Beruflich Dokumente
Kultur Dokumente
net/publication/251955958
CITATIONS READS
17 386
1 author:
SEE PROFILE
All content following this page was uploaded by Andre Luiz Diniz on 16 July 2014.
markets.
Abstract — Generation scheduling and other types of Four test cases were created, whose transmission data are
optimization problems for hydrothermal systems have been taken from the 24, 57, 118 and 300-bus IEEE-based test
studied for more than 60 years. A large number of algorithms systems. Generation buses of each system were linked to a set
and solving strategies have already been proposed in the
of hydro and thermal units. Hydro data are based on some
literature. Despite of this huge amount of publications, we still
lack the existence of standardized test systems that can be used characteristics of the hydro plants of the real Brazilian system
to benchmark the performance and solution quality of so many and include, for example, cascaded reservoirs, water delay
proposed techniques. In this sense, this paper proposes some test times, and hydro plants input-output curves [7]. Most of the
cases that can be used to unit commitment and hydrothermal thermal unit commitment data are taken from [8].
scheduling problems both in regulated and deregulated markets. This paper is organized as follows: from sections II to IV
Electrical network data are taken from the 24, 57, 118 and 300-
we describe the hydro data, thermal data, and transmission
bus IEEE-based test systems, which were fictitiously linked to a
set of up to 20 thermal units and more than 100 hydro units. data, respectively. Time and case-dependent data are
Hydro data are based on the real Brazilian system and include described in section V. In section VI we formulate the short
cascaded reservoirs, water delay times, and hydro plants input- term hydrothermal scheduling problem as considered in this
output curves. Thermal data are taken from the literature. paper. In section VII we present the hydro and thermal
Index Terms-- Hydrothermal scheduling, Unit commitment, configurations for each test case. The Appendix section lists
Test cases.
all hydro and thermal related data. Transmission system data
is given in [9]. Finally, in section VIII we state the
I. INTRODUCTION
conclusions of this work and some recommendations for the
• Fourth degree polynomials for the forebay level ( hup ) as a of startup and shutdown curves is presented in [13], [14].
function of storage (V) and for the tailrace level ( hdn ) as a IV. TRANSMISSION NETWORK DATA
function of the sum of turbined (Q) and spillage (S) Transmission data are taken from the well known 24-bus,
outflows, as described in expressions (1) and (2): 57-bus, 118-bus and 300-bus IEEE test systems. In this paper
hup = a0 + a1V + a 2V 2 + a3V 3 + a 4V 4 (1) we focus on the necessary data for a dc representation of the
electrical network, as listed below:
hdn = b0 + b1 D + b2 D 2 + b3 D 3 + b4 D 4 , (2) • A set of buses, labeled from 1 to NB, and a set of NL
where D = Q+S. transmission lines. The extreme buses of each line i are
denoted by fr(i) and to(i) ;
C. Hydro units data
• Reactance (x), resistance (r) and flow capacity ( f ) of
These data comprise physical characteristics for each of
each line;
the nhi hydro units of a hydro plant i, as follows:
• Φ T i / Φ H i : index set of thermal / hydro plants connected to
• upper bound for turbined outflow ( q ) and generation
each bus i;
( gh );
• penstock head losses (lh) in % of the net head; V. TIME-DEPENDENT DATA
• average generation efficiency (η), per unit of water head
The data from sections IV to VI refer to static data related
and turbined outflow (MW/((m3/s).m)).
From these data we can compute the power generation gh to physical characteristics of the system. In this section we
of a hydro unit as a multivariate function of its turbined list the set of data whose values are time-dependent, since
outflow q, the storage V in the reservoir, and the total plant they may vary along the day, week or season of the year. In
outflow Q+S, as follows: the specific case of the STHTS problem considered in this
gh = HPF (V , q, Q, S ) = work, the following data are necessary:
(3) • Time discretization: the horizon of study is divided into
= min{gh ; η ρ q[hup (V ) − hdn (Q, S )] lh }. T time steps, each one with duration Δti.
The generation GH of the whole plant is given by the sum of • Initial storage of the reservoirs;
the generation of all its units: t
• Water inflows I i to each hydro plant i at each time step t;
nh i
(4)
∑
GH = gh
j =1
j
t
• load d i of each bus i at each time step t;
Hydro data can be further refined in order to express q , • Coordination with mid term planning is done by setting
gh and lh as nonlinear functions of the water head [10], [11] storage limit targets ViT and ViT for the reservoirs at the
and η as a hill-shaped function of the net head and the end of the time horizon; Alternatively, water values for the
turbined outflow [12]. reservoirs could be given [7].
III. THERMAL DATA VI. PROBLEM FORMULATION
In this paper the data for each thermal unit include:
This paper considers the network constrained short term
• lower and upper bounds ( gt , gt ) for generation;
hydrothermal scheduling problem (STHTS), taking into all
• thermal generation cost as a quadratic function of power physical and operation constraints described from sections II
generation gt, as follows: to V. The aim is to determine the optimal generation of hydro
c( gt ) = c0 + c1 gt + c2 gt 2 ; (5) and thermal units of the system, taking into account several
• startup costs, as an exponential function of the time the physical and operational constraints on hydro units, thermal
unit has been “off”: units and transmission lines, and minimizing a given
( )
−β t
cst (toff ) = chot + (ccold − chot ) 1 − e off (6) objective function.
In the case of a cost minimization objective function, the
• minimum time the unit has to remain “on” before shutting problem comprising all the data presented in the paper can be
down (ton), and minimum time the unit has to remain “off” formulated as follows:
(toff), before being started again;
∑∑ [c ( gt ) + u (1 − u ]
T NT
• duration of the shutdown and startup processes (tdn and tup, min i
t
i
t
i
t −1
i
t
)cst (toff i ) (7a)
respectively); t =1 i =1
of hydro plants immediately upstream plant i; Ω L is the set plant # unit # bus # plant # unit # bus #
i
18 19 20
14 15 16 17
21
Figure 2 – Hydro plants configuration for the 57-bus STHTS test case.
22
The connection of each hydro unit to the electrical
network is shown in Table VI. Figure 3 – Hydro plants configuration for the 118-bus STHTS test case.
5
This is the largest case, composed of 32 hydro plants (with Unit # bus # gt gt
a total of 150 hydro units), 20 thermal units, and a network of
1,2 98 8,9,10,20 164
300 buses and 409 branches.
1) Hydro configuration 3 88 11,12 170
The hydro configuration is composed by all hydro plants 4 128 13 222
in Fig. 1 and Fig. 3 in addition to the hydro plants from # 23 5,6 261 14,15,16,17 247
to 32 shown in Fig. 4 below. The connections to the electrical 7 125 18,19 293
network are shown in Table XIV.
6
not require that all features of the STHTS problem considered 18 3.0011e+02 1.8949e-02 -7.7661e-06 2.0558e-09 -2.1199e-13
in this paper must be taken into account. One can represent 19 2.7989e+02 - - - -
only the data and constraints that can be handled by his 20 1.8400e+02 - - - -
application. In this sense, it would be useful to derive several 21 8.2202e+02 3.3634-01 -2.7850e-03 1.6027e-05 -3.7995e-08
variants of each test case, obtained by weather or not 22 5.8404e+02 1.7542e-02 -1.0850e-05 5.4901e-09 -1.1547e-12
considering some of the aspects of the problem (with or 23 4.2621e+02 7.7381e-03 -1.5872e-06 2.3821e-10 -1.4826e-14
without UC constraints, with a DC or AC approach for the 24 3.7330e+02 2.5151e-03 -1.4946e-07 7.0983e-12 -
electrical network, with or without water delay times, and so 4.9320e+02 5.5064e-03 -9.7902e-09 -7.7966e-09 1.4546e-11
25
on). Each variant should be labeled properly in order to
26 4.6550e+02 7.7527e-03 -4.7736e-06 2.0896e-08 -3.9060e-11
identify which one is being considered in each application.
27 3.1398e+02 1.5885e-03 -6.9970e-08 3.4068e-12 -7.5036e-17
IX. APPENDIX 2.7700e+02 3.6697e-03 -4.7424e-07 1.2200e-10 -3.0704e-14
28
A. Hydro plants data
29 4.3943e+02 8.9155e-03 -4.0333e-06 1.3732e-09 -1.6982e-13
Table A.I lists the topological data, storage capacity and
30 4.2650e+02 1.7357e-02 -1.0233e-05 -1.5366e-08 -1.2149e-11
number of units of each hydro plant. Coefficients of the
31 3.7970e+02 2.1841e-03 -1.2786e-07 7.2738e-12 7.9277e-15
forebay and tailrace polynomials (1) and (2) for each
32 3.5600e+02 5.6617e-03 -8.0838e-07 -1.6166e-09 3.0731e-12
reservoir are listed in Tables A.II and A.III, respectively.
Data for each hydro unit are listed in Table A.IV.
7