CBMM CONSTRUCTION

CHRISTOPHER MARQUEZ CHRISTOPHER MARQUEZ


Commercial and Residential Building Contractor JEREMIAS Y. MARQUEZ JR.
Address: #323 P. Inquimboy St., Pasay City CIVIL ENGINEERS
Contact Numbers:
Tel. nos. : 516 – 7363
Cell. Nos.: 0947 – 459 - 0304
Email Address:
miasmarquez311@gmail.com

August 3, 2016

Dear Sir:

This is to quote you the following scope of works to be mobilized and estimated for completion
within 15 days (for partitions and doors only) with 12 workers.

1. Installation of Metal Studs for partition wall frames.


2. Installation of hardiflex partition walls.
3. Painting of hardiflex partition walls.
4. Installation of doors for partition walls.
5. Installation of under the mezzanine stair covering for mini kitchen.
Additional Activities

6. CHB wall Cutting and Installation of exit door and exit stair.
7. CHB wall Cutting and Installation of 2-panel glass door at GMG Bldg. main hallway.
8. Installation of Steel wide flange beams and joists for the additional steel mezzanine
floor.(to be confirmed)
9. Installation of steel plate mezzanine slab. (to be confirmed)
10. Rust protection and Painting of steel mezzanine floor. (to be confirmed)
Labor and Material Cost Estimate:

Material Qty. Cost

148.44 sq. m. @ php


Partition Wall 44,532.00
300/sq.m.

Door 1 1 pc. @ php 25,000 25,000.00

Door 2 10 pcs.@ php 5000 each 45,000.00

Door 3 1 pc. @ php 10,000 10,000.00


Hallway and Exit wall
2 doors @ 3000 each 6,000
Cutting
Exit door stair 1 pc. @ 10,000 10,000
Steel Mezzanine floor 45 sq. meters @ php
202,500.00
(to be confirmed) 4,500/sq.m.
Total Cost(labor and
Php 343,032.00
materials)

For any questions and clarifications regarding this proposal please don’t hesitate to contact us
at the contact numbers given above.

Thank you,

Christopher Marquez
CONTRACTOR