Sie sind auf Seite 1von 6

Weather and Climate Extremes 21 (2018) 117–122

Contents lists available at ScienceDirect

Weather and Climate Extremes


journal homepage: www.elsevier.com/locate/wace

Watershed management strategies for flood mitigation: A case study of T


Jakarta's flooding
Chay Asdaka, Sudradjat Supianb, Subiyantoc,∗
a
Postgraduate Program on Environmental Studies and Faculty of Agricultural Industrial Technology, Universitas Padjadjaran, Sumedang, Indonesia
b
Department of Mathematics, Faculty of Mathematics and Natural Sciences, Universitas Padjadjaran, Sumedang, Indonesia
c
Department of Marine Science, Faculty of Fishery and Marine Science, Universitas Padjadjaran, Sumedang, Indonesia

A R T I C LE I N FO A B S T R A C T

Keywords: Jakarta is a capital city of Indonesia located in the delta of Ciliwung river. This city suffers annual flooding with
Flooding some serious damage for certain extreme rainfall events, especially occurring at the upper parts of the Ciliwung
Watershed management watershed. In 1992 rainy season, flooding in Jakarta was scattered in 61 sites. In 1996, the flooding increased to
Upstream-downstream hydrological relation 90 sites, and further increased in the rainy season of 2002 to be 159 sites. Jakarta experienced a major flooding
Indonesia
on 9–10 February 2015 after having seen two occurrences of major flooding in the two preceding years 2013 and
2014 (Siswanto et al., 2017). Such extreme flooding events might become more frequent in the future due to the
impacts of land use and climate change (Kure et al., 2014). To reduce the magnitude and frequency of further
flooding, on-site as well as off-site program actions need to be taken comprehensively. This paper is specifically
aimed at, firstly understanding the main problems causing flooding in the coastal area of Jakarta, and secondly
proposing medium and long-term solutions from the perspective of an integrated watershed management ap-
proach. The proposed solution will also include institutional and financial arrangements in a cross-adminis-
trative boundary situation.

1. Introduction Wijnker, 1997). Jakarta has already experienced many severe river
floods due to heavy monsoon rains, particularly in the years 1996,
As in many cities in the flood-prone areas in Indonesia, Jakarta has 2002, 2007, 2013, and 2014 (Takagi et al., 2016; Siswanto et al., 2017).
been reported to have big flood as early as in the year of 1621 (BBWS, Particularly, the floods that took place in January 2013 resulted in 40
2014). There was no detailed information on this flood, but it was re- deaths, 45,000 refugees, and substantial economic damage (Kure et al.,
ported that the depth of the flood was more than one meter high. In 2014). The floods in February 2007 also caused extensive economic
1876, another report indicated that the downstream area of the Cili- losses, mounting up to between 4.1 and 7.3 trillion IDR (Sagala et al.,
wung river, which was then known as part of the city of Jakarta was 2013). The 2013 flood disaster caused a loss of 15 billion IDR, and in
flooded severely. Ciliwung watershed approximately has 347 km2 in the 2014 calamity the loss has reached 100 million IDR per day
area and the length of its main river is 117 km (Ali et al., 2016). This (Oppusunggu and Tantular, 2015).
flood forced the Dutch government at that time to build three dams to Despite various efforts to reduce the flood carried out by the Dutch
control the river flow. The three dams were Bendungan Hilir located at government, and later on by the Indonesian government, Jakarta
the downstream of the Ciliwung river (Jakarta), Bendungan Jago and cannot be entirely freed from flooding. Naturally, this is associated with
Bendungan Udik were both located at the upper parts of the same river the fact that Jakarta is located on a flat area with an altitude of 0–20 m
(Hasanah et al., 2013). Later on, as a result of the large flood occurring above sea level, but some areas have 1–1.5 m elevation below sea level.
in 1876 and the subsequence flood events, the Dutch government This occurred due to land subsidence with its estimated rate that
through its representative for the flood control task force, Prof. Herman reaches 1–15 cm/year, spatially and temporally (Latief et al., 2018). It
van Breen, built the Banjir Kanal (flood canal) stretching from Man- is typical of flood-prone areas located in the delta of major rivers. An-
ggarai in the city center to Muara Angke at the coastal area of Jakarta. other natural factor that makes Jakarta critical to the flood is that there
The main purpose of this canal is to make the flood water flowing faster are 13 mostly small rivers flowing and transferring a large amount of
into the Java sea, and hence, preventing the flooding in Jakarta rainwater into around 40% area of the city of Jakarta (Fig. 1). Apart


Corresponding author.
E-mail address: subiyanto@unpad.ac.id (Subiyanto).

https://doi.org/10.1016/j.wace.2018.08.002
Received 28 September 2017; Received in revised form 1 August 2018; Accepted 17 August 2018
Available online 18 August 2018
2212-0947/ © 2018 The Authors. Published by Elsevier B.V. This is an open access article under the CC BY-NC-ND license
(http://creativecommons.org/licenses/BY-NC-ND/4.0/).
C. Asdak et al. Weather and Climate Extremes 21 (2018) 117–122

Fig. 1. Map showing rivers flowing into the city of Jakarta (NCICD, 2014).

from the natural causing factors, the recent uncontrolled land-based 2006) with rainfall data from JICA (2004). The basis of operation of
development of upstream areas of those rivers combined with high ANSWERS (and most other watershed models) is the continuity equa-
population growth in the city of Jakarta and poor urban-rural planning tion (Foster and Meyer, 1972):
make the flooding-related problems becoming more serious and com-
dS
plicated (to handle). =I−O
dt (1)
This paper discusses one case study, the watershed management
strategies that using Jakarta flood study for understanding the main where
problems causing flooding in the coastal area of Jakarta. This paper
proposed medium and long-term solutions from the perspective of in- S : volume of water in storage (surface detention),
tegrated watershed management approach. We start by reviewing the t : time,
general Jakarta disaster management and then we discuss the role of I : inflow rate,
institutional and financial arrangements in a cross-administrative O : outflow rate.
boundary situation.
The governing equation for the erosion model is the continuity
equation as described below:
2. Material and methods
dG
=R+D
dx (2)
This study was carried out in Ciliwung Watershed. The geography,
location and boundaries of those watersheds are 060 06′ 00” - 060 where
46′12″ S and 1060 48′ 36” - 1070 00′ 00″ E which covers the admin-
istrative region of Bogor District, Bogor City, Depok City, and Jakarta G : the rate of sediment movement inflow (weight per unit width per
Province (Sun et al., 2014; Arifasihati and Kaswanto, 2016). The unit time),
methods in this study are described as follows: a) Preliminary analysis. x : distance along flow surface,
This analysis is aiming to identify the hydrological proses and the R : rainfall detachment rate (weight per unit area per unit time),
causes of the flooding in the area of study. The analysis of land use D : flow detachment rate (weight per unit area per unit time).
changes was also carried out in this study; and b) The hydrological
impact. The hydrological simulation study linking the disappearance of The solution of Equation [2] requires three steps in ANSWERS, and
forest in the upper Ciliwung with the downstream flooding was con- in each step the lesser of the two calculated rates controls (Beasley
ducted using the ANSWERS model (Beasley et al., 1980; Singh et al., et al., 1980). The three steps are:

118
C. Asdak et al. Weather and Climate Extremes 21 (2018) 117–122

I. The available transport rate is compared to the incoming sediment Ciliwung watershed. Not surprisingly that the declining of the forest
movement rate. Any excess transport capacity is transferred to step and plantation areas was followed by the sharp increase of dry land
II. farming (169%) and housing/building coverage (338%) in 10 years
II. ANSWERS solves for the impact detachment rate and compares this period of time. This land use changes in the middle and upper parts of
rate with the available (excess) transport rate. the Ciliwung watershed have resulted in tremendous negative en-
III. If additional transport capacity exists, the rate of flow detachment is vironmental effects, especially hydrological disturbances. The hydro-
calculated and compared to the transport rate. logical disturbances associated with the land use changes can be briefly
explained as follows: In a watershed system, upstream areas are hy-
3. Results and discussion drological linked to downstream areas through stream flow behavior
and sediment transfer. Land use change in the upstream areas are not
3.1. Understanding the hydrological processes only resulting in an on-site impact in the form of increased runoff and
soil erosion, but it will also give off-site impact of increasing stream
In Java island, flooding has been around for centuries, especially flow and river sedimentation downstream. The increasing of both
during big rainfall events. The flood gives benefits, mostly in the form runoff and erosion rates are mainly caused by decreasing conservation
of basic requirement for plants and animals to grow, flashing down any index (CI) as a result of land use changing from forest cover to poor
unwanted materials at soil surface as well as in rivers, and forming agricultural practices and/or housing/building coverage. Land use with
fertile deltas that benefiting people in the downstream areas. However, greater conservation index means greater capability of infiltration
most flooding resulting in negative impacts as shown by flooding that rainwater into the soil (greater groundwater recharge), therefore re-
hits Jakarta and other areas in Indonesia. ducing runoff and soil erosion as also shown in Asdak and Supian
In the case of flooding in Jakarta, one should put the downstream (2017) and Wang et al. (2018).
flood events in the context of the entire Ciliwung watershed (Asdak,
2010). The Ciliwung river drains into the Java sea and it runs about 3.2. The causes of the flooding
117 km long from its upper most area in Puncak, West Java. It was
mentioned that despite the Ciliwung river, there are more than 10 It was mentioned earlier that the flood in the city of Jakarta is
streams flowing into the Jakarta area, however this paper focuses on closely associated with both natural and anthropogenic factors. Natural
the Ciliwung watershed for at least three reasons. First, this river is the factors are commonly related to the following: (1) Jakarta is located on
largest river system entering Jakarta. Second, the upper and middle a low-lying flat coastal area, which is influenced by backwater effect
parts of this river are now experiencing a large change in land use, from the Java sea during the rise of the sea level, (2) more than 10 small
particularly from mostly land uses that recharge the groundwater to be rivers flowing into Jakarta, and (3) annual rainfall in the Ciliwung
runoff-producing type of land uses. Third, the Ciliwung watershed watershed, especially in the upper part is high (> 3000 mm). While
covering three different local governments, namely the capital city of natural factors are not so easy to handle for flood mitigation, the an-
Jakarta, the District of Bogor, the city of Bogor and the city of Depok thropogenic factors making the flooding mitigation even more difficult.
(Arifasihati and Kaswanto, 2016). These local governments would have This later factors including landscape changing due to high competition
their own different interests in managing their areas, and therefore on land-based economic activities, poor urban as well as rural spatial
would need a collective agreement for flood control measures in a planning, and lack of integrated institutional capacity and arrangement,
trans-boundary situation. The following is the land use characteristics especially in the context of cross administrative boundary situation
and change and its upstream-downstream linkages of the Ciliwung (special district of Jakarta versus the province of West Java).
watershed.
The Ciliwung watershed area is around 32,573 ha and it is classified 3.3. Rapid land use changes
as a degraded watershed, especially in the middle and upper parts of the
watershed as indicated by small area of forest cover (< 15%) and high The major flooding hits the streets of Jakarta is commonly asso-
housing/building coverage (35%). This is understandable considering ciated with the overload of Jakarta's drainage water system and land-
that the middle and upper Ciliwung watershed is closed to the capital scape changing occurring in the middle and upper parts of the Ciliwung
city of Jakarta and closed to the center of economic development ac- watershed. Table 1 shows that during 2000–2009, the forest and
tivities in the upstream areas such as Depok, Bogor, and Puncak (West plantation areas declined by 28%. So does the wet paddy field, de-
Java). clining by 73%. These land use types are widely known as an effective
The scale of catchment disturbance of the Ciliwung watershed, surface water (runoff) retention. Reducing large area of these land uses
especially in the middle and upper parts of the watershed can be seen making more rainwater available for flooding in the downstream area.
from the rate of land use change during the period of 1990 and 1999. In Another land use that good for surface water retention is pond/lake.
that period of time, the forested area declined by 10%. So does the Table 1 shows that the change of pond/lake is not significant. But an-
plantation (18%), mostly tea plantation in the upper parts of the other source indicates that before 2007 the number of pond/lake in the

Table 1
Land use change at the middle and upper of the Ciliwung watershed.
Source: Sabar (2009); (−) decreased, (+) increased
Land Use Entire Ciliwung Watershed Upper and Middle Watershed 2000 Upper and Middle Watershed 2009 Change in Land Use (2000–2009) (%)
(ha) (ha) (ha)

Forest 5094 5600 5034 (−) 10


Plantation 5730 6848 5612 (−) 18
Dry land farming 7770 2330 6267 (+) 169
Paddy field (wet rice) 1665 10,409 2833 (−) 73
House/Building complex 11,590 1613 7058 (+) 338
Pond/Lake – 38 36 –
Others (incl. pond/lake) 724 – – –

Total 32,573 26,841 26,841

119
C. Asdak et al. Weather and Climate Extremes 21 (2018) 117–122

upper Ciliwung was about 122. After 2007, the number went down to of Ciliwung were hydrological disturbed as a result of the land use
be only 28 (BPLHD, 2012). If this report is correct, then the scale of changing.
hydrological disturbance in the upper part of the Ciliwung should be The flooding in Jakarta is not only causing the loss of economic and
greater. In the lower part (the Jakarta area), apart from the steadily human life, but it also spurs the debate within scientific communities
increase in population, the number of water retention systems (mostly whether disappearing of forest land in the upper most Ciliwung wa-
ponds) were sharply reduced from 35 in 2007 to none in 2009. The tershed to be the important factor for the Jakarta's flooding. To clarify
conversion of mangrove forest in the northwest parts of Jakarta's this issue, the Center for Research and Development of Water Resources
coastal areas for waterfront luxurious housing complex and the so- conducted a hydrological simulation study linking the disappearance of
called reclamation of other parts of the same coastal areas have ex- forest in the upper Ciliwung (Katulampa station) with the downstream
acerbated the scale of the flood in Jakarta. flooding (Ilyas, 2004; BBWS, 2014). Apart from clarifying the debatable
The adverse hydrological impact caused by reducing those surface issue, this study is also important for considering which factors need to
water retention areas has been exacerbated by sharp increase in dry be given high priority for solving flooding in the deltaic city of Jakarta.
land farming areas (169%) and increased of housing/building coverage The result of the hydrologic simulation study shows that for the five-
by 338%. Opposite to the good function of forest, plantation and wet year return period, the reduction of forested area at the upper part of
paddy field for water conservation measures, the dry land farming and Citarum watershed from 58% to 34% resulting in the increase of peak
housing/building areas commonly found in the Ciliwung watershed are flood around 14%, from 312.5 m3/sec to 364.5 m3/sec (Fig. 3). The
not favorable for conserving ground water, which means increasing simulation study also indicates that when the rainfall regime was in-
runoff, because their conservation index numbers are reduced sub- creased to 192 mm (25-year return period), 206 mm (50-year return
stantially. Therefore, it can be said from this data that landscape period), and 238 mm (100-year return period), the percentage of in-
changing in the middle and upper parts of the Ciliwung watershed crease in the peak flood at Katulampa hydrological station were all less
could be an important factor for flooding in Jakarta. than 10%. This hydrological simulation result is in line with many other
The hydrological impact resulting from the above landscape chan- research findings worldwide, where small rainfall events produce a
ging may be seen from the following stream flow data analysis carried significant effect on peak flow as a result of forest cutting, but when
out at the hydrological station at Katulampa, representing the upper rainfall regime increased considerably, then there is no significant hy-
part of Ciliwung watershed and at Sugutamu station, representing the drological effect statistically.
middle part of the same watershed. Using daily stream flow data of Based on this simulation study, the influence of forest cover in the
1987–1999, it can be seen that for both hydrological stations, the five- upper most parts of the Ciliwung watershed to the Jakarta's flooding is
year moving average of daily maximum discharge was increased over relatively small. Therefore, it is suspected that the major contributor for
time with the coefficient of correlation (r) of 0.77 and 0.83, respectively the Jakarta's flooding is defined more by the landscape changing in the
(Fig. 2). While the five-year moving average of daily minimum dis- middle parts of the Ciliwung watershed, especially the sharp increase in
charge for both Katulampa and Sugutamu stations were observed to be housing/building areas combined with inadequate drainage system
decreased over time (r = 0.97 and r = 0.93, respectively). These hy- within the city of Jakarta.
drological data indicate clearly that the middle and upper catchments

Fig. 2. The five-year maximum and minimum moving average of the stream flow for two hydrological stations at Katulampa (left) and Sugutamu (right) (data
adapted from Sabar, 2009).

120
C. Asdak et al. Weather and Climate Extremes 21 (2018) 117–122

Fig. 3. Forest area changed from 58% to 34% and its impact on peak flood at 5-year return period in the Upper Ciliwung watershed (data adapted from Ilyas, 2004).

3.4. Problems associated with spatial planning and institutional capacity district/city will be suffering without economic compensation (from the
upstream activities). This is because there is no upstream-downstream
It has been stated that the important anthropogenic factor con- compensation mechanism that is now operating in Indonesia. Without
tributing to the downstream flooding is the uncontrolled land-based this mechanism and adequate institutional capacity to run the me-
activities in the middle and upper parts of the Ciliwung watershed. This chanism, cross-boundary conflicts will be intensified. For example, in
is mainly caused by rapid population growth combined with un-in- cases where downstream area is sensitive to water shortage and/or
tegrated urban-rural spatial planning within the watershed. The popu- floods, conflicts between local government in the upstream area and
lation growth in greater Jakarta is increasing from 4.5 million people in that of the local government in the downstream is intensified. This kind
1975 to 6.3 million in 1985, 9.0 million in 1995, and exceeding 9.6 of conflict should have been prevented if the urban-rural planning is
million in 2010, plus approximately 2.5 million daily commuters from designed properly, especially when this rural-urban area are integrated
the adjacent cities, and a total land area of 662 km2 (Firman et al., into one watershed, one plan and one integrated (upstream-downstream)
2010). It was estimated that the number of residents in the Greater management. In the case of the Ciliwung watershed, the rural-urban
Jakarta will reach 13 million in 2025 (Goenawan et al., 2015). The planning system should include the city of Bogor and the district of
difficult situation is intensified with the implementation of Law No. 23/ Bogor in the upper part, city of Depok in the middle, and the city of
2014 on Regional Government which is also known as the law of re- Jakarta in the lower area. Right now, each of these administrative units
gional autonomy (decentralization). According to this law, central has its own planning system, which is not linked adequately from the
government to decentralize most of its authority to local governments perspective of the integrated watershed management. The problem is
including the management of natural resources. With this law, the local intensified with the distorted interpretation of Law No. 23/2014 on
governments (district and city governments) are autonomously in Regional Government, where many local governments ignore the im-
charge in the management and allocation of local resources for their portance of sequential land use planning from provincial down to re-
regional income. With the new law, local government does not receive gency level.
full funding from the central government anymore, therefore, most of
the local governments then intensify their economic activities without
paying too much attention to negative consequences on their neighbors. 4. Conclusion
What is actually happening in the last five years since the im-
plementation of the Law No. 23/2014 is that: The flooding in Jakarta is becoming a regular event. It shows a
tendency of increasing in magnitude as well as in frequency rather than
a) Local governments are becoming too economic oriented in the decreasing despite a number of engineering efforts have been carried
management of their natural and man-made resources. Because of out to control it. The causes of the Jakarta's flooding are a combination
the short-term economic orientation activities many natural re- of natural as well as anthropogenic factors. The factors are from within
sources, for example forested areas, are changed to other cash crops the city of Jakarta and from its upstream areas. Meaning, it requires
and/or human settlement for more fresh money. more than just a conventional on-site engineering solution to control
b) Local governments are becoming independent from central and the flooding. To be more effective in the long run, the approach to
provincial governments. This is becoming a big problem for an in- mitigate the flooding in Jakarta should be shifted from an on-site
tegrated cross administrative boundary planning, because each of conventional engineering flood mitigation to a more integrated catch-
the local government is now making its own spatial planning ment management one. It is clear from the spatial analysis based on
without considering other local government's spatial planning and landscape changes and the hydrological data that the middle and upper
not referring to the provincial and national spatial planning. parts of the Ciliwung watershed play an important role in the Jakarta's
flooding. Based on the result of the hydrological analysis shows that the
According to Law No. 26/2007 on Spatial Planning, the spatial reduction of forested area at the upper part of Citarum watershed from
planning of every local government should refer to the provincial and 58% to 34% resulting in the increase of peak flood around 14%, from
national spatial planning. But this, in many cases, is not happening 312.5 m3/sec to 364.5 m3/sec. The influence of forest cover in the
because there is no such mechanism to force the local government to upper most parts of the Ciliwung watershed to the Jakarta's flooding is
follow the regulation and lack of institutional capacity in facilitating relatively small. Therefore, an integrated catchment management of the
the formulation of a spatial planning in a cross-administrative boundary Ciliwung and Cisadane watersheds for the Jakarta's flooding mitigation
system. The problem with the current system of spatial planning is if the should be given greater priority, especially on how to make a multi-
spatial planning of a district/city in the upstream of a watershed is tend stakeholder participation in a trans-boundary planning system. In this
to increase annual stream flow or water pollution, the downstream study, we conclude that the flood mitigation for medium to long-term
period should be focused on a sustainable conservative programs

121
C. Asdak et al. Weather and Climate Extremes 21 (2018) 117–122

focusing on a comprehensive-integrative approach, with the following doi.org/10.1016/j.proenv.2016.03.098.


strategies: Asdak, C., 2010. Hydrology and the Management of Watershed. Gadjah Mada University
Press, Yogyakarta.
Asdak, C., Supian, S., 2017. Hydrological implication of traditional farming systems: a
a) Formulate a grand design for water resource management of the case study of the Citarum and Cimanuk watersheds, West Java. J. Eng. Appl. Sci. 12
Ciliwung-Cisadane watersheds covering Jakarta, Bogor, Depok, and (17), 4415–4419.
BPLHD, 2012. Implementasi kajian lingkungan strategik dalam pengelolaan kawasan
Tangerang-Bekasi areas which consider biophysical as well as socio- bogor, Puncak, dan Cianjur. Kerjasama PPSDAL-Lembaga Penelitian Unpad dan
economic aspects of the areas. The current single focus of en- BPLHD Propinsi Jawa Barat.
gineering approach in water resource management for flood miti- BBWS, 2014. Konsep Penanganan Sistem Makro Pengendalian Banjir Jakarta. Direktorat
Jenderal Sumber Daya Air. Kementerian Pekerjaan Umum dan Perumahan Rakyat,
gation should be avoided. Jakarta.
b) Formulate an improved water resource-related organization which Beasley, D.B., Huggins, L.F., Monke, E.J., 1980. ANSWERS: a model for watershed
focuses more on a multi-disciplinary and trans-boundary institu- planning. Trans. ASAE (Am. Soc. Agric. Eng.) 23 (4), 988–994.
Firman, T., Surbakti, M.I., Idroes, I.C., Simarmata, A.H., 2010. Potential climate-change
tional approach in designing an integrated spatial planning. This
related vulnerabilities in Jakarta: challenges and current status. Habitat Int. 35 (2),
type of organization/institution arrangement should also consider 372–378. https://doi.org/10.1016/j.habitatint.2010.11.011.
the importance of establishing an upstream-downstream cash flow Foster, G.R., Meyer, L.D., 1972. A closed-form soil erosion equation for upland areas. In:
as part of the upstream-downstream compensation mechanism. In: Shen, H.W. (Ed.), Proceeding of Sedimentation Symposium to Honor Prof. H. a.
Einstein, vol 12. Colorado State University, Fort Collins, pp. 1–19.
c) The long-term proposed strategy for flood mitigation will require a Goenawan, R.D., Ridwan, R., Sadly, M., Sudinda, T., Kudsy, M., Seto, T.H., Harsoyo, B.,
large amount of funding. The special province of Jakarta alone will 2015. Experimental assessment of integrated technology application used to rain
not capable of financing the proposed flood mitigation program. (WM4RR) & floods reduction (AR-DWIS) in Jakarta. Procedia Eng. 125, 270–276.
https://doi.org/10.1016/j.proeng.2015.11.039.
Therefore, it is important to involve large companies in Jakarta such Hasanah, Y., Herlina, M., Zaikarina, H., 2013. Flood prediction using transfer function
as the Jakarta International Airport, the Jakarta International model of rainfall and water discharge approach in Katulampa dam. Procedia Environ.
Seaport, and other Jakarta-based large companies that suffered from Sci. 17, 317–326. https://doi.org/10.1016/j.proenv.2013.02.044.
Ilyas, M.A., 2004. Usaha Konservasi Terhadap Banjir, Erosi, Sedimentasi pada DAS
flooding to contribute financially to the proposed program. Cipinang, Ciliwung di Jawa Barat dan DKI. In: Proceeding of the National Seminar on
d) As part of the program on dispersing big flood in Jakarta into many Water and Disasters. Jakarta, 23 April 2004.
small floods in the upper and middle areas of the Ciliwung and JICA, 2004. Hydrology and Meteorology of the Ciliwung Watershed. Japan International
Cooperation Agency, Jakarta.
Cisadane watersheds (flood distribution concept), it is necessary to
Kure, S., Farid, M., Fukutani, Y., Muhari, A., Bricker, J., Udo, K., 2014. Several social
build small to medium scale dams at the tributaries and other arti- factors contributing to floods and characteristics of the January 2013 flood in
ficial surface water retention at the catchment of the two main Jakarta, Indonesia. J. Jpn. Soc. Civ. Eng. Ser. G (Environ. Res.) 70 (5), 211–217.
https://doi.org/10.2208/jscejer.70.I_211.
rivers.
Latief, H., Putri, M.R., Hanifah, F., Afifah, I.N., Fadli, M., Ismoyo, D.O., 2018. Coastal
e) To encourage rural people in the middle and upper Ciliwung and hazard assessment in northern part of Jakarta. Procedia Eng. 212, 1279–1286.
Cisadane watersheds to maintain and establish home-gardens and https://doi.org/10.1016/j.proeng.2018.01.165.
mixed gardens and other surface water retention such as ponds, NCICD, 2014. Master Plan National Capital Integrated Coastal Development.
Coordinating Ministry for Economic Affairs, Jakarta.
small check dams, and ground water recharge wells. To get this Oppusunggu, R.E., Tantular, R., 2015. Creating People's awareness and pushing active
program moving at a massive scale, it should be integrated to the contribution. Case: wider public engagement on flood and land use problems in
incentive and dis-incentive system, for example through tax mea- Jakarta and surroundings. Procedia Soc. Behav. Sci. 184, 240–244. https://doi.org/
10.1016/j.sbspro.2015.05.085.
sures or another incentive mechanism. Sabar, A., 2009. Kajian Ekstremitas Debit Air dan Pelestarian Air di Kawasan Konservasi.
In: Proceeding of the National Seminar on Implementation and Development of
Acknowledgment Environmentally Sound Technology in the Globalization Era. Surabaya, October
2009.
Sagala, S., Lassa, J.A., Yasaditama, H., Hudalah, D., 2013. The Evolution of Risk and
We would like to thank the financial support from Universitas Vulnerability in Greater Jakarta: Contesting Government Policy in Dealing with a
Padjadjaran through the Academic Leadership Grant (ALG). Megacity's Exposure to Flooding. pp. 18 IRGSC Working Paper, No.2.
Singh, R., Tiwari, K.N., Mal, B.C., 2006. Hydrological studies for small watershed in India
using the ANSWERS model. J. Hydrol. 318, 184–199. https://doi.org/10.1016/j.
Appendix A. Supplementary data jhydrol.2005.06.011.
Siswanto, van der Schrier, G., van Oldenborgh, G.J., van den Hurk, B., Aldrian, E.,
Swarinoto, Y., Sulistiya, W., Sakya, A.E., 2017. A very unusual precipitation event
Supplementary data related to this article can be found at https://
associated with the 2015 floods in Jakarta: an analysis of the meteorological factors.
doi.org/10.1016/j.wace.2018.08.002. Weather Clim. Extreme 16, 23–28. https://doi.org/10.1016/j.wace.2017.03.003.
Sun, Y., Doan, C.D., Dao, A.T., Liu, J., Liong, S.Y., 2014. Improving numerical forecast
References accuracy with ensemble Kalman filter and chaos theory: case study on Ciliwung river
model. J. Hydrol. 512, 540–548. https://doi.org/10.1016/j.jhydrol.2014.03.016.
Takagi, H., Esteban, M., Mikami, T., Fujii, D., 2016. Projection of coastal floods in 2050
Ali, M., Hadi, S., Sulistyantara, B., 2016. Study on land cover change of Ciliwung Jakarta. Urban Clim. 17, 135–145. https://doi.org/10.1016/j.uclim.2016.05.003.
downstream watershed with spatial dynamic approach. Procedia Soc. Behav. Sci. Wang, J., Wang, H., Ning, S., Hiroshi, I., 2018. Predicting future land cover change and its
227, 52–59. https://doi.org/10.1016/j.sbspro.2016.06.042. impact on streamflow and sediment load in a trans-boundary river basin. Proc. IAHS
Arifasihati, Y., Kaswanto, 2016. Analysis of land use and cover changes in Ciliwung and 379, 217–222. 2018. https://doi.org/10.5194/piahs-379-217-2018.
Cisadane Watershed in three decades. Procedia Environ. Sci. 33, 465–469. https://

122

Das könnte Ihnen auch gefallen