ID WBS Task Name Duration Start Finish Predecessors % Complete June 01 July 01 August 01 Septe 01 October 01 Novem 01 Decem

Finish Predecessors % Complete June 01 July 01 August 01 Septe 01 October 01 Novem 01 Decem 01 January 01 Febru 01 M
1/0 5/0 9/0 3/0 6/0 0/0 3/0 7/0 1/1 5/1 9/1 2/1 6/1 0/1 4/1 7/0 1/0 4/0 8/0 4/0
1 1 MANAGED PRESSURE DRILLING & RISER GAS HANDLING CO 153 days? Wed 18/07/12 Fri 22/02/13 66%
2 1.1 212377 SURFACE EQUIPMENT & AIR RECEIVER 124 days Wed 18/07/12 Mon 14/01/13 87%
3 1.1.1 Design 104 days Wed 18/07/12 Mon 10/12/12 90%
4 1.1.1.1 FDS 10 days Wed 18/07/12 Tue 31/07/12 100%
5 1.1.1.2 Software Requirements Specification 86 days Wed 18/07/12 Wed 14/11/12 90%

6 1.1.1.3 Control System Definition Document 14 days Wed 18/07/12 Mon 06/08/12 100%

7 1.1.1.4 Electrical Block / Single Line Diagrams 10 days Wed 18/07/12 Tue 31/07/12 100%

8 1.1.1.5 Electrical Interconnection Drawings 10 days Wed 18/07/12 Tue 31/07/12 100%

9 1.1.1.6 Pneumatic Interconnection Drawings 10 days Mon 19/11/12 Fri 30/11/12 20%

10 1.1.1.7 Power Supply Distribution Diagrams 10 days Wed 18/07/12 Tue 31/07/12 100%

11 1.1.1.8 Cable & Piping Schedule 2 days Mon 03/12/12 Tue 04/12/12 4,5,6,7,8,9,10 10%

12 1.1.1.9 Tag Label Drawing 1 day Mon 10/12/12 Mon 10/12/12 0%

13 1.1.1.10 Component Specification / BOM 75 days Wed 01/08/12 Tue 13/11/12 95%

14 1.1.2 Procurement 87 days Wed 22/08/12 Thu 20/12/12 89%


15 1.1.2.1 AEL Enclosure & Contents 30 days Fri 05/10/12 Thu 15/11/12 100%

16 1.1.2.2 Atex Solenoids / Actuators 3.7 wks Tue 30/10/12 Fri 23/11/12 80%

17 1.1.2.3 Index Enclosures 6 wks Fri 12/10/12 Thu 22/11/12 90%

18 1.1.2.4 JWF Pressure Transmitters 13.3 wks Wed 22/08/12 Thu 22/11/12 95%

19 1.1.2.5 Parmley Graham CPU, Profibus equipment, WINCC etc 30 days Fri 14/09/12 Thu 25/10/12 95%

20 1.1.2.6 Powersolve Electronics - Power Supply / Battery equip. 11 wks Wed 05/09/12 Tue 20/11/12 95%

21 1.1.2.7 Relays / Drivers 7 days Fri 19/10/12 Mon 29/10/12 100%

22 1.1.2.8 Vega Sensors 14 days Wed 12/09/12 Mon 01/10/12 100%

23 1.1.2.9 Zone 1 Touch Screen 12 wks Fri 31/08/12 Thu 22/11/12 95%

24 1.1.2.10 Air receiver 4 wks Fri 23/11/12 Thu 20/12/12 0% Graham / Tom

25 1.1.3 Manufacture 12 days Fri 21/12/12 Mon 14/01/13 0%


26 1.1.3.1 Assembly of components 2 wks Fri 21/12/12 Thu 10/01/13 14 0%

27 1.1.3.2 Factory Acceptance Testing 2 days Fri 11/01/13 Mon 14/01/13 26 0%


28 1.2 212378 HYDRAULIC POWER UNIT 148 days? Wed 18/07/12 Fri 15/02/13 75%
67 1.3 212379 FLOWSPOOL CONTROLS & MONITORING 142.5 days? Wed 18/07/12 Fri 08/02/13 57%
94 1.4 212380 SOFTWARE DEVELOPMENT 100 days Tue 14/08/12 Mon 07/01/13 0%
105 1.5 212459 UMBILICAL JUMPER & SURFACE TERMINATIONS 110 days Wed 01/08/12 Tue 08/01/13 68%
120 1.6 GENERAL DOCUMENTATION 50 days Mon 10/12/12 Fri 22/02/13 0%

Task Progress Summary External Tasks Deadline


Project: Draft Project Schedule
Date: Wed 21/11/12
Split Milestone Project Summary External Milestone