Sie sind auf Seite 1von 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/271437293

IEC 61850 communication based distance protection

Conference Paper · May 2014


DOI: 10.1109/EPE.2014.6839537

CITATIONS READS

8 1,046

2 authors:

Kinan Wannous Petr Toman


Brno University of Technology Brno University of Technology
10 PUBLICATIONS   25 CITATIONS    95 PUBLICATIONS   188 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Modeling and control of wind permanent magnet synchronous generator View project

LO1210 View project

All content following this page was uploaded by Kinan Wannous on 21 April 2016.

The user has requested enhancement of the downloaded file.


IEC 61850 Communication Based Distance
Protection
Kinan Wannous, Petr Toman
Brno University of Technology
Brno, Czech Republic
xwanno00@stud.feec.vutbr.cz, toman@feec.vutbr.cz

Abstract—IEC 61850 is the standard for communication A specific feeder as an example is not physically connected to
substation which determines new applications of protection based a protection device anymore. It can be located anywhere in the
on peer-to-peer communications between multifunctional system to protect a specific feeder. As a result it might be
protection devices (IEDs). The GOOSE messages (Generic Object possible to have spare equipment connected to the substation
Oriented Substation Event) can be used to replace the hard wired network. In the case of a failure of one protection relay it might
control signals exchanged between IEDs for interlocking and be possible from remote to load the spare relay with the
protection purposes. The idea is that the implementation of high- specific set of parameters from the failed relay. So a failed
speed peer-to-peer communications should be equal or better device can be replaced with a spare without the immediately
than what is achievable by existing technology. The paper focus
need to send someone to the substation.
on using IEC 61850 based protection relays and on possibility of
modeling of this processes in Matlab.

Keywords—IEC 61850 Application; Comparing of GOOSE


technology with conventional technology; Advanced distance
protection

I. INTRODUCTION
The IEC 61850 standard Communication Networks and
Systems for Substation Automation allows utilities to consider
new designs for substations applicable for both new substation
and refurbishments. The levels of functional integration and
flexibility of communications based solutions bring significant
advantages in costs in all stages of a project. This integration
affects not only the design of the substation but almost every Fig. 1. Model of a relay for distance protection [4].
component and/or system in it such as protection, monitoring
and control by replacing the hardwired interfaces with
communication link. The paper focus on design of protection A. Connecting CTs and VTs with IEC 61850
element based of IEC 61850 communications: GOOSE With IEC 61850 can be replaced analog signal from CTs
message, (SV) sample value. IEC 61850 will have an effect on and VTs to serial communication based on optical sensor but
protection from many sides: IEC 61850 can replace the analog also can be connected conventional instrument to
signals from CTs and VTs with serial communication based on communication network by merging unit. It can in one
new technologies like optic sensor. The hardware and software communication message transmit sampled values of three
design of protection could change input/output of protection voltages and the three currents [4].
equipment and the wiring between relays can be removed. Not only CTs and VTs can be connected with a
communication interface to the substation automation system.
II. DESIGN OF PROTECTION ELEMENTS WITH IEC 61850 Also switchgear equipment like circuit breakers can either be
The elements of distance protection relay and principle equipped directly with a digital communication interface or be
according to IEC 61850 is shown on Fig.1 where PTRC connected through a remote I/O device. GOOSE messages can
(protection trip conditioning), TCTR (current transformer), be used to transmit a trip signal from the protection relay to the
TVTR (voltage transformer), PDIS (different zone for distance circuit breaker. In that case we have a process bus that
protection function), XCBR Interface to the circuit breaker) are completely decouples the bay level equipment like protection
parts of the model. The LN ATCTR (current transformer) and relays from the process. A communication based process
ATVTR (voltage transformer) are the interface of measured connection provides besides the reduction of copper wires -
current and voltage. They achieve to conversion analog signal some additional advantages related to this. The wiring between
to digital [4]. All information is available anywhere by using a the IEDs interfacing the process (Merging units) and the
process bus to distribute the information within the substation. process may be done and tested during manufacturing [4],[9].
The paper was prepared at Centre for Research and Utilization of
Renewable Energy (CVVOZE). Authors gratefully acknowledge financial
support from National Feasibility Program I of Ministry of Education, Youth
and Sport of the Czech Republic under project No. LO1210.

978-1-4799-3807-0/14/$31.00 ©2014 IEEE


With other words instead of handling many wired on the protocol of substation communication and on the
connections during engineering, commissioning and testing, requirements of the application. Fig. 4 shows relay based
this is reduced to handle a few communication connections. intermediate equipment.
Further with the serial communication defined in IEC 61850 a
stream of digitized samples replaces the analog signal. The
representation of the values is independent from any specific
properties of the instrument transformer. The values are
transmitted with the data type integer or real. In the case of the
real representation the actual process value from the power
system without any scaling or rating is transmitted. In the case
of the integer representation the value is scaled; the scaling
parameters are included in the data model so that any receiver
can calculate the actual process value. As a consequence the
bay level equipment does not need to handle issues like the
rated values and the ratio of the transformers [4], see Fig. 2.

Fig. 4. Intermediate equipment for transmitting signal [1]

The IEC 61850 can replace intermediate teleprotection by


using direct serial communication between the relays. The
availability of serial communications interface in later versions
of microprocessor based transmission line protection relays
allows the implementation of accelerated schemes without
using intermediate teleprotection devices. The exchange of
permissive or blocking signal in this case is using a proprietary
communications protocol between the relays at the ends of the
protected transmission line. This implementation has
advantages over the classical one described above due to
improvements in performance and reliability by eliminating the
hard wired interface between the relays and teleprotection
Fig. 2. Connection CTs and VTs with IEC 61850 [4] devices at the sending and receiving ends of the distributed
application [1]. An accelerated scheme implementation using
B. Design and testing protection with IEC 61850 direct serial communications between the relays at both ends of
the protected transmission line is shown in Fig. 5.
The first of all protection system should be part of the
substation system and responsible for the performance and
functionality of the system.
Then IEC 61850 functions are selected for a protection
relay. When design the protection schemes there is important to
know what information are exchanged between IEDs [4] as is
shown at Fig. 3.

Fig. 5. Serial communcation with Distance Protection [1]

The introduction of IEC 61850 as an international standard


for substation communications and the significant increase in
the availability of fiber optic cables between substations allows
a new way of implementation of accelerated schemes that
offers some important benefits. The specifics of each
implementation are still determined by the communications
Fig. 3. Wires replased by GOOSE message [4] available between the substations at the ends of the protected
line [1].
C. Achievement of Accelerated Schemes
If power line carrier signaling equipment is available for
In traditional relay there is used intermediate device for
communications between the substations, the system will
transmitting the different signal (blocking or permissive) logically be similar to the one shown in Fig. 3 but the hard
between two sides of the protected line. How it works? The wiring between the relay outputs of the protection devices and
first relay send signal to teleprotection device, then the inputs of the communications device are replaced with the
communication device sends signal to other communication virtual connects using GOOSE messages. Several GOOSE
device which it connected with relay in other side of the line. messages are required depending on the selected scheme as is
This scheme is based on the available communication channel, described below, see Fig. 6.
To increase the reliability digital protection system includes to IEC 61850 it should be less than 4 ms at each end of the line,
three stages: giving us a total of about 8 ms for both ends. When both
solutions are compared the GOOSE based scheme is about
• sampling of the input data, 8 ms (half a cycle) faster than the hard wired equivalent. All of
• determining when protection starts, the above has to be proven using testing of the accelerated
protection scheme, which in the case of IEC 61850 based
• the implementation of protection. implementations will require some new tools compared with
the conventional scheme testing.

III. THE IEC 61850 STANDARD


IEC 61850 provides two communication principles.
GOOSE messages are used to replace the hard wired control
signals exchanged between IEDs for interlocking, protection
purposes, sensitive missions, critical time and highly reliability.
The information exchange is based on a publisher/subscriber
mechanism. The publisher writes the values in a local buffer at
the sending side; the receiver reads the values from a local
buffer at the receiving side. The communication system is
responsible to update the local buffers of the subscribers. The
GOOSE messages contain information that gives permission
the receiving device to know that an official position has
changed and the time of the last official position is changed.
The time of the last official position change gives permission
the receiving device to set local timers relating to a given
event. The associated IEDs are receiving the message
containing information to determine what the appropriate
protection response is for the given state. The appropriate
action to GOOSE messages is needed when a message timeout
Fig. 6. Communication of Relay Protection [3] due to a communication failure is determined by local
intelligence in the IEDs receiving the GOOSE message.
D. Comparing time between hard wire and GOOSE GOOSE message can extend possibilities of circuit breaker
accelerated schemes: failure protection to trip next breaker. Considering the
Numerous tests performed by different relay manufacturers importance of functions performed by using GOOSE messages
and test companies show that GOOSE based distributed IEC 61850 defines very strict performance requirements. The
applications consistently outperform hard wired schemes with total peer-to-peer time should not to be longer than 4ms and
the same functionality. This may look strange at the beginning high reliability is important requirement for the GOOSE
but as can be seen from the careful analysis of the factors that message. It must be repeated as long as state continues. Hold
determine the overall operating time of a distributed protection time mean give the message time to live to take max
function it is what should be expected. If we consider that the dependability and security. Sending message from devices
breaker tripping and the communications exchange between sending GOOSE message shall continue to send the message
the two ends of the protected line are performed in the same with a long cycle time, whether no state/value change has
manner by the IEDs in both cases there is possible to analyze occurred. Reduce the network traffic during severe fault
the time from the operation of the directional element in the conditions, the GOOSE message has been designed on the base
sending relay and the resulting detection of the operation of the of the idea to have a single message that conveys all required
optic input of the communications device at the sending end of protection scheme information regarding an individual
the line as well as the time from the receiving of the protection IED. It represents a state machine that reports the
accelerating signal and the resulting detection of it by the relay status of device in the IED to its peers.
at the receiving end.
A. IEC 61850 GOOSE Advantages
In the conventional hard wired scheme this will include the
operating time of two output relays (each about 3 ms) plus the GOOSE replaces a complex network of hardwired
two detections of the energization of optic inputs (depending connections with an Ethernet network at the station level for
on the availability or lack of filtering and the scanning of the inter-IED communication. It causes reduced copper wiring cost
optic inputs this time for each can be from 2 to 8 ms). If we along with improved reliability, accuracy signal response and
assume an average time of optic input with filtering of about fast than hardwired schemes for protection application like as
5 ms the total time at each end for the hard wired interface break failure protection, reclosing and load shedding. With this
between the relay and communication device is about 8 ms and result it can be used to improve the performance of control and
it is giving us a total time about 16 ms for both ends. If the time protection functions by satisfying the real time performance
between the directional element output and the communication requirement of these applications for which the transfer time
device detection of the GOOSE message is analyzed, according should not exceed 4ms. In the same way GOOSE service can
also be used for testing the performance of protective relays in an advanced distance protection scheme used for
applications. In GOOSE based system several virtual acceleration or adaptation of the relay to changing
inputs/outputs are available through software configuration configuration or system conditions. Distance protection logic
which improves functionalities and enables new to be added in schemes are permissive and blocking schemes. The
substations in near future. Further monitoring the status of multifunctional distance protection relays also perform
hardwired connections in traditional hardware based schemes automatic functions such as multi-shot reclosing and local
is a crucial and difficult task. In communication-based schemes backup protection such as breaker failure protection. To
Ethernet enables supervision of GOOSE messages and virtual achieve cleared fault from system is connected with many
connections for any abnormalities in the system. If any failure conditions like, correct operation of the protection elements,
of communication link found in any device or in healthy secondary current and voltage circuits, and break trip
communication path it can be rectified automatically or or close circuit [6], [7], see Fig. 7.
reported to substation operator for necessary action. Thus
GOOSE provides an opportunity to design new and innovative
protection applications that can support the self-healing
capability in substation automation system [9], [11].

B. IEC 61850 Sampled Values


IEC 61850-9-2 Sampled Values can be used for applying
voltage and current signals to devices instead of using analogue
current and voltage from amplifiers. Maximum sample
transmission time for an IEC 61850-9-2 sampled value
message used for protection is typically specified less than 3ms
for sample rates faster than 480 samples/cycle. An IEC 61850
device referred to as a Merging Unit (MU) is used to transmit
sampled values derived from transducers using IEC 61850-9-2 Fig. 7. Distance protection block diagram [7]
messages over the process bus.
Messages sent by MUs may contain an arbitrary number of V. PROTECTIVE RELAY MODELLING
current and voltage channels (phases) but the initial In the power system three-phase currents sensed by the
implementations of 61850-9-2 send messages with CT’s in the power system are noisy analog signals that must be
instantaneous 3-phase plus neutral voltage and current samples. sampled, filtered and processed by the computer relay
Arbitrary sample rates are permitted by IEC 61850-9-2. But instantaneously. An overcurrent relay model (see Fig. 8)
initial implementations of MUs commonly referred to as IEC requires that instantaneous values of the three-phase currents
61850-9-2LE used for protection typically send samples from the power system model are signal-conditioned (e.g. by
at 80 samples/cycle. means of filters and other signal processing blocks) before
With the implementation of IEC 61850 communications in being inputted into the relay logic block. The digital filter is a
the RTDS Simulator all signals are passed to and from the very important element of a digital relay. The behavior of
protective relays via a separate station bus and process bus, digital relays is directly dependent on the output of the digital
both based on Ethernet. The IEC 61850 GOOSE/GSSE facility filter. After the digital filter the current signals are input to
described in this paper allows up to 64 binary inputs and 64 another calculation block to extract the fundamental values
binary outputs to be provided to as many as 8 different IED’s from the sampled input data. A full cycle discrete Fourier
(e.g. relays) from one device. Therefore the trip and reclose transform (DFT block) is used to obtain the magnitude of the
signals plus the breaker status signals for the double ended line Fundamental frequency component of each of the three current
protection tests can be provided by one Ethernet connection signals.
representing a single station bus. An added Ethernet connection
is required for a process bus to pass up to 8 sampled value
(analogue) signals to each relay [5][8].

IV. DEVELOPED DISTANCE PROTECTION WITH IEC 61850


The most important thing to excess distance protection to
clear faults immediately which can reduce the negative
influence of the fault on the substation devices. Analog input
module is a filter and processes the secondary currents and
voltages which supplies distance protection relay then analog
input module provides immediate sampled values to internal
digital bus. After that inputs of protection can be taken from Fig. 8. Block diagram of protection system using overcurrent relay
outputs of the measurement elements [8]. When a protection As previously noted the distance relay inputs are current and
element detects fault it operates and decides trip command to voltage analog signals. These signals must be sampled and
clear a fault. It may also interact with other protection elements converted to digital form. This conversion is done by the
Analog to Digital Converter (ADC). Once the magnitude of necessary components to model the power system. The
the fundamental is computed by the DFT block a comparator system designed is symmetric one source system. Each of
or relational element compares the absolute value of the relay the components of the three phase currents and voltages are
input signal with the pick-up setting to check the status of the obtained. The components are sent to the relay subsystem,
power system. If a fault exists in the protection zone of the which filters the high frequency harmonic components.
system, then the absolute value of the relay input signal is
greater than the pickup setting; otherwise it is smaller than the
pickup value. The output of the comparator is the “Trip”
signal for the circuit breaker, if fault exists within the zone of
protection. Once the relay detects the value of the fault
currents, a trip signal is sent to the circuit breaker and the
three-phase currents become zero. Fig. 9. One-line diagram of simulation system
The fault calculation algorithm used depends on the type of
the fault that occurs. The line to line (LL) fault, double line to The relay model has been designed and connected with the
ground (DLG) fault and single line to ground (SLG) fault are main power system model with the help of the subsystem
classified as unsymmetrical faults [2],[10]. The power system tool in SIMULINK. This makes the overall model compact
for simulation purposes (Fig. 9) has been designed in and easy to observe during analysis (Fig. 10, Table I).
MATLAB SIMULINK. The SimPowerSystem provides the The results of the simulation are shown at Fig. 11 to Fig. 15.

Fig. 10. Simulink sub-system model


TABLE I. MODEL PARAMETERS
° Ω
Three phase source block °
Value Unit
° Ω °
Source phase to phase voltage 400 kV
Phasor angle of phase A 0 degree
Nominal frequency 50 Hz
° °
Distributed line parameters block
Line length 75 km
Positive sequence resistance 0.0275 Ω/km ° °
Zero sequence resistance 0.275 Ω/km
Positive sequence inductance 0.001345 H/km ° °
°
Zero sequence inductance 0.003725 H/km
Fig. 15. Impedance - time development - detail
Positive sequence capacitance 9.483e-9 F/km
Zero sequence capacitance 6.711e-9 F/km VI. CONCLUSION
Load parameters
The paper describes introduction part of research focused
Active power P 200 MW
on development of digital distance protection function based on
Inductive reactive power QL 40 MVAr
standard PC platform. The first part of research is based on IEC
61850 properties and on possibilities of modelling in Matlab
software.
line voltage [V]

REFERENCES
[1] A. Apostolov, "Impact of IEC 61850 on the Interoperability and
Reliability of Protection Schemes", In proceedings of 2013 IEEE
Power and Energy Society General Meeting (PES), USA, 2013,
ISSN 1944-9925.
time [s] [2] M. H. Idris, M. S. Ahmad, A. Z. Abdullah, S. Hardi, "Adaptive Mho
Fig. 11. Voltage od phase A measured by relay after filltering and DFT Type Distance Relaying Scheme with Fault Resistance Compensation",
In proceedings of 2013 IEEE 7th International Power Engineering and
Optimization Conference (PEOCO2013), pp. 2013-217, ISBN 978-1-
line current [A]

4673-5072-3.
[3] H. Wang, Z. Cai, Z. Su and Z. Zhu, "The Analysis of Relay Protection
Communication Mechanism Based on IEC61850”, In proceedings of
2011 International Conference on Advanced Power System Automation
and Protection (APAP), pp 223-227, 2011, ISBN 978-1-4244-9622-8.
[4] C. Brunner," The Impact of IEC 61850 on Protection", In proceedings of
IET 9th International Conference on Developments in Power System
time [s] Protection, 2008. DPSP 2008, pp. 14-19, ISBN 978-0-86341-902-7.
Fig. 12. Current of phase A measured by relay after filltering and DFT [5] R. Kuffel, D. Ouellette and P. Forsyth, “Real Time Simulation and
Testing Using IEC 61850", 2010 Proceedings of the International
Symposium Modern Electric Power Systems (MEPS), pp. 1-8, Canada,
measured line impedance [Ω ]

2010, ISBN 978-83-921315-7-1.


[6] A. Apostolov, "IEC 61850 9-2 Process Bus Applications and Benefits",
In proceedings of 10th IET International Conference on Developments
in Power System Protection (DPSP 2010), pp. 1-5, 2010.
[7] A. Apostolov and B. Vandiver, "Testing of Advanced Distance
Protection Relays", In Proceedings of 2009 62nd Annual Conference for
Protective Relay Engineers, pp. 353-358, 2009, ISBN 978-1-4244-4183-
9.
time [s] [8] M. Gilany, D. K. Ibrahim, "Traveling-Wave-Based Fault-Location
Fig. 13. Impedance measured by relay Scheme for Multiend-Aged Underground Cable System", IEEE
Transactions on Power Delivery, Vol.22, No.1, pp. 82-89, 2007, ISSN
° Ω 0885-8977.
°
[9] J. Jirickova, "IEC61850: Implementation in new Generation of Electrical
° Ω ° Protection", Proceedings of The IVth International Scientific
Symposium on electric Power Engineering – Elektroenergetika 2007, pp
471-473, 2007.
° ° [10] Z. Muller, J. Svec, M. Cernan and J.Kyncl, "The Use of Regression
Methods for Measurement and Diagnostics in Electrical Power
Engineering". In Proceedings of the 13th International Scientific
° ° Conference EPE 2012. pp. 413-417, 2012, ISBN 978-80-214-4514-7.
[11] X. Sun and M. A Redfern, "An Investigation into the Design of an IEC
° ° 61850 Based Protection Relay", In 2009 Proceedings of the 44th
° International Universities Power Engineering Conference (UPEC), pp.
Fig. 14. Impedance - time development 1-5, 2009, ISBN 978-1-4244-6823-2.

View publication stats

Das könnte Ihnen auch gefallen