Project
Schedule Percentage Work Completed 53%
Health
Planned Completion Date 15 December 2016
RGA
Cost Comment Cost expected to rise due to project suspension
RGA
Procurement Comment All procurement has been completed
Purchase Orders
PO# Scope of Work Supplier Invoice paid Purchase Value
(Y/N)
48013721 CONSTRUCTION OF NEW MAST STEFANUTTI STOCKS Partial 7, 831, 903.96
48011527 CONTRACT LABOUR GOBA (PTY) LTD Y 1,907,727.09
48011682 FEEDER CABLES REQ. DTT MIG. KATHREIN - WERKE KG Partial 844,842.08
BURGERSFORT ANTENNEN. ELECT
48012340 ANTENNA VERTEX 4.7 METER DISH GLOBECAST SOUTH AFRICA Y 194,596.40
TVRO
48012408 Lightning Rod Kit with ELP System GLOBECAST SOUTH AFRICA Y 10,679.03
48012794 Guy ropes for Burgersfort AMSTEEL SYSTEMS (PTY) LTD Y 2,691,579.90
48013261 Manufacture, deliver and install @ Burge THABA AIR CC Partial 231,233.60
KATHREIN - WERKE KG
48013347 Feeder Cables - Burgersfort ANTENNEN. ELECT Partial 274,924.13
48013368 Supply of fresh air louvers DGT POWER CC N 19,613.00
Variation PO48012320 for Burgersfort STEFANUTTI STOCKS CIVILS
48013443 TX (PTY) LTD Y 2,469,227.59
48013475 Cash Upfront connection ESKOM DISTRIBUTION GROUP Y 7,488,971.03
TANK DIESEL 9000 LITRES FOR
48013572 BURGERSFORT KUTA-MANZI TRANSPORT N 135,760.50
48013608 Principal Agent for Burgersfort GOBA (PTY) LTD Y 2,120,432.73
COMBINER SIRA FM 46-WAY HIGH COMMUNICATIONS TECHN
48013613 POWER QPLX BROADC P/L Y 614,407.72
48013647 Eskom Power security ESKOM DISTRIBUTION GROUP Y 129,092.54
STEFANUTTI STOCKS CIVILS
48013721 Construction of new mast at Burgersfort (PTY) LTD Partial 7,831,903.96
Contracts
2
Achievements
1
Finalisation of discussions with Ga-Riba community with regards to community issues raised affecting
the project.
2 Finalisation on way forward with regards to no signed contract between Stefanutti Stocks and Sentech
Key Risks
Major Issues
Scope Changes
1 Non
2