Sie sind auf Seite 1von 2

BILL OF QUANTITIES

PROJECT : COMPOUND SCHOOL FOR GIRLS

ITEM DESCRIPTION ‫وصف البند‬ Q'TY. UNIT RATE AMT./SR

General notes:

Supply installation and commissioning of a complete system of


Air condition system, ductwork, all piping, fittings and controls
as herein specified and shown on plans. Price for system shall
A include all required equipment accessories, pipe sleeves &
Escutcheons, Equipment identification, tools & spare parts,
protective painting of all systems ...etc

Specification, drawings, and bill of quantities are


B complimentary and are to be taken together for complete
interpretations of the work.

C
In case of conflict between contract document, please refer to
the engineer for clarification.

Quantities, include in this bill of quantities is for guidance, the


D contractor shall check and verify all quantities.

The contractor should include in his offer all required materials


E needed for optimum operation whatever or not mentioned in the
bill of quantity.
Responsibility of contractor is to ensure that all works are in
F conformity with international stated codes and local
regulations.
The specification, the accompanying drawings and bill of
quantities, are intended to secure the provisions of all material,
G labor equipment, and services necessary to install complete,
tested, ready for operation and set to work the fire fighting
systems in accordance with the specifications and drawings.

To Collection

1/2
BILL OF QUANTITIES

PROJECT : COMPOUND SCHOOL FOR GIRLS

ITEM DESCRIPTION ‫وصف البند‬ Q'TY. UNIT RATE AMT./SR

01- Package units :-


Provide and install package air cooled scroll roof top units, ‫ توريد وتركيب وتوصيل ومعايرة واختبار معدات‬Package
including all accessories, fittings, wiring, connection etc. units ‫على أن يشمل كل بند على كافة المحلقات وقطع التوصيل‬
required for completion of the work.
‫ومجموعة المحابس ودوائر التحكم والوصلت المرنة وكاتم‬
‫الصوت لوحدات التوليد وموانع الهاتزاز وكافة الكسسوارات‬
‫اللزمة للداء طبقا ا للمواصفات والمخططات ومواصفات‬
ASHRE . NFPA

P.U.-01 (360,000 BTU/H) 1 No

P.U.-02 (300,000 BTU/H) 34 No

P.U.-03 (240,000 BTU/H) 20 No

P.U.-04 (120,000 BTU/H) 6 No

02- CONDENSING units ( DX ) :-


C.U units including support , sleeve pipe , pip insulation, ‫ توريد وتركيب وتوصيل ومعايرة واختبار وحدات التكثيف‬C.U
oil trap , disconnected switch, electric connection , (CONDENSING UNIT) ‫على ان يشمل البند على كافة الملحقات‬
electric switch , selector switch and all accessories ‫وقطع التوصيل ومجموعة المحابس ودوائر التحكم والوصلت المرنة وكاتم‬
according to dwg and specification . ‫الصوت وموانع الهأتزاازا وكافة الكسسوارات اللزامة طبقا ا للمواصفات‬
‫والمخططات ومواصفات‬.ASHRE.NFPA

C.U. -01 (210,000 BTU/H) 2 No

C.U. -02 (198,000 BTU/H) 4 No

C.U. -03 (168,000 BTU/H) 2 No

03- AIR HAND UNITS ( DX ) :-

Supply and install, connecting, testing and commissioning of ‫[ توريد و تركيب واختبار و تسليم وحدات مناولة الهواء‬Air
air handling units according to the schedules and specifications Handling unit ] ‫كاملة بالمحرك و ملفات التبريد و الفلتر‬
including accessories,components,supply fan, cooling coil,bag
[Pre + Bag ] ‫[ و مراوح التغذية من النوع‬Backward
filter,prefilter, dampers, earthing ,steel base and frame, shut-off
valves, balancing valve, drainage valves, vent valves, strainer, Centrifugal] ‫و توريد و تركيب مواسير الصرف و موانع‬
neoprene connectors, thermometers pressure gauges, piping ‫الهاتزاز والقواعد وعدادات القياس وثرموستات التشغيل من‬
required to be connected with the system include fittings, ‫النوع الذى يركب داخل مجاري الهواء الراجع شامل وحدة التحكم‬
flanges, bolts, nuts, gaskets, supports and paint, Rubber pads, controller)) ‫وكذلك الوصلت المرنة المضادة للحريق‬
sealers for leakage, thermal insulation complete with cladding, ‫ تكون من الداخل‬، ‫لتوصيلت الصاج‬treated aluminum fins
tags, labels, flow indicators and color code finishing, duct
/copper coil ..) ‫و طبقا للمواصفات و الجداول الفنية وطبقا ا‬
connection and flexible duct at supply and fresh air intake. See
arrangement drawing, and detail drawings. ‫ لما يلي‬: -

AHU.DX-01 (396,000 BTU/H) 2 No

AHU.DX-02 (210,000 BTU/H) 2 No

AHU.DX-03 (168,000 BTU/H) 2 No

To Collection

04-00. EXHAUST FAN:-

Supply, installation, connecting, testing, commissioning and ‫توريد وتركيب المراوح والعمال تشمل تركيب المراوح على‬
balancing of fan with all accessories, components, devices as
per schedules and specifications complete with earthing, steel ‫شاسيهات من زوايا الحديد المدهون وتوصيلها من خلل وصلة‬
base and frame, rubber pads, sealers for leakage, tags, labels,
flow indicators and color code finishing, duct connection and ‫مرنة )كنفس( بمجرى الهواء الخاص بها وتوصيل المراوح كهربائيا‬
flexible duct on outlet and inlet. See schedule, and detail
drawings. ‫وطبق ا للمواصفات الفنية وجداول المعدات والرسومات‬

04-01. SINGLE INLET :-