Framework for Project Monitoring & Evaluation

Establishing List of
Cost Centers (CCTRs)

Detailed Calculation of Setting of Standard Setting of Standard


Quantities Man-hours (Mnhrs) Machine-hours (Mchrs)

Estimation of Material Calculation of Machine-


Requirements Calculation of Man-hours
Required for the Project hours and POL
Required for the Project

Updating Store with


Budgeted Material, POL Loading Materials, Mchrs
and Monthly Material & Mnhrs in Project
Requirements Schedule

Planning

Raising Material Intends Charging of Labor / Direct Execution of Project Charging of Mchrs and POL
and Issuing Materials on Manpower on Proper According to the Schedule on Proper CCTRs
Proper CCTRs CCTRS

Execution

Evaluation of: Evaluation of:


Actual Man-hours Progress Monitoring & Evaluation of POL:
Actual Materials Issued Getting Earned Values i.e. Actual Issued
vs Consumed
vs Earnable Quantities (IPC), vs
Quantities Earned or Work Payable Mnhrs (Salaries) Payable / Justifiable
Done Payable Manhours against
Work Done Payable Mchrs (Rentals) Against Work Done

Monitoring & Evaluation