Beruflich Dokumente
Kultur Dokumente
net/publication/317844343
CITATIONS READS
0 215
2 authors, including:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Syed Umer Abdi on 13 January 2019.
In order to reduce cost and establish competitiveness in A preliminary inspection of the KSEW work environment
shipbuilding internationally, USA’s National revealed the following weaknesses:
Shipbuilding Research Program (NSRP) has launched a • Access inventory (parts and material) without proper
Lean Shipbuilding Initiative, to enable transformation to identification labels were left at store, yard, field and
Lean practices across shipbuilding and ship repair shop floor area.
industries in America [xxvi]. Lean Project Planning (LPP)
is also one of the best approach for project planning that • Problems in transporting, handling, and receiving of
has been developed from the Last Planner System to items from one shop to another due to
overcome shortcomings in the Earned Value Management mismanagement of transportation resources (cranes,
approach [xxvii]. 16-wheeler flatbed vehicles, fork lifters, etc.).
• Delays in completion of WOS (Work Order Sheets).
That is why the shipbuilding industries are also
implementing lean manufacturing techniques in their • Higher quantities of defective items. Most of the
manufacturing systems to avoid the delay in completion defects occurred in fabricating, welding, painting &
product and to reduce the wastage of material. The installations of different items.
fabrication is the main value-added process of the • Over-processing in shipbuilding hall; unnecessary
manufacturing of ship blocks and the inspection of the movement of men and material.
surveyor is key component to ensure integral structural
members of ship to complete as per given specification • Underutilization of manpower. Most workers were
without defect. However, it is not possible that every ship idle and were not properly assigned or effectively
did not contain any defect in the fabrication Process utilized for production at the shop floor level.
[xxviii].
• Unused computing resources; advanced technology
and facilities were rarely utilized to their maximum
Practical lessons learnt from implementation of lean
advantage.
systems illustrates that it is an influential technique for
traditional change in manufacturing. Lean As part of the investigation, KSEW records consisting of
implementation is low cost and have a significant ROI. Work Order Sheets (WOS) were analyzed to identify the
Main advantage of lean is that it includes hassle free reasons for work delays. Additionally, interviews with
thinking and support fruitful results for improvement shop managers were conducted that focused on:
efforts. i. Reviewing Record of Old WOS
ii. Reviewing Record of Defects (QC & Client
III. Preliminary Investigation and Study Observations)
Objectives:
A. Data Collection & Analysis: iii. Internal Audits
The data was collected by the Quality Assurance (QA) Shop records at KSEW revealed that Actual Man Hours
Auditors, quality Control (QC) Inspectors, Safety in every department exceeded the Total Scheduled Man
inspectors & Area Planners. The manufacturing processes Hours. Graphical statistics given below (Fig. 1) show
data were collected through the QA Auditors, whereas comparison of the Actual and Scheduled Man hours and
execution of Product related data was collected through the utilization of excess man hours in the various
Area Planners, QC inspectors and safety related departments at KSEW prior to introduction of Lean
Systems.
Internal Audit Observations
Measurement
Design
Resource Planning
Material
Man Power
Work Plan
Duties (KPI)
Safety
Maintenance and calibration
Methods
0 10 20 30 40 50 60 70 80
Intensity of Problems
Figure 3: WOS analysis using fish bone diagram (Cause and Effect diagram)
Poka Yoke and CAPA: 4. Hiring of planning personnel is delayed, and the few
planning employees did not have field experience
In this methodology, identified problems are solved by and project management training. Why?
taking Corrective and Preventive Actions (CAPA) to 5. Newly recruited personnel in Planning Department
avoid recurrence, and are aimed to implement error free without shipyard orientation are asked to commence
/ mistake proof ‘Poka Yoke’ process. QHSE team management tasks without local knowledge of
members together with concerned managers review and procedures. Why?
analyze problems, and recommend corrective and
preventive action (CAPA) aiming that after Root Cause Analysis: Competencies of Planning
implementation of these changes the system would Department Personnel are inadequate; hence, they are
become fool proof and free from mistakes (Poka Yoke). being dictated by Production department.
Recommendations are endorsed in corrective and CAPA / Poka Yoke: Planning personnel lacking in
preventive action format as per requirement of ISO 9001 knowledge should be trained by deputing one senior
standards. Further interrogation was carried out through manager to each newly appointed employee as a coach.
5 Why tool.
5 Whys to Identify delays (Production
5 Whys to Identify delays (Planning
Department)
Department)
1. Work Order Sheets are not started and not finished
1. Work Order Sheets are not completed on time. on time. Why?
Why?
2. Improper management and slackness observed as
2. Work starts late; moreover, work relationship is not Scheduled Start vs. Actual Start differ. Why?
categorized in the system as ‘early start, early finish,
late start and late finish with slack/float. Why? 3. Shop floor actual planning & monitoring to manage
employees & WOS is absent, resulting in excess of
3. Shortage of planning personnel, while most of them man hours, as most of work takes place in overtime.
have not received adequate training. Why? Why?
4. Crew compositions are incorrect, with improper 3. Preventive and/or routine maintenance is not carried
work assignment from supervisors to worker. Why? out, whereas only corrective maintenance on
machines is carried out. Why?
5. Supervisors do not properly utilize their staff, which
increases time lines and causes delays. Why? 4. Shop floor supervisor and machine operators lack
expertise to perform preventive maintenance, and
Root Cause Analysis: Supervisors are illiterate and
only corrective maintenance is implemented due to
untrained; hence, they do not plan, manage and execute
absence of maintenance system at maintenance
work according to WOS.
department. Why?
CAPA / Poka Yoke: Training of supervisors to be
5. Machine operators are neither trained in-house nor
initiated and senior managers will get involved in real
from OEM. Further, KSEW’s training institute does
planning of shop floor.
not have qualified trainers and usually calls experts
5 Whys to Identify delays (Design Department) from different shops. Why?
1. WOS are started early but not finished on time due Root Cause Analysis: Lifting capacity is low and
to shortage of resources and frequent rework. Why? planning aspect at shop floor is missing. Preventive
/Routine Maintenance is missing, and no proper
2. Revised and amended drawings are received late, procedure and log sheets are available. Workers are not
which causes rework. Why? familiar with the preventive maintenance routines.
3. Drawing revisions, amendments, missing details CAPA / Poka Yoke: Lifting capacity should be
and improper technical specifications halt the increased. Preventive maintenance to be initiated by the
production. As a result, queries are sent to the machine operators and planning aspect at shop floor is to
designer and await reply, resulting in overtime. be covered by shop floor manager. Machine operators’
Why? needs are to be addressed that their training from training
4. Shipyard does not have its own design house to institute or OEM is to be arranged to encounter
promptly resolve the issues. Hence, normal working breakdown and work order delays.
hours are not properly utilized, and 40 % of work is 5 Whys; Quality Control Department &
completed in overtime. Workers do not involve in
work during day time, with support from
Client Observations regarding Defects:
union/action committee. Additionally, 1. Poor workmanship due to insufficient field
unavailability of multi-skilled workers. Why? experience of managers and workers on different
ships. Why?
5. When managers send their requirements to drawing
distribution section, additional resources are neither 2. Employees’ attitude lacks concentration and focus
provided on time nor utilized properly (sorting time on job. Why?
is high, over processing and excess use of
inventory); plus, shortage of man power. Why? 3. Improper supervision & guidance because
experienced second line management (engineers)
Root Cause Analysis: Monitoring, resource allocation, were missing. Why?
and management aspects are weak, so regular
correspondence and product related issues are not 4. Engineers were not hired as needed, and supervisors
addressed in time, i.e., design house availability is the did not check the product before offering Quality
cause of the problem. Control. Why?
CAPA / Poka Yoke: Monitoring must be strengthened 5. No self-check Performa was available in system.
by the supervisors by implementing self -check and Self-check of Supervisor was missing causing 35%
timely raising queries on incomplete or incorrect of work to be rejected. Why?
drawings. Root Cause Analysis: Supervisor self-check Performa
does not exist in the current system.
5 Whys to Identify delays (Maintenance
CAPA / Poka Yoke: Self check system is to be
Department)
implemented.
1. Shop floor’s actual planning & monitoring does not
exist resulting in excess man hours. Why? B. 5S (Sort, Set, Shine, Standardize & Sustain)
2. Lifting capacity is low, and cannot handle more than Common problems in all work orders sheets were
40 tons. Further most of the machines are old and identified and solved by applying 5 Whys tool. Kaizen,
not working on their full capacity. Why? 5S, Corrective and Preventive Actions (CAPA) tools
were used, and by setting SMART objectives and Their storage and preservation require huge amount to
similarly QC observation were analyzed. maintain serviceability. In practice, the vessel orders
5S technique was implemented in Quality Assurance often differed from the expression of intent and forecast.
department, Shipbuilding Hall, Block Fabrication and
To resolve the inventory problem, ‘Just in Time’ concept
Machinery outfit section. After 5S implementation, the
was introduced, and the following modifications in the
following improvements were observed:
ordering procedure were made:
• Work order delays were reduced by eliminating the
i. After taking an account of project the Kits of
sorting time and traceability of tools, sub-
Material (KOM) will be procured against confirmed
assemblies and parts.
orders by KSEW.
• Power and hand tools management improved by ii. The client will provide all the Kit of Material
elimination of searching for serviceable tools, which (KOM) before start of project or in packages
also minimized movement of workers from ship to according to schedule.
store.
D. Kaizen (Continuous Improvement)
• Critical defects associated with paint work were
eliminated. Kaizen is essential part of all progressive organizations
and is also requirement to obtain ISO 9001 certification.
• High rise racks were fabricated to store consumables A unique method of Kaizen implementation without
(raised flange and piping spools) and eliminate affecting the ongoing production activities was proposed
waste. The standard of housekeeping in the work in this research. Although, applied in segregation from
area also improved. other Lean techniques, it may lose momentum
• Sorting time of files in the QA department was nevertheless 5S should be used as a ground tool for
reduced by applying identification tags and color further change efforts.
coding to files.
• QA department was made accessible to all
E. SMART (Set, Measurable Achievable
employees and a meeting table for Kaizen activities
was placed in QA department. Realistic Timed) objectives
The commitment of management to production is
• Cleaning and space saving improved the outlook of
reflected in quality objectives; therefore, objectives must
QA and other departments, and now it gives a better
be set keeping in view the continuous improvement
impression to external auditors and clients.
process at each level. Following that, prepared objectives
Pictorial representation of 5S implementation is shown are distributed to each departmental manager, and
in Appendix 1 communicated to every employee in the organization.
Effectiveness of the objectives is double-checked after
C. Just in Time conducting periodic audits to ensure achievement of
The Kit of Material (KoM) were purchased and tagged objectives according to plan. If objectives are not
by the project number and stored at the Warehouse. Prior achieved then a justification asked from concerned
to lean system implementation, material was procured on employees if required, and re-planning of objectives is
the basis of forecast according to schedule planning. This regularly carried out.
enabled the planning department to plan production
schedule with Work order sheet (WOS) and material Smart objectives are implemented in all divisions of
requisition note (MRN) that permitted drawing material KSEW as referred in table 1. This is an effective tool to
from store. Planning production on the basis of forecast, plan and set smart targets for both long and short term
however, created excess inventory that occupied space. according to time line as decided by general manager in
Moreover, expiry of the dated material and consumables, consultation of QHSE team members after RCA.
such as paint and electrodes, caused unnecessary waste.
Table: 1 “SMART Objectives and Achievements after implementing Lean tools”
Main Business Unit – 1 (SHIPBUILDING SHOPS)
Sr.# SMART Objectives Achievement
Timely completion of raised WOS within the agreed Overall Shop WOS completed within time =
01
WOS dates (Start/Finish) 100%
100% calibration of all in use Measuring & Testing Calibration of Measuring & Testing Equipment
02
Equipment in all workshops in KSEW =100%
Plan Load Test of all Cranes, Shackles, Slings, Wire Planning of Load Test Cranes, Shackles, Wire
03
Ropes etc. before due date Rope etc. = 72%
Quality Control department observation to be Quality Control department observation
04
decreased to 50% decreased to 61%
05 Upkeep of Shop Equipment/Machineries 80% Upkeep of shop equipment / machinery = 71%
F. Improvement in WOS timey execution after Lean System tools that resulted in saving excess man
Lean Systems implementation hours. Block wise statistics of improvement is shown in
following table.02 which indicates up to 5% saving in
The problem of delays in completion of Work Order manhour of the two pushing tugs in a one-month duration.
Sheets was solved through implementation of selected
Table: 02 “Total Blocks Manufacturing Sch. V/s Act. Man Hours before and after Lean System
Implementation
Description of Blocks Schedule Actual Man Actual Man Result Total saved Man
Man Hours without hours with LM Saved Hours in percentage
Hours LM Man
Hours
Keel Block 8292 8562 8292 0
ST Block 3233 3302 3200 33
CR Block 7727 8102 7354 373
BW Block 6592 6704 6233 359
ER Block 5236 5844 5236 0 5% (Five
BD Block 3979 3992 3489 490 Percentage)
WH Block 2609 2754 2600 9
Bilge Keel Marking 920 920 688 232
B-D WH Block 2216 2365 2200 16
Radar MST 1159 1180 1159 0
Launching Cradle arrangements 6748 6748 6106 642
Reduction in identified problem of Internal Audit before and after lean implementation
70
60
50
39 40
40
31 29
30 26
22 21 23 25
19 18 17
20
10 8 6
10
3 3 3 1
0
Figure 6: Comparison between Last and Current Internal Audit (after Lean implementation)
1330
1061
809.5
576
0 0
2005-2006 2006-2007 2007-2008 2008-2009 2009-2010 2010-2011 2011-2012 2012-2013
Appendix I:
Before After
Quality Assurance Department Before and After 5S Implementation