Beruflich Dokumente
Kultur Dokumente
3,320,364.81
1,106,788.27
29369.14
Republic of the Philippines
Item No. DESCRIPTION QTY UNIT MARK-UPS IN PERCENT TOTAL MARK-UP VAT
ESTIMATED TOTAL INDIRECT TOTAL COST UNIT COST
DIRECT COST OCM PROFIT % VALUE COST
(9) (10) (11) (12) (13)
(1) (2) (3) (4) (5) (6) (7) (8)
(5)x(8) (13%[(5)+(9)] (9)+(10) (5)+(11) (12)/(3)
I MOBILIZATION / DEMOBILIZATION 1.00 Lot P 4,128.00 0.0% 0.0% 0.0% P - P 536.64 P 536.64 P 4,664.64 P 4,664.64
II TEMPORARY FACILITIES AND BILLBOARD 1.00 Lot P 12,113.72 15.0% 10.0% 25.0% P 3,028.43 P 1,968.48 P 4,996.91 P 17,110.63 P 17,110.63
III SAFETY AND HEALTH 85.00 days P 24,282.43 0.0% 10.0% 10.0% P 2,428.24 P 3,472.39 P 5,900.63 P 30,183.06 P 355.09
IV EARTHWORKS 255.60 cu.m. P 120,057.06 15.0% 10.0% 25.0% P 30,014.27 P 19,509.27 P 49,523.54 P 169,580.60 P 663.47
V TERMITE CONTROL WORKS 183.74 sq.m. P 2,728.44 15.0% 10.0% 25.0% P 682.11 P 443.37 P 1,125.48 P 3,853.92 P 20.97
VI CONCRETE WORKS
Structural Concrete (Class A) 67.62 cu.m. P 451,416.67 15.0% 10.0% 25.0% P 112,854.17 P 73,355.21 P 186,209.38 P 637,626.05 P 9,429.55
Reinforcing Steel 8501.52 kgs P 513,241.74 15.0% 10.0% 25.0% P 128,310.44 P 83,401.78 P 211,712.22 P 724,953.96 P 85.27
VII MASONRY WORKS 138.96 cu.m. P 271,089.68 15.0% 10.0% 25.0% P 67,772.42 P 44,052.07 P 111,824.49 P 382,914.17 P 2,755.57
VIII FABRICATED MATERIALS AND HARDWARES 31.80 sq.m. P 361,864.90 15.0% 10.0% 25.0% P 90,466.23 P 58,803.05 P 149,269.28 P 511,134.18 P 16,073.40
IX FINISHING WORKS 1006.04 sq.m. P 137,871.20 15.0% 10.0% 25.0% P 34,467.80 P 22,404.07 P 56,871.87 P 194,743.07 P 193.57
X CARPENTRY WORKS 172.42 sq.m. P 186,480.88 15.0% 10.0% 25.0% P 46,620.22 P 30,303.14 P 76,923.36 P 263,404.24 P 1,527.69
XI ROOF AND FRAMING WORKS 326.14 sq.m. P 755,901.36 15.0% 10.0% 25.0% P 188,975.34 P 122,833.97 P 311,809.31 P 1,067,710.67 P 3,273.74
XII PAINTING WORKS 965.89 sq.m. P 97,499.80 15.0% 10.0% 25.0% P 24,374.95 P 15,843.72 P 40,218.67 P 137,718.47 P 142.58
XIII ELECTRICAL WORKS 1.00 lot P 156,515.73 15.0% 10.0% 25.0% P 39,128.93 P 25,433.81 P 64,562.74 P 221,078.46 P 221,078.46
XIV PLUMBING / SANITARY WORKS 1.00 lot P 89,184.88 15.0% 10.0% 25.0% P 22,296.22 P 14,492.54 P 36,788.76 P 125,973.64 P 125,973.64
Labor
1 Construction Foreman 12.00 hrs ₱63.46 ₱761.52
2 Skilled Laborers 12.00 hrs ₱45.99 ₱1,103.76
2 Unskilled Laborers 12.00 hrs ₱35.56 ₱853.44
Sub-Total ₱12,113.72
OCM (15%) ₱1,817.06
Contractors Profit (10%) ₱1,211.37
VAT + BARMM Tax ( 12%+1%) ₱1,968.48
TOTAl COST ₱17,110.63
Total Unit Cost ₱17,110.63
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
III. SAFETY AND HEALTH 85.00 days
Item SPL-1 Personal Protective Equipment (PPE)
Materials
a. Const. Safety Helmet (Hard Hat) 12.00 pcs ₱200.00 ₱2,400.00
b. Const. Safetry Shoes (Steel Toe) 12.00 pcs ₱1,000.00 ₱12,000.00
c. Safety Gloves 24.00 pcs ₱100.00 ₱2,400.00
d. Safety Goggles 4.00 pcs ₱150.00 ₱600.00
e. High Visibility Vest 4.00 pcs ₱500.00 ₱2,000.00
f. First-Aid Kit 1.00 set ₱2,352.79 ₱2,352.79
Equipment
1 Plate Compactor 36.00 hrs ₱123.00 ₱4,428.00
Item 804(b) Gravel Bedding @ CF, SW, FTB, SOF, Trench 29.24 cu.m.
Materials
a. Gravel 30.00 cu.m. ₱563.71 ₱16,911.30
Labor
1 Const. Foreman 36.00 hrs ₱63.46 ₱2,284.56
2 Unskilled Laborer 36.00 hrs ₱35.56 ₱2,560.32
Labor
1 Const. Foreman 36.00 hrs ₱63.46 ₱2,284.56
2 Unskilled Laborer 36.00 hrs ₱35.56 ₱2,560.32
Equipment
1 Plate Compactor 36.00 hrs ₱123.00 ₱4,428.00
Sub-Total ₱120,057.06
OCM (15%) ₱18,008.56
Contractors Profit (10%) ₱12,005.71
VAT + BARMM Tax ( 12%+1%) ₱19,509.27
TOTAl COST ₱169,580.60
Total Unit Cost ₱663.47
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
V. TERMITE CONTROL WORKS 183.74 sq.m.
Materials
a. Soil Poisoning, 250ml/bottle (Termiticide Sol.) 25.00 bottles ₱75.00 ₱1,875.00
Labor
1 Unskilled Laborer 24.00 hrs ₱35.56 ₱853.44
Sub-Total ₱2,728.44
OCM (15%) ₱409.27
Contractors Profit (10%) ₱272.84
VAT + BARMM Tax ( 12%+1%) ₱443.37
TOTAl COST ₱3,853.92
Total Unit Cost ₱20.97
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
VI. Concrete Works
Item 900(a) RC for CF and WF 7.59 cu.m.
Item 900(b) RC for FTB 9.45 cu.m.
Item 900(c) RC for C,PC and Stiffener 8.34 cu.m.
Item 900(d) RC for RB amd LRB 13.02 cu.m.
Item 900(e) RC for SOF, Corridor Ramp 26.94 cu.m.
RC for toilet and handwash facility 2.28 cu.m.
67.62 cu.m.
Materials
a. Portland Cement 610.00 bags ₱290.00 ₱176,900.00
b. Fine Aggregates 35.00 cu.m. ₱503.71 ₱17,629.85
c. Gravel 70.00 cu.m. ₱563.71 ₱39,459.70
d. Coco Lumber, Assorted 1,353.00 bd.ft. ₱25.00 ₱33,825.00
e. Marine Plywood (1/2" x 4' x 8') 55.00 pcs ₱800.00 ₱44,000.00
f. Assorted C.W. Nails 15.00 kgs ₱70.00 ₱1,050.00
Labor
1 Const. Foreman 96.00 hrs ₱63.46 ₱6,092.16
8 Skilled Laborer 96.00 hrs ₱45.99 ₱35,320.32
16 Unskilled Laborer 96.00 hrs ₱35.56 ₱54,620.16
Equipment
1 One Bagger Mixer 96.00 hrs ₱172.00 ₱16,512.00
1 Concrete Vibrator 96.00 hrs ₱148.88 ₱14,292.48
1 Water Truck (1000 gal) 11.00 hrs ₱1,065.00 ₱11,715.00
Sub-Total ₱451,416.67
OCM (15%) ₱67,712.50
Contractors Profit (10%) ₱45,141.67
VAT + BARMM Tax ( 12%+1%) ₱73,355.21
TOTAl COST ₱637,626.05
Total Unit Cost ₱9,429.55
Equipment
1 Bar Cutter 54.00 hrs ₱219.75 ₱11,866.50
1 Bar Bender 54.00 hrs ₱351.50 ₱18,981.00
1 Cargo Truck (10T, 270hp) 12.00 hrs ₱1,102.00 ₱13,224.00
Sub-Total ₱513,241.74
OCM (15%) ₱76,986.26
Contractors Profit (10%) ₱51,324.17
VAT + BARMM Tax ( 12%+1%) ₱83,401.78
TOTAl COST ₱724,953.96
Total Unit Cost ₱85.27
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
VII MASONRY WORKS 138.96 cu.m.
Item 506(1a) Masonry Units 178.43
Masonry Units (Toilet and HW Facility) 43.90
Materials
a. CHHB 6" thck 3,075.00 pcs ₱25.00 ₱76,875.00
b. CHB 4" thck (for Toilet and HW Facility) 963.00 pcs ₱20.00 ₱19,260.00
c. Portland Cement 227.00 bags ₱290.00 ₱65,830.00
d. Washed Sand 20.00 cu.m. ₱503.71 ₱10,074.20
e. 87pcs-10mm x 6m RSB 515.04 kgs ₱50.00 ₱25,752.00
f. G.I. Tie Wire 12.00 kgs ₱70.00 ₱840.00
g. Concrete Louver Blocks 50.00 pcs ₱35.00 ₱1,750.00
Labor
1 Const. Foreman 96.00 hrs ₱63.46 ₱6,092.16
6 Skilled Laborer 96.00 hrs ₱45.99 ₱26,490.24
8 Unskilled Laborer 96.00 hrs ₱35.56 ₱27,310.08
Equipment
1 Dump Truck 8.00 hrs ₱1,352.00 ₱10,816.00
Sub-Total ₱271,089.68
OCM (15%) ₱40,663.45
Contractors Profit (10%) ₱27,108.97
VAT + BARMM Tax ( 12%+1%) ₱44,052.07
TOTAl COST ₱382,914.17
Total Unit Cost ₱2,755.57
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
VIII FABRICATED MATERIALS AND HARDWARES 31.80 sq.m.
Materials
a. (D-1) 2.4m x 0.9m Panel Door Type Hinged Door 6.00 sets ₱7,200.00 ₱43,200.00
and Fixed Glass Transom on 50 x 150mm Wood
Jambs/Frames with Keyed Lever Type Locksets with
Complete Accessories
b. (D-2) 2.1m x 0.9m Solid Core Flush Type Hinged 3.00 sets ₱6,000.00 ₱18,000.00
Door on 50 x 150mm Wood Jambs/Frames Provide
Kickplate
c. (W-1) 2.5m x 1.68m Shutter Type Window Holder 6.00 ₱8,500.00 ₱51,000.00
with Clear Glass Blades with Fixed Clear Glass and
Transoms on 50 x 150mm Window Jambs/ Frames
with Complete Accessories
with Clear Glass Blades with Fixed Clear Glass and
Transoms on 50 x 150mm Window Jambs/ Frames
with Complete Accessories
(W-2) 1.2 x 1.68m Shutter Type Window Holder with
d. Clear Glass Blades with Fixed Clear Glass and 6.00 sets ₱4,300.00 ₱25,800.00
Transoms on 50x150mm Window Jambs/Framed
with Complete Acessories
e. Blackboard with Chalk Dust Box 3.00 sets ₱5,000.00 ₱15,000.00
Labor
1 Const. Foreman 64.00 hrs ₱63.46 ₱4,061.44
6 Skilled Laborer 64.00 hrs ₱45.99 ₱17,660.16
6 Unskilled Laborer 64.00 hrs ₱35.56 ₱13,655.04
Equipment
a. Dumptruck ( for delivery of chairs) 0.00 trips ₱2,000.00 ₱0.00
Sub-Total ₱361,864.90
OCM (15%) ₱54,279.74
Contractors Profit (10%) ₱36,186.49
VAT + BARMM Tax ( 12%+1%) ₱58,803.05
TOTAl COST ₱511,134.17
Total Unit Cost ₱16,073.40
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
IX FINISHING WORKS 1,006.04 sq.m.
Item 1021(c) Plain Cement Finish with Floor Hardener 229.50 sq.m.
Item 1021(c-1) Plain Cement Finish with Floor Hardener Non-Skid 43.20 sq.m.
Item 1021(c-2) Non-Skid Cement Floor Finish w/ 6mm Groove Lines 11.52 sq.m.
Item 1027(a) Plain Cement Plaster Finish 637.60 sq.m.
Item SPL-5 Rail Guard 1.60 lot
Plain Cement Plaster Finish 84.22 sq.m.
Materials
a. Portland Cement 150.00 bags ₱290.00 ₱43,500.00
b. Washed Sand 16.00 cu.m. ₱503.71 ₱8,059.36
c. Floor Hardener 3.20 liter ₱1,200.00 ₱3,840.00
d. 200x200mm Vitrified Ceramic Glazed Wall Tiles 120.00 pcs ₱20.00 ₱2,400.00
e. 200x200mm Vitrified Ceramic Unglazed Wall Tiles 130.00 pcs ₱18.00 ₱2,340.00
f. Tile Adhesive 25kg/bag 30.00 bags ₱230.00 ₱6,900.00
g. Tile Trim PVC 6mm x 2.44m 32.00 pcs ₱45.00 ₱1,440.00
h. Tile Grout (3kg/bag) 30.00 bags ₱100.00 ₱3,000.00
i. 38mm Dia. X 20ft. G.I. Pipe Handrail 8.00 length ₱2,000.00 ₱16,000.00
j. Welding Rod 8.00 kgs ₱120.00 ₱960.00
Labor
1 Const. Foreman 84.00 hrs ₱63.46 ₱5,330.64
6 Skilled Laborer 84.00 hrs ₱45.99 ₱23,178.96
6 Unskilled Laborer 84.00 hrs ₱35.56 ₱17,922.24
Equipment
1 Welding Machine (Acetylene) 12.00 hrs ₱150.00 ₱1,800.00
1 Welding Machine (Electric) 12.00 hrs ₱100.00 ₱1,200.00
Sub-Total ₱137,871.20
OCM (15%) ₱20,680.68
Contractors Profit (10%) ₱13,787.12
VAT + BARMM Tax ( 12%+1%) ₱22,404.07
TOTAL COST ₱194,743.07
Total Unit Cost ₱193.57
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
X CARPENTRY WORKS 172.42 sq.m.
Item 1003 Carpentry for Ceiling with Insulation
Materials
a. 4.5mm thk, Fiber Cement Ceiling Board 98.00 pcs ₱500.00 ₱49,000.00
b. 12mm x 38mm x 5m x 0.8mm thk Double 156.00 pcs ₱275.00 ₱42,900.00
Furring Channel (Nailer)
c. 0.5mm thk x 25mm x 25mm x 2.4m Wall Angle Furrin 86.00 pcs ₱45.00 ₱3,870.00
d. 12mm x 38mm x 5m x 0.8mm thk Double 51.20 pcs ₱275.00 ₱14,080.00
Furring Channel (Nailer)
e. 1.0mm thk. Carryingg Channel Joiner 32.00 pcs ₱5.50 ₱176.00
f. 0.4mm thk. Furring Clip 336.00 pcs ₱4.00 ₱1,344.00
g. Suspension Rod Hanger 336.00 pcs ₱22.00 ₱7,392.00
h. 25 x 25 x 300mm Wooden Ceiling Ventilation 9.60 sets ₱450.00 ₱4,320.00
(w/ Wire Mesh Inside pcs
i. Blind Rivets 3,600.00 pcs ₱0.75 ₱2,700.00
j. Concrete Nails 3.20 kgs ₱75.00 ₱240.00
Labor
1 Const. Foreman 96.00 hrs ₱63.46 ₱6,092.16
4 Skilled Laborer 96.00 hrs ₱45.99 ₱17,660.16
6 Unskilled Laborer 96.00 hrs ₱35.56 ₱20,482.56
Equipment
1 Dump Truck 12.00 hrs ₱1,352.00 ₱16,224.00
Sub-Total ₱186,480.88
OCM (15%) ₱27,972.13
Contractors Profit (10%) ₱18,648.09
VAT + BARMM Tax ( 12%+1%) ₱30,303.14
TOTAl COST ₱263,404.24
Total Unit Cost ₱1,527.69
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
XI ROOF AND FRAMING WORKS 326.14 sq.m.
Item 1014 Pre-Painted Metal Sheets 326.14 sq.m.
Materials
a. 0.40mm thk. X 1.22m Long Span Pre-painted 328.00 ln.m. ₱450.00 ₱147,600.00
G.I. Roofing
b. 0.6mm thk. Pre-painted G.I. Ridge Roll 13.00 pcs ₱495.00 ₱6,435.00
c. 0.6mm thk. Pre-painted G.I. Flashing 10.00 pcs ₱495.00 ₱4,950.00
d. 6mm dia., J-bolt 2,180.00 pcs ₱5.00 ₱10,900.00
e. Roof Sealant 3.00 length ₱380.00 ₱1,140.00
Materials
a. Angle Bar Steel Trusses 2,162.48 kgs ₱60.00 ₱129,748.80
b. 16mm dia. x 300mm anchor bolts w/ nuts & 19.20 pcs ₱40.00 ₱768.00
washers
c. 12mm dia. X 150mm Long Anchor Bolt 25.00 pcs ₱30.00 ₱750.00
d. Welding Rod 48.00 kgs ₱120.00 ₱5,760.00
e. Oxygen (Content Only) 3.20 tank ₱370.00 ₱1,184.00
f. Acetylene 3.20 tank ₱670.00 ₱2,144.00
g. 150 x 65 x 20 x 20mm LC Purlins 4,290.61 kgs ₱60.00 ₱257,436.48
h. 100 x 100 x 6mm thkkk. Angular Base Plate 324.83 kgs ₱60.00 ₱19,489.92
i. 12mm di. Sag Rod w/ standard nut & washer 68.19 kgs ₱60.00 ₱4,091.52
j. Cross-Bracing 272.86 kgs ₱60.00 ₱16,371.84
k. Turn Buckle 25.60 each ₱88.00 ₱2,252.80
Labor
1 Const. Foreman 150.00 hrs ₱63.46 ₱9,519.00
8 Skilled Laborer 150.00 hrs ₱45.99 ₱55,188.00
8 Unskilled Laborer 150.00 hrs ₱35.56 ₱42,672.00
Equipment
1 Welding Machine (Acetylene) 150.00 hrs ₱150.00 ₱22,500.00
1 Welding Machine (Electric) 150.00 hrs ₱100.00 ₱15,000.00
Sub-Total ₱755,901.36
OCM (15%) ₱113,385.20
Contractors Profit (10%) ₱75,590.14
VAT + BARMM Tax ( 12%+1%) ₱122,833.97
TOTAl COST ₱1,067,710.67
Total Unit Cost ₱3,273.74
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
XII PAINTING WORKS 965.89 sq.m.
Item 1032(a-1) Masonry Painting 723.10 sq.m.
Toilet and HW Facilty Painting 130.00
Materials
a. Concrete Neutralizer 36.00 gal ₱135.00 ₱4,860.00
b. Flat Latex Primer 40.00 gal ₱510.00 ₱20,400.00
c. Masonry Putty 40.00 gal ₱320.00 ₱12,800.00
d. Semi-Gloss Latex 40.00 gal ₱605.00 ₱24,200.00
e. Acri Color 13.00 gal ₱165.00 ₱2,145.00
f. Painte Roller with Pan #3 7.00 gal ₱150.00 ₱1,050.00
g. Paint Brush #3 8.00 pcs ₱75.00 ₱600.00
Labor
1 Const. Foreman 60.00 hrs ₱63.46 ₱3,807.60
2 Skilled Laborer 60.00 hrs ₱45.99 ₱5,518.80
4 Unskilled Laborer 60.00 hrs ₱35.56 ₱8,534.40
Sub-Total ₱97,499.80
OCM (15%) ₱14,624.97
Contractors Profit (10%) ₱9,749.98
VAT + BARMM Tax ( 12%+1%) ₱15,843.72
TOTAl COST ₱137,718.47
Total Unit Cost ₱142.58
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
XIII ELECTRICAL WOKRS 1.00 lot
Item 1100 Conduits, Boxes and Fittings 1.00 lot
Materials
a. PVC Pipe 15mm x 3.0m 75.00 pcs ₱65.00 ₱4,875.00
b. RCS Pipe 20mm x 3.0m 7.50 pcs ₱227.00 ₱1,702.50
c. Locknuts and Bushing 110.00 pcs ₱5.30 ₱583.00
d. PVC Adaptor - 15mm 110.00 pcs ₱2.90 ₱319.00
e. Utility Box Deep Type 6.00 pcs ₱27.00 ₱162.00
f. Junction Box Deep Type 18.00 pcs ₱27.00 ₱486.00
g. Square Box Deep Type 6.00 pcs ₱7.10 ₱42.60
h. Service Entrance Cap 3.00 pcs ₱42.00 ₱126.00
Sub-Total ₱156,515.73
OCM (15%) ₱23,477.36
Contractors Profit (10%) ₱15,651.57
VAT + BARMM Tax ( 12%+1%) ₱25,433.81
TOTAl COST ₱221,078.46
Total Unit Cost ₱221,078.46
ITEM DESCRIPTION QTY. UNIT UNIT COST TOTAL COST
XIV PLUMBING / SANITARY WORS 1.00 lot
Materials
a. Water Closet ( Pail Type) 3.00 set ₱1,200.00 ₱3,600.00
b. Lavatory w/ complete accessories 3.00 set ₱1,000.00 ₱3,000.00
c. Water Closet Flange 3.00 set ₱200.00 ₱600.00
d. Faucet 15.00 pcs ₱150.00 ₱2,250.00
e. Floor Drain 6.00 pcs ₱100.00 ₱600.00
f. 38mm dia.. Textured Stainless Grab Bar 3.00 pcs ₱2,000.00 ₱6,000.00
g. 100m dia. PVC 3.00 pcs ₱570.00 ₱1,710.00
h. 75mm dia. PVC 3.00 pcs ₱410.00 ₱1,230.00
i. 50mm dia. PVC x 10ft. 8.00 pcs ₱265.00 ₱2,120.00
j. 20mm dia. G.I. Pipe 6.00 pcs ₱460.00 ₱2,760.00
k. Septic Vault with complete fittings 0.00 set ₱5,000.00 ₱0.00
l. PVC Fittings, Assorted 25.00 pcs ₱200.00 ₱5,000.00
m. Solvent 8.00 can ₱150.00 ₱1,200.00
n. Teflon 8.00 pcs ₱30.00 ₱240.00
Labor
1 Const. Foreman 48.00 hrs ₱63.46 ₱3,046.08
2 Skilled Laborer 48.00 hrs ₱45.99 ₱4,415.04
2 Unskilled Laborer 48.00 hrs ₱35.56 ₱3,413.76
Sub-Total ₱89,184.88
OCM (15%) ₱13,377.73
Contractors Profit (10%) ₱8,918.49
VAT + BARMM Tax ( 12%+1%) ₱14,492.54
TOTAl COST ₱125,973.64
Total Unit Cost ₱125,973.64
₱4,128.00
₱4,128.00
₱412.80
₱4,664.64
₱9,395.00
₱2,718.72
₱1,817.06 ₱12,113.72
₱17,110.63
₱21,752.79
₱1,529.64
₱1,000.00
₱24,282.43
₱30,183.06
₱17,702.40
₱7,405.20
₱4,428.00
₱16,911.30
₱4,844.88
₱59,492.40
₱4,844.88
₱4,428.00
₱120,057.06
₱18,008.56
₱169,580.60
₱1,875.00
₱853.44
₱2,728.44
₱409.27
₱3,853.92
₱312,864.55
₱96,032.64
₱42,519.48
₱451,416.67
₱67,712.50
₱637,626.05
1.6 339.98
1.6 1,123.24
1.6 1,574.69
1.6 1,466.08
1.6 756.16
1.6 53.30
1.6 5,313.45
1.6 112.00
₱437,496.00 1.6 6.00
1.6 72.00
1.6 72.00
₱31,674.24 1.6 72.00
1.5 36.00
1.5 36.00
₱44,071.50 1.5 8.00
₱513,241.74
₱76,986.26
₱724,953.96
1.6 111.52
1.6 27.44
1.6 1,737.00
1.6 343.00
1.6 151.00
1.6 12.00
1.6 321.90
1.6 7.00
₱200,381.20 1.6 32.00
1.5 72.00
1.5 72.00
₱59,892.48 1.5 72.00
₱10,816.00
₱271,089.68
₱40,663.45
₱382,914.17
1.5 4.00
1.5 2.00
1.5 4.00
1.5 4.00
1.5 2.00
₱326,488.26
₱35,376.64
₱0.00
₱361,864.90
₱54,279.74
₱511,134.17
1.6 116.20
1.6 27.00
1.6 5.78
1.6 293.96
1.6 1.00
1.6 52.64
1.6 100.00
1.6 10.00
1.6 2.00
1.6 457.00
1.6 189.00
1.6 18.00
1.6 20.00
1.6 19.00
1.6 6.00
₱88,439.36 1.6 5.00
1.5 56.00
1.5 56.00
₱46,431.84 1.5 56.00
1.5 8.00
₱3,000.00 1.5 8.00
₱137,871.20
₱20,680.68
₱194,743.07
1.6 65.00
1.6 105.00
1.6
1.6 57.00
1.6 32.00
1.6
1.6 20.00
1.6 210.00
1.6 210.00
1.6 6.00
1.6
₱126,022.00 1.6 2,250.00
1.6 2.00
1.5 64.00
1.5 64.00
₱44,234.88 1.5 64.00
₱263,404.24
1.6 203.84
1.6
1.6 205.00
1.6
1.6 8.00
1.6 6.00
1.6 1,362.00
₱171,025.00 1.6 2.00
1.6
1.6 1,351.55
1.6 2,681.63
1.6 203.02
1.6 42.62
1.6 170.54
1.6 16.00
1.6
1.6
1.6 1,351.55
1.6 12.00
1.6
1.6 14.00
1.6 30.00
1.6 2.00
1.6 2.00
1.6 2,681.63
1.6 203.02
1.6 42.62
1.6 170.54
₱439,997.36 1.6 16.00
1.5 136.00
1.5 136.00
₱107,379.00 1.5 136.00
1.5 136.00
₱37,500.00 1.5 136.00
₱755,901.36
₱113,385.20
₱1,067,710.67
1.6 451.94
1.6 54.88
1.6
1.6 23.00
1.6 25.00
1.6 25.00
1.6 25.00
1.6 8.00
1.6 4.00
₱66,055.00 1.6 5.00
1.6
1.6 41.46
1.6
1.6 2.00
1.6 2.00
1.6 4.00
1.6 2.00
1.6 2.00
1.6 2.00
₱8,289.00 1.6 2.00
1.6
1.6 29.03
1.6
1.6 4.00
1.6 2.00
₱5,295.00 1.6 2.00
1.5
1.5
1.5 40.00
1.5 40.00
₱17,860.80 1.5 40.00
₱97,499.80
₱14,624.97
₱137,718.47
1.5 50.00
1.5 5.00
1.5 70.00
1.5 70.00
1.5 4.00
1.5 12.00
1.5 4.00
₱8,296.10 1.5 2.00
1.5
1.5 1.00
1.5
1.5 500.00
1.5 8.00
1.5 4.00
1.5 2.00
1.5 2.00
₱28,710.00 1.5 2.00
1.5
1.5 1.00
1.5
1.5 12.00
1.5
1.5 5.00
1.5
₱32,415.00 1.5 4.00
1.5
1.5 1.00
1.5
₱3,900.00 1.5 1.00
1.5
1.5
1.5 40.00
1.5 40.00
₱17,860.80 1.5 40.00
₱65,333.83
₱156,515.73
₱23,477.36
₱221,078.46
1.5 2.00
1.5 2.00
1.5 2.00
1.5 2.00
1.5 2.00
1.5 1.00
1.5 1.00
1.5 1.00
1.5 5.00
1.5 3.00
1.5 1.00
1.5 15.00
1.5 5.00
₱30,310.00 1.5 5.00
1.5 32.00
1.5 32.00
₱10,874.88 1.5 32.00
₱48,000.00
₱89,184.88
₱13,377.73
₱125,973.64
₱3,184,376.49
OCM
₱1,817.06
₱1,211.37
₱3,028.43
0.000 -
10000000
Hand Wash Facility with Toilet Quantity Units Unit Cost Cost
Laborers
1 Const. Foreman 18.00 hours ₱63.46 ₱1,142.28
2 Skilled Laborer 18.00 hours ₱45.99 ₱1,655.64
4 Unskilled Laborer 18.00 hours ₱35.56 ₱2,560.32
Masonry Works
Materials
CHB 4" thck 963 pcs ₱20.00 ₱19,260.00
Portland Cement 23 bags ₱290.00 ₱6,670.00
Washed Sand 6 cu.m. ₱503.71 ₱3,022.26
87pcs-10mm x 6m RSB 52 kgs ₱50.00 ₱2,600.00
G.I. Tie Wire 4 kgs ₱70.00 ₱280.00
Laborers
1 Const. Foreman 18.00 hours ₱63.46 ₱1,142.28
1 Skilled Laborer 18.00 hours ₱45.99 ₱827.82
4 Unskilled Laborer 18.00 hours ₱35.56 ₱2,560.32
Finishing Works
Materials
Portland Cement 15.00 bags ₱290.00 ₱4,350.00
Washed Sand 5.00 cu.m. ₱503.71 ₱2,518.55
Floor Hardener 2.00 liter ₱1,200.00 ₱2,400.00
200x200mm Ceramic Glazed Tiles 120.00 pcs ₱20.00 ₱2,400.00
200x200mm Unglazed Tiles 130.00 pcs ₱18.00 ₱2,340.00
Tile Adhesive 25kg/bag 3.00 bags ₱230.00 ₱690.00
Tile Trim PVC 6mm x 2.44m 0.00 pcs ₱45.00 ₱0.00
Tile Grout (3kg/bag) 3.00 bags ₱100.00 ₱300.00
38mm Dia. X 20ft. G.I. Pipe Handrail 0.80 length ₱2,000.00 ₱1,600.00
Laborers
1 Const. Foreman 24.00 hours ₱63.46 ₱1,523.04
1 Skilled Laborer 24.00 hours ₱45.99 ₱1,103.76
4 Unskilled Laborer 24.00 hours ₱35.56 ₱3,413.76
Laborers
1 Const. Foreman 36.00 hours ₱63.46 ₱2,284.56
4 Skilled Laborer 36.00 hours ₱45.99 ₱6,622.56
8 Unskilled Laborer 36.00 hours ₱35.56 ₱10,241.28
Equipments
Welding Machine (Acetylene) 36 hours ₱150.00 ₱5,400.00
Welding Machine (Electric) 36 hours ₱100.00 ₱3,600.00
Painting Works
Materials
Concrete Neutralizer 4 gal ₱135.00 ₱540.00
Flat Latex Primer 8 gal ₱510.00 ₱4,080.00
Masonry Putty 4 gal ₱320.00 ₱1,280.00
Semi-Gloss Latex 4 gal ₱605.00 ₱2,420.00
Acri Color 2 gal ₱165.00 ₱330.00
Painte Roller with Pan #3 2 gal ₱150.00 ₱300.00
Paint Brush #3 2 pcs ₱75.00 ₱150.00
Flatwall Enamel (Primer) 2 gal ₱573.00 ₱1,146.00
Quick Dry Enamel (QDE) 2 gal ₱585.00 ₱1,170.00
Paint Thinner 2 gal ₱260.00 ₱520.00
Tinting Collor (Oil) 2 qrt ₱95.00 ₱190.00
Laborers
1 Const. Foreman 16.00 hours ₱63.46 ₱1,015.36
2 Skilled Laborer 16.00 hours ₱45.99 ₱1,471.68
4 Unskilled Laborer 16.00 hours ₱35.56 ₱2,275.84
Laborers
1 Const. Foreman 36.00 hours ₱63.46 ₱2,284.56
2 Skilled Laborer 36.00 hours ₱45.99 ₱3,311.28
2 Unskilled Laborer 48.00 hours ₱35.56 ₱3,413.76
54 0.1 5.4
54 0.1 5.4
₱110,866.22
Excavation VOL UNITS
CF1 1.20 x 1.20 x 1.00 = 1.44 = 14.00 = 20.16
WF/FTB 0.25 x 0.40 x 82.00 = 8.20 = 1.00 = 8.20
CF2 0.80 x 0.80 x 1.00 = 0.64 = 8.00 = 5.12
WF2 0.25 x 0.40 x 26.00 = 2.60 = 1.00 = 2.60
36.08
MASONRY
BLDG 82 / 0.40 = 205.00
3 / 0.20 = 15.00 3075.00
MASONRY painting
82 x 2.7 = 221.40 x 2 = 442.80
26 x 2.5 = 65.00 x 2 = 130.00
Republic of the Philippines
% OF MINIMUM EQUIPMENT
DESCRIPTION OF WORK TOTAL DESCRIPTION REQUIRED
MOBILIZATION / DEMOBILIZATION 0.10% a. Backhoe (0.80 cu.m) 0
TEMPORARY FACILITIES AND BILLBOARD 0.38% b. Dump Truck (10 cu.m) 1
SAFETY AND HEALTH 0.67% c. Water Truck 1
EARTHWORKS 3.77% d. Plate Compactor 1
TERMITE CONTROL WORKS 0.09% e. Concrete Vibrator 1
CONCRETE WORKS f. One Bagger Mixer 1
Structural Concrete (Class A) 14.19% g. Bar Cutter 1
Reinforcing Steel 16.14% h. Bar Bender 1
MASONRY WORKS 8.52% i. Welding Machine (Acetylene) 1
FABRICATED MATERIALS AND HARDWARES 11.38% k. Welding Machine (ELectric) 1
FINISHING WORKS 4.33%
CARPENTRY WORKS 5.86%
ROOF AND FRAMING WORKS 23.77%
PAINTING WORKS 3.07%
ELECTRICAL WORKS 4.92%
PLUMBING / SANITARY WORKS 2.80%
MANPOWER REQUIREMENT
Project Engineer 1
Materials Engineer 1
Construction Foreman 1
Construction Safety Officer 1
100.00%
Page 1 of 2
BREAKDOWN OF EXPENDITURE
1. Labor P 507,517.36 A. Sub-Total (DC and Cont. Profit) P 3,502,401.33
2. Materials P 2,509,744.15 B. Construction Contingencies P 473,394.91
3. Rental of Equipment P 167,114.98 C. Total Construction Cost
4. Rental of Field Office D. Engineering and Admin
5. Rental of Service Vehicle Overhead (3%)
6. Direct Cost P 3,184,376.49 E. Payment of Affected
7. Contractors Profit P 318,024.85 Improvements
8. VAT P 516,853.51
9. OCM P 473,394.91
10. Sub-Total P 4,492,649.75
11. Engineering & Admin. P 148,981.34
Overhead (3%)
12. Payment of Affected
Improvements F. TOTAL ESTIMATED
13. TOTAL P 4,641,631.09 COST 3,975,796.24
previously
1
2 #REF! #REF! #REF! #REF!
3
4 #REF!
5 #REF! #REF! #REF! #REF!
P
#VALUE!
#VALUE!
#VALUE!
#VALUE!
a. Transit Mixer (5 cu.m.)
b. Concrete Vibrator
6 XIV 683.2
207969.6326
614669.75
113082.35
30001.39
- 2,502,401.3335000 338503.248
0.27 127014.532
1431924.1
674,632.34
$ 318,437.65 0.2688052252
-2,975,796.241750000000
###
$ 3,685.60
BAHINON N N2 NI
24,203.76 BALANCE
477,656.47
4,000,000.0000
140000
REVIEWED BY:
SAIDALE M. MITMUG
Engineer III / Chief, Planning & Design Section
= 13 cu.m. = ₱4,492,649.75
Total
Common Borrow = ₱500.00 per cu.m.
Sub-Total = ₱73,000.00 = ₱7,995,051.08
Hauling
= ₱148,981.34
Total Counterpart
Total = ₱797,818.85