Government of Nepal

Ministry of Education
Department of Education
District Education Office, Baglung

Measurement Book & Completion Report


Of
( 2 Storey 4 roomed with R.C.C School Block )

Name of School :Shree Karlim Basic School


Address : Khathekhola Rural Municipality -5,BhiunkotBaglung

Fiscal Year : 207/2075 to 2075 to2076


nt of Nepal

Education
of Education
n Office, Baglung

& Completion Report


Of
th R.C.C School Block )

c School
Municipality -5,BhiunkotBaglung

075 to 2075 to2076


Name of the School: Shree Karlim Basic School

Address: Khathekhola Rural Municipality -5,BhiunkotBaglung

Name of the work: 4 Roomed School Block

Estimated Amount : NRs. 3666199.90

Valuated Amount: NRs 0.00

Programme Grant : NRs 3600000.00

Community Contribution: NRs. -3600000.00

………………………….

District Education Officer


Government of Nepal
Ministry of Education
Department of Education

District Education Office


Baglung
Abstract of Cost
(SCHOOL BLOCK)
Name of School : Shree Karlim Basic School
Address : Khathekhola Rural Municipality -5 F/Y : 2074/2075 to 2076
Name Of Project : 2 Storey 4 Roomed R.C.C. Blocks Construction works .

S.N Particulars UNIT Quantity Rate Amount REMARKS

A clearing the site of the vegetation roots and other unuseful materials including
1 ecavation of op soil to a deph of 15 cm removing bushned,trees and levelling the
site foe stacking the useful items in specified space and sisposing other items
before commencing the construction works as per instruction of ht site engineer
all complete including layout of the building, rods and ancillary services. LS 1.00 500.00 500.00
Earth in excavation in the trenche, foundation et. Including timbering and
2 pumping out water from the basement ( if necessary ) dressing of the side
ramming of the bottam , lift up to 3.5 m as theper specaification the drawing and
instruction of the site engineer. cu.m. 167.78 468.65 78629.16
Earthworks in filling in the floor including cosnolidation in layers of 15 cm and
3
watering as per instruction of site engineer. cu.m. 25.57 325.00 8309.28
Providing and laying stone boulder soling in the foundation and floor including
4
voides filling with stone dust all complete as per instruction the site engineer. cu.m. 21.22 2425.00 51446.98
Providing laying and curing random rubble stone masonary works in cement,
5 sand mortar ( 1:4) in the foundation finished upto plinth level in the perfect lines
and level including weting the stone , packing, the joints as per specification ,
drawing and instruction of the site engineer. cu.m. 18.09 8779.20 158815.73

Prepared by: SMC: HeadTeacher: Approved by:


Government of Nepal
Ministry of Education
Department of Education

District Education Office


Baglung
Abstract of Cost
(SCHOOL BLOCK)
Name of School : Shree Karlim Basic School
Address : Khathekhola Rural Municipality -5 F/Y : 2074/2075 to 2076
Name Of Project : 2 Storey 4 Roomed R.C.C. Blocks Construction works .

S.N Particulars UNIT Quantity Rate Amount REMARKS

Providing laying and curing random rubble Bricks masonary works in cement,
6 sand mortar ( 1:4) in the perfect lines and level including good quality local
chimney made stone work , packing, the joints as per specification , drawing and
instruction of the site engineer. cu.m. 53.34 14204.50 757649.56
providing laying, compacking and curing plinth cement concrete (1:3:6) in solid
7 Floor and preapet coping with cement, sand and stone ballast 20 mm gauge
finishing to approved level, lines and dimendions all complete and instruction of
the site Engineer. cu.m. 19.15 9756.00 186819.11
Providing laying compacting and curing 1:1.5:3 plain cement concrete for slab,
8 beams, tie beam lintal sill and all kinds of R.C.C. works with cement sand and
stone ballast 20mm down finishing to approved level line and dimesions, drawing
and instruction of the site engineer, all complete. cu.m. 75.37 15177.25 1143833.45
centering and shuttering with approved quality wood and metal prop for all
9 kindS of R.C.C. works includes all necessary propping, scaffolding staging,
supporting, dismentalling and clearing from the site all complete as per drawing ,
specafication, and instruction of the site engineer. Sq.m 469.34 1082.62 508116.87

Toresteel steel bars ( grade 415 ) reinforcement works including straightening


10 cleaning cutting bending binding with 20 SWG anneled wire and fixing in
position as per drawing, bar bending schedule for raft foundation column beam
wall stair slab in all R.C.C works as per specification, drawing and instructation
of the site enginner, approved bands, himal iron, panchakanya or equivalent. kg 3944.10 113.10 446077.90

Prepared by: SMC: HeadTeacher: Approved by:


Government of Nepal
Ministry of Education
Department of Education

District Education Office


Baglung
Abstract of Cost
(SCHOOL BLOCK)
Name of School : Shree Karlim Basic School
Address : Khathekhola Rural Municipality -5 F/Y : 2074/2075 to 2076
Name Of Project : 2 Storey 4 Roomed R.C.C. Blocks Construction works .

S.N Particulars UNIT Quantity Rate Amount REMARKS

Providing laying and curing 12.5 mm thicks cement sand ( 1:4) plastering in the
11 celling and beams surface including chipping and wetting the concrete surface
finished in the perfect plimb. Line and level as per drawing, specification and
instuction of the site engineer. Sq.m 156.40 326.60 51080.24
Providing laying and curing (1 :1 ) cement sand punning on the floor wit skirting
12 and roof of the building on the perfect line and level as per design specification
and instruction of the site engineer. Sq.m 190.38 242.17 46103.11

13 Providing and fixing well seasoned salla wood chaukhata for fixied/ openable
door and window l as per design specification and instruction of the site engineer. cu.m. 1.37 83866.00 114791.59
Making and fitting fixing panel door and window shutter with 38 mm thicks salla
14
wood frame as per design drawing and specification all complete Sq.m 6.24 6482.02 40471.14
Providing and painting two coats of water proof cement paint of
15 approved brand and colour over plastered surface of the building walls,
celling and passage area as per specification and instrution of the site
engineer. Sq.m 528.95 139.06 73555.79

TOTAL 3666199.90

Prepared by: SMC: HeadTeacher: Approved by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
Estimate of Quantities
(SCHOOL BLOCK)

Name of School : Shree Karlim Basic School


Address : Khathekhola Rural Municipality -5,BhiunkotBaglun
Name Of Project : 2 Storey 4 Roomed R.C.C. Blocks Construction works .
S.N ITEMS UNIT NO L B H QTY. REMARKS
1 Site prepration
Site clearance and layout
A clearing the site of the vegetation roots and other unuseful materials
including ecavation of op soil to a deph of 15 cm removing bushned,trees
and levelling the site foe stacking the useful items in specified space and
sisposing other items before commencing the construction works as per
instruction of ht site engineer all complete including layout of the building,
rods and ancillary services. LS 1 1 1 1 LS LS
2 Earth works
Earth in excavation in the trenche, foundation et. Including timbering and
pumping out water from the basement ( if necessary ) dressing of the side
ramming of the bottam , lift up to 3.5 m as theper specaification the
drawing and instruction of the site engineer. cu.m 167.778
F1 4.000 2.100 2.100 1.300 22.932
F2 6.000 2.800 2.800 1.300 61.152
F3 2.000 3.300 3.300 1.300 28.314
Long wall 3.000 12.000 0.600 1.300 28.080
Short wall 4.000 8.750 0.600 1.300 27.300
Total . 167.778
Earthworks in filling in the floor including cosnolidation in layers of 15
3
cm and watering as per instruction of site engineer. cu.m 25.567
Room 2.000 8.800 5.600 0.600 16.117
stair room 1.000 4.500 3.500 0.600 9.450
Total 25.567
4 Stone works
Providing and laying stone boulder soling in the foundation and floor
including voides filling with stone dust all complete as per instruction the
site engineer. 21.215
F1 4.000 2.100 2.100 0.150 2.646
F2 6.000 2.800 2.800 0.150 7.056
F3 2.000 3.300 3.300 0.150 3.267
long wall 3.000 12.000 0.400 0.150 2.160
short wall 4.000 8.750 0.400 0.150 2.100
stair room 1.000 4.500 4.350 0.150 2.936
Room 2.000 8.750 0.400 0.150 1.050
Total 21.215

Providing laying and curing random rubble stone masonary works in


cement, sand mortar ( 1:4) in the foundation finished upto plinth level in
5
the perfect lines and level including weting the stone , packing, the joints as
per specification , drawing and instruction of the site engineer.
cu.m 18.090
long wall 3.000 12.000 0.300 0.600 6.480
short wall 4.000 8.750 0.300 0.600 6.300
Room 2.000 8.750 0.300 0.600 3.150
Ramp 1.000 12.000 0.300 0.600 2.160
Total 18.090
Providing laying and curing random rubble Bricks masonary works in
cement, sand mortar ( 1:4) in the perfect lines and level including good
6
quality local chimney made stone work , packing, the joints as per
specification , drawing and instruction of the site engineer. cu.m 53.339
Gorund floor.

Prepared by: SMC: HeadTeacher: Approved by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
Estimate of Quantities
(SCHOOL BLOCK)

Name of School : Shree Karlim Basic School


Address : Khathekhola Rural Municipality -5,BhiunkotBaglun
Name Of Project : 2 Storey 4 Roomed R.C.C. Blocks Construction works .
S.N ITEMS UNIT NO L B H QTY. REMARKS
long wall 2.000 12.000 0.230 2.400 13.250
short wall 4.000 8.750 0.230 2.400 19.320
First Floor
long wall 2.000 12.000 0.230 2.400 13.250
short wall 4.000 8.750 0.230 2.400 19.320
Deducation
Door 8.000 1.100 0.230 2.200 -4.453
window W1 11.000 1.500 0.230 1.500 -5.693
Window W2 4.000 1.200 0.230 1.500 -1.656
Total 53.339
7 Cement concrete works cu.m
providing laying, compacking and curing plinth cement concrete (1:3:6) in
solid Floor and preapet coping with cement, sand and stone ballast 20 mm
gauge finishing to approved level, lines and dimendions all complete and
instruction of the site Engineer. 19.149
F1 4.000 2.100 2.100 0.075 1.323
F2 6.000 2.800 2.800 0.075 3.528
F3 2.000 3.300 3.300 0.075 1.634
long wall 3.000 22.950 0.600 0.075 3.098
short wall 4.000 9.080 0.600 0.075 1.634
Room 2.000 8.800 5.600 0.075 7.392
Ramp 1.000 12.000 0.600 0.075 0.540
Total 19.149

Providing laying compacting and curing 1:1.5:3 plain cement concrete for
slab, beams, tie beam lintal sill and all kinds of R.C.C. works with cement
8
sand and stone ballast 20mm down finishing to approved level line and
dimesions, drawing and instruction of the site engineer, all complete.
cu.m
On the column Base
F1 4.000 2.100 2.100 0.100 1.760
F2 6.000 2.800 2.800 0.100 4.700
F3 2.000 3.300 3.300 0.100 2.180
column up to tie beam
F1 4.000 0.350 0.350 2.400 1.180
F2 6.000 0.350 0.350 2.400 1.760
F3 2.000 0.350 0.350 2.400 0.590
Ground floor
column 12.000 0.300 0.300 2.400 2.590
Foundation and Tie beam
Gride A and B Long wall 3.000 13.500 0.300 0.300 3.645
Gride1,2,3 4 Short wall 4.000 8.100 0.300 0.300 2.916
Beam
Gride A and B Long wall 4.000 13.500 0.300 0.300 2.300
Gride 1,2,3 4 5 and 6Short wall 6.000 8.100 0.300 0.300 4.374
Lintal beam
Gride A and B Long wall 2.000 13.500 0.250 0.075 0.510
Girde 1,2,3 4 5 and 6 ,Short wall 4.000 8.000 0.250 0.075 0.600
Slab 1 1.000 14.500 9.600 0.100 13.920
Stair part
Sloping part 1.000 4.300 3.000 0.100 1.290
landing 1.000 3.000 2.000 0.100 0.600
Rise and Treads 20.000 0.150 0.230 0.900
First floor
column 12.000 0.300 0.300 2.400 2.590
Tie beam 0.000
Gride A and B Long wall 2.000 13.500 0.300 0.300 2.430

Prepared by: SMC: HeadTeacher: Approved by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
Estimate of Quantities
(SCHOOL BLOCK)

Name of School : Shree Karlim Basic School


Address : Khathekhola Rural Municipality -5,BhiunkotBaglun
Name Of Project : 2 Storey 4 Roomed R.C.C. Blocks Construction works .
S.N ITEMS UNIT NO L B H QTY. REMARKS
Gride1,2,3 4 5 and 6 Short wall 3.000 8.100 0.300 0.300 2.190
Beam 0.000
Gride A and B Long wall 2.000 13.500 0.300 0.300 2.430
Gride 1,2,3,4 5 and 6 Short wall 3.000 8.100 0.300 0.300 2.190
Lintal beam 0.000
Gride A and B Long wall 2.000 24.600 0.250 0.075 0.920
Girde 1,2,3 4 5 and 6Short wall 2.000 8.000 0.250 0.075 0.300
Slab 1 1.000 14.500 9.600 0.100 13.920
Stair part 0.000
Sloping part 1.000 4.300 3.000 0.100 1.290
landing 1.000 3.000 2.000 0.100 0.600
Rise and Treads 20.000 0.150 0.230 0.690
Total 75.365
9 Formworks Sq.m

centering and shuttering with approved quality wood and metal prop for all
kindS of R.C.C. works includes all necessary propping, scaffolding
staging, supporting, dismentalling and clearing from the site all complete as
per drawing , specafication, and instruction of the site engineer.

F1 12.000 4.200 0.300 15.120


Column 12.000 1.200 2.500 36.000
Frist Floor 0.000
Column 12.000 1.200 0.000 3.000 43.200
Tie beam
Gride A and B long wall 2.000 9.100 0.300 5.460
Gride 1,2,3,4,5 and 6 Short wall 6.000 8.500 0.300 15.300
Beam
Ground floor
Gride A and B Long wall 2.000 9.100 0.570 10.370
Gride 1 and 6 Short wall 6.000 8.500 0.570 29.070
Lintal band Gorund floor .
Girde A and B Long wall 2.000 9.100 0.150 2.730
Gride 1,2,3,4,5 And 6 Short wall 6.000 8.500 0.150 7.650
Slab 1 2.000 13.500 10.200 275.400
Stair part
Sloping part 1.000 4.580 3.000 13.740
Landing 2.000 3.000 2.100 6.300
Rise and Treads 40.000 0.150 1.500 9.000
Total 469.340
10 Reinforcement kg
Toresteel steel bars ( grade 415 ) reinforcement works including
straightening cleaning cutting bending binding with 20 SWG anneled wire
and fixing in position as per drawing, bar bending schedule for raft
foundation column beam wall stair slab in all R.C.C works as per
specification, drawing and instructation of the site enginner, approved
bands, himal iron, panchakanya or equivalent.

Prepared by: SMC: HeadTeacher: Approved by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
Estimate of Quantities
(SCHOOL BLOCK)

Name of School : Shree Karlim Basic School


Address : Khathekhola Rural Municipality -5,BhiunkotBaglun
Name Of Project : 2 Storey 4 Roomed R.C.C. Blocks Construction works .
S.N ITEMS UNIT NO L B H QTY. REMARKS
on other R.C.C structur such as beam pillar @ 1.5% of the R.C.C Works
75.365
0.502 7850.000 3944.102
Total 3944.102

Providing laying and curing 12.5 mm thicks cement sand ( 1:4) plastering
in the celling and beams surface including chipping and wetting the
11
concrete surface finished in the perfect plimb. Line and level as per
drawing, specification and instuction of the site engineer.
sq.m 156.400
Ground floor.
Room 4.000 8.500 4.600 156.400
Total 156.400
Floor finishing
Providing laying and curing (1 :1 ) cement sand punning on the floor wit
12 skirting and roof of the building on the perfect line and level as per design
specification and instruction of the site engineer. sq.m 190.375
Ground floor.
Room 4.000 8.500 4.600 156.400
Stair room 1.000 4.500 4.350 19.575
Ramp 1.000 12.000 1.200 14.400
Total 190.375
13 Wood works cu.m
Providing and fixing well seasoned salla wood chaukhata for fixied/
openable door and window l as per design specification and instruction of
the site engineer. 1.369
D 8.000 6.700 0.075 0.125 0.503

Prepared by: SMC: HeadTeacher: Approved by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
Estimate of Quantities
(SCHOOL BLOCK)

Name of School : Shree Karlim Basic School


Address : Khathekhola Rural Municipality -5,BhiunkotBaglun
Name Of Project : 2 Storey 4 Roomed R.C.C. Blocks Construction works .
S.N ITEMS UNIT NO L B H QTY. REMARKS
W1 12.000 5.300 0.075 0.125 0.596
W2 2.000 14.400 0.075 0.125 0.270
Total 1.369
Making and fitting fixing panel door and window shutter with 38 mm
14 thicks salla wood frame as per design drawing and specification all
complete sq.m 6.244
Door 4.000 1.075 1.452 6.244
Total 6.244

Providing and painting two coats of water proof cement paint of approved
15 brand and colour over plastered surface of the building walls, celling and
passage area as per specification and instrution of the site engineer.
sq.m 528.950
Ground floor
Room Celling 4.000 7.600 5.600 170.240
Room wall 4.000 26.400 3.000 316.800
Stari room 1.000 4.850 3.000 14.550
Verndaha Celling 4.000 5.600 1.200 26.880
Outside of building 1.000 65.600 1.200 78.720
Deducation
Door 8.000 2.100 1.100 -18.480
W1 24.000 1.500 1.500 -54.000
W2 4.000 1.200 1.200 -5.760
Total 528.950

Prepared by: SMC: HeadTeacher: Approved by:


g]kfn ;/sf/ d=n]=k=kmf=g+= !*^
lzIff dGqfno
lzIff ljefu
lhNnf lzIff sfof{no, afun'Ë
sfof{nosf] gfd M lhNnf lzIff sfof{no 7]Ssf ;DalGw lan
lansf] qmd ;+=
of]hgfsf] gfdM lj1fg ;+sfo ;~rfngs]f nflu $ sf]7] ejg lgdf{0f
ljBfnosf] gfd M >L l;ufgf dfWolds ljBfno, afgkf ( , afun'ª .
7]Ssf k§fsf] ;+Vof M @$,)),))).– e'QmfgL ef}r/ g+=
Oli6d]6eGbf 36L a9L M 5}g . e'QmfgL ldlt
cl3Nnf] e'QmfgL ljnsf] qmd ;+Vof gfkL lstfa g+= ! sf] k[i7 g+==============
cl3Nnf] e'QmfgL ljnsf] ef}=g+=
sfof{/De cfb]z ldlt‫!&)@ ׃‬.!@.!)
sfd ;DkGg ug'{ kg]{] ldlt‫&)@ ׃‬#.#.#!
sfd ;DkGg ePsf]] ldlt ‫&)@ ׃‬#.!!. @#
cfO{6
d; cWofjlw sfd ePsf] cl3Nnf] ljndf r9]sf] xfn ePsf] sfdsf]
+Vof sfdsf] ljj/0f PsfO{
kl/df0f b/ hDdf d"No kl/df0f hDdf d"No kl/df0f hDdf d"No s}lkmot
A clearing the site of the vegetation roots and other unuseful materials including ecavation of op soil
to a deph of 15 cm removing bushned,trees and levelling the site foe stacking the useful items in
1 specified space and sisposing other items before commencing the construction works as per
instruction of ht site engineer all complete including layout of the building, rods and ancillary
services. LS 1.00 500.00 500.00 --- 1.00 500.00
Earth in excavation in the trenche, foundation et. Including timbering and pumping out water from
2 the basement ( if necessary ) dressing of the side ramming of the bottam , lift up to 3.5 m as theper
specaification the drawing and instruction of the site engineer. cu.m. 167.78 468.65 78629.16 --- 167.78 78629.16
Earthworks in filling in the floor including cosnolidation in layers of 15 cm and watering as per
3 instruction of site engineer. cu.m. 25.57 325.00 8309.28 --- 26.20 8514.03
Providing and laying stone boulder soling in the foundation and floor including voides filling with
4 stone dust all complete as per instruction the site engineer. cu.m. 21.22 2425.00 51446.98 --- 13.09 31751.01
Providing laying and curing random rubble stone masonary works in cement, sand mortar ( 1:4) in
5 the foundation finished upto plinth level in the perfect lines and level including weting the stone ,
packing, the joints as per specification , drawing and instruction of the site engineer. cu.m. 18.09 8779.20 158815.73 --- 17.09 150036.53
Providing laying and curing random rubble Bricks masonary works in cement, sand mortar ( 1:4)
6 in the perfect lines and level including good quality local chimney made stone work , packing, the
joints as per specification , drawing and instruction of the site engineer. cu.m. 53.34 14204.50 757649.56 --- 40.74 578672.86
providing laying, compacking and curing plinth cement concrete (1:3:6) in solid Floor and preapet
7 coping with cement, sand and stone ballast 20 mm gauge finishing to approved level, lines and
dimendions all complete and instruction of the site Engineer. cu.m. 19.15 9756.00 186819.11 --- 21.82 212912.99
Providing laying compacting and curing 1:1.5:3 plain cement concrete for slab, beams, tie beam lintal
8 sill and all kinds of R.C.C. works with cement sand and stone ballast 20mm down finishing to
approved level line and dimesions, drawing and instruction of the site engineer, all complete. cu.m. 75.37 15177.25 1143833.45 --- 59.75 906901.40
centering and shuttering with approved quality wood and metal prop for all kindS of R.C.C. works
9 includes all necessary propping, scaffolding staging, supporting, dismentalling and clearing from the
site all complete as per drawing , specafication, and instruction of the site engineer. Sq.m 469.34 1082.62 508116.87 --- 437.56 473711.21
Toresteel steel bars ( grade 415 ) reinforcement works including straightening cleaning cutting
bending binding with 20 SWG anneled wire and fixing in position as per drawing, bar bending
10 schedule for raft foundation column beam wall stair slab in all R.C.C works as per specification,
drawing and instructation of the site enginner, approved bands, himal iron, panchakanya or
equivalent. kg 3944.10 113.10 446077.90 --- 3127.13 353677.95
Providing laying and curing 12.5 mm thicks cement sand ( 1:4) plastering in the celling and beams
11 surface including chipping and wetting the concrete surface finished in the perfect plimb. Line and
level as per drawing, specification and instuction of the site engineer. Sq.m 156.40 326.60 51080.24 --- 260.50 85079.30

12 Providing laying and curing (1 :1 ) cement sand punning on the floor wit skirting and roof of the
building on the perfect line and level as per design specification and instruction of the site engineer. Sq.m 190.38 242.17 46103.11 --- 156.40 37875.39
Providing and fixing well seasoned salla wood chaukhata for fixied/ openable door and window l as
13
per design specification and instruction of the site engineer. cu.m. 1.37 83866.00 114791.59 --- 185.35 15544563.10
Making and fitting fixing panel door and window shutter with 38 mm thicks salla wood frame as per
14 design drawing and specification all complete Sq.m 6.24 6482.02 40471.14 --- 1.37 8872.26
Providing and painting two coats of water proof cement paint of approved brand and colour over
15 plastered surface of the building walls, celling and passage area as per specification and instrution of
the site engineer. Sq.m 528.95 139.06 73555.79 --- 6.24 868.24
Total 3,666,199.90 --- --- Total 18472565.42

pko'{Qm adf]lhd 7Ls 5 egL k|dfl0ft ug]{sf] ;xL

of] adf]lhd hDdf gub ? @$,)),))).—

cl3Nnf] lanaf6 e'QmfgL ePsf] ?=

afFsL lbg' kg]{ ?= @$,)),))).— }

s§f ug'{ kg]{ ?=

v'b lbg' kg]{]{ ? =@$,)),))).— hfFr ug]{sf] ;xL lj=Jo=; cWoIfsf] ;lx k|=c sf] ;lx l:js[t ug]{sf] ;xL

tof/ ug]{sf] ;xL bhf{ bhf{

bhf{

hDdf ?=@$,)),))).— cIf/]kL rf}lj; nfv ?k}of dfq =r]s g= ====================af6 k|fKt ePsf] egL ;xL ug]{
g]kfn ;/sf/ d=n]=k=kmf=g+= !&^
lzIff dGqfno
lzIff ljefu
lhNNnf lzIff sfof{no, afun'Ë
sfof{nosf] gfd M lhNnf lzIff sfof{no sfo{ ;DkGg k|ltj]bg
ljBfnosf] gfd M >L l;ufgf dfWolds ljBfno, afgkf ( , afun'ª .
sfdsf] gfd M lj1fg ;+sfo ;~rfngs]f nflu $ sf]7] ejg lgdf{0f
Oli6d]6sf] s'n cÍ M @&,*),!#!.%) lgdf0f{sf] nflu k|fKt ;xof]usf] ljj/0f
Oli6d]6eGbf 36L a9L M 36L /sd? . >f]tsf] k|sf/ ;xof]o /sd ? vr{ /sd ?=
36L a9Lsf] k|ltztM ) lh=lz=sf= 2400000.00 2400000.00
sfd z'? ePsf] ldlt M @)&!.!!.!) hg >dbfg (2,400,000.00) (2,400,000.00)
sfd ;DkGg ug'{ kg]{] ldlt @)&#.#.#! cGo 0.00 0.00
sfd ;DkGg ePsf]] ldlt ‫&)@ ׃‬#.!!.@# hDdf /sd ?= - -
d]h/d]G6 ePsf]] ldlt ‫&)@ ׃‬$.)@.!$
Oli6d]6 jdf]lhdsf] v'b ePsf] sfdsf] km/s
qm=;= sfdsf] ljj/0f PsfO{ s}lkmot
kl/df0f b/ hDdf kl/df0f ;Demf}tf b/ hDdf kl/df0;Demf}tf hDdf
A clearing the site of the vegetation roots and other unuseful materials including ecavation of op
soil to a deph of 15 cm removing bushned,trees and levelling the site foe stacking the useful items in
1 specified space and sisposing other items before commencing the construction works as per
instruction of ht site engineer all complete including layout of the building, rods and ancillary
services. LS 1.00 500.00 500.00 500.00 - --- ---
Earth in excavation in the trenche, foundation et. Including timbering and pumping out water from
2 the basement ( if necessary ) dressing of the side ramming of the bottam , lift up to 3.5 m as theper
specaification the drawing and instruction of the site engineer. cu.m. 167.78 468.65 78629.16 468.65 - --- ---
Earthworks in filling in the floor including cosnolidation in layers of 15 cm and watering as per
3 instruction of site engineer. cu.m. 25.57 325.00 8309.28 325.00 - --- ---
Providing and laying stone boulder soling in the foundation and floor including voides filling with
4 stone dust all complete as per instruction the site engineer. cu.m. 21.22 2425.00 51446.98 2425.00 - --- ---
Providing laying and curing random rubble stone masonary works in cement, sand mortar ( 1:4) in
5 the foundation finished upto plinth level in the perfect lines and level including weting the stone ,
packing, the joints as per specification , drawing and instruction of the site engineer. cu.m. 18.09 8779.20 158815.73 8779.20 - --- ---
Providing laying and curing random rubble Bricks masonary works in cement, sand mortar ( 1:4)
6 in the perfect lines and level including good quality local chimney made stone work , packing, the
joints as per specification , drawing and instruction of the site engineer. cu.m. 53.34 14204.50 757649.56 14204.50 - --- ---
providing laying, compacking and curing plinth cement concrete (1:3:6) in solid Floor and preapet
7 coping with cement, sand and stone ballast 20 mm gauge finishing to approved level, lines and
dimendions all complete and instruction of the site Engineer. cu.m. 19.15 9756.00 186819.11 9756.00 - --- ---
Providing laying compacting and curing 1:1.5:3 plain cement concrete for slab, beams, tie beam
8 lintal sill and all kinds of R.C.C. works with cement sand and stone ballast 20mm down finishing to
approved level line and dimesions, drawing and instruction of the site engineer, all complete. cu.m. 75.37 15177.25 1143833.45 15177.25 - --- ---

centering and shuttering with approved quality wood and metal prop for all kindS of R.C.C. works
9 includes all necessary propping, scaffolding staging, supporting, dismentalling and clearing from the
site all complete as per drawing , specafication, and instruction of the site engineer. Sq.m 469.34 1082.62 508116.87 1082.62 - --- ---
Toresteel steel bars ( grade 415 ) reinforcement works including straightening cleaning cutting
bending binding with 20 SWG anneled wire and fixing in position as per drawing, bar bending
10 schedule for raft foundation column beam wall stair slab in all R.C.C works as per specification,
drawing and instructation of the site enginner, approved bands, himal iron, panchakanya or
equivalent. kg 3944.10 113.10 446077.90 113.10 - --- ---
Providing laying and curing 12.5 mm thicks cement sand ( 1:4) plastering in the celling and beams
11 surface including chipping and wetting the concrete surface finished in the perfect plimb. Line and
level as per drawing, specification and instuction of the site engineer. Sq.m 156.40 326.60 51080.24 326.60 - --- ---

12 Providing laying and curing (1 :1 ) cement sand punning on the floor wit skirting and roof of the
building on the perfect line and level as per design specification and instruction of the site engineer. Sq.m 190.38 242.17 46103.11 242.17 -
Providing and fixing well seasoned salla wood chaukhata for fixied/ openable door and window l as
13 per design specification and instruction of the site engineer. cu.m. 1.37 83866.00 114791.59 83866.00 - --- ---
Making and fitting fixing panel door and window shutter with 38 mm thicks salla wood frame as per
14 design drawing and specification all complete Sq.m 6.24 6482.02 40471.14 6482.02 - --- ---
Providing and painting two coats of water proof cement paint of approved brand and colour over
15 plastered surface of the building walls, celling and passage area as per specification and instrution of
the site engineer. Sq.m 528.95 139.06 73555.79 139.06 - --- ---
Total 3,666,199.90 Total - --- ---

______ ______ ______ ______ ________


tof/ ug]{ –O{lGhlgo/ k|=c= lj=Jo=;=cWoIf sfof{no k|d'v
RATE(Inclusive of VAT)
SN DESCRIPTION UNIT UNIT WT (Kg.) RATE
for external materials

1.0 Skilled Labour MD 330.00 330

2.0 Unskilled Labour MD 220.00 220

3.0 Local wood M1 12300.00 12300.00

4.0 Flagstone (50 mm) M2 95.00 95.00

5.0 Soil M3 230.00 230.00

6.0 Husk KG 1.00 1.00

7.0 Stone M3 650.00 650.00

8.0 Aggregate 10-20 mm M3 1100.00 1100.00

9.0 Aggregate 20-40 mm M3 1100.00 1100.00

10.0 Sand M3 750.00 750.00

11.0 Cowdung KG 2.50 2.50

12.0 Cement KG 1 9.60 10.85

13.0 CGI sheet 26 gauge M2 3.35 370.56 418.73

14.0 Bitumen washer NO 0.005 0.55 0.62

15.0 L-hook NO 0.1 18.00 20.34

16.0 Plain GI sheet 26 gauge M2


3.35 370.56 418.73

17.0 Nails KG 1 106.00 119.78

18.0 Tower bolt 6" Aluminium NO 0.2 89.00 100.57

19.0 Tower bolt 4" Aluminium NO 0.15 67.00 75.71

20.0 Hinge (75 mm) NO 0.1 13.00 14.69

21.0 Screw NO 0.005 0.90 1.02

22.0 Hold Fast NO 0.25 17.00 19.21

23.0 Handle (150mm) NO 0.15 20.00 22.6

24.0 Hinge (150 mm) NO 0.2 28.00 31.64

25.0 Locking set 250mm NO 0.3 215.00 242.95

26.0 Rebar 8 mm dia. KG 1 102.00 115.26

27.0 Rebar 5.5 mm dia. KG 1 92.00 103.96

28.0 Metal clip NO 0.2 14.00 15.82

29.0 Nail (5mm dia) for Truss KG 1 106.00 119.78

30.0 Roofing nail KG 1 106.00 119.78

31.0 Polythene Sheet M2


0.5 50.00 56.5

32.0 Transparent Pipe M 0.07 20.00 22.6

33.0 Binding Wire KG 1 106.00 119.8

34.0 HDP Pipe 110 mm f 4 Kgf M 1.703 323.57 365.63


35.0 HDP Pipe 63 mm f 4 Kgf M 1.25 135.00 152.55

36.0 HDP Pipe 16 mm f 4 Kgf M 0.25 40.00 45.2


Government of Nepal
Ministry of Education
Department of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

SUMMARY OF COST

Name of project: School Toilet Block Construction


Name of School: Shree Sharada Higher Secondary School
Village Dev. Committee: Batakachaur Tole: F/Y 066/67
S.N DESCRIPTION PROJECT COMMUNITY TOTAL REMARKS

1.0 School Toilet block construction. 150000.00 #REF! #REF!

Grand total 150000.00 #REF! #REF!

Prepared by: Checked by: Approved by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

LIST OF LABOUR AND MATERIAL

Name of School: Shree Tribhuwan Secondary School


VDC: Dagatumdanda

S.N MATERIALS AND LABOUR UNIT QUANTITY REMARKS

1.00 Skilled Labour MD #N/A

2.00 Unskilled Labour MD 109.99

3.00 Stone M3 #N/A

4.00 Aggregate 10-20 mm M3 #N/A

5.00 Aggregate 20-40 mm M3 #N/A

6.00 Sand M3 #N/A

7.00 Local wood M3 #N/A

8.00 Cement KG #N/A

9.00 CGI sheet 26 gauge M2 #N/A

10.00 Bitumen washer NO #N/A

11.00 L-hook NO #N/A

12.00 Nails KG #N/A

Prepared by: Approved by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

LIST OF LABOUR AND MATERIAL

Name of School: Shree Tribhuwan Secondary School


VDC: Dagatumdanda

S.N MATERIALS AND LABOUR UNIT QUANTITY REMARKS

13.00 Tower bolt 4" Aluminium NO #N/A

14.00 Hinge (75 mm) NO #N/A

15.00 Screw NO #N/A

16.00 Hold Fast NO #N/A

17.00 Handle (150mm) NO #N/A

18.00 Locking set 250mm NO #N/A

19.00 Soil M3 #N/A

all sizes are included


20.00 Rebar 8 mm dia. KG #N/A in weight

21.00 Roofing nail KG #N/A

22.00 Transparent Pipe M #N/A

23.00 HDP Pipe 110 mm f 4 Kgf M #N/A

24.00 HDP Pipe 63 mm f 4 Kgf M #N/A

25.00 HDP Pipe 16 mm f 4 Kgf M #N/A

26.00 Metal clip No #N/A

Total

Prepared by: Approved by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

RATE OF MATERIAL AND LABOUR

Name of School: Shree Tribhuwan Secondary School


VDC: Dagatumdanda Ward No: 7 Tractor TPT dist (km): 65 Porter TPT dist (km): 0.3
Total rate of
Transportation Total rate of material
S.N ITEMS UNIT Quantity UNIT Wt. (Kg) Transportation by Porter Unit Rate of material
by Tractor transportation ( transportatio
+cost) Total Cost

1 Skilled Labour MD #N/A 330 330.00 #N/A

2 Unskilled Labour MD #N/A 220 220.00 #N/A

3 Stone M3
#N/A 650 650.00 #N/A

4 Aggregate 10-20 mm M3 #N/A 1100 1100.00 #N/A

5 Aggregate 20-40 mm M3
#N/A 1100 1100.00 #N/A

6 Sand M3 #N/A 750 750.00 #N/A

7 Local wood M3
#N/A 12300 12300.00 #N/A

8 Soil M3 #N/A 230 230.00 #N/A

9 Cement KG #N/A 1 5.85 0.06 5.91 10.85 16.76 #N/A

10 CGI sheet 26 gauge M2 #N/A 3.35 19.60 0.22 19.82 418.73 438.55 #N/A

11 Bitumen washer NO #N/A 0.005 0.03 0.00 0.03 0.62 0.65 #N/A

12 L-hook NO #N/A 0.1 0.59 0.01 0.59 20.34 20.93 #N/A

13 Plain GI sheet 26 gauge M2 #N/A 3.35 19.60 0.20 19.80 418.73 438.53 #N/A

14 Nails KG #N/A 1 5.85 0.06 5.91 119.78 125.69 #N/A

15 Tower bolt 6" Aluminium NO #N/A 0.2 1.17 0.01 1.18 100.57 101.75 #N/A

Prepared by: Approved by:

Checked by: Recommended by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

RATE OF MATERIAL AND LABOUR

Name of School: Shree Tribhuwan Secondary School


VDC: Dagatumdanda Ward No: 7 Tractor TPT dist (km): 65 Porter TPT dist (km): 0.3
Total rate of
Transportation Total rate of material
S.N ITEMS UNIT Quantity UNIT Wt. (Kg) Transportation by Porter Unit Rate of material
by Tractor transportation ( transportatio
+cost) Total Cost

16 Tower bolt 4" Aluminium NO #N/A 0.15 0.88 0.01 0.89 75.71 76.60 #N/A

17 Hinge (75 mm) NO #N/A 0.1 0.59 0.01 0.59 14.69 15.28 #N/A

18 Screw NO #N/A 0.005 0.03 0.00 0.03 1.02 1.05 #N/A

19 Hold Fast NO #N/A 0.25 1.46 0.02 1.48 19.21 20.69 #N/A

20 Handle (150mm) NO #N/A 0.15 0.88 0.01 0.89 22.6 23.49 #N/A

21 Hinge (150 mm) NO #N/A 0.2 1.17 0.01 1.18 31.64 32.82 #N/A

22 Locking set 250mm NO #N/A 0.3 1.76 0.02 1.77 242.95 244.72 #N/A

23 Rebar 8 mm dia. KG #N/A 1 5.85 0.06 5.91 115.26 121.17 #N/A

24 Roofing nail KG #N/A 1 5.85 0.06 5.91 119.78 125.69 #N/A

25 Transparent Pipe M #N/A 0.07 0.41 0.00 0.41 22.6 23.01 #N/A

26 Binding wire KG #N/A 1 5.85 0.06 5.91 119.78 125.69 #N/A

27 HDP Pipe 110 mm f 4 Kgf M #N/A 1.703 9.96 0.10 10.06 365.63 375.69 #N/A

28 HDP Pipe 63 mm f 4 Kgf M #N/A 1.25 7.31 0.08 7.39 152.55 159.94 #N/A

29 HDP Pipe 16 mm f 4 Kgf M #N/A 0.25 1.46 0.02 1.48 45.2 46.68 #N/A

30 Metal clip NO #N/A 0.2 1.17 0.01 1.18 15.82 17.00 #N/A

Total #N/A

Prepared by: Approved by:

Checked by: Recommended by:


Government of Nepal
Ministry of Education & Sports
District Education Office
Martadi, Bajura
&
SAVE THE CHILDREN-NORWAY/PEACEWIN, Bajura

SUMMARY OF COST

Name of project: School Toilet Block Construction


School block and wooden floor sitting construction.
Name of School: Shree Tribhuwan Secondary School
Village Dev. Committee: Dagatumdanda Ward no: 7 Tole: Kharbang
S.N DESCRIPTION PROJECT COMMUNITY TOTAL REMARKS

1.0 External Material #N/A


2.0 Transportation
By truck #N/A
By porter #N/A
2.0 Labour
Skilled Labour #N/A
Unskilled Labour #N/A
2.0 Local Material, collection & transportation #N/A
Sub total

Grand total 430000.00 #N/A #N/A

Prepared by: Checked by: Approved by:

Jr. Engineer Engineer District Education Officer


EFA Program, SCN/PEACEWIN EFA Program, SCN/PEACEWIN DEO, Martadi, Bajura District
Government of Nepal
Ministry of Education & Sports
District Education Office
Martadi, Bajura
&
SAVE THE CHILDREN-NORWAY/PEACEWIN, Bajura

SUMMARY OF COST

Name of project: School Toilet Block Construction


School block and wooden floor sitting construction.
Name of School: Shree Tribhuwan Secondary School
Village Dev. Committee: Dagatumdanda Ward no: 7 Tole: Kharbang
S.N DESCRIPTION PROJECT COMMUNITY TOTAL REMARKS
Date: Date: Date:
Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

ANALYSIS OF RATES

All kind of excavation work in hard clay soft morum boulder ( upto 30 cm) mixed soil. Disposal 10 mtr and lift
1.0 upto 15 mtr.Earthwork in excavation with 10m lead and 1.5m lift pipeline trench in : In Cu. mtr.

S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks

1.0 Labour

Unskilled labour Rs/day 280.00 0.800 224.00

Rate/m3 0.800 224.00 ###


###
Filling by ordinary soil (spreading with thickness of 15 cm and compacting soil with water sprinkle, lead 10 mtr), In Cu. Mtr.
2.0 Site clearence
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks

1.0 Labour

Unskilled labour Rs/day 280.00 0.500 140.00

Rate/m3 0.500 140.00 ###


###
3.0 Stone Masonry in Mud mortar (Lead 30 mtr and height upto 5 mtr.) In Cu. Mtr.

S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materils

Stone m3 900.00 1.100 990.00

Soil m 3
250.00 0.420 105.00

Sub total 1095.00

2.0 Labour

Skilled labour No 400.00 1.000 400.00

Unskilled labour No 280.00 2.250 630.00

Sub total 1030.00


Rate/m3 4.770 2125.00 ###

Prepared by: Approved by:

Checked by: Recommended by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

ANALYSIS OF RATES

###
4.0 Stone soling. In Cu. Mtr.

S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks

1.0 Materials

Stone m3 800.00 1.100 880.00

Sub total 880.00

2.0 Labour

Skilled labour No 400.00 1.000 400.00

Unskilled labour No 280.00 3.500 980.00

Sub total 1380.00


Rate/m3 5.600 2260.00 ###
###

6.0 Cement concrete (1:3:6) in foundation and wall (lead 30 mtr providing materials) In Cu. mtr.
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Cement Kg 13.22 220.000 2908.40


Sand m 3
900.00 0.470 423.00
Aggregate 20-40 mm m3 1650.00 0.890 1468.50
Sub total 4799.90
2.0 Labour
Skilled labour No 400.00 1.000 400.00
Unskilled labour No 280.00 4.000 1120.00
Sub total 1520.00
Rate/m3 226.360 6319.90 ###
###
7.0 Cement conrete in superstructure, deck slab, and beam. In Cu. mtr.
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Cement Kg 13.22 320.000 4230.40


Sand m3 900.00 0.445 400.50
Aggregate 10-20 mm m 3
1650.00 0.330 544.50
Aggregate 20-40 mm m 3
1650.00 0.520 858.00
Sub total 6033.40
2.0 Labour
Skilled labour No 400.00 0.800 320.00
Unskilled labour No 280.00 7.000 1960.00
Sub total 2280.00
Rate/m3 329.095 8313.40 ###

Prepared by: Approved by:

Checked by: Recommended by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

ANALYSIS OF RATES

###

8.0 Rebar (8 mm dia.) work for RCC (Cutting, bending, proper placement and binding, lead 30 mtr) In Kg.
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Rebar 8 mm dia. Kg 80.23 1.050 84.24

Sub total 84.24


2.0 Labour
Skilled labour No 400.00 0.012 4.80
Unskilled labour No 280.00 0.012 3.36
Sub total 8.16
Rate/m3 1.074 92.40 ###
###

10.0 20 mm thick cement sand plastering (1:4). In Sq. mtr.

S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Cement Kg 13.22 8.100 107.08


Sand m 3
900.00 0.022 19.80
Sub total 126.88
2.0 Labour
Skilled labour No 400.00 0.140 56.00
Unskilled labour No 280.00 0.190 53.20
Sub total 109.20
Rate/m2 8.452 236.08 ###
###
11.0 3 mm Cement Punning (1:1) In Sq. mtr.

S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Cement Kg 13.22 3.360 44.42


Sand m 3
900.00 0.002 2.07
Sub total 46.49
2.0 Labour
Skilled labour No 400.00 0.100 40.00
Unskilled labour No 280.00 0.100 28.00
Sub total 68.00
Rate/m2 3.562 114.49 ###

Prepared by: Approved by:

Checked by: Recommended by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

ANALYSIS OF RATES

###
12.0 Flush rule pointing in stone masonry (1:3) In Sq. mtr.

S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Cement Kg 13.22 3.060 40.45


Sand m 3
900.00 0.006 5.67
Sub total 46.12
2.0 Labour
Skilled labour No 400.00 0.100 40.00
Unskilled labour No 280.00 0.140 39.20
Sub total 79.20
Rate/m2 3.306 125.32 ###
###

In Sq. mtr.
14.0 Complete roofing work with CGI sheet providing materials.
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

CGI sheet 26 gauge m2 349.05 1.200 418.86


Bitumen washer m 2
0.57 5.500 3.11
L-hook No 20.34 2.500 50.85
Roofing nail Kg 105.09 0.050 5.25
Sub total 478.07
2.0 Labour
Skilled labour No 400.00 0.110 44.00
Unskilled labour No 280.00 0.125 35.00
Sub total 79.00
Rate/m3 9.485 557.07 ###
###
15.0 Beam, Rafter etc making from wood and fixing. In Cu. mtr.
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Local wood Cum 12500.00 1.050 13125.00


Nails Kg 105.09 1.000 105.09
Sub total 13230.09
2.0 Labour
Skilled labour No 400.00 17.650 7060.00
Unskilled labour No 280.00 1.760 492.80
Sub total 7552.80
Rate/m3 21.460 20782.89 ###

Prepared by: Approved by:

Checked by: Recommended by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

ANALYSIS OF RATES

###
17.0 38mm frame panelled shutter making for door (0.85 x2.00m)
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Local wood Cum 12500.00 0.087 1087.50


Hinge (150 mm) No 31.70 6.000 190.19
Tower bolt 4" Aluminium No 27.12 1.000 27.12
Tower bolt 6" Aluminium No 44.07 2.000 88.14
Hinge (75 mm) No 15.82 3.000 47.46
Locking set 250mm No 142.38 1.000 142.38
Screw No 1.15 7.000 8.07
Handle (150mm) No 24.86 2.000 49.72
Sub total 1640.58
2.0 Labour
Skilled labour No 400.00 10.400 4160.00
Unskilled labour No 280.00 1.040 291.20
Sub total 4451.20
Rate/m3 33.527 6091.78 ###
###
18.0 Wood work for Chaukhat In Cu. mtr.
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Local wood Cum 12500.00 1.100 13750.00


Hold fast No 19.28 92.000 1773.76
Screw No 1.15 184.000 211.60
Sub total 15735.36
2.0 Labour
Skilled labour No 400.00 34.000 13600.00
Unskilled labour No 280.00 3.400 952.00
Sub total 14552.00
Rate/m3 314.500 30287.36 ###

Prepared by: Approved by:

Checked by: Recommended by:


Government of Nepal
Ministry of Education
District Education Office
Baglung
&
Gaja Youth Club, Baglung/Save the Children -Norway

ANALYSIS OF RATES

###
19.0 Wood work for 25mm thick Eaves board including fixing. In Sq. mtr.
S.n Materials and labours Unit Rate Rs/Unit Quantity Cost Rs. Remarks
1.0 Materials

Local wood Cum 12500.00 0.0275 343.75


Nails kg 105.09 1.000 105.09
Sub total 448.84
2.0 Labour
Skilled labour No 400.00 0.143 57.20
Unskilled labour No 280.00 0.014 3.92
Sub total 61.12
Rate/m3 1.185 509.96 ###
###

Prepared by: Approved by:

Checked by: Recommended by: