Beruflich Dokumente
Kultur Dokumente
Sustainability
CSR produces a range of energy efficient building products and systems which
have the potential to reduce heating and cooling costs of homes and buildings,
essentially saving tonnes of greenhouse gases each year. Many of these
products are also produced from recycled materials thus:
• Reducing the demand for raw materials
• Lowering emissions and pollution during manufacturing
• Saving land-fill space.
CSR Guarantee
CSR Building Products guarantees its Gyprock™ products to be free of defects
in materials and manufacture.
If a CSR product does not meet our standard, we will, at our option, replace or
repair it, supply an equivalent product, or pay for doing one of these.
CSR recommends that only products, components and systems recommended
by it be used. If this is not done, CSR will need to be satisfied that any defect
in its product is attributable to our failure to meet our standard (and not another
cause) before this guarantee applies.
This guarantee excludes all other guarantees and liability for damage or loss
in connection with defects in CSR's product, other than those imposed by
legislation.
Ceiling Systems E
Services Systems F
Index IN
A Nº Nº Nº Nº Nº Nº Nº Nº Nº Nº Nº Nº
on page A3. The Red Introduction 010 B10 230 B18 513 B20 698 C22 834 E9 955 E12
015 B10 231 B18 515 B20 722 D16 835 E9 958 E11
025 B10 235 B18 516 B20 723 D16 836 E9 959 E11
032 B10 240 B19 520 B21 724 D16 837 E9 967 B31
035 B10 241 B19 521 B21 730 D16 838 E9 968 B31
D
091 B29 297 B25 544 D11 774 D8 862 E13 75PP D13
092 B29 298 B26 545 D11 775 D8 863 E13 75PP-DC D13
E
125 B22 330 C6 575 C9 781 D8 870 E12 B35
126 B34 335 C7 580 C9 783 D8 871 E12 Powerwall
127 B34 350 C7 582 C9 784 D8 874 E13 Hebel
Ceiling Systems
C19
128 B34 352 C7 600 B11 787 D9 875 E13 Powerwall
F
152 B23 390 C16 611 B13 798 D17 891 E15 SS08 F5
155 B23 391 C16 613 B13 801 E6 892 E15 SS09 F5
reference.
Service Systems 165 B36 392 C16 614 B13 803 E6 893 E15 SS10 F5
G
175 B23 415 C15 653 C8 808 E6 903 C17
178 B37 419 C15 654 C8 809 E6 911 C18 SS19 F6
SS20 F6
Z
194 B38 493 C23 670 C14 816 E7 924 C20 SS30 F7
each page.
195 B38 494 C23 671 C14 817 E7 925 C20 SS31 F7
IN
208 B15 501 C11 680 C10 823 E8 941 B32 SS40 F8
212 B16 502 C11 681 C10 824 E8 942 B32 SS41 F8
216 B16 503 C11 682 C10 825 E8 945 B28 SS42 F8
Index 217
218
B15
B15
506
507
C12
C12
690
693
C21
C21
826
827
E8
E8
946
947
B28
B28
SS44
SS45
F4
F4
222 B17 508 C12 694 C22 829 E8 950 E12 SS46 F4
223 B17 509 C12 695 C22 831 E9 951 E12
225 B17 510 B20 696 C21 832 E9 952 E12
System Tables – Sections B, C, d, e & F Steel Frame Internal Wall Systems – Single Stud
SYSTEM SPECIFICATION TYPICAL LAYOUT (CSR 010a shown) ACOUSTIC
PKA-052
➎ ➏ ➐
➋ Check for appropriate fire rating (FRL) if required.
• Lining material as per system table.
NOTES:
Acoustic performance valid for studs 0.50 BMT.
Rw / Rw+Ctr
92 150
CSR 005
➌
BOTH SIDES (c) 75 GW Partition 11kg – 42/33 42/33 43/34 45/36
➋
–/–/–
➊ ➍
• 1 x 13mm GYPROCK
Plasterboard CD.
(d) TSB3/ASB3 Polyester
(e) 60 Soundscreen™ 1.6
39/31 39/32 40/33 41/34 43/36
– 41/31 42/32 43/33 45/35
➎ Check System Specifications for elements common to the systems. CSR 011
SIDE ONE
• 1 x 13mm GYPROCK
WALL THICKNESS mm
(a) Nil
(b) 50 GW Partition 11kg
77 90 102 118
35/27 37/30 37/30 38/31 41/34
39/29 41/32 42/33 43/34 45/36
176
➏ Check the typical layout illustration for the basic system format.
• 1 x 13mm GYPROCK (e) 60 Soundscreen™ 1.6 – 42/32 43/33 44/34 46/36
Plasterboard CD.
WALL THICKNESS mm 77 90 102 118 176
CSR 015 (a) Nil 38/30 39/32 40/33 42/35 45/38
SIDE ONE
(b) 50 GW Partition 11kg 43/33 44/35 45/36 47/38 49/40
• 1 x 13mm GYPROCK
(c) 75 GW Partition 14kg – 46/37 46/37 48/39 50/41
➑
Plasterboard CD.
section. Installation layouts are shown at the back of sections (where applicable).
• Wall with required sound rating. WALL THICKNESS mm 77 90 102 118 176
GYPROCK
Panel
Ceiling
B9
System
The Red Book™
EXTENT OF INSULATION
1200mm each side
SYSTEM Nº CEILING LININGS Nil Entire Ceiling
of the wall
Rw
(a) Gyprock plasterboard panel 10mm 38 44 45
Flanking Path Systems – Section G (ef) USG Radar, Impressions, Olympia Micro 15mm
35
30-36
35-36
30-36
35-36
PKA–A031
100mm
➋ Check the typical layout illustration for the appropriate system format.
• Floor or roof structure. System insulation min System insulation
➎
• 50mm Bradford Glasswool Partition batts –
11kg/m3 to extent specified in table.
Ceiling Framing
➏
• Ceiling lining as per system table.
Tape and set or
• Wall with required sound rating.
➋
GYPROCK
Acoustic performance values are provided via a matrix of options. SYSTEM Nº CEILING LININGS Nil
1200mm each side
of the wall
Rw / Rw+Ctr
Entire Ceiling
46/38
J-Track fixed to studs
➌49/40
52/44
50/41
53/45
G3
Fix track at each
main runner
The Red Book™ J-Track
Main Runner
Mechanical fire
damper tested and
approved for
AS1530.4 10mm dia. MS rod
Junctions & Penetrations – Section Z FIG Z002: DEFLECTION HEAD FIG Z005: HEAD FOR SUSPENDED CEILING
100mm max.
(do not fix Fix cornice to
Refer to manufacturer for assessment number and installation details.
Steel studs
at 600mm
Furring Channel in centres
through track) ceiling only with normal setout position Rondo angles
Gyprock Cornice Finish as required mechanically
Cement fixed to studs
➋
channel fix track to furring
at each intersection
Contents
An Introduction to The Red Book™ A6
Components A6 – A15
Definitions A24
530mm
590mm
EC08 Partition is an economical, non-fire rated board for
general areas where acoustic requirements are not high.
EC08 Fire is the original GECA certified EC08™ board with
fire and acoustic rating for party walls and meeting rooms.
EC08 Impact is fire and acoustic rated with impact resistance 1130mm
1191mm
for high traffic areas such as hallways and stairs in education
and health facilities. All products in the range have been
certified by GECA as meeting the requirements of their
environmental standard for Panel Boards. Supatone™ is a paper faced white ceiling tile suited to basic
commercial ceilings. A low maintenance bright white panel,
Gyprock ™ Flexible Plasterboard has been designed
it can be wiped clean with a damp cloth.
for curved wall and ceiling systems and has an enhanced
core to enable bending to a small radius. It is composed of Freshtone™ diamond White has a lightly textured vinyl
a gypsum core encased in a heavy duty linerboard. Long surface which resists fading and mould growth. With a white
edges are recessed to assist in producing a smooth, even finish, it is suitable for shopping centres, factories and offices.
and continuous surface once jointed. Gyprock™ Flexible Acoustic Wall and Ceiling Panels
Plasterboard is 6.5mm thick and is installed in two layers.
CSR provides a range of acoustic ceiling and wall products
CeminSeal™ Wallboard is an autoclaved, cellulose fibre through the Fricker Comprador division. The range includes
reinforced cement sheet that is immune to permanent mineral fibre and glasswool ceiling panels, metal pan ceiling
water damage and has high impact resistance. Ceminseal™ panels, and glasswool wall panels. Brands include Ecophon,
Wallboard is suitable for internal walls as well as internal USG, Daiken, Fricker and Comprador.
and external ceiling applications. It has a recess on both
The products have a variety of physical properties to assist
long edges so that sheets may be flush jointed, using CSR
in their specification, including Noise Reduction Coefficient
jointing materials.
(NRC), Ceiling Attenuation Class (CAC), Light Reflectance
Gyprock™ Perforated Plasterboard has been designed for (LR), colour and edge profile. These and other properties
use on walls and ceilings where additional sound absorption are listed in Section E.
is required. It is composed of a gypsum core encased in a
CSR Fricker Comprador supplies fully integrated ceiling
heavy duty linerboard and incorporates CD technology. Long
solutions including suspension systems, ceiling tiles, lights,
edges are recessed for flush jointing. Perforations total 8.2%
diffusers and perimeter trims.
of the sheet area. For detailed pattern information, refer to
Section ‘E’. For more information call 1300 374 253.
3600mm
GYPRoCk™ GYPRoCk™
CoVe CoRNICe JAZZ CoRNICe
Impressions
ClimaPlus™
• 15mm thick mineral
fibre panels with three
edge options.
GYPRoCk™ GYPRoCk™
SYMPhoNY CoRNICe CoNCeRTo CoRNICe
Mars ClimaPlus™
• 19mm thick mineral
fibre/glasswool
panels with three
edge options.
GYPRoCk™ GYPRoCk™
TeMPo CoRNICe CLASSIC CoRNICe
olympia Micro
ClimaPlus™
• 15mm thick mineral
fibre panels with three
edge options.
GYPRoCk™ ShAdoWSeT
Mass
Gyprock™ Cornice Products Size
kg/m2
55 0.7kg/m
COVE CORNICE 70 0.9kg/m
90 1.3kg/m
CLASSIC™ CORNICE 90 1.2kg/m
TEMPO™ CORNICE 90 1.8kg/m
SYMPHONY™ CORNICE 75 0.9kg/m
CONCERTO™ CORNICE 90 1.6kg/m
JAZZ™ CORNICE 75 1.8kg/m
SHADOWSET™ 105 1.0kg/m
Fasteners
CSR Gyprock distributes a comprehensive range of ring
shank nails, hot-dip galvanised clouts, and screws for
use with timber and steel framing to accommodate most
installation applications. For exterior applications, refer to the
appropriate installation guide.
NOTES:
Type 'W' screws of equivalent length may be used as an alternative to Type S ‘NP’ when fixing to timber only.
Predrill 9mm and 12mm Wallboard for easier fixing.
Fixings are suitable for internal applications only.
NP = Needle Point Screws.
DP = Drill Point Screws.
GAL = Galvanised.
TABLe A8: FIxING FIBRe CeMeNT ANd PLASTeRBoARd To STeeL 0.5 – 0.8mm BMT
TABLe A9: FIxING FIBRe CeMeNT ANd PLASTeRBoARd To STeeL 0.8 – 2.4mm BMT
NOTES:
Predrill 9mm and 12mm Wallboard for easier fixing.
Fixings are suitable for internal applications only.
NP = Needle Point Screws.
DP = Drill Point Screws.
GAL = Hot-Dip Galvanised.
Product Abbreviation
25mm Bradford Fibertex 450 – 80kg/m3 25 Fibertex 450
45mm Bradford Rockwool Partition batts – 38kg/m3 45 Rockwool Partition batts
60mm Bradford Soundscreen™ R1.6 wall batts (Rockwool) – 35kg/m3 60 Soundscreen™ 1.6
75mm Bradford Soundscreen™ R2.0 wall batts (Rockwool) – 32.5kg/m3 75 Soundscreen™ 2.0
88mm Bradford Soundscreen™ R2.5 wall batts (Rockwool) – 40kg/m3 88 Soundscreen™ 2.5
120mm Bradford Soundscreen™ R3.0 floor / ceiling batts (Rockwool) – 30kg/m3 120 Soundscreen™ 3.0
50mm Bradford Glasswool Partition batts – 11kg/m3 50 GW Partition – 11kg
75mm Bradford Glasswool Partition batts – 11kg/m3 75 GW Partition – 11kg
110mm Bradford Glasswool Partition batts – 11kg/m3 110 GW Partition – 11kg
165mm Bradford Glasswool Partition batts – 11kg/m3 165 GW Partition – 11kg
50mm Bradford Glasswool Partition batts – 14kg/m3 50 GW Partition – 14kg
75mm Bradford Glasswool Partition batts – 14kg/m3 75 GW Partition – 14kg
100mm Bradford Glasswool Partition batts – 14kg/m3 100 GW Partition – 14kg
75mm Bradford Gold Batt™ R1.5 wall batts (Glasswool) – 8.8kg/m3 75 Gold Batts™ 1.5
75mm Bradford Gold Batt™ R2.0 wall batts (Glasswool) – 18.0kg/m3 75 Gold Batts™ 2.0
90mm Bradford Gold Batt™ R2.0 wall batts (Glasswool – 10.5kg/m3 90 Gold Batts™ 2.0
90mm Bradford Gold Batt™ R2.7 wall batts (Glasswool) – 34.0kg/m3 90 Gold Batts™ 2.7
140mm Bradford ceiling Gold Batt™ R2.5 (Glasswool) – 6.4kg/m3 140 Gold Batts™ 2.5
165mm Bradford ceiling Gold Batt™ R3.0 (Glasswool) – 6.7kg/m3 165 Gold Batts™ 3.0
215mm Bradford ceiling Gold Batt™ R4.0 (Glasswool) – 6.9kg/m3 215 Gold Batts™ 4.0
Tontine TSB 2 (50mm) / Autex ASB 2 (50mm) Polyester Insulation TSB2/ASB2 Polyester
Tontine TSB 3 (65mm) / Autex ASB 3 (60mm) Polyester Insulation TSB3/ASB3 Polyester
Tontine TSB 4 (75mm) / Autex ASB 4 (70mm) Polyester Insulation TSB4/ASB4 Polyester
Tontine TSB 5 (85mm) Polyester Insulation TSB5 Polyester
Tontine Blanket (25mm) 10kg/m3 Polyester Insulation TBL/1025 Polyester
38mm Bradford Masonry Wall Blanket (HP Glasswool) Masonry Wall Blanket R1.2
Thermal Performance
Gyprock™ and Cemintel™ products have been tested to
ASTM C518 for thermal performance.
The ‘R’ values for Gyprock™ plasterboards are:
• 10mm plasterboard = 0.04 – 0.05 m2K/W.
• 13mm plasterboard = 0.05 – 0.07 m2K/W.
• 16mm plasterboard = 0.07 – 0.09 m2K/W.
Product
Properties
Thermal & Moisture Stability
Gyprock ™ plasterboard and Cemintel ™ fibre cement
products are stable building materials when subjected to the
normal range of interior temperature and humidity conditions.
Thermal coefficient of Linear Expansion (α).
• Plasterboard: α =16.2 x 10 -6 mm (mm/ºC) in the
temperature range 4°C to 38°C.
• Fibre cement: α = 7.5 x 10-6/°C.
• Final length is calculated as follows:
Lf = Li (1 + αT).
The hygrometric coefficient of expansion (δ).
• P l a s t e r b o a rd : δ = 7 . 2 x 1 0 -6 m m / m m / % R . H .
(5% – 90% R.H.). Final length is calculated as follows:
Lf = Li (1 + δRH).
• Fibre cement: δ = 0.18% (expansion from equilibrium to
saturated). Final length is calculated Lf = Li x δ x (% of
saturation).
Internal Moisture
Gyprock™ plasterboard must not be used where it will be
in contact with liquid water or an atmosphere of constant
relative humidity above 90%.
Gyprock ™ Plasterboard CD, Gyprock Supaceil ™ and
Gyprock Soundchek™ are designed for use in dry areas only.
ASEA Group
Standards
CSR Product Report
m2/kg Number All materials and procedures shall comply with the following
10 – 13mm Plasterboard CD <250 1 ➊ standards where applicable, and all additional details
10mm SUPACEIL™ <250 1 ➊ contained in Gyprock™ and Cemintel™ Technical Literature.
FIG A3: STANdARd TIMe vs TeMPeRATuRe CuRVe • The second 120 indicates ‘Insulation’ for 120 minutes.
900
loadbearing walls; or FRLs expressed as x/y/z* relate to walls
with additional design limits.
800
The test performance of the specimen is expressed as a ‘Fire Fire rated smoke proof walls should be selected from the
Resistance Level’, which indicates the number of minutes for steel framed systems (refer to Section ‘B’) with an appropriate
which the specimen fulfils the requirements of the three fire FRL.
test criteria. These numbers are then rounded down to the Smoke proof walls required for Class 9c buildings may use
nearest regulatory requirement. steel or timber framing with linings of 13mm Gyprock™
All systems in this guide with a stated FRL have been Plasterboard CD or CeminSeal™ Wallboard. Refer to systems
assessed by Registered Testing Authorities, including CSIRO, CSR 010, 654 and 310.
BRANZ and Exova Warrington Fire.
DECORATION
Flat/Matt/Satin/
Semi-gloss/Gloss
Low Sheen
Pastel/
Dark tones
Mid-tones
Glancing light
Shadow zone
Jointing
Glancing light
TABLe A12: STReNGTh ANd IMPACT PRoPeRTIeS TABLe A13: MINIMuM RAdIuS FoR CuRVed WALLS
Lining Bending Soft Body Surface
Plasterboard Lining Minimum Radius Minimum Radius
Strength Impact Damage
(Concave) (Convex)
Resistance Resistance
6.5mm Flexible
10mm Gyprock 450 mm 250 mm
✰ ✰ ✰ Plasterboard
plasterboard CD
10mm plasterboard
10mm Superchek ✰✰ ✰✰ ✰✰✰ 900 mm 900 mm
CD
13mm Impactchek ✰✰✰✰ ✰✰✰ ✰ 13mm plasterboard
13mm EC08 CD and 10mm 1000 mm 1000 mm
✰✰✰ ✰✰✰ ✰✰✰
Impact Supaceil
6mm CeminSeal 13 & 16mm Fyrchek 3m 3m
✰ ✰ ✰✰✰✰
Wallboard 13mm Perforated
20m 20m
Note: More ✰’s indicates higher performance. Plasterboard sheet
Where the background noise level is low, such as in remote • The lack of simplicity in construction could reduce actual
areas, consideration should be given to providing a higher performance.
than standard level of sound insulation.
Minimum Performance Levels
Variation in occupant Perception of for external Walls
Noise The BCA does not set minimum performance levels of
Tolerance for noise varies greatly between people, and transmission for external walls. Guidance should be sought
variations of up to 15dB can be considered acceptable. from an acoustic consultant or local authority for setting
This means consideration should be given to the occupant’s the design requirements of these elements, as they may be
expectation of the internal acoustic environment. Users of affected by road or aircraft noise.
concert halls and practice rooms may have higher acoustic Issues that may affect the design levels for external walls are:
expectations than guests of inner city hotels.
• Va r i a t i o n i n o c c u p a n t p e r c e p t i o n s o f n o i s e ,
e.g. high, medium or low cost housing.
Minimum Performance Levels for
• Background noise levels are low.
Internal Walls and Ceilings
• Flanking transmission of the surrounding structure,
The BCA sets out minimum performance levels for internal
particularly at windows and doors.
walls and ceilings based on acceptable standards for
affordable housing. The performance requirements are in • The lack of simplicity in construction could reduce actual
terms of Rw, Rw+Ctr and Ln,w+CI. performance.
• Flanking transmission of the surrounding structure. Perimeters and penetrations for services must be sealed with
Lightweight structures can be more prone to low frequency an acoustic sealant that is capable of accommodating the
flanking. expected building movement.
• The presence of services will vary which BCA provisions For systems that are multi-layered, such as masonry
are applicable, and could mean separate construction is composite systems, each layer must be air tight, as services
required. such as power points and switches can act as airborne
flanking paths. To remedy this, consider using acoustic rated
• The lack of simplicity in construction could reduce actual
power boxes, the Gyprock™ Silencer, and insulation in the
performance.
cavity. Refer to flanking details, Section ‘Z’.
Contents
Stud Selection Tables B2 – B4
Introduction B4
Design Considerations B4 – B6
Installation B6 – B7
Components B7 – B8
Internal Wall System Specifications
Single Stud B9 – B12
Rondo Quiet Stud B13
Staggered Stud B14 – B16
Double Stud B17 – B19
StrataWall™ B20 – B22
Party Wall B23 – B24
SecurityWall™ B25 – B27
Resilient Mount B28
Cinema Wall B29
Studs Lined One Side B30 – B31
Shaft Wall B32
Laminated Services B33 – B36
External Wall System Specifications
Steel Cladding B37
ExpressWall™ B38 – B39
RendaLine™ B39 – B41
Cladding On Battens B42
Texture Base Sheet For Houses B43
Concrete B44
Hebel Powerpanel™ B44
Masonry B45
Columns & Beams B46
ECO8 Internal Wall System Specifications B47 – B52
System Installation Details B53 – B65
TABLE B1: MAXIMUM WALL HEIGHT WITH RONDO LIPPED STEEL STUDS – NON-LOADBEARING WALLS
– WALLS GENERALLY (LOAD = 0.25kPa)
Stud Size 51 64 76 92 150
Wall Frame and
BMT 0.5 0.75 0.5 0.75 1.15 0.55 0.75 1.15 0.55 0.75 1.15 0.75 1.15
Lining Configuration
Linings (mm) Maximum Wall Height (m)
10 2.77 2.91 3.33 3.93 4.17 3.70 4.43 4.65 4.54 4.83 5.11 6.55 7.22
600mm max. cts
13 3.20 3.32 3.72 4.22 4.43 4.13 5.02 5.22 4.94 5.50 5.75 6.99 7.54
16 3.38 3.52 3.91 4.35 4.52 4.30 5.25 5.42 5.18 5.71 5.92 7.19 7.65
CSR 080(-/180/180) 2.60 2.60 3.30 3.60 4.30 3.80 4.10 5.00 4.40 4.80 5.00 7.00 7.65
600mm max. cts 10 2.32 2.60 2.72 3.13 3.53 3.20 3.58 4.05 3.61 4.13 4.69 5.33 6.81
13 2.32 2.60 2.72 3.25 3.58 3.24 3.82 4.05 3.61 4.18 4.69 5.37 6.81
16 2.32 2.60 2.75 3.28 3.59 3.25 3.87 4.05 3.61 4.20 4.69 5.37 6.81
TABLE B2: MAXIMUM WALL HEIGHT WITH RONDO LIPPED STEEL STUDS – NON-LOADBEARING WALLS
– WALLS OF SHAFTS AND FIRE ISOLATED EXITS (LOAD = 0.35kPa)
Stud Size 51 64 76 92 150
Wall Frame and
BMT 0.5 0.75 0.5 0.75 1.15 0.55 0.75 1.15 0.55 0.75 1.15 0.75 1.15
Lining Configuration
Linings (mm) Maximum Wall Height (m)
10 2.42 2.55 2.93 3.49 3.70 3.25 3.81 3.81 3.81 3.81 3.81 3.81 3.81
600mm max. cts
13 2.81 2.92 3.29 3.75 3.94 3.65 4.43 4.60 4.39 4.84 5.06 5.71 5.71
16 3.00 3.12 3.45 3.84 3.99 3.78 4.62 4.77 4.60 5.01 5.20 6.37 6.89
CSR 080(-/180/180) 2.60 2.60 3.30 3.60 4.30 3.78 4.10 4.77 4.40 4.80 5.00 6.37 6.89
600mm max. cts 10 2.07 2.34 2.34 2.80 3.15 2.76 3.20 3.62 3.06 3.70 3.81 3.81 3.81
13 2.07 2.34 2.34 2.80 3.17 2.76 3.37 3.62 3.06 3.70 4.20 4.83 5.53
16 2.07 2.34 2.34 2.90 3.18 2.76 3.41 3.62 3.06 3.70 4.20 4.83 5.53
NOTES:
TABLE B3: MINIMUM NUMBER OF NOGGINGS
Deflection Limit is span/240 to a maximum of 30mm, in accordance
with BCA Specification C1.8. Number of Noggings
Lining Configuration Wall Height (m)
Tabulated heights do not include axial loads (except self weight) or (equally spaced)
shelf loading. 0 - 4.4 0
Lined Both Sides
Loadings: Table B1 Pultimate = 0.375 kPa, Pservice = 0.25 kPa. 4.4 - 8.8 1
Loadings: Table B2 Pultimate = 0.525 kPa, Pservice = 0.35 kPa. 0.0 - 3.0 1
Walls are not for external applications. Lined One Side* 3.0 - 6.0 2
All loadings in accordance with AS1170:2002. 6.0 - 8.0 3
Walls analysed in accordance with AS4600:1996. Staggered Studs All 0
Noggings in accordance with Table B3.
NOTE: * Plus noggings at head. Refer to details in Section Z.
Staggered stud walls use 64mm lipped studs in 92mm track with
Gyprock™ Staggered Stud Clip.
Tables have been prepared by Rondo Building Services Pty Ltd.
13 4.13 4.41
16 4.30 4.58
TABLE B5: MAXIMUM WALL HEIGHT FOR GYPROCK SECURITYWALL™ SYSTEMS (UDL = 0.25kPa)
Wall Frame and Lining Configuration Security Panel Minimum Lining Thickness (mm) Maximum Wall Height (m)
TABLE B6: MAXIMUM WALL HEIGHT FOR GYPROCK STRATAWALL™ WITH H-STUDS AT 600mm CENTRES
0.25 3.0 –
0.25 – 3.0
or or
TABLE B7: MAXIMUM WALL HEIGHT FOR GYPROCK STRATAWALL™ WITH C-STUDS AT 600mm CENTRES – WALL
SYSTEM FRL –/60/60
• To be in accordance with AS4600. • In wet areas, Gyprock Fyrchek MR™ must be used in lieu
of Gyprock Fyrchek™.
• Assuming no contribution to axial strength is required of
the wall linings. • For single layer systems and the first layer of multi-layer
systems, butt joints must be backed by either a stud or
To meet the stated Fire Resistance Level (FRL), the axial load
nogging.
capacity of some wall systems is reduced. This is a result of
the steel weakening at high temperature during a fire test. • For multi-layer vertically sheeted applications, outer layer
The systems are noted with an Axial Capacity Reduction butt joints may be reinforced using laminating screws
percentage (ACR%). For these systems, the designer must without the need for framing support.
increase the applied loads before selecting stud size to • Joints in the outer layer of all systems lined with
compensate for the axial capacity reduction percentage, as plasterboard or Wallboard must be set with Gyprock™
shown in the system specification. paper tape. As a minimum, a single coat finish may be
The capacity of head and base tracks for walls subject to used.
wind loads must be checked. Typically, studs are cleated • All joints in Texture Base Sheets must be formed on
at head and base with a Rondo angle bracket. Contact framing.
Rondo for more information on designing walls subject to
• Joints in external systems lined with Cemintel™ Texture
wind loads.
Base Sheet must be set with the tape and compound
recommended for the texture coating system.
Fire Resistance
For additional information on frame design and detailing,
The steel frame wall systems in this manual are suitable
including treatment at junctions, sub floor and roof areas,
for the stated FRL when designed in accordance with the
cavity barriers and penetrations, refer to brochure NºGYP544,
structural considerations above. Wall system ratings apply
Gyprock™ Steel Frame Wall Systems.
in either direction, unless noted otherwise.
The Fire Resistance Level (FRL) of the systems detailed in
CSR fire rated steel stud wall systems have been designed
this section will not be detrimentally affected by:
with fire protection that limits the temperature of the
steel framing to a maximum of 450°C at the FRL stated. • Increasing the thickness of the wall.
Therefore the structural design of the framing need only • Increasing the cross-sectional dimensions of the framing
provide for normal temperature conditions, and no additional elements.
consideration of fire rating is required. In some systems this • Decreasing the stud spacing.
temperature is exceeded and the axial capacity of the stud
must be reduced to compensate for the loss of strength. The • Decreasing the fixing centres of wall sheet materials.
percentage reduction is noted for each affected systems. • The inclusion of bulk cavity insulation materials such as
To protect structural steel beams and columns that are Glasswool, Rockwool and Polyester.
entirely within a wall, the FRL of the wall system must be at • The use of Fyrchek™ MR, Impactchek™, EC08 Fire or
least equivalent to that required by the structural member. EC08 Impact plasterboard in lieu of Fyrchek™ plasterboard
For example, a wall system with FRL 90/90/90 provides FRL of the same thickness.
90/–/– for a steel column within the wall. • Additional layers of plasterboard or Cemintel™ fibre cement.
Framing & Lining • Wall curved in plan with a radius of curvature no less than
Steel framed walls required to have an FRL must comply 3m.
with the following: • The attachment of light weight fixtures through to the framing.
• The addition of an exterior cladding.
• The order of lining sheets that are fixed direct to framing. Walls lined with Gyprock™ plasterboard or CeminSeal™
Wallboard may be finished with tiles. For tiles greater than
• The substitution of Aquachek™ for Gyprock™ Plasterboard
32kg/m 2 or over 6.5mm thickness, specific installation
CD of the same thickness.
details apply. Refer to the appropriate installation manual.
• The substitution of Gyprock Fyrchek MR™ for Fyrchek™ of
the same thickness. Plasterboard Jointing & Finishing
Refer to the Gyprock ™ Residential Installation Guide,
NºGYP547 and Cemintel ™ Wet Area Lining Systems,
NºFC101 for detailed jointing and finishing information.
It should be noted that:
• Multi-layered systems only require jointing and finishing of
the outer layer.
• It is recommended that a water resistant taping
compound, such as Gyprock™ Wet Area Base Coat be
used at horizontal and vertical joints within wet areas such
as showers.
External Walls
TABLE B9: RONDO STEEL STUD AVAILABILITY
CSR external wall systems rely on a range of cladding
systems to provide weather resistance. There is a range of Stud Stud Depth (mm)
effectiveness of these systems, and CSR recommends the BMT (mm) 51 64 76 92 150
cladding be installed with a drained cavity. Cavity systems 0.50* ✓ ✓ – – –
allow drainage and drying of any water that penetrates, and 0.55* – – –
✓ ✓
are known to have good long-term performance.
0.75 ✓ ✓ ✓ ✓ ✓
Sarking is also recommended to provide additional weather
1.15 – ✓ ✓ ✓ ✓
protection to framing and lining.
NOTE: * Rondo Hemmed Stud
External walls require specific design for condensation
control and energy efficiency, depending on the climate and
internal environment. Contact CSR Bradford for information
on thermal insulation systems and products.
TABLE B10: QUIET STUD
Depth
BMT BMT 18
0.75 1.15
6.35 8.0
33.5 35.0
6mm
GYPROCK STAGGERED STUD CLIP
Rondo
64mm
Lipped
Steel
Stud
92mm
Rondo
92mm
Track
6mm
43mm
CSR Gyprock®
Staggered Stud Clip
5.0
BMT
Depth
0.50/0.55
5.0
35.4
25mm
35mm
PKA-052
NOTES:
Acoustic performance valid for studs 0.50 BMT.
PKA-052
NOTES:
Acoustic performance valid for studs 0.50 BMT.
CSR 033 SIDE ONE (a) Nil 41/34 43/36 44/37 45/38 48/42
• 1 x 13mm GYPROCK (b) 50 GW Partition 11kg 46/37 48/39 49/40 50/41 52/44
SOUNDCHEK
Plasterboard. (c) 75 GW Partition 11kg – 50/41 50/41 51/42 53/45
–/–/–
SIDE TWO (d) TSB3/ASB3 Polyester 46/39 47/40 48/41 49/42 51/45
• 2 x 13mm GYPROCK (e) 60 Soundscreen™ 1.6 – 49/39 50/40 51/41 53/44
SOUNDCHEK
Plasterboard. WALL THICKNESS mm 90 103 115 131 189
CSR 039 (a) Nil 34/26 37/30 37/30 38/31 41/34
SIDE ONE
(b) 50 GW Partition 11kg 39/29 42/33 42/33 43/34 45/36
• 1 x 13mm GYPROCK
IMPACTCHEK. (c) 75 GW Partition 11kg – 44/35 43/34 44/35 46/37
–/–/–
SIDE TWO (d) TSB3/ASB3 Polyester 39/31 41/34 41/34 42/35 44/37
• 1 x 13mm GYPROCK (e) 60 Soundscreen™ 1.6 – 43/33 43/33 44/34 46/36
Plasterboard CD.
WALL THICKNESS mm 77 90 102 118 176
CSR 600 (a) Nil 34/27 36/29 37/30 38/31 41/34
(b) 50 GW Partition 11kg 39/30 41/32 42/33 43/34 45/36
BOTH SIDES (c) 75 GW Partition 14kg – 44/35 44/35 45/36 47/38
–/–/– • 1 x 6mm CeminSeal™
(d) TSB3/ASB3 Polyester 39/32 40/33 41/34 42/35 44/37
Wallboard.
(e) 60 Soundscreen™ 1.6 – 42/32 43/33 44/34 46/36
WALL THICKNESS mm 63 76 88 104 162
CSR 601 (a) Nil 39/32 40/33 41/34 42/35 45/39
(b) 50 GW Partition 11kg 44/35 45/36 46/37 47/38 49/41
BOTH SIDES (c) 75 GW Partition 11kg – 47/38 47/38 48/39 50/42
–/–/– • 1 x 9mm CeminSeal™
(d) TSB3/ASB3 Polyester 44/37 44/37 45/38 46/39 48/42
Wallboard.
(e) 60 Soundscreen™ 1.6 – 46/36 47/37 48/38 50/41
WALL THICKNESS mm 69 82 94 110 168
CSR 605 (a) Nil 34/26 35/28 37/30 37/30 41/34
SIDE ONE
(b) 50 GW Partition 11kg 39/29 40/31 42/33 42/33 45/36
• 1 x 6mm CeminSeal™
Wallboard. (c) 75 GW Partition 14kg – 43/34 44/35 44/35 47/38
–/–/–
SIDE TWO (d) TSB3/ASB3 Polyester 39/31 39/32 41/34 41/34 44/37
• 1 x 13mm GYPROCK (e) 60 Soundscreen™ 1.6 – 41/31 43/33 43/33 46/36
Plasterboard CD.
WALL THICKNESS mm 70 83 95 111 169
PKA-052
• Lining material as per system table.
• Steel Studs at 600mm maximum centres.
• Lining material as per system table.
NOTES:
Acoustic performance valid for studs of 0.50 BMT.
*ACR = Axial Capacity Reduction
PKA-052
• Lining material as per system table.
• Steel Studs at 600mm maximum centres.
• Lining material as per system table.
NOTES:
Acoustic performance valid for studs of 0.50 BMT.
*ACR = Axial Capacity Reduction
PKA-052
NOTES:
*ACR = Axial Capacity Reduction
PKA-052
NOT
Deemed
• Lining material as per system table. Discontinuous
• Staggered Steel Studs at 600mm maximum centres Construction
each side. Studs restrained in track or angle at top and
bottom with minimum 22mm clearance between stud and
opposing lining.
• Lining material as per system table.
PKA-052
NOT
Deemed
• Lining material as per system table. Discontinuous
• Staggered Steel Studs at 600mm maximum centres Construction
each side. Studs restrained in track or angle at top and
bottom with minimum 22mm clearance between stud and
opposing lining.
• Lining material as per system table.
PKA-052
• Lining material as per system table.
① TEST
• Staggered Steel Studs at 600mm maximum centres TL461
each side. Studs restrained in track or angle at top and
bottom with minimum 22mm clearance between stud and NOT
opposing lining. Deemed
Discontinuous
• Lining material as per system table. Construction
NOTES:
*ACR = Axial Capacity Reduction
NOTES:
Unless otherwise specified cavity infill is required in one
stud row only.
*ACR = Axial Capacity Reduction
CSR 204 SIDE ONE (a) Nil 50/44 51/45 52/46 53/47
• 2 x 13mm GYPROCK (b) 50 GW Partition 11kg 58/50 59/51 60/52 61/53
– /90/90 FYRCHEK plasterboard.
(c) 75 GW Partition 11kg 60/52 60/52 61/53 62/54
30/30/30 SIDE TWO (ANY ORDER)
(d) TSB3/ASB3 Polyester 57/51 58/52 59/53 60/54
• 1 x 13mm GYPROCK
FAR2357 FYRCHEK plasterboard. (e) 60 Soundscreen™ 1.6 59/50 60/51 61/52 62/53
• 1 x 6mm CeminSeal™
WALL THICKNESS mm 193 245 295 345
Wallboard.
NOTES:
Unless otherwise specified cavity infill is required in one
stud row only.
CSR 217 and 218 require batts in each stud row.
*ACR = Axial Capacity Reduction
CSR 216
SIDE ONE
– /60/60 (a) 165 GW Partition – 11kg
30/30/30 • 1 x 13mm GYPROCK
FYRCHEK Plasterboard. + 55/50 ➀
60/60/60*
(*ACR15%) SIDE TWO 50 GW Partition 11kg
• 1 x 16mm GYPROCK
FAR 2357
FYRCHEK Plasterboard.
WALL THICKNESS mm 201
① Test
• Lining material as per system table laminated to Shaft ATF 1912
Liner Panel.
• 2 x 25mm GYPROCK Shaft Liner Panel in H-Studs at ② Test
600mm maximum centres. ATF 19322
STUD DEPTH mm 64 92
FRL SYSTEM
WALL LININGS CAVITY INFILL (Refer to Section ‘A’)
Report/Opinion Nº Rw / Rw+Ctr
STUD CAVITY FURRING CAVITY
CSR 230 (a) 75 GW Partition 11kg 50 GW Partition 11kg 60/50 60/50
STUD SIDE
CSR 241
(a) Nil 59/48 60/49
–/120/120 SIDE 1 AND 2 (b) 75 GW Partition 11kg - both sides 64/55 65/56
WFRA • 1 x 13mm GYPROCK (d) TSB5 Polyester - both sides 63/54 63/54
21241 SOUNDCHEK.
CSR 243
(a) Nil 58/47 58/47
CSR 244
(b) 75 GW Partition 11kg - both sides 62/53 62/53
–/60/60 SIDE 1 AND 2
(c) 100 GW Partition 14kg - both sides – 63/54
• 1 x 9mm CeminSeal™
SF 45743 Wallboard.
STUD DEPTH mm 64 76
FRL SYSTEM
WALL LININGS
Report/Opinion Nº CAVITY INFILL (Both Sides) Rw / Rw+Ctr
(Refer to Section ‘A’)
CSR 100
(a) 75 GW Partition 14kg 60/48 61/49
60/60/60 BOTH SIDES (b) 110 GW Partition 11kg 62/50 62/50
• 2 x 10mm GYPROCK (c) 88 RW Soundscreen R2.5 61/49 62/50
EWFA 45743 Plasterboard CD.
CSR 101
(a) 75 GW Partition 14kg 62/50 62/51
60/60/60 BOTH SIDES (b) 110 GW Partition 11kg 63/52 63/52
• 2 x 13mm GYPROCK
EWFA 45743
(c) 88 RW Soundscreen R2.5 63/51 63/52
Plasterboard CD.
CSR 102
(a) 75 GW Partition 14kg 60/48 61/49
60/60/60 BOTH SIDES (b) 110 GW Partition 11kg 62/50 62/50
• 1 x 13mm GYPROCK (c) 88 RW Soundscreen R2.5 61/49 62/50
EWFA 45743 SOUNDCHEK.
CSR 103
BOTH SIDES (a) 75 GW Partition 11kg 61/49 61/50
60/60/60 • 1 x 6mm CeminSeal™ (b) 75 GW Partition 14kg 62/50 62/51
Wallboard.
EWFA 45743
(c) 88 RW Soundscreen R2.5 63/51 63/52
• 1 x 10mm GYPROCK
AQUACHEK.
MINIMUM WALL THICKNESS mm 249 281
STUD DEPTH mm 64 76 92
FRL SYSTEM
WALL LININGS
Report/Opinion Nº CAVITY INFILL (Both Sides) Rw / Rw+Ctr
(Refer to Section ‘A’)
CSR 111
(a) 50 GW Partition 11kg 61/48 61/48 62/50
90/90/90 BOTH SIDES (b) 75 GW Partition 14kg 63/50 63/50 64/52
• 1 x 13mm GYPROCK (c) 60 RW Soundscreen R1.6 62/48 62/48 63/50
EWFA 45743 Plasterboard CD.
CSR 114
(a) 50 GW Partition 11kg 61/48 61/49 62/50
90/90/90 BOTH SIDES (b) 75 GW Partition 14kg 63/50 63/51 64/52
• 1 x 6mm CeminSeal™ (c) 60 RW Soundscreen R1.6 62/48 62/49 63/50
EWFA 45743 Wallboard.
CSR 115
(a) 50 GW Partition 11kg 62/50 62/50 63/51
90/90/90 BOTH SIDES (b) 75 GW Partition 11kg 63/51 63/51 64/52
• 1 x 13mm GYPROCK (c) 60 RW Soundscreen R1.6 63/50 63/50 64/51
EWFA 45743 AQUACHEK.
PKA-054
Discontinuous
• Lining material as per system table. Construction
• Gyprock SecurityWall™ Panel 27.
• Cavity determined by track width.
• Gyprock SecurityWall™ Panel 27.
• Lining material as per system table.
PKA-054
Discontinuous
• Lining material as per system table. Construction
PKA-054
• Lining material as per system table.
• Gyprock SecurityWall™ Panel 50. Discontinuous
Construction
• Cavity determined by track width.
• Gyprock SecurityWall™ Panel 50.
• Lining material as per system table.
NOTES:
^ SecurityWall™ Panel ribs offset to enable insulation to fit.
TRACK WIDTH mm 28 51 64
FRL SYSTEM
WALL LININGS CAVITY INFILL
Report/Opinion Nº Rw / Rw+Ctr
(Refer to Section ‘A’)
PKA-054
CSR 298
(a) Nil 48/40 49/41 50/42
BOTH SIDES
(a) Nil – –
FRL • 1 x 10mm GYPROCK
–/–/– SUPERCHEK
plasterboard.
WALL THICKNESS mm 49 71
CSR 285
WALL THICKNESS mm 55 77
NOTES:
*ACR = Axial Capacity Reduction.
PKA-201001
FRL SYSTEM
WALL LININGS CAVITY INFILL (Refer to Section ‘A’) Rw
Report/Opinion Nº
CSR 945
(a) 2 x Tontine Acoustisorb-1 77
120/120/120 BOTH SIDES (b) 2 x 110 Bradford Glasswool Building Blanket 77
• 3 x 16mm GYPROCK (c) 2 x Autex AAB32-100 77
FAR2357 FYRCHEK plasterboard
PKA-052
FRL SYSTEM
WALL LININGS CAVITY INFILL
Report/Opinion Nº Rw / Rw+Ctr
(Refer to Section ‘A’)
CSR 085
• 1 x 13mm GYPROCK CD
–/–/– (a) Nil 24/22
plasterboard.
CSR 086
• 1 x 10mm GYPROCK
–/–/– SUPERCHEK (a) Nil 25/22
plasterboard.
CSR 089
• 1 x 13mm GYPROCK
–/–/– SOUNDCHEK (a) Nil 31/28
plasterboard.
CSR 090
Fire rated from
lined side only
– /30/30
• 2 x 13mm GYPROCK
and (a) Nil 33/30
FYRCHEK plasterboard.
30/30/30
FAR2357
CSR 091
Fire rated from
lined side only
– /60/60
• 2 x 16mm GYPROCK
and (a) Nil 33/30
FYRCHEK plasterboard.
60/60/60
FAR2357
PKA-052
CSR 092
Fire rated from
lined side only
– /90/90
• 3 x 13mm GYPROCK
and (a) Nil 36/33
FYRCHEK plasterboard.
90/90/90
FAR2357
CSR 093
Fire rated from
lined side only
– /120/120
• 3 x 16mm GYPROCK
and (a) Nil 36/33
FYRCHEK plasterboard.
120/120/120
FAR2357
PKA-052
NOTE:
Acoustic performance valid for studs of 0.5mm BMT
PKA-052
CSR 967SA
CSR 968S
CSR 968SA
PKA-052
STUD SIZE mm 64 76 92
FRL SYSTEM
WALL LININGS CAVITY INFILL
Report/Opinion Nº Rw / Rw+Ctr
(Refer to Section ‘A’)
WFRA 21898 WALL SIDE (d) TSB3/ASB3 Polyester 53/46 53/46 54/47
• 1 x 13mm GYPROCK (e) 60 Soundscreen™ 1.6 55/45 55/45 56/46
plasterboard CD.
WALL THICKNESS mm 128 140 156
CSR 137 SHAFT SIDE (a) Nil 47/40 48/41 49/42
• 3 x 13mm GYPROCK (b) 50 GW Partition 11kg 55/46 56/47 56/47
–/90/90 FYRCHEK plasterboard. (c) 75 GW Partition 11kg 56/47 57/48 58/49
WALL SIDE
WFRA 21898 (d) TSB3/ASB3 Polyester 54/47 55/48 56/49
• 1 x 13mm GYPROCK
(e) 60 Soundscreen™ 1.6 56/46 57/47 58/48
SOUNDCHEK
plasterboard. WALL THICKNESS mm 128 140 156
CSR 138 (a) Nil 46/39 47/40 49/42
SHAFT SIDE
(b) 50 GW Partition 11kg 54/45 55/46 56/47
• 3 x 13mm GYPROCK
–/90/90 FYRCHEK plasterboard. (c) 75 GW Partition 11kg 55/46 56/47 58/49
WFRA 21898 WALL SIDE (d) TSB3/ASB3 Polyester 53/46 54/47 56/49
• 1 x 13mm GYPROCK (e) 60 Soundscreen™ 1.6 55/45 56/46 58/48
AQUACHEK.
WALL THICKNESS mm 128 140 156
CSR 139 (a) Nil 46/39 47/40 47/40
SHAFT SIDE
(b) 50 GW Partition 11kg 54/45 55/46 54/45
• 3 x 13mm GYPROCK
–/90/90 FYRCHEK plasterboard. (c) 75 GW Partition 11kg 55/46 56/47 56/47
WFRA 21898 WALL SIDE (d) TSB3/ASB3 Polyester 53/46 54/47 54/47
• 1 x 6mm CeminSeal™ (e) 60 Soundscreen™ 1.6 55/45 56/46 56/46
Wallboard.
WALL THICKNESS mm 121 133 149
PKA 052
STUD SIZE mm 64 76 92
FRL SYSTEM
WALL LININGS CAVITY INFILL
Report/Opinion Nº Rw / Rw+Ctr
(Refer to Section ‘A’)
WFRA 21898
WALL SIDE (d) TSB3/ASB3 Polyester 53/46 54/47 56/49
• 1 x 13mm GYPROCK (e) 60 Soundscreen™ 1.6 55/45 56/46 58/48
AQUACHEK.
WALL THICKNESS mm 137 149 165
CSR 143 (a) Nil 46/39 47/40 49/42
SHAFT SIDE
(b) 50 GW Partition 11kg 54/45 55/46 56/47
• 3 x 16mm GYPROCK
–/120/120 FYRCHEK plasterboard. (c) 75 GW Partition 11kg 55/46 56/47 58/49
WFRA 21898
WALL SIDE (d) TSB3/ASB3 Polyester 53/46 54/47 56/49
• 1 x 6mm CeminSeal™ (e) 60 Soundscreen™ 1.6 55/45 56/46 58/48
Wallboard.
WALL THICKNESS mm 130 142 158
RP 02267S
WALL THICKNESS mm 64
CSR 249
WALL THICKNESS mm 64
PKA-055
CSR 941
CSR 942
PKA-055
EXTERNAL SIDE
–/–/– – (a) Nil 35
• Nil
CSR 934
PKA-055
CSR 932
EXTERNAL SIDE (a) Nil 43/36 44/38 1.8 1.5
FAR2357 INTERNAL SIDE (c) 75 Soundscreen™ 2.0 51/37 52/39 3.2 2.9
• 1 x 16mm GYPROCK
FYRCHEK plasterboard
TYPICAL WALL THICKNESS mm 168 226
PKA-055
PKA-055
PKA-055
PKA-055
• Cemintel RendaLine™ sheet on timber or steel battens.
• 25mm Bradford Fibertex™ Rockwool.
• Wire mesh.
• Sarking
• Steel studs at 600mm maximum centres.
• Lining material to internal side as per system table.
CSR 171
EXTERNAL SIDE (a) Nil 43/35 1.8 1.6
• As per system
60/60/60 specification (b) 75 Gold Batts™ 1.5 47/38 2.6 2.4
PKA-055
• Cemintel RendaLine™ sheet fixed to tophats.
• 25mm Bradford Fibertex™ 450 Rockwool.
• Sarking.
• 1 x 6mm CeminSeal™ Wallboard.
• Steel studs at 600mm maximum centres.
• Lining material to internal side as per system table.
NOTES:
Acoustic performance valid for studs of 0.80 BMT.
*ACR = Axial Capacity Reduction.
• 1 x 10mm GYPROCK
Plasterboard CD. TYPICAL WALL THICKNESS mm 129
• Sarking.
• Lining material to external side as per system table.
• Steel studs at 600mm maximum centres.
• Lining material to internal side of steel studs as per system
table.
NOTES:
Acoustic performance valid for studs 0.80 BMT.
*ACR = Axial Capacity Reduction.
PKA-055
• 150mm concrete wall min 2400kg/m3.
• Rondo furring channel No.129
• 66mm cavity.
• Cavity infill as per system table.
• Lining as per system table.
Notes:
Foil side to plasterboard.
2010675.1/
2401A/R1/JH
HEBEL 1401
(a) Nil 46/40 46/40 0.9 0.9
240/180/180 INTERNAL SIDE
(from outside only) (b) 90 Gold Batts™ 2.0 53/44 53/45 2.8 2.6
• 1 x 10mm GYPROCK
FSV0356 Plasterboard CD.
PKA-055
• Fire rated masonry veneer wall.
• Steel studs at 600mm maximum centres with 40mm
minimum gap to masonry.
• Lining material as per system table.
Notes:
Masonry to be minimum 90mm thick and 170kg/m2
CSR 185
EXTERNAL WALL SIDE (a) Nil 55/48 0.6 0.6
FRL
• Masonry veneer wall with
60/60/60 (b) 75 Gold Batts™ 1.5 62/55 2.2 2.0
FAR 2357 FRL 60/60/60.
and refer to INTERNAL WALL SIDE (c) 88 Soundscreen™ 2.5 62/54 3.2 2.9
Masonry
• 1 x 16mm GYPROCK
Manufacturer
FYRCHEK plasterboard.
TYPICAL WALL THICKNESS mm 258
CSR 186
EXTERNAL WALL SIDE (a) Nil 55/48 0.6 0.6
FRL
• Masonry veneer wall with
90/90/90 (b) 75 Gold Batts™ 1.5 62/55 2.2 2.0
FAR 2357 FRL 90/90/90.
and refer to INTERNAL WALL SIDE (c) 88 Soundscreen™ 2.5 62/54 3.3 3.0
Masonry
• 2 x 13mm GYPROCK
Manufacturer
FYRCHEK plasterboard.
TYPICAL WALL THICKNESS mm 268
CSR 187
EXTERNAL WALL SIDE (a) Nil 58/51 0.7 0.7
FRL
• Masonry veneer wall with
120/120/120 (b) 75 Gold Batts™ 1.5 65/58 2.2 2.1
FAR 2357 FRL 90/90/90.
and refer to INTERNAL WALL SIDE (c) 88 Soundscreen™ 2.5 65/57 3.3 3.0
Masonry
• 2 x 16mm GYPROCK
Manufacturer
FYRCHEK plasterboard.
TYPICAL WALL THICKNESS mm 274
Rondo Track
fixed to column RHS/SHS
CSR 195 at ends and Steel Column
800mm max.
centres
90/–/– • 2 x 16mm GYPROCK 18mm
FYRCHEK Each layer of
CSIRO GYPROCK FYRCHEK
FCO 1494
plasterboard. plasterboard fixed at
200mm maximum
centres to all tracks
CSR 196
FIXING TO STEEL UNIVERSAL BEAM
120/–/– • 3 x 13mm GYPROCK
CSR Gyprock ® Universal
FYRCHEK Encasement Clips at
CSIRO
FCO 1494
plasterboard. 800mm maximum centres
along column flanges and
150mm maximum from
each end of column
An economical, non-fire rated The original, GECA certified Fire and acoustic rated with
board for general requirements EC08™ board with fire and impact resistance for high traffic
where fire and acoustics acoustic rating for party walls areas such as in education
are not required. and meeting rooms. and health facilities.
PKA-056
NOTES:
Acoustic performance valid for 0.5 BMT.
PKA-056
NOTES:
Acoustic performance valid for 0.5 BMT.
CSR EC615 SIDE ONE (a) Nil 40/33 41/34 42/35 43/36 46/40
• 1 x 13mm GYPROCK
(b) 50 GW Partition 11kg 45/36 46/37 47/38 48/39 50/42
- /60/60 ECO8™ Fire.
• 1 x 6mm CeminSeal™ (c) 75 GW Partition 11kg – 48/39 48/39 49/40 51/43
FAR 2357
Wallboard. (d) TSB3/ASB3 Polyester 44/37 45/38 46/39 47/40 49/43
&
BWA 23035 SIDE TWO (e) 60 Soundscreen™ 1.6 – 47/37 48/38 49/39 51/42
• 1 x 13mm GYPROCK
ECO8™ Fire. WALL THICKNESS mm 83 96 108 124 182
CSR EC210 (a) Nil 40/33 42/35 43/36 44/37 47/41
SIDE ONE
- /90/90 (b) 50 GW Partition 11kg 45/36 47/38 48/39 49/40 51/43
• 1 x 13mm GYPROCK
ECO8™ Fire. (c) 75 GW Partition 14kg – 50/41 50/41 51/42 53/45
FAR 2357
SIDE TWO (d) TSB3/ASB3 Polyester 44/37 46/39 47/40 48/41 50/44
&
BWA 23035 • 2 x 13mm GYPROCK (e) 60 Soundscreen™ 1.6 – 48/38 49/39 50/40 52/43
ECO8™ Fire.
WALL THICKNESS mm 90 103 115 131 189
CSR EC315 (a) Nil 45/38 47/41 48/42 48/42 50/44
PKA-056
PKA-056
• Lining material as per system table.
Discontinuous
• 2 Rows of Steel Studs at 600mm maximum centres with Construction
20mm minimum gap.
• Lining material as per system table.
NOTES:
Unless otherwise specified, cavity infill is required in one
stud row only.
PKA-054
NOTES:
^ SecurityWall™ Panel ribs offset to enable insulation to fit.
TRACK WIDTH mm 28 51 64
FRL SYSTEM
WALL LININGS CAVITY INFILL
Report/Opinion Nº Rw / Rw+Ctr
(Refer to Section ‘A’)
PKA-056
- /90/90
LINING
FC0 1786 • 3 x 13mm GYPROCK (a) Nil 35
& ECO8™ Fire.
BWA 23035
300mm
CSR Bradford Acoustic max.
Insulation if required
200mm
min.
Refer to perimeter details
FIG B3: FASTENER FIXING – SINGLE LAYER HORIZONTAL SHEETING – NON-TILED AREAS
For additional information, refer to GYP544, Gyprock™ Steel Frame Wall Systems Installation Guide.
NON-FIRE RATED
Fixing Specifications
Screws Refer to Section ‘A’
For Level 4 finish, form butt Location Fixing & Spacing
joints between framing
Field Screws at 400mm
max. centres
Sheet
Width
400mm 300mm 900mm 4 Screws
max. max. 1200mm 4 Screws
1350mm 5 Screws
One layer of Gyprock® Recessed Screw at each stud
plasterboard to each side Edges
of wall
Butt joints Screws at 200mm
max. centres
Corners & Screws at 300mm
Openings max. centres
SUITABLE FOR:
200mm
max.
Refer to perimeter
details
230mm
CSR Bradford Acoustic max.
Insulation if required
200mm
min.
Refer to perimeter details
FIG B7: INSTALLATION DETAIL FOR INTERNAL WALL SYSTEMS – CEMINSEAL™ WALLBOARD – NON-TILED AREAS
HORIZONTAL SHEETING – FASTENER FIXING
For additional information, refer to FC101, Cemintel™ Wet Area Systems.
NON-FIRE RATED
Fixing Specifications
Screws Refer to Section ‘A’
Location Fixing & Spacing
Field Screws at 300mm
max. centres
SUITABLE FOR:
200mm
max.
FIRE RATED
200mm max. Fixing Specifications
Noggings behind but joints Screws Refer to Section ‘A
staggered 600mm min.
Location Fixing & Spacing
Field Screws at 300mm
max. centres
CSR Bradford Acoustic Recessed Screws at
Insulation if required 600mm 300mm
min. max. Edges 300mm max. centres
Butt Screws at
Joints 200mm max. centres
Corners & Screws at
Openings 300mm max. centres
SUITABLE FOR:
300mm 300mm
One layer of GYPROCK max. max.
FYRCHEK plasterboard
to each side of wall in
accordance with system
specifications
FIG B9: INSTALLATION DETAIL FOR INTERNAL WALL SYSTEMS – SINGLE LAYER – HORIZONTAL SHEETING
For additional information, refer to GYP544, Gyprock™ Steel Frame Wall Systems Installation Guide.
FIRE RATED
Fixing Specifications
Screws Refer to Section ‘A
Location Fixing & Spacing
Field Screws at 300mm
300mm max. centres
max. Recessed Screw at
Edges each stud
Refer to perimeter
details
Noggings may not be permitted
in staggered stud systems
FIRE RATED
Fixing Specifications
Screws Refer to Section ‘A
1st Layer Fixing & Spacing
Recessed Screws at 600mm
Edges max. centres
& Field
300mm
max. 2nd Layer Fixing & Spacing
Field Screws at 300mm
200mm max. max. centres
CSR Bradford Acoustic
Insulation if required laminating screws Recessed Screws at
600mm Edges 300mm max. centres
max.
Butt Screws at
Two layers of GYPROCK Joints 200mm max. centres
FYRCHEK plasterboard Corners & Screws at
to each side of wall in Openings 300mm max. centres
accordance with system
specifications
SUITABLE FOR:
200mm
max.
300mm 300mm
Noggings behind but joints max. max.
staggered 600mm min.
Refer to perimeter
details
Noggings may not be permitted
in staggered stud systems
FIG B11: INSTALLATION DETAIL FOR INTERNAL WALL SYSTEMS – TWO LAYER – VERTICAL+HORIZONTAL SHEETING
For additional information, refer to GYP544, Gyprock™ Steel Frame Wall Systems Installation Guide.
FIRE RATED
Fixing Specifications
Screws Refer to Section ‘A
CSR Bradford Acoustic 200mm 1st Layer Fixing & Spacing
Insulation if required max.
Recessed Screws at 600mm
Edges max. centres
& Field
300mm
max. 2nd Layer Fixing & Spacing
Field Screws at 300mm
max. centres
300mm
max. Recessed Screw at
Edges each stud
Butt Screws at
Joints 200mm max. centres
600mm Corners & Screws at
max. Openings 300mm max. centres
300mm min.
300mm
max. Recessed Screw at
Studs at 600mm maximum Edges each stud
centres Butt Screws at
Joints 200mm max. centres
Corners & Screws at
600mm Openings 300mm max. centres
max.
FIRE RATED
400mm Fixing Specifications for
Horizontal Sheeting
Screws Refer to Section ‘A
1st Layer Fixing & Spacing
400mm Recessed Screws at 600mm
Edges, max. centres on
Field, studs
Refer to perimeter Butt Joints,
details Corners &
Openings
400mm
2nd Layer Fixing & Spacing
Recessed Screws at 600mm
Edges max. centres on
studs
Field Screws at 300mm
max. centres on
studs
Corners & Screws at 300mm
Openings max. centres
Butt Joints Screws at 200mm
max. centres on
studs
3rd Layer Fixing & Spacing
Recessed Laminating screws
Edges, at 400x400mm max.
Field, Butt grid
Joints
Corners &
Openings
SUITABLE FOR:
200mm
400mm
200mm
Refer to
system table
for girt spacing
200mm
400mm
200mm
FIRE RATED
Fixing Specifications for SUITABLE FOR:
Vertical Sheeting (shown)
Screws Refer to Section ‘A
1st Layer Fixing & Spacing
Field & Screws at 200mm
Butt Joints max. centres to all
girts
2nd & 3rd Fixing & Spacing
Layers
Recessed Laminating Screws at
Edges & 200mm max. centres
Butt Joints
Field Laminating Screws at
400 x 400mm max.
grid
Alternative stud
type for in-line
stud framing
300mm
max. IMPORTANT
300mm Walls enclosing lift shafts MUST
max. have both layers of GYPROCK
1st layer of FYRCHEK separately fastened to the
GYPROCK FYRCHECK top and bottom J tracks with screws
plasterboard at 300mm maximum spacings.
600mm
Refer to perimeter details max.
75mm 400mm
IBS Backing Steel Angle max.
Rod at head internal
of 1st layer framing
Apply adhesive*
and screw fix
2nd layer to
75mm 400mm vertical steel
600mm max. max. angles with Apply adhesive*
25/45mm and screw fix
Gyprock screws. body of 3rd
Fix body with layer with
laminating laminating
screws at screws only at
600mm max. 600mm max.
horizontal x horizontal x
400mm max. 400mm max.
vertical centres vertical centres
SecurityWall
Track 27
FIRE RATED
Gyprock 300mm Fixing Specifications for
max.
SecurityWall Vertical Sheeting (shown)
Panel 27 Screws Refer to Section ‘A
1st Layer Fixing & Spacing
Recessed Screws at 600mm
Edges, & max. vertical centres
Field x 300mm max.
horizontal centres
Butt Screws at
Joints 200mm max. centres
Cavity
Insulation
Blanket
300mm
max.
Base Track
Security Wall
FIRE RATED
Track 27
Fixing Specifications for
Vertical Sheeting (shown)
Steel Stud Profiles as Screws Refer to Section ‘A
per system table at Adhesive
600mm centres or 300mm
Gyprock SecurityWall max. 1st Layer Fixing & Spacing
Panel 50
Recessed Screws at 600mm
Edges, & max. vertical centres
Gyprock Field to all stud profiles
SecurityWall OR
Panel 27 200mm
max. Screws at 600mm
max. vertical centres
1x 10mm and 300mm max.
GYPROCK horizontal centres to
plasterboard CD steel sheeting
2nd Layer Fixing & Spacing
200mm
1x 16mm min. Recessed Screws at corners
GYPROCK Edges and 600mm max. cts
FYRCHEK 600mm
max. 300mm Field Rows of Adhesive
plasterboard max. Daubs at 600mm
max. horizontal cts x
300mm max. vertical
Cavity cts and 200mm min.
Insulation from fastener points
Blanket Screw along
centreline at 1200mm
max. cts
600mm Butt Screws at
max. Joints 200mm max. centres
300mm
max. Corners & Screws at
Base Track Openings 300mm max. centres
FIRE RATED
Security Wall Fixing Specifications for
Track 50 Vertical Sheeting (shown)
Screws Refer to Section ‘A
1st Layer Fixing & Spacing
Gyprock Top, Bottom Screws at 600mm
SecurityWall & Field max. vertical centres
Panel 50 x 300mm max.
horizontal centres to
all steel ribs
Butt Screws at
Joints 216mm max. centres
216mm Corners & Screws at
typical. Openings 300mm max. centres
1x 13mm
GYPROCK
FYRCHEK 600mm
plasterboard max.
Cavity
Insulation
Blanket 300mm
max.
Base Track
Head Angle
FIRE RATED
Security Wall
Track 50 Fixing Specifications for
Vertical Sheeting (shown)
Steel Stud Profiles as Screws Refer to Section ‘A
per system table at Adhesive
600mm centres or
Gyprock SecurityWall 1st Layer Fixing & Spacing
Panel 50 Recessed Screws at 600mm
200mm Edges max. vertical centres
Gyprock max. & Field to all stud profiles
SecurityWall OR
Panel 50 Screws at 600mm
max. vertical centres
216mm x 300mm max.
typical horizontal centres to
1x 10mm all steel ribs
GYPROCK
plasterboard CD 2nd Layer Fixing & Spacing
200mm min. Recessed Screws at 450mm
1x 16mm Edges max. cts
GYPROCK
FYRCHEK 600mm Field Rows of Adhesive
max. 300mm max. Daubs at 600mm
plasterboard
max. horizontal cts x
300mm max. vertical
cts and 200mm min.
Cavity from fastener points
Insulation Screw along
Batts 300mm
600mm max. centreline at 1300mm
max. max.cts
Butt Screws at
Joints 200mm max. centres
Corners & Screws at
433mm Openings 300mm max. centres
433mm typical
Base Angles typical
Screw along sheet
centreline at
Caulk all perimeter gaps 1200mm max. cts
with Gyprock Fire Mastic
Stud centres
400mm
max. ctrs
450mm
max. ctrs
400mm
max. ctrs
450mm
max. ctrs Butt Joints
in 3rd/4th
layers offset
600mm min.
Stagger joints
300mm min.
450mm
max. ctrs
FIRE RATED
SUITABLE FOR:
Fixing Specifications
Screws Refer to Section ‘A
1st Layer Fixing & Spacing
At all studs Screws at 400mm
max. centres
2nd, 3rd & Fixing & Spacing
4th Layers
Recessed Laminating screws at
Edges, 450mm max.
Field & horizontal centres
Butt Joints and 400mm max.
vertical centres
Contents
Timber Stud Height Tables C2
Introduction C3
Design Considerations C3 – C4
Installation C5
Components C5
System Specifications – Internal Walls
Single Stud C6 – C9
Double Stud C10 – C12
Party Wall C13 – C14
Staggered Stud C15 – C17
Resilient Mount C18 – C19
Studs Lined One Side C20 – C21
System Specifications – External Walls
Cladding on Battens C22 – C23
Texture Base Sheet for Houses C24
Hebel Powerpanel™ C25
Masonry C26 – C27
Rendaline™ C28 – C29
Commercial ExpressWall™ C30
Column & Beam C31
System Installation Details C32 – C37
450mm 70 3.2 3.5 3.5 3.8 3.7 4.0 3.6 3.9 3.9 4.3 4.1 4.5
cts.
90 4.1 4.5 4.5 4.9 4.7 5.1 4.6 5.1 5.0 5.5 5.3 5.8
120 5.5 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0
600mm cts.
70 2.7 2.9 2.9 3.2 3.1 3.3 3.0 3.3 3.3 3.6 3.5 3.8
90 3.4 3.7 3.8 4.1 4.0 4.3 3.9 4.2 4.2 4.6 4.5 4.9
300mm 300mm
cts. cts.
120 4.6 5.0 5.0 5.5 5.3 5.8 5.2 5.7 5.6 6.0 6.0 6.0
450mm 70 3.4 3.7 3.8 4.1 3.9 4.3 3.9 4.2 4.2 4.6 4.5 4.9
cts.
90 4.4 4.8 4.9 5.3 5.1 5.5 5.0 5.5 5.4 5.9 5.8 6.0
120 5.9 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0
600mm cts.
70 2.9 3.1 3.2 3.3 3.6 3.9 3.0 3.6 3.5 3.9 3.8 4.1
90 3.7 4.0 4.1 4.4 4.3 4.7 4.2 4.6 4.6 5.0 4.9 5.3
300mm 300mm
cts. cts.
120 5.0 5.4 5.5 5.9 5.7 6.0 5.6 6.0 6.0 6.0 6.0 6.0
Timber frame wall systems are typically used in multi- • To be in accordance with AS1720.1 or AS1684.
residential applications. • Assuming no contribution to axial strength is required of
the wall linings.
Design To meet the stated Fire Resistance Level (FRL), the axial load
capacity of some wall systems is reduced. This is a result
of loss of stud section from charring during a fire test. The
For detailed information on wall junctions, intersections, • At junctions with other building elements.
frame attachments and penetrations, refer to Section Z of • At junctions with different lining materials.
this guide and Woods & Forests publication, Timber Framed
• At change of structural support system.
Construction for Mult-Residential Buildings.
• At each storey or rise of studs.
Walls curved in plan may be built with timber stud frames.
Table for stud centres and plasterboard thickness for various
External Walls
curvatures can be found in CSR Gyprock™ Residential
Installation, Guide NºGYP547. Gyprock ™ timber frame external wall systems rely on a
range of cladding systems to provide weather resistance.
Gyprock™ Party Wall systems have additional installation
There is a range of effectiveness of these systems, and
requirements. Refer to brochure NºGYP513 Gyprock™ Party
CSR Gyprock™ recommends the cladding be installed with
Wall Systems.
a drained cavity. Cavity systems allow drainage and drying
of any water that penetrates, and are known to have good
Wallboard & Plasterboard Fixing long-term performance.
Interior walls may be built to achieve a particular ‘Level of
Sarking is also recommended to provide additional weather
Finish’ as defined in AS/NZS2589.1. The Level of Finish
protection to framing and lining.
specified can have requirements for frame alignment,
jointing and back blocking methods, and sheet orientation. External walls require specific design for condensation
CeminSeal™ Wallboard and Gyprock™ plasterboard may be control and energy efficiency, depending on the climate and
installed vertically or horizontally, although for some Levels of internal environment. Contact CSR Bradford for information
Finish horizontal sheeting must be used. on thermal insulation systems and products.
• It is recommended that a water resistant taping compound, For details on Cemintel RendaLine™ Façades, refer to CSR
such as Gyprock™ Wet Area Base Coat be used at vertical guides FC945, Commercial RendaLine™ (using steel top
wall junctions and horizontal and vertical joints within wet hat framing), and FC133, Residential RendaLine™ (using
areas such as showers. timber battens
PKA-051
• Lining material as per system table.
• Timber studs at 600mm maximum centres.
• Cavity insulation as per system table.
• Lining material as per system table.
NOTES:
Acoustic performance valid for 35mm wide studs at
600mm centres.
PKA-051
• Lining material as per system table.
• Timber studs at 600mm maximum centres.
• Cavity insulation as per system table.
• Lining material as per system table.
NOTES:
Acoustic performance valid for 35mm wide studs at
600mm centres.
Both SideS (b) 75 Gold Batts™ 1.5 39/30 41/32 42/33 43/34
–/–/– • 1 x 10mm GYPROCK (c) 75 Soundscreen™ 2.0 40/30 42/32 43/33 44/34
SUPERCHEK
plasterboard. (d) TSB3/ASB3 Polyester 37/30 39/32 39/32 40/33
Both SideS (b) 75 Gold Batts™ 1.5 41/32 42/33 44/36 45/37
–/–/– • 1 x 13mm GYPROCK (c) 75 Soundscreen™ 2.0 42/32 43/33 45/36 46/37
SOUNDCHEK
plasterboard. (d) TSB3/ASB3 Polyester 39/32 40/33 41/35 42/36
Both SideS (b) 75 Gold Batts™ 1.5 46/37 48/40 49/41 50/42
–/–/– • 2 x 10mm GYPROCK (c) 75 Soundscreen™ 2.0 47/37 49/40 50/41 51/42
SUPERCHEK
plasterboard. (d) TSB3/ASB3 Polyester 44/37 46/40 46/40 47/41
PKA-051
• Lining material as per system table.
• Timber studs at 600mm maximum centres.
• Cavity insulation as per system table.
• Lining material as per system table.
NOTES:
Acoustic performance valid for 35mm wide studs at
600mm centres.
CsR 352 Side one (Any order) (a) Nil 38/31 39/32 42/35 42/36
• 1 x 10mm GYPROCK
– /60/60 Plasterboard CD. (b) 75 Gold Batts™ 1.5 42/33 43/34 46/37 46/38
and • 1 x 13mm GYPROCK
30/30/30 (c) 75 Soundscreen™ 2.0 43/33 44/34 47/37 47/38
FYRCHEK plasterboard.
FAR 2303 Side two (d) TSB3/ASB3 Polyester 40/33 41/34 43/36 43/37
• 1 x 13mm GYPROCK
FYRCHEK plasterboard. WALL THICKNESS mm 106 126 156 176
CsR 350 (a) Nil 35/28 37/30 38/31 39/33
– /60/60 (b) 75 Gold Batts™ 1.5 39/30 41/32 42/33 43/35
and Both SideS
30/30/30 • 1 x 13mm GYPROCK (c) 75 Soundscreen™ 2.0 40/30 42/32 43/33 44/35
FYRCHEK plasterboard.
FAR 2303 (d) TSB3/ASB3 Polyester 37/30 39/32 39/32 40/34
NOTES:
*ACR = Axial Capacity Reduction. (Refer to Table C3)
Acoustic performance valid for 35mm wide studs at
600mm centres.
CsR 667 Side one (Any order) (a) Nil 43/37 44/38 45/39 46/40
• 1 x 6mm CeminSeal™
– /90/90 Wallboard. (b) 75 Gold Batts™ 1.5 47/39 48/40 49/41 50/42
and • 1 x 16mm GYPROCK
60/60/60 (c) 75 Soundscreen™ 2.0 48/39 49/40 50/41 51/42
FYRCHEK plasterboard.
FAR 2303 Side two (d) TSB3/ASB3 Polyester 45/39 46/40 46/40 47/41
• 2 x 16mm GYPROCK
FYRCHEK plasterboard. WALL THICKNESS mm 124 144 174 194
CsR 375 (a) Nil 42/36 44/38 45/39 46/40
– /120/120 (b) 75 Gold Batts™ 1.5 46/38 48/40 49/41 50/42
and Both SideS
90/90/90 • 2 x 13mm GYPROCK (c) 75 Soundscreen™ 2.0 47/38 49/40 50/41 51/42
FYRCHEK plasterboard.
FAR 2303 (d) TSB3/ASB3 Polyester 44/38 46/40 46/40 47/41
NOTES:
Unless otherwise specified, cavity infill is required in one stud row
only.
Both SideS (b) 75 Gold Batts™ 1.5 55/47 57/49 58/50 59/51
–/–/– • 1 x 13mm GYPROCK (c) 75 Soundscreen™ 2.0 56/47 58/49 59/50 60/51
SOUNDCHEK
plasterboard. (d) TSB3/ASB3 Polyester 54/48 56/50 57/51 58/52
NOTES:
*ACR = Axial Capacity Reduction. (Refer to Table C3)
Unless otherwise specified, cavity infill is required in one stud row
only.
CSR 556 requires one row of batts in each stud row.
sTud dEPTh mm 70 90 120 140
FRL sYsTEm
WALL LiNiNgs CAViTY iNFiLL
Report/Opinion Nº Rw / Rw+Ctr
(Refer to Section ‘A’)
CsR 579 Side one (a) Nil 48/42 50/44 51/45 52/46
• 1 x 16mm GYPROCK
– /60/60 FYRCHEK plasterboard. (b) 75 Gold Batts™ 1.5 57/49 59/51 60/52 61/53
and Side Two (Any order)
60/60/60 (c) 75 Soundscreen™ 2.0 58/49 60/51 61/52 62/53
• 1 x 16mm GYPROCK
FAR 2303 FYRCHEK plasterboard. (d) TSB3/ASB3 Polyester 56/50 58/52 59/53 60/54
• 1 x 6mm CeminSeal™
Wallboard WALL THICKNESS mm 198 238 298 338
CsR 680 (a) Nil 51/45 52/46 53/47 54/48
– /60/60 Both SideS
(b) 75 Gold Batts™ 1.5 60/52 61/53 62/54 63/55
and • 1 x 6mm CeminSeal™
60/60/60 Wallboard (against studs). (c) 75 Soundscreen™ 2.0 61/52 62/53 63/54 64/55
• 1 x 13mm GYPROCK
FAR 2303 (d) TSB3/ASB3 Polyester 59/53 60/54 61/55 62/56
FYRCHEK plasterboard.
WALL THICKNESS mm 198 238 298 338
CsR 681 (a) Nil 51/45 52/46 54/48 55/49
Both SideS
– /60/60 (b) 75 Gold Batts™ 1.5 60/52 61/53 63/55 64/56
• 1 x 16mm GYPROCK
and FYRCHEK plasterboard
60/60/60 (c) 75 Soundscreen™ 2.0 61/52 62/53 64/55 65/56
(against studs).
FAR 2303 • 1 x 6mm CeminSeal™ (d) TSB3/ASB3 Polyester 59/53 60/54 62/56 63/57
Wallboard.
WALL THICKNESS mm 204 244 304 344
CsR 682 (a) Nil 51/45 52/46 54/48 55/49
– /90/90 Both SideS
(b) 75 Gold Batts™ 1.5 60/52 61/53 63/55 64/56
60/60/60 • 1 x 6mm CeminSeal™
90/90/90* Wallboard (against studs). (c) 75 Soundscreen™ 2.0 61/52 62/53 64/55 65/56
* ACR Group 3 • 1 x 16mm GYPROCK
(d) TSB3/ASB3 Polyester 59/53 60/54 62/56 63/57
FAR 2303 FYRCHEK plasterboard.
WALL THICKNESS mm 204 244 304 344
NOTES:
Unless otherwise specified, cavity infill is required in one
stud row only.
sTud dEPTh mm 70 90
FRL sYsTEm
WALL LiNiNgs CAViTY iNFiLL
Report/Opinion Nº Rw / Rw+Ctr
Both sides (Refer to section ‘A’)
CsR 360
(a) 75 Gold Batts™ 2.0 60/47 61/49
• 1 x 10mm GYPROCK
60/60/60 SUPERCHEK (b) 90 Gold Batts™ 2.0 62/50 63/51
plasterboard.
EWFA 45743
(c) 88 Soundscreen™ 2.5 63/51 64/52
• 1 x 10mm GYPROCK
plasterboard CD.
WALL THICKNESS mm 245 285
sTud dEPTh mm 70 90
FRL sYsTEm
WALL LiNiNgs CAViTY iNFiLL
Report/Opinion Nº Rw / Rw+Ctr
Both sides (Refer to Section ‘A’)
CsR 368
(a) 75 Gold Batts™ 1.5 63/51 64/52
PKA-051
• Lining material as per system table.
• Staggered timber studs at 600mm maximum centres each NOT
side. Deemed
Discontinuous
• Minimum 20mm clearance between stud and opposing Construction
lining.
• No noggings or any connection between studs.
• Cavity insulation as per system table. (Insulation may need
to be cut and placed between studs).
• Lining material as per system table.
PKA-051
• Lining material as per system table.
• Staggered timber studs at 600mm maximum centres each NOT
side. Deemed
Discontinuous
• Minimum 20mm clearance between stud and opposing Construction
lining.
• No noggings or any connection between studs.
• Cavity insulation as per system table. (Insulation may need
to be cut and placed between studs).
• Lining material as per system table.
PKA-051
Both SideS (b) 75 Gold Batts™ 1.5 50/41 52/44 53/45 53/45
–/–/– • 1 x 13mm GYPROCK (c) 75 Soundscreen™ 2.0 51/41 53/44 54/45 54/45
SOUNDCHEK
plasterboard. (d) TSB3/ASB3 Polyester 48/41 50/44 50/44 51/45
CsR 403 Side One (Mount Side) (a) Nil 45/38 47/40 48/42 48/42
• 2 x 10mm GYPROCK
SUPERCHEK (b) 75 Gold Batts™ 1.5 53/44 55/46 56/48 55/47
plasterboard.
–/–/– (c) 75 Soundscreen™ 2.0 54/44 56/46 57/48 56/47
Side Two
• 1 x 10mm GYPROCK (d) TSB3/ASB3 Polyester 51/44 53/46 53/47 53/47
SUPERCHEK
plasterboard. MIN. WALL THICKNESS mm 128 148 178 198
CsR 410 Side one (Mount Side) (a) Nil 44/37 45/38 47/40 47/40
• 2 x 10mm GYPROCK
(b) 75 Gold Batts™ 1.5 52/43 53/44 55/46 54/45
SUPERCHEK
–/–/– plasterboard. (c) 75 Soundscreen™ 2.0 53/43 54/44 56/46 55/45
Side two
(d) TSB3/ASB3 Polyester 50/43 51/44 52/45 52/45
• 1 x 10mm GYPROCK
AQUACHEK plasterboard. MIN. WALL THICKNESS mm 128 148 178 198
CsR 411 Side one (Mount Side) (a) Nil 44/37 46/39 47/40 48/42
• 2 x 10mm GYPROCK
(b) 75 Gold Batts™ 1.5 52/43 54/45 55/46 55/47
SUPERCHEK
–/–/– plasterboard. (c) 75 Soundscreen™ 2.0 53/43 55/45 56/46 56/47
Side two
(d) TSB3/ASB3 Polyester 50/43 52/45 52/45 53/47
• 1 x 6mm CeminSeal™
Wallboard. MIN. WALL THICKNESS mm 124 144 174 194
PKA-051
PKA-051
WALL THICKNESS mm 80
CsR 387
WALL THICKNESS mm 83
CsR 388
WALL THICKNESS mm 83
CsR 389
WALL THICKNESS mm 86
PKA-051
CsR 900
externAl wAll Side (a) Nil 36 1.0 1.0
60/60/60* • 1 x 16mm GYPROCK
from outside only (b) 75 Gold Batts™ 1.5 39 2.4 2.2
FYRCHEK MR plasterboard.
* ACR Group 2
internAl wAll Side
(c) 75 Soundscreen™ 2.0 40 3.0 2.7
FAR 2303 • 1 x 10mm GYPROCK
Plasterboard CD. TYPICAL WALL THICKNESS mm 157
CsR 901
externAl wAll Side (a) Nil 38 1.1 1.0
• 1 x 16mm GYPROCK
60/60/60 (b) 75 Gold Batts™ 1.5 41 2.5 2.3
FYRCHEK MR plasterboard.
FAR 2303 internAl wAll Side
(c) 75 Soundscreen™ 2.0 42 3.0 2.8
• 1 x 16mm GYPROCK
FYRCHEK plasterboard. TYPICAL WALL THICKNESS mm 163
CsR 907
externAl wAll Side (a) Nil 38 1.1 1.0
NOTES:
*ACR = Axial Capacity Reduction. (Refer to Table C3).
Acoustic performance valid for 35mm wide studs at
600mm centres.
FRL sYsTEm sTud dEPTh mm 90 ThERmAL
WALL LiNiNgs
Report/Opinion Nº CAViTY iNFiLL (Refer to Section ‘A’) Rw Rt(win) Rt(sum)
externAl wAll Side
(a) Nil 40 1.1 1.0
CsR 911 • 1 x 6mm
60/60/60 CSR CeminSeal™
and Wallboard (against studs) (b) 75 Gold Batts™ 1.5
43 2.5 2.3
(90/90/90* • 1 x 16mm GYPROCK
from outside only) FYRCHEK MR
* ACR Group 3 (c) 75 Soundscreen™ 2.0
plasterboard. 44 3.0 2.8
FAR 2303 internAl wAll Side
• 1 x 16mm GYPROCK
TYPICAL WALL THICKNESS mm 169
FYRCHEK plasterboard.
externAl wAll Side
(a) Nil 44 1.2 1.1
CsR 912 • 1 x 6mm
CSR CeminSeal™
90/90/90* Wallboard (against studs) (b) 75 Gold Batts™ 1.5
48 2.5 2.3
• 1 x 16mm GYPROCK
* ACR Group 3
FYRCHEK MR
(c) 75 Soundscreen™ 2.0
FAR 2303 plasterboard. 49 3.0 2.8
internAl wAll Side
• 2 x 13mm GYPROCK
TYPICAL WALL THICKNESS mm 179
FYRCHEK plasterboard.
NOTES:
*ACR = Axial Capacity Reduction. (Refer to Table C3).
Acoustic performance valid for 35mm wide studs at 600mm
centres.
FRL sYsTEm sTud dEPTh mm 90 ThERmAL
WALL LiNiNgs
Report/Opinion Nº CAViTY iNFiLL (Refer to Section ‘A’) Rw / Rw+Ctr Rt(win) Rt(sum)
CsR 902
externAl wAll Side (a) Nil 40/33 0.5 0.5
60/60/60* • 1 x 13mm GYPROCK
from outside only (b) 90 Gold Batts™ 2.7 46/37 3.2 2.9
FYRCHEK MR plasterboard.
* ACR Group 1 internAl wAll Side
(c) 75 Soundscreen™ 2.0 45/35 2.4 2.2
FAR 2303 • 1 x 10mm GYPROCK
Plasterboard CD. WALL THICKNESS mm 120
CsR 903
externAl wAll Side (a) Nil 40/33 0.5 0.5
CsR 915
60/60/60 externAl wAll Side (a) Nil 45/39 0.6 0.6
and • 1 x 16mm GYPROCK
(b) 90 Gold Batts™ 2.7 51/43 3.3 3.0
90/90/90* FYRCHEK MR plasterboard.
internAl wAll Side
* ACR Group 3 (c) 75 Soundscreen™ 2.0 50/41 2.5 2.3
• 2 x 13mm GYPROCK
FAR 2303 FYRCHEK plasterboard. WALL THICKNESS mm 139
CsR 916 externAl wAll Side (a) Nil 45/39 0.6 0.6
60/60/60 • 1 x 16mm GYPROCK
and FYRCHEK MR plasterboard.
(b) 90 Gold Batts™ 2.7 51/43 3.2 3.0
90/90/90* internAl wAll Side
* ACR Group 3
• 1 x 6mm CSR CeminSeal™
(c) 75 Soundscreen™ 2.0 50/41 2.5 2.3
Wallboard (against studs).
FAR 2303 • 1 x 16mm GYPROCK
FYRCHEK plasterboard. WALL THICKNESS mm 135
2010675.1/
• CSR Hebel Powerpanel AAC (75mm) screw fixed to
2401A/R1/Jh
22mm battens installed at 1200mm maximum vertical
centres.
• Timber studs at 600mm maximum centres.
• Cavity insulation as per system table.
• Lining material as per system table to internal side.
NOTES:
Refer to CSR Hebel for design considerations and panel
installation details.
NOTES:
To achieve stated acoustic performance masonry must be
a minimum of 90mm thick and 170kg/m2.
*ACR = Axial Capacity Reduction. (Refer to Table C3).
CsR 920
externAl Side (a) Nil 54/46 0.6 0.6
60/60/60
• Masonry veneer wall with
(b) 75 Gold Batts™ 1.5 61/53 2.2 2.0
FAR 2303 FRL 60/60/60.
internAl Side
Refer to masonry (c) 88 Soundscreen™ 2.5 62/54 3.2 2.9
manufacturer
• 1 x 16mm GYPROCK
FYRCHEK plasterboard. WALL THICKNESS mm 256
NOTES:
To achieve stated acoustic performance masonry must be
a minimum of 90mm thick and 170kg/m2.
*ACR = Axial Capacity Reduction. (Refer to Table C3).
NOTES:
Acoustic performance valid for 35mm wide studs at 600mm
centres.
• As per system
60/60/60 (b) 75 Gold Batts™ 1.5 50 2.6 2.4
specification.
CsR 697
externAl Side (a) Nil 45 1.8 1.5
CsR 698
externAl Side (a) Nil 50 1.3 1.2
• As per system
90/90/90 (b) 75 Gold Batts™ 1.5 53 2.7 2.5
specification.
FAR 2303 internAl Side
(c) 88 Soundscreen™ 2.5 54 3.7 3.4
• 2 x 13mm GYPROCK
FYRCHEK plasterboard. WALL THICKNESS mm 165
PKA-055
• Cemintel Commercial ExpressWall™ system.
• Sarking.
• 1 x 16mm GYPROCK FYRCHEK MR plasterboard fixed to
framing.
• Timber stud framing as required.
• 1 layer x 10mm GYPROCK plasterboard CD fixed to framing.
CsR 905
(a) Nil 41 1.2 1.1
NOTES:
To achieve stated acoustic performance masonry must be
a minimum of 140mm thick and 180kg/m2 laid.
CsR 936
(a) Nil 53/39 0.8 0.8
externAl Side
• Masonry veneer
block wall with 1 x
(b) 75 Gold Batts™ 1.5 59/45 2.4 2.2
–/–/– 9mm. CSR Cemintel
ExpressWall™ cladding
system.
(c) 75 Soundscreen™ 2.0 59/45 2.9 2.7
internAl Side
• 1 x 13mm GYPROCK
Plasterboard CD.
WALL THICKNESS mm 345
• 1 x 13mm
30/ – / – GYPROCK
CSIRO
FYRCHEK
FCO 1494
plasterboard.
CsR 494
• 2 x 13mm
60/ – / – GYPROCK
CSIRO
FYRCHEK
FCO 1494
plasterboard.
75mm
max.
CsR 496
• 2 x 16mm
90/ – / – GYPROCK
CSIRO
FYRCHEK
FCO 1494
plasterboard.
CsR 498
200mm max.
Apply External
Angle Bead to all
corners and set
200mm
max.
NoN-FiRE RATEd
Form butt joints on or
between studs as required by Fixing specifications
level of finish (back-block butt
joints formed between studs) Nails or Refer to Section ‘A’
Double Nails Screws
50mm apart
at 300mm Location Fixing & spacing
Stagger butt joints on max. Field 2 Nails 50mm apart at
adjacent sheets and on centres 300mm max. centres
opposite sides of wall by OR or
one stud space minimum Screws 1 screw at 400mm
at max. centres
400mm
max. 300mm Recessed 1 Nail or 1 Screw
centres max. Edges at each stud
Butt Nails at 150mm max. or
Joints on Screws at 200mm max.
studs
300mm min.
stagger all horizontal joints
300mm minimum Butt Nails at
2 Nails Joints 150mm max. centres
50mm or
apart or Screws at
1 Screw 200mm max. centres.
Corners, Nails at
Openings, 150mm max. centres
Top & or
Bottom Screws at
300mm max. centres
Studs at 600mm maximum
centres SUITABLE FOR:
CSR Bradford Insulation
where applicable
300mm min.
Plasterboard to each side Joints 150mm max. centres
of wall 2 Nails
50mm or
apart or Screws at
1 Screw 200mm max. centres.
Corners & Nails at
Openings 150mm max. centres
or
Screws at
300mm max. centres
Studs at 600mm maximum
centres 600mm NOTE:
max. Second layer butt joints may
be formed between studs with
laminating screws at 200mm max.
CSR Bradford Insulation centres each side of joint.
where applicable
Fig C7: iNsTALLATioN dETAiL – TimBER sTud WiTh REsiLiENT mouNTEd FuRRiNg ChANNEL –
gYPRoCK FYRChEK TWo LAYER – hoRiZoNTAL shEETiNg – sCREW FixiNg
centres
Recessed Screw at each stud
CSR Gyprock® Resilient Edges
Mounts to each stud at
1200mm max. from tracks Butt Screws at
and 1200mm max. centres Joints 200mm max. centres
Corners & Screws at
Openings 300mm max. centres
NOTE:
Stagger butt joints by
600mm one stud minimum Single layer systems are fixed to the
max. same specifications as detailed for
Studs at 600mm maximum the 2nd layer.
centres 300mm
max. Second layer butt joints may
be formed between studs with
CSR Bradford Insulation laminating screws at 200mm max.
where applicable centres each side of joint.
200mm
Refer to Section ‘Z’ for max.
perimeter details
SUITABLE FOR:
Rondo Track or
Angle fixed to floor Fasteners at 10 to 16mm
from sheet edges
FiRE RATEd
Fixing specifications for
Vertical sheeting (shown)
Fasteners Nails or Screws
Refer to Section ‘A
1st Layer Fixing & spacing
Recessed Screws or Nails at
Edges, 600mm max. centres
600mm Field, on studs
600mm Corners &
Openings
2nd Layer Fixing & spacing
Recessed Screws or Nails at
Edges 300mm max. centres
on studs
Field 1 Screw or 2 Nails at
300mm max. centres
on studs
300mm 300mm
Butt Joints Laminating Screws at
200mm max. centres
Corners & Screws at 300mm max.
Studs at 600mm maximum Openings centres
centres or
Nails at 150mm max.
400mm centres
3rd Layer Fixing & spacing
Recessed Laminating screws at
Edges, 400x400mm max. grid
400mm Field,
Offset all joints 300mm Corners &
min. from previous layer Openings
Butt Joints Laminating screws at
400mm 200mm max. centres
FiRE RATEd
Studs at 600mm maximum Fixing specifications
centres
Fasteners Refer to Section ‘A’
Stagger horizontal joints 200mm
300mm minimum between max. 1st Layer Fixing & spacing
1st and 2nd layer Edges & Nails or Screws at
300mm Field 600mm max. centres
Stagger butt joints in max.
adjacent sheets and 2nd Layer Fixing & spacing
between 1st and 2nd layer Field Nails at 300mm max.
by one stud minimum 200mm centres
For tiled areas – Nails
300mm min.
max.
at 200mm max. centres
Top & Nails at
Bottom 200mm max. centres
Plates
Fasten GYPROCK Recessed Nails at
FYRCHEK plasterboard Edges each stud
at 600mm maximum
centres and 10 to 16mm Butt Nails at
600mm max.
Fasteners 50mm
200mm max. min. from sheet
corners
One layer of GYPROCK
FYRCHEK MR
Plasterboard fixed to FiRE RATEd
studs
Fixing specifications
Fasteners Refer to Section ‘A’
Joint and finish outer 200mm 1st Layer Fixing & spacing
layer only (refer to max.
‘Jointing’ specification). Edges & Nails or Screws at
All joints to be formed on Field 600mm max. centres
framing
2nd Layer Fixing & spacing
Recessed Nails to framing at
200mm Joints, 200mm max. centres
Sarking max. Field,
Top &
Noggings at 1350mm max Bottom
Plates
Corners & Nails at
Openings 200mm max. centres
200mm
CSR Bradford Insulation max.
where applicable
NOTE: Fixing spacings for Cemintel™ Texture Base Sheet may need to be reduced to meet wind loadings. Refer to
publication NºFC122, Cemintel™ Texture Base Sheet & Texture Coating System guide.
Contents
Stud Selection Tables D2 – D3
Introduction D3
Design Considerations D3 – D4
Installation D5
Components D5
System Specifications
TABLE D1: mAximum WALL hEighT WiTh RONDO LiPPED STEEL STuDS – NON-LOADBEARiNg WALLS
– WALLS gENERALLy (LOAD uDL = 0.25kPa)
10 2.32 2.60 2.72 3.13 3.53 3.20 3.58 4.05 3.61 4.13 4.69 5.33 6.81
600mm max. cts
13 2.32 2.60 2.72 3.25 3.58 3.24 3.82 4.05 3.61 4.18 4.69 5.37 6.81
16 2.32 2.60 2.75 3.28 3.59 3.25 3.87 4.05 3.61 4.20 4.69 5.37 6.81
TABLE D2: mAximum WALL hEighT WiTh RONDO LiPPED STEEL STuDS – NON-LOADBEARiNg WALLS
– WALLS Of ShAfTS AND fiRE iSOLATED ExiTS (LOAD uDL = 0.35kPa)
10 2.07 2.34 2.34 2.80 3.15 2.76 3.20 3.62 3.06 3.70 3.81 3.81 3.81
600mm max. cts
13 2.07 2.34 2.34 2.80 3.17 2.76 3.37 3.62 3.06 3.70 4.20 4.83 5.53
16 2.07 2.34 2.34 2.90 3.18 2.76 3.41 3.62 3.06 3.70 4.20 4.83 5.53
NOTES:
Deflection Limit is span/240 to a maximum of 30mm, in accordance with BCA Specification C1.8.
Tabulated heights do not include axial loads (except self weight) or shelf loading.
Loadings: Table D1 Pultimate = 0.375 kPa, Pservice = 0.25 kPa.
Loadings: Table D2 Pultimate = 0.525 kPa, Pservice = 0.35 kPa.
Walls are not for external applications.
All loadings in accordance with AS1170:2002.
Walls analysed in accordance with AS4600:1996.
Noggings in accordance with Table D3.
Tables have been prepared by Rondo Building Services Pty Ltd.
TABLE D3: NOggiNgS fOR STEEL fRAmiNg TABLE D4. mAximum SPAciNg Of WALL SuPPORT
cLiPS fOR fuRRiNg chANNELS.
Number of Noggings
Lining Configuration Wall Height (m) (LOAD uDL = 0.35kPa)
(equally spaced)
0.0 - 3.0 1
Rondo Furring Channel Part Nº Maximum Spacing of Clips (mm)
Lined One Side* 3.0 - 6.0 2
308 (16mm) 900
6.0 - 8.0 3
129 (28mm) 1200
NOTES: * Plus noggings at head. Refer to details.
NOTES: Support clips include Gyprock™ Resilient Mounts and Rondo
direct fixing clips.
70 2.7 2.9 2.9 3.2 3.1 3.3 3.0 3.3 3.3 3.6 3.5 3.8
600mm cts.
90 3.4 3.7 3.8 4.1 4.0 4.3 3.9 4.2 4.2 4.6 4.5 4.9
120 4.6 5.0 5.0 5.5 5.3 5.8 5.2 5.7 5.6 6.0 6.0 6.0
NOTES:
Stud heights have been determined based on a maximum deflection of H÷240 or 30mm maximum.
Noggings at 1350mm maximum centres, measured vertically.
Introduction Design
Gyprock™ plasterboard and CeminSeal™ Wallboard can
be used with masonry walls for effective fire and acoustic Considerations
solutions. These linings can eliminate the need for render,
increase the fire rating of the masonry, or provide an acoustic Structural Performance
performance to meet sound transmission and sound impact
All wall elements must be designed for the applied loads.
ratings.
Vertical loads may be supported by the masonry element
Systems incorporating masonry and an insulated cavity are of the wall, or for non-fire rated walls, by the stud framing.
generally used where there is a requirement for excellent
Lateral loads should be considered separately for framed
acoustic performance and discontinuous construction. The
and masonry parts of a wall. To achieve the specified sound
provision of a cavity also allows the inclusion of services.
performance, ties from masonry to the stud framing must
Gyprock ™ plasterboard may be directly applied to the not be used.
masonry substrate, screw fixed to metal furring channels
framed Wall Elements
that are fixed to the masonry, or may be fixed to separate
stud framing. CeminSeal™ Wallboard may be fixed to furring Guidance is given in Tables D1, D2, & D5 for the selection of
channels or studs. Rondo studs and for timber studs in non-loadbearing internal
walls only for 0.25kPa and 0.35kPa. For other brands of
Systems in this section are suitable for a wide range of
studs, studs that are required to be loadbearing, and studs
masonry products. These are typically clay and concrete
subject to higher lateral pressures, contact the manufacturer
blocks, autoclaved aerated concrete blocks and panels, and
for design information. Maximum spans for Rondo furring
may include cast concrete elements. Minimum performance
channels are given in Table D4.
conditions apply to the substrates to achieve the system
performance values, and these are stated in the system Tall multi-residential buildings often have exterior operable
specifications. Specific fixing details apply to each type of doors and windows, resulting in internal walls being subject
substrate. to wind pressure. In these cases, walls must be designed
for the appropriate loads.
These wall systems are generally used in internal applications
in commercial, industrial, institutional, domestic and high-rise Stud frames that are part of a masonry wall system may be
domestic construction, or in the renovation of older buildings. loadbearing. A qualified person must complete the structural
A number of systems for external masonry veneer walls can design of loadbearing wall systems. Walls with shelving
be found in Section ‘B’ and Section ‘C’. attached are considered loadbearing.
Acoustic Performance
The acoustic performance of some systems is dependant
on a minimum Rw of the masonry wall element. This is to
be the tested performance of the masonry without render
or sheet linings, and must be verified by the masonry unit
manufacturer.
Installation of the masonry element of the wall must be in
accordance with the manufacturer’s details for the tested
product.
Systems that meet the BCA requirements for discontinuous
construction are noted in the system specifications. These
have studs that are separated from the masonry by at least
12mm. The plasterboard lining on the studs (the wall leaf)
therefore has a separation of at least 12mm plus the depth
of the stud, which exceeds the BCA minimum of 20mm.
Ties between masonry and stud framing must not be used.
All brick and block walls are to be installed in accordance • At 12m maximum centres.
with AS3700 Masonry Structures. CSR Hebel Powerpanel™ • At change of substrate material.
must be installed in accordance with CSR Hebel literature.
For stud framed wall elements:
Manual NºGYP544, Gyprock™ Steel Frame Wall Systems • Walls with plasterboard outer layer: at 12m maximum
Installation Guide has detailed information on the installation centres.
of steel stud framing. • At junctions with other wall elements.
• At changes of lining material.
Wallboard & Plasterboard fixing
Walls may be built to achieve a particular ‘Level of Finish’
as defined in AS/NZS2589.1. The Level of Finish specified Components
can have requirements for frame alignment, jointing, back
blocking methods and sheet orientation. CeminSeal ™ Lining & fixing materials
Wallboard and Gyprock ™ plasterboard may be installed Refer to Section ‘A’ of this manual for detailed information
vertically or horizontally, although for some Levels of Finish on Gyprock ™ and Cemintel ™ lining products, masonry
horizontal sheeting must be used. adhesive, and for fastener specifications for fixing GYPROCK
Except for fire grade plasterboard, fixing to framing may be plasterboard to steel studs and furring channel.
fastener only or combination fastener/adhesive. Plasterboard Gyprock ™ Masonry Adhesive is a fast and convenient
fixed direct to masonry may be adhesive daub fixed, full bed method of fixing GYPROCK plasterboard systems to
adhesive fixed, or mechanically fixed. A nominal 5mm has masonry substrates. Gyprock™ Acrylic Stud Adhesive is
been allowed for adhesive thickness. used for fixing non-fire grade linings to framing.
• Multi-layered systems only require jointing and finishing of Fixing clips include CSR Resilient Mount, Rondo direct fixing
the outer layer. clips Nº237, Beta-Fix and STSC clips. Furring channels part
Nº308 or Nº129 are to be fitted into wall track part Nº142 or
• It is recommended that a water resistant taping
Nº140 respectively at top and bottom.
compound, such as Gyprock™ Wet Area Base Coat be
used at horizontal and vertical joints within wet areas such
as showers.
masonry
For systems in this section, masonry may include clay or
control Joints concrete blocks, autoclaved aerated concrete blocks and
panels, and reinforced concrete. Brick and block substrates
Control joints must be installed to allow for structural
shall comply with AS3700.
movement. Allowance for movement must be made through
the masonry and any direct fixed lining, and through framed
wall elements.
Control joints must be installed at all construction joints in
the building, and at the following locations:
PKA-053
Discontinuous
Construction
• Lining as per table, fixed to studs.
• Steel stud framing, as per table, at 600mm max. centres.
• Cavity infill as per table.
• 12mm minimum cavity between masonry and framing.
• Single Brick, Block or Concrete wall with Rw as stated.
• Plasterboard as per system table, direct fixed to masonry.
• 1 x 13mm GYPROCK
(b) 90 Gold Batts™ 2.0 57/47 58/48
plasterboard CD
stud side
(c) TSB4/ASB4 Polyester 55/45 56/46
• 1 x 6mm CeminSeal™
Wallboard. ADDITIONAL WALL THICKNESS mm 100 128
cSR 760
Masonry side (a) 75 GW Partition 11kg 56/48 58/50
• 1 x 13mm GYPROCK
(b) 90 Gold Batts™ 2.0 57/49 59/51
plasterboard CD
Tested stud side
Brick, (c) TSB4/ASB4 Polyester 55/47 57/49
• 1 x 13mm GYPROCK
Block or
plasterboard CD. ADDITIONAL WALL THICKNESS mm 107 135
concrete
Wall with Rw cSR 761 Masonry side (a) 75 GW Partition 11kg 58/50 59/52
> 41
Refer to Masonry • 1 x 13mm GYPROCK
Wall Manufacturer plasterboard CD (b) 90 Gold Batts™ 2.0 59/51 60/53
for FRL Details stud side
• 1 x 13mm GYPROCK (c) TSB4/ASB4 Polyester 57/49 58/51
SOUNDCHEK
plasterboard. ADDITIONAL WALL THICKNESS mm 107 135
PKA-053
Discontinuous
Construction
• Lining as per table, fixed to studs.
• Steel stud framing, as per table, at 600mm max. centres.
• Cavity infill as per table.
• 12mm minimum cavity between masonry and framing.
• Single Brick, Block or Concrete wall with Rw as stated.
• Plasterboard as per system table, direct fixed to masonry.
• 1 x 13mm GYPROCK
(b) 90 Gold Batts™ 2.0 60/50 61/51
plasterboard CD
stud side
(c) TSB4/ASB4 Polyester 58/48 59/49
• 1 x 6mm CeminSeal™
Wallboard. ADDITIONAL WALL THICKNESS mm 100 128
cSR 764
Masonry side (a) 75 GW Partition 11kg 59/51 61/53
• 1 x 13mm GYPROCK
(b) 90 Gold Batts™ 2.0 60/52 62/54
plasterboard CD
Tested stud side
Brick, (c) TSB4/ASB4 Polyester 58/50 60/52
• 1 x 13mm GYPROCK
Block or
plasterboard CD. ADDITIONAL WALL THICKNESS mm 107 135
concrete
Wall with Rw cSR 765 Masonry side (a) 75 GW Partition 11kg 61/53 62/55
> 44
Refer to Masonry • 1 x 13mm GYPROCK
Wall Manufacturer plasterboard CD (b) 90 Gold Batts™ 2.0 62/54 63/56
for FRL Details stud side
• 1 x 13mm GYPROCK (c) TSB4/ASB4 Polyester 60/52 61/54
SOUNDCHEK
plasterboard. ADDITIONAL WALL THICKNESS mm 107 135
PKA-053
Discontinuous
Construction
• Lining as per table, fixed to studs.
• Steel stud framing, as per table, at 600mm max. centres.
• Cavity infill as per table.
• 12mm minimum cavity between masonry and framing.
• Single Brick, Block or Concrete wall with Rw as stated.
• Plasterboard as per system table, direct fixed to masonry.
• 1 x 13mm GYPROCK
(b) 90 Gold Batts™ 2.0 62/52 63/54
plasterboard CD
stud side
(c) TSB4/ASB4 Polyester 60/50 61/52
• 1 x 6mm CeminSeal™
Wallboard. ADDITIONAL WALL THICKNESS mm 100 128
cSR 739
Masonry side (a) 75 GW Partition 11kg 60/51 62/54
• 1 x 13mm GYPROCK
(b) 90 Gold Batts™ 2.0 61/52 63/55
plasterboard CD
stud side
(c) TSB4/ASB4 Polyester 59/50 61/53
• 1 x 10mm GYPROCK
plasterboard CD. ADDITIONAL WALL THICKNESS mm 104 132
Tested cSR 767
Brick, Masonry side (a) 75 GW Partition 11kg 61/53 63/55
Block or • 1 x 13mm GYPROCK
concrete (b) 90 Gold Batts™ 2.0 62/54 64/56
plasterboard CD
Wall with Rw stud side
> 46 (c) TSB4/ASB4 Polyester 60/52 62/54
• 1 x 13mm GYPROCK
Refer to Masonry
Wall Manufacturer plasterboard CD. ADDITIONAL WALL THICKNESS mm 107 135
for FRL Details
cSR 768 Masonry side (a) 75 GW Partition 11kg 63/55 64/57
• 1 x 13mm GYPROCK
plasterboard CD (b) 90 Gold Batts™ 2.0 64/56 65/58
stud side
• 1 x 13mm GYPROCK (c) TSB4/ASB4 Polyester 62/54 63/56
SOUNDCHEK
plasterboard. ADDITIONAL WALL THICKNESS mm 107 135
PKA-053
cSR 774
(a) 75 GW Partition 11kg 60/45 61/46
cSR 775
(a) 75 GW Partition 11kg 59/45 60/47
cSR 781
(a) 75 GW Partition 11kg 62/49 63/50
Both sides
(b) 90 Gold Batts™ 2.0 63/50 64/51
• 1 x 13mm GYPROCK
SOUNDCHEK
(c) TSB4/ASB4 Polyester 60/47 61/48
plasterboard.
PKA-053
cSR 776
(a) 75 GW Partition 11kg 62/47 63/48
cSR 777
(a) 75 GW Partition 11kg 62/48 63/50
cSR 784
(a) 75 GW Partition 11kg 64/51 66/53
Both sides
(b) 90 Gold Batts™ 2.0 65/52 67/54
• 1 x 13mm GYPROCK
SOUNDCHEK
(c) TSB4/ASB4 Polyester 62/49 64/51
plasterboard.
PKA-053
cSR 778
(a) 75 GW Partition 11kg 65/50 66/51
cSR 779
(a) 75 GW Partition 11kg 64/50 66/53
cSR 788
(a) 75 GW Partition 11kg 67/54 68/55
Both sides
(b) 90 Gold Batts™ 2.0 68/55 69/56
• 1 x 13mm GYPROCK
SOUNDCHEK
(c) TSB4/ASB4 Polyester 65/52 66/53
plasterboard.
PKA-053
cSR 540
(a) 50 GW Partition 11kg (a) 50 GW Partition 11kg 57/45 59/47
Both sides
(b) 75 GW Partition 11kg (b) 50 GW Partition 11kg 58/46 60/48
Tested • 1 x 13mm
Brick, GYPROCK
(c) TSB4/ASB4 Polyester (c) TBL1025 55/43 57/45
Block or plasterboard CD.
concrete ADDITIONAL WALL THICKNESS mm 142 170
Wall with
Rw > 41 cSR 541
(a) 50 GW Partition 11kg (a) 50 GW Partition 11kg 59/47 60/49
Refer to Both sides
Masonry Wall
• 1 x 13mm (b) 75 GW Partition 11kg (b) 50 GW Partition 11kg 60/48 61/50
Manufacturer
for FRL Details GYPROCK
SOUNDCHEK (c) TSB4/ASB4 Polyester (c) TBL1025 57/45 58/47
plasterboard.
ADDITIONAL WALL THICKNESS mm 142 170
cSR 542 (a) 50 GW Partition 11kg (a) 50 GW Partition 11kg 60/48 62/50
Both sides
(b) 75 GW Partition 11kg (b) 50 GW Partition 14kg 62/50 64/52
• 1 x 13mm
GYPROCK
(c) TSB4/ASB4 Polyester (c) TBL1025 58/46 60/48
plasterboard CD.
PKA-053
cSR 549
(a) 50 GW Partition 11kg (a) 50 GW Partition 11kg 61/48 63/51
Both sides
(b) 75 GW Partition 11kg (b) 50 GW Partition 14kg 63/50 65/53
• 1 x 10mm
GYPROCK
(c) TSB4/ASB4 Polyester (c) TBL1025 59/46 61/49
plasterboard CD.
cSR 544
(a) 50 GW Partition 11kg (a) 50 GW Partition 11kg 62/50 64/52
Both sides
(b) 75 GW Partition 11kg (b) 50 GW Partition 11kg 63/51 65/53
• 1 x 13mm
Tested
GYPROCK
Brick, (c) TSB4/ASB4 Polyester (c) TBL1025 60/48 62/50
plasterboard CD.
Block or
concrete ADDITIONAL WALL THICKNESS mm 142 170
Wall with cSR 545
Rw > 46 (a) 50 GW Partition 11kg (a) 50 GW Partition 11kg 64/52 65/54
Refer to Both sides
Masonry Wall (b) 75 GW Partition 11kg (b) 50 GW Partition 11kg 65/53 66/55
• 1 x 13mm
Manufacturer
GYPROCK
for FRL Details
SOUNDCHEK (c) TSB4/ASB4 Polyester (c) TBL1025 62/50 63/52
plasterboard.
ADDITIONAL WALL THICKNESS mm 142 170
cSR 551 stud side (a) 50 GW Partition 11kg (a) 50 GW Partition 11kg 62/50 64/52
• 1 x 13mm
GYPROCK (b) 75 GW Partition 11kg (b) 50 GW Partition 11kg 63/51 65/53
plasterboard CD.
Furring side (c) TSB4/ASB4 Polyester (c) TBL1025 60/48 62/50
• 1 x 6mm
CeminSeal™ ADDITIONAL WALL THICKNESS mm 135 163
Wallboard.
PKA-053
NOT
• Lining as per table, direct fixed to furring. Deemed
• 28mm furring channel at 600mm max. centres, fixed to Discontinuous
Construction
masonry with CSR Gyprock™ Resilient Mounts.
• Cavity infill, as per table.
• Single Brick, Block or Concrete wall with Rw as stated.
• Plasterboard as per system table, direct fixed to masonry.
masonry
SySTEm
Wall WALL LiNiNgS cAViTy iNfiLL (Refer to Section A) Rw / Rw+ctr
Nº
Requirements
cSR 530 Masonry side
(a) 50 GW Partition 11kg 55/42
• 1 x 13mm GYPROCK
plasterboard CD
Furring side (b) TSB2/ASB2 Polyester 53/40
• 1 x 13mm GYPROCK
SOUNDCHEK
ADDITIONAL WALL THICKNESS mm 71
plasterboard.
Tested
cSR 531 Masonry side
Brick, (a) 50 GW Partition 11kg 58/45
Block or • 1 x 13mm GYPROCK
concrete plasterboard CD
Wall with Rw Furring side (b) TSB2/ASB2 Polyester 56/43
> 41 • 2 x 13mm GYPROCK
Refer to Masonry SOUNDCHEK
ADDITIONAL WALL THICKNESS mm 84
Wall Manufacturer plasterboard.
for FRL Details
cSR 526
Masonry side (a) 50 GW Partition 11kg 55/42
• 1 x 13mm GYPROCK
plasterboard CD
(b) TSB2/ASB2 Polyester 53/40
Furring side
• 1 x 9mm CeminSeal™
Wallboard. ADDITIONAL WALL THICKNESS mm 67
PKA-053
NOT
• Lining as per table, direct fixed to furring. Deemed
• 28mm furring channel at 600mm max. centres, fixed to Discontinuous
Construction
masonry with CSR Gyprock™ Resilient Mounts.
• Cavity infill, as per table.
• Single Brick, Block or Concrete wall with Rw as stated.
• Plasterboard as per system table, direct fixed to masonry.
masonry
SySTEm
Wall WALL LiNiNgS cAViTy iNfiLL (Refer to Section A) Rw / Rw+ctr
Nº
Requirements
cSR 534 Masonry side
(a) 50 GW Partition 11kg 60/47
• 1 x 13mm GYPROCK
plasterboard CD
Furring side (b) TSB2/ASB2 Polyester 58/45
• 1 x 13mm GYPROCK
SOUNDCHEK
ADDITIONAL WALL THICKNESS mm 71
plasterboard.
Tested
cSR 535 Masonry side
Brick, (a) 50 GW Partition 11kg 63/50
Block or • 1 x 13mm GYPROCK
concrete plasterboard CD
Wall with Rw Furring side (b) TSB2/ASB2 Polyester 61/48
> 46 • 2 x 13mm GYPROCK
Refer to Masonry SOUNDCHEK
ADDITIONAL WALL THICKNESS mm 84
Wall Manufacturer plasterboard.
for FRL Details
cSR 528
Masonry side (a) 50 GW Partition 11kg 60/47
• 1 x 13mm GYPROCK
plasterboard CD
(b) TSB2/ASB2 Polyester 58/45
Furring side
• 1 x 9mm CeminSeal™
Wallboard. ADDITIONAL WALL THICKNESS mm 67
ATf-1023
fRL SySTEm
WALL LiNiNgS cAViTy iNfiLL (Refer to Section A) Rw / Rw+ctr
Report/Opinion Nº
hEBEL 1030/1031
2010861.1/
0505A/
• Plasterboard as per table, fixed to studs.
R2/Vf
• 64mm steel studs at 600mm max. centres.
Discontinuous
• Cavity infill, as per table. Construction
• 35mm minimum gap.
• 75mm CSR Hebel Powerpanel™.
• Plasterboard as per table, fixed to panel.
fRL SySTEm
WALL LiNiNgS cAViTy iNfiLL (Refer to Section A) Rw / Rw+ctr
Report/Opinion Nº
hEBEL 1000/1001
fRL SySTEm
WALL LiNiNgS cAViTy iNfiLL (Refer to Section A) Rw / Rw+ctr
Report/Opinion Nº
hEBEL 1006/1007
fRL SySTEm
WALL LiNiNgS cAViTy iNfiLL (Refer to Section A) Rw / Rw+ctr
Report/Opinion Nº
hEBEL 1032/1033
N/A
fRL SySTEm
WALL LiNiNgS ADDiTiONAL fRL
Report/Opinion Nº
cSR 730
Both sides
• 1 x 16mm GYPROCK X+30 / Y+60 / Z+60
FYRCHEK plasterboard
cSR 731
masonry
Wall Both sides
• 2 x 13mm GYPROCK X+60 / Y+120 / Z+120
x/y/Z FYRCHEK plasterboard.
FCO 382
cSR 732
Both sides
• 2 x 16mm GYPROCK X+90 / Y+180 / Z+180
FYRCHEK plasterboard.
N/A
one side
• 1 x 16mm GYPROCK X+30 / Y+30 / Z+30 X+0 / Y+20 / Z+30
FYRCHEK plasterboard
cSR 723
masonry
Wall one side
• 2 x 13mm GYPROCK X+60 / Y+60 / Z+60 X+0 / Y+40 / Z+60
x/y/Z FYRCHEK plasterboard.
FCO 382
cSR 724
one side
• 2 x 16mm GYPROCK X+90 / Y+90 / Z+90 X+0 / Y+60 / Z+90
FYRCHEK plasterboard.
Fasten at
butt joints with 200mm max.
Direct fasten
each layer of laminating
GYPROCK screws at
FYRCHEK 200mm max
plasterboard with centres
Steel reinforced Tapcon™ 10g
concrete column screws (or Apply
equivalent) at 400 External
x 400mm max. Angle
horizontal and Bead to
vertical centres all
corners
and set
Note: Butt joints in single layer systems to be
backed by furring channel or nogging
400mm max.
75mm
max.
Adhesive daubs
50mm max. Adhesive daubs
from sheet at 230mm max. Adhesive daubs
edge centres 50mm max. NON-fiRE RATED
from sheet
edge fiRE RATED
Adhesive daubs
100mm max from fixing Specifications
top edge of sheet
Adhesive Refer to Section ‘A’
Location fixing & Spacing
Field Adhesive at 460mm
max. centres
beginning 100mm
max. from top and
bottom sheet edges
and 50mm max.
Adhesive daubs from recessed sheet
at 460mm max. edges
centres
Butt Joints, Adhesive at 460mm
Adhesive Corners & max. centres 50mm
daubs GYPROCK Openings max. from sheet
at 460mm Plasterboard edges
max.
centres
Adhesive daubs
100mm max from
bottom edge of
sheet
Daubs of GYPROCK Masonry Adhesive.
Rondo Track or
Angle fixed to ceiling
frame
NON-fiRE RATED
One or two layers fiRE RATED
of GYPROCK
FYRCHEK fixing Specifications
Plasterboard to 300mm
each side of wall max. Screws Refer to Section ‘A’
1st Layer fixing & Spacing
Edges & Screws at 600mm
Field max. centres
300mm min.
Rondo Track or
Angle fixed to floor
Fasteners at 10 to 16mm
from sheet edges
300mm
max.
6mm min.
gap
600 mm
max.
fig D7: iNSTALLATiON DETAiL – hEBEL AAc WALL – hORiZONTAL ShEETiNg – ScREW fixiNg
For additional information, refer to CSR Hebel Design Guide – Acoustic Wall Systems
NON-fiRE RATED
fiRE RATED
fixing Specifications
Fixings 50mm x 10g bugle
CSR Hebel AAC Panel
head screws
Location fixing & Spacing
Field, Butt Screws at 600mm
Joints & max. horizontal
Edges centres x 300mm
max. vertical centres
CSR Hebel AAC Panel
GYPROCK
Plasterboard
300mm
max.
6mm min.
gap
600mm
10-16mm max.
min. from
each edge
Contents
Introduction E2
Design Considerations E2 – E3
Installation E4
Components E4 – E5
System Specifications
loor/Ceiling Systems
F
(Timber Flooring) E6 – E15
loor/Ceiling Systems
F
(Concrete Flooring) E16 – E23
oof/Ceiling Systems
R
(Pitched Roofing) E24 – E29
oof/Ceiling Systems
R
(Steel Sheet Roofing) E30 – E33
eiling Systems
C
– Fire Rated from Above E34
eiling Systems – Fire Rated
C
from Above and/or Below E35
ebel PowerFloor™ – Fire Rated
H
from Above and/or Below E36
Acoustic Tile Ceiling Systems E37 – E38
System Installation Details E39 – E43
d) Screw fixing to suspended concealed metal grid. Steel framing to which plasterboard will be fixed must comply
with AS/NZS4600, ‘Cold Formed Steel Structures’.
e) Lay-in tiles in suspended exposed metal grid or Fricker
Easy Access System™. Suspended Ceiling Systems
Ceiling suspension systems must be designed to
Design
AS/NZS2785 ‘Suspended Ceilings – Design and Installation’.
Ceilings in this manual are not trafficable. Trafficable systems
shall be designed in accordance with AS1657 ‘Fixed
20mm
40mm (Nº129)
28mm (Nº308)
lined with plasterboard. In multi-layer systems, jointing
and finishing is required on the visible outer layer only. As
a minimum, one base coat with paper tape may be used.
Furring Channel
Expressed joints are recommended for ceilings lined with Nº129 or Nº308
Control Joints
Control joints are used to reduce the possibility of cracks Top Cross Rail
forming from structural movement, thermal and moisture
Resilient Mount to
movement and the like. Locations for joints should be chosen Top Cross Rail Clip
80mm
1200mm
3600mm
1040mm
1200mm
440mm 160mm 440mm
Overall 3600mm
TABLe e2: MAXiMuM SPAnS FOR MeTAL BATTen/FuRRinG CHAnneL uSeD in CeiLinGS
PKA–056
• Floor finished bare or with carpet and underlay, as per
system table.
• 1 x 19mm or 22mm particleboard, or timber flooring of at
least 15kg/m2.
• Timber or steel joists at 600mm maximum centres.
• Minimum 190mm cavity depth.
• Cavity infill as per system table.
• Ceiling lining as per system table, direct fixed to framing.
CSR 801
(a) Nil 39/32 – 60 – 65
• 1 x 13mm GYPROCK
–/–/– (b) 90 Gold Batts™ 2.0 42/34 – 60 – 65
Plasterboard CD.
CSR 803
(a) Nil 37/30 – 60 – 65
• 1 x 10mm GYPROCK
–/–/– SUPACEIL (b) 90 Gold Batts™ 2.0 40/32 – 60 – 65
plasterboard.
(c) 75 Soundscreen™ 2.0 40/32 – 60 – 65
CSR 804
(a) Nil 43/37 – 55 – 60
• 2 x 10mm GYPROCK
–/–/– (b) 90 Gold Batts™ 2.0 46/39 80 – 85 55 – 60
SUPERCHEK.
PKA–056
• Floor finished bare or with carpet and underlay, as per
system table.
• 1 x 19mm or 22mm particleboard, or timber flooring of at
least 15kg/m2.
• Timber or steel joists at 600mm maximum centres (except
where noted in system table).
• Minimum 190mm cavity depth.
• Cavity infill as per system table.
• Ceiling lining as per system table, direct fixed to framing.
CSR 820
(a) Nil 40/34 – 55 – 60
• 1 x 16mm GYPROCK
30/30/30 FYRCHEK (b) 90 Gold Batts™ 2.0 43/36 – 55 – 60
EWFA 26162
Plasterboard.
(c) 75 Soundscreen™ 2.0 43/36 – 55 – 60
CSR 806
(a) Nil 43/37 – 55 – 60
60/60/60 • 2 x 13mm GYPROCK
+RISF 30
FYRCHEK (b) 90 Gold Batts™ 2.0 46/39 80 – 85 55 – 60
minutes
EWFA 26162
Plasterboard.
(c) 75 Soundscreen™ 2.0 46/39 80 – 85 55 – 60
CSR 807
(a) Nil 42/36 – 55 – 60
90/90/90 • 2 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 90 Gold Batts™ 2.0 45/38 80 – 85 55 – 60
minutes
EWFA 26162
Plasterboard.
(c) 75 Soundscreen™ 2.0 45/38 80 – 85 55 – 60
CSR 808
(a) Nil 45/39 80 – 85 50 – 55
120/120/120 • 3 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 90 Gold Batts™ 2.0 48/41 80 – 85 50 – 55
minutes
EWFA 26162
Plasterboard.
(c) 75 Soundscreen™ 2.0 48/41 80 – 85 50 – 55
CSR 886
(a) Nil 39/32 80-85 60-65
• 1 x 10mm GYPROCK
–/–/– (b) 90 Gold Batts™ 2.0 44/37 75-80 60-62
Plasterboard CD.
CSR 885
(a) Nil 42/36 80-85 60-62
• 1 x 10mm GYPROCK
–/–/– SUPERCHEK (b) 90 Gold Batts™ 2.0 47/41 75-80 55-60
plasterboard.
(c) 75 Soundscreen™ 2.0 47/41 75-80 55-60
CSR 811
(a) Nil 40/34 80-85 60-62
• 1 x 13mm GYPROCK
–/–/– (b) 90 Gold Batts™ 2.0 45/39 75-80 55-60
Plasterboard CD.
CSR 812
(a) Nil 41/34 – 55 – 60
• 1 x 6mm CeminSeal™
–/–/– (b) 90 Gold Batts™ 2.0 46/37 80 – 85 55 – 60
Wallboard.
CSR 888
(a) Nil 45/39 75-80 55-60
• 2 x 10mm GYPROCK
–/–/– SUPERCHEK (b) 90 Gold Batts™ 2.0 50/44 70-75 50-55
plasterboard.
(c) 75 Soundscreen™ 2.0 50/44 70-75 50-55
CSR 816
(a) Nil 42/36 – 55 – 60
• 1 x 16mm GYPROCK
30/30/30
FYRCHEK (b) 90 Gold Batts™ 2.0 47/39 80 – 85 55 – 60
EWFA 26162
plasterboard.
(c) 75 Soundscreen™ 2.0 47/39 80 – 85 55 – 60
CSR 814
(a) Nil 45/39 80 – 85 55 – 60
60/60/60 • 2 x 13mm GYPROCK
+RISF 30
minutes
FYRCHEK (b) 90 Gold Batts™ 2.0 50/42 75 – 80 55 – 60
plasterboard.
EWFA 26162
(c) 75 Soundscreen™ 2.0 50/42 75 – 80 55 – 60
CSR 817
(a) Nil 44/38 80 – 85 55 – 60
90/90/90 • 2 x 16mm GYPROCK
+RISF 60
minutes
FYRCHEK (b) 90 Gold Batts™ 2.0 49/41 80 – 85 55 – 60
plasterboard.
EWFA 26162
(c) 75 Soundscreen™ 2.0 49/41 80 – 85 55 – 60
CSR 818
(a) Nil 47/41 80 – 85 55 – 60
120/120/120 • 3 x 16mm GYPROCK
+RISF 60
minutes
FYRCHEK (b) 90 Gold Batts™ 2.0 52/44 75 – 80 55 – 60
plasterboard.
EWFA 26162
(c) 75 Soundscreen™ 2.0 52/44 75 – 80 55 – 60
• 1 x 13mm GYPROCK
–/–/– (b) 90 Gold Batts™ 2.0 55/46 65 – 70 50 – 55
Plasterboard CD.
CSR 823
(a) Nil 46/40 75 – 80 55 – 60
• 1 x 10mm GYPROCK
–/–/– SUPERCHEK (b) 90 Gold Batts™ 2.0 55/47 65 – 70 50 – 55
plasterboard.
(c) 75 Soundscreen™ 2.0 54/45 65 – 70 50 – 55
CSR 824
(a) Nil 49/43 75 – 80 55 – 60
• 2 x 10mm GYPROCK
–/–/– SUPERCHEK (b) 90 Gold Batts™ 2.0 58/50 65 – 70 50 – 55
plasterboard.
(c) 75 Soundscreen™ 2.0 57/48 65 – 70 50 – 55
CSR 826
(a) Nil 46/40 75 – 80 55 – 60
• 1 x 16mm GYPROCK
30/30/30
FYRCHEK (b) 90 Gold Batts™ 2.0 55/47 65 – 70 50 – 55
EWFA 26162
plasterboard.
(c) 75 Soundscreen™ 2.0 54/45 70 – 75 50 – 55
CSR 822
(a) Nil 50/44 70 – 75 50 – 55
60/60/60 • 2 x 13mm GYPROCK
+RISF 30
minutes
FYRCHEK (b) 90 Gold Batts™ 2.0 59/51 60 – 65 45 – 50
plasterboard.
EWFA 26162
(c) 75 Soundscreen™ 2.0 58/48 60 – 65 45 – 50
CSR 827
(a) Nil 50/44 70 – 75 50 – 55
90/90/90 • 2 x 16mm GYPROCK
+RISF 60
minutes
FYRCHEK (b) 90 Gold Batts™ 2.0 59/51 60 – 62 45 – 50
plasterboard.
EWFA 26162
(c) 75 Soundscreen™ 2.0 58/48 60 – 62 45 – 50
CSR 828
(a) Nil 49/43 70-75 35-40
120/120/120 • 3 x 16mm GYPROCK
+RISF 60
minutes
FYRCHEK (b) 90 Gold Batts™ 2.0 59/53 60-62 35-40
plasterboard.
EWFA 26162
(c) 75 Soundscreen™ 2.0 59/52 60-62 35-40
PKA–056
• Floor finished bare or with carpet and underlay, as per
system table.
• 1 x 19mm or 22mm particleboard, or timber flooring of at
least 15kg/m2.
• Timber or steel joists.
• Minimum 340mm cavity depth.
• RONDO Suspended Ceiling System.
• Cavity infill as per system table.
• Ceiling lining as per system table, fixed to furring channel.
• 1 x 13mm GYPROCK
–/–/– (b) 90 Gold Batts™ 2.0 52/45 75 – 80 55 – 60
Plasterboard CD.
CSR 833
CSR 832
(a) Nil 48/42 80 – 85 60 – 65
CSR 834
(a) Nil 49/43 80 – 85 60 – 65
CSR 836
CSR 839
• 1 x 13mm GYPROCK (a) Nil 50/44 75 – 80 55 – 60
FYRCHEK
60/60/60 plasterboard. (b) 90 Gold Batts™ 2.0 56/50 70 – 75 50 – 55
+RISF 60
minutes • 1 x 16mm GYPROCK
EWFA 26162 FYRCHEK (c) 75 Soundscreen™ 2.0 56/50 70 – 75 50 – 55
plasterboard (any
order). (d) 165 GW Partition 58/52 70 – 75 50 – 55
CSR 837
(a) Nil 49/43 80 – 85 55 – 60
CSR 838
(a) Nil 52/46 75 – 80 55 – 60
CSR 845
(a) Nil 48/42 75 – 80 55 – 60
• 1 x 13mm GYPROCK
FYRCHEK
(b) 90 Gold Batts™ 2.0 54/48 70 – 75 50 – 55
30/30/30 plasterboard.
EWFA 26162 • Furring channels at
(c) 75 Soundscreen™ 2.0 54/48 70 – 75 50 – 55
450mm maximum
centres.
(d) 165 GW Partition 56/50 65 – 70 50 – 55
CSR 846
CSR 847
(a) Nil 51/45 70 – 75 50 – 55
CSR 848
(a) Nil 54/48 70 – 75 45 – 50
PKA–056
CSR 258
(a) Nil 57/47 70-75 35-40
CSR 259
(a) Nil 56/46 70-75 35-40
• 1 x 10mm GYPROCK
Refer to
SUPACEIL (b) 50 GW Partition 11kg 60/50 65-70 35-40
AS3600 plasterboard.
(c) TSB3/ASB3 Polyester 59/49 65-70 35-40
CSR 260
(a) Nil 58/49 65-70 35-40
• 1 x 10mm GYPROCK
Refer to
SUPERCHEK (b) 50 GW Partition 11kg 62/54 65-70 35-40
AS3600 plasterboard.
(c) TSB3/ASB3 Polyester 61/53 65-70 35-40
CSR 261
(a) Nil 59/50 65-70 35-40
• 1 x 13mm GYPROCK
Refer to
SOUNDCHEK (b) 50 GW Partition 11kg 64/56 60-65 35-40
AS3600 plasterboard.
(c) TSB3/ASB3 Polyester 63/55 60-65 35-40
CSR 262
(a) Nil 60/52 65-70 35-40
PKA–056
CSR 264
(a) Nil 59/50 65-70 35-40
60/60/60 • 2 x 13mm GYPROCK
+RISF 30
FYRCHEK (b) 50 GW Partition 11kg 62/54 60-65 40-45
minutes
EWFA 26162
plasterboard.
(c) TSB3/ASB3 Polyester 61/53 60-65 40-45
CSR 266
(a) Nil 62/54 65-70 35-40
90/90/90 • 2 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 50 GW Partition 11kg 66/58 60-65 35-40
minutes
EWFA 26162
plasterboard.
(c) TSB3/ASB3 Polyester 65/57 60-65 35-40
CSR 267
(a) Nil 63/56 65-70 35-40
120/120/120 • 3 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 50 GW Partition 11kg 68/61 60-65 35-40
minutes
EWFA 26162
plasterboard.
(c) TSB3/ASB3 Polyester 67/60 60-65 35-40
PKA–056
CSR 959
(a) Nil 58/48 65-70 40-45
CSR 339
(a) Nil 57/47 70-75 40-45
• 1 x 10mm GYPROCK
Refer to
SUPACEIL (b) 50 GW Partition 11kg 61/51 65-70 40-45
AS3600 plasterboard.
(c) TSB3/ASB3 Polyester 60/50 65-70 40-45
CSR 340
(a) Nil 59/50 62-66 40-45
• 1 x 10mm GYPROCK
Refer to
SUPERCHEK (b) 50 GW Partition 11kg 63/55 60-62 40-45
AS3600 plasterboard.
(c) TSB3/ASB3 Polyester 62/54 60-62 40-45
CSR 341
(a) Nil 60/51 62-66 40-45
• 1 x 13mm GYPROCK
Refer to
SOUNDCHEK (b) 50 GW Partition 11kg 65/56 60-62 40-45
AS3600 plasterboard.
(c) TSB3/ASB3 Polyester 64/55 60-62 40-45
CSR 342
(a) Nil 61/53 62-66 40-45
PKA–056
CSR 344
(a) Nil 60/52 62-66 40-45
60/60/60 • 2 x 13mm GYPROCK
+RISF 30
FYRCHEK (b) 50 GW Partition 11kg 67/59 55-60 40-45
minutes
EWFA 26162
plasterboard.
(c) TSB3/ASB3 Polyester 66/58 55-60 40-45
CSR 346
(a) Nil 63/55 60-64 40-45
90/90/90 • 2 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 50 GW Partition 11kg 66/58 55-60 40-45
minutes
EWFA 26162
plasterboard.
(c) TSB3/ASB3 Polyester 65/57 55-60 40-45
CSR 347
(a) Nil 64/57 60-62 40-45
120/120/120 • 3 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 50 GW Partition 11kg 68/61 55-60 40-45
minutes
EWFA 26162
plasterboard.
(c) TSB3/ASB3 Polyester 68/61 55-60 40-45
PKA–056
PKA–056
PKA–056
PKA–056
PKA–056
CSR 952
(a) 165 Gold Batts™ 3.0 43/33 41/36 43/37
• 1 x 13mm GYPROCK
–/–/– (b) 215 Gold Batts™ 4.0 44/35 42/37 44/39
Plasterboard CD.
CSR 949
(a) 165 Gold Batts™ 3.0 42/32 40/35 42/36
• 1 x 10mm GYPROCK
–/–/– SUPACEIL (b) 215 Gold Batts™ 4.0 43/34 41/36 43/38
plasterboard.
(c) 120 Soundscreen™ 3.0 42/32 40/35 42/36
CSR 950
(a) 165 Gold Batts™ 3.0 44/35 45/39 46/40
• 1 x 10mm GYPROCK
–/–/– SUPERCHEK (b) 215 Gold Batts™ 4.0 46/37 46/40 48/41
plasterboard.
(c) 120 Soundscreen™ 3.0 44/35 45/39 46/40
CSR 953
(a) 165 Gold Batts™ 3.0 47/38 46/41 48/42
• 1 x 13mm GYPROCK
–/–/– SOUNDCHEK (b) 215 Gold Batts™ 4.0 49/40 47/43 49/44
plasterboard.
(c) 120 Soundscreen™ 3.0 47/38 46/41 48/42
CSR 951
(a) 165 Gold Batts™ 3.0 49/40 50/44 51/45
• 2 x 10mm GYPROCK
–/–/– (b) 215 Gold Batts™ 4.0 51/42 51/45 53/46
SUPERCHEK.
PKA–056
CSR 956
(a) 165 Gold Batts™ 3.0 49/40 47/43 50/44
60/60/60 • 2 x 13mm GYPROCK
+RISF 30
FYRCHEK (b) 215 Gold Batts™ 4.0 51/42 48/44 51/45
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 49/40 47/43 50/44
CSR 871
(a) 165 Gold Batts™ 3.0 51/42 50/45 52/46
90/90/90 • 2 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 215 Gold Batts™ 4.0 52/44 51/45 53/47
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 51/42 50/45 52/46
CSR 955
(a) 165 Gold Batts™ 3.0 54/45 53/48 55/49
120/120/120 • 3 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 215 Gold Batts™ 4.0 55/47 54/49 56/50
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 54/45 53/48 55/49
PKA–056
• 1 x 10mm GYPROCK
–/–/– (b) 215 Gold Batts™ 4.0 45/36 43/38 45/40
Plasterboard CD.
CSR 842
(a) 165 Gold Batts™ 3.0 45/35 43/38 45/39
• 1 x 13mm GYPROCK
–/–/– (b) 215 Gold Batts™ 4.0 46/37 44/39 46/41
Plasterboard CD.
CSR 868
(a) 165 Gold Batts™ 3.0 45/35 43/38 45/39
• 1 x 6mm CeminSeal™
–/–/– (b) 215 Gold Batts™ 4.0 46/37 44/39 46/41
Wallboard.
CSR 863
(a) 165 Gold Batts™ 3.0 46/37 47/41 48/42
• 1 x 10mm GYPROCK
–/–/– SUPERCHEK (b) 215 Gold Batts™ 4.0 48/39 48/42 50/43
plasterboard.
(c) 120 Soundscreen™ 3.0 46/37 47/41 48/42
CSR 864
(a) 165 Gold Batts™ 3.0 49/40 48/43 50/44
• 1 x 13mm GYPROCK
–/–/– SOUNDCHEK (b) 215 Gold Batts™ 4.0 51/42 49/45 51/46
plasterboard.
(c) 120 Soundscreen™ 3.0 49/40 48/43 50/44
CSR 843
(a) 165 Gold Batts™ 3.0 47/37 45/40 47/41
• 2 x 10mm GYPROCK
–/–/– (b) 215 Gold Batts™ 4.0 48/39 46/41 48/43
Plasterboard CD.
PKA–056
• A pitched tiled roof with or without 350g/m2 sarking.
OR
A steel sheet roof minimum 0.42mm with minimum
Bradford Anticon 55 insulation over battens.
• Ceiling Joists or Trusses.
• RONDO Furring channel at 600mm max. centres except
where noted in system table.
• Cavity infill as per system table.
• Ceiling lining as per system table, fixed to furring channel.
CSR 874
(a) 165 Gold Batts™ 3.0 51/42 49/45 52/46
60/60/60 • 2 x 13mm GYPROCK
+RISF 30
FYRCHEK (b) 215 Gold Batts™ 4.0 53/44 50/46 53/47
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 51/42 49/45 52/46
CSR 876
(a) 165 Gold Batts™ 3.0 53/44 52/47 54/48
90/90/90 • 2 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 215 Gold Batts™ 4.0 54/46 53/47 55/49
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 53/44 52/47 54/48
CSR 867
(a) 165 Gold Batts™ 3.0 56/47 55/50 57/51
120/120/120 • 3 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 215 Gold Batts™ 4.0 57/49 56/51 58/52
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 56/47 55/50 57/51
PKA–056
• A pitched tiled roof with or without 350g/m2 sarking.
OR
A steel sheet roof minimum 0.42mm with minimum
Bradford Anticon 55 insulation over battens.
• Ceiling Joists or Trusses.
• RONDO Furring Channel clipped to Gyprock™ Resilient
Mounts.
• Cavity infill as per system table.
• Ceiling lining as per system table, fixed to furring channel.
• 1 x 13mm GYPROCK
–/–/– (b) 215 Gold Batts™ 4.0 48/39 46/41 48/43
Plasterboard CD.
CSR 854
(a) 165 Gold Batts™ 3.0 46/36 44/39 46/40
• 1 x 10mm GYPROCK
–/–/– SUPACEIL (b) 215 Gold Batts™ 4.0 47/38 45/40 47/42
plasterboard.
(c) 120 Soundscreen™ 3.0 46/36 44/39 46/40
CSR 851
(a) 165 Gold Batts™ 3.0 48/39 49/43 50/44
• 1 x 10mm GYPROCK
–/–/– SUPERCHEK (b) 215 Gold Batts™ 4.0 50/41 50/44 52/45
plasterboard.
(c) 120 Soundscreen™ 3.0 48/39 49/43 50/44
CSR 853
(a) 165 Gold Batts™ 3.0 51/42 50/45 52/46
• 1 x 13mm GYPROCK
–/–/– SOUNDCHEK (b) 215 Gold Batts™ 4.0 53/44 51/47 53/48
plasterboard.
(c) 120 Soundscreen™ 3.0 51/42 50/45 52/46
CSR 852
(a) 165 Gold Batts™ 3.0 53/44 54/48 55/49
• 2 x 10mm GYPROCK
–/–/– SUPERCHEK (b) 215 Gold Batts™ 4.0 55/46 55/49 58/50
plasterboard.
(c) 120 Soundscreen™ 3.0 53/44 54/48 55/49
PKA–056
• A pitched tiled roof with or without 350g/m2 sarking.
OR
A steel sheet roof minimum 0.42mm with minimum
Bradford Anticon 55 insulation over battens.
• Ceiling Joists or Trusses.
• RONDO Furring Channel clipped to Gyprock™ Resilient
Mounts. Furring Channel at 600mm max. centres except
where noted in system table.
• Cavity infill as per system table.
• Ceiling lining as per system table, fixed to furring channel.
CSR 856
(a) 165 Gold Batts™ 3.0 53/44 51/47 54/48
60/60/60 • 2 x 13mm GYPROCK
+RISF 30
FYRCHEK (b) 215 Gold Batts™ 4.0 55/46 52/48 55/49
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 53/44 51/47 54/48
CSR 858
(a) 165 Gold Batts™ 3.0 55/46 54/49 56/50
90/90/90 • 2 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 215 Gold Batts™ 4.0 56/48 55/49 57/51
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 55/46 54/49 56/50
CSR 859
(a) 165 Gold Batts™ 3.0 58/49 57/52 59/53
120/120/120 • 3 x 16mm GYPROCK
+RISF 60
FYRCHEK (b) 215 Gold Batts™ 4.0 59/51 58/53 60/54
minutes
EWFA 26162
plasterboard.
(c) 120 Soundscreen™ 3.0 58/49 57/52 59/53
PKA–056
CSR 891
CSR 896
CSR 898
• 1 x 13mm GYPROCK
FYRCHEK
30/30/30 (a) 140 Gold Batts™ 2.5 47/38
plasterboard.
EWFA 26162 • Furring channels at
(b) 120 Soundscreen™ 3.0 47/38
450mm maximum
centres.
CSR 892
CSR 894
PKA–056
CSR 065
CSR 860
CSR 066
CSR 067
CSR 068
CSR 069
PKA–056
CSR 070
• 1 x 13mm GYPROCK
FYRCHEK
(a) 140 Gold Batts™ 2.5 47/38
30/30/30 plasterboard.
EWFA 26162 • Furring channels at
(b) 120 Soundscreen™ 3.0 47/38
450mm maximum
centres.
CSR 071
CSR 073
PKA–056
• A low slope metal roof with Bradford Anticon 55.
• 150mm Timber or Steel Purlins.
• RONDO Furring channel at 600mm max. centres except
where noted in system table.
• Cavity infill as per system table.
• Ceiling lining as per system table, fixed to furring channel.
FRL SYSTeM
CeiLinG LininGS CAViTY inFiLL (Refer to Section A) Rw / Rw+Ctr
Report/Opinion nº
CSR 873
(a) 140 Gold Batts™ 2.5 46/37
• 1 x 13mm GYPROCK
–/–/–
Plasterboard CD.
(b) 120 Soundscreen™ 3.0 46/37
CSR 877
• 1 x 10mm GYPROCK (a) 140 Gold Batts™ 2.5 47/38
–/–/– SUPERCHEK
plasterboard. (b) 120 Soundscreen™ 3.0 47/38
CSR 878
60/60/60 • 2 x 13mm GYPROCK (a) 140 Gold Batts™ 2.5 51/42
+RISF 30
FYRCHEK
minutes
EWFA 26162
plasterboard. (b) 120 Soundscreen™ 3.0 51/42
• 1 x 13mm GYPROCK
CSR 880
FYRCHEK
60/60/60 plasterboard. (a) 140 Gold Batts™ 2.5 52/43
+RISF 60
minutes • 1 x 16mm GYPROCK
EWFA 26162 FYRCHEK (b) 120 Soundscreen™ 3.0 52/43
plasterboard (any
order).
CSR 865
90/90/90 • 2 x 16mm GYPROCK (a) 140 Gold Batts™ 2.5 50/42
+RISF 60
FYRCHEK
minutes
EWFA 26162
plasterboard. (b) 120 Soundscreen™ 3.0 50/42
CSR 866
120/120/120 • 3 x 16mm GYPROCK (a) 140 Gold Batts™ 2.5 52/44
+RISF 60
FYRCHEK
minutes
EWFA 26162
plasterboard. (b) 120 Soundscreen™ 3.0 52/44
PKA–052
FRL SYSTeM
CeiLinG LininGS CAViTY inFiLL (Refer to Section A) Rw / Rw+Ctr
Report/Opinion nº
Above (a) Nil 38/31
60/60/60
from top • 1 x 16mm GYPROCK FYRCHEK.
CSR 981 (b) 50 GW Partition – 11kg/m3 42/33
only below
FAR 2358 • 1 x 10mm GYPROCK Plasterboard CD. (c) 90 Gold Batts™ 2.0 45/36
Above
60/60/60
from top • 2 x 16mm GYPROCK FYRCHEK.
CSR 982 (a) Nil 33/30
only below
FAR 2358 • Nil.
Above
120/120/120
• 2 x 16mm GYPROCK FYRCHEK. (a) Nil 44/37
from top
CSR 983
only below (b) 75 GW Partition – 14kg/m3 50/41
FAR 2358 • 1 x 10mm GYPROCK Plasterboard CD.
Above
90/90/90
from top • 3 x 13mm GYPROCK FYRCHEK.
CSR 986 (a) Nil 36/33
only below
FAR 2358 • Nil.
Above
120/120/120
from top • 3 x 16mm GYPROCK FYRCHEK.
CSR 985 (a) Nil 36/33
only below
FAR 2358 • Nil.
PKA–052
• Ceiling lining as per system table, fixed to framing.
• Steel framing maximum 1.6mm BMT at 600mm maximum
centres.
• Minimum cavity depth 150mm.
• Cavity infill as per system table.
• Ceiling lining as per system table, fixed to framing.
FRL SYSTeM
CeiLinG LininGS CAViTY inFiLL (Refer to Section A) Rw / Rw+Ctr
Report/Opinion nº
Above & below (a) Nil 41/35
60/60/60 CSR 994 • 1 x 16mm GYPROCK FYRCHEK
FAR 2358
plasterboard. (b) 50 GW Partition – 11kg/m3 45/37
90/90/90
from below Above & below (a) Nil 47/41
120/120/120 CSR 992 • 2 x 16mm GYPROCK FYRCHEK
from above plasterboard. (b) 50 GW Partition – 11kg/m3 51/43
FAR 2358
Above
• 2 x 16mm GYPROCK FYRCHEK (a) Nil 49/43
120/120/120 CSR 993 plasterboard.
FAR 2358 below
(b) 50 GW Partition – 11kg/m3 53/45
• 3 x 16mm GYPROCK FYRCHEK
plasterboard.
PKA–052
FRL SYSTEM
CEILING LININGS CAVITY INFILL Rw / Rw+Ctr Ln,w+CI
Report/Opinion Nº
Hebel 1600
240/240/240
from above
① ②
FCO 1303 • Nil (a) Nil 33/30 45
–/–/–
from below
Hebel 1635
240/240/240
from above
FCO 1303 • 3 x 16mm GYPROCK
(a) 75 Gold Batts™ 1.5 58/54 34
120/120/120 FYRCHEK plasterboard
from below
EWFA 26162
Refer to
acoustic ceiling tiles. Fricker Top Hat Cross
Runner every third tile
CSR Fricker
OR
• Fricker Easy Access System™ with appropriate acoustic
ceiling tiles
OR
Fricker Ceiling Tile
System CSR 890 with acoustic Material & Edge CAC Ceiling System
Colour NRC LR
ceiling tile options as per below Thickness Details (db) TWE TWA OWE FC WP
SQ White .70-.80 35 89% •
Mineral Fibre
USG Mars ClimaPlus™ SLT White .75-.85 35 89% •
19mm
FLB White .70-.80 35 89% •
Mineral Fibre SQ White .50-.60 33-35 84% •
USG Radar ClimaPlus™
15mm SLT White .50-.60 33-35 84% •
Mineral Fibre SQ White .55 33-35 84% •
USG Impressions ClimaPlus™
15mm SLT White .55 33-35 84% •
Mineral Fibre SQ White .50 30-35 87% •
USG Olympia Micro ClimaPlus™
15mm SLT White .50 30-35 87% •
Mineral Fibre
USG Millennia ClimaPlus™ SQ White .70 35 87% •
19mm
SQ White .55-.60 36-40 87% •
Mineral Fibre
Daiken Exceltone New NDF TB White .55-.60 36-40 87% •
15mm
AK White .55-.60 36-40 87% •
SQ White .55-.60 36-40 87% •
Mineral Fibre
Daiken Exceltone Travertine Delica TB White .55-.60 36-40 87% •
15mm
AK White .55-.60 36-40 87% •
Mineral Fibre SQ White .70 33-39 88% •
Fricker 610-A
15mm SBK White .70 33-39 88% •
Mineral Fibre SQ White .55 33-39 88% •
Fricker 611-A
15mm SBK White .55 33-39 88% •
Mineral Fibre SQ White .70 33-39 88% •
Fricker 616-A
15mm SBK White .70 33-39 88% •
notes:
edge Details Ceiling System
SQ = Square, TWE = Two Way Exposed
SLT = Shadowline Tapered TWA = Two Way Access
FLB = Fineline Bevel OWE = One Way Exposed
TB = Tegular FC = Fully Concealed
SBK = Kerfed, Bevelled and Cut Back WP = Wall Panel
AK = Shiplap NRC = Noise Reductionj Coefficient
AK (F) = Tongue & Groove direct fix CAC = Ceiling Attenuation Class
LR = Light Reflectance
Custom tile options, metal pan perforations and module sizes are available. Please contact your local CSR Fricker Comprador sales office on
1300 FRICKER (1300 374 253) for further information or detailed technical data sheets on individual products.
Refer to
acoustic ceiling tiles. Fricker Top Hat Cross
Runner every third tile
CSR Fricker
OR
• Fricker Easy Access System™ with appropriate acoustic
ceiling tiles
OR
Fricker Ceiling Tile
System CSR 890 with acoustic Material & Edge CAC Ceiling System
Colour NRC LR
ceiling tile options as per below Thickness Details (db) TWE TWA OWE FC WP
Ecophon Focus A SQ White Frost .85 21 85% •
Ecophon Focus Ds Glasswool AK White Frost .80 25 85% •
Ecophon Focus E 20mm TB White Frost .80 23 85% •
Ecophon Focus F AK (F) White Frost .75 n/a 85% •
Ecophon Master A Glasswool SQ White Frost .95 30 85% •
Ecophon Master F 40mm AK (F) White Frost .95 n/a 85% •
Glasswool
Ecophon Solo S SQ White Frost n/a n/a 85% •
40mm
Glasswool
Ecophon Hygiene Meditec SQ White Frost .80 n/a 84% •
20mm
Glasswool
Ecophone Hygiene Performance A SQ White Frost .85-.95 n/a 84% •
20mm
Glasswool
Ecophon Wall Panel A SQ Turquoise .95-1.0 n/a 49% •
40mm
SQ Brown 610 .95-1.0 n/a 14% •
Glasswool
Ecophon Wall Panel C SQ Cerise 810 .95-1.0 n/a 16% •
40mm
SQ Med Grey 920 .95-1.0 n/a 34% •
Perforated Plasterboard (with Plasterboard
SQ - .49 n/a n/a •
Bradford Anticon 55, foil face up) 13mm
Perforated Metal Pan (1820 perf SQ - .70 13 68% • • • •
Steel 0.7mm
with black fleece backing) TB - .70 13 68% •
Perforated Metal Pan (1820 perf SQ - .85 30 68% • • • •
Steel 0.7mm
with 18mm x 80kg/m³ insulation) TB - .85 30 68% •
notes:
edge Details Ceiling System
SQ = Square, TWE = Two Way Exposed
SLT = Shadowline Tapered TWA = Two Way Access
FLB = Fineline Bevel OWE = One Way Exposed
TB = Tegular FC = Fully Concealed
SBK = Kerfed, Bevelled and Cut Back WP = Wall Panel
AK = Shiplap NRC = Noise Reductionj Coefficient
AK (F) = Tongue & Groove direct fix CAC = Ceiling Attenuation Class
LR = Light Reflectance
Custom tile options, metal pan perforations and module sizes are available. Please contact your local CSR Fricker Comprador sales office on
1300 FRICKER (1300 374 253) for further information or detailed technical data sheets on individual products.
FiG e4: inSTALLATiOn DeTAiL – TWO LAYeR – ADHeSiVe & SCReW FiXinG
For additional information, refer to GYP570, Gyprock™ Ceiling Systems Installation Guide. nOn-FiRe RATeD
Timber or Steel Framing Fixing Specifications
at 600mm max. centres 1st Layer Refer to Section ‘A’
Screws Gyprock Stud Adhesive
2nd Layer
Fasteners Refer to Section ‘A’
Adhesive Gyprock Stud Adhesive
200mm max. 1st Layer Fixing & Spacing
Body Screw fix to each
Sheet framing member at
230mm 300mm max. centres
max. Width
900mm 4 screws equally spaced
1200mm 5 screws equally spaced
1350mm 6 screws equally spaced
300mm Butt Joints Screw fix at 200mm
max. on framing max. centres
Sheet Screw fix at 300mm
Ends & max. centres
Openings
300mm max. 2nd Layer Fixing & Spacing
for cornice finish 200mm min. Body Adhesive Daubs at
150mm max. 230mm max. centres
for set finish 230mm max. Sheet and 200mm min. from
Width fastener points
200mm min.
Adhesive 900mm 2 daubs
Daubs 1200mm 4 daubs
1350mm 4 daubs
Recessed Screw fix at each
Temporary block Joints frame member
For Levels of Finish 0 to Centreline Screw fix at each frame
3, Butt Joint on member of Sheet member
and screw fix at 200mm
max. centres Butt Joints Screw fix at 200mm
on framing max. centres
For Level of Finish 4 and 5,
where Butt Jointing is Butt Joints Laminating screws at
unavoidable, joint centrally Begin 1st layer between 200mm max. centres
between members, fix with Butt Joints in 1st with a half framing
laminating screws at 200mm layer may be on width sheet Openings Screws at 200mm max.
same member centres
Offset Butt Joints in 2nd
layer 600mm min. in Begin 2nd layer with a full width sheet Sheet For cornice finish, screw
adjoining sheets and and offset recessed joint 300mm Ends fix at 300mm max. cts.
between layers minimum between 1st and 2nd layer For set finish, screw fix
at 150mm max. centres
nOn-FiRe RATeD
Practical
minimum 150mm Fixing Specifications
Structural support Screws Refer to Section ‘A’
of timber, steel or
concrete Location Fixing & Spacing
Recessed Screw fix to each frame
Joints at 10 to 16mm from
& Body sheet edges and at
Sheet 300mm max. centres
Width between.
900mm 4 screws equally spaced
Suspended Grid at 1200mm 5 screws equally spaced
600mm maximum 1350mm 6 screws equally spaced
centres Butt Joints Joint within 50mm of
between centre line between
300mm max. for cornice finish 300mm framing framing. Back-block
150mm max. for set finish max. and fix with laminating
screws at 200mm max.
centres.
Butt Joints Screw fix at 200mm
on framing max. centres
Openings Screw fix at 200mm
max. centres
200mm max.
Sheet For cornice finish, screw
Ends fix at 300mm max. cts.
For set finish, screw fix
For Level of Finish 4 and at 150mm max. centres
5, where Butt Jointing is
unavoidable, support
plasterboard with additional
framing
200mm max.
Where permitted, Butt Joint
on member and screw fix at
200mm max. centres
(Levels of Finish 0 to 3)
nOn-FiRe RATeD
25mm GYPROCK screws Fixing Specifications
at 300mm centres
Screws Refer to Section ‘A’
Location Fixing & Spacing
At butt joints, screw at
200mm centres opposed Recessed Screw fix to each frame
Joints & at 10 to 16mm from
Body sheet edges and at
300mm max. centres
between
Butt Joints Screw fix at 200mm
on framing max. centres
Sheet Screw fix at 200mm
Ends max. centres
Openings Screw fix at 200mm
max. centres
150mm max.
Perimeter track/angle
required in fire rated Stagger butt joints
ceiling systems (refer in adjacent sheets
to Perimeter Details) and offset fasteners
FiG e8: inSTALLATiOn DeTAiL – One OR TWO LAYeR – nAiL OR SCReW FiXinG –
FOR SYSTeMS WiTH LininG ABOVe OR BeLOW FRAMinG
For additional information, refer to GYP570, Gyprock™ Ceiling Systems Installation Guide.
Refer to system FiRe RATeD
specifications
Fixing Specifications
Fasteners Refer to Section ‘A’
Location Fixing & Spacing
Body of Fasten to each framing
Sheet member at 25mm from
1st & 2nd sheet edges and at
Layer 200mm max. centres
40mm 200mm Butt Butt Joint on framing
max. Joints and fasten at 40mm
25mm 1st Layer from sheet edges,
150mm 15mm from sheet ends
max. and at 150mm max.
40mm centres (offset fasteners)
40mm 40mm
Butt Butt Joint within 50mm
15mm Joints of centre line between
15mm 2rd layer framing and fix to 1st
min. layer with Laminating
25mm 200mm max.
Screws at 25mm from
Butt Joints in 2nd sheet edges, 40mm
layer must be centred from sheet ends and at
between framing members 200mm max. centres
and fixed with laminating Sheet Fasten at 40mm from
screws sheet edges, 15mm min.
Ends
from sheet ends and at
Butt Joints must be offset 150mm max. centres
600mm minimum in adjoining Openings Fasten at 15mm min.
sheets and between layers from sheet edges and at
150mm max. centres
Perimeter track/angle
required in fire rated
ceiling systems (refer
to Junction Details)
Begin 1st
Begin 2nd layer with full width sheet layer with half
Stagger butt joints width sheet
and offset recessed joint 300mm in adjacent sheets
minimum between 1st and 2nd layer and offset fasteners
Perimeter track/angle
required in fire rated
ceiling systems (refer Begin 1st layer with 400mm width sheet
to Perimeter Framing Begin 2nd layer with 800mm width sheet
& Caulking) Begin 3rd layer with full width sheet
FiRe RATeD
150mm Bottom Layers
max. 150mm Fixing Specifications
200mm max.
max. Fasteners Refer to Section ‘A’
Sheet Refer to 1, 2 and 3 layer
fixing installation details
SUITABLE FOR:
1200mm max.
between suspension
points
Main
300mm Tee
600mm
300mm
GYPROCK plasterboard
or accoustic tile
1200mm
600mm
Main Tee
Duo 1/Duo 3
Cross Tee
Duo 4
FiG e12: TYPiCAL inSTALLATiOn DeTAiL – FRiCKeR eASY ACCeSS SYSTeM™ WiTH ACOuSTiC CeiLinG TiLeS
Fricker Suspension Clip
and 5mm hanging rod
staggered at 1200mm
centres
Modules of
1000 x 1000mm to
1500 x 1500mm
Tiles can be
rotated 90° in
modules
Contents
Introduction F2
Fire Resistance F2
Acoustic Performance F2
Components F3
System Specifications
Fire Resistance Penetrations for downlights must be neat and tight to the
fitting. No additional sealing is required. Ensure insulation
material is kept clear of fittings and that transformers are
The services systems in this section have no Fire Resistance
supported separately from the plasterboard lining.
Level. They may be used in conjunction with fire rated
wall and ceiling systems selected from elsewhere in this The installation of exhaust grilles and ducting may reduce the
manual. performance of the systems. The building designer should
contact the exhaust system manufacturer for performance
details.
Similarly, access panels might be required. Contact the panel
manufacturer for suitable products.
Lagging of pipes or ducts is specified in some services
systems. Lagging must provide complete coverage for the
full extent of the pipe or duct.
Bradford Glasswool
batts
Maximum
number of Locally remove
downlights as insulation
per system
specification
FIG F2: InsulaTIon CompRessIon FIG F3: FIRe RaTed ReGal haloGen downlIGhT
75mm 25mm
Insulation
Service
lagging
pKa–058
maximum nº
Insulation
system nº linings pipe lagging downlights Rw + Ctr
(Refer to System Specification)
per 5m2
CsR ss44
(a) 75 GW Partition – 11kg Nil 5 26
• 1 x 10mm GYPROCK
AQUACHEK plasterboard.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 40
CsR ss45
(a) 75 GW Partition – 11kg Nil 0 30
• 1 x 6mm CeminSeal™
Wallboard.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 42
CsR ss01
(a) Nil Nil 0 25
• 1 x 10mm GYPROCK
SUPERCHEK
plasterboard. (b) 75 GW Partition – 11kg Nil 5 28
CsR ss02
(a) 75 GW Partition – 11kg Nil 5 28
• 1 x 13mm GYPROCK
plasterboard CD.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 42
CsR ss04
(a) Nil Nil 0 26
• 2 x 10mm GYPROCK
plasterboard CD.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 43
CsR ss46
(a) Nil Nil 0 31
• 2 x 16mm GYPROCK
FYRCHEK plasterboard.
(b) Nil Acoustilag™ 45 0 45
pKa–058
maximum nº
Insulation
system nº linings pipe lagging downlights Rw + Ctr
(Refer to System Specification)
per 5m2
CsR ss08
(a) 75 GW Partition – 11kg Nil 0 25
• 1 x 10mm GYPROCK
AQUACHEK plasterboard.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 38
CsR ss10
(a) 75 GW Partition – 11kg Nil 5 27
• 1 x 10mm GYPROCK
SUPERCHEK
plasterboard.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 41
CsR ss11
(a) 75 GW Partition – 11kg Nil 5 26
• 1 x 13mm GYPROCK
(b) Nil Acoustilag™ 45 0 36
plasterboard CD.
CsR ss12
(a) Nil Nil 0 27
• 1 x 13mm GYPROCK
SOUNDCHEK (b) Nil Acoustilag™ 45 0 41
plasterboard.
(c) 75 GW Partition – 11kg Acoustilag™ 45 5 43
CsR ss13
Nil Nil 0 25
• 2 x 10mm GYPROCK
plasterboard CD.
75 GW Partition – 11kg/90 Gold Batts™ Acoustilag™ 45 5 42
CsR ss17
Nil Nil 0 31
• 2 x 16mm GYPROCK
FYRCHEK plasterboard.
75 GW Partition – 11kg/90 Gold Batts™ Acoustilag™ 45 5 44
pKa–058
maximum nº
Insulation
system nº linings pipe lagging downlights Rw
(Refer to System Specification)
per 5m2
CsR ss20
(a) 75 GW Partition – 11kg Nil 3 30
• 1 x 10mm GYPROCK
AQUACHEK plasterboard.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 50
CsR ss18
(a) 75 GW Partition – 11kg Nil 5 31
• 1 x 6mm CeminSeal™
Wallboard.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 52
CsR ss21
(a) 75 GW Partition – 11kg Nil 5 31
• 1 x 10mm GYPROCK
SUPERCHEK
plasterboard. (b) 75 GW Partition – 11kg Acoustilag™ 45 5 52
CsR ss22
(a) 75 GW Partition – 11kg Nil 5 31
• 1 x 13mm GYPROCK
plasterboard CD.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 52
CsR ss23
(a) Nil Nil 0 31
• 1 x 13mm GYPROCK
SOUNDCHEK
plasterboard. (b) 75 GW Partition – 11kg Acoustilag™ 45 5 54
CsR ss19
(a) Nil Nil 0 34
• 2 x 16mm GYPROCK
FYRCHEK plasterboard.
(b) 75 GW Partition – 11kg Nil 0 40
pKa–058
maximum nº
Insulation
system nº linings pipe lagging downlights Rw
(Refer to System Specification)
per 5m2
CsR ss30
(a) Nil Nil 0 22
• 1 x 10mm GYPROCK
AQUACHEK plasterboard.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 48
CsR ss38
(a) 75 GW Partition – 11kg Nil 5 30
• 1 x 6mm CeminSeal™
Wallboard.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 51
CsR ss31
(a) 75 GW Partition – 11kg Nil 5 30
• 1 x 10mm GYPROCK
SUPERCHEK
plasterboard. (b) 75 GW Partition – 11kg Acoustilag™ 45 5 51
CsR ss32
(a) 75 GW Partition – 11kg Nil 3 30
• 1 x 13mm GYPROCK
plasterboard CD.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 50
CsR ss34
(a) 75 GW Partition – 11kg Nil 5 31
• 2 x 10mm GYPROCK
plasterboard CD.
(b) 75 GW Partition – 11kg Acoustilag™ 45 5 52
CsR ss39
(a) Nil Nil 0 34
• 2 x 16mm GYPROCK
FYRCHEK plasterboard.
(b) Nil Acoustilag™ 45 0 55
pKa–052
Service Shaft or Ceiling
• Inner layer lining (as per system table) direct fixed to timber
or steel framing, to encase services.
maximum nº
Insulation
system nº linings downlights Rw/Rw+Ctr
(Refer to System Specification)
per 5m2
CsR ss40
Inner Layer (a) 50 GW Partition – 11kg Nil 46/37
CsR ss41
Inner Layer (a) 50 GW Partition – 11kg Nil 49/40
• 2 x 13mm GYPROCK FYRCHEK.
Outer Layer/CeILIng
• 1 x 10mm GYPROCK Plasterboard CD. (b) TSB4 Polyester Nil 49/42
CsR ss42
Inner Layer (a) 50 GW Partition – 11kg Nil 53/44
• 2 x 13mm GYPROCK FYRCHEK.
Outer Layer/CeILIng
• 2 x 13mm GYPROCK Plasterboard CD. (b) TSB4 Polyester Nil 53/46
1 x 13mm
GYPROCK
Plasterboard CD
Waste Pipe
1 x 10mm
GYPROCK
Plasterboard CD
each side of steel
studs 1 x 13mm GYPROCK
Plasterboard CD
Habitable room Non-habitable room
Waste
Pipe
75mm Bradford
Glasswool
Partition Batts -
11kg/m3 Acoustilag 45
Timber or
steel framing
1 x 13mm
GYPROCK
Plasterboard CD
each side of steel 1 x 13mm GYPROCK
studs Plasterboard CD
600mm min.
Habitable room Non-habitable room
Contents
Introduction G2
PKA–A031
Steel angle to Rondo DUO Two-way
support ceiling grid Steel Grid Ceiling
• Floor or roof structure. 100mm System
System insulation min System insulation
• 200mm minimum cavity.
• 50mm Bradford Glasswool Partition batts –
11kg/m3 to extent specified in table.
• Ceiling lining as per system table.
• Wall with required sound rating. GYPROCK
Panel
Ceiling
System
EXTENT OF INSULATION
1200mm each side
SYSTEM Nº CEILING LININGS Nil Entire Ceiling
of the wall
Rw
(a) Gyprock plasterboard panel 10mm 38 44 45
(ef) USG Radar, Impressions, Olympia Micro 15mm 30-35 30-36 30-36
PKA–A031
100mm
• Floor or roof structure. System insulation min System insulation
(d) USG Radar, Impressions, Olympia Micro 15mm 30-35 30-36 30-36
PKA–A031
600mm
PKA–A031
600mm
Ceiling
framing
• Floor or roof structure.
• 200mm minimum cavity.
• 600mm wide barrier of Bradford Glasswool
Partition batts – 11kg/m3, compressed 30%. Tape and
GYPROCK
• Ceiling lining as per system table. plasterboard set or
ceiling system cornice
finish
• Wall with required sound rating, to underside continuous
over wall
of ceiling.
Bradford
Glasswood 11kg/m3
– compressed 30%
PKA–A031
50mm Glasswool
seal continuous over 10mm GYPROCK
wall, held in place plasterboard min.
with track or angle continuous over wall
and fixed to soffit
• Floor or roof structure.
• 200mm minimum cavity.
• 10mm GYPROCK Plasterboard CD barrier
with 50mm Glasswool seal.
• Ceiling lining as per system table. GYPROCK Panel Finish Bead as
Ceiling System in required
• Wall with required sound rating, to underside Rondo DUO
of ceiling. Two-way Steel Grid Fix track to ceiling
frame with Rondo
Screw fix ceiling Nº704
tile to wall track
Continuous bead of
CSR Gyprock
Wall with required Sealant above wall
sound rating track
PKA–A031
50mm Glasswool
seal continuous over 10mm GYPROCK
wall, held in place plasterboard min.
with track or angle continuous over wall
and fixed to soffit
• Floor or roof structure.
• 200mm minimum cavity. Ceiling frame
PKA–A031
Bradford Wavebar Quadzero
(4.0kg/m2) continuous over
wall and fixed to soffit 50mm Glasswool
Blanket continuous
• Floor or roof structure. 300mm min. over wall
PKA–A031
Bradford Wavebar Quadzero
(4.0kg/m2) continuous over 50mm Glasswool
wall and fixed to soffit Blanket continuous
• Floor or roof structure. 300mm min. over wall
50mm Bradford
Partition batts
11kg/m3 1200mm
each side of wall
PKA–A031
PKA–A031
Sheet metal or
tiled roof
• Roof structure.
• Bradford Rockwool insulation between
Roof framing with
battens. min. 200mm cavity
Bradford Gold
• 200mm minimum average cavity height. batts R2.5
• Bradford Gold Batts R2.5.
• Ceiling lining as per system table fixed to
framing.
• Wall with required sound rating. Masonry GYPROCK
plasterboard ceiling
wall 110mm min.. thickness, extending to (no acoustically Tape and set or
underside of roof battens. untreated lights,vents cornice finish
or similar penetrations)
Wall system with
Masonry wall min. required rating
110mm thick
PKA–A031
PKA–A031
• Roof structure.
• 500mm minimum average cavity height.
• Bradford Gold Batts R1.5.
• Ceiling lining as per system table fixed to framing.
• CSR Party Wall system with required sound rating.
Central barrier extending to underside of roof battens.
20-40mm gap
each side of wall
System insulation
• Timber framed floor/ceiling.
• 75mm Bradford Gold Batts™ R1.5 in floor/
ceiling system.
• Ceiling lining, material and fixing as per
system table.
• Double stud wall with required sound rating,
Continuously
above and below floor/ceiling. fill gap with
GYPROCK
plasterboard ceiling Gyprock
system direct fixed to sealant
joists or to furring/batten
Tape and set or
Wall with required cornice finish
sound rating
SYSTEM Nº Rw / Rw+Ctr
CSR FP60 60/55
Continuously
• Timber frame floor with separate joists and fill gap with
Seal skirting with 3mm
Gyprock
discontinuous flooring. sealant polyethylene tape
Discontinuous
flooring
SYSTEM Nº Rw / Rw+Ctr
CSR FP61 48/42
Continuously
• Timber framed floor with common joists and fill gap with
Seal skirting with 3mm
Gyprock
discontinuous flooring. sealant polyethylene
y tape
SYSTEM Nº Rw / Rw+Ctr
CSR FP62 45/39
Continuously
• Timber frame floor with common joists and fill gap with
Gyprock
continuous flooring. sealant
• Double stud wall with required sound rating.
SYSTEM Nº Rw / Rw+Ctr
CSR FP63 45/39
PKA–A031
Stud
Tape and
Intersecting wall with set corners
required sound rating
GYPROCK
Steel Angle (75 x 75 x plasterboard as
0.7mm BMT) fixed to per system table
stud with panhead screw
at 600mm max. cts
CSR Gyprock
Staggered Studs
and Clips
10mm
Fix end stud to masonry nom. gap
at 500mm maximum from
vertical centres masonry
GYPROCK
plasterboard as to lining
per system table
GYPROCK
plasterboard as
per system table
Sealant
PKA–A031
Finish corners
as required
Intersecting wall with
required sound rating
PKA–A031
Wall system insulation
Dampcourse
Tape and
set corners
BARRIER
SYSTEM Nº WALL LININGS Nil 6mm Cemintel™ Wallboard
Rw / Rw+Ctr
(a) 1 x 10mm GYPROCK Plasterboard CD. 39/30 59/50
Contents
Junctions
Penetrations
Service Penetrations
Acoustic & Fire Performance Z17 – Z18
6 – 10mm
100mm max. clearance to
to first fastener GYPROCK
(Do not fix plasterboard
through track) RONDO P50 or P60
Shadowline Stopping
Fill gap with CSR Bead (finish as
Gyprock Sealant for required)
acoustic integrity
Stud Fix wall sheets at 10
6mm to15mm below head NOTE: This method of
NOTE: Junction may be clear Track section with track flanges Stud construction is not
finished square, with of 32mm flange fastened recommended for studs
stopping bead or with soffit to soffit at 600mm adjacent to windows or
cornice. Do not rigidly centres max. doors or studs carrying
fix cornice to walls loads greater than
where friction joints are 0.25kPa.
used
FIG Z002: DEFLECTION HEAD FIG Z005: HEAD FOR SUSPENDED CEILING
20mm gap
100mm max.
(do not fix Fix cornice to Furring Channel in
through track) ceiling only with normal setout position
Gyprock Cornice Finish as required
Cement
NOTE: Stopping bead
or cornice finish as Flexible Mastic
required. Do not rigidly Fix wall sheets at 10 Fix Head Track to Furring
fix cornice to walls Deflection Head Track to15mm below head Channel at 600mm max.
where friction joints are fastened at 600mm track flanges centres
used Stud centres max. Where wall runs
Stud perpendicular to furring
channel fix track to furring
at each intersection
FIG Z003: HEAD USING ALUMINIUM HEAD TRACK FIG Z006: WALL BASE DETAIL
STEEL STUD WALL SYSTEM
Fix extruded track at
Furring each furring channel
Channel
Tape and
GYPROCK set or Finish Bead as
cornice GYPROCK Panel
plasterboard Ceiling System required
ceiling system finish
continuous over
continuous wall in Rondo
over wall Continuous bead of
DUO Two-way CSR Gyprock
Steel Grid Sealant or a closed
cell foam tape
above wall track
FIG Z008: WALL/CEILING JUNCTION – PLASTERBOARD FIG Z011: WALL/CEILING JUNCTION – PANEL LINING
LINING
GYPROCK
plasterboard GYPROCK Panel
ceiling Tape and set or Ceiling System
cornice finish
FIG Z009: WALL/CEILING JUNCTION – PLASTERBOARD FIG Z012: WALL/CEILING JUNCTION – PANEL LINING
LINING
50mm Bradford
Partition batts
11kg/m3 1200mm
each side of wall
GYPROCK
plasterboard ceiling Tape and set or 50mm Bradford
GYPROCK panel Partition batts
system cornice finish or ceiling system
shadowline bead 1200mm each
side of wall
Wall system with
required rating Wall system with
required rating
10mm GYPROCK
Single AQUACHEK or
or FYRCHEK MR
double
stud 1 or 2 layers of GYPROCK
wall FYRCHEK MR
(minimum 1 x 13mm
CSR Gyprock®
Staggered Stud Clip Angle Flashing
Ceramic Tiles
Nogging for
plasterboard fixing
FIG Z014: STAGGERED STUD BASE – WITH RONDO
Flashing Tape
P140 SPACER (HEAD SIMILAR) (25mm min.)
Flexible Sealant
Screw fix
J-track to
stud 6mm
Preformed
Shower Base
Mortar Bed
Timber Stud
Plasterboard lining not shown
6mm
Plasterboard lining not shown
(minimum 1 x 13mm
Bath
Approved Flashing
when required by
building regulations
Support Batten
Masking Tape fixed to framing
Mortar Bed
FIG Z018: FRICTION FIT HEAD FIG Z021: HEAD/BASE – STUDS LINED ONE SIDE ONLY
(Maintains the FRL of the wall system in which it is installed).
Track section with
Continuously fill gap 32mm flange fastened
with CSR Gyprock to ceiling at 600mm
Fire Mastic maximum centres
Furring Channel
over wall Suspended Ceiling
Top Cross Rail
100mm max. to 20mm clearance
first fastener. Do to stud and
not fix through GYPROCK
head track plasterboard
Continuously fill gap
with CSR Gyprock
Fire Mastic to 13mm
NOTE: Stopping bead minimum depth 10mm Gap 6mm Gap
or cornice finish as
required. Do not rigidly Deflection Head Track Gyprock Fire Tape and set if
fix cornice to walls fastened to ceiling at Mastic required
where friction joints Stud 600mm maximum
are used centres Rondo P50
1, 2 or 3 layers
GYPROCK GYPROCK
FYRCHEK FYRCHEK
plasterboard 2 or 3 layers plasterboard
1, 2 or 3 layers GYPROCK Stud
FYRCHEK
plasterboard
GYPROCK
Staggered
FIG Z025: RECESSED SKIRTING DETAIL stud clip
FRL 120/120/120
75mm max. to Continuously fill gap
first fastener. with CSR Gyprock
Fire Mastic
GYPROCK
plasterboard
FIG Z028: CORNER DETAIL PLASTERBOARD WALL FIG Z030: WALL END DETAIL PLASTERBOARD WALL
Track
Track
m
than 25°
m
0m
10
Metal track
fixings
Set corner with
GYPROCK external angle
Fix at 600mm FYRCHEK
max. centres bead and cement Set corner with
plasterboard
along track internal angle
bead and cement
Track
Track
Metal track
fixings
GYPROCK
FYRCHEK
plasterboard
CSR Gyprock
Staggered Studs
and Clips
Finish corners
as required
Intersecting wall with
required sound rating
Additional stud to
form control joint Tracks discontinuous Additional stud to
RONDO P35 at control joint form control joint
Control Joint Stud in
normal Cemintel™
position Wallboard 20mm min.
2 x 13mm GYPROCK
Finish surface
15-20mm FYRCHEK plasterboard
as per external angles
Finish surface Backing Rod
as per external angles 15-20mm – non fire rated
gap 22mm dia. for
acoustic integrity FIG Z041: CONTROL JOINT FOR COMPOSITE WALL
SYSTEMS – STEEL OR TIMBER STUD FRAME
(Maintains FRL of the wall system in which it is installed).
FIG Z038: CONTROL JOINT AT INTERSECTION OF
MASONRY AND STEEL STUD WALL
Furring Channel
FIG Z043: CONTROL JOINT PARALLEL TO STEEL FIG Z046: CONTROL JOINT PERPENDICULAR TO
FRAMING – 2 LAYERS STEEL FRAMING – 2 LAYERS
(Maintains FRL of the ceiling system in which it is installed). (Maintains FRL of the ceiling system in which it is installed).
Continuous back-block of Continuously fill gap Back-block between furring Continuously fill gap
GYPROCK FYRCHEK same with CSR Gyprock® channel with GYPROCK with CSR Gyprock®
thickness as ceiling sheet Fire Mastic to depth FYRCHEK same thickness Fire Mastic to depth
Fix one side of back-block of first layer minimum as ceiling sheet of first layer minimum
with laminating screws at Fix one side of back-block
600mm max. centres or with laminating screws at
plaster based adhesive 600mm max. centres or Furring Channel
60 to 70mm plaster based adhesive Joiner Nº138
Furring
Channel 200mm min.
Furring Channel
FIG Z044: CONTROL JOINT PARALLEL TO STEEL FIG Z047: CONTROL JOINT PERPENDICULAR TO
FRAMING – 3 LAYERS STEEL FRAMING – 3 LAYERS
(Maintains FRL of the ceiling system in which it is installed). (Maintains FRL of the ceiling system in which it is installed).
RONDO P35 1st and 2nd layers of 2nd and 3rd layers of
GYPROCK FYRCHEK RONDO P35
Control Joint Control Joint GYPROCK FYRCHEK
15 to 20mm gap plasterboard fixed to 15 to 20mm gap plasterboard fixed with
with set finish with set finish
furring at 200mm max. laminating screws to
3rd layer of GYPROCK centres layer above at 200mm
FYRCHEK plasterboard max. centres
fixed with laminating screws
at 200mm max. centres
FIG Z049: CONTROL JOINT PARALLEL TO TIMBER FIG Z052: CONTROL JOINT PERPENDICULAR TO
FRAMING – 2 LAYERS TIMBER FRAMING – 2 LAYERS
(Maintains FRL of the ceiling system in which it is installed). (Maintains FRL of the ceiling system in which it is installed).
Back-block between trimmers Continuously fill gap
Back-block between trimmers Continuously fill gap with GYPROCK FYRCHEK same with CSR Gyprock®
with GYPROCK FYRCHEK same with CSR Gyprock® thickness as ceiling sheet Fire Mastic to depth
thickness as ceiling sheet Fire Mastic to depth of first layer minimum
Laminating screws at of first layer minimum
Laminating screws at
200mm max. centres 200mm max. centres
Trimmers at 450mm
max. centres
Joist
300mm min.
Joist Joist
200mm min. 200mm min.
GYPROCK GYPROCK
RONDO P35 FYRCHEK
Control Joint FYRCHEK
15 to 20mm gap plasterboard 15 to 20mm gap plasterboard
with set finish
RONDO P35
Laminating screws at Control Joint Laminating screws at
200mm max. centres with set finish 200mm max. centres
FIG Z050 CONTROL JOINT PARALLEL TO TIMBER FIG Z053: CONTROL JOINT PERPENDICULAR TO
FRAMING – 3 LAYERS TIMBER FRAMING – 3 LAYERS
(Maintains FRL of the ceiling system in which it is installed). (Maintains FRL of the ceiling system in which it is installed).
Back-block between trimmers Continuously fill gap Back-block between trimmers Continuously fill gap with CSR
with GYPROCK FYRCHEK same with CSR Gyprock® with GYPROCK FYRCHEK same Gyprock® Fire Mastic to depth
thickness as ceiling sheet Fire Mastic to depth thickness as ceiling sheet of one layer minimum
of first layer minimum
Fix back-block to ceiling sheet Fix back-block to ceiling sheet
with plaster based adhesive with plaster based adhesive
or laminating screws Trimmers at 450mm or laminating screws
max. centres
300mm min.
Joist Joist Joist
200mm min. 200mm min.
Step 1: Step 2:
Choose a suitable Choose a suitable
ceiling perimeter perimeter caulking
framing detail. detail.
Refer to Refer to
FIG Z101 FIG Z140
to to
FIG Z130 FIG Z147
Ceiling Joist
Angle may be
required as backing
1 or 2 layers of for caulking
GYPROCK FYRCHEK Packer to suit 1 or 2 layers of
GYPROCK FYRCHEK
Rondo Wall Track fixed at
Refer to FIG Z100 Non fire 600mm max. centres
rated or Blocking to suit FRL. Refer to 'National
lower Association of Forest Industries Ltd'
NOTE: Caulking of the rated publication 'MRTFC'
ceiling perimeter may timber
be necessary before wall
fixing wall linings GYPROCK system GYPROCK
Plasterboard Plasterboard
Ceiling Joist
1, 2 or 3 layers of
GYPROCK FYRCHEK 1, 2 or 3 layers of
Rondo Wall Track fixed at GYPROCK FYRCHEK
Rondo Wall Track fixed at
600mm max. centres with 600mm max. centres with
metal fasteners metal fasteners
Fire rated
wall system
Refer to FIG Z100
600mm max.
1, 2 or 3 layers of
GYPROCK FYRCHEK 1, 2 or 3 layers of
Steel Track fixed at GYPROCK FYRCHEK
600mm max. centres Steel Angle or Track fixed
with metal fasteners at 600mm max. centres
with metal fasteners
1, 2 or 3 layers of
GYPROCK FYRCHEK 1, 2 or 3 layers of
GYPROCK FYRCHEK
Steel Angle fixed at Steel Angle fixed at
600mm max. centres with 600mm max. centres with
metal fasteners metal fasteners
1, 2 or 3 layers of 1, 2 or 3 layers of
GYPROCK FYRCHEK GYPROCK FYRCHEK
Refer to FIG Z100
Ceiling Joist
Ceiling Joist
Ceiling Joist
1, 2 or 3 layers of 1, 2 or 3 layers of
GYPROCK FYRCHEK GYPROCK FYRCHEK
Rondo Wall Track fixed at
600mm max. centres with Rondo Wall Track fixed at
metal fasteners 600mm max. centres with
metal fasteners
Refer to FIG Z100
Wall System
Backing rod
(non fire rated)
10mm Continuously fill gap at
min. Continuously fill gap at edge of all sheets with
edge of sheet with CSR Gyprock® Fire Mastic
CSR Gyprock® Fire Mastic
min. 16mm depth
Wall System
Shadowline stopping bead
Rondo P50 Continuously fill gap at
Continuously fill gap at edge of all sheets with
edge of sheet with vermiculite plaster
CSR Gyprock® Fire Mastic
min. 16mm depth Tape and set joint
70mm max.
Concrete Slab
Water supply
Mixer
only
Head
Silencer inside
track and held by
Track
Fire Performance
Rondo clip Gyprock
Silencer Service penetrations in fire rated walls and ceilings that
can be effectively rated include electrical and data cables,
switches and GPOs, hydraulic pipes, vents and mechanical
ducts. Access panels and control joints can also be installed
with appropriate fire resistance levels.
Power outlets and light switches can be installed in fire
rated walls using either fire rated switch boxes or with
standard switches within a Gyprock Silencer ™. When
installed correctly, these methods can maintain the FRL of
the wall system in which they are installed.
The fire resistance of electrical penetrations was tested at
the CSR Research NATA Laboratory. Standard power points
Gyprock
Base Track Silencer were positioned back to back within Gyprock Silencers™
or Angle
without degrading the fire resistance of the wall system up
to –/120/120. (CSIRO assessment FCO 2039). Taps and
Screw fix Gyprock Silencer similar plumbing penetrations can also be installed in the
to base track or angle
Silencer™ for the same rating.
Where fire and acoustic rated switch boxes are specified,
50mm refer to the manufacturer for appropriate products and
installation details.
200mm 50mm Metal pipe penetrations may be treated as per BCA
deemed-to-satisfy details or in accordance with a
proprietary assessed detail. These details typically involve
mastic sealants. Plastic pipes, and pipes with insulation
lagging, are usually treated with fire collars in accordance
with manufacturers details, in both walls and ceilings.
Some assessed details and typical details for proprietary
treatment of penetrations are included. Additional
information can be found in relevant Gyprock™ installation
manuals, and refer to the appropriate product manufacturer.
Where wall
General purpose system has only
GYPROCK power outlet one layer of
Plasterboard CD GYPROCK
FYRCHEK,
CSR Gyprock provide extra
Fire Mastic 200mm wide
thickness 15mm border and fix 20mm
min. with laminating
screws
25mm
Gyprock
SecurityWall
150mm max.
Panel
GYPROCK Gyprock
AQUACHEK GYPROCK FYRCHEK
Mixer Silencer fixed to studs and
plasterboard Set over stopping bead
tap set noggings around cutout
at 150mm maximum around opening
centres
GYPROCK
Plasterboard
wall with
required fire
rating
GYPROCK
FYRCHEK Electrical
Cables
Cable
Tray
PVC pipe
16mm 16mm 16mm 16mm FIG 211: TYPICAL PVC PIPE PENETRATION RETROFIT
FIRE COLLAR
CSR Gyprock Fire Mastic Refer to manufacturer for assessment number and installation details.
overlapping face of board Fill all gaps with CSR
minimum 30mm around Gyprock Fire Mastic
penetration
Fire rated wall
to system
specification
Fire rated
sealant as per
system PVC Pipe
specification
PROMAT™ PROMAT™
Fyre Collar Fyre Collar
fixed to support fixed to support
framing framing
GYPROCK
FYRCHEK IBS™ strips
Cable Tray 50 x 19mm
wall lining
25mm
GYPROCK
25mm FYRCHEK
1 or 2
layers
10-30mm
CSR Gyprock
Fire Mastic
FIG Z212: INSTALLATION DETAIL FOR FIRE DAMPER IN STUD WALL SYSTEM
Appraisal: PROMAT FCO 2106
Boxed studs
Deflection Head
Track fixed to studs
Caulk between
plasterboard and
Mechanical fire damper body sides
damper tested and with Promaseal
approved for Acrylic Mastic 5mm
AS1530.4 min. depth
1 or 2 layers
GYPROCK
FYRCHEK
Plasterboard as
per FRL
Sheetmetal
Riser
Sheetmetal ductwork
J-Track
Mechanical fire
damper tested and
approved for
AS1530.4 10mm dia. MS rod
fixed to slab and
support angle
1400mm max.
Steel studs
at 600mm
centres
Rondo angles
mechanically
fixed to studs
GYPROCK
FYRCHEK
plasterboard Steel studs at
600mm centres
Proprietary
intumescent
damper
Spigot to terminate
with break joint
Steel studs
at 600mm
centres
Fire Damper
1 or 2 layers of GYPROCK
FYRCHEK plasterboard
7mm
Two layers
16mm *Support
GYPROCK 250 x 50 x 3mm 285mm 2 layer x 16mm
FYRCHEK GYPROCK FYRCHEK
*Light trim
IBS Strip
50 x 20mm 520mm high Timber
wire mesh support
Shield, plate
200mm
diameter
Contents
Index to Systems IN2 – IN3
Disclaimer Telephone: 13 17 44
Facsimile: 1800 646 364
This guide is current at September 2011 and supersedes CSR designLINk™ Technical Support Service
all previous versions of the Fire and Acoustic Design Guide. Telephone: 1800 621 117
CSR has taken all reasonable care in producing this guide, Facsimile: 1800 069 904
however CSR makes no representations or warranties, Email: designlink@csr.com.au
express or implied, as to the accuracy, reliability or
completeness of the guide, and disclaims all liability, direct New South Wales and ACT
or indirect (and whether or not arising out of the negligence, 376 Victoria Street, Wetherill Park NSW 2164
default or lack of care of CSR) for any loss or damage
Queensland
(whether foreseeable or not) suffered by the recipient or
768 Boundary Road, Coopers Plains QLD 4108
any other person arising out of, or in connection with, any
use or reliance by any of them on the guide. Liability which Victoria
cannot legally be excluded is limited to the maximum extent 277 Whitehall Street, Yarraville VIC 3013
possible.
South Australia
Information including acoustic and fire rating has been
Lot 100 Sharp Court, Mawson Lakes SA 5095
sourced from recognised third parties and is current at
the time of printing. Systems, Standards and Building Western Australia
Codes are subject to change. To ensure the information 21 Sheffield Road, Welshpool WA 6106
is current, check the websites www.gyprock.com.au and
www.cemintel.com.au or contact CSR. Tasmania
PO Box 61, Glenorchy TAS 7010
The guide is copyright © CSR Limited (A.B.N 90 000 001 276)
and its related bodies corporate (“CSR”). Copyright 2011. Northern Territory
Cnr Stuart Hwy & Angliss St, Berrimah NT 0828
The following are trade marks of CSR Limited and are under license. CSR™,
Gyprock™, Supaceil™, Soundchek™, Aquachek™, Impactchek™, Superchek™,
Fyrchek™, FyrchekMR™, ECO8™, Bradford™, designLINK™, Cemintel™,
SeminSeal™, RendaLine™, StrataWall™, ExpressWall™.
Publication GYP500.BMS9600.1111