Sie sind auf Seite 1von 510

PAYMENT MODALITIES 01 12 2014

SN Stages %

1 Structure 30.00
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6.00

1.2. Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight 4.00
• GF Roof and Portico Roof Slab including Staircase Second Flight
7.00

First Floor
• Columns and Slope Roof 6.00
• FF Roof Slab 7.00
2 Masonry & Plastering 15.00
2.1. Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades 2.00
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2.00

2.2. Plastering of ceiling and walls


• GF 3.00
• FF 3.00
2.3. Plastering in External Elevation in all floors 5.00
3 Flooring, Dado & Skirting 20.00
3.1. Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom 4.00
• FF-All Bedrooms, lobby & Balconies 4.00
• Clay tiling at all Open terraces 2.00
• Car Park & All round villa flagging concrete and other finishing Works
2.00

3.2. All Dadoo, Granite & Flooring


• GF Toilet, Dining & Kitchen Granite Works with Sink 3.00
• FF All Toilets 3.00
3.3. Staircase & Landings, etc., 2.00
4 Joinery & MS Railing Works 14.00
4.1. Door frames & Shutters
• GF 3.00
• FF 3.00
4.2. Window frames & Shutters
• GF 3.00
• FF 3.00
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF 1.00

• FF 1.00
5 Painting Works 10.00

5.1. Painting of Internal Walls & Ceilings

• GF 3.00

• FF 3.00

5.2. Painting for External Elevation

• GF 2.00

• FF 2.00

6 Water proofing Works in all floors 4.00

6.1. Toilet Water Proofing 2.00

6.2. Terrace, balcony water Proofing 2.00

7 Plumbing & Sanitary Works in all floors 4.00

7.1. Internal Plumbing and Sanitary Works

• Marking, Wall Chasing, Pipe Works for Water & Waste Line incl Pressure
Testing
1.00

• Fixing CP & Sanitary fittings 2.00

7.2. External Plumbing and Sanitary lines

• Pipe Works for Water Line, Waste Line & Rain Water down take lines
0.50
• Gully Traps & Chambers with connections complete (Pumps & Valves),
Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25

• Testing, Commissioning and Handing Over 0.25

8 Miscellaneous Works in all floors 3.00

8.1. Expansion Joint Treatment Works & Flagging Concrete 1.00

8.2. MS Staircase to terrace & Fencing for site 2.00


TOTAL 100.00
NAME OF WORK : CONSTRUCTION OF SHRESTA VILLAS AT MADUKKARAI,COIMBATORE
NAME OF OWNER : M/S. SHRIRAM PROPERTIES (COIMBATORE) PVT LTD
NAME OF CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : FIRST RUNNING BILL A.SHEET FOR VILLA 36A
DATE :01.11.14 to 10.12.014
AREA 1475 SFT Overall
1. 4 6 7 8 9 10 13 14 15 16 19 20 21 25 26

3BHK 4BHK 4BHK 4BHK 4BHK 4BHK 4BHK 4BHK 3BHK 3BHK 3BHK 3BHK 3BHK 3BHK 3BHK

Description of work 36A 50 54 56 60 65 66 68 70 72 72a 73 74 77 78 83 91 113 115 117 119 120 121 123 124 126A 128 130 126 131 142 169 171A 171 174 177 178 187 194 226 231 234A 245
Structure
1 30
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column
up to Plinth, Plinth Beam 6 6 4 4 4 4 4 6 5 4 4 6 6 6 5 5 5 6 5 5 5 6 5 5 6 6 5 6 6 5 6 5 4 5 5 5 5 5 4 3 4 5 4 5
1.2. Super-structure - RCC frame

Ground Floor

• Columns & Staircase First Flight


4 4 3 3 3 3
• GF Roof and Portico Roof Slab including
Staircase Second Flight 7 7
First Floor

• Columns and Slope Roof


6 6
• FF Roof Slab
7 7
Masonry & Plastering
2 15
2.1. Masonry Works
• GF Masonry Works up to Roof including
Lintel and Sunshades 2 2
• FF Masonry Works up to Roof including
Lintel, Lofts and Sunshades 2 2
2.2. Plastering of ceiling and walls

• GF
3
• FF
3
2.3. Plastering in External Elevation in all floors
5 5
Flooring, Dado & Skirting
3 20
3.1. Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen,
Bedroom 4
• FF-All Bedrooms, lobby & Balconies
4
• Clay tiling at all Open terraces
2
• Car Park & All round villa flagging
concrete and other finishing Works 2
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works
with Sink 3
• FF All Toilets
3
3.3. Staircase & Landings, etc.,
2
Joinery & MS Railing Works
4 14
4.1. Door frames & Shutters

• GF
3
• FF
3
4.2. Window frames & Shutters

• GF
3
• FF
3
MS Railing Works for Windows, Staircase,
4.3.
Balcony & Terrace
• GF
1
• FF
1
Painting Works
5 10
5.1. Painting of Internal Walls & Ceilings

• GF
3
• FF
3
5.2. Painting for External Elevation

• GF
2
• FF
2
Water proofing Works in all floors
6 4
6.1. Toilet Water Proofing
2
6.2. Terrace, balcony water Proofing
2
Plumbing & Sanitary Works in all floors
7 4
7.1. Internal Plumbing and Sanitary Works
• Marking, Wall Chasing, Pipe Works for
Water & Waste Line incl Pressure testing
1
• Fixing CP & Sanitary fittings
2
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line &
Rain Water down take lines 1
• Gully Traps & Chambers with connections
complete (Pumps & Valves), Supply & Fixing
0
Syntex Tank & Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
0
Miscellaneous Works in all floors
8 3
Expansion Joint Treatment Works & Flagging
8.1.
Concrete 1
8.2. MS Staircase to terrace & Fencing for site
2

TOTAL
100 39 4 4 4 4 4 9 5 4 4 6 6 6 5 5 5 6 5 5 5 6 5 5 9 6 5 6 9 5 9 5 4 5 5 5 5 5 4 3 4 5 4 5
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRES

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORP

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

Block Total No Work Rate/S Total value of


S.no Type Area
No of Villas started ft work

1 4 3 BHK 1 1 1475 1395 2,057,625


2 5 4BHK 11 0 1685 1395 25,856,325
3 6 4BHK 11 11 1685 1395 25,856,325
4 7 4BHK 6 2 1685 1395 14,103,450
5 8 4BHK 6 6 1685 1395 14,103,450
6 9 4BHK 12 11 1685 1395 28,206,900
7 10 4BHK 9 5 1685 1395 21,155,175
8 13 4BHK 9 4 1685 1395 21,155,175

9 14 4BHK 11 9 1685 1395 25,856,325


10 15 3BHK 11 10 1475 1395 22,633,875

11 16 3BHK 9 5 1475 1395 18,518,625

12 19 3BHK 9 6 1475 1395 18,518,625

13 20 3BHK 10 7 1475 1395 20,576,250

14 21 3BHK 11 1 1475 1395 22,633,875

15 22 3BHK 9 0 1475 1395 18,518,625

16 25 3BHK 9 6 1475 1395 18,518,625

17 26 3BHK 11 4 1475 1395 22,633,875

Total 155 88 340,903,125

For SENTHIL CONSTRUCTION CORPORATION Pvt.Ltd

AUTHORISED SIGNATORY
HRIRAM SHRESHTA" VILLAS AT COIMBATORE

TRUCTORS PVT LTD

RUCTION CORPORATION PVT.LTD

2.15

Percentage of work completed Value of work complete


Total value of
work started Upto
current Cumulative Upto previous
previous Current bill
bill bill bill
Bill

2,057,625 57.50% 22.00% 79.50% 1,183,134 452,678


- 0.00% 0.00% 0.00% - -
25,856,325 3.45% 2.55% 6.00% 893,219 658,161
4,701,150 7.50% 2.00% 9.50% 352,586 94,023
14,103,450 6.67% 2.42% 9.08% 940,230 340,833
25,856,325 6.52% 3.61% 10.14% 1,686,538 934,354
11,752,875 2.15% 4.25% 6.40% 252,687 499,497
9,402,300 10.56% 3.56% 14.13% 993,118 334,957

21,155,175 10.19% 3.81% 14.00% 2,156,653 805,072


20,576,250 1.40% 4.25% 5.65% 288,068 874,491

10,288,125 2.10% 4.50% 6.60% 216,051 462,966

12,345,750 8.50% 1.50% 10.00% 1,049,389 185,186

14,403,375 3.43% 2.43% 5.86% 493,830 349,796

2,057,625 4.00% 1.00% 5.00% 82,305 20,576

- 0.00% 0.00% 0.00% - -

12,345,750 3.50% 2.88% 6.38% 432,101 354,940

8,230,500 2.63% 2.19% 4.81% 216,051 180,042

195,132,600 7.65% 3.70% 11.36% 11,235,958 6,547,572


ork completed

Cumulative bill

1,635,812
-
1,551,380
446,609
1,281,063
2,620,891
752,184
1,328,075

2,961,725
1,162,558

679,016

1,234,575

843,626

102,881

787,042

396,093

17,783,530

###
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : THIRD RUNNING BILL
BILLING PERIOD 11.01.15 to 07.02.15
Total Block-4 ( 27A to 37 ) - 11 Nos x 1475 sft x Rs. 1395/ sft Rs 22,633,875

Block 4
Claim. ( 36A ) -
1 Nos x 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
Payment completed
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill

Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing,
Column up to Plinth, Plinth Beam 6%

Marking & Earthwork 2.00% 0.00% 41,153 - 41,153


PCC for footing 1.00% 0.00% 20,576 - 20,576
RCC for footing 1.00% 0.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 0.00% 20,576 - 20,576
RCC for plinth beam 1.00% 0.00% 20,576 - 20,576
0.00% 0.00% - - -
1.2. Super-structure - RCC frame
0.00% 0.00% - - -
Ground Floor
0.00% 0.00% - - -
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab 4% 4.00% 0.00% 82,305 - 82,305
including Staircase Second Flight 7% 7.00% 0.00% 144,034 - 144,034
First Floor
0.00% 0.00% - - -
• Columns and Slope Roof
6% 6.00% 0.00% 123,458 - 123,458
• FF Roof Slab
7% 7.00% 0.00% 144,034 - 144,034
Masonry & Plastering
2 15% 0.00% 0.00% - - -
2.1. Masonry Works
• GF Masonry Works up to Roof 0.00% 0.00% - - -
including Lintel Works
• FF Masonry and Sunshades
up to Roof 2% 2.00% 0.00% 41,153 - 41,153
including Lintel, Lofts and Sunshades 2% 2.00% 0.00% 41,153 - 41,153
2.2. Plastering of ceiling and walls
0.00% 0.00% - - -
• GF
3% 3.00% 0.00% 61,729 - 61,729
• FF
Plastering in External Elevation in all 3% 3.00% 0.00% 61,729 - 61,729
2.3.
floors 5% 5.00% 0.00% 102,881 - 102,881
Flooring, Dado & Skirting
3 20% 0.00% 0.00% - - -
3.1. Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, 0.00% 0.00% - - -
Bedroom 4% 0.00% 4.00% - 82,305 82,305
• FF-All Bedrooms, lobby & Balconies
4% 0.00% 4.00% - 82,305 82,305
• Clay tiling at all Open terraces
• Car Park & All round villa flagging 2% 1.00% 1.00% 20,576 20,576 41,153
concrete and other finishing Works 2% 0.00% 0.00% - - -
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite 0.00% 0.00% - - -
Works with Sink 3% 0.00% 3.00% - 61,729 61,729
• FF All Toilets
3% 0.00% 3.00% - 61,729 61,729
3.3. Staircase & Landings, etc.,
2% 0.00% 2.00% - 41,153 41,153
Percentage of work
Value of work completed
Payment completed
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill
Joinery & MS Railing Works
4 14% 0.00% 0.00% - - -
4.1. Door frames & Shutters
0.00% 0.00% - - -
• GF
3% 1.00% 0.00% 20,576 - 20,576
• FF
3% 1.00% 0.00% 20,576 - 20,576
4.2. Window frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
MS Railing Works for Windows, 3% 0.00% 0.00% - - -
4.3.
Staircase, Balcony & Terrace 0.00% 0.00% - - -
• GF
1% 1.00% 0.00% 20,576 - 20,576
• FF
1% 1.00% 0.00% 20,576 - 20,576
Painting Works
5 10% 0.00% 0.00% - - -
5.1. Painting of Internal Walls & Ceilings
0.00% 0.00% - - -
• GF
3% 1.00% 0.00% 20,576 - 20,576
• FF
3% 1.00% 0.00% 20,576 - 20,576
5.2. Painting for External Elevation
0.00% 0.00% - - -
• GF
2% 0.25% 0.00% 5,144 - 5,144
• FF
2% 0.25% 0.00% 5,144 - 5,144
Water proofing Works in all floors
6 4% 0.00% 0.00% - - -
6.1. Toilet Water Proofing
2% 2.00% 0.00% 41,153 - 41,153
6.2. Terrace, balcony water Proofing
2% 2.00% 0.00% 41,153 - 41,153
Plumbing & Sanitary Works in all floors
7 4% 0.00% 0.00% - - -
7.1. •Internal
Marking, Wall Chasing,
Plumbing PipeWorks
and Sanitary Works
for Water & Waste Line incl Pressure 0.00% 0.00% - - -
testing 1% 1.00% 0.00% 20,576 - 20,576
• Fixing CP & Sanitary fittings
2% 0.00% 2.00% - 41,153 41,153
7.2. External Plumbing and Sanitary lines
0.00% 0.00% - - -
•• Pipe Works
Gully Trapsfor
&Water Line, with
Chambers Waste
Line & Rain complete
connections Water down take &lines
(Pumps 0.50% 0.00% 0.50% - 10,288 10,288
Valves), Supply
• Testing, & Fixing Syntex
Commissioning and Tank 0.25% 0.00% 0.25% - 5,144 5,144
& Connections
Handing Over (Pumps & Valves) 0.25% 0.00% 0.25% - 5,144 5,144
Miscellaneous Works in all floors
8 Expansion Joint Treatment Works & 3% 0.00% 0.00% - - -
8.1.
Flagging Concrete
MS Staircase to terrace & Fencing for 1% 0.00% 0.00% - - -
8.2.
site 2% 0.00% 2.00% - 41,153 41,153
TOTAL - - -
100% 57.50% 22.00% 1,183,134 452,678 1,635,812

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
S.No

2
2.1.

2.2.

2.3.

3
3.1.

3.2.
S.No

3.3.

4
4.1.

4.2.

4.3.
S.No

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.

8
8.1.
8.2.
S.No

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCT
NAME OF THE OWNER
NAME OF THE CONTRACTOR : M/S.
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth,
Plinth Beam

Marking & Earthwork


PCC for footing
RCC for footing
Column upto plinthbeam
RCC for plinth beam

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
Description of work

• GF Roof and Portico Roof Slab including Staircase


Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and
Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and
Sunshades
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other
finishing Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Description of work

Staircase & Landings, etc.,


Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Description of work

Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste
Line incl Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water
•down
Gully
takeTraps
lines & Chambers with connections complete
(Pumps & Valves), Supply & Fixing Syntex Tank &
Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site
Description of work

TOTAL

repared by
CCPL Er
CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIM
NER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
CTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LT
NNING BILL
11.01.15 to 07.02.15
VILLA 36A (3 BHK) - 1475 sft x Rs. 1395/

Percentage of work
Value of wor
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

30%

6%

2.00% 41,153
1.00% 20,576
1.00% 20,576
1.00% 20,576
1.00% 20,576
-
-
-
4% 4.00% 82,305
Percentage of work
Value of wor
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

7% 7.00% 144,034
-
6% 6.00% 123,458
7% 7.00% 144,034
15% -
-
2% 2.00% 41,153
2% 2.00% 41,153
-
3% 3.00% 61,729
3% 3.00% 61,729
5% 5.00% 102,881
20% -
-
4% 4.00% -
4% 4.00% -
2% 1.00% 1.00% 20,576
2% -
-
3% 3.00% -
3% 3.00% -
Percentage of work
Value of wor
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

2% 2.00% -
14% -
-
3% 1.00% 20,576
3% 1.00% 20,576
-
3% -
3% -
-
1% 1.00% 20,576
1% 1.00% 20,576
Percentage of work
Value of wor
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

10% -
-
3% 1.00% 20,576
3% 1.00% 20,576
-
2% 0.25% 5,144
2% 0.25% 5,144
4% -
2% 2.00% 41,153
2% 2.00% 41,153
4% -
-
1% 1.00% 20,576
2% 2.00% -
-
0.50% 0.50% -
0.25% 0.25% -
0.25% 0.25% -
3% -
1% -
2% 2.00% -
Percentage of work
Value of wor
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

-
100% 57.50% 22.00% 1,183,134

Checked by
SCCPL Er
ESHTA" VILLAS AT COIMBATORE
TRUCTORS PVT LTD
ON CORPORATION PVT.LTD

1475 sft x Rs. 1395/ sft Rs 2,057,625

Value of work completed

Current bill Cumulative bill

- 41,153
- 20,576
- 20,576
- 20,576
- 20,576
- -
- -
- -
- 82,305
Value of work completed

Current bill Cumulative bill

- 144,034
- -
- 123,458
- 144,034
- -
- -
- 41,153
- 41,153
- -
- 61,729
- 61,729
- 102,881
- -
- -
82,305 82,305
82,305 82,305
20,576 41,153
- -
- -
61,729 61,729
61,729 61,729
Value of work completed

Current bill Cumulative bill

41,153 41,153
- -
- -
- 20,576
- 20,576
- -
- -
- -
- -
- 20,576
- 20,576
Value of work completed

Current bill Cumulative bill

- -
- -
- 20,576
- 20,576
- -
- 5,144
- 5,144
- -
- 41,153
- 41,153
- -
- -
- 20,576
41,153 41,153
- -
10,288 10,288
5,144 5,144
5,144 5,144
- -
- -
41,153 41,153
Value of work completed

Current bill Cumulative bill

- -
452,678 1,635,812

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : THIRD RUNNING BILL
BILLING PERIOD 11.01.15 to 07.02.15
Total Block-6 ( 49 to 59 ) - 11 Nos x 1685 sft x Rs. 1395/ sft Rs 25,856,325
Block 6
( 49 ,
Claim. 50,51,52,54,54A,56,57,58,59 )
11 Nos x 1685 sft x Rs. 1395/ sft Rs 25,856,325
-
Percentage of work
Value of work completed
Payment completed
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill

Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing,
Column up to Plinth, Plinth Beam 6%

Marking & Earthwork 1.45% 0.45% 376,092 117,529 493,621


PCC for footing 0.55% 0.36% 141,035 94,023 235,058
RCC for footing 0.55% 0.18% 141,035 47,012 188,046
Column upto plinthbeam 0.55% 0.18% 141,035 47,012 188,046
RCC for plinth beam 0.18% 0.18% 47,012 47,012 94,023
0.00% 0.00% - - -
1.2. Super-structure - RCC frame
0.00% 0.00% - - -
Ground Floor
0.00% 0.00% - - -
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab 4% 0.18% 0.91% 47,012 235,058 282,069
including Staircase Second Flight 7% 0.00% 0.27% - 70,517 70,517
First Floor
0.00% 0.00% - - -
• Columns and Slope Roof
6% 0.00% 0.00% - - -
• FF Roof Slab
7% 0.00% 0.00% - - -
Masonry & Plastering
2 15% 0.00% 0.00% - - -
2.1. Masonry Works
• GF Masonry Works up to Roof 0.00% 0.00% - - -
including Lintel Works
• FF Masonry and Sunshades
up to Roof 2% 0.00% 0.00% - - -
including Lintel, Lofts and Sunshades 2% 0.00% 0.00% - - -
2.2. Plastering of ceiling and walls
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
Plastering in External Elevation in all 3% 0.00% 0.00% - - -
2.3.
floors 5% 0.00% 0.00% - - -
Flooring, Dado & Skirting
3 20% 0.00% 0.00% - - -
3.1. Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, 0.00% 0.00% - - -
Bedroom 4% 0.00% 0.00% - - -
• FF-All Bedrooms, lobby & Balconies
4% 0.00% 0.00% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging 2% 0.00% 0.00% - - -
concrete and other finishing Works 2% 0.00% 0.00% - - -
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite 0.00% 0.00% - - -
Works with Sink 3% 0.00% 0.00% - - -
• FF All Toilets
3% 0.00% 0.00% - - -
3.3. Staircase & Landings, etc.,
2% 0.00% 0.00% - - -
Percentage of work
Value of work completed
Payment completed
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill
Joinery & MS Railing Works
4 14% 0.00% 0.00% - - -
4.1. Door frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
4.2. Window frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
MS Railing Works for Windows, 3% 0.00% 0.00% - - -
4.3.
Staircase, Balcony & Terrace 0.00% 0.00% - - -
• GF
1% 0.00% 0.00% - - -
• FF
1% 0.00% 0.00% - - -
Painting Works
5 10% 0.00% 0.00% - - -
5.1. Painting of Internal Walls & Ceilings
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
5.2. Painting for External Elevation
0.00% 0.00% - - -
• GF
2% 0.00% 0.00% - - -
• FF
2% 0.00% 0.00% - - -
Water proofing Works in all floors
6 4% 0.00% 0.00% - - -
6.1. Toilet Water Proofing
2% 0.00% 0.00% - - -
6.2. Terrace, balcony water Proofing
2% 0.00% 0.00% - - -
Plumbing & Sanitary Works in all floors
7 4% 0.00% 0.00% - - -
7.1. •Internal
Marking, Wall Chasing,
Plumbing PipeWorks
and Sanitary Works
for Water & Waste Line incl Pressure 0.00% 0.00% - - -
testing 1% 0.00% 0.00% - - -
• Fixing CP & Sanitary fittings
2% 0.00% 0.00% - - -
7.2. External Plumbing and Sanitary lines
0.00% 0.00% - - -
•• Pipe Works
Gully Trapsfor
&Water Line, with
Chambers Waste
Line & Rain complete
connections Water down take &lines
(Pumps 0.50% 0.00% 0.00% - - -
Valves), Supply
• Testing, & Fixing Syntex
Commissioning and Tank 0.25% 0.00% 0.00% - - -
& Connections
Handing Over (Pumps & Valves) 0.25% 0.00% 0.00% - - -
Miscellaneous Works in all floors
8 Expansion Joint Treatment Works & 3% 0.00% 0.00% - - -
8.1.
Flagging Concrete
MS Staircase to terrace & Fencing for 1% 0.00% 0.00% - - -
8.2.
site 2% 0.00% 0.00% - - -
TOTAL - - -
100% 3.45% 2.55% 893,219 658,161 1,551,380

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 49 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work completed Value of work completed


S.No Description of work Payment modality
Upto previous
current bill Upto previous bill Current bill Cumulative bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2% 0% 47,012 - 47,012

PCC for footing 1% - 23,506 23,506

RCC for footing 1% - 23,506 23,506

Column upto plinthbeam 1.0% - 23,506 23,506

RCC for plinth beam - - -

- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
2% - - -
• Car Park & All round villa flagging concrete and other finishing Works
2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing and Sanitary Works
- - -
• Marking, Wall Chasing, Pipe Works for Water & Waste Line incl Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
- - -
• Pipe Works for Water Line, Waste Line & Rain Water down take lines
0.50% - - -
• Gully Traps & Chambers with connections complete (Pumps & Valves), Supply &
Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -

- - -
TOTAL
100% 2% 3.0% 47,012 70,517 117,529

Prepared by Checked by Verified by

SCCPL Er SCCPL Er SCPL Er


NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : THIRD RUNNING BILL
BILLING PERIOD 11.01.15 to 07.02.15
VILLA 50 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
S.No Description of work Payment modality Upto
current Upto previous
previous Current bill Cumulative bill
bill bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth
Beam 6%

Marking & Earthwork 2% 47,012 - 47,012


PCC for footing 1% 23,506 - 23,506
RCC for footing 1% 23,506 - 23,506
Column upto plinthbeam 1% 23,506 - 23,506
RCC for plinth beam 1% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second 4% 2% 1.0% 47,012 23,506 70,517
Flight 7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
• GF Masonry Works up to Roof including Lintel and - - -
Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and 2% - - -
Sunshades 2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other 2% - - -
finishing Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line - - -
incl Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down - - -
•takeGully
lines Traps & Chambers with connections complete 0.50% - - -
(Pumps & Valves), Supply & Fixing Syntex Tank &
0.25% - - -
Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 8% 1.0% 188,046 23,506 211,552

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.

4
4.1.
4.2.

4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.
8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRU
NAME OF THE OWNER
NAME OF THE CONTRACTOR : M
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth
Beam
Marking & Earthwork
PCC for footing
RCC for footing
Column upto plinthbeam
RCC for plinth beam

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second
Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and
Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and
Sunshades
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other
finishing Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line
incl Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down
•takeGully
lines Traps & Chambers with connections complete
(Pumps & Valves), Supply & Fixing Syntex Tank &
Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site

TOTAL

epared by
CPL Er
NSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBA
R : M/S. SHRIPROP CONSTRUCTORS PVT LTD
R : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL
11.01.15 to 07.02.15
VILLA 51 (4 BHK) - 1685 sft x Rs. 1395/

Percentage of work
Upto Value of wo
Payment modality completed
current Upto previous
previous
bill bill
Bill
30%

6%
2% 0% 47,012
1% -
1% -
1.0% -
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 2% 3.0% 47,012

Checked by
SCCPL Er
S AT COIMBATORE
LTD
ON PVT.LTD

5 sft x Rs. 1395/ sft Rs 2,350,575

Value of work completed


Current bill Cumulative bill

- 47,012
23,506 23,506
23,506 23,506
23,506 23,506
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
70,517 117,529

Verified by
SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.

4
4.1.

4.2.
4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.

8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCT
NAME OF THE OWNER :
NAME OF THE CONTRACTOR : M/S. S
BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Be

Marking & Eart


PCC for f
RCC for f
Column upto plint
RCC for plinth

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flig
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunsh
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line in
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down tak
lines
• Gully Traps & Chambers with connections complete (Pumps
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & V
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
ION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
M/S. SHRIPROP CONSTRUCTORS PVT LTD
SENTHIL CONSTRUCTION CORPORATION PVT.LTD

11.01.15 to 07.02.15
VILLA 52 (4 BHK) - 1685 sft x Rs. 1395/ sft

Percentage of work
Value of work completed
completed
Payment Upto Upto
modality current Current
previous previous
bill bill
Bill bill

30%

6%
0% 2% - 47,012
1% - 23,506
0% - -
- -
- -
- -
- -
- -
4% - -
7% - -
- -
6% - -
7% - -
15% - -
- -
2% - -
2% - -
- -
3% - -
3% - -
5% - -
20% - -
- -
4% - -
4% - -
2% - -
2% - -
- -
3% - -
3% - -
2% - -
14% - -
- -
3% - -
3% - -
- -
3% - -
3% - -
- -
1% - -
1% - -
10% - -
- -
3% - -
3% - -
- -
2% - -
2% - -
4% - -
2% - -
2% - -
4% - -
- -
1% - -
2% - -
- -
0.50% - -
0.25% - -
0.25% - -
3% - -
1% - -
2% - -
- -
100% 0% 3% - 70,517

Checked by
SCCPL Er
TORE

Rs 2,350,575

work completed
Cumulative
bill

47,012
23,506
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
70,517

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 54 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment Upto Upto Cumulative
S.No Description of work current Current bill
modality previous previous
bill bill
Bill bill

Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2% 47,012 - 47,012
PCC for footing 1% 23,506 - 23,506
RCC for footing 1% 23,506 - 23,506
Column upto plinthbeam 1% 23,506 - 23,506
RCC for plinth beam 1% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3% - 70,517 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. •Internal Plumbing
Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 6% 3% 141,035 70,517 211,552

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 54A (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto Cumulative
previous Current bill
bill previous bill bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 0% 2% - 47,012 47,012


PCC for footing 0% 1% - 23,506 23,506
RCC for footing 0% - - -
Column upto plinthbeam 0% - - -
RCC for plinth beam 0% - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3.00% - 70,517 70,517

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 55 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto Cumulative
previous Current bill
bill previous bill bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 0% 1% - 23,506 23,506


PCC for footing 0% - - -
RCC for footing 0% - - -
Column upto plinthbeam 0% - - -
RCC for plinth beam 0% - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. •Internal Plumbing
Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 1.00% - 23,506 23,506

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 56 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Upto Value of work completed
S.No Description of work Payment modality completed
current Upto Cumulative
previous Current bill
bill previous bill bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth
Beam 6%
Marking & Earthwork 2% 47,012 - 47,012
PCC for footing 1% 23,506 - 23,506
RCC for footing 1% 23,506 - 23,506
Column upto plinthbeam 1% 23,506 - 23,506
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second 4% - - -
Flight 7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
• GF Masonry Works up to Roof including Lintel and - - -
Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and 2% - - -
Sunshades 2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other 2% - - -
finishing Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste - - -
Line incl Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down - - -
•takeGully
lines Traps & Chambers with connections complete 0.50% - - -
(Pumps & Valves), Supply & Fixing Syntex Tank &
0.25% - - -
Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 5% 0.00% 117,529 - 117,529

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.
4
4.1.

4.2.

4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.
7.2.

8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILL

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth
Beam
Marking & Earthwork
PCC for footing
RCC for footing
Column upto plinthbeam
RCC for plinth beam

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second
Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and
Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and
Sunshades
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other
finishing Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing and Sanitary Works
• Marking, Wall Chasing, Pipe Works for Water & Waste
Line incl Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down
•takeGully
lines Traps & Chambers with connections complete
(Pumps & Valves), Supply & Fixing Syntex Tank &
Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site

TOTAL

epared by
CPL Er
ESHTA" VILLAS AT COIMBATORE

PORATION PVT.LTD

11.01.15 to 07.02.15
VILLA 57 (4 BHK) - 1685 sft x Rs. 1395/ sf

Percentage of work
Upto Value of work
Payment modality completed
current Upto
previous
bill previous bill
Bill
30%

6%
2% 47,012
1% 23,506
1% 23,506
1% 23,506
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 5% 0.00% 117,529

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,350,575

Value of work completed


Cumulative
Current bill
bill

- 47,012
- 23,506
- 23,506
- 23,506
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- 117,529

Verified by
SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.

4
4.1.
4.2.

4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.
8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILL

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam

Marking & Earthw


PCC for foo
RCC for foo
Column upto plinthb
RCC for plinth b

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshad
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take
lines
• Gully Traps & Chambers with connections complete (Pumps &
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valv
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15
VILLA 58 (4 BHK) - 1685 sft x Rs. 1395/ sft

Percentage of work
Payment Upto Value of work complet
completed
current Upto
modality previous
bill previous bill
Bill
30%

6%
2% 47,012
1% 23,506
1% 23,506
1% 23,506
1% -
-
-
-
4% 3% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 5% 4% 117,529

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,350,575

Value of work completed


Current bill Cumulative bill

- 47,012
- 23,506
- 23,506
- 23,506
23,506 23,506
- -
- -
- -
70,517 70,517
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
94,023 211,552

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 59 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed
current Upto
modality previous Current bill Cumulative bill
bill previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2% 47,012 - 47,012
PCC for footing 1% 23,506 - 23,506
RCC for footing 1% 23,506 - 23,506
Column upto plinthbeam 1% 23,506 - 23,506
RCC for plinth beam 1% - 23,506 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3% - 70,517 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 3% - 70,517 70,517
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 5% 7% 117,529 164,540 282,069

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL


BILLING PERIOD 11.01.15 to 07.02.15
Total Block 7- ( 60 to 65 ) - 6 Nos x 1685 sft x Rs. 1395/ sft Rs 14,103,450

Block-7
Claim. ( 60,65 ) -
2 Nos x 1685 sft x Rs. 1395/ sft Rs 4,701,150

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality Upto previous
previous current bill Current bill Cumulative bill
bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column
up to Plinth, Plinth Beam 6%

Marking & Earthwork 2.00% 0.00% 94,023 - 94,023


PCC for footing 1.00% 0.00% 47,012 - 47,012
RCC for footing 1.00% 0.00% 47,012 - 47,012
Column upto plinthbeam 1.00% 0.00% 47,012 - 47,012
RCC for plinth beam 1.00% 0.00% 47,012 - 47,012
0.00% 0.00% - - -
1.2. Super-structure - RCC frame
0.00% 0.00% - - -
Ground Floor
0.00% 0.00% - - -
• Columns & Staircase First Flight
4% 1.50% 1.50% 70,517 70,517 141,035
• GF Roof and Portico Roof Slab including
Staircase Second Flight 7% 0.00% 0.00% - - -
First Floor
0.00% 0.00% - - -
• Columns and Slope Roof
6% 0.00% 0.00% - - -
• FF Roof Slab
7% 0.00% 0.00% - - -
Masonry & Plastering
2 15% 0.00% 0.00% - - -
2.1. Masonry Works
0.00% 0.00% - - -
• GF Masonry Works up to Roof including
Lintel and Sunshades 2% 0.00% 0.50% - 23,506 23,506

• FF Masonry Works up to Roof including


Lintel, Lofts and Sunshades 2% 0.00% 0.00% - - -

2.2. Plastering of ceiling and walls


0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
2.3. Plastering in External Elevation in all floors
5% 0.00% 0.00% - - -
Flooring, Dado & Skirting
3 20% 0.00% 0.00% - - -
3.1. Flooring & Skirting
0.00% 0.00% - - -
• GF-Foyer, Living, Dining, Kitchen,
Bedroom 4% 0.00% 0.00% - - -
• FF-All Bedrooms, lobby & Balconies
4% 0.00% 0.00% - - -
• Clay tiling at all Open terraces
2% 0.00% 0.00% - - -
• Car Park & All round villa flagging
concrete and other finishing Works 2% 0.00% 0.00% - - -
3.2. All Dadoo, Granite & Flooring
0.00% 0.00% - - -
• GF Toilet, Dining & Kitchen Granite
Works with Sink 3% 0.00% 0.00% - - -
• FF All Toilets
3% 0.00% 0.00% - - -
3.3. Staircase & Landings, etc.,
2% 0.00% 0.00% - - -
Joinery & MS Railing Works
4 14% 0.00% 0.00% - - -
4.1. Door frames & Shutters
0.00% 0.00% - - -
Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality Upto previous
previous current bill Current bill Cumulative bill
bill
Bill
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
4.2. Window frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
MS Railing Works for Windows, Staircase,
4.3.
Balcony & Terrace 0.00% 0.00% - - -
• GF
1% 0.00% 0.00% - - -
• FF
1% 0.00% 0.00% - - -
Painting Works
5 10% 0.00% 0.00% - - -
5.1. Painting of Internal Walls & Ceilings
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
5.2. Painting for External Elevation
0.00% 0.00% - - -
• GF
2% 0.00% 0.00% - - -
• FF
2% 0.00% 0.00% - - -
Water proofing Works in all floors
6 4% 0.00% 0.00% - - -
6.1. Toilet Water Proofing
2% 0.00% 0.00% - - -

6.2. Terrace, balcony water Proofing


2% 0.00% 0.00% - - -
Plumbing & Sanitary Works in all floors
7 4% 0.00% 0.00% - - -
7.1. Internal Plumbing and Sanitary Works
0.00% 0.00% - - -

• Marking, Wall Chasing, Pipe Works for


Water & Waste Line incl Pressure testing
1% 0.00% 0.00% - - -

• Fixing CP & Sanitary fittings


2% 0.00% 0.00% - - -

7.2. External Plumbing and Sanitary lines


0.00% 0.00% - - -

• Pipe Works for Water Line, Waste Line &


Rain Water down take lines 0.50% 0.00% 0.00% - - -

• Gully Traps & Chambers with


connections complete (Pumps & Valves),
Supply & Fixing Syntex Tank & Connections 0.25% 0.00% 0.00% - - -
(Pumps & Valves)

• Testing, Commissioning and Handing


Over 0.25% 0.00% 0.00% - - -

Miscellaneous Works in all floors


8 3% 0.00% 0.00% - - -
Expansion Joint Treatment Works & Flagging
8.1.
Concrete 1% 0.00% 0.00% - - -

8.2. MS Staircase to terrace & Fencing for site


2% 0.00% 0.00% - - -

- - -
TOTAL
100% 7.50% 2.00% 352,586 94,023 446,609

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 60 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% - 70,517 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 6% 3.50% 141,035 82,270 223,305

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 61 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork - - -


PCC for footing - - -
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 0.00% - - -

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 63(4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork - - -


PCC for footing - - -
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 0.00% - - -

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 63A (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork - - -


PCC for footing - - -
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 0.00% - - -

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 63A (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork - - -


PCC for footing - - -
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 0.00% - - -

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 65 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9% 0.50% 211,552 11,753 223,305

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS P
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORP
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

S.No Description of work

Structure
1
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up
to Plinth, Plinth Beam

Marking & Earthwork


PCC for footing
RCC for footing
Column upto plinthbeam
RCC for plinth beam
S.No Description of work

1.2. Super-structure - RCC frame

Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including
Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab

Masonry & Plastering


2
2.1. Masonry Works
• GF Masonry Works up to Roof including
Lintel and Sunshades
• FF Masonry Works up to Roof including
Lintel, Lofts and Sunshades
2.2. Plastering of ceiling and walls
• GF
• FF
S.No Description of work

2.3. Plastering in External Elevation in all floors

Flooring, Dado & Skirting


3
3.1. Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen,
Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete
and other finishing Works
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works
with Sink

• FF All Toilets

3.3. Staircase & Landings, etc.,

Joinery & MS Railing Works


4
S.No Description of work

4.1. Door frames & Shutters

• GF

• FF

4.2. Window frames & Shutters

• GF

• FF
MS Railing Works for Windows, Staircase,
4.3.
Balcony & Terrace
• GF

• FF

Painting Works
5
5.1. Painting of Internal Walls & Ceilings
• GF
• FF
5.2. Painting for External Elevation
S.No Description of work

• GF
• FF

Water proofing Works in all floors


6
6.1. Toilet Water Proofing
6.2. Terrace, balcony water Proofing

Plumbing & Sanitary Works in all floors


7

7.1. Internal Plumbing and Sanitary Works


• Marking, Wall Chasing, Pipe Works for
Water & Waste Line incl Pressure testing

• Fixing CP & Sanitary fittings

7.2. External Plumbing and Sanitary lines

• Pipe Works for Water Line, Waste Line &


Rain Water down take lines
S.No Description of work

• Gully Traps & Chambers with connections


complete (Pumps & Valves), Supply & Fixing
Syntex Tank & Connections (Pumps & Valves)

• Testing, Commissioning and Handing Over

Miscellaneous Works in all floors


8
Expansion Joint Treatment Works & Flagging
8.1.
Concrete
8.2. MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
ONSTRUCTORS PVT LTD
NSTRUCTION CORPORATION PVT.LTD
BILL
11.01.15 to 07.02.15
Total Block-8 ( 66 to 72 ) - 6 Nos x 1685 sft x Rs. 1395

Block-8 (66,67,68,69,70,72 )
Claim. -
6 Nos x 1685 sft x Rs. 139

Percentage of work
Value of work
Payment completed
modality Upto previous Upto previous
current bill
Bill bill

30%

6%

2.00% 0.00% 282,069


1.00% 0.00% 141,035
1.00% 0.00% 141,035
0.83% 0.17% 117,529
0.33% 0.00% 47,012
0.00% 0.00% -
Percentage of work
Value of work
Payment completed
modality Upto previous Upto previous
current bill
Bill bill

0.00% 0.00% -

0.00% 0.00% -
4% 1.00% 0.50% 141,035

7% 0.50% 1.08% 70,517

0.00% 0.00% -
6% 0.00% 0.67% -
7% 0.00% 0.00% -

15% 0.00% 0.00% -

0.00% 0.00% -

2% 0.00% 0.00% -

2% 0.00% 0.00% -

0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
Percentage of work
Value of work
Payment completed
modality Upto previous Upto previous
current bill
Bill bill

5% 0.00% 0.00% -

20% 0.00% 0.00% -

0.00% 0.00% -
4% 0.00% 0.00% -
4% 0.00% 0.00% -
2% 0.00% 0.00% -

2% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -

3% 0.00% 0.00% -

2% 0.00% 0.00% -

14% 0.00% 0.00% -


Percentage of work
Value of work
Payment completed
modality Upto previous Upto previous
current bill
Bill bill
0.00% 0.00% -

3% 0.00% 0.00% -

3% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -

3% 0.00% 0.00% -

0.00% 0.00% -

1% 0.00% 0.00% -

1% 0.00% 0.00% -

10% 0.00% 0.00% -

0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
Percentage of work
Value of work
Payment completed
modality Upto previous Upto previous
current bill
Bill bill
2% 0.00% 0.00% -
2% 0.00% 0.00% -

4% 0.00% 0.00% -

2% 0.00% 0.00% -
2% 0.00% 0.00% -

4% 0.00% 0.00% -

0.00% 0.00% -

1% 0.00% 0.00% -

2% 0.00% 0.00% -

0.00% 0.00% -

0.50% 0.00% 0.00% -


Percentage of work
Value of work
Payment completed
modality Upto previous Upto previous
current bill
Bill bill

0.25% 0.00% 0.00% -

0.25% 0.00% 0.00% -

3% 0.00% 0.00% -

1% 0.00% 0.00% -

2% 0.00% 0.00% -
-
100% 6.67% 2.42% 940,230

Checked by
SCCPL Er
x 1685 sft x Rs. 1395/ sft Rs 14,103,450

s x 1685 sft x Rs. 1395/ sft Rs 14,103,450

Value of work completed

Current bill Cumulative bill

- 282,069
- 141,035
- 141,035
23,506 141,035
- 47,012
- -
Value of work completed

Current bill Cumulative bill

- -

- -
70,517 211,552

152,787 223,305

- -
94,023 94,023
- -

- -

- -

- -

- -

- -
- -
- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -
- -
- -
- -

- -

- -

- -

- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -
- -
- -
- -
Value of work completed

Current bill Cumulative bill

- -
- -

- -

- -
- -

- -

- -

- -

- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -
- -
340,833 1,281,063

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 66 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 4.50% 35,259 105,776 141,035
First Floor
- - -
• Columns and Slope Roof
6% 4.00% - 94,023 94,023
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 8.50% 246,810 199,799 446,609

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.
3.2.

3.3.

4
4.1.

4.2.

4.3.

5
5.1.
5.2.

6
6.1.
6.2.

7
7.1.

7.2.

8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILL

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam

Marking & Earthw


PCC for foo
RCC for foo
Column upto plinthb
RCC for plinth b

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshad
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF

• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing

Plumbing & Sanitary Works in all floors

Internal Plumbing and Sanitary Works


• Marking, Wall Chasing, Pipe Works for Water & Waste Line incl
Pressure testing

• Fixing CP & Sanitary fittings


External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take
lines

• Gully Traps & Chambers with connections complete (Pumps &


Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valv

• Testing, Commissioning and Handing Over


Miscellaneous Works in all floors

Expansion Joint Treatment Works & Flagging Concrete


MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15

VILLA 67 (4 BHK) - 1685 sft x Rs. 1395/ sft

Percentage of work
Value of work comple
completed
Payment
modality Upto
current Upto
previous
bill previous bill
Bill

30%

6%

2% 47,012
1% 23,506
1% 23,506
1% 23,506
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -

-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -

3% -
-
2% -
2% -
4% -
2% -
2% -

4% -

1% -

2% -
-

0.50% -

0.25% -

0.25% -
3% -

1% -
2% -
-
100% 5.00% 0.00% 117,529

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,350,575

Value of work completed

Current bill Cumulative bill

- 47,012
- 23,506
- 23,506
- 23,506
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -

- -
- -
- -
- -
- -
- -
- -

- -

- -

- -

- -
- -

- -

- -

- -
- -

- -
- -
- -
- 117,529

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 68 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 2.00% 35,259 47,012 82,270
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 2.00% 223,305 47,012 270,316

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.
3.2.

3.3.

4
4.1.

4.2.

4.3.

5
5.1.

5.2.
6
6.1.
6.2.

7
7.1.

7.2.

8
8.1.
8.2.
Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILL

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam

Marking & Earthw


PCC for foo
RCC for foo
Column upto plinthb
RCC for plinth b

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works

• GF Masonry Works up to Roof including Lintel and Sunshades

• FF Masonry Works up to Roof including Lintel, Lofts and Sunshad

Plastering of ceiling and walls


• GF
• FF
Plastering in External Elevation in all floors

Flooring, Dado & Skirting

Flooring & Skirting


• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing and Sanitary Works
• Marking, Wall Chasing, Pipe Works for Water & Waste Line incl
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take
lines

• Gully Traps & Chambers with connections complete (Pumps &


Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valv

• Testing, Commissioning and Handing Over

Miscellaneous Works in all floors

Expansion Joint Treatment Works & Flagging Concrete


MS Staircase to terrace & Fencing for site

TOTAL
Prepared by
SCCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15

VILLA 69 (4 BHK) - 1685 sft x Rs. 1395/ sft

Percentage of work
Value of work compl
completed
Payment
modality Upto
current Upto previous
previous
bill bill
Bill

30%

6%

2% 47,012
1% 23,506
1% 23,506
1% -
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-

2% -

2% -

-
3% -
3% -
5% -

20% -

-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-

0.50% -

0.25% -

0.25% -

3% -

1% -
2% -
-
100% 4.00% 1.00% 94,023
Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,350,575

Value of work completed

Current bill Cumulative bill

- 47,012
- 23,506
- 23,506
23,506 23,506
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -

- -

- -

- -
- -
- -
- -

- -

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -

- -

- -

- -

- -

- -
- -
- -
23,506 117,529
Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 70 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2% 47,012 - 47,012


PCC for footing 1% 23,506 - 23,506
RCC for footing 1% 23,506 - 23,506
Column upto plinthbeam 1% 23,506 - 23,506
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 5.00% 0.00% 117,529 - 117,529

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 72 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% - 70,517 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 6.00% 3.00% 141,035 70,517 211,552

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : THIRD RUNNING BILL
BILLING PERIOD 11.01.15 to 07.02.15
Total Block-9 ( 72A to 83 ) - 12Nos x 1685 sft x Rs. 1395/ sft Rs 28,206,900

Block-9
Claim. (72A,73,74,75,77,78,79,81,81A, 11 Nos x 1685 sft x Rs. 1395/ sft Rs 25,856,325
82,83) -

Percentage of work
Value of work completed
completed
Payment
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill

Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam 6%

Marking & Earthwork 1.64% 0.36% 423,104 94,023 517,127


PCC for footing 0.82% 0.18% 211,552 47,012 258,563
RCC for footing 0.73% 0.18% 188,046 47,012 235,058
Column upto plinthbeam 0.55% 0.36% 141,035 94,023 235,058
RCC for plinth beam 0.55% 0.00% 141,035 - 141,035
0.00% 0.00% - - -
1.2. Super-structure - RCC frame
0.00% 0.00% - - -

Ground Floor
0.00% 0.00% - - -
• Columns & Staircase First Flight
4% 1.64% 0.00% 423,104 - 423,104
• GF Roof and Portico Roof Slab including Staircase
Second Flight 7% 0.61% 1.16% 158,664 299,698 458,362
First Floor
0.00% 0.00% - - -
• Columns and Slope Roof
6% 0.00% 1.09% - 282,069 282,069
• FF Roof Slab
7% 0.00% 0.00% - - -
Masonry & Plastering
2 15% 0.00% 0.00% - - -
2.1. Masonry Works
0.00% 0.00% - - -
• GF Masonry Works up to Roof including Lintel and
Sunshades 2% 0.00% 0.27% - 70,517 70,517

• FF Masonry Works up to Roof including Lintel,


Lofts and Sunshades 2% 0.00% 0.00% - - -

2.2. Plastering of ceiling and walls


0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
2.3. Plastering in External Elevation in all floors
5% 0.00% 0.00% - - -

Flooring, Dado & Skirting


3 20% 0.00% 0.00% - - -

3.1. Flooring & Skirting


0.00% 0.00% - - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% 0.00% 0.00% - - -
• FF-All Bedrooms, lobby & Balconies
4% 0.00% 0.00% - - -
• Clay tiling at all Open terraces
2% 0.00% 0.00% - - -
• Car Park & All round villa flagging concrete and
other finishing Works 2% 0.00% 0.00% - - -
3.2. All Dadoo, Granite & Flooring
0.00% 0.00% - - -
• GF Toilet, Dining & Kitchen Granite Works with
Sink 3% 0.00% 0.00% - - -
• FF All Toilets
3% 0.00% 0.00% - - -
Percentage of work
Value of work completed
completed
Payment
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill

3.3. Staircase & Landings, etc.,


2% 0.00% 0.00% - - -

Joinery & MS Railing Works


4 14% 0.00% 0.00% - - -

4.1. Door frames & Shutters


0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
4.2. Window frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
MS Railing Works for Windows, Staircase, Balcony &
4.3.
Terrace 0.00% 0.00% - - -

• GF
1% 0.00% 0.00% - - -
• FF
1% 0.00% 0.00% - - -
Painting Works
5 10% 0.00% 0.00% - - -

5.1. Painting of Internal Walls & Ceilings


0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
5.2. Painting for External Elevation
0.00% 0.00% - - -
• GF
2% 0.00% 0.00% - - -
• FF
2% 0.00% 0.00% - - -
Water proofing Works in all floors
6 4% 0.00% 0.00% - - -
6.1. Toilet Water Proofing
2% 0.00% 0.00% - - -
6.2. Terrace, balcony water Proofing
2% 0.00% 0.00% - - -
Plumbing & Sanitary Works in all floors
7 4% 0.00% 0.00% - - -

7.1. Internal Plumbing and Sanitary Works


0.00% 0.00% - - -
• Marking, Wall Chasing, Pipe Works for Water &
Waste Line incl Pressure testing
1% 0.00% 0.00% - - -

• Fixing CP & Sanitary fittings


2% 0.00% 0.00% - - -

7.2. External Plumbing and Sanitary lines


0.00% 0.00% - - -
• Pipe Works for Water Line, Waste Line & Rain
Water down take lines 0.50% 0.00% 0.00% - - -
• Gully Traps & Chambers with connections
complete (Pumps & Valves), Supply & Fixing Syntex
0.25% 0.00% 0.00% - - -
Tank & Connections (Pumps & Valves)

• Testing, Commissioning and Handing Over


0.25% 0.00% 0.00% - - -

Miscellaneous Works in all floors


8 3% 0.00% 0.00% - - -

8.1. Expansion Joint Treatment Works & Flagging Concrete


1% 0.00% 0.00% - - -

8.2. MS Staircase to terrace & Fencing for site


2% 0.00% 0.00% - - -
0.00% 0.00% - - -
TOTAL
100% 6.52% 3.61% 1,686,538 934,354 2,620,891

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL 0

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 72A (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.75% 4.25% 41,135 99,899 141,035
First Floor
- - -
• Columns and Slope Roof
6% 4.00% - 94,023 94,023
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.75% 8.75% 252,687 205,675 458,362

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 73 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.75% 4.25% 41,135 99,899 141,035
First Floor
- - -
• Columns and Slope Roof
6% 4.00% - 94,023 94,023
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.75% 8.75% 252,687 205,675 458,362

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 74 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.75% 4.25% 41,135 99,899 141,035
First Floor
- - -
• Columns and Slope Roof
6% 4.00% - 94,023 94,023
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.75% 8.75% 252,687 205,675 458,362

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.

4
4.1.
4.2.

4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.
8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILL

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam

Marking & Earthw


PCC for foo
RCC for foo
Column upto plinthb
RCC for plinth b

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshad
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take
lines
• Gully Traps & Chambers with connections complete (Pumps &
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valv
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site

TOTAL

epared by
CCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15
VILLA 75 (4 BHK) - 1685 sft x Rs. 1395/ sft

Percentage of work
Payment Upto Value of work comple
completed
current Upto
modality previous
bill previous bill
Bill
30%

6%
2.00% 47,012
1.00% 23,506
0.00% -
-
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 3.00% 0.00% 70,517

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,350,575

Value of work completed


Current bill Cumulative bill

- 47,012
- 23,506
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- 70,517

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 77 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.0% 47,012 - 47,012


PCC for footing 1.0% 23,506 - 23,506
RCC for footing 1.0% 23,506 - 23,506
Column upto plinthbeam 1.0% 23,506 - 23,506
RCC for plinth beam 1.0% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.0% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.5% 11,753 - 11,753
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 0.50% 223,305 11,753 235,058

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 78 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.0% 47,012 - 47,012


PCC for footing 1.0% 23,506 - 23,506
RCC for footing 1.0% 23,506 - 23,506
Column upto plinthbeam 1.0% 23,506 - 23,506
RCC for plinth beam 1.0% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.0% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.5% 11,753 - 11,753
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 0.50% 223,305 11,753 235,058

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 79 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed Upto
modality previous current bill Current bill Cumulative bill
previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2% 47,012 - 47,012
PCC for footing 1% 23,506 - 23,506
RCC for footing 1% 23,506 - 23,506
Column upto plinthbeam 1% - 23,506 23,506
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 4% 1% 94,023 23,506 117,529

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 81 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed Upto
modality previous current bill Current bill Cumulative bill
previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2.00% - 47,012 47,012
PCC for footing 1.00% - 23,506 23,506
RCC for footing 1.00% - 23,506 23,506
Column upto plinthbeam 1.00% - 23,506 23,506
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 5% - 117,529 117,529

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 81A (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed Upto
modality previous current bill Current bill Cumulative bill
previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2% - 47,012 47,012
PCC for footing 1% - 23,506 23,506
RCC for footing 1% - 23,506 23,506
Column upto plinthbeam 1% - 23,506 23,506
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 5% - 117,529 117,529

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 82 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed Upto
modality previous current bill Current bill Cumulative bill
previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2% 47,012 - 47,012
PCC for footing 1% 23,506 - 23,506
RCC for footing 1% 23,506 - 23,506
Column upto plinthbeam 1% - 23,506 23,506
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 4% 1% 94,023 23,506 117,529

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 83 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.50% 11,753 - 11,753
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 0.50% 223,305 11,753 235,058

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESH
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPOR
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

S.No

1
1.1.
S.No

1.2.

2
2.1.
S.No

2.2.

2.3.

3.1.

3.2.
S.No

3.3.

4.1.

4.2.

4.3.
S.No

5.1.

5.2.

6
6.1.
6.2.

7
S.No

7.1.

7.2.

8.1.
S.No

8.2.

Prepared by
SCCPL Er
AME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLA
AME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
AME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV
LL NO : THIRD RUNNING BILL
LLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam

Marking & Earthwork


PCC for footing
RCC for footing
Column upto plinthbeam
Description of work

RCC for plinth beam

Super-structure - RCC frame

Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase
Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab

Masonry & Plastering

Masonry Works
• GF Masonry Works up to Roof including Lintel and
Sunshades
• FF Masonry Works up to Roof including Lintel,
Lofts and Sunshades
Description of work

Plastering of ceiling and walls


• GF
• FF

Plastering in External Elevation in all floors

Flooring, Dado & Skirting

Flooring & Skirting

• GF-Foyer, Living, Dining, Kitchen, Bedroom


• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and
other finishing Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with
Sink
Description of work

• FF All Toilets

Staircase & Landings, etc.,

Joinery & MS Railing Works

Door frames & Shutters

• GF
• FF
Window frames & Shutters
• GF
• FF

MS Railing Works for Windows, Staircase, Balcony &


Terrace

• GF
Description of work

• FF

Painting Works

Painting of Internal Walls & Ceilings

• GF
• FF

Painting for External Elevation

• GF
• FF

Water proofing Works in all floors

Toilet Water Proofing


Terrace, balcony water Proofing

Plumbing & Sanitary Works in all floors


Description of work

Internal Plumbing and Sanitary Works


• Marking, Wall Chasing, Pipe Works for Water &
Waste Line incl Pressure testing

• Fixing CP & Sanitary fittings

External Plumbing and Sanitary lines


• Pipe Works for Water Line, Waste Line & Rain
Water down take lines

• Gully Traps & Chambers with connections


complete (Pumps & Valves), Supply & Fixing Syntex
Tank & Connections (Pumps & Valves)

• Testing, Commissioning and Handing Over

Miscellaneous Works in all floors

Expansion Joint Treatment Works & Flagging Concrete


Description of work

MS Staircase to terrace & Fencing for site

TOTAL

epared by
CCPL Er
RAM SHRESHTA" VILLAS AT COIMBATORE
CTORS PVT LTD
ON CORPORATION PVT.LTD

11.01.15 to 07.02.15
Block-10
Total (91,84,85,86,87,88,90,90A,92 ) 9 Nos x 1685 sft x Rs. 1395/
-

Clam. Block-10 ( 84,85,87,90,91 ) 5 Nos x 1685 sft x Rs. 1395

Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

30%

6%

0.40% 1.60% 47,012


0.20% 0.80% 23,506
0.20% 0.20% 23,506
0.20% 0.00% 23,506
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.20% 0.00% 23,506


0.00% 0.00% -
0.00% 0.00% -

0.00% 0.00% -
4% 0.60% 0.00% 70,517

7% 0.35% 0.85% 41,135

0.00% 0.00% -
6% 0.00% 0.80% -
7% 0.00% 0.00% -

15% 0.00% 0.00% -

0.00% 0.00% -

2% 0.00% 0.00% -

2% 0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -

5% 0.00% 0.00% -

20% 0.00% 0.00% -

0.00% 0.00% -

4% 0.00% 0.00% -
4% 0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -
0.00% 0.00% -

3% 0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

3% 0.00% 0.00% -

2% 0.00% 0.00% -

14% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -

0.00% 0.00% -

1% 0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

1% 0.00% 0.00% -

10% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -
3% 0.00% 0.00% -

0.00% 0.00% -

2% 0.00% 0.00% -
2% 0.00% 0.00% -

4% 0.00% 0.00% -

2% 0.00% 0.00% -
2% 0.00% 0.00% -

4% 0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.00% 0.00% -

1% 0.00% 0.00% -

2% 0.00% 0.00% -

0.00% 0.00% -

0.50% 0.00% 0.00% -

0.25% 0.00% 0.00% -

0.25% 0.00% 0.00% -

3% 0.00% 0.00% -

1% 0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

2% 0.00% 0.00% -
-
100% 2.15% 4.25% 252,687

Checked by
SCCPL Er
5 sft x Rs. 1395/ sft Rs 21,155,175

85 sft x Rs. 1395/ sft Rs 11,752,875

Value of work completed

Current bill Cumulative bill

188,046 235,058
94,023 117,529
23,506 47,012
- 23,506
Value of work completed

Current bill Cumulative bill

- 23,506
- -
- -

- -
- 70,517

99,899 141,035

- -
94,023 94,023
- -

- -

- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -
- -
- -

- -

- -

- -

- -
- -
- -
- -
- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -
- -
- -
- -
- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -
- -

- -

- -
- -

- -

- -
- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -

- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -
- -
499,497 752,184

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 84 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 47,012 47,012


PCC for footing 1.00% - 23,506 23,506
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3.00% - 70,517 70,517

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 85 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2% - 47,012 47,012


PCC for footing 1% - 23,506 23,506
RCC for footing 1% - 23,506 23,506
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 4.00% - 94,023 94,023

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 87 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2% - 47,012 47,012


PCC for footing 1% - 23,506 23,506
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3.00% - 70,517 70,517

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 90(4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2% - 47,012 47,012


PCC for footing 1% - 23,506 23,506
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3.00% - 70,517 70,517

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 91 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.75% 4.25% 41,135 99,899 141,035
First Floor
- - -
• Columns and Slope Roof
6% 4.00% - 94,023 94,023
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.75% 8.25% 252,687 193,922 446,609

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESH
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPOR
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

S.No Description of work

Structure
1
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam
Marking & Earthwork
PCC for footing
RCC for footing
Column upto plinthbeam
RCC for plinth beam

1.2. Super-structure - RCC frame


Ground Floor
S.No Description of work
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including
Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
2
2.1. Masonry Works
• GF Masonry Works up to Roof including Lintel
and
• FFSunshades
Masonry Works up to Roof including Lintel,
Lofts and Sunshades
2.2. Plastering of ceiling and walls
• GF
• FF
2.3. Plastering in External Elevation in all floors
Flooring, Dado & Skirting
3
3.1. Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete
and other finishing Works
3.2. All Dadoo, Granite & Flooring
S.No Description of work
• GF Toilet, Dining & Kitchen Granite Works
with Sink
• FF All Toilets
3.3. Staircase & Landings, etc.,
Joinery & MS Railing Works
4
4.1. Door frames & Shutters
• GF
• FF
4.2. Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony
4.3.
& Terrace
• GF
• FF
Painting Works
5
5.1. Painting of Internal Walls & Ceilings
• GF
• FF
5.2. Painting for External Elevation
• GF
• FF
S.No Description of work
Water proofing Works in all floors
6
6.1. Toilet Water Proofing
6.2. Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
7
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water
& Waste Line incl Pressure testing
• Fixing CP & Sanitary fittings
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain
•Water
Gully Traps
down take& lines
Chambers with connections
complete (Pumps & Valves), Supply & Fixing
Syntex TankCommissioning
• Testing, & Connections and(Pumps & Valves)
Handing Over
Miscellaneous Works in all floors
8 Expansion Joint Treatment Works & Flagging
8.1.
Concrete
8.2. MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
HRIRAM SHRESHTA" VILLAS AT COIMBATORE
TRUCTORS PVT LTD
UCTION CORPORATION PVT.LTD

11.01.15 to 07.02.15 Block-13


Total (113,115,117,119,111,112,114,1 9 Nos x 1685 sft x Rs. 1395/ s
17A,118 ) -
Claim. Block-13 (113,115,117,119) 4 Nos x 1685 sft x Rs. 1395/ s

Percentage of work
Payment Value of work com
Upto completed Upto previous
modality current bill
previous Bill bill

30%

6%
2.00% 0.00% 188,046
1.00% 0.00% 94,023
1.00% 0.00% 94,023
1.00% 0.00% 94,023
1.00% 0.00% 94,023
0.00% 0.00% -
0.00% 0.00% -
0.00% 0.00% -
Percentage of work
Payment Value of work com
Upto completed Upto previous
modality current bill
previous Bill bill
4% 3.00% 0.00% 282,069
7% 1.56% 2.19% 146,911
0.00% 0.00% -
6% 0.00% 1.00% -
7% 0.00% 0.00% -
15% 0.00% 0.00% -
0.00% 0.00% -
2% 0.00% 0.38% -
2% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
5% 0.00% 0.00% -
20% 0.00% 0.00% -
0.00% 0.00% -
4% 0.00% 0.00% -
4% 0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -
0.00% 0.00% -
Percentage of work
Payment Value of work com
Upto completed Upto previous
modality current bill
previous Bill bill
3% 0.00% 0.00% -
3% 0.00% 0.00% -
2% 0.00% 0.00% -
14% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
1% 0.00% 0.00% -
1% 0.00% 0.00% -
10% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -
Percentage of work
Payment Value of work com
Upto completed Upto previous
modality current bill
previous Bill bill
4% 0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -
4% 0.00% 0.00% -
0.00% 0.00% -
1% 0.00% 0.00% -
2% 0.00% 0.00% -
0.00% 0.00% -
0.50% 0.00% 0.00% -
0.25% 0.00% 0.00% -
0.25% 0.00% 0.00% -
3% 0.00% 0.00% -
1% 0.00% 0.00% -
2% 0.00% 0.00% -
-
100% 10.56% 3.56% 993,118

Checked by
SCCPL Er
1685 sft x Rs. 1395/ sf Rs 21,155,175
1685 sft x Rs. 1395/ sf Rs 9,402,300

Value of work completed


Current bill Cumulative bill

- 188,046
- 94,023
- 94,023
- 94,023
- 94,023
- -
- -
- -
Value of work completed
Current bill Cumulative bill
- 282,069
205,675 352,586
- -
94,023 94,023
- -
- -
- -
35,259 35,259
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Value of work completed
Current bill Cumulative bill
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Value of work completed
Current bill Cumulative bill
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
334,957 1,328,075

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 113 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 4.50% 35,259 105,776 141,035
First Floor
- - -
• Columns and Slope Roof
6% 4.00% - 94,023 94,023
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.500% 8.50% 246,810 199,799 446,609

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 115 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 35,259 - 35,259
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 0.50% 246,810 11,753 258,563

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 117 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 35,259 - 35,259
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 0.50% 246,810 11,753 258,563

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 119 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.75% 4.25% 41,135 99,899 141,035
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.5% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.75% 4.75% 252,687 111,652 364,339

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESH
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPOR
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

S.No Description of work

Structure
1
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam

Marking & Earthwork


PCC for footing
RCC for footing
S.No Description of work

Column upto plinthbeam


RCC for plinth beam

1.2. Super-structure - RCC frame

Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase
Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab

Masonry & Plastering


2

2.1. Masonry Works

• GF Masonry Works up to Roof including Lintel


and Sunshades
• FF Masonry Works up to Roof including Lintel,
Lofts and Sunshades
S.No Description of work

2.2. Plastering of ceiling and walls

• GF
• FF

2.3. Plastering in External Elevation in all floors

Flooring, Dado & Skirting


3

3.1. Flooring & Skirting

• GF-Foyer, Living, Dining, Kitchen, Bedroom


• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and
other finishing Works
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with
Sink
• FF All Toilets

3.3. Staircase & Landings, etc.,


S.No Description of work

Joinery & MS Railing Works


4
4.1. Door frames & Shutters
• GF
• FF
4.2. Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony &
4.3.
Terrace
• GF
• FF
Painting Works
5
5.1. Painting of Internal Walls & Ceilings
• GF
• FF
5.2. Painting for External Elevation
S.No Description of work

• GF
• FF

Water proofing Works in all floors


6

6.1. Toilet Water Proofing

6.2. Terrace, balcony water Proofing

Plumbing & Sanitary Works in all floors


7

7.1. Internal Plumbing and Sanitary Works

• Marking, Wall Chasing, Pipe Works for Water &


Waste Line incl Pressure testing

• Fixing CP & Sanitary fittings

7.2. External Plumbing and Sanitary lines


S.No Description of work

• Pipe Works for Water Line, Waste Line & Rain


Water down take lines

• Gully Traps & Chambers with connections


complete (Pumps & Valves), Supply & Fixing
Syntex Tank & Connections (Pumps & Valves)

• Testing, Commissioning and Handing Over

Miscellaneous Works in all floors


8

Expansion Joint Treatment Works & Flagging


8.1.
Concrete

8.2. MS Staircase to terrace & Fencing for site

TOTAL
S.No Description of work

Prepared by
SCCPL Er
RAM SHRESHTA" VILLAS AT COIMBATORE
UCTORS PVT LTD
TION CORPORATION PVT.LTD

11.01.15 to 07.02.15
Block-14
Total (120,121,123,124,126A,127,1 11 Nos x 1685 sft x Rs. 1395/ s
28,130,122,126,129 ) -

Block-14
Claim. (120,121,123,124,126,126A,1 9 Nos x 1685 sft x Rs. 1395/ sf
27,128,130)

Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

30%

6%

2.00% 0.00% 423,104


1.00% 0.00% 211,552
1.00% 0.00% 211,552
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

1.00% 0.00% 211,552


1.00% 0.00% 211,552
-
-

-
4% 3.00% 0.00% 634,655
7% 1.19% 2.47% 252,687
0.00% 0.00% -
6% 0.00% 0.89% -
7% 0.00% 0.00% -

15% 0.00% 0.00% -

0.00% 0.00% -

2% 0.00% 0.44% -

2% 0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.00% 0.00% -

3% 0.00% 0.00% -
3% 0.00% 0.00% -

5% 0.00% 0.00% -

20% 0.00% 0.00% -

0.00% 0.00% -

4% 0.00% 0.00% -
4% 0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -

2% 0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

14% 0.00% 0.00% -

0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
1% 0.00% 0.00% -
1% 0.00% 0.00% -
10% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

2% 0.00% 0.00% -
2% 0.00% 0.00% -

4% 0.00% 0.00% -

2% 0.00% 0.00% -

2% 0.00% 0.00% -

4% 0.00% 0.00% -

0.00% 0.00% -

1% 0.00% 0.00% -

2% 0.00% 0.00% -

0.00% 0.00% -
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.50% 0.00% 0.00% -

0.25% 0.00% 0.00% -

0.25% 0.00% 0.00% -

3% 0.00% 0.00% -

1% 0.00% 0.00% -

2% 0.00% 0.00% -

-
100% 10.19% 3.81% 2,156,653
Percentage of work
Value of work c
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

Checked by
SCCPL Er
1685 sft x Rs. 1395/ s Rs 25,856,325

1685 sft x Rs. 1395/ sf Rs 21,155,175

Value of work completed

Current bill Cumulative bill

- 423,104
- 211,552
- 211,552
Value of work completed

Current bill Cumulative bill

- 211,552
- 211,552
- -
- -

- -
- 634,655
523,003 775,690
- -
188,046 188,046
- -

- -

- -

94,023 94,023

- -
Value of work completed

Current bill Cumulative bill

- -

- -
- -

- -

- -

- -

- -
- -
- -
- -
- -
- -
- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Value of work completed

Current bill Cumulative bill

- -
- -

- -

- -

- -

- -

- -

- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -

- -
805,072 2,961,725
Value of work completed

Current bill Cumulative bill

Verified by
SCPL Er
Value of work completed

Current bill Cumulative bill

1,386,839.25
1,574,885.25
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 120 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.50% 2.50% 11,753 58,764 70,517
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 3.00% 223,305 70,517 293,822

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 121 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.50% 2.50% 11,753 58,764 70,517
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 3.00% 223,305 70,517 293,822

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 123 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.75% 4.25% 41,135 99,899 141,035
First Floor
- - -
• Columns and Slope Roof
6% 4.00% - 94,023 94,023
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.75% 8.75% 252,687 205,675 458,362

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 124 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.75% 4.25% 41,135 99,899 141,035
First Floor
- - -
• Columns and Slope Roof
6% 4.00% - 94,023 94,023
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.75% 8.75% 252,687 205,675 458,362

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 126 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 35,259 - 35,259
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 0.50% 246,810 11,753 258,563

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 126A (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 35,259 - 35,259
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 0.50% 246,810 11,753 258,563

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.

4
4.1.
4.2.

4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.
8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILL

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam

Marking & Earthw


PCC for foo
RCC for foo
Column upto plinthb
RCC for plinth b

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshad
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take
lines
• Gully Traps & Chambers with connections complete (Pumps &
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valv
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15
VILLA 127 (4 BHK) - 1685 sft x Rs. 1395/ sft

Percentage of work
Payment Upto Value of work comple
completed
current Upto
modality previous
bill previous bill
Bill
30%

6%
2.00% 47,012
1.00% 23,506
1.00% 23,506
1.00% 23,506
1.00% 23,506
-
-
-
4% 3.00% 70,517
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 9% 0% 211,552

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,350,575

Value of work completed


Current bill Cumulative bill

- 47,012
- 23,506
- 23,506
- 23,506
- 23,506
- -
- -
- -
- 70,517
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- 211,552

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 128 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 4.50% 35,259 105,776 141,035
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 5.00% 246,810 117,529 364,339

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 130 (4 BHK) - 1685 sft x Rs. 1395/ sft Rs 2,350,575

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 47,012 - 47,012


PCC for footing 1.00% 23,506 - 23,506
RCC for footing 1.00% 23,506 - 23,506
Column upto plinthbeam 1.00% 23,506 - 23,506
RCC for plinth beam 1.00% 23,506 - 23,506
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 70,517 - 70,517
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.75% 4.25% 41,135 99,899 141,035
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 11,753 11,753
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.75% 4.75% 252,687 111,652 364,339

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : THIRD RUNNING BILL
BILLING PERIOD 11.01.15 to 07.02.15
Block-15
Total (131,132,133,135,135A,136, 11 Nos x 1475 sft x Rs. 1395/ sft Rs 22,633,875
137,138,139,140,141 ) -

Block-15
Claim. (131,132,133,135,135A,136, 10Nos x 1475 sft x Rs. 1395/ sft Rs 20,576,250
137,138,140,141)

Percentage of work
Value of work completed
completed
Payment
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill

Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam 6%

Marking & Earthwork 0.70% 1.30% 144,034 267,491 411,525


PCC for footing 0.10% 0.90% 20,576 185,186 205,763
RCC for footing 0.10% 0.80% 20,576 164,610 185,186
Column upto plinthbeam 0.10% 0.60% 20,576 123,458 144,034
RCC for plinth beam 0.10% 0.00% 20,576 - 20,576
0.00% 0.00% - - -
1.2. Super-structure - RCC frame
0.00% 0.00% - - -
Ground Floor
0.00% 0.00% - - -
• Columns & Staircase First Flight
4% 0.30% 0.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase
Second Flight 7% 0.00% 0.60% - 123,458 123,458
First Floor
0.00% 0.00% - - -
• Columns and Slope Roof
6% 0.00% 0.00% - - -
• FF Roof Slab
7% 0.00% 0.00% - - -
Masonry & Plastering
2 15% 0.00% 0.00% - - -
2.1. Masonry Works
0.00% 0.00% - - -
• GF Masonry Works up to Roof including Lintel
and Sunshades 2% 0.00% 0.05% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel,
Lofts and Sunshades 2% 0.00% 0.00% - - -

2.2. Plastering of ceiling and walls


0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
2.3. Plastering in External Elevation in all floors
5% 0.00% 0.00% - - -
Flooring, Dado & Skirting
3 20% 0.00% 0.00% - - -
3.1. Flooring & Skirting
0.00% 0.00% - - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% 0.00% 0.00% - - -
• FF-All Bedrooms, lobby & Balconies
4% 0.00% 0.00% - - -
• Clay tiling at all Open terraces
2% 0.00% 0.00% - - -
• Car Park & All round villa flagging concrete and
other finishing Works 2% 0.00% 0.00% - - -
3.2. All Dadoo, Granite & Flooring
0.00% 0.00% - - -
• GF Toilet, Dining & Kitchen Granite Works with
Sink 3% 0.00% 0.00% - - -
• FF All Toilets
3% 0.00% 0.00% - - -
3.3. Staircase & Landings, etc.,
2% 0.00% 0.00% - - -
Percentage of work
Value of work completed
completed
Payment
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill
Joinery & MS Railing Works
4 14% 0.00% 0.00% - - -
4.1. Door frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
4.2. Window frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
MS Railing Works for Windows, Staircase, Balcony &
4.3.
Terrace 0.00% 0.00% - - -

• GF
1% 0.00% 0.00% - - -
• FF
1% 0.00% 0.00% - - -
Painting Works
5 10% 0.00% 0.00% - - -

5.1. Painting of Internal Walls & Ceilings


0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
5.2. Painting for External Elevation
0.00% 0.00% - - -
• GF
2% 0.00% 0.00% - - -
• FF
2% 0.00% 0.00% - - -
Water proofing Works in all floors
6 4% 0.00% 0.00% - - -
6.1. Toilet Water Proofing
2% 0.00% 0.00% - - -
6.2. Terrace, balcony water Proofing
2% 0.00% 0.00% - - -
Plumbing & Sanitary Works in all floors
7 4% 0.00% 0.00% - - -

7.1. Internal Plumbing and Sanitary Works


0.00% 0.00% - - -
• Marking, Wall Chasing, Pipe Works for Water &
Waste Line incl Pressure testing
1% 0.00% 0.00% - - -

• Fixing CP & Sanitary fittings


2% 0.00% 0.00% - - -
7.2. External Plumbing and Sanitary lines
0.00% 0.00% - - -
• Pipe Works for Water Line, Waste Line & Rain
Water down take lines 0.50% 0.00% 0.00% - - -
• Gully Traps & Chambers with connections
complete (Pumps & Valves), Supply & Fixing
0.25% 0.00% 0.00% - - -
Syntex Tank & Connections (Pumps & Valves)

• Testing, Commissioning and Handing Over


0.25% 0.00% 0.00% - - -

Miscellaneous Works in all floors


8 3% 0.00% 0.00% - - -

Expansion Joint Treatment Works & Flagging


8.1.
Concrete 1% 0.00% 0.00% - - -

8.2. MS Staircase to terrace & Fencing for site


2% 0.00% 0.00% - - -
- - -
TOTAL
100% 1.40% 4.25% 288,068 874,491 1,162,558

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 131 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 6.00% - 123,458 123,458
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.00% 6.50% 185,186 133,746 318,932

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 132 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam 1.00% - 20,576 20,576
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 5.00% - 102,881 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.

4
4.1.

4.2.
4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.

8
8.1.
8.2.
Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VI

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Be

Marking & Eart


PCC for f
RCC for f
Column upto plint
RCC for plinth

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flig
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunsh
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line in
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down tak
lines
• Gully Traps & Chambers with connections complete (Pumps
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & V
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site
TOTAL

Prepared by
SCCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15
VILLA 133 (3 BHK) - 1475 sft x Rs. 1395/ sft

Percentage of work
Payment Upto Value of work comp
completed
current Upto
modality previous
bill previous bill
Bill
30%

6%
2.00% 41,153
1.00% -
1.00% -
1.00% -
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 2% 3% 41,153

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,057,625

Value of work completed


Current bill Cumulative bill

- 41,153
20,576 20,576
20,576 20,576
20,576 20,576
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
61,729 102,881

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 135 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 4.00% - 82,305 82,305

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 135A (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed
current Upto
modality previous Current bill Cumulative bill
bill previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2.00% 41,153 - 41,153
PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam 1.00% - 20,576 20,576
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 2% 3% 41,153 61,729 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 136 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 4.00% - 82,305 82,305

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 137 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam 1.00% - 20,576 20,576
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 5.00% - 102,881 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 138(3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam 1.00% - 20,576 20,576
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 5.00% - 102,881 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.

4
4.1.

4.2.
4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.

8
8.1.
8.2.
Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VI

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Be

Marking & Eart


PCC for f
RCC for f
Column upto plint
RCC for plinth

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flig
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunsh
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line in
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down tak
lines
• Gully Traps & Chambers with connections complete (Pumps
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & V
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site
TOTAL

Prepared by
SCCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15
VILLA 140 (3 BHK) - 1475 sft x Rs. 1395/ sft

Percentage of work
Payment Upto Value of work comp
completed
current Upto
modality previous
bill previous bill
Bill
30%

6%
2.00% -
1.00% -
-
-
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 0% 3% -

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,057,625

Value of work completed


Current bill Cumulative bill

41,153 41,153
20,576 20,576
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
61,729 61,729

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 141 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed
current Upto
modality previous Current bill Cumulative bill
bill previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 1.00% 1.00% 20,576 20,576 41,153
PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam 1.00% - 20,576 20,576
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 1% 4% 20,576 82,305 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESH
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPOR
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

S.No Description of work

Structure
1
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam

Marking & Earthwork


PCC for footing
S.No Description of work

RCC for footing


Column upto plinthbeam
RCC for plinth beam

1.2. Super-structure - RCC frame

Ground Floor

• Columns & Staircase First Flight

• GF Roof and Portico Roof Slab including


Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab

Masonry & Plastering


2

2.1. Masonry Works


S.No Description of work

• GF Masonry Works up to Roof including Lintel


and Sunshades
• FF Masonry Works up to Roof including Lintel,
Lofts and Sunshades
2.2. Plastering of ceiling and walls
• GF
• FF

2.3. Plastering in External Elevation in all floors

Flooring, Dado & Skirting


3

3.1. Flooring & Skirting

• GF-Foyer, Living, Dining, Kitchen, Bedroom

• FF-All Bedrooms, lobby & Balconies

• Clay tiling at all Open terraces


• Car Park & All round villa flagging concrete
and other finishing Works
S.No Description of work

3.2. All Dadoo, Granite & Flooring


• GF Toilet, Dining & Kitchen Granite Works
with Sink
• FF All Toilets

3.3. Staircase & Landings, etc.,

Joinery & MS Railing Works


4

4.1. Door frames & Shutters

• GF
• FF

4.2. Window frames & Shutters

• GF
• FF
S.No Description of work

MS Railing Works for Windows, Staircase,


4.3.
Balcony & Terrace

• GF

• FF

Painting Works
5

5.1. Painting of Internal Walls & Ceilings

• GF
• FF
5.2. Painting for External Elevation
• GF
• FF

Water proofing Works in all floors


6
6.1. Toilet Water Proofing
S.No Description of work

6.2. Terrace, balcony water Proofing

Plumbing & Sanitary Works in all floors


7

7.1. Internal Plumbing and Sanitary Works


• Marking, Wall Chasing, Pipe Works for Water
& Waste Line incl Pressure testing

• Fixing CP & Sanitary fittings

7.2. External Plumbing and Sanitary lines

• Pipe Works for Water Line, Waste Line & Rain


Water down take lines
• Gully Traps & Chambers with connections
complete (Pumps & Valves), Supply & Fixing
Syntex Tank & Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over

Miscellaneous Works in all floors


8
S.No Description of work

Expansion Joint Treatment Works & Flagging


8.1.
Concrete

8.2. MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
HRIRAM SHRESHTA" VILLAS AT COIMBATORE
TRUCTORS PVT LTD
UCTION CORPORATION PVT.LTD

11.01.15 to 07.02.15
Block-16
Total (142,144,144A,145,146,14 9 Nos x 1475 sft x Rs. 1395/ sft
7,148,149,150 ) -

Block-16
Claim. (142,144,145,147,149)
5 Nos x 1475 sft x Rs. 1395/ sft

Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

30%

6%

0.40% 1.60% 41,153


0.20% 0.80% 20,576
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.20% 0.40% 20,576


0.20% 0.00% 20,576
0.20% 0.00% 20,576
0.00% 0.00% -
0.00% 0.00% -

0.00% 0.00% -

4% 0.60% 0.00% 61,729

7% 0.30% 0.90% 30,864

0.00% 0.00% -
6% 0.00% 0.80% -
7% 0.00% 0.00% -

15% 0.00% 0.00% -

0.00% 0.00% -
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

2% 0.00% 0.00% -
2% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -

5% 0.00% 0.00% -

20% 0.00% 0.00% -

0.00% 0.00% -

4% 0.00% 0.00% -

4% 0.00% 0.00% -

2% 0.00% 0.00% -

2% 0.00% 0.00% -
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.00% 0.00% -

3% 0.00% 0.00% -

3% 0.00% 0.00% -

2% 0.00% 0.00% -

14% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -
3% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -
3% 0.00% 0.00% -
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.00% 0.00% -

1% 0.00% 0.00% -

1% 0.00% 0.00% -

10% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -

4% 0.00% 0.00% -

2% 0.00% 0.00% -
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

2% 0.00% 0.00% -

4% 0.00% 0.00% -

0.00% 0.00% -

1% 0.00% 0.00% -

2% 0.00% 0.00% -

0.00% 0.00% -

0.50% 0.00% 0.00% -

0.25% 0.00% 0.00% -

0.25% 0.00% 0.00% -

3% 0.00% 0.00% -
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

1% 0.00% 0.00% -

2% 0.00% 0.00% -
-
100% 2.10% 4.50% 216,051

Checked by
SCCPL Er
1475 sft x Rs. 1395/ sft Rs 18,518,625

1475 sft x Rs. 1395/ sft Rs 10,288,125

Value of work completed

Current bill Cumulative bill

164,610 205,763
82,305 102,881
Value of work completed

Current bill Cumulative bill

41,153 61,729
- 20,576
- 20,576
- -
- -

- -

- 61,729

92,593 123,458

- -
82,305 82,305
- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -
- -
- -
- -
- -

- -

- -

- -

- -

- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -

- -
- -

- -

- -
- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -
- -
- -
- -
- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -
Value of work completed

Current bill Cumulative bill

- -

- -
- -
462,966 679,016

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 142 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.0% 41,153 - 41,153


PCC for footing 1.0% 20,576 - 20,576
RCC for footing 1.0% 20,576 - 20,576
Column upto plinthbeam 1.0% 20,576 - 20,576
RCC for plinth beam 1.0% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.0% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.5% 4.5% 30,864 92,593 123,458
First Floor
- - -
• Columns and Slope Roof
6% 4% - 82,305 82,305
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 8.50% 216,051 174,898 390,949

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 144 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.0% - 41,153 41,153


PCC for footing 1.0% - 20,576 20,576
RCC for footing 1.0% - 20,576 20,576
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 4.00% - 82,305 82,305

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 145 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.0% - 41,153 41,153


PCC for footing 1.0% - 20,576 20,576
RCC for footing 1.0% - 20,576 20,576
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 4.00% - 82,305 82,305

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 147 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.0% - 41,153 41,153


PCC for footing 1.0% - 20,576 20,576
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3.00% - 61,729 61,729

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 149 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.0% - 41,153 41,153


PCC for footing 1.0% - 20,576 20,576
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3.00% - 61,729 61,729

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESH
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPOR
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

S.No Description of work

Structure
1
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam

Marking & Earthwork


PCC for footing
S.No Description of work

RCC for footing


Column upto plinthbeam
RCC for plinth beam

1.2. Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including
Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
2
2.1. Masonry Works
• GF Masonry Works up to Roof including Lintel
and Sunshades
• FF Masonry Works up to Roof including Lintel,
Lofts and Sunshades
2.2. Plastering of ceiling and walls
• GF
S.No Description of work

• FF
2.3. Plastering in External Elevation in all floors
Flooring, Dado & Skirting
3
3.1. Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and
other finishing Works
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with
Sink
• FF All Toilets
3.3. Staircase & Landings, etc.,
Joinery & MS Railing Works
4
4.1. Door frames & Shutters
• GF
• FF
S.No Description of work

4.2. Window frames & Shutters


• GF
• FF
MS Railing Works for Windows, Staircase, Balcony
4.3.
& Terrace
• GF
• FF
Painting Works
5
5.1. Painting of Internal Walls & Ceilings
• GF
• FF
5.2. Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
6
6.1. Toilet Water Proofing
6.2. Terrace, balcony water Proofing
S.No Description of work

Plumbing & Sanitary Works in all floors


7
7.1. Internal Plumbing and Sanitary Works
• Marking, Wall Chasing, Pipe Works for Water &
Waste Line incl Pressure testing
• Fixing CP & Sanitary fittings
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain
•Water
Gully
downTraps
take& lines
Chambers with connections
complete (Pumps & Valves), Supply & Fixing
Syntex Tank & Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
8
Expansion Joint Treatment Works & Flagging
8.1.
Concrete
8.2. MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
S.No Description of work

SCCPL Er
IRAM SHRESHTA" VILLAS AT COIMBATORE
UCTORS PVT LTD
TION CORPORATION PVT.LTD

11.01.15 to 07.02.15
Block-19
Total (169,171,171A,174,177,172, 9 Nos x 1475 sft x Rs. 1395/ sft
173,175,176 ) -

Block-19
Claim. (169,171,171A,174,176,177 6 Nos x 1475 sft x Rs. 1395/ sf
)

Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

30%

6%

1.67% 0.33% 205,763


0.83% 0.17% 102,881
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.83% 0.17% 102,881


0.83% 0.00% 102,881
0.83% 0.00% 102,881
0.00% 0.00% -
0.00% 0.00% -
0.00% 0.00% -
4% 2.58% 0.00% 318,932
7% 0.92% 0.42% 113,169
0.00% 0.00% -
6% 0.00% 0.00% -
7% 0.00% 0.00% -
15% 0.00% 0.00% -
0.00% 0.00% -
2% 0.00% 0.42% -
2% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 8.50% 1.50% 1,049,389

Checked by
Percentage of work
Value of work com
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

SCCPL Er
475 sft x Rs. 1395/ sft Rs 18,518,625

1475 sft x Rs. 1395/ sft Rs 12,345,750

Value of work completed

Current bill Cumulative bill

41,153 246,915
20,576 123,458
Value of work completed

Current bill Cumulative bill

20,576 123,458
- 102,881
- 102,881
- -
- -
- -
- 318,932
51,441 164,610
- -
- -
- -
- -
- -
51,441 51,441
- -
- -
- -
Value of work completed

Current bill Cumulative bill

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Value of work completed

Current bill Cumulative bill

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Value of work completed

Current bill Cumulative bill

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
185,186 1,234,575

Verified by
Value of work completed

Current bill Cumulative bill

SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 169 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.50% 10,288 - 10,288
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 0.50% 195,474 10,288 205,763

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 171 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.0% 41,153 - 41,153


PCC for footing 1.0% 20,576 - 20,576
RCC for footing 1.0% 20,576 - 20,576
Column upto plinthbeam 1.0% 20,576 - 20,576
RCC for plinth beam 1.0% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.0% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.5% 1.0% 10,288 20,576 30,864
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 1.50% 195,474 30,864 226,339

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 171A (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 1.50% 30,864 30,864 61,729
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.5% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 2.00% 216,051 41,153 257,203

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 174 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto Cumulative
previous Current bill
bill previous bill bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.50% 72,017 - 72,017
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 30,864 - 30,864
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.5% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 11.00% 0.50% 226,339 10,288 236,627

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 176 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto Cumulative
previous Current bill
bill previous bill bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 4.00% - 82,305 82,305

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 177 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 1.50% 30,864 - 30,864
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.5% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 10.50% 0.50% 216,051 10,288 226,339

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : THIRD RUNNING BILL
BILLING PERIOD 11.01.15 to 07.02.15
Block-20
Total (178,180,187,180A,181,182,1 10 Nos x 1475 sft x Rs. 1395/ sft Rs 20,576,250
83,184,185,186 ) -

Block-20
Claim. (178,180,181,182,184,186,187 7 Nos x 1475 sft x Rs. 1395/ sft Rs 14,403,375
)

Percentage of work
Value of work completed
completed
Payment
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill

Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam 6%
Marking & Earthwork 0.86% 1.00% 123,458 144,034 267,491
PCC for footing 0.43% 0.43% 61,729 61,729 123,458
RCC for footing 0.43% 0.43% 61,729 61,729 123,458
Column upto plinthbeam 0.43% 0.43% 61,729 61,729 123,458
RCC for plinth beam 0.29% 0.00% 41,153 - 41,153
0.00% 0.00% - - -
1.2. Super-structure - RCC frame
0.00% 0.00% - - -
Ground Floor
0.00% 0.00% - - -
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including 4% 0.86% 0.00% 123,458 - 123,458
Staircase Second Flight 7% 0.14% 0.00% 20,576 - 20,576
First Floor
0.00% 0.00% - - -
• Columns and Slope Roof
6% 0.00% 0.00% - - -
• FF Roof Slab
7% 0.00% 0.00% - - -
Masonry & Plastering
2 15% 0.00% 0.00% - - -
2.1. Masonry Works
• GF Masonry Works up to Roof including Lintel 0.00% 0.00% - - -
and
• FFSunshades
Masonry Works up to Roof including Lintel, 2% 0.00% 0.14% - 20,576 20,576
Lofts and Sunshades 2% 0.00% 0.00% - - -
2.2. Plastering of ceiling and walls
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
2.3. Plastering in External Elevation in all floors
5% 0.00% 0.00% - - -
Flooring, Dado & Skirting
3 20% 0.00% 0.00% - - -
3.1. Flooring & Skirting
0.00% 0.00% - - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% 0.00% 0.00% - - -
• FF-All Bedrooms, lobby & Balconies
4% 0.00% 0.00% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete 2% 0.00% 0.00% - - -
and other finishing Works 2% 0.00% 0.00% - - -
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works 0.00% 0.00% - - -
with Sink 3% 0.00% 0.00% - - -
• FF All Toilets
3% 0.00% 0.00% - - -
3.3. Staircase & Landings, etc.,
2% 0.00% 0.00% - - -
Joinery & MS Railing Works
4 14% 0.00% 0.00% - - -
4.1. Door frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
4.2. Window frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
Percentage of work
Value of work completed
completed
Payment
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill
MS Railing Works for Windows, Staircase,
4.3.
Balcony & Terrace 0.00% 0.00% - - -
• GF
1% 0.00% 0.00% - - -
• FF
1% 0.00% 0.00% - - -
Painting Works
5 10% 0.00% 0.00% - - -
5.1. Painting of Internal Walls & Ceilings
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
5.2. Painting for External Elevation
0.00% 0.00% - - -
• GF
2% 0.00% 0.00% - - -
• FF
2% 0.00% 0.00% - - -
Water proofing Works in all floors
6 4% 0.00% 0.00% - - -
6.1. Toilet Water Proofing
2% 0.00% 0.00% - - -
6.2. Terrace, balcony water Proofing
2% 0.00% 0.00% - - -
Plumbing & Sanitary Works in all floors
7 4% 0.00% 0.00% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water 0.00% 0.00% - - -
& Waste Line incl Pressure testing
1% 0.00% 0.00% - - -
• Fixing CP & Sanitary fittings
2% 0.00% 0.00% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain 0.00% 0.00% - - -
•Water
Gully Traps
down take& lines
Chambers with connections 0.50% 0.00% 0.00% - - -
complete (Pumps & Valves), Supply & Fixing
0.25% 0.00% 0.00% - - -
•Syntex TankCommissioning
Testing, & Connections and
(Pumps & Valves)
Handing Over
0.25% 0.00% 0.00% - - -
Miscellaneous Works in all floors
8 Expansion Joint Treatment Works & Flagging 3% 0.00% 0.00% - - -
8.1.
Concrete 1% 0.00% 0.00% - - -
8.2. MS Staircase to terrace & Fencing for site
2% 0.00% 0.00% - - -
- - -
TOTAL
100% 3.43% 2.43% 493,830 349,796 843,626

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er

1,386,839.25
(543,213.00)
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 178 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.50% 10,288 - 10,288
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 0.50% 195,474 10,288 205,763

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.
4
4.1.

4.2.

4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.
7.2.

8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILL

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam

Marking & Earthw


PCC for foo
RCC for foo
Column upto plinthb
RCC for plinth b

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshad
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing and Sanitary Works
• Marking, Wall Chasing, Pipe Works for Water & Waste Line incl
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take
lines
• Gully Traps & Chambers with connections complete (Pumps &
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valv
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15
VILLA 180 (3 BHK) - 1475 sft x Rs. 1395/ sft

Percentage of work
Payment Upto Value of work comple
completed
current Upto
modality previous
bill previous bill
Bill
30%

6%
2.00% 41,153
1.00% 20,576
1.00% 20,576
1.00% 20,576
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 5% 0% 102,881

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,057,625

Value of work completed


Current bill Cumulative bill

- 41,153
- 20,576
- 20,576
- 20,576
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- 102,881

Verified by
SCPL Er
S.No

1
1.1.

1.2.
2
2.1.

2.2.

2.3.

3
3.1.

3.2.

3.3.

4
4.1.
4.2.

4.3.

5
5.1.

5.2.

6
6.1.
6.2.

7
7.1.

7.2.
8
8.1.
8.2.

Prepared by
SCCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILL

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam

Marking & Earthw


PCC for foo
RCC for foo
Column upto plinthb
RCC for plinth b

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel and Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshad
Plastering of ceiling and walls
• GF
• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing
Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony & Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl
Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take
lines
• Gully Traps & Chambers with connections complete (Pumps &
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valv
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging Concrete
MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
LLAS AT COIMBATORE

PVT.LTD

11.01.15 to 07.02.15
VILLA 181 (3 BHK) - 1475 sft x Rs. 1395/ sft

Percentage of work
Payment Upto Value of work complet
completed
current Upto
modality previous
bill previous bill
Bill
30%

6%
2.00% -
1.00% -
1.00% -
1.00% -
-
-
-
-
4% -
7% -
-
6% -
7% -
15% -
-
2% -
2% -
-
3% -
3% -
5% -
20% -
-
4% -
4% -
2% -
2% -
-
3% -
3% -
2% -
14% -
-
3% -
3% -
-
3% -
3% -
-
1% -
1% -
10% -
-
3% -
3% -
-
2% -
2% -
4% -
2% -
2% -
4% -
-
1% -
2% -
-
0.50% -
0.25% -
0.25% -
3% -
1% -
2% -
-
100% 0% 5% -

Checked by
SCCPL Er
sft x Rs. 1395/ sft Rs 2,057,625

Value of work completed


Current bill Cumulative bill

41,153 41,153
20,576 20,576
20,576 20,576
20,576 20,576
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
102,881 102,881

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 182 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed
current Upto
modality previous Current bill Cumulative bill
bill previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2.00% - 41,153 41,153
PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam 1.00% - 20,576 20,576
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 5% - 102,881 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 182 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed
current Upto
modality previous Current bill Cumulative bill
bill previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 1.00% - 20,576 20,576
PCC for footing - - -
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 1% - 20,576 20,576

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 186 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed
current Upto
modality previous Current bill Cumulative bill
bill previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 2.00% - 41,153 41,153
PCC for footing 1.00% - 20,576 20,576
RCC for footing 1.00% - 20,576 20,576
Column upto plinthbeam 1.00% - 20,576 20,576
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 5% - 102,881 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 187 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.50% 10,288 - 10,288
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 0.50% 195,474 10,288 205,763

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD
BILL NO : THIRD RUNNING BILL
BILLING PERIOD 11.01.15 to 07.02.15
Block-21
Total (194,195,196,198,198A,193, 11 Nos x 1475 sft x Rs. 1395/ s Rs 22,633,875
192,191,190,189A,189 ) -

Claim. Block-21 (194) 1 Nos x 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill

Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam 6%

Marking & Earthwork 2.00% 0.00% 41,153 - 41,153

PCC for footing 1.00% 0.00% 20,576 - 20,576


RCC for footing 1.00% 0.00% 20,576 - 20,576
Column upto plinthbeam 0.00% 1.00% - 20,576 20,576
RCC for plinth beam 0.00% 0.00% - - -
0.00% 0.00% - - -
1.2. Super-structure - RCC frame
0.00% 0.00% - - -
Ground Floor
0.00% 0.00% - - -
• Columns & Staircase First Flight
4% 0.00% 0.00% - - -
• GF Roof and Portico Roof Slab including Staircase
Second Flight 7% 0.00% 0.00% - - -
First Floor
0.00% 0.00% - - -
• Columns and Slope Roof
6% 0.00% 0.00% - - -
• FF Roof Slab
7% 0.00% 0.00% - - -
Masonry & Plastering
2 15% 0.00% 0.00% - - -
2.1. Masonry Works
0.00% 0.00% - - -
• GF Masonry Works up to Roof including Lintel
and Sunshades 2% 0.00% 0.00% - - -
• FF Masonry Works up to Roof including Lintel,
Lofts and Sunshades 2% 0.00% 0.00% - - -
2.2. Plastering of ceiling and walls
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
2.3. Plastering in External Elevation in all floors
5% 0.00% 0.00% - - -
Flooring, Dado & Skirting
3 20% 0.00% 0.00% - - -
3.1. Flooring & Skirting
0.00% 0.00% - - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% 0.00% 0.00% - - -
• FF-All Bedrooms, lobby & Balconies
4% 0.00% 0.00% - - -
• Clay tiling at all Open terraces
2% 0.00% 0.00% - - -
• Car Park & All round villa flagging concrete and
other finishing Works 2% 0.00% 0.00% - - -
3.2. All Dadoo, Granite & Flooring
0.00% 0.00% - - -
• GF Toilet, Dining & Kitchen Granite Works with
Sink 3% 0.00% 0.00% - - -
• FF All Toilets
3% 0.00% 0.00% - - -
3.3. Staircase & Landings, etc.,
2% 0.00% 0.00% - - -
Joinery & MS Railing Works
4 14% 0.00% 0.00% - - -
4.1. Door frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
Percentage of work
Value of work completed
completed
Payment
S.No Description of work
modality Upto Upto previous
current bill Current bill Cumulative bill
previous Bill bill
• FF
3% 0.00% 0.00% - - -
4.2. Window frames & Shutters
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
MS Railing Works for Windows, Staircase, Balcony &
4.3.
Terrace 0.00% 0.00% - - -
• GF
1% 0.00% 0.00% - - -
• FF
1% 0.00% 0.00% - - -
Painting Works
5 10% 0.00% 0.00% - - -
5.1. Painting of Internal Walls & Ceilings
0.00% 0.00% - - -
• GF
3% 0.00% 0.00% - - -
• FF
3% 0.00% 0.00% - - -
5.2. Painting for External Elevation
0.00% 0.00% - - -
• GF
2% 0.00% 0.00% - - -
• FF
2% 0.00% 0.00% - - -
Water proofing Works in all floors
6 4% 0.00% 0.00% - - -
6.1. Toilet Water Proofing
2% 0.00% 0.00% - - -
6.2. Terrace, balcony water Proofing
2% 0.00% 0.00% - - -
Plumbing & Sanitary Works in all floors
7 4% 0.00% 0.00% - - -
7.1. Internal Plumbing and Sanitary Works
• Marking, Wall Chasing, Pipe Works for Water & 0.00% 0.00% - - -
Waste Line incl Pressure testing
1% 0.00% 0.00% - - -
• Fixing CP & Sanitary fittings
2% 0.00% 0.00% - - -
7.2. External Plumbing and Sanitary lines
0.00% 0.00% - - -
• Pipe Works for Water Line, Waste Line & Rain
•Water down
Gully take& lines
Traps Chambers with connections 0.50% 0.00% 0.00% - - -
complete (Pumps & Valves), Supply & Fixing
0.25% 0.00% 0.00% - - -
Syntex Tank & Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
0.25% 0.00% 0.00% - - -
Miscellaneous Works in all floors
8 3% 0.00% 0.00% - - -
Expansion Joint Treatment Works & Flagging
8.1.
Concrete 1% 0.00% 0.00% - - -
8.2. MS Staircase to terrace & Fencing for site
2% 0.00% 0.00% - - -
- - -
TOTAL
100% 4.00% 1.00% 82,305 20,576 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er

1,386,839.25
(1,283,958.00)
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 194 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% - 20,576 20,576
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. •Internal Plumbing
Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 4% 1.00% 82,305 20,576 102,881

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESH
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPOR
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

S.No

1
1.1.
S.No

1.2.
S.No

2
2.1.

2.2.

2.3.

3
3.1.
S.No

3.2.

3.3.

4
4.1.

4.2.
S.No

4.3.

5
5.1.

5.2.

6
S.No

6.1.

6.2.

7
7.1.

7.2.

8
8.1.
S.No

8.2.

Prepared by
SCCPL Er
AME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLA
AME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
AME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV
LL NO : THIRD RUNNING BILL
LLING PERIOD

Description of work

Structure

Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam

Marking & Earthwork


Description of work

PCC for footing

RCC for footing

Column upto plinthbeam

RCC for plinth beam

Super-structure - RCC frame

Ground Floor

• Columns & Staircase First Flight


• GF Roof and Portico Roof Slab including Staircase
Second Flight
First Floor

• Columns and Slope Roof

• FF Roof Slab
Description of work

Masonry & Plastering

Masonry Works
• GF Masonry Works up to Roof including Lintel
and Sunshades
• FF Masonry Works up to Roof including Lintel,
Lofts and Sunshades
Plastering of ceiling and walls

• GF

• FF

Plastering in External Elevation in all floors

Flooring, Dado & Skirting

Flooring & Skirting

• GF-Foyer, Living, Dining, Kitchen, Bedroom

• FF-All Bedrooms, lobby & Balconies


Description of work

• Clay tiling at all Open terraces


• Car Park & All round villa flagging concrete and
other finishing Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with
Sink
• FF All Toilets

Staircase & Landings, etc.,

Joinery & MS Railing Works

Door frames & Shutters

• GF

• FF

Window frames & Shutters

• GF
Description of work

• FF
MS Railing Works for Windows, Staircase, Balcony &
Terrace
• GF

• FF

Painting Works

Painting of Internal Walls & Ceilings

• GF

• FF

Painting for External Elevation

• GF

• FF

Water proofing Works in all floors


Description of work

Toilet Water Proofing

Terrace, balcony water Proofing

Plumbing & Sanitary Works in all floors

Internal Plumbing and Sanitary Works


• Marking, Wall Chasing, Pipe Works for Water &
Waste Line incl Pressure testing

• Fixing CP & Sanitary fittings

External Plumbing and Sanitary lines


• Pipe Works for Water Line, Waste Line & Rain
Water down take lines
• Gully Traps & Chambers with connections
complete (Pumps & Valves), Supply & Fixing
Syntex Tank & Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over

Miscellaneous Works in all floors


Expansion Joint Treatment Works & Flagging
Concrete
Description of work

MS Staircase to terrace & Fencing for site

TOTAL

epared by
CCPL Er
RAM SHRESHTA" VILLAS AT COIMBATORE
UCTORS PVT LTD
TION CORPORATION PVT.LTD

11.01.15 to 07.02.15
Block-25
Total (231,226,227,228,229,234A, 9 Nos x 1475 sft x Rs. 1395/ sft
230,232,234 ) -

Block-25
Claim. (226,228,229,230,231,234A)
6 Nos x 1475 sft x Rs. 1395/ sft

Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

30%

6%

1.00% 1.00% 123,458


Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.50% 0.50% 61,729

0.50% 0.00% 61,729

0.50% 0.00% 61,729

0.50% 0.00% 61,729

0.00% 0.00% -

0.00% 0.00% -

0.00% 0.00% -

4% 0.50% 0.50% 61,729

7% 0.00% 0.50% -

0.00% 0.00% -

6% 0.00% 0.00% -

7% 0.00% 0.00% -
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

15% 0.00% 0.00% -

0.00% 0.00% -

2% 0.00% 0.38% -

2% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -

3% 0.00% 0.00% -

5% 0.00% 0.00% -

20% 0.00% 0.00% -

0.00% 0.00% -

4% 0.00% 0.00% -

4% 0.00% 0.00% -
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

2% 0.00% 0.00% -

2% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -

3% 0.00% 0.00% -

2% 0.00% 0.00% -

14% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -

3% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

3% 0.00% 0.00% -

0.00% 0.00% -

1% 0.00% 0.00% -

1% 0.00% 0.00% -

10% 0.00% 0.00% -

0.00% 0.00% -

3% 0.00% 0.00% -

3% 0.00% 0.00% -

0.00% 0.00% -

2% 0.00% 0.00% -

2% 0.00% 0.00% -

4% 0.00% 0.00% -
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

2% 0.00% 0.00% -

2% 0.00% 0.00% -

4% 0.00% 0.00% -

0.00% 0.00% -

1% 0.00% 0.00% -

2% 0.00% 0.00% -

0.00% 0.00% -

0.50% 0.00% 0.00% -

0.25% 0.00% 0.00% -

0.25% 0.00% 0.00% -

3% 0.00% 0.00% -

1% 0.00% 0.00% -
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

2% 0.00% 0.00% -

100% 3.50% 2.88% 432,101

Checked by
SCCPL Er
1475 sft x Rs. 1395/ sft Rs 18,518,625

1475 sft x Rs. 1395/ sft Rs 12,345,750

work completed

Current bill Cumulative bill

123,458 246,915
work completed

Current bill Cumulative bill

61,729 123,458

- 61,729

- 61,729

- 61,729

- -

- -

- -

61,729 123,458

61,729 61,729

- -

- -

- -
work completed

Current bill Cumulative bill

- -

- -

46,297 46,297

- -

- -

- -

- -

- -

- -

- -

- -

- -
work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -
work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -
work completed

Current bill Cumulative bill

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -

- -
work completed

Current bill Cumulative bill

- -

- -

354,940 787,042

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 226 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% - 61,729 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.75% - 15,432 15,432
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 6% 3.75% 123,458 77,161 200,618

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 228 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3.00% - 61,729 61,729

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 229 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3.00% - 61,729 61,729

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 230(3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% - 41,153 41,153


PCC for footing 1.00% - 20,576 20,576
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3% - 61,729 61,729

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 231 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.75% - 15,432 15,432
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9% 0.75% 185,186 15,432 200,618

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 234A (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2% 41,153 - 41,153


PCC for footing 1% 20,576 - 20,576
RCC for footing 1% 20,576 - 20,576
Column upto plinthbeam 1% 20,576 - 20,576
RCC for plinth beam 1% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 3% - 61,729 61,729
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.75% - 15,432 15,432
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 6% 3.75% 123,458 77,161 200,618

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESH
NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT
NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPOR
BILL NO : THIRD RUNNING BILL
BILLING PERIOD

S.No

1
1.1.
S.No

1.2.

2
2.1.

2.2.
S.No

2.3.

3
3.1.

3.2.

3.3.

4
4.1.
S.No

4.2.

4.3.

5
5.1.

5.2.

6
6.1.
6.2.
S.No

7
7.1.

7.2.

8
8.1.
8.2.

Prepared by
SCCPL Er
AME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLA
AME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD
AME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PV
LL NO : THIRD RUNNING BILL
LLING PERIOD

Description of work

Structure
Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam
Marking & Earthwork
PCC for footing
RCC for footing
Description of work

Column upto plinthbeam


RCC for plinth beam

Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase
Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
Masonry Works
• GF Masonry Works up to Roof including Lintel
and Sunshades
• FF Masonry Works up to Roof including Lintel,
Lofts and Sunshades
Plastering of ceiling and walls
• GF
Description of work

• FF
Plastering in External Elevation in all floors
Flooring, Dado & Skirting
Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and
other finishing Works
All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with
Sink
• FF All Toilets
Staircase & Landings, etc.,
Joinery & MS Railing Works
Door frames & Shutters
• GF
• FF
Description of work

Window frames & Shutters


• GF
• FF
MS Railing Works for Windows, Staircase, Balcony &
Terrace
• GF
• FF
Painting Works
Painting of Internal Walls & Ceilings
• GF
• FF
Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
Toilet Water Proofing
Terrace, balcony water Proofing
Description of work

Plumbing & Sanitary Works in all floors


Internal Plumbing and Sanitary Works
• Marking, Wall Chasing, Pipe Works for Water &
Waste Line incl Pressure testing
• Fixing CP & Sanitary fittings
External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain
Water down
• Gully take& lines
Traps Chambers with connections
complete (Pumps & Valves), Supply & Fixing
Syntex Tank & Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
Expansion Joint Treatment Works & Flagging
Concrete
MS Staircase to terrace & Fencing for site

TOTAL

epared by
CCPL Er
RAM SHRESHTA" VILLAS AT COIMBATORE
UCTORS PVT LTD
TION CORPORATION PVT.LTD

11.01.15 to 07.02.15
Block-26
Total (235,245,236,237,238,239, 11 Nos x 1475 sft x Rs. 1395/ sft
240,241,243,234A,244) -

Block-26
Claim. (235,237,239,245)
4 Nos x 1475 sft x Rs. 1395/ sft

Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

30%

6%
0.75% 1.00% 61,729
0.25% 0.50% 20,576
0.25% 0.25% 20,576
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.25% 0.00% 20,576


0.25% 0.00% 20,576
0.00% 0.00% -
0.00% 0.00% -
0.00% 0.00% -
4% 0.75% 0.00% 61,729
7% 0.13% 0.31% 10,288
0.00% 0.00% -
6% 0.00% 0.00% -
7% 0.00% 0.00% -
15% 0.00% 0.00% -
0.00% 0.00% -
2% 0.00% 0.13% -
2% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

3% 0.00% 0.00% -
5% 0.00% 0.00% -
20% 0.00% 0.00% -
0.00% 0.00% -
4% 0.00% 0.00% -
4% 0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
2% 0.00% 0.00% -
14% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
1% 0.00% 0.00% -
1% 0.00% 0.00% -
10% 0.00% 0.00% -
0.00% 0.00% -
3% 0.00% 0.00% -
3% 0.00% 0.00% -
0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -
4% 0.00% 0.00% -
2% 0.00% 0.00% -
2% 0.00% 0.00% -
Percentage of work
Value of work completed
completed
Payment
modality Upto Upto previous
current bill
previous Bill bill

4% 0.00% 0.00% -
0.00% 0.00% -
1% 0.00% 0.00% -
2% 0.00% 0.00% -
0.00% 0.00% -
0.50% 0.00% 0.00% -
0.25% 0.00% 0.00% -
0.25% 0.00% 0.00% -
3% 0.00% 0.00% -
1% 0.00% 0.00% -
2% 0.00% 0.00% -
-
100% 2.63% 2.19% 216,051
216051

Checked by
SCCPL Er
1475 sft x Rs. 1395/ sft Rs 22,633,875

1475 sft x Rs. 1395/ sft Rs 8,230,500

work completed

Current bill Cumulative bill

82,305 144,034
41,153 61,729
20,576 41,153
work completed

Current bill Cumulative bill

- 20,576
- 20,576
- -
- -
- -
- 61,729 1.17
25,720 36,008
- -
- -
- -
- -
- -
10,288 10,288
- -
- -
- -
work completed

Current bill Cumulative bill

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
work completed

Current bill Cumulative bill

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
work completed

Current bill Cumulative bill

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
180,042 396,093

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 235 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed
current Upto
modality previous Current bill Cumulative bill
bill previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam
6%
Marking & Earthwork 1% 20,576 - 20,576
PCC for footing 1% - 20,576 20,576
RCC for footing 1% - 20,576 20,576
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% - - -
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% - - -
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 1% 2.00% 20,576 41,153 61,729

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15


VILLA 237 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Payment Upto Value of work completed
S.No Description of work completed
current Upto
modality previous Current bill Cumulative bill
bill previous bill
Bill
Structure
1 30%
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam 6%
Marking & Earthwork 0% 2% - 41,153 41,153
PCC for footing 1% - 20,576 20,576
RCC for footing - - -
Column upto plinthbeam - - -
RCC for plinth beam - - -
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase 4% - - -
Second Flight 7% - - -
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
• GF Masonry Works up to Roof including Lintel and - - -
Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts 2% - - -
and Sunshades 2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and 2% - - -
other finishing Works 2% - - -
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with - - -
Sink 3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
MS Railing Works for Windows, Staircase, Balcony & 3% - - -
4.3.
Terrace - - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal
• Marking,Plumbing and Sanitary
Wall Chasing, PipeWorks
Works for Water & - - -
Waste Line incl Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain - - -
•Water
Gully
downTraps
take& lines
Chambers with connections 0.50% - - -
complete (Pumps & Valves), Supply & Fixing Syntex
0.25% - - -
•Tank & Connections
Testing, (Pumpsand
Commissioning & Valves)
Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 0% 3% - 61,729 61,729

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" V

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATIO

BILL NO : THIRD RUNNING BILL

BILLING PERIOD

S.No Description of work

Structure
1
1.1. Sub-structure, Foundations
Marking, Earth Work, PCC, Footing, Column up to
Plinth, Plinth Beam

Marking & Earthwork


PCC for footing
RCC for footing
Column upto plinthbeam
RCC for plinth beam

1.2. Super-structure - RCC frame


Ground Floor
• Columns & Staircase First Flight
• GF Roof and Portico Roof Slab including Staircase
Second Flight
First Floor
• Columns and Slope Roof
• FF Roof Slab
Masonry & Plastering
2
2.1. Masonry Works
• GF Masonry Works up to Roof including Lintel and
Sunshades
• FF Masonry Works up to Roof including Lintel, Lofts
and Sunshades
2.2. Plastering of ceiling and walls
• GF
• FF
2.3. Plastering in External Elevation in all floors
Flooring, Dado & Skirting
3
3.1. Flooring & Skirting
• GF-Foyer, Living, Dining, Kitchen, Bedroom
• FF-All Bedrooms, lobby & Balconies
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and
other finishing Works
3.2. All Dadoo, Granite & Flooring
• GF Toilet, Dining & Kitchen Granite Works with
Sink
• FF All Toilets
3.3. Staircase & Landings, etc.,
Joinery & MS Railing Works
4
4.1. Door frames & Shutters
• GF
• FF
4.2. Window frames & Shutters
• GF
• FF
MS Railing Works for Windows, Staircase, Balcony &
4.3.
Terrace
• GF
• FF
Painting Works
5
5.1. Painting of Internal Walls & Ceilings
• GF
• FF
5.2. Painting for External Elevation
• GF
• FF
Water proofing Works in all floors
6
6.1. Toilet Water Proofing
6.2. Terrace, balcony water Proofing
Plumbing & Sanitary Works in all floors
7
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water &
Waste Line incl Pressure testing
• Fixing CP & Sanitary fittings
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain
Water down take lines
• Gully Traps & Chambers with connections
complete (Pumps & Valves), Supply & Fixing Syntex
Tank & Connections (Pumps & Valves)
• Testing, Commissioning and Handing Over
Miscellaneous Works in all floors
8
8.1. Expansion Joint Treatment Works & Flagging Concrete
8.2. MS Staircase to terrace & Fencing for site

TOTAL

Prepared by
SCCPL Er
SHRESHTA" VILLAS AT COIMBATORE

S PVT LTD

CORPORATION PVT.LTD

11.01.15 to 07.02.15

VILLA 239 (3 BHK) - 1475 sft x Rs. 1395/ sft

Percentage of work
Value of work completed
completed
Payment
modality Upto
current Upto
previous Current bill
bill previous bill
Bill

30%

6%

2% - 41,153
- -
- -
- -
- -
- -
- -
- -
4% - -
7% - -
- -
6% - -
7% - -
15% - -
- -
2% - -

2% - -

- -
3% - -
3% - -
5% - -
20% - -
- -
4% - -
4% - -
2% - -

2% - -

- -
3% - -
3% - -
2% - -
14% - -
- -
3% - -
3% - -
- -
3% - -
3% - -
- -
1% - -
1% - -
10% - -
- -
3% - -
3% - -
- -
2% - -
2% - -
4% - -
2% - -
2% - -
4% - -
- -
1% - -
2% - -
- -

0.50% - -

0.25% - -

0.25% - -
3% - -
1% - -
2% - -
- -
100% 0% 2% - 41,153

Checked by
SCCPL Er
Rs 2,057,625

ompleted

Cumulative bill

41,153
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
41,153

Verified by
SCPL Er
NAME OF THE WORK : CONSTRUCTION OF "SHRIRAM SHRESHTA" VILLAS AT COIMBATORE

NAME OF THE OWNER : M/S. SHRIPROP CONSTRUCTORS PVT LTD

NAME OF THE CONTRACTOR : M/S. SENTHIL CONSTRUCTION CORPORATION PVT.LTD

BILL NO : THIRD RUNNING BILL

BILLING PERIOD 11.01.15 to 07.02.15

VILLA 245 (3 BHK) - 1475 sft x Rs. 1395/ sft Rs 2,057,625

Percentage of work
Value of work completed
completed
Payment
S.No Description of work Upto
modality current Upto
previous Current bill Cumulative bill
bill previous bill
Bill

Structure
1 30%
1.1. Sub-structure, Foundations

Marking, Earth Work, PCC, Footing, Column up to Plinth, Plinth Beam


6%

Marking & Earthwork 2.00% 41,153 - 41,153


PCC for footing 1.00% 20,576 - 20,576
RCC for footing 1.00% 20,576 - 20,576
Column upto plinthbeam 1.00% 20,576 - 20,576
RCC for plinth beam 1.00% 20,576 - 20,576
- - -
1.2. Super-structure - RCC frame
- - -
Ground Floor
- - -
• Columns & Staircase First Flight
4% 3.00% 61,729 - 61,729
• GF Roof and Portico Roof Slab including Staircase Second Flight
7% 0.50% 1.25% 10,288 25,720 36,008
First Floor
- - -
• Columns and Slope Roof
6% - - -
• FF Roof Slab
7% - - -
Masonry & Plastering
2 15% - - -
2.1. Masonry Works
- - -
• GF Masonry Works up to Roof including Lintel and Sunshades
2% 0.50% - 10,288 10,288
• FF Masonry Works up to Roof including Lintel, Lofts and Sunshades
2% - - -
2.2. Plastering of ceiling and walls
- - -
• GF
3% - - -
• FF
3% - - -
2.3. Plastering in External Elevation in all floors
5% - - -
Flooring, Dado & Skirting
3 20% - - -
3.1. Flooring & Skirting
- - -
• GF-Foyer, Living, Dining, Kitchen, Bedroom
4% - - -
• FF-All Bedrooms, lobby & Balconies
4% - - -
• Clay tiling at all Open terraces
• Car Park & All round villa flagging concrete and other finishing 2% - - -
Works 2% - - -
3.2. All Dadoo, Granite & Flooring
- - -
• GF Toilet, Dining & Kitchen Granite Works with Sink
3% - - -
• FF All Toilets
3% - - -
3.3. Staircase & Landings, etc.,
2% - - -
Joinery & MS Railing Works
4 14% - - -
4.1. Door frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.2. Window frames & Shutters
- - -
• GF
3% - - -
• FF
3% - - -
4.3. MS Railing Works for Windows, Staircase, Balcony & Terrace
- - -
• GF
1% - - -
• FF
1% - - -
Painting Works
5 10% - - -
5.1. Painting of Internal Walls & Ceilings
- - -
• GF
3% - - -
• FF
3% - - -
5.2. Painting for External Elevation
- - -
• GF
2% - - -
• FF
2% - - -
Water proofing Works in all floors
6 4% - - -
6.1. Toilet Water Proofing
2% - - -
6.2. Terrace, balcony water Proofing
2% - - -
Plumbing & Sanitary Works in all floors
7 4% - - -
7.1. Internal Plumbing
• Marking, and Sanitary
Wall Chasing, PipeWorks
Works for Water & Waste Line incl - - -
Pressure testing
1% - - -
• Fixing CP & Sanitary fittings
2% - - -
7.2. External Plumbing and Sanitary lines
• Pipe Works for Water Line, Waste Line & Rain Water down take - - -
lines
• Gully Traps & Chambers with connections complete (Pumps & 0.50% - - -
Valves), Supply & Fixing Syntex Tank & Connections (Pumps & Valves) 0.25% - - -
• Testing, Commissioning and Handing Over
0.25% - - -
Miscellaneous Works in all floors
8 3% - - -
8.1. Expansion Joint Treatment Works & Flagging Concrete
1% - - -
8.2. MS Staircase to terrace & Fencing for site
2% - - -
- - -
TOTAL
100% 9.50% 1.75% 195,474 36,008 231,483

Prepared by Checked by Verified by


SCCPL Er SCCPL Er SCPL Er
Column Portico
Plinth
Block Total value of E. Pedestal upto gf beam and
S.no Type Villa No P.C.C FOOTING beam
No work WORK concrete slab slab
concrete
concrete concrete

1 6 4BHK Villa-50 2350575 - - - - - 3.0 3.5

2 6 4BHK Villa-54 2350575 - - - - - - 3.5

3 6 4BHK Villa-56 2350575 - - - - - - 3.5

4 7 4BHK Villa-60 2350575 - - - - 1 3 3.5

5 7 4BHK Villa-65 2350575 - - - - - - 3.5

6 8 4BHK Villa-66 2350575 - - - - - - 1.5

7 8 4BHK Villa-68 2350575 - - - - - - 3.5

8 8 4BHK Villa-70 2350575 - - - - 1 3 3.5

9 8 4BHK Villa-72 2350575 - - - - 1 3 3.5

10 10 4BHK Villa-91 2350575 - - - - - - 1.5

11 13 4BHK Villa-113 2350575 - - - - - - 3.5

12 13 4BHK Villa-115 2350575 - - - - - - 1.5

13 13 4BHK Villa-117 2350575 - - - - - - 3.5

14 13 4BHK Villa-119 2350575 - - - - - - 1.5


15 8 4BHK Villa-67 2350575 - - - - 1 3 3.5

16 7 4BHK Villa-59 2350575 - - - - 1 3 3.5

17 7 4BHK Villa-58 2350575 - - - - 1 3 3.5

18 7 4BHK Villa -57 2350575 - - - - 1 3 3.5

19 8 4BHK Villa-69 2350575 - - 1 1 1 3 3.5

20 16 3BHK Villa-142 2057625 - - - - - - 3.5

21 19 3BHK Villa -169 2057625 - - - - - - 3.5

22 19 3BHK Villa-171A 2057625 - - - - - - 3.5

23 19 3BHK Villa-171 2057625 - - - - - 3 3.5

24 19 3BHK Villa-174 2057625 - - - - - - 3.5

25 19 3BHK Villa-177 2057625 - - - - - - 3.5

SIVAKUMAR
1 9 4BHK Villa-72a 2350575 - - - - - - 1.5

2 9 4BHK Villa-73 2350575 - - - - - - 1.5

3 9 4BHK Villa-74 2350575 - - - - - - 1.5

4 8 4BHK Villa-75 2350575 - - 1 1 1 3 3.5

5 9 4BHK Villa-77 2350575 - - - - - - 3.5

6 9 4BHK Villa-78 2350575 - - - - - - 3.5

7 9 4BHK Villa-79 2350575 2 1 1 1 1

8 9 4BHK Villa-83 2350575 - - - - - - 3.5

9 14 4BHK Villa-120 2350575 - - - - - - 3.5

10 14 4BHK Villa-121 2350575 - - - - - - 3.5

11 14 4BHK Villa-123 2350575 - - - - - - 1.5

12 14 4BHK Villa-124 2350575 - - - - - - 1.5

13 14 4BHK Villa-126A 2350575 - - - - - - 3.5

14 14 4BHK Villa-128 2350575 - - - - - - 3.5

15 14 4BHK Villa-130 2350575 - - - - - - 1.5

16 14 4BHK villa -126 2350575 - - - - - - 3.5


17 14 4BHK Villa-127 2350575 - - - - 1 3 3.5

18 9 4BHK Villa-82 2350575 2 1 1 1 1 - -

19 15 3BHK Villa-131 2057625 - - - - - - 1.5

20 20 3BHK Villa-178 2057625 - - - - - - 3.5

21 20 3BHK Villa-187 2057625 - - - - - - 3.5

22 21 3BHK Villa-194 2057625 - - - 1 3 3.5

23 25 3BHK Villa-226 2057625 - - - - 1 3 3.5

24 25 3BHK Villa-231 2057625 - - - - - 3 3.5

25 25 3BHK Villa-234A 2057625 - - - - 1 3 3.5

26 26 3BHK Villa-245 2057625 - - - - - - 3.5

27 20 3BHK Villa-180 2057625 - - 1 1 1 3 3.5

28 25 3BHK Villa-235 2057625 - 1 1 1 1 3 3.5

29 25 3BHK Villa-237 2057625 2 1 1 1 1 - -

30 15 3BHK 133 2057625 2 1 1 1 1 - -

Total 119893275 SUDHAKAR


Gf slab Achievement
Percentage of work Upcoming Value Current bill
and beam
completed % Achieved Vlaue Value
concrete
previous current
Bill bill
8.00% 1.00% 6.50% 152787.38 23505.75 176293

6.00% 3.00% 3.50% 82270.13 70517.25 152787

5.00% 0.50% 3.50% 82270.13 11752.88 94023

6.00% 3.50% 7.50% 176293.13 82270.13 258563

9.00% 0.50% 3.50% 82270.13 11752.88 94023

3.5 10.50% 8.50% 5.00% 117528.75 199798.88 317328

9.50% 2.00% 3.50% 82270.13 47011.50 129282

5.00% 0.00% 7.50% 176293.13 0.00 176293

6.00% 3.00% 7.50% 176293.13 70517.25 246810

3.5 10.75% 8.25% 5.00% 117528.75 193922.44 311451

3.5 10.50% 8.50% 7.00% 164540.25 199798.88 364339

10.50% 0.50% 1.50% 35258.63 11752.88 47012

3.5 10.50% 0.50% 7.00% 164540.25 11752.88 176293

3.5 10.75% 6.00% 5.00% 117528.75 141034.50 258563


5.00% 0.00% 7.50% 176293.13 0.00 176293

5.00% 7.00% 7.50% 176293.13 164540.25 340833

5.00% 4.00% 7.50% 176293.13 94023.00 270316

5.00% 0.00% 7.50% 176293.13 0.00 176293

4.00% 1.00% 9.50% 223304.63 23505.75 246810

10.50% 8.50% 3.50% 72016.88 174898.13 246915

9.50% 0.50% 3.50% 72016.88 10288.13 82305

10.50% 2.00% 3.50% 72016.88 41152.50 113169

9.50% 1.50% 6.50% 133745.63 30864.38 164610

11.00% 0.50% 3.50% 72016.88 10288.13 82305

10.50% 0.50% 3.50% 72016.88 10288.13 82305

3149979.75 1635236.44 4785216.19


3.5 10.75% 8.75% 5.00% 117528.75 205675.31 323204

3.5 10.75% 8.75% 5.00% 117528.75 205675.31 323204

3.5 10.75% 8.75% 5.00% 117528.75 205675.31 323204

3.00% 0.00% 9.50% 223304.63 0.00 223305

9.50% 0.50% 3.50% 82270.13 11752.88 94023

9.50% 0.50% 3.50% 82270.13 11752.88 94023

0.00% 0.00% 6.00% 141034.50 0.00 141035

9.50% 0.50% 3.50% 82270.13 11752.88 94023

9.50% 3.00% 3.50% 82270.13 70517.25 152787

9.50% 3.00% 3.50% 82270.13 70517.25 152787

3.5 10.75% 8.75% 5.00% 117528.75 205675.31 323204

3.5 10.75% 8.75% 5.00% 117528.75 205675.31 323204

10.50% 0.50% 3.50% 82270.13 11752.88 94023

10.50% 5.00% 3.50% 82270.13 117528.75 199799

3.5 10.75% 4.75% 5.00% 117528.75 111652.31 229181

10.50% 0.50% 3.50% 82270.13 11752.88 94023


9.00% 0.00% 7.50% 176293.13 0.00 176293

- 0.00% 0.00% 6.00% 141034.50 0.00 141035

3.5 9.00% 6.50% 5.00% 102881.25 133745.63 236627

9.50% 0.50% 3.50% 72016.88 10288.13 82305

9.50% 0.50% 3.50% 72016.88 10288.13 82305

4.00% 1.00% 7.50% 154321.88 20576.25 174898

6.00% 3.75% 7.50% 154321.88 77160.94 231483

9.00% 0.75% 6.50% 133745.63 15432.19 149178

6.00% 3.75% 7.50% 154321.88 77160.94 231483

9.50% 1.75% 3.50% 72016.88 36008.44 108025

5.00% 0.00% 9.50% 195474.38 0.00 195474

1.00% 2.00% 10.50% 216050.63 41152.50 257203

- 0.00% 0.00% 6.00% 123457.50 0.00 123458

- 0.00% 0.00% 6.00% 123457.50 0.00 123458

5.46% 3619083 1879170 5498253

Das könnte Ihnen auch gefallen