APPENDIX TO TENDER
relating to data provided by Employer.
Engineer’s name and address 1.1.2.4 & 1.3 Preferably named in tender
documents
Maximum amount of deductibles for insurance of Employer’s 18.2(d) For the Employer to
risk determine
Minimum amount of third party insurance 18.3 Minimum of Euro 1,000,000
but can be greater
Date by which the DAB (Dispute Adjudication Board) shall be 20.2 1 person 28 days after
appointed Commencement Date
Appointment of DAB (Dispute Adjudication Board), if not 20.3 The President of FIDIC or
agreed other Employer nominee
who is totally independent
Notes:
1) As Contract Price is unknown at the time of tender, and a percentage may not represent
estimated damages, it is recommended the Employer calculate the anticipated costs
that he would incur per day if the contract were delayed. These may include:
Finance costs
Additional supervisory costs
Lack of revenue from completed works
Employer’s administrative costs.
2) As with Note 1, as the Contract Price is unknown at the time of tender, a total sum that is
derived from the daily damages should be determined. The number of days applicable to
determine the limit may be in the order of 5 – 10% of the Time for Completion of the
Works.
3) The number of the DAB persons will depend on the size and complexity of the project.
As a guide for contracts valued up to 50 million euro, a single person DAB may be
acceptable, but for above this value generally a 3 person DAB is advisable.