Sie sind auf Seite 1von 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/250393973

Telluric Currents: A Meeting of Theory and Observation

Article  in  Corrosion -Houston Tx- · September 1998


DOI: 10.5006/1.3284894

CITATIONS READS

23 612

2 authors, including:

David Boteler
Natural Resources Canada
160 PUBLICATIONS   1,868 CITATIONS   

SEE PROFILE

All content following this page was uploaded by David Boteler on 09 March 2015.

The user has requested enhancement of the downloaded file.


~..
CORROSION ENGINEERING SECTION

Telluric Currents:
A Meeting of Theory and Observation

D.H. Boteler' and W.H. Seager.'

ABSTRACT INTRODUCTION

Pipe-to-soil (PIS)potential variations resulting from telluric Telluric current effects have been observed in
currents have been observed on pipelines in many locations. Alaska,! Canada,2-3 Norway,4 Australia,5 New
However, it has never been clear which parts ofa pipeline Zealand,6 the United States,7 and Africa.s Their
will experiencethe worst effects. Two studies were con- occunence coincides with variations in the earth's
ducted to answer this question. Distlibuted-source magnetic field. and it generally is recognized that the
transmission
ifmod l . line (DSn) theory was applied to the problem
0 e mg geomagnetic ind uc"UJn . l .mesoTh tS
"'-. m pipe . the ory tellunc cunents are dnven by '. the mduced . electric
predicted that the largest PIS potential variations would field produce~ by the changmg magnetic field. Al-
occur at the ends ofthe pipeline. The theory also predicted though at a different frequency, the processes are the
that large PIS potential variations, ofopposite sign, should same as those involved in the production of alternat-
occur on either side of an insulating flange. Independently, ing cunents lAC) in pipelines sharing a right-of-way
an observation program was conducted to determine the with a high-voltage power line. Past telluric cunent
change in teUuric current PIS potential variations and to observations have shown that problems are worse at
design counteractive measures along a pipeline in northern particular sites, but there has been no generally ac-
Canada. Observations showed that the amplitude ofPIS cepted theory to explain the greater susceptibility of
potential fluctuations had maxima at the northern and south- these locations. Pipeline surveys make successive
ern ends ofthe pipeline. Ajurther set of recordings around observations at a series of locations. Thus when
an insulating flange showed large PIS potential variations.. ..' .
if it.
0 oppos e sign, on e ith ers id eo ifth eJfI~~ ge. A greement tellunc cunents are
. observed, It often IS not possIble

between the observations and theoretical predictions was to tell whether theIr appearance resulted from a
remarkable. While the observations confimted the theory. the change of site or a change of time. Using these tech-
theory explains how PIS potential variations are produced niques, it has been impossible to determine how the
by telluric currents and provides the basis for design of pipeline potential varied along the pipe ata particu-
cathodic protection systems for pipelines that can counteract lar instant.
any adverse telluric effects. Two independent works recently have been
.. l .me the ory,
,..UJUted-source transmtSS1On
KEY WORDS : dtS", brought together and are spawning new investiga-
modeling, pipelines, soU,telluric currents tions into the effects of telluric cunents on pipelines.
Theoretical work has shown that pipeline potentials
should have a characteristic pattern resulting from
S b tied '
u m1 .or pu
bli
cation
J
une
1997
: in r
evi
se
d '
.onn.
M
arc
h telluric currents. Concurrently, some innovative mea-

1998. surements have provided the fIrst observed potential


.GeomagneticLaboratory,Geological Surveyof Canada.1 profiles along a whole pipeline. Combination of the
Observatory
..CORRPRO,
Crescent,Ottawa,Ontario.Canada.KIAOY3.
200-807ManningRoad.NE. ManningPark,Calgary. th eore ti Cal an d 0bserva ti on al wor ks has proVl.d ed th e
Alberta. basis for a new understanding of telluric current

Reprintedfrom CORROSION. Vol. 54, No.9, pp. 751-755(1998)September


Copyright1998 by NACEInternational.P.O. Box218340.Houston,Texas77218-8340
CORROSIONENGINEERINGSECTION . -

I + ~ dx If the disturbance is uniform along the pipe, then E


-!- ~ does not vary with distance (i.e., dE/dx = 0), and
these equations have solutions of the form:

V V + ~ dx I = ~ ( 1 + Ae-y(x-xI)+ Be-Y("2-x)) (6)


I I rlZo

I. dx .1 V=!(Ae-Y(X-XI)-Be-Y("2-x)) (7)
1
FIGURE. 1. Equivalent circuit for a short section of pipeline.
where A and B are constants determined by the con-
ditions at the ends of the pipeline. For a long pipeline
of length L terminated at Ends 1 and 2 by imped-
effects on pipelines and has prompted a new interna- ances to ground 2! and~, respectively, this
tional study to investigate factors influencing the becomes:
amplitude of pipe-to-soil (PIS) potential variations
produced by tellurtc currents.
I=!_le-yx_~e-y(L-x) (8)
THEORY 2 20 20

Induction in a pipeline can be analyzed using the -yx -y(L-x)


theory for a transmission line with a distrtbuted V(x)= -~e + ~e (9)
source, as shown by Taflove and Dabkowski.9 This
method has been applied to tellurtc current studies where:
by Boteler and Cookson.!o Each short section of pipe-
line is represented by a sertes impedance (2) and a E 2 E 2
parallel admittance (Y),and the induced electrtc field ~ = -1 and ~ = -2 (10)
(E) is represented by a voltage source as shown in 1 Zo+ ZI 1 20+ ~
Figure 1. Response of the pipeline depends upon the
propagation constant (oy)and charactertstic imped- These expressions show that P/S potential variations
ance (20)given by: for a long. straight pipeline will be largest at the ends
of the pipeline, fall exponentially with distance from
v1 either end. and cross through zero in the middle of
1=~,Zo= -(1) the pipeline (Figure 2). The theory also predicts that
Y the variations in V at opposite ends of the pipeline
are out of phase. In contrast, I is in phase all along
Voltage (V) and current (I) along the pipeline are the pipeline and reaches its maximum value in the
given by: center of the pipeline.

dV OBSERVATIONS
-=E-IZ (2)
dx Having shown that tellurtc currents can pose a
sertous corrosion threat to coated pipelines in the
dI auroral zone, Seager realized that it was necessary to
~ =-VY (3) develop a means to control the adverse tellurtc ef-
fect.!! To do this, two questions had to be answered:
'. -Did the telluric phase relationship remain
Differentiation and substitution leads to. constant for a length of pipeline cathodically pro-
tected by one rectifier?
d2v dE -Was there a predictable pattern for the telluric
2-'Y2y=~ (4) potential along the length of the pipeline?
dx If the answers to these questions were in the
affirmative, then the adverse tellurtc effects could be
counteracted by properly sized and located, auto-
~ -11 = -YE (5) matically controlled P/S potential rectifiers. which
dx2 are readily available in the corrosion industry.

752 CORROSION-SEPTEMBER 1998


ENGINEERING SECTION

Phase Relationship 0 Z=0.10-km Y=0.1 mho/km


During monitoring of the Norman Wells-Zama -
pipeline in northwest Canada. the phase relationship
""
of telluric variations was determined by visually com- 5' '<:
paring plots of PIS potential recordings taken ';;;' E
simultaneously at several locations, Special tests ?i 0 ~
-'-
were undertaken to determine where the predicted g <3
phase reversal would occur. This was done by leap-"j' -Voltage
frogging two PIS potential recorders by helicopter to 0 --Current
provide partially overlapping graphs of PIS potential 10 20 40 60 80 100
vs time. At two locations on each side of and near to Distance(km)
the pipeline's midpoint. PIS potential variations were
recorded. It was shown clearly that phase reversal FIGURE2. PISpotentialand telluriccurrentin a longpipeline
occurred at the midpoint. Through analysis of hun- exposedtoan inducedelectricfieldof 1 Vlkm,
dreds of recordings taken over several years. it was
shown that the phase relationship remained constant
lac t or "lor th e te11unc'
over the entire northern half of the pipeline, and .
lik ' " th tir th half proVlded a correc t Ion
'"
eWlse,lor e en e sou ern .'
magm tu des.
Thus. the telluric phase relationship remained
constant over a length of pipeline much greater than
that cathodically protected by one rectifier, Correctedtelluric magnitude = (11)
Additional tests were conducted at Wrigley ARX
Station (KP 335) where an insulating flange. normally observedtelluric magnitude xH:RX
shorted by a bond wire, was located. When the bond
was opened. the telluric potential increased substan-
tially on both sides, and a phase reversal of the This procedure was used to obtain the schematic
telluric potentials on opposite sides of the insulating telluric patterns shown in Figure 3,
flange was noted. Thus. there was a predictable pattern of telluric
intensity along the length of a pipeline.
Telluric Intensity
During periods of telluric activity (the usual COMPARISON
condition at the Norman Wells pipeline location), it BETWEEN THEORY AND OBSERVATION
was not possible to measure a single PIS potential
with any degree of confidence since the meter read- The pattern of telluric PIS potential variations
ing continually varied over a wide range of observed on the Norman Wells-Zama pipeline
potentials. To overcome this problem, recordings of showed the basic features predicted by the DSTL
the potentials were made for several minutes at theory, To allow a more detailed comparison. theo-
each location. The difference between maximum retical calculations were made specifically for the
and minimum in these recordings provided a clear Norman Wells-Zama pipeline. The pipeline was
indication of the magnitude of the telluric effect at 868 km (542 miles) long and had a series resis-
that particular time and location. Because of vari- tance of 0.028 .Q-km. The coating was assumed to
ability of the telluric effect with time, combined have a conductance per unit area of 10-5S/m2
with the usual PIS potential survey method of which. with a pipe circumference of 1 m (39 in.),
moving from test station to test station sequentially giving a parallel conductance for the pipeline of
along the pipeline, a method was devised to allow 10-2S/km. This gave values for the characteristic
comparison of the readings with elimination of the impedance of = 1.67 .Qand a propagation constant
time factor. This was made possible by continuous of 0.0167 Ikm. The exponential fall-off of the
recording of the geomagnetic field conducted at the potential at the ends of the pipeline was character-
Yellowknife Magnetic Observatory. By knowing the ized by an adjustment distance 1/'Y, which had the
exact time when each PIS potential reading was value 60 km (37 miles). Using these values in
taken and the geomagnetic activity at that time, a Equations (8) and (9) and assuming there were no
correction factor could be applied to each reading grounds at the ends of the pipeline allowed the
to create a telluric potential profile over the entire potential profile to be calculated for any specified
pipeline, which was equivalent to a Mstoppedtime" electric field (E). Figure 4 shows the potential pro-
representation. A convenient measure of geomag- file for an electric field of 1 V Ikm parallel to the
netic activity was the range of variations in each pipeline. This figure also shows the calculated
hour (HRX), The ratio of the HRX value to the potential profile for the pipeline with an insulating
average of the range values for the full year (ARX) flange at KP 335. I

CORROSION-Vol.
54,
No.9 753.
...CORROSION
-

CORROSIONENGINEERINGSECTION
\

Norman i ~ t large P /5 potential is observed. Thus. inserting an


Wells I I insulating flange in a long pipeline would only pro-
I r duce other regions where the telluric current is
I I forced to flow on and off the pipe. thus producing
: other places where lar
I J ge P /5 potential variations will
, ,be observed.
.I I Some differences between the theoretical calcula-
I I tions and the observations were revealed by
I comparison of Figures 3 and 4. For example, the
.j calculations were made assuming an electric field
;';~tT~e;: I that was uniform along the pipeline and produced
I potential variations equal and opposite at the ends of
I the pipeline. In contrast, the observations showed
larger P/5 potential variations at the northern end of
the pipeline. indicating the electric field was larger at
that end. This illustrated the need to extend the
theoretical calculations to include variations in E.
Also, the more realistic potential pattern shown in
I Figure 3(c) included potential dips to zero resulting
I from pump station grounds and rectifier drain points
I and illustrated these as features that need to be in-
I cluded in the theoretical calculations.
I

.I ~ DISCUSSION

lama I I .
..Agreement between the observations and the
(a) (b) (c) theoretical calculations has encouraged a new under-
standing of the effects of telluric currents on
FIGURE3. TelluricPISpotentialprofile obtainedfromobservations pipelines. To further this work, the Geological Survey
on the NormanWells-Zamapipeline. Curvesshowprofilefor: (a)the of Canada and an international consortium of pipe-
wholelineconnectedthroughout,(b)theline withan insulatingflange line companies are conducting a major study
at KP 335,and (c)a connectedline but includingtheeffectsof station involving multi-point observations of telluric currents
grounding. in pipelines. A set of 10 data loggers has been ac-
quired and will be used by participating companies
for potential measurements on their pipelines. This
The calculated potential proflle (Figure 4) agreed will provide a unique database of observations of
very well with the potential profile derived from ob- telluric current effects on pipelines. As well as pro-
servations (Figure 3). Both showed the characteristic viding time variations of the potentials for correlation
5 shape, with potential variations at one end of the with recording of magnetic field variations, it will
pipeline having the opposite sign to those at the provide snapshots of the potential proflle along the
other end. The theoretical calculations also correctly pipe that will provide the first quantitative pictures of
reproduced the observed effect of the insulating the spatial variation of the telluric current potentials.
flange. This agreement showed the DSTL theory can In parallel with the observation program. the
be used to provide the theoretical framework for un- international study will include work to extend the
derstanding telluric potential observations. theory to deal with more complicated pipeline net-
The theory shows that an electric field drives a works. The present DSTL theory is only applicable to
current along the length of the pipeline (Figure 2). single pipelines with resistive terminations, and there
This produces a movement of electrical charge away is a need to extend the theory to include active termi-
from one end and a buildup of charge at the other nations, which would allow modeling of multiple
end, resulting in the S-shaped potential profile ob- pipeline sections. Representing a pipe by 7t-sections
served. At one end, the negative potential of the pipe has been found useful in modeling AC induction in
with respect to the ground causes a current to flow pipelines. and it will be seen if this approach can be
onto the pipe; whereas at the other end, the positive used to model telluric currents. The aim of this work
potential causes the current to leave the pipe. is to develop methods that will be able to handle
A large telluric current also is seen in the middle small-scale variations in pipeline characteristics that
of the pipeline where the P/5 potential is small. It is would allow modeling of actual pipelines and provide
only where the telluric current is caused to flow to a versatile modeling scheme for examining the
ground, such as at the end of the pipeline. that a response of pipelines to telluric currents.

754 CORROSION-SEPTEMBER 1998


CORROSIONENGINEERINGSECTION

Therefore, it will be possible to predict telluric g


potentials and to design rectifiers of suitable voltage
~-
"C::-
o
and current capacity to counteract any adverse ~ In
effect. The optimum rectifier locations may be prede- "'550
termined not only for t athodic protection purposes ~
.0
but also to ensure that "the proper phase relation- (Q ~
ships are maintained C)ver the rectifier's area of a..g
influence. ':- 0 100 200 300 400 500 600 700 800
The present result5 provide some guidance for Distance (km)
the design of cathodic protection systems. For ex- (a)
ample. it is apparent that a telluric counteracting
rectifier cannot be located at or near the phase rever- 0
0
sallocation. To do so would reduce the telluric effect ~ -

on one side but would increase telluric variations on ~ ~


the other side. Thus, a rectifier, primarily for ~
cathodic protection bu"t also to counteract telluric c: 0
l}.
must be located so that jts significant area of influ- & 0
ence does not extend a.cross a telluric phase reversal ~:
point. * 0 100 200 300 400 500 600 700 800
Distance (km)
CONCLUSIONS (b)

.:. Independently obtai:I1ed theoretical calculations FIGURE4. Resultsof DSTL modelingfor the Norman Wells-Zama
and observations oftbe telluric potential profile on a pipeline: (a)assuminga straight electricallycontinuouspipeline and
long pipeline showed rl?-markable agreement. This (b)for a pipeline with an insulatingflangeat KP 335.
meeting of theory and observation is helping to pro-
duce a new understanding of telluric current effects
on pipelines.
.:. An international study has been implemented to REFERENCES
make multi-point observations of telluric currents, to
extend the theory and to test the theoretical predic- 1. A. Smart. IEEETrans.Ind. Appl. 1A-18(1982):p. 557-567.
tions in a variety of pipeline situations. It is hoped 2. G.I. Russell.L.B. Nelson.Corrosion10 (1954):p. ~OO. "
3. R Shapka. "Geomagnetic Effects on Modem Pipeline Systems.
that this work will lead to the capability to simulate Proc. Solar-Terrestrial Predictions Workshop. Ottawa. Canada.
the telluric currents in pjpeline networks and to pre- May18-2~. 1992(Bo~der.CO: NOAA.1993)..
deslgn. ca
th
0
d .
lC pro
t
ec
-to';
,-,on sys
t
ems
th
a
t al
so can
4. J.F.
sion
Henriksen.
on Buried
R ElVik.
PipelInes."
L. Granasen.
Proc. 8th
-rellunc
Scand.
Current
Corros. Cong..
Corro-

counteract any adverse telluric effect. Helsinki.Finland.NKM8.vol. 2 (Helsinki.Finland:Univ. of


Technology.1978).p. 167-176.
ACKN OWLEDGMENTS 5. B.A.Martin. Corrosion49 (1993):p. 343-350.
6. T.G.Proctor.MP 13 (1974):p. 24-30.
7. D.N.Gideon.MP 10(1971):p. 5-10.
The authors acknowledge the assistance of lnter- 8. R.H.Barker.N.J. Skinner. MP 19 (1980):p. 25-28.
9. A. Taflove.J. Dabkowski. IEEE Trans. PowerApp. Sys. PAS-98
provincial Pipelines, Ltd., in granting permission to (1979): p. 780-794.
publish results for the Norman Wells-Zama pipeline 10. D.H. Boteler. M.J. Cookson. MP 25. 3 (1986): p. 27-32.
..11. W.H. Seager. "AdverseTelluric Effects on Northern Pipelines."
and of the Geological Survey of Canada under contri- Int. ArcticTechnol.Conf..Anchorage.Alaska. May29-31. 1991
bution no. 1,996,435. (Richardson.TX:SPE.1991).

CORROSION-Vol. 541,No.9 Printedin U.S.A. 755


View publication stats

Das könnte Ihnen auch gefallen