Calculation for 90cm dia Hume Pipe

S. Length Breath Height Quantity Remark


N0. Description No (m) (m) (m) (m3) s
1 Site Clearance 1 4.5 10 0 45 Sq .m
Total 45 Sq. m
2 Earth work in excavation in ordinary soil
a. Hume pipe 1 7.5 3.44 1.15 29.67
b. Fence Wall 2 3.44 1 2 13.76
c. Catch Pit 1 1.5 1 2 3
D. Pipe bed 1 3.44 1 2 6.88
Total 53.31
3 PCC in 1:3:6 in bed
a. Pipe bed 1 7.5 1.13 0.27 2.28
b. Fence Wall 2 2.3 1.14 0.3 1.57
c. Inlet & Outlet Pit 1 1.5 2.75 0.1 0.41
Total 4.26
4 Brick Masonry 1:4
a. u/s & d/s Head Wall 2 2.3 2.3 0.7 7.41
subtotal 7.41
Deduction for pipe opening 2 P*(1.1)^2/4 1 -1.9
Total 5.51
5 Back filling 4.5 2 2 18
Deduction for pipe 1 P*(1.1)^2/4 4.5 4.29
Total 13.71
6 Hume pipe of 90cm dia 1 7.5 7.5 m
Total 7.5 m

Calculation for 60cm dia Hume Pipe

S. Length Breath Height Quantity Remark


N0. Description No (m) (m) (m) (m3) s
1 Site Clearance 1 4.5 10 0 45 Sq .m
Total 45 Sq. m
2 Earth work in excavation in ordinary soil
a. Hume pipe 1 5 2.6 1.15 14.95
b. Fence Wall 2 2.66 1 0.5 2.6
c. Catch Pit 1 1.5 1 0.5 1.5
D. Pipe bed 1 1.5 1 0.5 0.75
Total 19.8
3 PCC in 1:3:6 in bed
a. Pipe bed 1 5 0.8 0.2 0.8
b. Fence Wall 2 1.7 1.02 0.1 0.35
c. Inlet & Outlet Pit 2 1.2 2.25 0.1 0.54
Total 1.69
4 Brick Masonry 1:4
a. Fence Wall 2 2.6 1.23 1 6.4
b. Parapet Wall 2 2.6 0.3 0.3 0.47
subtotal 6.86
Deduction for pipe opening 2 P*(0.72)^2/4 1 -0.81
Total 6.05
5 Back filling 4.5 1.15 2 10.35
Deduction for pipe 1 P*(0.72)^2/4 4.5 1.84
Total 13.71
6 Hume pipe of 90cm dia 1 5 5 5 m
Total 5