SCOPE OF WORK
CLOSET
. Two doors every closet (UPPER DOOR ,LOWER DOOR ).
. provision of 2 sets of PADLOCKS in one closet for a total of 8 sets of Padlocks for 4-closets.
. Put handle Total of 8 pcs handles for 4 closets. (for UPPER & LOWER door).
. Remove the drawer at the lower part of closet and remain the shelve.
DOUBLE DECK BEDFRAME
.
Vertical post of railing at the upper deck should only be three to be placed at both corner and the center and
railing should be placed outside the edge of bedframe.
. Remain the height of bed frame as per actual mock up (from FFL to top of RAIL measure at 1800mm.)
Put 3-steps only at the ladder and should not be slanted, placed it perpendicular to bedframe.
.
. On the ceiling 2 LIGHTING ONLY at the hall (1 at the center of stUdy area,and the other one is in the center
of bed area) both with horizontal orientation.
TOILET AREA
. TOTAL WIDTH of toilet inside would be extended outside to 50mm. It should be measure at 950mm inside.
. at the same time moved also the main door outside the toilet to 50mm also going right side.
. Placed the sliding door of toilet inside, with exposed top rail.
. shower partition 300mm W X 1500mm H.
. Make mock up of Ramp sink, wait for the details to be send by architech uly.
HALLWAY
. Atrium railing
3/15/2019
STATUS REMARKS
DONE
DONE
1 SET OF DOUBLE
DONE DECK BED FRAME
INSTALLED,
BALANCE 1 SET
FOR
INSTALLATION
DONE C/O NAGALES
DONE
jalousie window
installed,waiting for grills to C/O NAGALES
installed
DONE
DONE
DONE
DONE
DONE
DONE
DONE C/O PALOMA
MELANIE BANTIGUE
prepared by: PC/CAD