Name of Work : Reinstallation of AGL fittings & related works during RWY Intersection Overlay.

BOQ
Sr.No Item Description UOM
A Supply
Supply of Secondary cable 2Cx4Sq.mm 600 Volt Stranded Cu. Conductor RMT
1 cable Upen/ Nexans/Untel Make in conformity to FAA 150/5345 - 7D

Supply of secondary connector Elfa make KD 501(including male and female Nos
2 set)
3 Supply of Shallow base bottom boxes for following AGLlight fittings
a.Inset Edge Light /SFL: 330 mm
b.TDZ & Centre Line light : 230 mm

B Installation :
Cleaning of Secondary conduit for passage of AGL cable with means of jet RMT
1 blast water, etc
Laying/Installation testing commissioning of AGL secondary cable in the RMT
2 HDPE/GI pipe from AGL chamber to RWY AGL lights i/c pulling out of
exisitng secondary cable
Installation, testing and commissioning of Secondary Connector kits suitable Nos
for connecting isolating transformers secondary with 1 kV grade
2Cx4 sq.mm Cu. XLPE cable.( Make Efla) for Taxiway centerline light, edge
3 lights, stopbar lights, guard lights, runway edge lights at the chembers only.

Dismantling/removing of AGL fitting top section and handing over to MIAL Nos
4 Maintenance dept i/c removal of shallow base bottom box
Installation of shallow base bottom section as per the drawing including Nos
5 coring ,filling of compound as per the ICAO/ FAA standards. Including
removal of all the debris generated during the installation/coring works
Installation of Top section of AGL fittings with proper connection, testing Nos
6 commissioning etc
Refurbishment of shallow/CI boxes including sand blasting for AGL fixtures Nos
7 and handing over to MIAL.

Note: The work need to be carried out in close co-ordination & with progress of re-carpeting work by c
Qty Cost/Unit Amount Time line Vendor

20,000 130 2,600,000

Neaxans/ Untel
450 700 315,000
15th January 19
Efla

25 4,200 105,000 ADB Safegate


200 2,800 560,000
A: Rs. ₹ 3,580,000.00

5,000 50 250,000

20,000 50 1,000,000

450 400 180,000

From 7th Feb 19-


30th March 19 ( 22
days - effective 4 AMA
Hours on every
225 600 135,000 closer)

225 13,000 2,925,000

225 200 45,000

225 500 112,500

B: Rs. ₹ 4,647,500.00
Total : Rs. ₹ 8,227,500.00