., J. R. Bailey, L. Wang, P. E. Pastusek. Drillstring Mechanics Model for Surveillance,
Root Cause Analysis, and Mitigation of Torsional and Axial Vibrations. Paper SPE/IADC
163420-MS presented at the IADC/SPE Drilling Conference, Amsterdam, 5-7 March 2013.
35. Chang, D-L., G. S. Payette, D. Pais, L. Wang, J. R. Bailey, and N. D. Mitchell. 2014. Field Trial
Results of a Drilling Advisory System. IPTC 17216 presented at the International Petroleum
Technology Conference in Doha, Qatar, 20-22 January.
36. Dupriest F.E., Pastusek, P.E., Prim M.T., ExxonMobil, “The Critical Role of Digital Data in a
Performance Management Workflow”, SPE 150208, to be presented at Intelligent Energy Con-
ference, The Netherlands, Utrecht, 27-29 March 2012