PERDAY OUTPUT OBSERVATION


BRICK WORK
S.NO CONTRACTOR MASON MASON INT PLASTER MASON EXT PLASTER
200 100
1 Ajay Bhagel 5 30.12 15.02
4 20.1 7.64
7 20.25 10.25
7 15.75 7.43
7 20.25 7.43
30 106.47 47.77
Avg B/w in Cum per day per
0.87
head
2 Kamlesh Mishra 4 19.51 10.22 5 40
4 19.48 7.43 7 60
5 22.03 11.23 6 35
8 36.42 15.79 8 50
6 15.75 8.92 4 30
27 113.19 53.59 30 215
Avg B/w in Cum per day per
1.04
head
Avg Plaster in Sqm per day per
7.17
head
3 Bhagwan Das 6 26.51 4.02 10 100
5 18.08 6.41 8 60
5 19.83 6.61 5 40
4 15.86 4.96 6 50
4 30
20 80.28 22 33 280
Avg B/w in Cum per day per
0.91
head
Avg Plaster in Sqm per day per
8.48
head
4 Manjur Alam 8.00 118.00
4.00 70.00
6.00 86.68
8.00 106.20
8.00 107.91
8.00 124.24
9.00 117.83
51.00 730.86
Avg Plaster in Sqm per day per
14.33
head
5 Sunder Kousaria 10.00 150.00
Avg Plaster in Sqm per day per
15.00
head 11.25

4 Istiak khan 103 760 7.38


5 Sudama 141 1140 8.09
6 Anand Paraste 57 324.12 5.69
7 Surya &co 83 464 5.59
8 Zahid 34 108 3.18
9 Hiradas 424 2240 5.28
10 Laxmi 58 260 4.48
11 vinod dixit 11 32 2.91
12 Abdul Sarkar 19 80 4.21
13 vinod kumar 12 47 3.92
942 5455.12
Avg Plaster in Sqm per day per
5.79 6.00
head
OUTPUT ABSTRACT
PER HEAD/
S.No ITEM UNIT
DAY
1 BRICK WORK CUM 0.94
2 INT PLASTERING SQM 11.00
3 EXT PLASTERING 2 coats SQM 6.00
4 CEMENT PRIMER SQM 92
5 PUTTY 1st coat SQM 53
6 PUTTY 2nd coat SQM 65
7 OBD 1st Coat SQM 50

Page 1 of 2
31/12/2015

8 OBD 2nd Coat SQM NO DATA


9 Wood Primer SQM 68
10 Enamel 1st Coat RAILING SQM 26
11 Enamel 2nd Coat WINDOW SQM 5.63
12 Emulsion 1st coat SQM 75
13 Emulsion 2nd coat SQM 75
14 Emulsion 2nd coat Sparay SQM 350-400
15 CeramiC Floor SQM 18
16 Cerami Dado SQM 4
17 Kitchen Platform SQM 0.9 1.8 sqm Plan Area
18 CPVC outside lines Rmt 32 64 Rmt for 6 Flats
19 PVC Outside lines Rmt 28 6 flats 42 rmt-2 Lines
20 Hdpe Tanks installation Nos 10
21 WC fixing Nos 4
22 Door Shutters Nos 5
23 Kota fixing SQM 9.65
24 Kota polishing SQM 11
25 Modular Box fixing Flat 1 15 box for 1 flats
66 m/c complete 1 block 60 flats inc corridor (166 Bundle wire) 3 Bundle wire
26 Wiring inc corri Flat 1
coil per head
27 PAVER BLOCKS WITH DUST SQM 12 1 MASON + 1 HELPER