Sie sind auf Seite 1von 1

Engineering works for B137 Chemical Storage Reconfiguration Study

Overall
Progress @ 30/6/19 Progress
Percentage
Base Reengineering
IFR AFC IFR AFC
1) Project Management 0.45218894
1.1 Reconfiguration Study Report (engineering workpack) 100% 100% 0% 0% 50%
1.2 Overall modification scope of works 100% 100% 50% 0% 63%
1.3 Construction Job cards 100% 100% Cancelled Cancelled 50%
1.4 Proposed Construction schedule 100% 100% Cancelled Cancelled 50%
1.5 Consolidated Bulk MTO's 100% 100% 0% 0% 50%
1.6 Cost Estimation 100% 100% Cancelled 0% 50%
1.7 Temporary pumping and storage requsition
1.7.1 -Temporary pump datasheet 100% 100% Cancelled Cancelled 50%
1.7.2 -Temporary tank datasheet 100% 100% Cancelled Cancelled 50%
1.7.3 -Temporary instrumentation datasheet 100% 100% Cancelled Cancelled 50%
1.7.4 -Temporary piping datasheet 100% 100% Cancelled Cancelled 50%
1.7.5 -Temporary pumping and storage (P&ID) 100% 100% Cancelled Cancelled 50%
1.7.6 -Temporary pumping and storage (Mech) 100% 100% Cancelled Cancelled 50%
1.7.7 -Temporary pumping and storage (piping) 100% 100% Cancelled Cancelled 50%
1.7.8 -Temporary pumping and storage (structural) 100% 100% Cancelled Cancelled 50%
1.7.9 -Temporary pumping and storage (electrical) 100% 100% Cancelled Cancelled 50%
1.7.10 -Temporary pumping and storage (site installation) 100% 100% Cancelled Cancelled 50%
1.8 Vendor data master list 100% 100% 100% 0% 75%
1.9 Safety Route Access 100% 100% 100% 0% 75%
2) Laser Scanning 100% 100% 100% 100% 0.3078597
3) Process 0.02534562
3.1 Piping & Instrumentation Diagram (P&ID) 100% 100% 100% 0% 75%
3.2 Piping & Instrumentation Diagram (P&ID) - Demolition 100% 100% 100% 0% 75%
3.3 Line Sizing Study 100% 100% 100% 0% 75%
3.4 Line List 100% 100% 100% 0% 75%
4) Mechanical 0.01337686
4.1 New Equipment Layout 100% 100% 100% 0% 75%
4.2 Equipment Layout (Demolition / Modification) 100% 100% 100% 0% 75%
4.3 Mechanical Equipment List 100% 100% 100% 0% 75%
4.4 Tank datasheet 100% 100% 100% 0% 75%
4.5 Pump datasheet 100% 100% 100% 0% 75%
5) Piping 0.14893753
5.1 Piping Design Basis 100% 100% Cancelled Cancelled 50%
5.2 Piping GA Drawing 100% 100% 50% 0% 63%
5.3 Piping GA Drawing (demolition) 100% 100% 100% 0% 75%
5.4 Piping Support Detail 100% 100% 0% 0% 50%
5.5 Piping Isometric Drawings 100% 100% 50% 0% 63%
5.6 Piping Support Standard 100% 100% 50% 0% 63%
5.7 Piping Specification and Datasheet 100% 100% 100% 0% 75%
5.8 Technical Requisition Package
Piping Manual Valve Datasheet 100% 100% 100% 0% 75%
Piping Specialty Item Datasheet 100% 100% 100% 0% 75%
5.9 Piping Bulk MTO 100% 100% 0% 0% 50%
5.10 Valve List 100% 100% 100% 0% 75%
5.11 Piping specialty item List 100% 100% 100% 0% 75%
5.12 Tie In List 100% 100% 100% 0% 75%
5.13 Pipe Stress Report - - 0% 0% 0%
6) Electrical & Instrumentation 0.03171403
6.1 Electrical & Instrumentation Design Basis 100% 100% Cancelled Cancelled 50%
6.2 Cable Tray Layout 100% 100% 100% 0% 75%
6.3 Cable Tray Layout (demolition) 100% 100% 100% 0% 75%
6.4 Instrument Layout 100% 100% 50% 0% 63%
6.5 Electrical Single Line Diagram 100% 100% 100% 0% 75%
6.6 Electrical Single Line Diagram (demolition) 100% 100% 100% 0% 75%
6.7 Electrical & Instrument support standards 100% 100% 100% 0% 75%
6.8 Hook Up and Termination Diagram
Level Gauge 100% 100% 100% 0% 75%
Level / Pressure Transmitter 100% 100% 100% 0% 75%
Pressure Gauge 100% 100% 100% 0% 75%
6.9 Instrument Datasheet
Pressure Gauge 100% 100% 100% 0% 75%
Pressure Safety Valve/ Relief Valve 100% 100% 100% 0% 75%
Level / Pressure Transmitter 100% 100% 100% 0% 75%
Level Gauge 100% 100% 100% 0% 75%
6.10 Electrical & Instrumentation Bulk MTO 100% 100% 0% 0% 50%
6.11 Electrical Cable Schedule 100% 100% 100% 0% 75%
6.12 Instrument Index 100% 100% 100% 0% 75%
6.13 Electrical Termination Diagram 100% 100% 100% 0% 75%
6.14 Electrical Datasheet - Junction Box - - 100% 0% 50%
6.14 Electrical Datasheet - RCU - - 100% 0% 50%
7) Civil, architecture, structure 0.02057732
7.1 Civil & Structural Design Basis 100% 100% Cancelled Cancelled 50%
7.2 Structural Layout 100% 100% 50% 0% 63%
7.3 Structural Layout (demolition) 100% 100% 100% 0% 75%
7.4 Structural Bulk MTO 100% 100% 0% 0% 50%
7.5 Bundwall layout 100% 100% 50% 0% 63%
7.6 Bundwall layout (demolition) 100% 100% 100% 0% 75%
7.7 Tank Foundation Layout (demolition) 100% 100% 100% 0% 75%
7.8 Structural Details - - 0% 0% 0%