Sie sind auf Seite 1von 10

Job Hazard Analysis

Job Description: Start Date: Finish Date:


TREE CUTTING, FELLING & BALLING
Task to be accomplished (Mga dapat gawin)
Steps To Take To Hazards Required Actions To Eliminate Or
Complete Task (Mga Panganib) Control The Hazard
(Mga Hakbang (Mga aksyon upang maalis o makontrol ang
upang panganib)
makumpleto ang
gawain)

- Provision of enough signages to guide the


-Falling workers about the hazards & control to be
MOBILIZATION OF (Materials fall down) made including the correct access
EQUIPMENT & and Tossing of Objects &/or locations
MATERIALS Debris
-Ground full of debris - Ensure assigned safety man to focus on
Safety Control only
RESULTS:
People: sprain, strain, laceration - Barricade possible extent of working and
Adjacent Properties / Job affected area
Process:
- Disruption, Disturbed quality living - Ensure back up of housekeeping team to
of adjacent properties/neighborhood/ help during activity execution - maintain
business extent of affected area to prevent
additional hazards to others

'- Slip & trips - Assess initially the path needed to take
- fall into the ground before handling a material
- being trapped
HAULING JOBS - Eliminate and control any possible
RESULTS: obstruction before and during the activity
(MANUAL People: sprain, strain, laceration
HANDLING) Adjacent Properties / Job - Provide a guide / spotter if necessary
Process: If obstructions are structures, ensure to be
Disruption, Disturbed quality living familiar to the path to eliminate additional
of adjacent properties/neighborhood/ risk
business - Train the workers for proper manual
Cracks, loose soils hauling technique
Prolonged work execution - Identify the weight of the materials to be
hauled do tandem lift if necessary

Page: 1 of 7
Job Hazard Analysis

- Hit by/hit against - Ensure a good equipment condition to


- Struck by/struck against minimize the produced by products
HEAVY - Contact with Machinery
EQUIPMENT and - Caught into - Exposure of personnel should be
OTHER - Run over by minimized
EQUIPMENT - Presence of available spare parts and
OPERATIONS RESULTS: Body Injury, Death
servicing personnel
PEOPLE: contusion, fracture, - Ensure that all workers have reflectorized
laceration, avulsion, death vest especially the Rigger and to give
proper signaling,
- Ensure that the Rigger are trained and
knowledgeable
- Don't go under the boom when the crane is
operating wait for the signal of Rigger and
Spotter

- Fall - Set up guidelines for elevated works


- Hit against applicable to the actual condition
- Struck into
- Availability of materials for fall prevention
RESULTS: control
ELEVATED JOBS contusion, fracture, avulsion, death
- Trained individual to be involved in the job
MATERIAL/ADJACENT
PROPERTIES: rupture, vent, - Do not store Equipment on working
cracks, scratches platforms. Area below must clear from
personnel. Working platform must have
handrails and edge protection

- Set up exclusion zone, barricade the area,


put enough signage and observed 100 % tie
off

Page: 2 of 7
Job Hazard Analysis

'- Electrocution - De-Energized and Lock Out/Tag out


- Physical Injuries Electrical Circuit/parts you will be working on
- Electrical Shock - Have an area outline with all the facilities
- Trip, Slip, Fall determined with location - All personnel
- Cut involved must have electrical safety/LOTOTO
RESULTS: Training
People: sprain, strain, laceration,
Fatality - Assess initially the path needed to take before
Adjacent Properties / Job Process: handling a material -
- Disruption, Disturbed quality living Follow permit to work system procedures
of adjacent properties/neighborhood/ - All temporary power supply must be
business remove/installed by a competent person
- Prolonged work execution - Personnel shall ensure that suitable PPE's is
worn at all times when handling sharp or
REMOVAL OF otherwise potentially hazardous materials
CABLES AND - Ensure that a safe system of work is
WIRES/ implemented so as to reduce the possibilities of
CONTACT WITH accidents/incidents caused by a lack of
DOWNED LINES communication.
AND LIVE
ELECTRICAL - Ensure that tree trimming operations to clear
EQUIPMENT AND electrical lines are performed only by qualified
OTHER UTILITIES line-clearance tree trimmers. A qualified line-
(E.G., GAS, clearance tree trimmer is knowledgeable in the
WATER) construction and operation of electric power
generation, transmission, or distribution
equipment involved, along with the associated
hazards

- Closely inspect trees for electrical conductors


passing through or within reaching distance of
workers before beginning tree work
- Consider all electrical power conductors to be
energized and not to be directly or indirectly
(e.g., through tools, branches, or other
equipment) touched
- Assume that electrical lines are energized
until proven otherwise. Lines and other
conductors may become re-energized without
warning as utilities are evaluated and restored
after a disaster
- Inspect the work area for downed conductors
and do not go near, drive over, or otherwise
come in contact with them

Page: 3 of 7
Job Hazard Analysis

- Downed electrical conductors can energize


other objects, including fences, water pipes,
bushes, trees, and telephone/CATV/fiber optic
cables
- Unless deenergized and visibly grounded,
maintain proper distance from overhead
electrical power lines (at least 10 feet) and/or
provide insulating barriers
- Do not approach any gas leaks; if a gas leak
is detected, secure spark-producing devices
(e.g., engines, tools, electronic, and
communications equipment) and evacuate the
area until the leak is secured

- Contact utility company to assist in locating,


marking, and shutting off/purging utility lines
that may pose a hazard or may be impacted;
ensure that lines have been purged as needed
before beginning work

-Ground full of debris - Provision of enough signages to guide the


- Slips and trips workers about the hazards & control to be
- Fall (same level of the ground) made including the correct access locations
- Struck into
PREPARATION - Ensure assigned safety man to focus on
FOR TREE RESULTS: Safety Control only
CUTTING/FELLING sprain, wounds, bruises,
/BALLING contusion, abrasion, puncture, stab - Barricade possible extent of working and
wounds affected area

- Ensure back up of housekeeping team to help


during activity execution - maintain extent of
affected area to prevent additional hazards to
others

Page: 4 of 7
Job Hazard Analysis

- Entasked a competent person to monitor


- Falling into adjacent area general condition
- Soil Disruption
- Collapse - Install suitable supports to brace affected
- Flooding/water penetration areas, should be designed also by a competent
person
RESULTS:
TREE BALLING People: soft tissue and bone injuries, - Advise relative authority regarding possible
EXCAVATION suffocation, death extent and phase of the activity
(MANUAL Material/Adjacent Properties: - Install signages informing public about the
EXCAVATION) mislay foundation activity
Environment
Unstable ground - Barricade area/zone of influence
- If necessary, provide walk zone for general
public 1 meter away from the zone of
influence

- Schedule and ensure proper removal of


excavated materials

Page: 5 of 7
Job Hazard Analysis

- Fence the work location to control - Provision of signages, strategically at the


the hazards noted; ensure that the highly potential areas.
fence compensates with the impact
of the hazard - Install enough fences and provide additional
protection for adjacent properties if necessary
- Methods of proper demolition
should be ready for discussion during - Issue complete Personal Protective
morning meeting to limit the listed Equipment for personnel involved and to those
hazards to do inspection from time to time.

- Off-set the highly critical areas from workers


- The fence should be designed to
minimize the environmental impact -Start saw on ground with foot on rear handle,
affecting near-by structure left hand firmly gripping saw grip, right hand
pulling starter cord. Maintain secure footing.

- Wear gloves, hard hat, chaps, sturdy work


TREE CUTTING boots. Saws weighing less than 15 pounds may
be drop started. Make sure, co-workers are
clear of saw.

-Maintain awareness of work areas; check


barricades; do not approach operators; shout
warnings to co-workers and bystanders.

- Control a quality condition of - Barricade possible entry that is too close to


heavy equipment to use to minimize work condition
the impact
- Position signage strategically that it can also
- Properly control the working hours provide proper information to project
personnel and others that may be affected.
- Improve process to control both
- Gather information from general affected
waste and dust
personnel for any schedule that construction
team needs to offset due to the environmental
impact

- Ensure availability of materials & equipment


to haul generated solid waste

- Avoid stock up of generated solid waste

- Use all necessary PPE's against the hazard

Page: 6 of 7
Job Hazard Analysis

- Prepare tree for felling (cut off low


Personal Injury: branches).
- Crushing
- Being hit by falling object - Ensure no persons in fall area.
- Hit by moving vehicle - Use agreed communication (eg: radio, hand
- Slips, trips, falls signals and/or whistles).
- Death
- During trimming, keep non-essential
response and recovery workers at least 20
feet beyond expected drop zones during
trimming
- During felling, designate work area so that
trees cannot fall into an adjacent occupied
work area. Adjacent occupied work areas
should be at least two treelengths from the
tree being felled (allow more if it is
reasonably foreseeable that the tree might roll
or slide)
- Always plan a clear path of retreat before
TREE FELLING cutting
- Determine the felling direction and how to
deal with forward, back, and/or side lean
- Determine the proper hinge size to safely
guide the tree in its fall-◾If tree is broken
and under pressure, make sure you know
which way the pressure is going. If not sure,
make small cuts to release some of the
pressure before cutting up the section
- - Be careful of young trees that other trees
have fallen against; they act like spring poles
and can propel back
- - If you have to cut a dead tree, be careful:
the top could break off
- - If possible, avoid felling trees into other
trees or objects; branches and objects may
get thrown back toward the tree cutter

Page: 7 of 7
Job Hazard Analysis

- Once back cut taken up and tree begins to


fall: use agreed communication to signal fall
- Hit by/Struck by a material remove saw and switch to off (this allows
- Caught into/trapped operator to hear) move to planned escape
(from falling debris and/or route
something collapsing)
- watch for falling debris
RESULTS:
People: contusion, abrasion, - watch for kickback/bounce.
avulsion, laceration, fracture - For much larger trees – use quarter cutting
Materials/Adjacent properties: techniques:
cracks, scratches, tear off and breaks,
TREE FELLING - cut scarf as normal
total wreckage
- plan cut (mark felling cuts on map or tree)
- select side of tree for first cut (if rot or lean
- If not, do not approach tree in direction of
fall
- Hung-up:
- Use machine
- Do not approach in direction of fall
- If manually – use can’t hook or levering
device to dislodge.
- Note: Do not leave trees in cut-up or hung-up
position
unless barricading and clearly signing the
area to prevent persons entering.

'- drop off material - Identify the weight of the materials to be


hauled
- forceful lifting
DISPOSAL OF -Ensure equipment use for transferring
MATERIALS - Struck by materials are in good condition
-Be aware of overhead obstructions & your
- Hit by surrounding at all times
- Ensure Proper handling of materials
RESULTS:
- Keep visual or audio contact with rigger
People: contusion, abrasion, avulsion, (pick up & landing points) at all times
laceration, fracture

Page: 8 of 7
Job Hazard Analysis

- Transfer the cut trees at accredited area


(Environmental Impact) endorsed by DENR for proper disposal
- Dust - Proper segregation of materials/waste
- Debris/solid Waste materials
- Cut tree - Dumped hauled treed on the area approved
by Municipal Government
''- Barricade possible entry that is too close to
work condition

DISPOSAL OF - Position signage strategically that it can also


MATERIALS provide proper information to project
personnel and others that may be affected.
- Gather information from general affected
personnel for any schedule that construction
team needs to offset due to the environmental
impact

- Ensure availability of materials & equipment


to haul waste
- Avoid stock up of waste
- Use all necessary PPE's against the hazard

- Poor materials arrangement slips - Good housekeeping shall perform before,


Post Work and trip. Hand injury & during and after. Ensure workers must have
ergonomic injuries complete Protective equipment.

Page: 9 of 7
Job Hazard Analysis

This JHA must be reviewed with all workers involved prior to starting any work.
(Bago umpisahan ang anumang trabaho, ang JHA na ito ay dapat masuri kasama ang lahat ng
manggagawa

Work Supervisor: ALFRED PATI-AN/ROEFI COLIMA/ABAD


MIRHAN/JOANNABLE SALALILA

Workers: JOEY CARANES


MARK JOHN DELA CRUZ
ERSON RIVAS
ESON MINGOY _
MAR BENHUR SAULOG

Page: 10 of
7

Das könnte Ihnen auch gefallen