TECHNICAL SPECIFICATIONS
SECTION B
SPECIAL PROVISIONS
Philipps Technical
Page 1
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
TABLE OF CONTENTS
SECTION B ...................................................................................................................................................... 1
SPECIAL PROVISIONS ..................................................................................................................................... 1
INTRODUCTION ............................................................................................................................................. 7
PART A – FACILITIES FOR THE ENGINEER..................................................................................................... 10
A.1 REQUIREMENTS........................................................................................................................... 10
A.2 MEASUREMENT AND PAYMENT ................................................................................................. 21
PART B – OTHER GENERAL REQUIREMENTS ............................................................................................... 24
B.1 OFFICES, SHEDS, STORES AND WORKMEN’S ACCOMMODATION FOR CONTRACTOR ............... 24
B.2 MEDICAL ROOM AND FIRST AID FACILITIES ................................................................................ 24
B.2 MOBILIZATION AND DEMOBILIZATION ....................................................................................... 24
B.3 CONSTRUCTION SAFETY AND HEALTH ........................................................................................ 25
B.4 TRAFFIC CONTROL SIGNS AND BARRICADES DURING CONSTRUCTION ..................................... 26
B.5 CONSTRUCTION AREA TRAFFIC CONTROL DEVICES .................................................................... 27
B.6 SETTING OUT ............................................................................................................................... 32
B.7 REMOVAL, RELOCATION, REPLACEMENT, IMPROVEMENT AND RECONSTRUCTION OF
PUBLIC UTILITIES AND INCLUSION OF SITE FACILITIES ................................................................ 33
PART C- EARTHWORKS............................................................................................................................... 36
100.3 METHOD OF MEASUREMENT...................................................................................................... 36
100.4 BASIS OF PAYMENT ..................................................................................................................... 36
ITEM 101 REMOVAL OF STRUCTURES AND OBSTRUCTIONS ...................................................................... 38
101.1 DESCRIPTION ............................................................................................................................... 38
101.4 BASIS OF PAYMENT ...................................................................................................................... 38
ITEM 103 STRUCTURE EXCAVATION ........................................................................................................ 40
103.1 DESCRIPTION ............................................................................................................................... 40
103.2 CONSTRUCTION REQUIREMENTS................................................................................................ 40
103.3 METHOD OF MEASUREMENT...................................................................................................... 41
ITEM 104 EMBANKMENT ..................................................................................................................... 42
104.2 MATERIALS REQUIREMENTS ....................................................................................................... 42
104.3 CONSTRUCTION REQUIREMENTS................................................................................................ 42
104.4 METHOD OF MEASUREMENT...................................................................................................... 43
104.5 BASIS OF PAYMENT ..................................................................................................................... 43
ITEM 105 SUBGRADE PREPARATION ................................................................................................... 44
105.2 MATERIAL REQUIREMENTS ........................................................................................................ 44
105.4 METHOD OF MEASUREMENT...................................................................................................... 44
105.5 BASIS OF PAYMENT .................................................................................................................... 44
PART D SUBBASE AND BASE COURSES..................................................................................................... 46
ITEM 200 AGGREGATE SUBBASE COURSE ........................................................................................... 46
200.2 MATERIAL REQUIREMENTS ......................................................................................................... 46
200.4 METHOD OF MEASUREMENT...................................................................................................... 47
200.5 BASIS OF PAYMENT ..................................................................................................................... 47
PARTE SURFACE COURSES ...................................................................................................................... 49
Philipps Technical
Page 2
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 3
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 4
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 5
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
INTRODUCTION
Philipps Technical
Page 6
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
INTRODUCTION
The Specifications describe in detail the work to be executed, the character and quality of
materials, workmanship and the specific responsibilities of the Contractor that are not covered by
the Conditions of Contract. It includes the Technical Specifications, the General Specifications and
Supplemental Notices or Addenda, if any, and shall be read in conjunction with the Plans and all
the other Contract Documents.
Pertinent notes appearing in the Contract Plans or Drawings shall also be considered as part and
parcel of the Technical Specifications.
Any further amendments to the Technical Specifications and to any other Document, if necessary,
will be furnished to the Contractors by means of Supplemental Notice or Addendum.
The Supplemental Specifications shall consist of modifications and additions to the DPWH Standard
Specifications (Volumes II), to adapt the latter to actual conditions and/or requirements relative to
this project. Some of these modifications and additions may actually be of general application but
in the absence of a supplemental specifications adopted by the DPWH, subsequent to the
publication of the DPWH Standard Specifications, 2013 Edition, Volume II – Highways, Bridges and
Airports and DPWH Standard Specifications for Public Works Structures, these Supplemental
Specifications have been included in the Technical Specifications of this project.
The Supplemental Specifications for this project shall consist of modifications and additions to the
DPWH Standard Specifications as follows:
(1) Modifications in the specification of standard work items under Part A to Part I of the
DPWH Standard Specifications 2013 Edition, Volume II – Highways, Bridges and Airports.
These modifications are carried out without changing the “number” and “name” of each
of such standard work items.
Philipps Technical
Page 7
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
(2) Specifications for additional items of work, respectively for Part A to Part H of the DPWH
Standard Specifications.
The Special Provisions are indicated on the Technical Specifications and shall consist of
specifications for work Items that are based on applicable Department Orders issued by the
DPWH or work items that are not stated in the DPWH Standard Specifications but shall be used
for the project.
The Item Number of the Special Provisions is distinguished by placing the symbol “SPL” before its
designated Number.
For Specifications of other special items of work not included in Volume II of the Technical
Specifications of this project, the corresponding standard specifications shall be deemed to apply:
Philipps Technical
Page 8
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART A
FACILITIES FOR THE
ENGINEER
Philipps Technical
Page 9
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
A.1 REQUIREMENTS
The Contractor shall provide and maintain until final completion and acceptance of the
Project one (1) unit combined Field Office and Laboratory Building and One (1) unit Living
Quarters for the Engineer on a rental basis, fully furnish to include the supply furniture,
equipment, apparatus and appliances as specified below, including all the necessary
electricity, water and drainage services for the use of the Engineer and his staff for twenty
four (24) hours a day for all days of the contract period.
The size of the Office/Laboratory Building must be at least 100 square meters and 100
square meters for the Living Quarters.
It shall be understood that if the Contractor cannot provide the articles as described or
intend to supply equipment substitutes, he should secure the approval of the Engineer, and
if such approval is granted it will be on the condition that adjustment in prices shall be
effected based on the submitted receipted invoices of the Contractor.
The Offices and Laboratory Building shall be ready for occupancy and used by the Engineer
within fifteen (15) calendar days of commencement of works.
The Contractor shall furnish the Office and laboratory with, but not limited to, the following
equipment and furniture:
a. Office Furniture, Equipment and Supplies (to be supplied on the 1st month)
a.1 Jr. Executive Table and Chair - 10 each
a.2 Visitor’s Chair - 6 each
a.3 Filing Cabinet, 4 drawers, fire resistant - 4 each
a.4 Steel Filing Cabinet for Horizontal Plans (5 drawers) - 1 each
a.5 Conference Table (10 pax capacity) - 1 each
a.6 Conference Chair - 10 each
a.7 Erasable White Board - 1 each
a.8 Working Bench/Chair - 6 each
a.9 Window Type Air Conditioner 1.5 HP - 3 each
a.10 Computer with Printer - 3 each
a.11 Fire Extinguisher, 10 lbs. - 2 each
a.12 Water Dispenser Hot and Cold - 1 each
a.13 Digital Camera with Micro SD Card - 1 each
a.14 Electric Stand Fan (16” dia. Blade) - 2 each
Philipps Technical
Page 10
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 11
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Computer Desktop (branded) – 6th generation Intel Core i7 – 6700 Processor (8M
Cache, up to 4.0GHz); 16GB DDR3L – 1600 DIM RAM (4GBx4); 2TB 7200 RPM SATA 6G
1st Hard Drive; SuperMulti DVDRW; HDMI, VGA and Network (RJ45) Interfaces with at
least six (6) USB 3.0 Ports; 4GB NVIDIA GeForce GTX 745 DDR3 FH GFX, 23 inch IPS
Monitor; Wired Multimedia Keyboard and Optical Mouse; On-board 10/100/1000Mbps
(Gigabit) Ethernet Support; 7-in-1 Media Card Reader.
Living Quarters
Philipps Technical
Page 12
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
rice plates, pitchers, ash trays, casserole, frying pan and canisters
c.19 Water Dispenser Hot and Cold - 1 each
c.20 Emergency Light - 2 each
c.21 Mop Head - 6 each
c.22 Waste Baskets - 5 each
c.23 Broom (Tambo) - 6 each
d. Furniture, Equipment and Supplies
The furnishing and equipment provided by the Contractor shall conform to the best
standard for the required types. The Contractor shall be responsible for replacing
and/or restoring furnishing and equipment which become damaged from cause or
become worn out , lost, misplaced or stolen. On completion of the Contract they shall
be turn over to the SBMA in good working conditions except the laboratory equipment
, apparatus, etc. utilized by the Contractor on rental basis, shall be turned over to the
Contractor after completion of the project.
The Contractor shall provide the following Field Office and Laboratory staff:
Laboratory Technician - 1
Laboratory Encoder - 1
Admin Officer/Encoder - 1
Instrument Man - 1
Survey Aides - 2
General Services Assistant - 1
(a) All tests shall be carried out at an accredited independent testing laboratory approved
by the Engineer except minor test to be carried out at site by the Contractor. The
Contractor shall provide qualified and experienced laboratory staff to make all the
necessary arrangement for the supply, collection and delivery of sample materials, for
such independent laboratory to keep all records of testing made by the independent
laboratory and other necessary documents regarding Quality Control of materials
incorporated in the Works.
(b) The testing equipment/apparatus and supplies provided by the approved accredited
independent testing laboratory shall include all that is necessary to carry out the tests
Philipps Technical
Page 13
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
listed below and any other tests required by the Contract. Unless otherwise stated, the
test shall be as specified in the latest edition of AASHTO.
(c) The approved independent testing laboratory shall provide all the necessary
equipment, appliances, etc. to carry out the under listed testing.
TEST REFERENCE
(AASHTO unless STANDARD METHOD TEST FOR:
otherwise stated)
T-87 Dry Preparation of Disturbed Soil Aggregate Sample for
Test
D1883 AASHTO Test for Bearing Ratio of Laboratory Compacted Soils (CBR
T-193
TEST REFERENCE
(AASHTO unless STANDARD METHOD TEST FOR:
otherwise stated)
Sampling Stone, Slag, Gravel, Sand and Stone Block for use
T-2 as Highway Materials
Philipps Technical
Page 14
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
TEST REFERENCE
(AASHTO unless STANDARD METHOD TEST FOR:
otherwise stated)
T-22 Compressive Strength of Cylindrical Concrete Specimens
TEST REFERENCE
(AASHTO unless STANDARD METHOD TEST FOR:
otherwise stated)
T-140 Sampling Bituminous Materials
Philipps Technical
Page 15
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
(d) To carry out the above tests, the approved independent testing laboratory shall furnish
all the necessary miscellaneous field and laboratory equipment for the testing of work
in the contract, including but not limited to the following:
ATTERBERG LILITS
Philipps Technical
Page 16
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PROCTOR TESTS
FIELD DENSITY
Philipps Technical
Page 17
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 18
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
1 each Pick
Technical Publications and Reference are basic Contractor’s guide provided to the Engineer
and is considered as Contractor’s property.
Philipps Technical
Page 19
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
It shall be understood that if the Contractor cannot provide the articles as described on
time, the Engineer has the right to secure equivalent substitute on condition that the
amount spent supported by the receipt on invoices, and shall be refundable from the
Contractor.
Delete “listed in the special provisions” in the second line of the first paragraph.
The Contractor shall provide and keep available at all times for the duration of the contract
one (1) unit, brand new service vehicle, 14-seater Commuter Van, diesel engine, loaded
with air-conditioner. The vehicle shall have its usual accessories of spare tire, early warning
devices, fire extinguisher, tools, etc. During the period that the vehicle is not yet available,
the Engineer may rent equivalent substitute vehicle, the cost including the supply of fuel,
lubricants, salary of driver and other maintenance and repair costs shall be shouldered by
the Contractor. The vehicle provided by the Contractor, after the completion of the
contract shall be turned over to SBMA.
The Contractor shall also provide and keep available at all times for the duration of the
contract one (1) unit Service Vehicle for the Engineer (Rental basis), diesel engine, loaded
with air-conditioner. The vehicle shall have its usual accessories of spare tire, early warning
devices, fire extinguisher, tools, etc. The supply of fuel, lubricants, salary of driver and other
maintenance and repair costs shall be shouldered by the Contractor.
The Contractor shall provide for the proper surveying activities under the contract, the
following minimum personnel, equipment, instruments and apparatus:
All equipment, instruments and apparatus to be provided shall require prior approval of the
Engineer. The survey equipment, instruments and apparatus provided by the Contractor
shall be on rental basis
Philipps Technical
Page 20
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
A.2.1 Measurement
1. The Contractor will provide (on Rental Basis) and maintain a Field Office and Laboratory
Office with a total area of 200 square meters. Payment will be per month.
2. The quantities for the provision of the furniture, office equipment, supplies and
appliances shall be the number of each type of furniture, office equipment, supplies
and appliances as listed. Payment shall be per lump sum.
3. Maintenance of the Field office, Laboratory and Living Quarters will be paid from the
time the Engineer occupies the building until completion and acceptance of the Project.
Payment shall be per month.
4. The quantity for the purchase of the vehicle for the Engineer shall be the total number
of vehicles the Contractor will provide to the Engineer. Payment shall be “Each”.
5. The operation and maintenance of the vehicle for the Engineer shall be paid from the
date the Engineer is supplied with each type of vehicle until the completion of the
contract. Unit of Measurement is “Month”.
6. Provision for the survey equipment (on Rental Basis) for the assistance to the Engineer
and operation and maintenance for the said instruments shall be paid on monthly
basis.
7. The quantities for progress photographs shall be the number of photographs selected
and provided as progress photographs. The unit of measurement is “Each”.
A.2.2 Payment
Philipps Technical
Page 21
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
the Engineer
Philipps Technical
Page 22
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART B
OTHER GENERAL
REQUIREMENTS
Philipps Technical
Page 23
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The selection of the site shall be the responsibility of the Contractor and shall be approved
by the Engineer. It is entirely up to the Contractor to make whatever arrangements he
deems necessary with the landowners regarding the use of land for the purpose of erecting
camps, workshops, garages, stockpiling of materials, locations of plant, housing of labor and
staff, welfare facilities, etc. All costs incurred in connection with the rental or lease of such
land shall be at the Contractor’s expense.
The Contractor shall be solely responsible for the erection, maintenance and subsequent
disposal of whatever facilities he deems necessary to execute the Works.
The Contractor shall not be permitted to erect temporary buildings or structures within the
road right-of-way without prior written approval from the Engineer.
Delete Section B.2 Medical Room and Facilities in its entirety and replace with the following:
B.2.1 Description
Mobilization, the Contractor shall perform all works necessary to transport equipment to
the site to be used for all purpose necessary for the realization of the Works.
Demobilization; when the Contractor has moved out equipment that is no longer necessary
and has completed its functions. The area shall then be cleaned and temporary
constructed offices, shops, accommodation, etc. of the Contractor shall be dismantled
properly to the satisfaction of the owner and acceptable to the ENGINEER.
B.2.2a Mobilization
1. The Contractor shall begin mobilizing his construction equipment as soon as the site(s)
of his equipment yard and other areas have been formalized.
2. Mobilized equipment required in the contract shall be duly listed for approval and shall
not be removed from the site by the Contractor without prior written approval by the
ENGINEER.
All Contractor’s mobilization costs such as planning and designing all temporary works and
facilities and making submittal to the ENGINEER, recruiting and transferring staff, obtaining
all Government licenses, permits, clearances, etc., clearing and grading areas for temporary
and any other costs involved in preparing to carry out the permanent works shall not be
paid separately.
Philipps Technical
Page 24
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
On completion of the Project, the Contractor shall dismantle all improvements erected on
the leased areas; clear all to the satisfaction of the lot owners, rentals due fully paid and
approved by the ENGINEER.
Payment for Mobilization and Demobilization shall be 75% and 25% respectively.
Within one month of his arrival on site the Contractor shall submit a Health and Safety Plan
with operational details of his proposals to the ENGINEER for his approval.
1. Due precautions shall be taken by the Contractor, at his own cost, to ensure the safety
and protection against accidents of all staff and labour engaged on the Works, local
residents in the vicinity of the Works, and the public traveling through the Works.
2. The Contractor shall have on his staff on Site a designated full-time officer qualified to
promote and maintain safe working practices. This officer shall have authority to issue
instructions and shall take protective measures to prevent accidents, including but not
limited to the establishment of safe working practices and the training of staff and
labor in their implementation.
3. The Contractor shall be responsible for all costs including medical treatment, transport,
accommodation etc. incurred by any member of the public or his labor forces whether
on direct contract or sub-contract as a result of injuries or illness arising from the
execution of the Works.
1. The Contractor shall at his own expense provide protective clothing and safety
equipment to all staff and labor engaged on the Works to the satisfaction of the
ENGINEER.
2. If the Contractor fails to provide such clothing and equipment the Employer shall be
entitled to provide the same and recover the cost from the Contractor.
Philipps Technical
Page 25
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The Contractor shall at his own expense provide first aid equipment at all camps and work
sites to the satisfaction of the ENGINEER, and shall ensure that at all camps and work sites
where 40 or more persons are engaged on the Works there shall at all times be a person
qualified in first-aid with access to appropriate first-aid equipment.
Health and Safety will be measured and paid in accordance with the current DPWH
Department Order, Series 2005: Re “Guidelines for the Implementation of DOLE D.O. No.
13, Series of 1998, Governing Occupational Safety and Health in the Construction Industry”.
B.4.1.1 The Contractor shall construct and maintain detours wherever the work will interfere with
traffic on existing roads, footways or other ways over which there is public or private right-
of-way, until such time as permanent diversions to serve such traffic shall have been
completed. No detours shall be constructed and no traffic diverted until the Contractor’s
proposals have been approved by the Engineer and by the appropriate government
authorities. Prior to the commencement of the construction and of the use of detours, the
Contractor shall provide the Engineer with a full photographic record of the existing roads,
pathways, etc. as required by the Engineer.
B.4.1.2 No work that will in any way inconvenience the travelling public shall be started until
adequate provision, satisfactory to the Engineer, shall have been made to divert or by-pass
traffic in safety and comfort. No road shall be closed to the public except by permission in
writing from the Engineer and the appropriate authorities. Where traffic conditions permit,
single lane operation may be permitted by the Engineer. When the road under construction
is being used by the travelling public, special attention shall be paid to traffic conditions so
that the public can travel in comfort and safety without undue delay. Materials stored upon
the roadway shall be so placed and the work shall be so conducted as to cause as little
obstruction as possible to the travelling public.
B.4.1.3 All detours shall be maintained in good condition at all times of and shall, where possible
and where not specified to be a higher standard, have a total width of at least 6 meters and
provided with a graveled surface having a minimum compacted thickness of 80mm. Where
existing public or private roads are used as detours, the same shall be maintained in good
riding condition at all times and just before completion of the Contract, such roads shall be
Philipps Technical
Page 26
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
restored to a condition not less satisfactory than that existing prior to the commencement
of the Works.
B.4.1.4 After receipt of the Notice to Proceed and official handing over of road sections, the
Contractor shall assume the responsibility for maintaining the road sections scheduled for
Construction under this Contract. This obligation shall extend also to public and private
roads outside the Contract limits which are used as access or haul roads by the
Contractor. Maintenance shall consist of but not limited to routine patching, repairs and
correction of deformations on asphalt and concrete surfaced road, and cycling grading at
the Contractor's expense. Maintenance and repair work shall be carried out in accordance
with accepted practices. Any failure of the Contract in the performance of these works
shall entitle the Engineer to carry out such works as deemed necessary and to charge the
Contractor with the full costs thereof plus ten percent (10%) of such cost, which sum shall
be deducted from any money due or which may become due to the Contractor under the
Contract.
B.4.1.5 Proper detour and construction signing and the employment of qualified flagmen will be
the responsibility of the Contractor when required for safety of the traveling public or when
directed by the Engineer's Representative.
B.4.2.1 The Contractor shall at all times during the Contract provide, erect and maintain at
his own expense such barricades, warning light, danger signals, reflectors, signs and
watchmen as may be required by the authorities or deed necessary by the Engineer.
B.4.2.2 Barricades and signs shall be constructed and used in accordance with the
requirements of the Engineer. All barricades, fences and such other aids as are required
shall be reflectorized and shall conform to the regulations of the DPWH and shall be
illuminated at night by lanterns.
B.4.2.3 The Contractor shall appoint, subject to the approval of the Engineer's Representative, a
responsible member of his staff to inspect daily traffic aids within the site and to
arrange such cleaning and repair as the Engineer considers necessary to maintain the
proper effectiveness of these traffic aids at all times.
.
Except as stated otherwise, payment for the works involved in these Special Provisions
are deemed to be included in pay items for other items of work included in the
Contract's Bill of Quantities.
B.5.1 General
Clause 75 "Public Convenience and Safety" of the 2004 DPWH Requirements and
Conditions (Volume I) sets forth the Contractor's responsibilities for public convenience
and public safety and the requirements concerning flagging and traffic devices.
Philipps Technical
Page 27
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
"The Contractor shall at all time so conduct his work as to assure the safety and
convenience of the general public and the residents near the work site and to assure the
protection of persons and property.
Care shall be taken to regulate the operations so as to protect visitors and campers in
the National Forest or Park or other Government reservation if affected. No road shall
be closed by the Contractor to the public except by written permission by the Engineer.
The Contractor will provide, erect and maintain at his own cost all necessary barricades,
suitable and sufficient lights, danger signals, signs and other traffic control devices, and
shall take all necessary precautions for the protection of the Works and safety of the
public Highways closed to traffic shall be protected by effective barricades, and
obstructions shall be illuminated during the hour of darkness. Suitable warning signs shall
be protected to properly control and direct traffic.
The Contractor shall erect warning signs in advance of any place on the project where
operations may interfere with the use of the road by traffic, and at all intermediate
points where the new work crosses or coincides with an existing road.
The Contractor shall furnish, erect, maintain and remove when directed any information
identification signs shown on the Plans. Warning sign shall be posted, whoever,
directed, during blasting operations."
B.5.2 Flaggers
Flaggers while on duty and assigned to traffic control or to give warning to the public that a
bridge and/or highway is under construction and of any dangerous conditions to be
encountered as a result thereof, shall perform their duties and shall be provided with the
necessary gear so that they can be easily seen by approaching traffic.
The provisions in this Sub-Clause B.5.2 shall in no way relieve the Contractor from his
responsibility for providing for the safety of the public as provided in Clause 75 of the
Conditions of Contract
B.5.3 Barricades
Barricades shall generally be used in conjunction with signs at or near hazards for the
control or diversion of vehicular, pedestrian, or other traffic. Barricades shall consist of
rails at least 200 mm wide mounted at a height of between 1,000 to 1,200 mm on fixed
or portable posts and shall be constructed of lightweight commercial quality materials, as
approved by the Engineer. The color of the rail shall be either one of the following
combinations.
Philipps Technical
Page 28
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
If the barricades are displaced or are not in an upright position, from any cause, said
barricades shall immediately be replaced or restored to their original location, in an
upright position, by the Contractor.
The color of the flashing lamps shall be restricted to yellow (amber). They shall not be
used to delineate the limits of a hazard of trafficable route. Their use shall be limited to
the following circumstances:
a) Single flashing yellow (amber) lamps may be used to draw attention to a sign, barrier,
or hazard, and shall be so located that not more than two (2) lamps are visible to
approaching traffic at any one time.
b) Yellow (amber) flashing lamps of the routing reflector type shall be used only on
emergency or service vehicle while they actually cause an obstruction or hazard to
road traffic. Permission of the relevant authority must be obtained.
c) A lamp having twin alternate flashing yellow (amber) elements may be used for the
same purpose and under the same conditions as the single yellow (amber) lamps
described in (a) above, provided it does not conflict with any regulatory traffic control
device.
Non-flashing yellow (amber) lamps shall be used to define the limits of usable road on a
through route, side tract or detour, and to define the limits of a hazard or non-
trafficable construction area.
B.5.6 Delineators
At the discretion of the road authority and subject to any limitation imposed by traffic
laws and regulation, a proportion of non-flashing yellow (amber) or red lamps may be
replaced by portable delineators of the same color.
Portable delineators, including the base, shall be composed of a material that has
sufficient rigidly to remain upright when unattended and shall be either flexible or
collapsible upon impact by a vehicle. The base shall be sufficient weight or shall be
anchored in a manner such that said delineator shall remain in an upright position.
If the portable delineators are displaced or are not in an upright position, from any cause,
said delineators shall immediately be replaced or restored to their original location, in an
upright position, by the Contractor.
Philipps Technical
Page 29
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
above the roadway surface. The reflective bands shall be visible at 300 meters at vision of
or corrected to
20/20.
Only one (1) type of portable delineator shall be used on the project. The type of portable
delineator proposed for use on the project shall be submitted to the Engineer for approval
prior to placement on the project.
The term "Construction Area Signs" shall include all temporary signs required for the
direction of public traffic through or around the work during construction.
Construction area signs shall be selected and located in accordance with established
standards and practices and as directed by the Engineer.
The Contractor shall clean all construction area sign panels at the time of installation and
as often thereafter as the Engineer determines to be necessary.
Design. Standard construction area signs are shown on the Plans. A special sign may
only be used if the design conforms to the following:
a) Message shall be brief and concise as possible, using the maximum size of legend
which can be accommodated.
c) The shape and color of the sign shall conform to that of a standard sign used for a
similar purpose.
a) BRIDGE WORK AHEAD - The "BRIDGE WORK AHEAD" sign shall be used to give
advance warning of any bridge construction or repair which creates a temporary
hazard.
b) DETOUR AHEAD -The "DETOUR AHEAD" sign shall be used to given advance warning
of a detour from the normal direction of the road.
c) BRIDGE CLOSED- The "BRIDGE CLOSED" sign shall be placed on the road pavement
where the bridge is closed to the traffic facing the sign. Usually this sign will need to
be supplemented by a sign "DETOUR".
d) DETOUR - The "DETOUR" sign shall be used to indicate the direction and point by
which traffic should leave the through route to detour via existing roads or streets
which by-pass an obstruction in the main route. On roads carrying fast or heavy
traffic or where sign distance is limited, it will usually be necessary to use the advance
sign "DETOUR AHEAD" in conjunction with this sign.
Philipps Technical
Page 30
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
e) Channelizers
Traffic Cones. Traffic Cones shall be at least 300 mm high and at least 150 mm wide at the
base of the cone. They shall be of good commercial quality and fluorescent red-orange.
Then used at night, a minimum of one-third of the surface area visible to approaching
traffic shall be covered with yellow reflective material.
Flexible or Collapsible Posts. Flexible or collapsible posts of suitable design may be used.
a) in place of rigid barrier posts if the probability of their being accidentally struck
or displaced by traffic is high; or
B.5.8.1 Measurement
a) Works prescribed in Section B.1 shall not be measured and paid for separately, same
shall be deemed to be included in Pay Items for other Items of Work.
b) Works prescribed in Section B.2 shall be measured and paid for on a lump sum basis.
c) Works prescribed in Section B.3 shall be measured and paid for on a lump sum basis.
d) Furnishing and installing construction area for traffic control devices as prescribed
under Clause B.4 such as barricades, flashing lamps, non flashing lamps and other
aids required which are used to fulfill the Contractor's responsibility to provide for the
safety of traffic and the public during construction in accordance with the
requirements of Clause 75 of the Conditions of Contract, shall not be paid for
separately and shall be deemed to be included in the pay items of other work.
Flaggers, construction area signs and channelizers shall be in accordance with the
specification and as directed by the Engineer. Cost of furnishing flaggers including the
necessary equipment and cost of furnishing, erecting, maintaining, moving and
removing construction area signs and channelizers shall be as determined in
accordance with Sub Clause 102(5), Erecting. Provisional sum (Sub-Section 4.6 of
Philipps Technical
Page 31
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
the Conditions of Particular Applications) and shall be charged against the Provisional
Sum provided for in Item B.4 - Construction Area Traffic Control Devices.
c) The maintenance of traffic shall include the furnishing of barricades, warning lights,
danger signals, reflectors, signs and the posting of watchmen and/or flagmen in
accordance with Section B.5, Construction Area Traffic Control Devices. This work
shall be paid for on a monthly basis included in the Bid Schedule which price and
payment shall constitute full compensation for furnishing and placing all materials
including all labor tools and incidentals necessary to complete the works prescribed in
this Item.
B.6.1 The Contractor shall set out the works in relation to survey stations, markers, reference
pegs and benchmarks, which have been previously established. Great importance is
attached to these stations and the Contractor shall safeguard and protect them from
harm at all times until completion of the works. The Contractor shall be paid
responsible for the establishment of any further survey stations, markers, reference pegs,
and benchmarks as necessary for the proper setting out.
B.6.2 Benchmarks and reference points shall be established by the Contractor. The stationing
shall be scratched or clearly marked with paint on the surface of the concrete or otherwise
clearly marked as to the satisfaction of the Engineer.
B.6.3 Should the Contractor discover any error in line or level in the basic setting out, he shall at
once notify the Engineer who will then issue amended drawings or instructions regarding
the correction of the error.
B.6.4 The Contractor shall establish temporary benchmarks at intervals along the road not
exceeding 200 m and shall provide the Engineer with a schedule of their levels.
B.6.5 The Contractor shall set out the roads line and level, the tops of cuttings and toes of
embankments, at intervals of not more than 50 m or such lesser intervals on horizontal
and curves as the Engineer may require. Reference pegs shall be provided clear of the
road in such positions that the centerline or level can readily be re-established at any time.
B.6.6 The Contractor shall after or in connection with staking out, survey the terrain along the
alignment, shall submit to the Engineer for his approval, a profile and cross-sections
generally at 20 m intervals and at intermediate points where make changes in slope
occurs; cross-section intervals may be increased to 40 m in uniform terrain at the
discretion of the Engineer. The Contractor shall be given by the Engineer not less than
24 hours notice of his intention to commence any setting out or surveying longitudinal
profiles or cross-sections in order that arrangements can be made for checking.
Checking of work by the Engineer shall not in any way relieve the Contractor of his
responsibility under Clause 17.1 of the General Conditions of Contract. After having
been approved by the Engineer, the profile and cross-sections shall form the basis for
measurement and payment.
Philipps Technical
Page 32
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The Contractor shall be responsible for measuring the horizontal detection angles. No
extra payment shall be made for any deviation from the angular measurement shown
on the Drawings.
Where removal, relocation, replacement and inclusion of public utilities and site facilities
are essential to the Works under the Contract, but such works are not to be executed by
the Contractor but by the respective owners of the utilities. Any damage cause by removal
and relocation operation shall be replaced by utility owners. The Contractor is instructed to
recognize the following stipulations:
b) No work shall commence on any part; portion or section of the Site of the Work that
may affect or disturb the functions or the original conditions of public utilities and site
facilities unless written permission has been first secured from the Engineer.
c) No expense shall be borne by the Contractor in connection with the removal, relocation
or inclusion of public utilities and site facilities except for the purpose of payment of
any claims from the owners of the utilities as a result of any damage or injuries caused
by the Contractor or any of his sub-contractors.
B.7.2 Removal and Relocation of Existing Water Line and Sewer Lump Sum
Line (Subic Water)
B.7.3 Line Revision and Pole Relocation along Columban Road Lump Sum
(OEDC)
Philipps Technical
Page 33
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
B.7.7 Removal and Relocation of Existing Fiber Optic and Lump Sum
Copper Cable Facilities (PLDT)
B.7.8 Removal and Relocation of Existing LED Signboard (at Lump Sum
Aguinaldo St)
B.7.12 Removal and Relocation of Existing Fire Hydrant near the Lump Sum
Sentry Gate
B.7.13 Removal and Restoration of Existing Fence and Pavement Lump Sum
at Harbor Point
Philipps Technical
Page 34
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART C
EARTHWORKS
Philipps Technical
Page 35
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART C- EARTHWORKS
The Contractor, prior to any tree cutting/removal operation shall prepare inventory
of trees scheduled for cutting/removal for the Engineer's approval. Trees to be cut
shall be submitted in tabulated form showing as such information for easy
identification as follows:
• Station Limit
• Description/Name/Species of Trees
• Size, Diameter (in centimeter)
• Distance from the centerline of the road
Upon Engineer's approval of the list, the Contractor shall make a request from the
Local DENR (with the approved list attached) that such number of trees will be
cut/removed for the improvement of the project. No trees shall be cut/removed
unless "Permit to Cut Trees" is issued by the DENR to the Contractor authorizing him
to cut only such approved number of trees.
The diameter of trees will be measured at a height of 1.4 m (50 inches) above the ground
and tress less than 150 mm (6 inches) in diameter will not be measured for payment. In
the measurement of trees by individual unit basis, the unit will be designated and
measured in accordance with the following schedule of sizes:
Add the following paragraph after the first paragraph and amend the second paragraph of
Section 100.4 to read as follows:
Pay Items 100(1) Clearing and Grubbing shall be paid in hectare and shall include the cost
of removing all trees except those called for in Items 100(3) and 100(4) located in the areas
to be cleared and grubbed. Removal of trees categorized as small and large in Items 100(3)
and 100(4) shall be paid by the total number of trees removed.
Philipps Technical
Page 36
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 37
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
101.1 DESCRIPTION
The existing covered walkway shall be dismantled carefully so as not to damage the
materials. The dismantled materials shall be turned over properly to SBMA.
The accepted quantities shall be paid for at the contract unit price for each pay items listed
in the Bill of Quantities, which price and payment shall be full compensation for removing
and disposing of all materials, labor, equipment, tools and incidentals necessary to
complete the work prescribed in this item. The price shall also include the removal and
disposal of the materials as provided herein this specification.
Philipps Technical
Page 38
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 39
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Structure excavation starts after the temporary cofferdam construction is completed. The
excavation shall be done mechanically and will proceed until ten (10) centimeters
(minimum) higher than the abutment and pier footing designed bottom elevation. The
final excavation and trimming shall be done manually to conform to the level and lines
indicated in the drawings. The bottom of the excavation works shall be free from
irregular mounds or any foreign materials.
Structure excavation shall be limited to the excavation for bridges, pipe culverts, retaining
walls, , manholes, drop inlets, and other structures for the whole or part of the structure as
shown on the drawings. The work shall consist of excavation in earth or rock within the
limits of the work as specified or shown on the drawings and backfilling of these structures
with suitable material. The work shall also include disposal of surplus materials and the
removal of existing structures or parts thereof which obstruct or encroach upon the
structural excavation.
Excavation for structures will be classified for measurement and payment as "Structure
Excavation Above Ordinary Water Level (AOWL)" as the case may be, and such classes shall
include all materials and shall be the excavation above the OWL indicated on the drawings.
"Structure Excavation Below Ordinary Water Level" shall be the excavation below the
BOWL indicated on the drawings.
The water elevations shown on the Drawings are approximate only and any variation in
elevation found during construction shall not be used as a basis for extra compensation for
this Item.
It shall also include the furnishing and placing of approved foundation fill material to
replace unsuitable material encountered below the foundation elevation of structures.
103.2.2 Excavation
Any excavation carried beyond the limits shown or described on the drawings or
specifications or beyond the dimension resulting from adjustments made by the Engineer
shall be backfilled with materials acceptable and as directed by the Engineer.
103.2.4 Cofferdams
Philipps Technical
Page 40
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The Contractor shall, upon request of the Engineer, submit drawings required to show in
detail the procedure and method of construction of the cofferdams as means of support or
protection to enhance or facilitate excavation under critical situations as when the
presence of water or other natural phenomenon threaten the stability of the permanent
structures to be constructed therein.
The quantities to be paid for structural excavation shall be measured in cubic meter in
original position of materials excavated in conformity with the lines, grades, elevations and
dimensions shown in the Drawings and accepted by the Engineer.
103.3.5 Basis of Payment
(4) Shoring and cribbing and related work required for excavation will be paid separately in
lump sum amount.
Philipps Technical
Page 41
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
All materials excavated from roadway, structures, drainage and ditches to the extent that
they are suitable in the formation of embankment and backfill shall be utilized as such.
Selected material to be used for embankment shall be river run gravelly sand as shown and
specified on the drawing or as directed and approved by the Engineer.
The material shall have the plasticity index of not more than 6 as determined by MSHTO
T90, a liquid limit of not more than 30 as determined by MSHTO T89 and a minimum soaked
CBR of 7% at 95% MOD.
In places where the road has to be raised by embankment over the existing road, as shown
on the Drawings or directed by the Engineer, the surface of the existing road shall be ripped,
to a depth specified on the Drawings. It shall then be bladed, reshaped and compacted to the
same or greater density as the material to be placed thereon to provide a uniform
foundation for the embankment material to follow.
The existing concrete pavement lies less than 100 centimeters of the subgrade shall be
broken down in such a way that it could be disposed of in a place designated by the Engineer.
104.3.3 Compaction
Placing of fill shall be suspended if, in the opinion of the Engineer, there is no adequate
compaction and grading equipment in operating condition available on site, to enable the fill
to be shaped and compacted immediately upon placement.
Any movement or displacement or whatever defect on the structures that may result due to
improper method of backfilling and compacting shall be corrected by the Contractor at his
own cost and shall not be entitled to any extra time on account of the delay incurred to
correct the defect.
Philipps Technical
Page 42
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Material from excavation per Item 102 which is used in embankment and accepted by the
Engineer will be paid under Item 104(1), Embankment from Roadway Excavation (Common
Materials).
Any material coming from roadways, structures, drainage or ditches excavations which are
suitable for use but are replaced by the Contractor with borrow materials without prior
approval by the Engineer, shall not be measured for payment.
Philipps Technical
Page 43
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Where the existing Asphalt Concrete Pavement (ACP) to be replaced requires the formation
of embankment to bring it to the required grade, the Contractor, if not specified on the
drawings or upon instruction of the Engineer, shall scarify, reshape and recompact the
surface to the required compaction density prior to the placement of embankment.
Subsequent formation of fill up to the subgrade level shall satisfy the degree of compaction
as prescribed under Sub-item 104.3.3 after which the subgrade shall be prescribed as
outlined in Sub-item 105.3.5.
In both excavation and embankment formation, the areas covered by widened road
sections and road shoulders are included in the same process of stabilization.
Insert the words "at or" between "ground" and "below" in paragraph (1). Add paragraphs (3)
and (4):
3) The preparation of the subgrade at locations where unsuitable materials have been
excavated and disposed shall be measured in square meters which shall be calculated
from surveys carried out defining the limits as delineated by the Engineer.
Philipps Technical
Page 44
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART D
SUBBASE AND BASE
COURSES
Philipps Technical
Page 45
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Aside from the first paragraph, this Sub-section is modified and supplemented with the
following:
The sources of aggregate subbase are listed in the Soils and Materials Report to serve as
guide of their locations. These include the results of tests conducted on them to determine
their individual quality and characteristics.
The Contractor shall carry out all relevant tests required prior to their use and whenever
such tests become necessary as determined by the Engineer.
Table 200.1 "Grading Requirements" is replaced by the following table, and must have a
smooth grading curve.
SIEVE DESIGNATION
50 2” 100
25 1” 55 - 80
9.5 3/8” 40 - 70
2 No. 10 20 - 45
0.425 No. 40 10 - 30
The portion passing the 0.425 mm (No. 40) sieve shall have a liquid limit not greater than 35
and a plasticity index not greater than 12 as determined by AASHTO T89 and T90,
respectively and sand equivalent value of not less than 40 as determined by AASHTO T176.
When used for filling of shoulder as shown on the drawings, the plasticity index shall not be
more than 8 and the liquid limit shall be 30% maximum.
The material shall have a soaked CBR value of not less than 25% determined in accordance
with AASHTO T193. The CBR value shall be obtained at the maximum dry density by AASHTO
T180, Method D.
Philipps Technical
Page 46
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The coarse aggregate material retained on a 4.75 mm (No.4) sieve shall have a mass
percentage of wear not exceeding 50 by the Los Angeles Abrasion Test as determined by
AASHTO T96.
If fillers, in addition to that naturally present in the aggregate subbbase materials are
necessary for meeting the grading requirements and/or for satisfactory bonding of material,
it shall be uniformly blended with the subbase course material on the road. The material for
such purpose shall be obtained from sources approved by the Engineer, shall be free from
hard lumps and shall not contain more than 15 percent of material retained on the No. 4
sieve.
After each layer of subbase course material has been placed with blending material,
when required, shall be thoroughly mixed to the full depth of the required layer by scarifying
and blading. When and if directed by the Engineer, the materials shall be watered to
prevent segregation of particle sizes and to obtain the moisture content required for
compaction. When uniformity is attained, the mixture shall be spread smoothly to the cross-
section shown on the drawings.
Aggregate subbase course will be measured by the cubic meter and the quantity to be paid
for shall be the design volume compacted in-place as shown on the Drawings, and accepted
by the Engineer in the completed subbase course.
Philipps Technical
Page 47
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART E
SURFACE COURSES
Philipps Technical
Page 48
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The emulsified asphalt shall be MC-70 Cut-back Asphalt and shall conform to the
requirements of AASHTO M-140.
The emulsified asphalt shall be grade SS-1 and shall conform to the requirements of
AASHTO M-140.
Philipps Technical
Page 49
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
310.1 DESCRIPTION
This Item shall consist of constructing a bituminous concrete surface course composed of
aggregates, mineral filler, and bituminous material mixed in a central plant, constructed and
laid hot on the prepared base in accordance with this Specification and in conformity with
lines, grades, thickness and typical cross-section shown on the Plans.
It shall be either Medium Curing (MC) Cut-back Asphalt or Asphalt Cement, whichever is
called for in the Bill of Quantities. It shall conform to the requirements of Item 702,
Bituminous Materials. The penetration grade, type and grade of bituminous material shall
be specified in the Special Provisions.
310.2.3 Aggregates
Aggregates shall conform to the requirements of Item 307, Bituminous Plant Mix Surface
Course-General.
It shall conform to the requirements of Item 307, Bituminous Plant Mix Surface Course-
General.
It shall conform to the requirements of Item 307, Bituminous Plant Mix Surface Course-
General.
The proportion of bituminous material on the basis of total dry aggregate shall be from 5.0
to 8.0 mass percent. The exact percentage to be used shall be fixed by the Engineer in
accordance with the job-mix formula and the other quality control requirements.
During the mixing operation, one-half to one (0.5 to 1.0) mass percent of hydrated lime, dry
aggregate basis, shall be added to the mixture. The lower percentage limit is applicable to
aggregates which are predominantly calcareous.
Philipps Technical
Page 50
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The area to be paid for under this items shall be the number of square meters (m2) of
asphalt pavement placed, compacted and accepted based on the thickness and density of
the cores taken in accordance with Subsection 307.3.10 (Acceptance, Sampling and Testing).
The accepted quantity, measured as prescribed in Section 310.4, shall be paid for at the
contract unit price for Bituminous Concrete Surface Course, Hot-Laid, which price and
payment shall be full compensation for furnishing all materials, handling, mixing,
hauling, placing, rolling, compacting, labor, equipment, tools and incidentals necessary
to complete this Item.
Philipps Technical
Page 51
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
311.1 DESCRIPTION
Add the following paragraphs to Section 311.1:
The introduction of minimum values for International Roughness Index (IRI) as part of the
basis for acceptance of newly constructed concrete and asphalt road projects requires more
accurate process control on the Contractor’s part. The Contractor’s Quality Control Plan shall
include for the Engineer’s review and acceptance, a process control flow chart, and a
Method Statement covering all activities in the process, describing how the activities will be
managed and undertaken to deliver the specified IRI values.
To achieve smooth pavements with values for International Roughness Index (IRI) of not
more than 3.0 m/km, the Contractor shall consider tightening the ranges and tolerances of
mix design components to produce a more consistent mix, and include revised target values
in the Contractor’s Quality Control Plan and Method Statement.
311.3.2 Equipment
To achieve smooth pavements with values for International Roughness Index (IRI) of not
more than 3.0 m/km, the Contractor shall ensure that the paver control system is capable of
smooth adjustments to automatically follow the surface shape (elevations and grades)
required. The preferred method is laser control following a surface shape input to the on-
board computer.
Philipps Technical
Page 52
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
To achieve smooth pavements with values for International Roughness Index (IRI) of not
more than 3.0 m/km, the Contractor shall ensure that the subgrade or base is prepared
using equipment with a control system capable of smooth adjustments to automatically
follow the surface shape (elevations and grades) required. The preferred method is laser
control following a surface shape input to the on-board computer.
The alignment and grade elevations of the forms shall be checked and corrections made by
the Contractor immediately before placing the concrete. To ensure compliance to the
maximum International Roughness Index (IRI) set by the Department, checking using
appropriate surveying instruments shall be done at 5.0 m intervals along the top portion of
the forms with a tolerance +/- 0.001 m.
When any form has been disturbed or any grade has become unstable, the form shall be
reset and rechecked. Also, when any form has been badly deteriorated which could affect
the smoothness of the surface; the form shall be replaced and not be used in any future
paving works.
Paved shoulders shall be subjected to surface test using a 3-m straight-edge. All areas within
the carriageway shall be subjected to surface test using an approved profiling system. The
profiling system shall qualify as Class 1 roughness measurement device and shall conform to
the latest version ASTM E-950/E950M.
The components of the profiling system shall be validated on regular basis per
manufacturer’s recommendations to ensure that the system is properly calibrated.
Validation reports shall be generated, for presentation to the Engineer, confirming that the
validations are current, and within tolerances specified by the manufacturer.
The acceptable Internal Roughness Index (IRI) for concrete pavements shall be not more
than 3.0 m/km for National Primary Road, measured in 100 meter sections, at the time of
completion.
Prior to any testing, the road surface for test shall be cleaned of loose or deleterious
material by brooming or other approved means. Survey shall only be conducted on dry
pavement surfaces only. Wide-beam lasers are recommended for textured surfaces like
diamond ground, diamond grooved or tyned surfaces where they yield lower IRI values than
single point or spot lasers.
Prior to data collection, a test segment with a length of 500 meters will be selected at site
for repeatability test. The repeatability test shall be witnessed by the authorized
representative of the contractor and the project engineer. Five profile runs will be made on
Philipps Technical
Page 53
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
the test segment for repeatability test. The profile runs for repeatability are acceptable if the
average IRI of the two wheel paths satisfy the following criteria:
a. The IRI values of each of the five (5) runs are within 1% of the mean IRI of the selected
runs.
b. The standard deviations of IRI of the selected runs are within 2% of the mean IRI.
If the runs do not meet the above criteria, the Profiling Team shall determine if the
variability between runs are due to operator or equipment error, and make additional
runs until five (5) runs free of equipment or operator errors are obtained. Where
necessary an accuracy calibration test shall be conducted in comparison with a Class 1
Profiler (SSI Walking Profiler CS8800 or similar) to resolve said errors.
If the IRI values from the profile runs (for repeatability) meet the above criteria, three (3)
runs per lane per site should be conducted for acceptance measurement. The IRI value for
the lane shall be the average IRI of the two wheel paths for the three (3) runs combined.
If the IRI value of the whole concrete pavement meets the required value regardless if there
are areas found to have exceeded the required IRI value, no correction shall be required,
provided that the areas with exceedance have an IRI value within the tolerance limit of
0.5m/km.
However, if the IRI value of the whole concrete pavement falls beyond the prescribed IRI of
3.0 m/km for National Primary Roads and exceeds the allowable tolerance, the contractor
may opt to undertake corrective action, otherwise, pay adjustment shall be made. The
completed concrete pavement shall be accepted on a LOT basis. A LOT shall be considered
as 100 linear meters of a lane of pavement. If the length of the last lot is less than 100m, it
shall be considered as a separate lot. LOT disincentive pay/pay deduction will be calculated
as prescribed in the table below:
If the contractor undertakes corrective action, further IRI Survey will be conducted to
validate if the pavement irregularities had been eliminated. Only one IRI survey will be done
after the corrective action takes place. If the IRI value of the whole concrete pavement
meets the prescribed IRI value of 3.0 m/km for National Primary Road and any 100 m
sections exceeding the prescribed value are within the allowable tolerance after correction,
Philipps Technical
Page 54
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
no reduction in payment will be made; otherwise, pay adjustment shall be made based on
the above Pay Adjustment Table.
Add the following at the end of the paragraph to Section 311.3.19 (1)
Slip form paver requires a guidance system. The preferred method is laser control following a
surface shape input to the on-board computer. Where the alternative of guide wires are to
be used, they should be properly tensioned, installed parallel to the edges of the
construction at both sides of the work area and maintained at fixed height and tension in
order to meet the maximum IRI set by the Department. Checking using appropriate
surveying instruments of the guide wire elevations shall be done at 0.50 m intervals with a
tolerance of +/- 0.001m.
7. Guide Wires
For flat terrain, guide wire shall be supported at 10.0 m intervals. For curves and tie-ins
to existing pavement, guide wires shall be supported at 5.0 m intervals.
No acceptance and final payment shall be made for the completed concrete pavement
unless core test for thickness determination is conducted, except for Barangay Roads where
the implementing office is allowed to waive such test, and for National Primary Roads
where the concrete pavement shall also meet the International Road Roughness (IRI)
criteria at the time of completion. The concrete pavement shall only be considered
accepted if it meets the specified IRI value at the time of completion.
Philipps Technical
Page 55
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART F
BRIDGE CONSTRUCTION
Philipps Technical
Page 56
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The testing of Bored Piles shall follow the procedures as outlined under DPWH
Department Order No. 37, Series of 2016 – “Policies and Guidelines on the Testing of
Bored Piles for Infrastructure Projects.”
Philipps Technical
Page 57
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 58
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
404.3.7 Welding
All butt weld splices in reinforcing bars shall be full penetration butt welds conforming to
the requirements in AWS D1.4 and the requirements of these specifications.
Welding shall be done by the manual shielded metal-arc process. Low Hydrogen
electrodes conforming to the requirements of AWSA 5.1 for E7016 or E7018 electrodes
shall be used.
Completed butt welded splices shall develop a minimum tensile strength, based on the
nominal bar area, of 430 MPa for ASTM Designation, A615 and A615M, Grade 60 bars.
Prior to use in the work, welded butt splices shall be qualified by tests made on sample
splices.
Reinforcing bars shall be preheated for a distance of not less than 150mm on each side of
the joint prior to welding.
In the event that any of the specified preheat, interpass and post weld cooling
temperature are not met, all weld and heat affected zone metal shall be removed and the
splice re-welded.
The quantity to be paid for shall be the calculated theoretical number of kilograms of
reinforcing steel bars, mesh or mats as determined from the net length of the steel as
shown on the drawings, incorporated in concrete and accepted. Reinforcing steel bars
shall not be measured and paid separately where structures are paid in unit, as they are
deemed to be included in the unit pay items of the structures.
The weight of plain or deformed bars or bar-mat will be computed from tile theoretical
weight of plain round bars of the same nominal size as shown on the following table:
Philipps Technical
Page 59
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 60
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
405.1 DESCRIPTION
On the first paragraph, delete first sentence and substitute the following:
Four classes of concrete are provided for in this item, namely: A, C, D, and Lean Concrete.
Each class shall be used in that part of the structures as called for in the Plans.
The following classes of concrete will generally be used for the different structures and
where shown on the drawings or directed by the Engineer:
Class A – 28 MPa for Cast in Place Slabs, Coping (Drop Panel), Abutments, Column,
Footings, , Approach Slabs, Gravity Wall and Retaining Wall
Class C – 28 MPa for Thin Reinforced Section such as Sidewalk, Parapet, Lamp Post, Traffic
Barrier and Concrete Pedestal
Philipps Technical
Page 61
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
concrete pedestal
Philipps Technical
Page 62
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
413.1 DESCRIPTION
The work shall also include pre-moulded expansion joint filler for the bridge shown on the
plan or as directed by the Engineer.
Philipps Technical
Page 63
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The quantity to be paid shall be in lump sum amount of provision, maintenance and
removal of temporary craneway accepted by the Engineer in accordance with the
plans and specifications provided by the Contractor with the Engineer’s approval.
Philipps Technical
Page 64
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Materials shall conform to the requirements for each and every item of work specified
to complete this item.
Structural Steel materials shall conform to the requirements of Item 403 Metal
Structures
Material for Steel Piles shall meet the requirements for Item 400 Piling.
Materials for Cast in Place Concrete and Precast Concrete Panel shall meet the
requirements for Item 405 Structural Concrete and as specified in the Plans.
Material for Steel Railings shall meet the requirements for Item 401 Railings and Item
403 Structural Steel.
SPL2.2.5 Roofing
Roofing materials shall be G.A. 24 Rib Type Long Span as specified in the plans.
The quantity to be paid shall be in lump sum amount of provision, maintenance and
removal of temporary pedestrian walkway accepted by the Engineer in accordance with
the plans and specifications provided by the Contractor with the Engineer’s approval.
Philipps Technical
Page 65
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 66
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The work will also include the furnishing, fabricating, hauling, erecting and painting of
structural metals, installation of GA#24 Rib Type Long Span Pre-Painted roofing,
installation of rain guards and pavement as shown on the Plans.
GA#24 Rib Type Long Span Pre-Painted roofing and acrylic board rain guard shall be
installed in accordance with the manufacturer's approved erection instructions and
diagrams or as indicated in the Plans.
Pedestrian covered walkway shall be measured and will be paid for in lump sum which
price and payment constitute full compensation for furnishing, fabricating, delivering
and erecting ready for use, all materials, labor, equipment, tools and incidentals
necessary to complete the work.
Philipps Technical
Page 67
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The work will also include the furnishing, fabricating, hauling ,erecting and painting of
structural metals as shown on the Plans.
Fabrication and erection of structural steel truss, columns and beams shall be carried out
in accordance with Item 403 - Metal Structures and Item 411-Paint
Temporary water pipe support shall be measured and will be paid for in lump sum which
price and payment constitute full compensation for furnishing, fabricating, galvanizing,
delivering and erecting ready for use, all materials, labor, equipment, tools and
incidentals necessary to complete the work.
Philipps Technical
Page 68
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
This item shall consist of steel gate barrier constructed in accordance with this
specification and as shown on the plans duly approved by the Engineer.
This shall include furnishing, fabricating, hauling, erecting, welding and painting of the
panel as called for in this specification or as shown on the Plans. Bridge steel gate
barrier will include panels, gates, post and other incidentals not otherwise provided for,
all in accordance with this specifications and Plans.
1. Description of the Bridge Steel Gate Barrier - the gate shall be made of 50 mm
square bar vertical rails at 200 mm on center welded to horizontal frame 100mm
G.I.Pipe on top and 75 mm G.l. pipe bottom frame. The whole gate system shall be
corrosion resistant.
2. The height of the gate shall be 2.0 m. Normal span/panel shall be 2.89 m as shown
on the drawings.
3. The gate support consists of 50 mm diameter pipe welded on the vertical and
horizontal frame.
4. Steel roller and steel guide shall be provided for easy opening and closure system of
the gate.
6. All steel materials shall be galvanized with minimum zinc coat of 275 glm2 treated
with adhesion layer and finally coated with polyester (minimum 60 micron) shall be
used.
Bridge Steel Gate Barrier shall be measured by lump sum amount completed and shall
include all materials, equipment and labor used to finish the item as called for in the
plans and specifications.
Philipps Technical
Page 69
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
This item shall consist of movable barrier constructed in accordance with this
specification and as shown on the plans duly approved by the Engineer.
This shall include furnishing, fabricating, hauling, erecting, welding and painting of the
panel as called for in this specification or as shown on the Plans. movable barrier will
include panels, gates, post, stopper and other incidentals not otherwise provided for, all
in accordance with this specifications and Plans.
1. Description of the Movable Barrier - the gate shall be made of 50 mm square bar
vertical rails at 200 mm on center welded to horizontal frame 100mm G.I.Pipe on
top and 75 mm G.l. pipe bottom frame. The whole gate system shall be corrosion
resistant.
2. The height of the gate shall be 2.0 m. Normal span/panel shall be 2.89 m as shown
on the drawings.
3. The gate support consists of 50 mm diameter pipe welded on the vertical and
horizontal frame.
4. Steel roller and stopper shall be provided for easy transfer of the barrier.
6. All steel materials shall be galvanized with minimum zinc coat of 275 glm2 treated
with adhesion layer and finally coated with polyester (minimum 60 micron) shall be
used.
Movable Barrier shall be measured by in lump sum amount completed and shall include
all materials, equipment and labor used to finish the item as called for in the plans and
specifications.
Philipps Technical
Page 70
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PARTG
Philipps Technical
Page 71
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
500.1 DESCRIPTION
This Item shall consist of the construction or reconstruction of reinforced concrete pipe
culverts in accordance with this Specification and in conformity with the lines and grades
shown on the Drawings or as established by the Engineer.
At the end of the 2nd paragraph, replace "Item 102, Excavation" with "Item 103, Structure
Excavation".
Philipps Technical
Page 72
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 73
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
510.3.4 Drainage
Weep Holes shall be provided as specified in the plans and as required by the Engineer
Delete the first and second paragraph and substitute the following:
The quantities to be paid for shall be measured by linear meter of concrete retaining
wall in-placed and accepted as shown on the Plans.
Philipps Technical
Page 74
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART H
MISCELLANEOUS
STRUCTURES
Philipps Technical
Page 75
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
605.1 DESCRIPTION
Project Signboard - Project Signboard shall be provided and installed at locations shown in
the Drawing or as directed by the Engineer. It shall conform to the DPWH Department
Order No. 21 Series of 2017 (February 22, 2017).
Project sign board installed and accepted shall be measured and paid for under the pay item
provided for in the Bid Schedule which price and payment constitute full compensation for
all costs involved including all labor, equipment, tools and incidental necessary to complete
the item.
Refer to DPWH Department Order No. 26 Series of 2016, DPWH Standard Specification for
Item 741 – Interlocking Precast Concrete Blocks
Philipps Technical
Page 76
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART I
OTHER SPECIAL STRUCTURES
Philipps Technical
Page 77
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
1.1 In general, the Contractor shall comply with the laws, city and municipal ordinances
and all Building Code rules and regulations.
1.2 The Contractor shall comply with all the architectural, electrical and engineering
specifications.
1.3 The work herein stipulated shall include but not limited to the following:
d. Specifications
The Contractor shall secure and pay for all construction permits, inspection fees, licenses
and taxes that may be incurred for the proper execution of the project.
The site shall be free from loose earth, rubbish and other perishable materials or obstructive
matter before actual excavation shall start.
3.1 In case where demolition shall take place, care should be taken to protect and maintain all
materials and other facilities. All unusable materials taken from the demolition shall be
removed from the site and shall be properly stacked to a designated place.
3.2 Staking Out- The security gate shall be staked out and all lines and grades shown on the
drawings shall be established before excavation is started. Reference mark shall be carried
out and made at such places where they will not be disturbed during the construction of
foundation.
3.3 Excavation -All excavations, whether rock or common excavation shall be such to meet the
alignment, grades, dimensions and shape shown on the construction drawings. No footing
shall rest on fill and if such is the case, then excavation shall be carried deeper until the
structure is reached for the safe bearing capacity of the soil.
Philipps Technical
Page 78
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
4.1 The Contractor shall employ competent workmen and maintain such workforce sufficient
enough to ensure the completion of the work.
4.2 All materials unless otherwise specified, shall be new and of the best quality of their
respective kind for their purpose.
4.3 Decision of the construction supervision Consultant regarding quality of materials shall be
final. Any changes thereof must bear the Consultant's/Owner approval.
The work comprises the furnishing of all labor, materials, equipment necessary to the
proper execution and final completion of the New SOG Office, Welcome Arch, Covered
Pedestrian Walkway (Pathway) and Temporary Pedestrian Pathway,
- Container van walls and ceiling shall be insulated with 2.5 in – 3.0 inches insulation
- Complete electrical (5 outlets/ 1-switch (2-gang) and 4 set fluorescent lighting with Reel
type breaker and industrial plug.
- Laminated wood flooring with PVC baseboard
- 60cm x 60cm granite tiles on entrance door
- Door: 1 – insulated container panel door with handle and barrel bolt inside and outside
- Windows: 2- 100cm x 100cm PVC Sliding windows with mosquito screen
- Provision of 1- 1.5HP Air Conditioning Unit including outlet, brand new
- With exterior and interior paint
- 10 - 1.0ft x 1.0 ft Concrete footings
- Comfort room to include water closet, lavatory, and shower.
- Septic Tank and Water Tank including tapping to existing
Upon completion of the New SOG Office the 40 footer Van shall be turn over to SBMA.
The intent of this specification is to cover the work for the above mentioned structure and
any work called for. Likewise, any materials which has been omitted from both drawings
and specifications, but is evidently necessary for the completion of the said structure shall
be furnished just the same as it was shown in the drawings and specifications.
6.0 SPECIFICATIONS
Structural Concrete- shall meet the requirements of Item 405 Structural Concrete
Steel Reinforcement - shall conform and meet the standard specifications for Item 404
Reinforcing Steel.
Philipps Technical
Page 79
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Painting -It must be understood that painting must cover the painting of the structure on
concrete, structural steel and other surfaces. All works shall be done by skilled painter in a
workman-like manner by brushing or spraying on the surfaces to be painted. All paints shall
be evenly applied so as to be free from sags, runs, crawls and other defects.
The accepted quantities measured ad accepted as prescribed, shall be paid for in lump sum
and monthly basis. The payment shall constitute full compensation for furnishing and
placing all materials including labor, equipment, tools and incidentals necessary to complete
the work prescribed in these items.
Philipps Technical
Page 80
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PARTJ
ELECTRICAL AND
AUXILIARY WORKS
Philipps Technical
Page 81
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
1.1 The work under this Section shall be subject to the requirements of the General conditions,
which shall be included as part of this Specifications and which shall apply to all work to be
performed under the Electrical Division. The contract documents, instructions, drawings and
specifications shall be considered as one. Whatever is called for by any of the documents
shall be as binding as if called for by all.
2.1 The work to be done under this Division of the Specifications consists of the fabrication,
furnishing, delivery and installation, complete in all detail of the Electrical Work at the
subject premises and all work materials incidental to the proper completion of the project,
except those portion of the work which are expressly stated to be done by others. All work
shall be in accordance with the governing Codes and Regulations and with the
Specifications, except where some shall conflict with codes, etc. which the latter shall then
govern. The requirements in regard to materials and workmanship specify the required
standard for the furnishing of all labor, materials and appliances necessary for the complete
installation of the work specified herein and indicated on the drawings. These specifications
are intended to provide a broad outline of the required equipment, but are not intended to
include all details of the design and construction.
3.1 Under this Division and together with the specifications, provide all materials and equipment
and perform all the work necessary for the complete execution of the electrical systems for
street lighting, bridge and covered pedestrian walkway (bridge), covered pedestrian
walkway(pathway), welcome arch and, SOG office as shown on the electrical drawings with
reference to the general construction drawings as herein specified, or both except as
otherwise excluded and which, without excluding the generality of the foregoing, shall
include but not limited to the following principal items of work:
c) Supply and installation of CB for the existing panelboards and disconnect switches
necessary to complete work. Refer Panel Load Schedule. Retain existing panelboards.
Supply all the lacking CB necessary to complete the work.
d) Furnish and installation of the complete power and control wiring to various mechanical
and sanitary equipment unless otherwise specified.
Philipps Technical
Page 82
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
e) Supply and installation of lighting fixtures and wiring devices including dimming control
panels and modules unless otherwise specified.
h) Securing and payment of electrical wiring permit and certificate of electrical inspection.
i). Application and securing the approval for the electrical power and telephone service
connections including the preparation of the necessary plans, forms and related
documents payments of fees and charges and coordination with power and telephone
companies and other authorities or persons involved in the procedures.
j) If anything has been omitted for any items of work or materials, usually furnished which
are necessary for the completion of the entire work as outlined herein before, then such
items must be and hereby included in this division of work.
4.1 The work under this Contract is to install according to the requirements of the latest
Philippine Electrical Code, the rules and regulations of the municipality and the
requirements of the local power and telephone companies. Nothing contained in these
specifications or shown on the drawings shall construed as to conflict with the National and
Local Ordinances or Laws governing the installation of the electrical work and all such laws
and ordinances are hereby made part of these specifications. The Contractor is required to
meet the requirements thereof.
4.2 All permits and electrical fees required for this work shall be obtained by and at the expense
of the Contractor. The Contractor shall furnish the Architect, Engineers and the Owner the
final certificate of inspection and approval from the proper government authorities after the
completion of the work. The contractor shall prepare all “As-Built” electrical plans and all
other paperwork required by the approving authorities.
5.1 The Contractor shall, during the progress of the work, must keep a careful record of all
changes where the actual installation differs from that shown on the construction drawings.
The engineers will furnish at cost a complete set of sepia prints on which the Contractor
shall, in a neat and accurate manner will make a complete record of all changes and
revisions to the original design, as installed in the completed work. These drawings shall be
submitted to the engineers for approval. After the approval they shall become the property
of the Engineers and final payment will be withheld until receipt of the approved record
drawings.
6.1 Prepare and submit for approval to the engineer shop drawings and cuts of all equipment,
appliances and fixtures to be furnished. After final approval by the engineer, a sufficient
Philipps Technical
Page 83
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
number of copies as directed shall be furnished for distribution. Fixture and device cuts
and/or catalogues shall be clearly marked to indicate the items furnished. Do not submit
individual sheets, cuts, catalogues or drawings, for instance, lighting fixture cuts should be
for all types of fixtures to be furnished, rather than a few type.
6.2 Submit to the Engineer for approval samples of conduits, wires, wiring devices, finished plates
and or any other items as may be required by the Engineer.
7.0 COORDINATIONS
7.1 The contractor shall cooperate in every way and work with all other contractors to whose
apparatus he shall connect is part of his work and also provide in his work connections and
facilities for the connection of their work. The contractor is hereby called upon to prepare
such drawings of details of his equipment, locations of sleeves, inserts and supports as may
be required for the assistance of the general contractor and the contractors for other
mechanical trades. Upon demand, he shall furnish these drawings in adequate numbers for
the information of all parties concerned and shall coordinate the preparation of these
drawings by consultation with other trades involved before submitting them. The approval
of such drawings will not relieve the Contractor in anyway from the responsibility of not
properly locating or coordinating his work with the work of others.
8.1 The plans as drawn are based upon the architectural plans and the details and shown
condition as accurately as it is possible to indicate them in scale. The plans are diagrammatic
and do not necessarily show all fittings, etc., necessary to fit to the building conditions. The
locations of outlets, apparatus and appliances shown on the plans are approximate. The
Contractor shall be responsible for the proper location in order to make them for with the
architectural details and instruction from Engineer’s representative at the site.
9.0 GUARANTEES
9.1 This Contractor shall guarantee that the entire electrical systems are free from all defective
workmanship and materials and will remain so for a period of two years from the date of
acceptance of the work.
9.2 The Contractor shall indemnify and save harmless the Owner, the Architect and the
Engineers from and against all liability for damages arising from injuries or disabilities to
persons or damages to property occasioned by any or omission of the contractor or any of
his subcontractors including any and all legal expenses or otherwise, which may be incurred
by the Owner, the Architect or the Engineers in the defense of any claims, actions, or suit.
10.1 Wherever hereinafter the work “for approval”, or “approved” (make, type, size,
arrangement, etc.) are used, especially in regard to manufactured specialties, or wherever it
is desired to substitute a different make or type of apparatus, shall be submitted to the
Engineer and their approval must be secured before the apparatus is ordered or installed.
Philipps Technical
Page 84
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
11.1 Ground Test: The entire installation shall be free from improper ground and from short
circuits. These shall be made and recorded in the presence of representative of the Owner,
project managers and the engineers. Each panel shall be tested with mains connected to the
feeder, branches connected and switches closed all fixtures in place and permanently
connected, lamps removed or omitted from the sockets, ballast disconnected and all wall
switches closed. Each individual power feeder shall be tested with the power equipment
connected for proper and intended operation. In no case shall the insulation resistance be
less than that allowed by the regulations for electrical equipment and buildings. Failures
shall be corrected in a manner satisfactory to the Engineers.
11.2 Performance Test: It shall be the responsibility of the electrical contractor to test all systems
of the entire electrical installation for proper operational conditions. This condition shall
apply to the power, lighting and auxiliary installations. Where sequence operation is
required, the electrical contractor shall test for proper sequence and he shall leave the
entire electrical installation in satisfactory working condition.
11.3 Cutting and Fittings: Contractor shall do all cutting and fittings required for the installation
the work to make and join the several parts and coordinate with the work of other trades, in
accordance with the drawings and in a manner satisfactory to the Engineers.
11.4 Protection: Contractor shall effectually protect his own work from damage during and as
may be necessary after installation and he shall likewise protect adjoining work of other
trades from damage resulting from the installation of electrical work.
12.1 The location of various items indicated on the drawings are presumed to be approximately
correct, but it is to be understood, however, that the small scale drawings are necessarily
diagrammatic and that such locations as shown, are subject to slight revision as the work is
installed, which may be necessary to accommodate local construction conditions. No major
change shall be made, however, without the approval in writing of the Engineers. The
contractor shall examine and study the architectural scale drawings, large scale and full size
details, the approved shop drawings of other trades and he shall frequently consult with the
general contractor to ascertain any changes that may have been made and he shall be
guided accordingly before establishing the precise locations of conduit runs, panels, pull and
junction boxes and outlets for all lighting, power and auxiliary system.
13.1 All wires shall be copper, soft-drawn and annealed, shall be of 99% conductivity, shall be
smooth and true and of a cylindrical form and shall be within 1% of the actual size called for.
13.2 All wires and cables shall comply with the requirements of the Underwriter’s Laboratories,
the A.S.T.M. and the I.P.C.E.A. as they apply in the particular.
Philipps Technical
Page 85
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
13.3 Wire and cables for lighting power and auxiliary systems shall be plastic insulated for 600
volts working pressure, type THHN unless otherwise noted on plans.
13.4 For lighting and power system, no wire smaller than 2.0 mm dia. shall be used.
Neutral - White
14.0 CONDUITS
14.1 Intermediate Metallic Conduit (IMC) for Service Entrance and Rigid Steel Conduit (RSC) for
exposed, Cable Tray hot-dipped galvanized and shall be a standard weight, mild steel, hot-
dip galvanized with an interior coating. Non-metallic conduits for interior systems shall be
sch. 40.
14.2 No conduits shall be used in any system smaller than 15mm dia. electric trade size, nor shall
have more than four 90-degree bends in any one run and when necessary, pull boxes shall
be provided as directed. Location and sizes of pull boxes shall be cleared to the engineer
prior to fabrication and installation.
14.3 No wires shall be pulled into any conduit unless the conduit system is complete in all details.
In the case of concealed work, until all rough plastering or masonry has been completed and
in the case of exposed work until the conduit has been completed in every detail.
14.4 The ends of all conduits shall be tightly plugged to exclude plaster, dust and moisture while
the building is in the process of construction.
14.5 All conduits and fittings on exposed work shall be secured by means of channels and
clamps. Conduit layout, in all cases shall run perfectly straight and true, satisfactory to the
Architect and to the Engineer.
15.1 All outlets of whatever kind, for all systems, these shall be provided with a suitable fittings,
which shall be either a box or other devices especially designed to receive the type of fittings
to be mounted thereon.
Philipps Technical
Page 86
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
15.2 The contractor shall consult with the architect and the engineers as to the nature of the
various fittings to be used before installing the outlet fittings and shall conform strictly in the
use of such fittings, to the nature of the appliance to be mounted on them, so that the work,
when finished will be a completed design.
16.1 Junction and pull boxes per code gauge steel shall only be subject to the permission of the
engineer and be provided as indicated or as required for facilitating the pulling of wires and
cables. Pull boxes in finished places shall be located and installed only with the permission of
and to the satisfaction of the Architect and Engineer. Sizes shall be subject to the approval of
the Engineer.
17.1 Wall switches shall be rated at 15 amperes, 300 volts, one-pole, two-pole, three-way or four-
way as required. Certain combinations shall be furnished with pilot lights as required and
where indicated on the drawings. Switches shall be of the quick connect terminal operated.
The type of switch shall be tumbler operation and the color, plating and appearance of wall
plates shall be selected by the Architect and appropriate samplers shall be submitted
prior to the purchase of wall switches and wall plates.
17.2 Receptacle outlets shall be for flush mounting, duplex rate at 10 ampere, 250 volts,
grounding type 3-wire. Type and color or receptacle outlet plates are selected by the
Architect and appropriate samples of outlets and plates shall be submitted prior to purchase
of devices.
18.0 PLATES
18.1 All switches and receptacle plates shall be approved by the Architect and Engineer prior to
procurement.
19.1 Standard panels and cabinets as far as possible shall be used and assembled at jobsite. All
panels shall be of dead-front construction furnished with trims for flush or surface mounting,
as required. Cabinets shall be of code gauge steel with gutters at least 150mm and wider, if
necessary. The trim for all panels shall be in gray enamel over a (ANSI#61) rust inhibitor.
19.2 Panels and cabinets shall be fabricated by a reputable fabricator. Fabricator’s shop drawings
in triplicate shall be submitted for approval before fabricating the panels.
Switchgear: Only one brand of circuit breakers and fabricator shall be used for the entire
requirement of the project.
19.3 Lighting panels shall be required with two-pole circuit breaker in the branch circuits and in
the main unless noted otherwise in the plans. As indicated on plans, the panels shall be
assembling in two or more sections where over 48 one-pole circuits. Ground bus terminals
shall be standard features to the panel.
Philipps Technical
Page 87
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
20.1 Enclosure for indoor application shall be NEMA-1 and for outdoor application shall be
NEMA-4X unless otherwise indicated in the plans.
20.2 Circuit breakers shall consist of a quick-make, quick-break type entirely trip-free operating
mechanism contacts with arc interrupter and thermal-magnetic trip used for each pole and
enclosed in a molded phenolic case. The thermal-magnetic trip unit shall provide time delay
overload protection and instantaneous short circuit protection and shall operate internal
common-trip bar which will open all poles in case of overload or short circuit current in any
one-pole. Circuit breaker shall be trip indicating with the tripped position of breaker midway
between “ON” and “OFF” positions.
20.3 Only a single acceptable brand of circuit breakers shall be used on the entire project
requirement. Submit brochures for approval.
20.4 Minimum interrupting capacities of each circuit breakers are indicated on the load schedule
application of circuit breakers shall be approved for the intended load per panelboard
schedule.
21.1 The contractor shall coordinate his work with all trades involved so that exact locations may
be obtained for all outlets, apparatus, appliances and equipment. The circuit numbers
indicated as numbers 1, 2, 3, may not correspond to actual panel circuit connection numbers
but must be balanced for better load distribution.
21.2 The location of outlets shown on diagrammatic wiring plans shall be considered as
approximate and it shall be incumbent upon the Contractor before installation of outlet
boxes, to study all pertinent drawings obtain precise information from the architectural
schedules, scale drawings, large scale and full size details of finished rooms and the
approved shop drawings of other trades or from the architect. Local switches shown near
the doors shall be verified with the architect’s drawings before installation.
22.0 SERVICES
28.1 Power supply shall be 230 volts, Three-phase, three(3)-wires plus ground.
23.1 All wiring shall be installed in PVC pipes Schedule 40 using concrete tight fittings and
connectors or as indicated in the plan and in general shall be concealed in the structure.
Philipps Technical
Page 88
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
23.4 Provide all lighting fixtures and lamps at locations shown on plans or as directed by the
Architect.
23.5 The Contractor must submit samples of all types of lighting fixtures to the Owner and to
Engineer for approval prior to procurement.
24.1 The telephone system shall consist of conduits, outlet boxes, junction boxes and terminal
cabinets and main distribution frames, as shown on the plans.
26.1 The CATV system shall consist of empty conduits, outlet boxes, junction boxes and terminal
cabinets as shown in the plan.
26.2 Branch conduits shall be non-metallic conduits with a minimum diameter of 20 mm or as
indicated in the plans.
26.3 Provide pulling wire inside empty conduits.
26.4 All work materials shall be brand new, free from defects, installed and constructed in a
workmanlike manner to prevailing standard practice.
27.0 CLEANING UP
27.1 The contractor shall at all times keep the construction area, including storage areas used by
him, free from accumulations of waste materials or rubbish and prior to completion of work
remove any rubbish from and about the premises and all tools, scaffolding, equipment, and
materials not the property of the Owner.
27.2 Upon completion of the construction, the Contractor shall leave the work and premises in a
condition satisfactory to the Owner and Engineer.
28.1 Upon completion of the project, the following procedures shall be followed:
28.1.a. Walk-thru inspection by the Owner, Engineer and Contractor. Any discrepancy noted shall be
fixed before project is closed.
Philipps Technical
Page 89
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
29.0 LAMPOST
29.1 Lamp Post shall meet the standard specifications as indicated in the Plans.
30.1 Standby Generator Set shall be SOUNDPROOF Type, 82.5 kVA, 60Hz, 200 – 240, (380) 400 –
480 V, 3 – Phase, 4 – Wires, 80% p.f. (lagging) with ± 0.5. Exciter with AVR Brushless,
Rotating Exciter (with AVR) RPM, 1800, 83 Kw/1800 RPM.
Philipps Technical
Page 90
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART K
OPERATING EQUIPMENT
Philipps Technical
Page 91
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
This item shall consist of furnishing and installing of Traffic Control System, CCTVs,
Paging System, Ternstile, Automatic Vehicle Counter and RFID Ready Pedestrian
Counter.
• All systems should be at least the latest technology at the time of delivery
• All items must meet and pass the minimum safety standards required
• The supplier/contractor shall perform Periodic Maintenance Service within the
warranty period, submit the Life Cycle Maintenance Plan, and provide all the
necessary equipment needed in the performance of the Periodic Maintenance
• The Contractor shall provide insurance coverage with SBMA as “assured party” for at
least one (1) year commencing on the date of project acceptance through
Government Service Insurance System (GSIS) Electronic Equipment Insurance Policy.
a. Controller
• An intelligent 32-Bit Signal Processor, 25KHz, Microprocessor Based
• Area/Urban Traffic Control Ready
• With at least 8 phases of traffic flow
• Operating modes: Automatic, Actuated, Manual, Flashing and Cable Link
• Protection: Built-in miniature circuit breaker, Green conflict monitoring,
TriAC short circuit detection, Transient voltage surge suppressor, Automatic
Voltage regulator
• Voltage/Frequency: 110-265VAC/50-60Hz
• Cabinet Construction: NEMA 3
• Meets any of the following Standards: AS2578, AS1099, BS2011, ISO 9001
• All other functions and features must be the same or similar to and
compatible with the system that are installed by others at SBFZ’s major
intersections.
b. Signal Poles
• All signal poles shall be bolted down with base plate
• Must be hot dipped galvanized with dark gray powder coated color
• (IF NECESSARY/NEEDED) Signal Pole Type A (SPA): shall be 5.5 meters height
mast arm type post, 4 meters outreach arm at 78º bend, 219mm diameter
galvanized steel traffic pole with 6mm wall thickness, a 12 mm thick x
110mm x 180mm steel rib plate (stiffener) and 30mm thk x 450mm x
450mm steel base plate with 4-30mm diameter holes.
Philipps Technical
Page 92
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
• Signal Pole Type B (SPB): shall be 4.1m height straight or I-type pole, 114mm
diameter galvanized steel traffic pole with 4mm wall thickness, a 12mm
thick x 100mm x 160mm steel rib plate (stiffener) and 12mm thick x 350mm
x 350mm steel base plate with 4-20mm diameter holes.
e. Pedestrian Lantern
• Type: Light Emitting Diode (LED)
• Design: Animated pedestrian stop and/or walk
• Size: 300mm Ø with countdown timer
• Construction: 2 aspect module UV-protected Polycarbonate
• Ingress Protection Rating: At least IP65-60 Hz
• Voltage: 110-265VAC/50
• Power: Power: ≤15 Watts; with heat sink for thermal management
• Lifetime: Lifetime: ≥60,000 Hours
• Compliant with CE, RoHS and ITE standards
Philipps Technical
Page 93
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
g. Vehicle Detector/Sensor
• Vehicle loop detector using inductive loop detector
• Advance vehicle detection system using video camera
B. CCTV System
a. Camera
• Outdoor Network Camera
• At least IP67 ingress protection
• Type: PTZ dome/vari-focal bullet/fixed dome
• Resolution: Ultra High Definition
• Infrared: 30m range/120m for PTZ
• Power –Over-Ethernet
• Wide Dynamic Range
• For PTZ Optical Zoom: at least 30x
• For Gate Cameras only: with built-in Analytic Feature (face recognition/plate
recognition)
b. Video Recorder
• Network Video Recorder
• Third-party network cameras supported
• At least 24 channels
• Up to 12 Megapixel resolution recording
• Up to 8 SATA interfaces (Support HDD hot swap)
• Support various Video Content Analytics (VCA) detection alarm and VCA
search
• Support H.265/H.264/MPEG4 video formats
• Support 2-ch HDMI, HMDI1 at up to 4K (3840x2160) resolution
• Includes HDD capable of storing of at least 2 months video recording in HD
resolution
• Includes PTZ Keyboard with PTZ Controller
c. Network Switch
• Indoor: at least 16 ports (802.3af/at) with 2 SF Ports
• Outdoor: at least 8 ports (802.3af/at) with 2 SF Ports/at least IP67
d. Wireless Bridge
• Outdoor 802.11AC Radio
• At least IP67 ingress protection
• 5 GHz Band (wide)
• Selectable channel width
• Power-Over-Ethernet
• At least 500Mbps bandwidth
• Compatible with existing wireless bridge installation at Bldg. 657
e. Monitor
Philipps Technical
Page 94
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
C. PAGING SYSTEM:
a. IP Network PA System Software: shall be with built in server, built-in encoder,
built-in media player, built-in status monitor, built-in weekly program timer,
Support English Windows 7 and Windows XP.
b. IP Network Microphone: shall be enabling to paging to individual zone, group
zones and all zones with different priority setting, each unit of 120 zone
capacity. System Capacity of 120 units, support to be built-up over existing LAN
Network
c. IP POE Powered Ceiling Speakers: shall be network controlled speaker volume,
scheduled broadcast program, priority-based multicast streaming, group
definition, working status supervision, remote on line technical support and
trouble shoot. The speaker shall be capable of broadcasting audio through
multicast
Philipps Technical
Page 95
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
The quantities determined under this item or as shown in the Bill of Quantities include
the total number of designated type of traffic signals, cctv’s, paging system, automatic
vehicle counter and rfid ready turnstile as completely installed and tested.
The quantities measured as determined in Item SPL K.4 - Method of Measurement, shall
be paid for the Contract Unit Price for the Pay Items shown in the Bill of Quantities
which price and payment shall constitute full compensation for furnishing and placing all
materials and for all labor, equipment, tools and incidentals necessary to complete the
Item.
Philipps Technical
Page 96
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART L
LANDSCAPING
Philipps Technical
Page 97
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
SPL L LANDSCAPING
The scope under this item shall include all labor, materials, equipment and services
necessary for the completion of the planting. Included in this scope are the finished grading,
soil preparation, lawn installation, planting of trees, shrubs and ground cover; guarantee and
replacement of lawns and plants; maintenance services and all related items required to
complete work as per drawings and specifications.
a. Topsoil – the Contractor shall furnish sufficient topsoil to properly install all works
specified. Depths of topsoil are indicated in the plans.
b. Manure – Shall be well-rooted animal manure free from wood shaving, sawdust or other
litter and containing no chemicals harmful to plant growth
c. Commercial Fertilizer – shall be “urea” or a brand approved by the Landscape Architect
and shall be brought to the site in its original unopened container.
d. Water- shall be made available at the site before any planting is started. The Contractor
shall furnish all necessary hose, equipment attachments or the adequate irrigation of all
lawns and planting.
e. Staking and Guying – Stakes for trees over 4 feet in height shall be 2” x 2” x 8’ sound
wood treated for ½ length with creosote or other wood preservative. For fastening trees
to stakes use 2” tie strips tie with no.16 gauge pliable galvanized wire.
f. Lawn Materials – all planting of lawns and grass shall be made by blocks and shall be
healthy, freshly dug, free of weeds and shall be properly protected until planting.
g. Plant Materials – a plant list specifying quantities, types and conditions accompanies the
planting plan as stated in the drawings.
Lanscaping shall be measured by in lump sum amount completed and shall include all
materials, equipment and labor used to finish the item as called for in the plans and
specifications.
Philipps Technical
Page 98
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Philipps Technical
Page 99
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
PART M
PROVISIONAL SUM
Philipps Technical
Page 100
Consultants Corp.
Proposed Construction of New Magsaysay Bridge at Subic Bay Freeport Zone Technical Specifications
April 2019
Provisional Sum means a sum included in the Contract and so designated in the Bill of Quantities for
the execution of any part of the Works or for the supply of goods, materials, plants or services, or for
contingencies, which sum may be used, in whole or in part, or not at all, on the instructions of the
Engineer. The Contractor shall be entitled to only such amounts in respect of the work, supply or
contingencies to which such Provisional Sums related as the Engineer shall determine. The
Provisional Sum is included as a fixed amount (as indicated in the Bill of Quantities) and the Bidders
are not entitled to modify the figure.
The Provisional Sum may be used for the execution of additional works beyond the limit of
Dayworks. This may be due to unknown or unforeseen underground obstruction wherein detailed
engineering cannot be possibly undertaken or for other works like relocation of public utilities which
requires specialization and maybe undertaken by a nominated subcontractor.
Works executed under the Provisional Sum shall be valued at the rates or prices set out in the Bid or
as determined by the ENGINEER. The Contractor shall submit to the ENGINEER all quotations,
invoices and accounts or receipts in connection with the expenditures on works under the
Provisional Sum.
Philipps Technical
Page 101
Consultants Corp.