COMPOSITION OF ONE GANG PER ITEM OF WORK

(IF BY ADMINISTRATION, WITH ENGINEERING ASSISTANT)

ITEM – 104: EMBANKMENT

1 Foreman
1 Laboratory Technician
4 Laborers

ITEM – 105: SUB – GRADE PREPARATION

1 Foreman
1 Laboratory Technician
2 Laborers

ITEM – 200: AGGREGATE SUB – BASE COURSE

1 Foreman
1 Laboratory Technician
4 Laborers
(NOTE: NO. OF DAYS IN HAULING AGG. NOT INCLUDED)

ITEM – 201: AGGREGATE BASE COURSE (ATTAIN BLUE TOP)

1 Foreman
1 Laboratory Technician
8 Laborers

ITEM – 311: PORTLAND CEMENT CONCRETE PAVEMENT (CF = 9.08)

USING 1 – BAGGER MIXER

1 Foreman
2 Mason/Carpenter
15 Laborers
(NOTE: INCLUDES INSTALLATION OF FORMS)

USING TRANSIT MIXER

1 Foreman
1 Laboratory Technician
6 Skilled Workers
10 Laborers
(NOTE: INCLUDES WORKFORCE BOTH AT BATCHING PLANT & SITE,
INSTALLATION OF FORMS)

ITEM – 405: STRUCTURAL CONCRETE CLASS “A” (CF = 9.08)

USING 1 – BAGGER MIXER

1 Foreman
2 Mason/Carpenter
15 Laborers
(NOTE: INCLUDES INSTALLATION OF FORMS)

USING TRANSIT MIXER

1 Foreman
1 Laboratory Technician
6 Skilled Workers
10 Laborers
(NOTE: INCLUDES WORKFORCE BOTH AT BATCHING PLANT & SITE,
INSTALLATION OF FORMS)
FURNISHING OF AGGREGATES
A. HAULING:
1. Stockpiling and loading
3
use: 1 – 7 Bulldozer, capacity = 500 m /day
3
use: 1 – Payloader, capacity = 500 m /day
P 9,258.00/day + P 4,662.00/day
3
Unit Cost = ------------------------------------------------ = P 27.84/m
3
500.00 m /day
2. Hauling Cost
Average Haul Distance = 5.00 KM.
Average truck speed per day = 25.00 KPH
2.00 x 5.00 x 60.00 kph
Travel time = ------------------------------------------------- = 24.00 mins.
25.00 kph
Loading, unloading & shifting time = 20.00 mins.
============
Total cycle time 44.00 mins.
8.00 X 60.00 (83.33% eff.)
No. of trips/day = ------------------------------------------- = 9.09 say 9.00 trips
44.00 mins.
P 6,024.00/day
3
Unit Cost = ------------------------------------------ = P 66.93/m
3
9.00 x 10.00 m /truck
3
3. Excise Tax (3.00% of items 1 & 2) = P 2.84/m
3
4. Royalty access road Prov’l. & Brgy. Tax = P 15.00/m
==========
3
Hauling Cost P 112.62/m
B. PROCESSING:
1. Fine Aggregates
P 3,198.00 + P 304.90 + P 220.00
3
Screening = ------------------------------------------------- = P 24.82/m
3
150.00 m /day
P 3,198.00 + P 304.90 + P 220.00
3
Washing = ------------------------------------------------- = P 18.61/m
3
200.00 m /day ==========
3
P 43.43/m
3 3 3
FA = P 112.62/m + P 43.43/m = P 156.05/m
2. Coarse Aggregate
P 3,198.00 + P 304.90 + P 220.00
3
Screening = ------------------------------------------------- = P 37.23/m
3
100.00 m /day
P 3,198.00 + P 304.90 + P 220.00
3
Washing = ------------------------------------------------- = P 18.61/m
3
200.00 m /day ==========
3
P 55.84/m
3 3 3
CA = P 112.62/m + P 55.84/m = P 168.46/m
3. Sub – base course
P 3,198.00 + P 304.90 + P 220.00
3
Screening = ------------------------------------------------- = P 14.89/m
3
250.00 m /day
P 3,198.00 + P 304.90 + P 220.00
3
Screening = ------------------------------------------------- = P 24.82/m
3
150 m /day

P 3,198.00 + P 304.90 + P 220.00


3
Blending = ------------------------------------------------- = P 12.41/m
3
300.00 m /day ==========
3
P 37.23/m
3 3
200 (Processed) = P ( 112.62 + 14.89 ) m /day= P 127.51/m
3 3
201 (Processed) = P ( 112.62 + 37.23 ) m /day= P 149.85/m