Sr. No.

Region City Site Name Quantity Required Current ACs Quantity

1 NOD MTR Multan Vehari Vehari 2 3

2 NOD MTR Multan Burewala Burewala 2 3

3 NOD MTR Multan Kacha Khau Kacha Khau 1 2

4 NOD MTR Multan Jahanian Jahanian 2 3

5 NOD MTR Multan Mailsi Mailsi 1 3

6 NOD MTR Multan Kabir Wala Kabir Wala 2 3

7 NOD MTR Multan Abdul Hakim Abdul Hakim 1 2

8 NOD MTR Multan Gaggo Mandi Gaggo Mandi 1 4

9 NOD MTR Multan Multan OFS CTX Multan 2 2


10 NOD MTR Multan Multan ZTE SS CTX Multan 1 3
11 NOD MTR Multan Multan OFS Gulgasht Multan 2 2
12 NOD MTR Multan Multan OFS New Multan 2 3
13 NOD MTR Multan Multan ZTE Local Junction New Multan 1 2
14 NOD MTR Multan Multan Huawei Local Junction New Multan 1 2
15 NOD MTR Multan Multan HCTE Mumtazabad Multan 2 1

OFS + Nokia 100G + DWDMs Huawei/ZTE + ZTE STM 64


1 NOD MTR Multan Bahwalpur 2 * 4 Tons 5*2.5 tons
+ MPLS Hall Ground Floor CTX Model town

2 NOD MTR Multan Bahwalpur HCTE + METRO + UMG Hall 1st flor Satellite Town 2 * 4 Tons 4*2.5 tons

Nokia 100G +METRO+DWDM OFS Hall 1st Floor Shahi


3 NOD MTR Multan Rahim Yar Khan 2 * 4 Tons 5*2.5 tons
Road Rahim yar Khan

Nokia 100G + STM 64+ corportae CCts DRS OFS Hall 1st
4 NOD MTR Multan Bahawalnagar 1 * 4 Tons 2*2.5 tons
Floor T/Exchange Bahwalnagar

5 NOD MTR Multan Bahwalpur MSAG-NGN Huawei Hall 1st floorCTX Model town 1* 4 Tons 2*2.5 tons

Nokia 100G + STM 64+ corportae CCts DRS OFS Hall 1st
6 NOD MTR Multan Hasilpur 1 * 4 Tons 3*2.5 tons
Floor T/Exchange Katchehri road hasilpur BWN

7 NOD MTR Multan Bahwalpur MSAG-NGN Huwaei-ZTE Hall CTX Model town 1* 4 Tons 2*2.5 tons

8 NOD MTR Multan Bahwalpur MSU APL Hall 1st floor CTX Model town 1* 4 Tons 2*2.5 tons

BRAS + NOKIA SSR + Huawei 600 +DSLAMs Cahe Servers


9 NOD MTR Multan Bahwalpur 1* 4 Tons 4*2.5 tons
Hall Ground Floor CTX Model town

10 NOD MTR Multan Bahwalpur OFS Hall 1st floor Satellite Town 1* 4 Tons 3*2.5 tons

11 NOD MTR Multan Bahwalpur Local junction Hall 1st floor CTX Model twon 1* 4 Tons 3*2.5 tons

MSAG-NGN + DSLAMs + Hall 1st Floor Shahi Road Rahim


12 NOD MTR Multan Rahim Yar Khan 1 * 4 Tons 4*2.5 tons
yar Khan
MSAG-NGN + DSLAMs + Hall Ground Floor Hospital
13 NOD MTR Multan Sadiqabad 1 * 4 Tons 4*2.5 tons
Road Sadiqabad RYK
MSAG-NGN Hall Ground Floor T/Exchange
14 NOD MTR Multan Bahawalnagar 1 * 4 Tons 3*2.5 tons
Bahawalnagar

NGN + NGN Rectifier+ Battery Bank Ist Floor T/Exchange


15 NOD MTR Multan Chishtian Chishtian 1 * 4 Tons 2*2 tons

NGN+ DSLAM+NGN Rectifier+ Battery Bank Ist Floor 2*2 tons


16 NOD MTR Multan Haroonabad T/Exchange Haroonabad 1 * 4 Tons
1*1.5 tons

NGN+ DSLAM+OLT+APL Switch+NGN Rectifier+ Battery


3*2 tons
17 NOD MTR Multan DG Khan Bank Ist Floor T/Exchange DG Khan 1 * 4 Tons

NGN+NGN Rectifier+ Battery Bank T/Exchange Rajan 2*2 tons


18 NOD MTR Multan Rajan pur pur 1 * 4 Tons

NGN+NGN Rectifier+ Battery Bank T/Exchange Layyah 2*2 tons


19 NOD MTR Multan Layyah 1 * 4 Tons

NGN+NGN Rectifier+ Battery Bank T/Exchange


2*2 tons
20 NOD MTR Multan Muzaffargarh Muzaffargarh 1 * 4 Tons

OFS HUB Rectifier+ Battery Bank T/Exchange Qureshi 3*2 tons


21 NOD MTR Multan Qureshi Chowk Chowk Room No.3 2 * 4 Tons 2* 2ton/4ton are Faulty

OFS HUB Rectifier+ Battery Bank T/Exchange Qureshi 2*2 tons


22 NOD MTR Multan Qureshi Chowk Chowk Room No.2 1 * 4 Tons

NGN+OFS+MPLSTP Rectifier+ Battery Bank T/Exchange 2*1.5 tons


23 NOD MTR Multan Shujabad Shujabad 1 * 4 Tons
Justification/Reason

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life.


Existing AC units have completed their useful life.
Existing AC units have completed their useful life.
Existing AC units have completed their useful life.
Existing AC units have completed their useful life.
Existing AC units have completed their useful life.
Existing AC units have completed their useful life.

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units
3. Nokia 100 G DWDM high Heat dissipation equipment installed
4. Temperature Sensitive 03 NOs DWDMs Ring Diversity equipments installed

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units
3. Transit Exchage equipment installed
4. Switch & Routes of both PIE & MMnBB, temperature sensitiveequipments are installed

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units
3. Nokia 100 G DWDM high Heat dissipation equipment installed
4. Temperature Sensitive 03 NOs DWDMs Ring Diversity equipments installed

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units
3. Nokia 100 G DWDM high Heat dissipation equipment installed
4. Temperature Sensitive 03 NOs DWDMs Ring Diversity equipments installed

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units.

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units
3. Nokia 100 G DWDM high Heat dissipation equipment installed
4. Temperature Sensitive 03 NOs DWDMs Ring Diversity equipments installed

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units.
1. Replacement of old 1997 make repeatedly repaired AC units
2. New equipment installed without AC Units.
1. Replacement of old 1997 make repeatedly repaired AC units
2. New equipment installed without AC Units.
1. Replacement of old 1997 make repeatedly repaired AC units
2. New equipment installed without AC Units.
1. Replacement of old 1997 make repeatedly repaired AC units
2. New equipment installed without AC Units.
1. Replacement of old 1997 make repeatedly repaired AC units
2. New equipment installed without AC Units.
1. Replacement of old 1997 make repeatedly repaired AC units
2. New equipment installed without AC Units.
1. Replacement of old 1997 make repeatedly repaired AC units
2. New equipment installed without AC Units.

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units.

1. Replacement of old 1997 make repeatedly repaired AC units


2. New equipment installed without AC Units.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Existing AC units have completed their useful life. Same will be used for space optimization purpose.

Das könnte Ihnen auch gefallen