BP DLC WORK SCHEDULE

ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10
1 A DISTANCE LEARNING CENTRE 175 days Wed 10/07/19 Wed 05/02/20
2 Project Procurement 52 days Mon 26/08/19 Sat 26/10/19
3 Oversees procurement and logistcs 52 days Mon 26/08/19 Sat 26/10/19
4 Shipment of MEP and IT equipment, materials and proprietary 45 days Mon 26/08/19 Thu 17/10/19
accessories
5 Shipmet of tiles,carpet,Aluminium profiles,glass glazing 52 days Mon 26/08/19 Sat 26/10/19
materials,gypsum board and demountable suspended ceiling

6 Loose Funitures and Kitchenware 52 days Mon 26/08/19 Sat 26/10/19


7 Main Construction Works 175 days Wed 10/07/19 Wed 05/02/20
8 Structural frame 175 days Wed 10/07/19 Wed 05/02/20
9 Subsructure 41 days Wed 10/07/19 Thu 29/08/19
10 Excavation 4 days Wed 10/07/19 Sun 14/07/19
11 Excavation of base pits and strip foundation 3 days Wed 10/07/19 Sat 13/07/19
12 Compaction 1 day Sun 14/07/19 Sun 14/07/19
13 Fundation 32 days Sun 14/07/19 Thu 22/08/19
14 Blinding concrete to foundation trenchs and column base 2 days Sun 14/07/19 Mon 15/07/19
15 Marking 1 day Tue 16/07/19 Tue 16/07/19
16 Polyane film 2 days Wed 17/07/19 Thu 18/07/19
17 Reinforcement rebars 12 days Thu 18/07/19 Wed 31/07/19
18 Formwork for trenches and column base 15 days Thu 18/07/19 Sun 04/08/19
19 Pipes (electricity / plumbing) to form pockets inside beams 3 days Thu 01/08/19 Sun 04/08/19
20 Casting of ground slab to -0,15m 1 day Sat 03/08/19 Sat 03/08/19
21 Casting of ground beams 1 day Sun 04/08/19 Sun 04/08/19
22 Curing and stripping of formwork 3 days Mon 05/08/19 Wed 07/08/19
23 Water proofing for beams 2 days Thu 08/08/19 Sat 10/08/19
24 Surface treatment /herbicide-pesticide 2 days Wed 14/08/19 Thu 15/08/19
25 Backfill around trenches and stub colums 6 days Sat 17/08/19 Thu 22/08/19
26 Ground Slab 6 days Sat 24/08/19 Thu 29/08/19
27 Reinforcement rebars 4 days Sat 24/08/19 Tue 27/08/19
28 Truncking, floor and wall socket boxes and juction boxes 4 days Mon 26/08/19 Thu 29/08/19
29 Formwork and concrete casting 1 day Wed 28/08/19 Wed 28/08/19
30 Up Structure 132 days Tue 03/09/19 Wed 05/02/20
31 Columns and Walls 12 days Tue 03/09/19 Mon 16/09/19
32 Marking of columns & walls 2 days Tue 03/09/19 Wed 04/09/19
33 Columns & walls formwork and Reinforcement rebars 7 days Wed 04/09/19 Wed 11/09/19
34 Columns & walls Concrete Casting 1 day Thu 12/09/19 Thu 12/09/19
35 Curing and stripping of formwork 3 days Sat 14/09/19 Mon 16/09/19
36 ROOF SLAB 38 days Tue 17/09/19 Wed 30/10/19
37 Formwork of roof slab 8 days Tue 17/09/19 Wed 25/09/19
Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress

Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
BP DLC WORK SCHEDULE
ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10
38 Reinforcement rebars 6 days Thu 26/09/19 Wed 02/10/19
39 Casting 1 day Thu 03/10/19 Thu 03/10/19
40 Curing and stripping of formwork 5 days Sat 26/10/19 Wed 30/10/19
41 Parapet and Skydom 3 days Sat 05/10/19 Mon 07/10/19
42 Parapet and Skydom 2 days Sat 05/10/19 Sun 06/10/19
43 Reinforcement rebars and formwork 1 day Mon 07/10/19 Mon 07/10/19
44 Casting of parapet walls and roof lights 1 day Mon 07/10/19 Mon 07/10/19
45 Roof waterproof 44 days Tue 08/10/19 Sat 30/11/19
46 Concrete for slope shape 2 days Tue 08/10/19 Wed 09/10/19
47 Water proofing 3 days Sat 12/10/19 Mon 14/10/19
48 Skydom 2 days Wed 20/11/19 Thu 21/11/19
49 Fixing solar panels and lightning rod 8 days Wed 20/11/19 Sat 30/11/19
50 Maconery 33 days Tue 08/10/19 Sat 16/11/19
51 Peripheral masonry and insulation 22 days Tue 08/10/19 Sat 02/11/19
52 Interior masonry 12 days Sat 02/11/19 Sat 16/11/19
53 MEP & IT and Installation -First Fix 15 days Sun 03/11/19 Wed 20/11/19
54 Cable installation path, Prewiring small power and data casing 15 days Sun 03/11/19 Wed 20/11/19
and tubing + electrical panal
55 Distribution piping installation 15 days Sun 03/11/19 Wed 20/11/19
56 Air conditioning duct 15 days Sun 03/11/19 Wed 20/11/19
57 Surface Finishes 56 days Wed 16/10/19 Sun 22/12/19
58 Wall covering (interior and exterior plastering) 34 days Wed 16/10/19 Mon 25/11/19
59 Ceiling 6 days Sat 23/11/19 Sat 30/11/19
60 Floor screed 9 days Sat 30/11/19 Mon 09/12/19
61 Carpet tiling 9 days Tue 10/12/19 Thu 19/12/19
62 Painting 10 days Wed 11/12/19 Sun 22/12/19
63 MEP, IT and other Building Services Installation 21 days Thu 05/12/19 Sun 29/12/19
64 HVAC, Electrical and lighting system final installation 21 days Thu 05/12/19 Sun 29/12/19
65 Fire protection system installatin 21 days Thu 05/12/19 Sun 29/12/19
66 Plumbing fixtures 21 days Thu 05/12/19 Sun 29/12/19
67 Communication & Security control system 21 days Thu 05/12/19 Sun 29/12/19
68 Windows Doors and Roof lights and stairs 21 days Thu 05/12/19 Sun 29/12/19
69 Aluminium windows 21 days Thu 05/12/19 Sun 29/12/19
70 Glazed sceen system 21 days Thu 05/12/19 Sun 29/12/19
71 Aluminim Metal louvres 21 days Thu 05/12/19 Sun 29/12/19
72 Wooden doors 21 days Thu 05/12/19 Sun 29/12/19
73 Handrails 21 days Thu 05/12/19 Sun 29/12/19
74 Iron mongery 21 days Thu 05/12/19 Sun 29/12/19
75 Disposal System 40 days Sat 05/10/19 Wed 20/11/19

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress

Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
BP DLC WORK SCHEDULE
ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10
76 Above ground drainage system 10 days Sat 05/10/19 Tue 15/10/19
77 Sewarage Tanks,manholes and inspection chambers 10 days Wed 16/10/19 Sun 27/10/19
78 Sewarge pump 10 days Mon 28/10/19 Thu 07/11/19
79 Stom water Drainage 10 days Sat 09/11/19 Wed 20/11/19
80 Loose Funitures ,sinage,fall arresor and Kitchenware 3 days Thu 05/12/19 Sun 08/12/19
81 Roof access Fall arrestor system 3 days Thu 05/12/19 Sun 08/12/19
82 Inspection & close out 33 days Mon 30/12/19 Wed 05/02/20
83 Final clean 10 days Mon 30/12/19 Thu 09/01/20
84 Provisional acceptance 3 days Sat 11/01/20 Mon 13/01/20
85 Commissioning and training 20 days Tue 14/01/20 Wed 05/02/20

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress

Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
BP DLC WORK SCHEDULE
Feb '20 Mar '20 Apr '20 May '20 Jun '20 Jul '20 Aug '20 Sep '20 Oct '20 Nov '20 Dec '20 Jan '21 Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '21
10 17 24 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress

Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4