Beruflich Dokumente
Kultur Dokumente
VISUAL INSPECTION
External visual inspections are performed to determine the external
condition of piping, insulation system, painting/coating systems and
associated hardware to check for signs of misalignment, vibration, and
leakage.
1. LEAKS
Leaks can be safety or fire hazards, they can cause the premature
shutdowns of equipment, and they often result in economic loss. Frequent
visual surveillance are carried out for leaks. Particular attention is given to
flanged joints, packing glands, bonnet of valves and expansion joints.
2. MISALINGNMENT
Piping network is inspected for misalignment, which may be indicated by
the following conditions:
Piping dislodged from one or more supports so that its weight is not
being properly distributed on the remaining hangers or saddles.
The deformation of a vessel in the vicinity of a piping attachment.
Piping supports forced out of plumb by expansion or contraction of
piping.
If significant piping misalignment is discovered, workscope and
maintenance notes are prepared for prompt correction.
3. SUPPORTS
Pipe supports consists of shoes, hangers (chains, rods or support springs)
and braces. Supports are visually inspected for
Deterioration of protective coatings or fire proofing.
Evidence of corrosion, especially at or near the foundation
attachments.
Distortion
General physical damage
Movement or deterioration of concrete footings
Failure or loosening of foundation bolts
Insecure attachments of brackets and beams to the supports
Insecure attachment or improper adjustment of pipe hangers
4. VIBRATION
If vibration or swaying is observed, welds are inspected for cracks,
particularly at points of restraint, such as areas where piping is attached
to equipment and near anchors.
THICKNESS MEASUREMENTS
Thickness monitoring with the aid of ultrasonic thickness meter is carried
out at numerous locations on the entire length of the pipe under
inspection. Readings of thickness in HAZ area, offshoot sections, stub-
ends, injection points and deadlegs are especially taken.
The inspection engineer is responsible for the taking the thickness
measurements
INSPECTION FREQUENCY/INTERVALS
An inspection plan is available to schedule the next inspection of a
particular piping system which is set to be five years from a particular
inspection date. The execution of the plan might be disturbed depending
upon various factors, which include; availability of scaffolding, removal of
insulation and the occurrence of any non-planned work/ project.
INSPECTION REPORT
Inspection findings are documented in the form of isometric sketches and
approved performas.
WORKSCOPES
Workscope, after detailed inspection, is prepared in the form of isometric
layouts and issued to the maintenance section for execution of repairs.