General:
The Project execution is divided into Packages as under mentioned:
Page 1 of 9
Project Method Statement ______ Contracting Group
2. Execution:
2. Finishing Excavation up to Zone A level then Start plain concrete then start
plaster work on shoring walls after pouring plain concrete then start making
the Water proofing under raft foundation for Zone A and make the
continuation with the water proofing on shoring walls up to 2.00mt height then
pour the protection screed over the water proofing.
3. At the same time complete excavation up to Zone B level then complete plain
concrete with the same sequencing as per Zone A in item No.2
4. After finishing all the Plain Concrete & water proofing systems under raft
foundations the HS divided Raft form work, Steel reinforcement, services
openings & concrete casting into another 2 zones C & D where Zone (C) is the
raft concrete work up to level -5.10, -6.50 & -9.30mt Levels to be steel
reinforced and supported to be casted all at the same time with considering all
trenches in raft for Generator, Transformers room & LT room.
While Zone (D) is to complete concrete work for raft Zone D up to -6.50 & -
5.10mt level & Retaining walls of Water tank & Lower Retaining walls of
Zone C as per approved shop drawings.
5. After pouring Concrete of raft stages then complete the 2nd basement ceiling of
the water tank & Pump room at -5.10mt Level & Stair ST-01.
6. Starting the retaining walls for the higher levels (Zone A) with columns &
Shear walls with complete set of columns & Shear walls formwork up to 1st
basement ceiling slab at ± 0.00 Level.
7. While completing the work for shear walls, retaining walls & 1st basement
columns Hs will use the same period to start making the form work of 1st
Page 2 of 9
Project Method Statement ______ Contracting Group
basement ceiling slab at ± 0.00 Level, preparing the formwork then openings
for different services as per approved shop drawings.
9. Sub structure concrete work is planned to be done in 17% of the project over
all duration.
1. with considering having at least 2 full set of flat slab formwork & 1 full set of
shear walls & columns for each floor with maximum duration of 17 working
days for each floor including (columns, Shear walls &flat slab with services
openings, Etc…
2. With that arrangement super structure work planned to be done within 52.3%
of the project over all duration which leaving enough time for the finishing &
all other trades to be done on time as per planned.
3. The above dates can only be achieved under a condition of dismantling the
formwork of each slab after 14 days only.
5. All detailed work will be shown on the detailed schedule as CPM (6days for
columns & Shear walls and 11 days for the flat slab formwork, services, Steel
Reinforcement and Casting).
6. Finishing Slab to start the stairs formwork between the upper and lower slab.
7. To get 2 sets of formwork for stairs to finish the ST-01 & ST-2A at the same
time then ST-02 & ST-03 at the same time after pouring the 1st two stairs
9. The dates mentioned above can only be achieved when the total duration for
each for work will take 17 working days with 14 calendar days for
dismantling.
10. All other trades (including BP2 & BP3) to submit their related shop drawing
in proper timing before starting the formwork of a certain floor and as stated at
the Preliminary time schedule.
Page 3 of 9
Project Method Statement ______ Contracting Group
The way of execution for this stage of the building was planned to be as follows:
1. Block Work Will Start after dismantling the concrete Slab Formwork with
considering all setting out lines and considering 14 days for dismantles & 2
days sequential for removing shutters, cleaning and curing.
2. Starting from the 2nd basement considering all the other services having
approved shop drawing for builders work & blocking out in Block Work. So
all of the approved Sub-contractors can start their own system openings &
conduiting (if any).
3. Prepare doors opening and start applying plaster for CMU walls and Fair face
paint for concrete surfaces with all required steps as described in the CPM
schedule for finishing.
5. Apply the tank insulation Paint for tank walls & Floor.
8. For 1st basement repeat the same stages from No. 1 to No. 7 with excluding
No. 5
19. Install all trenches Grating covers for transformer rooms & LT room.
Page 4 of 9
Project Method Statement ______ Contracting Group
20. For ground floor repeat all the items above except for 12, 16, 17, 18 & 19 and
add the following:
1. Applying water proofing treatment for toilets and wet areas after
fair face for ceiling and plaster work for walls.
2. Install sanitary fixtures and accessories in toilets.
21. For 1st mezzanine & 2nd mezzanine repeat all mentioned in item No. 20 with
considering all the NIC area will be left as concrete & block Work finish.
22. For all typical floors starting from 1st floor up to 6th floor to repeat all
mentioned in item No. 20 except for the prayer room finishes as the walls will
be plastered then applying putty for walls then false ceiling hanging system to
be installed then install Gypsum Board & paint it then paint wall then install
all system in ceiling.
23. For typical floor from 7th to 12th repeat all sequence as item No. 21.
24. For 13th floor all items to be repeated as item No. 21 Except for the roof deck
that walls will be fair faced to be ready for painting with emulsion then floor
to apply water proofing system with protection then install ceramic tiles as
mentioned in schedule of finishing and architectural drawing.
c. Machine room walls (CMU only) to receive plaster then putty then
paint as per finishing schedule.
d. Fair face the Machine room ceiling and the concrete walls to be ready
for painting.
Page 5 of 9
Project Method Statement ______ Contracting Group
27. All the above is done with considering all other trades as follows:
5.1.4.1 Install piping & fittings after fair face, plaster work
and painting for all surfaces (ceiling & walls).
5.1.4.2 Install foam nozzles.
5.1.4.3 Install sprinklers & foam indicators after finishing
all finishing of the area.
5.1.4.4 Install foam tank after installing the piping & fitting
and making all connection required to ease
operating the system.
5.1.5 Install fire hose real cabinets, landing valve cabinets & fire
extinguisher cabinets after walls painting and floor finish.
5.1.6 Install Halon alternative fire suppression system for IT
room, electrical meter room, LT room, HT room and
transformer room.
5.1.7 For General:
5.1.7.1 KFD fire fighting as- built approval after approval
by consultant.
5.1.7.2 KFD fire fighting check for installation after all fire
fighting system is finished.
5.1.7.3 Start testing & commissioning after launching
Power Supply.
5.1.8 Any interface with any other trade to be co-ordinated.
5.1.9 Testing for installations.
5.1.10 Prepare and submit As-built Drawing.
5.1.11 Submit the as built for MEW for approval.
5.1.12 Making all the required arrangement with MEW for
launching Power Supply.
5.1.13 Testing & commissioning for the system.
Page 7 of 9
Project Method Statement ______ Contracting Group
5.3.1 Install all piping types and fittings after finishing fair
face of ceilings if it is exposed as the parking or
installing it before the hanging systems of false ceiling
if it was above false ceilings.
5.3.2 Install drainage riser inside shafts after plastering and
fair face with painting for these shafts.
5.3.3 Install high pressure pipes & fittings from waste sump
pumps inside waste water sump pit and make the
connection and termination with building storm water
manhole.
5.3.4 Install pressure pipes & fittings for portable vacuum
pump from sump inside elevator pits before installing
elevators carriage.
5.3.5 Connection to be done between building soil/waste line
to MEW sanitary manhole
5.3.6 Connection to be done between building storm water
line to the nearest manhole of MPW.
5.3.7 Installing for all floor traps, floor cleanouts before
making the water proofing systems in toilets and wet
areas.
5.3.8 Install rain water drain or outlet before applying the
roofing system and after screed.
5.3.9 Installing all sanitary fixture and its accessories (in
contract) after finishing all internal walls, floors &
ceiling finishes and installing the door of each unit.
5.3.10 Any interface with any other trade to be co-ordinated.
5.3.11 Testing for installations.
5.3.12 Prepare and submit As-built Drawing.
5.3.13 Submit the as built for MEW for approval.
5.3.14 Making all the required arrangement with MEW for
launching Power Supply.
5.3.15 Testing & commissioning for the system.
6.6 Complete the remaining of the elevations after dismantling the high
level parapet at level +68.35mt.
6.7 Complete all scaffolding work for the remaining of elevation.
6.8 Complete all eh required alignment for the supporting system for the
walls that will receive cladding.
6.9 Repeat the steps from 6.4 to 6.5.
6.10 Finish the installation of cladding, installation of aluminum windows,
applying the sigma paint for the elevations
6.11 Installing window cleaning system rail as per contract.
6.12 Prepare for cleaning and removing scaffolding from the elevations.
Page 9 of 9