ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10
1 A DISTANCE LEARNING CENTRE 175 days Wed 10/07/19 Wed 05/02/20
2 Project Procurement 52 days Mon 26/08/19 Sat 26/10/19
3 Oversees procurement and logistcs 52 days Mon 26/08/19 Sat 26/10/19
4 Shipment of MEP and IT equipment, materials and proprietary 45 days Mon 26/08/19 Thu 17/10/19
accessories
5 Shipmet of tiles,carpet,Aluminium profiles,glass glazing 52 days Mon 26/08/19 Sat 26/10/19
materials,gypsum board and demountable suspended ceiling
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 1
BP DLC WORK SCHEDULE
ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10
38 Reinforcement rebars 6 days Thu 26/09/19 Wed 02/10/19
39 Casting 1 day Thu 03/10/19 Thu 03/10/19
40 Curing and stripping of formwork 5 days Sat 26/10/19 Wed 30/10/19
41 Parapet and Skydom 3 days Sat 05/10/19 Mon 07/10/19
42 Parapet and Skydom 2 days Sat 05/10/19 Sun 06/10/19
43 Reinforcement rebars and formwork 1 day Mon 07/10/19 Mon 07/10/19
44 Casting of parapet walls and roof lights 1 day Mon 07/10/19 Mon 07/10/19
45 Roof waterproof 44 days Tue 08/10/19 Sat 30/11/19
46 Concrete for slope shape 2 days Tue 08/10/19 Wed 09/10/19
47 Water proofing 3 days Sat 12/10/19 Mon 14/10/19
48 Skydom 2 days Wed 20/11/19 Thu 21/11/19
49 Fixing solar panels and lightning rod 8 days Wed 20/11/19 Sat 30/11/19
50 Maconery 33 days Tue 08/10/19 Sat 16/11/19
51 Peripheral masonry and insulation 22 days Tue 08/10/19 Sat 02/11/19
52 Interior masonry 12 days Sat 02/11/19 Sat 16/11/19
53 MEP & IT and Installation -First Fix 15 days Sun 03/11/19 Wed 20/11/19
54 Cable installation path, Prewiring small power and data casing 15 days Sun 03/11/19 Wed 20/11/19
and tubing + electrical panal
55 Distribution piping installation 15 days Sun 03/11/19 Wed 20/11/19
56 Air conditioning duct 15 days Sun 03/11/19 Wed 20/11/19
57 Surface Finishes 56 days Wed 16/10/19 Sun 22/12/19
58 Wall covering (interior and exterior plastering) 34 days Wed 16/10/19 Mon 25/11/19
59 Ceiling 6 days Sat 23/11/19 Sat 30/11/19
60 Floor screed 9 days Sat 30/11/19 Mon 09/12/19
61 Carpet tiling 9 days Tue 10/12/19 Thu 19/12/19
62 Painting 10 days Wed 11/12/19 Sun 22/12/19
63 MEP, IT and other Building Services Installation 21 days Thu 05/12/19 Sun 29/12/19
64 HVAC, Electrical and lighting system final installation 21 days Thu 05/12/19 Sun 29/12/19
65 Fire protection system installatin 21 days Thu 05/12/19 Sun 29/12/19
66 Plumbing fixtures 21 days Thu 05/12/19 Sun 29/12/19
67 Communication & Security control system 21 days Thu 05/12/19 Sun 29/12/19
68 Windows Doors and Roof lights and stairs 21 days Thu 05/12/19 Sun 29/12/19
69 Aluminium windows 21 days Thu 05/12/19 Sun 29/12/19
70 Glazed sceen system 21 days Thu 05/12/19 Sun 29/12/19
71 Aluminim Metal louvres 21 days Thu 05/12/19 Sun 29/12/19
72 Wooden doors 21 days Thu 05/12/19 Sun 29/12/19
73 Handrails 21 days Thu 05/12/19 Sun 29/12/19
74 Iron mongery 21 days Thu 05/12/19 Sun 29/12/19
75 Disposal System 40 days Sat 05/10/19 Wed 20/11/19
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 2
BP DLC WORK SCHEDULE
ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10
76 Above ground drainage system 10 days Sat 05/10/19 Tue 15/10/19
77 Sewarage Tanks,manholes and inspection chambers 10 days Wed 16/10/19 Sun 27/10/19
78 Sewarge pump 10 days Mon 28/10/19 Thu 07/11/19
79 Stom water Drainage 10 days Sat 09/11/19 Wed 20/11/19
80 Loose Funitures ,sinage,fall arresor and Kitchenware 3 days Thu 05/12/19 Sun 08/12/19
81 Roof access Fall arrestor system 3 days Thu 05/12/19 Sun 08/12/19
82 Inspection & close out 33 days Mon 30/12/19 Wed 05/02/20
83 Final clean 10 days Mon 30/12/19 Thu 09/01/20
84 Provisional acceptance 3 days Sat 11/01/20 Mon 13/01/20
85 Commissioning and training 20 days Tue 14/01/20 Wed 05/02/20
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 3
BP DLC WORK SCHEDULE
Feb '20 Mar '20 Apr '20 May '20 Jun '20 Jul '20 Aug '20 Sep '20 Oct '20 Nov '20 Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21
10 17 24 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12