Bearer Network Product Cabinet (800 mm-Deep)

Quick Installation Guide


Serial Number: SJ-20130307172319-010 Publishing date: 2013-03-01(R1.0)

ZTE Corporation
Address:No.55, Hi-tech Road South,Shenzhen,
P.R.China 518057
Telephone:+86-755-26770800
Email:800@zte.com.cn Fax:+86-755-26770801
Website: http://support.zte.com.cn

Safety Instructions:
The safety precautions must be strictly followed to ensure personal safety.
◆ When operating the ZTE equipment, abide by the local laws and regulations. If no local regulations are available, follow the
information provided in this document.
◆ The personnel in charge of installation must be trained and qualified for installing or maintaining the equipment.
◆ Personnel protection
• Before operating equipment, take off the personnel jewelry that conduct electricity, such as watches, chains, bracelets and rings.
• Wear personnel protective articles.
• Note the safety signs and warnings pasted on the equipment. Never cover or remove the safety signs and warnings.
◆ Equipment installation safety
• When carrying the cabinet, wear protective gloves.
• Before touching the cabinet, subracks, boards or cables, wear anti-static
资料编号:SJ-20110718112401-030 gloves or an anti-static wrist strap to prevent the
发布日期:2012-10-15(R1.0)
electrostatic discharge of the human body from damaging sensitive components.
• The personnel who install the electrical facilities must be qualified, because improper electrical installation can result in fire,
electric shocks, explosions, personal injury or death.

Tools:
The following diagrams are only for reference. The tools and meters that are purchased on site prevail. All the meters must be
calibrated and proofed before they are used.

Gloves: Tape:
Anti-static gloves: Hacksaw: Marker: Punch:
Used during Anti-static gloves Cuts the anti-static floor Marks position of ground Makes a dimple on the
installation. Measures a length. floor to guide the drill bit.
Used during installation. or metal. drilling holes.

Cross-head Flat-head Level instrument:


Vacuum cleaner: Rubber hammer: Spanner: screwdriver: screwdriver: Checks levelness of an
Cleans installation holes Installs expansion bolts. Secures bolts. Secures cross-head Secures flat-head adjustable base and a
and the ground. screws. screws. cabinet.

Ladder: Multimeter: Torque spanner: Percussion drill:


Measures insulation cable
Used for work at connections and electric Secures bolts. Drills holes.
heights. performance indexes.
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

1. Removing Cabinet Doors


1.1 Removing the Front Door
1 Open the latch on the front door. 2 Use a crosshead screwdriver to disconnect
the grounding wires.

A B
A

3 Remove the cabinet front door.


1 Hold the front door, and pull the upper and lower 3 Hold the front door, and lift it up to separate the pivot
door shafts down and out of the shaft sleeves. hole from the shaft pin at the bottom of the cabinet
2 Turn the door shafts until the shafts are locked.

A
A

B
A

The removed cabinet door should be kept


properly to prevent it from being lost or damaged.

2
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

1.2 Removing the Cabinet Side Doors


1 Use a screwdriver to loosen the eight screws 2 Hold both sides of the side door and slide
of each side door. it outwards slowly.
A

2. Determining the Cabinet Installation Position


The installation position of the cabinet is determined by the system configuration.

m
1m 1m 1.2
m
1.2
1m

m
1.5 m
1.5

Requirements for installing a single cabinet Requirements for side-by-side installation

When the cabinets are installed side by side, the


cabinets in the same row must face the same direction.

3
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

3. Installing an Individual Cabinet


3.1 Installing a Cabinet on a Concrete Floor

1 Use a marker pen and marking template to mark the hole positions on the concrete floor for
installing the cabinet.
800mm
668mm

Concrete floor
mm
mm
600
534

4- 20mm Marking template

Installation hole

2 Remove the marking template, and drill holes on the marked positions.

If the floor is slippery, use a punch to make a dimple to "guide"


the tip of the drill bit.

When drilling holes, ensure that the drill bit is vertical to the
floor, with two hands holding the drill stock firmly and pressing
110mm

downward vertically. Do not shake the percussion drill.

3 Install the expansion bolts into the installation holes.

Bolt
Spring washer
Plain washer Tighten
Insulation Tighten
washer
Expansion
tube

4
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

4 Place the front and rear insulation plates on the installation holes.
m
534m 668
mm

85mm

Insulation plate

5 Place the cabinet. 6 Install four expansion bolts in the


installation holes.

A
Expansion bolt
Spring washer
Plain washer
Insulation washer

Insulation
plate

7 Use a level instrument to ensure that the 8 Use a multimeter to measure the
cabinet is level. resistance between the cabinet and the
ground.
A
U-shape B
insulation
washer
A

A B

Level instrument

The levelness deviation must be less than 3 mm. The resistance must be larger than 5 MΩ.
If the cabinet is not level, place U-shape washers on If not, remove all the cabinet parts. Check whether all
the expansion bolts. the insulation washers are installed and complete.
Use a torque spanner to secure the four expansion Ensure that all the insulation washers are installed,
bolts. reinstall the cabinet, and test the resistance again.

5
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

3.2 Installing a Cabinet on an Adjustable Base


When a cabinet is installed in the equipment room with an antistatic floor, an adjustable base needs to be installed between the
antistatic floor and the concrete floor.

·Adjustable Base Description:


The 19-inch cabinet provides three types of adjustable bases: A, B and C. They m
319 m
are different in adjustment height ranges. The adjustment height range is marked
on each base.

390~690mm
m
319m
m

240~390mm
319m

160~240mm

m
534m m m
534 m 534m

Adjustable base A: Adjustable base B:


Adjustable base C:
Adjustment height range: Adjustment height range:
Adjustment height range:
160 to 240mm 240 to 390mm
390 to 690mm
·Steps:
The following steps use the methods for adjusting adjustable base A as an example.

1 Mark the hole positions for installing the cabinet. Refer to step 1 of the“3.1 Installing a Cabinet on a Concrete
Floor”.
2 Drill holes on the marked hole positions. Refer to step 2 of the“3.1 Installing a Cabinet on a Concrete Floor”.

Depth of the drill holes should be 110 mm.

3 Install four M12×90 expansion bolts.

Tighten

Bolt

Spring washer
Plain
washer
Insulation
washer

Loosen
Expansion
tube

6
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

4 Adjust the height of an adjustable base. 5 Remove the screws from the adjustable
Loosen the height locking screws. Move the adjustable base top.
frames upwards or downwards. Tighten the screws on
each side and then tighten the screws on the frame top.

6 Use expansion bolts (M12X90) to secure the adjustable base.


1 Place two insulation plates that are parallel to each 2 Place an adjustable base to the position and align the
other on the installation holes. installation holes on the base bottom with the installed
A expansion tubes and tighten the expansion bolts.
A

668
mm

7 Level the adjustable bases.

The levelness deviation of each base or every two


adjacent bases must not be larger than 1 mm.
8 Secure four hex bolts (M12X30) to install the
cabinet to the adjustable bases.

Spring washer
Plain washer

7
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

9 Adjust the levelness of the cabinet. 10 Use the multimeter to measure the resistance
between the cabinet grounding terminal and
each expansion bolt.
A

B A
A
B

The horizontal deviation must be less than 3 mm. If The resistance must be larger than 5 MΩ.
the adjustable base is not leveled, you can insert U- If not, remove all the parts. Check whether all the
shape plates between the adjustable bases and the insulation washers are installed and complete. Ensure
cabinet, and use a torque spanner to secure four that all the insulation washers are installed, reinstall
M12×30 hex bolts. the cabinet, and test the resistance again.

4. Installing a Top Cover

Hex bolt

Top
A

5. Connecting Multiple Cabinets in a Row


After each cabinet is installed in accordance with“Installing an Individual Cabinet”, you need to connect the cabinets.

The steps for connecting cabinets with top covers and without top covers are similar, except for connection hole positions. The
cabinets with top covers are connected through the holes on the top covers. The cabinets without top covers are connected through
the holes on the cabinet tops.
This document uses the methods for connecting cabinets without top covers as an example.

8
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

M4 hex bolt
Connection plate

A When two cabinets are installed side by side, the


side doors between these two cabinets are not
required.

The four M4 hex bolts on the outer sides of the


cabinet tops are used for connecting multiple
cabinets.

The space between two adjacent cabinets in a


row must be less than 3 mm.
The cabinet rows must be parallel and aligned to
each other and the deviation must be less than 5
mm.

6. Securing a Cabinet on Top


After a cabinet is installed, top connection plates can be used to secure the cabinet to the cabling racks to improve the
cabinet shockproof capacity.

The steps for securing cabinets with top covers and without top covers are similar, except for connection hole positions. The cabinets
with top covers are secured through the holes on the top covers. The cabinets without top covers are secured through the holes on the
cabinet tops.
This document uses the methods for securing cabinets without top covers as an example.

· When all the connection holes on cabinet top are under the cabling
rack, the installation diagram is as follows:
Insulation sleeve
Connection plate
Insulation washer

M12 hex bolt

The four M12 hex bolts on the inner sides of the cabinet
top are used for securing the cabinet through the top.

·When the cabinet is not close to the cabling rack. The installation
diagram is as follows:

9
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

A
Hex bolt

A
The connection plates of the same type
are used as horizontal plates and B B
upright plates.
If the horizontal connection plate is
longer than the distance between the Hex bolt
cabinet top and the cabling rack, cut
off a piece of connection plate as
required.

Use four top connection plates to


secure an individual cabinet.
When multiple cabinets are
installed side by side, determine
the number of connection plates
as required.

7. Installing Cabinet Doors

7.1 Installing the Front Door


Align the shaft hole at the bottom of Turn the shafts out of the shaft blocks,
1 the front door with the shaft at the 2
cabinet bottom and insert the shaft in and push them upwards to insert them
the hole . in the shaft sleeves.

A
A

10
Bearer Network Product Cabinet (800 mm-Deep) Quick Installation Guide

Use a crosshead screwdriver to install the


3 protective grounding wires. 4 Lock the door.

1 2

7.2 Installing side doors

1 Use a screwdriver to tighten eight screws on each side door.